Case Law[2025] ZAGPPHC 423South Africa
Gutter Innovations CC v Innovative Machinery Hub (Pty) Ltd (8303/2022) [2025] ZAGPPHC 423 (8 May 2025)
High Court of South Africa (Gauteng Division, Pretoria)
8 May 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 423
|
Noteup
|
LawCite
sino index
## Gutter Innovations CC v Innovative Machinery Hub (Pty) Ltd (8303/2022) [2025] ZAGPPHC 423 (8 May 2025)
Gutter Innovations CC v Innovative Machinery Hub (Pty) Ltd (8303/2022) [2025] ZAGPPHC 423 (8 May 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_423.html
sino date 8 May 2025
IN THE HIGH COURT OF
SOUTH AFRICA
(GAUTENG DIVISION,
PRETORIA)
Case No:
8303/2022
(1)
REPORTABLE:
(2)
OF INTEREST TO OTHER JUDGES:
(3)
REVISED:
8 May 2025
In the matter between:
GUTTER
INNOVATIONS CC
Applicant
(Registration No.
1993/07985/23)
and
INNOVATIVE
MACHINERY HUB (PTY) LTD
Respondent
JUDGMENT
RETIEF J
INTRODUCTION
[1]
This is an application for the final winding-up of the respondent
brought in terms of section 344(f), read with section 345(1)(a)
of
the Companies Act, 61 of 1973 [Companies Act]. The respondent opposes
the relief. The respondent was placed under provisional
winding-up on
the 4 November 2024 and the applicant’s compliance of the
provisional order is not in dispute.
[2]
The provisional winding-up order has been preceded by a previous
liquidation application brought by the applicant in which the
respondent was also placed under provisional winding-up based on a
unpaid debt claimed in terms of a breach of contract [2019
agreement]. This provisional winding up order was granted on the 25
May 2021 under case number 56032/2020 [first liquidation
application].
[3]
This application too is brought by the applicant based on an alleged
unpaid debt arising from the cancellation of the 2019 agreement
as a
result of breach. The applicant claimed restitution (restoration of
the status quo ante) from the respondent upon cancellation
as a
result of the breach. Performance failure by the respondent to repay
the monies already paid in advance by the applicant for
the
manufacture of certain machines in terms of the 2019 agreement is
common cause. The procedural history giving rise to this
application
is relevant and the applicant correctly incorporated the pleadings
and made reference to the first liquidation in its
founding
affidavit.
BACKGROUND
HISTORY
[4]
The 2019 agreement was concluded between the applicant and the
respondent in January 2019. The terms of the agreement are common
cause. In terms of the 2019 agreement, the applicant commissioned the
respondent to manufacture and to deliver certain machines.
The
respondent undertook to manufacture the machines within an agreed
manufacturing period being 12-16 weeks from date of conclusion
of the
2019 agreement. Payment terms were agreed and were made up of three
payment increments. The total price of R 1 104 000.00
(inclusive of
value added tax) [total price] was agreed. The last increment, being
a vat inclusive price of 30% of the total price,
R 331 200.00, was
due and payable on the delivery of the machines. The applicant
however paid the total price at once.
[5]
The respondent breached the 2019 agreement by its failure to
manufacture the machines within the manufacturing period. The
applicant waited approximately a year from the date of such breach
before it delivered its section 345 demand
[1]
dated 13 August 2020 [the demand]. In the demand, the applicant, as a
result of the breach, demanded specific performance by way
of
delivery but, also sought the repayment of the R331 200.00 as
the same was only due when the respondent performed by delivering
the
machines. At that stage, breach was common cause. The respondent
through its attorney then in writing, undertook to deliver
the
machines by the end of January 2021. This undertaking was given in
August 2020. The respondent reneged on its own written undertaking
yet again. Although the respondent’s undertaking was made on
its own terms during the Covid epidemic it later pegged its
own
inability to perform on Covid.
[6]
Be that as it may, the applicant launched the first liquidation
proceedings in October 2020. The respondent opposed the first
liquidation application raising,
inter alia,
the ground that
the amount claimed R331 200.00, did not constitute a debt in law but
an “-
untested claim for restitution of an amount allegedly
paid sine causa.”
The Court having regard to all the facts
and defences raised, granted a provisional winding up order and, the
respondent before
the return date, in a settlement agreement,
acknowledged its indebtedness to the applicant in the amount of R 331
200.00 and repaid
it. After the repayment, the applicant had still
paid a vat inclusive amount of R 772,000.00 (R 1 104 000.00 less R
331 200.00)
to the respondent in order to secure their manufacture of
the machines. The terms of the settlement was made an order of Court
on the return date, the 30 August 2021 [settlement order].
[7]
The settlement order effectively reinforced specific performance of
delivery in terms of the 2019 agreement and,
inter alia
, set
out the applicant’s rights, other than in possessed in law,
absent the respondent’s compliance delivery. According
to the
settlement order the respondent had to deliver the machines by the 15
November 2021 [delivery date]. The non-compliance
of the delivery
date, by order, triggered certain procedural options and other
remedial rights by consent. In particular clause
7 provided
effectively for the extension of the provisional order until the
respondent had delivered the machines by the 15 November
2021.
Therefore, the delivery date too was intended to trigger the
discharge of the provisional order.
[8]
The provisional order, contrary to the settlement order, was already
discharged on the return date, the 30 August 2021. This
may have been
because payment of the debt relied on had been paid. However, the
respondent failed to deliver the machines in compliance
of the Court
order. In truth, no evidence before or subsequent to such failure has
been tendered by the respondent other than a
hollow allegation, that
it commenced with the manufacture of the machines, this is since the
date of its commission in January
2019 to date (in other words,
within the period of approximately 6 years).
[9]
The respondent’s failure to deliver the machines in terms of
the settlement order is common cause. As result of the respondent’s
continued failure to manufacture the machines, the applicant elected
to cancel the 2019 agreement. It expressed this election on
the 14
January 2022 . Upon cancellation, it too claimed for the repayment of
the R 772,000.00 by demand. Simultaneously with the
cancellation and
repayment claim, the applicant launched a contempt application in
respect of the non-compliance of the settlement
order.
[10]
Receipt of the demand and its content, in compliance of the Companies
Act is not disputed. The respondent failed to respond
to such demand.
The cancellation of the agreement and non-compliance of the
settlement order is common cause. The respondent failed
to respond to
the obligation to perform by repaying the amount claimed or any part
thereof.
[11]
On receipt of the demand other than the respondent electing not to
pay, it also elected not to exercise any of its rights or
defences it
deemed it was entitled to as against applicant. Nor, for that matter,
did it tender or repay the applicant any amount
it deemed appropriate
in the circumstances. It simply just waited for the applicant to
proceed with the liquidation proceedings,
a procedure foretold in the
demand and foreseen in the settlement order.
[12]
In response to this application, the respondent opposes the relief
and raises 3 (three) grounds of defences contending that
the
same is
bona fide
. Briefly the three grounds are: the
settlement order cannot be cancelled and that the respondent’s
obligation towards the
applicant remained delivery of the machines;
that the respondent’s inability to perform in terms of the
settlement order
was as a result of the applicant in that, it was
partially impossible to perform in that there was a hold on its bank.
Such had
been frozen as a result of the provisional order in the
first liquidation application up and until Friday, the 2 November
2021
and, lastly that the applicant approached the Court with dirty
hands, in that it was the party who prevented the respondent from
performing in terms of the settlement order and as such, it submits
it is not obliged to pay the applicant the amount of R 772,800.00
or
any part thereof, but in terms of the settlement it is still liable
to deliver the machines. In conclusion of its defence it
makes the
following statement:
“
5.5
The refusal to make payment is not as a result of an inability on its
part to pay debts, but it is a refusal
as a result of the claim being
disputed.
”
[13]
The veracity of these defences and too the statement at paragraph 5.5
in the respondent’s answering affidavit, must too
be considered
together with the evidence tendered by way of affidavit, on the
return date which was duly filed on the 17 April
2025. The respondent
uploaded the affidavit which was deposed to by Mr Matthew Greeff [Mr
Greeff], the designer manager of the
respondent. Mr Greeff intended
to show good cause why the final provisional order should not be made
final. Insofar as Mr Greeff
in his affidavit refers to the necessity
to apply for condonation, no substantive application was brought.
Notwithstanding, none
was required as evidence was called for by
order and in consequence, leave was granted for its contents to be
tendered into evidence.
In fact the applicant’s Counsel
referred to its contents in oral argument. In this way the Court
could take cognizance of
all the relevant facts in the adjudication
of the application and in the exercise of its discretion whether to
grant a final winding-up
order.
[14]
Before dealing with the material allegations pertaining to the merits
of any good cause raised by Mr Greeff it is important,
as this
juncture, to mention that Mr Greeff who was not in Court at the date
of the hearing of the provisional order relayed certain
utterances in
his affidavit made to him by the respondent’s attorney, Mr Van
Der Berg concerning what transpired in Court.
Such utterances he
voiced as concerning. The content, as raised, was not confirmed by Mr
Van Der Berg under oath. Notwithstanding,
the relayed utterances at
Mr Greeff’s insistence should have been brought to the Court’s
attention. Mr Van Der Bergh
did not raise such utterances or concerns
nor did he refer the Court to such utterances in oral argument. For
that matter Mr Van
Der Berg who argued the matter did not deal with
such evidence in written argument either as he did not file nor did
he tender
any written heads of argument during the proceedings.
[15]
In short, such utterances related to certain alleged
ad hominem
attacks against Mr Van Der Berg, before arguments were heard by the
Court and,
inter alia,
references were made to remarks of
‘
shenanigans’
and that the applicant had shown the
respondent ‘
grace on grace’
. Reference to all the
utterances are relayed in paragraph 7 of Mr Greeff’s affidavit.
Mr Greeff submitted that they tainted
the proceeding before the Court
and at the provisional stage, which may be cause for a review.
[16]
Without dealing with the legal basis for such a review at this time,
this Court, absent any argument nor confirmation under
oath by Mr Van
Der Berg, still deemed it appropriate, before finally dealing with
the matter, to ask both the parties, in light
of Mr Greeff’s
concerns whether the parties had any objection to this Court
adjudicating the matter to finality. No objections
written or
otherwise were raised nor received, no application for, nor mention
of a recusal was filed. Therefore no party exercised
any of its
rights afforded to it procedurally or otherwise based on Mr Greeff’s
submissions. This Court considering all the
circumstances and absent
further evidence, is of the opinion that it is capable of applying an
objective mind to bear on the material
issues before it and apply the
evidence.
[17]
In so doing, this Court now deals with Mr Greeff’s evidence.
FURTHER
EVIDENCE ON TH RETURN DATE
Does
Mr Greeff’s evidence show good cause in favour of the
respondent and tip the balance
?
[18]
Mr Greeff deposed to the affidavit pursuant to prayer 3 of the
provisional order as an employee of the respondent. From the
evidence
presented in the first liquidation and in this application, Mr Greeff
appears to play an active and pivotal role in the
day to day
activities of the respondent of which, his daughter is the sole
director. Such is enough to draw a reasonable inference
from the
facts that he, has a legitimate interest, a required enquiry, by
order, this is without him alleging the same on the papers.
To
commence, at this juncture it is important to note that Mr Greeff
states that soon after the provisional liquidation was granted,
being
the 14 November 2024, the respondent provided its attorney with
instructions to provide security for the claim against it
to bring an
end to the liquidation proceedings. This is confirmed by the
respondent’s director who deposed to a confirmatory
affidavit.
The intention to pay security did not come to the applicant’s
attention nor did the payment thereof occur. In
fact save for the
instructions to their attorney, no further procedural steps were
taken by the respondent from the 14 November
2024 until the 17 April
2025 when Mr Greeff’s affidavit was filed.
[19]
According to Mr Greeff the reason for not paying the security as
intended, was that during a consultation with Mr Van Der Bergh,
which
took place on the 8 April 2025, the respondent had a change of heart
in that the respondent did not wish to pay security
when it still
held the view that quantum was in dispute. In amplification, the
respondent on the advice of its attorney in this
affidavit holds the
view that the applicant’s claim is not a claim for a debt but
one of damages or one based on enrichment.
Furthermore, it was argued
that the adjudication of such claims are not suited on application
nor, for that matter, by way of liquidation
proceedings. In this way
the respondent extended its defence grounds in its answering
affidavit and, amplified it by arguing that
its opportunity to have
the applicant’s actual claim in law adjudicated constitutes an
infringement of its right to defend
its case before a Court as
envisaged in terms of section 34 of the Constitution.
[20]
The applicant did not raise any argument against the respondent’s
procedural right nor prejudice it may suffer because
the respondent,
in this manner, extended its defences not specifically raised in
answering affidavit. In consequence, this Court
deals with it as
raised. In so doing, this Court will reconsider the three distinct
defences raised, were applicable too.
To commence, the Court
agrees that motion proceedings are suited for damages nor enrichment
claims. However, the applicant did
not claim repayment in the form of
damages flowing from cancellation nor on the basis of enrichment but
for a debt. Its demand
is clear; it requires the repayment of monies
paid as a result of a breach of contract. The non-compliance of the
settlement order
was just another string in its bow to demonstrate
yet another non-compliance. The settlement order itself, in any
event, attempted
to settle the matters arising in the first
liquidation application. In other words the payment of an
acknowledged debt and a means
to enforce performance by delivery.
Payment for delivery still owing by the applicant.
[21]
The 2019 agreement at the time of the settlement order had not been
cancelled. The applicant still required the respondent
to manufacture
the machines it had already commissioned in January of 2019 for
which, it had paid in advance. Failure to manufacture
the machines,
as stated in the demand as a failure to provide the status of
their manufacture constituted a breach upon which,
the applicant
appearing exasperated with the situation, now wished to cancel the
commissioning of the machines all together. No
evidence tendered,
even after the respondent’s bank accounts were unfrozen, that
it commenced with the manufacture of the
machines. Simply put the
applicant did not want the respondent to manufacture the machines
anymore. The cancellation valid. This
does not translate into what
the respondent perceived as a ‘cancellation’ of the
settlement agreement. This argument
has never been advanced by the
applicant nor could it be sustained.
[22]
Furthermore it is trite that a claim for restitution following a
breach of contract is a distinct remedy and is a proper
measure and a
substitute for damages.
[2]
Upon
cancellation of the 2019 agreement and a claim for restitution, an
obligation by the respondent to perform was established.
Such
obligation a debt
[3]
and, in
this case, the obligation to pay money. The claimed amount was
set out in the demand wherein restoration and repayment
of amounts
advanced for the manufacture of the machines was clearly set out. The
claimed debt remains unpaid.
[23]
Flowing from this finding, the respondent’s argument based on
any infringement in terms of section 34 of the Constitution
based on
its ability to ventilate its defence in respect of the claim not
constituting a debt and the nature of such claim which
follow in a
Court of law is not sustainable. Furthermore the respondent has had
access to legal representation at all times, it
has possessed the
liberty of responding to every delivered demand and legal process.
Such allegation of infringement at this time
and so raised is
opportunistic and must fail.
[24]
Returning to Mr Greeff’s evidence is clear that the respondent
was not in a position to pay the security it intended
to pay in
November 2024. This is because its ability to pay was dependant
on future recoverable debts, the payment of which
was not secured and
would only occur at a future uncertain date. In other words, as
argued by the applicant’s Counsel and
absent evidence to the
contrary, the only reasonable inference to be drawn on the undisputed
facts by Mr Greeff was that the respondent
did not have sufficient
funds at its disposal to pay the security it intended to pay.
Evidence of the respondent’s ability
to pay the applicant if
and when it was called upon to do so was not only lacking in these
papers but also in the papers filed
in the first liquidation
application.
[25]
Over and above the consideration of intent to pay security, Mr Greeff
too raised certain factors he wanted this Court to consider
when it
exercised its discretion whether to grant the final relief or not.
The weight of such factors was considered and the necessary
weight
applied. Saliently the following factors:
25.1.
Factor 1
25.1.1. The applicant is
the respondent’s only creditor. In support thereof Mr Greeff
submits that respondent does not even
have to pay for its monthly
rent and as such its landlord is not a creditor. In support thereof,
Mr Greeff alleges that a company
called DKM Machinery (Pty) Ltd [DKM]
pays its monthly rent. The only evidence in support of this
allegation is an invoice raised
by a company called Zanli Engineering
Works (Pty) Ltd [Zanli] to DKM. Zanli ostensibly the landlord. The
invoice tendered was for
the payment of DKM’s monthly rent
occupied by DKM and payable to Zanli. It is unclear from the invoice
and from Mr Greeff’s
evidence which portion of the leased space
the respondent
de facto
occupies, if any. The invoice is
silent on the matter. No confirmatory affidavit by a person from
Zanli is provided. How this proves
that the applicant is DKM’s
only creditor is unclear.
25.1.2. On the facts both
the respondent and DKM carry on business at the same place namely at
8 Mount Joy Road, Wilbart, Germiston.
In truth although not much
turns on that fact that businesses share the same premises it does
require further scrutiny. Why DKM
pays the respondents monthly
expenses is unexplained as the veracity of the relationship between
DKM and the respondent not
supported by a confirmatory
affidavit by DKM’s sole director Deborah Greeff under oath.
Without explanation of the
inter partes
arrangement or
confirmation thereof, DKM may reasonably too be a creditor on the
facts. No further documents other than this invoice
was tendered in
support of the allegation. Not even a copy or extract from its
creditor control account was supplied. The statement
that the
applicant is its only creditor rings hollow.
25.1.3. What does not
ring hollow is that from the invoice provided, as it demonstrates
that the landlord Zanli also carries on
its business at the same
premises at factory 18, 8 Mount Joy Road, Wilbart, Germiston. In
other words, all the parties, the respondent,
DKM and Zanli operate
business from the same premises. This is not explained. Why then
would Zanli raise the invoice for DKM to
pay the rent of a premises
it too occupies and operates from? What is the nature of the
relationship between all the parties?
25.1.4. The assertion
that the applicant is the respondent’s only creditor is not
persuasive and only raises further unanswered
questions and doubts as
to the respondent’s
bona fides
.
25.2.
Factor 2
25.2.1. The next factor
to be considered is of greater concern. This is as a result of
Mr Greeff’s and the respondent’s
understanding and
appreciation for the effect of a provisional winding up order. He
under oath stated that the respondent on the
16 August 2021, sold
some of its equipment, movable property, for value, to DKM. On the 16
August 2021 the respondent was factually
still under provisional
winding up by order as a result of the first liquidation application.
25.2.2. As to the fact
that such equipment was sold to DKM, this is factually untrue. The
evidence in support of the allegation
demonstrates that the
respondent sold the equipment to D Greeff. Although D Greeff may very
well be Deborah Greeff the only director
of DKM, no proof exists that
DKM itself bought or paid for the assets on the invoice raised by the
respondent. The evidence shows
that D Greeff in her personal capacity
acquired and paid for such equipment. The transaction is not
confirmed under oath by D Greeff
nor is the capacity of D Greeff at
the time, explained when such transaction was entered into. The
transfer was not only unlawful
at the time but, the veracity of the
allegations rejected. The weight and circumstances during which such
purported transaction
took place is a factor for consideration and
goes to the heart of the respondent’s
bona fides
.
25.3.
Factor 3
25.3.1. Mr Greeff
confirms that a number of the assets attached by the Sheriff on the 5
December 2024 actually belong to DKM. Mr
Greeff lists the assets. Any
reliance on the transaction of the 16 August 2021 in support of the
ownership claim, as discussed
is rejected. Even if the Court is to
accept the allegations it is counterproductive and only diminishes
the respondent’s
ability to demonstrate that it is in
possession of sufficient disposable movable assets on attachment to
satisfy the amount claimed
by the applicant. Mr Greeff’s
evidence is not confirmed by DKM. The allegation not persuasive. This
too is a factor for consideration.
25.4.
Factor 4
18.4.1 Mr Greeff states
that: “
It is common cause that a payment was made to the
respondent for the commissioning of machines and that the contract
was cancelled
by the applicant as a result of machines not being
delivered timeously.
” Against the common cause fact, “-
a
payment was made to the respondent for the commissioning of
machines-“
Against this admission, Mr Greeff attempts
to argue that the debt claimed by the applicant in its demand is not
a liquidated
debt. This aspect has previously been reasoned and can’t
stand.
18.4.2 The applicant’s
claim determinable on the common cause facts. The amount claimed
exceeds R 100 and it is common cause
that the respondent has not paid
nor is willing to pay the amount or part thereof nor able to pay the
amount as security.
Factor 5
Mr Greeff alleges
certain dignity violations having occurred involving the applicant’s
attorney. Mr Greeff is not precluded
from pursing such a claim. The
veracity of which is not before this Court to determine but, the
allegation has been considered
collectively with the other factors in
so far as it may advance good cause in favour of the respondent in
this application.
Factor 6
The contempt application
brought by the applicant in respect of the respondent’s
non-compliance of the settlement order
is not a claim for
specific performance on any interpretation. Any declarator relief
granted in the applicant’s favour in
the contempt relief will
be dealt with on appeal. As raised on the papers by both parties,
the appeal in no way effects the
basis upon which the applicant
launched this application. The contempt proceedings raised in the
founding papers and the outcome
of such appeal even, if upheld, will
not disturb the common cause and admitted facts in this application.
This Court has considered
this factor as raised.
[26]
Considering Mr Greeff’s evidence and the factors raised does
not tip the balance in the respondent’s favour, the
reverse is
true.
CONCLUSION
[27]
The deeming provisions of section 345(1)(a) of the Companies Act
create a rebuttable presumption to the effect that the respondent
is
unable to pay its debts. The respondent did not admit that the claim
constituted a the debt nor was it willing to pay any portion
of the
amount nor could it, on Mr Greeff’s version, pay the security
intended. No financial statement or bank accounts are
tendered to
enable the Court to be satisfied that the respondent can pay and does
pay its day to day expenses absent such an allegation.
According to
Mr Greeff it does not even pay its monthly rent. No unconditional
payment was made nor tendered by the respondent
to avoid liquidation.
[28]
When recalling the respondent’s defences raised in its founding
papers they too, as reasoned and applied logically, fail
to
constitute reasonable
bona fide
grounds. Having regard to all
the evidence the respondent has failed to rebut the deeming provision
of section 345 of the Companies
Act and is found to be unable to pay
its debts. In consequence, it stands to be wound-up.
[29]
In argument the applicant too submitted that it would be just and
equitable in terms of section 344(h) of the Companies Act
to wind-up.
This is often raised by applicants without supporting evidence.
However in this matter the applicant’s Counsel
argued that the
Court should consider the affidavit of Mr Greeff and the weight of
the respondent’s confirmation of such
facts to determine
whether it is just and equitable. In so doing and having regard to
the impact of such evidence as against the
respondent itself, the
Court finds that it is just and equitable to wind up the respondent.
The Court is satisfied that the applicant
has complied with all the
statutory and procedural requirements. The inevitable flows.
[30]The
following order:
1. The Respondent
be and is hereby placed under final winding up.
2. Costs of the
application are costs in the liquidation, taxed on Scale B.
L.A.
RETIEF
Judge
of the High Court
Gauteng
Division
Appearances
:
For
the Applicant:
Adv H.P.
Wessels
Email:
hpwessels@group33advocates.com
Instructed
by attorneys: Van Der
Merwe & Associates Attorneys
Tel: 087 654 0209
Email:
legal7@vdmass.co.za
For
the Respondent:
BC Van Der Berg Attorneys
Cell: 078 849 3464
Email: bennie@vdbatt.com
Date
of hearing:
23 April 2025
Date
of judgment:
8
May 2025
[1]
In
terms of section 345 (1)(a)(i) of the Companies Act.
[2]
Barker
v Probert 1985(3) SA 429 (A); De Vos, Verrykingsaanspreeeklikheid in
Suid-Afrikaanse Reg (2
nd
ed) at 141-143.
[3]
See
the definition of a “debt” in Electricity Supply
Commission v Stewart and Lloyd of SA (Pty) Ltd 1981(3) SA 340
and,
as applied in Cook v Morrison and Another (1319/2017) [2019] ZASCA8;
[2019] 3 All SA 673
(SCA);
2019 (5) SA 51
(SCA) (8 March 2019).
sino noindex
make_database footer start
Similar Cases
G. J. L and Another v Road Accident Fund (A118/2023) [2025] ZAGPPHC 232 (19 March 2025)
[2025] ZAGPPHC 232High Court of South Africa (Gauteng Division, Pretoria)98% similar
Topfix (Pty) Ltd v Go Business (Pty) Ltd and Another (020590/2024) [2025] ZAGPPHC 115 (30 January 2025)
[2025] ZAGPPHC 115High Court of South Africa (Gauteng Division, Pretoria)98% similar
Pro Secure (Pty) Ltd v Mogale City Local Municipality and Others (2025-043172) [2025] ZAGPPHC 479 (16 May 2025)
[2025] ZAGPPHC 479High Court of South Africa (Gauteng Division, Pretoria)98% similar
New Gx Enviro Solutions and Another v City of Tshwane Metropolitan Municipality and Another (53694/2020) [2023] ZAGPPHC 745 (25 August 2023)
[2023] ZAGPPHC 745High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Smith and Another (65895/18) [2025] ZAGPPHC 1134 (25 September 2025)
[2025] ZAGPPHC 1134High Court of South Africa (Gauteng Division, Pretoria)98% similar