Case Law[2025] ZAGPPHC 919South Africa
Sasol Oil (Pty) Ltd v National Energy Regulator of South Africa and Others (059715/2023) [2025] ZAGPPHC 919 (2 September 2025)
High Court of South Africa (Gauteng Division, Pretoria)
2 September 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 919
|
Noteup
|
LawCite
sino index
## Sasol Oil (Pty) Ltd v National Energy Regulator of South Africa and Others (059715/2023) [2025] ZAGPPHC 919 (2 September 2025)
Sasol Oil (Pty) Ltd v National Energy Regulator of South Africa and Others (059715/2023) [2025] ZAGPPHC 919 (2 September 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_919.html
sino date 2 September 2025
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
Case
Number: 059715/2023
(1)
REPORTABLE: YES / NO
(2)
OF INTEREST TO OTHER JUDGES: YES/NO
(3)
REVISED: YES/NO
DATE
02/09/2025
SIGNATURE
In
the matter between:
SASOL
OIL (PTY) LTD
Applicant
and
NATIONAL
ENERGY REGULATOR OF SOUTH AFRICA
First Respondent
TRANSNET
SOC LTD
Second
Respondent
TOTALENERGIES
MARKETING SOUTH AFRICA (PTY) LTD
Third
Respondent
SHELL
DOWNSTREAM SOUTH AFRICA (PTY) LTD
Fourth
Respondent
ENGEN
PETROLEUM LTD
Fifth
Respondent
BP
SOUTHERN AFRICA (PTY) LTD
Sixth
Respondent
ASTRON
ENERGY (PTY) LTD
Seventh Respondent
ROYAL
REFINERY (PTY) LTD
Eighth
Respondent
AIRLINE
INDUSTRY ASSOCIATION OF
Ninth
Respondent
SOUTHERN
AFRICA NPC
MINISTER
OF MINERAL RESOURCES AND ENERGY
Tenth Respondent
JUDGMENT
MAKHOBA, J
Introduction
[1]
On 23 February 2023, the National Energy Regulator of South
Africa (“NERSA”) approved the tariffs applicable to
Transnet’s petroleum pipeline system for the period
1 April 2023
to 31 March 2024.
[2]
The applicant, Sasol Oil (Pty) Ltd (“Sasol”), became
aware
of the impugned decision on 16 March 2023, following its
publication on NERSA's website.
[3]
Sasol seeks
an order to review and set aside NERSA's decision in terms of the
Promotion of Administrative Justice Act
[1]
(“PAJA”), alternatively, under the principle of legality.
Parties
[4]
The applicant is Sasol, a company duly incorporated in terms of the
company
laws of the Republic of South Africa.
[5]
The first
respondent is NERSA, a statutory body established in terms of section
3 of the National Energy Regulator Act
[2]
(“the NERSA Act”). NERSA has a mandate in terms of
section 28 of the Petroleum Pipelines Act
[3]
(“the PPA”) to “set as a condition of a licence the
tariffs to be charged by a licensee in the operation of a
petroleum
pipeline and approve the tariffs for storage facilities and load
facilities”.
[6]
The second
respondent is Transnet SOC Ltd (“Transnet”), a
state-owned entity incorporated in terms of the company laws
of the
Republic of South Africa, and the Legal Succession to the South
African Transport Services Act.
[4]
[7]
The third respondent is TotalEnergies Marketing South Africa (Pty)
Ltd
(“Total”), a company incorporated in terms of the
company laws of the Republic of South Africa.
[8]
The fourth respondent is Shell Downstream South Africa (Pty) Ltd
(“Shell”),
a company incorporated in terms of the company
laws of the Republic of South Africa.
[9]
The fifth respondent is Engen Petroleum Ltd (“Engen”), a
public
company incorporated in accordance with the company laws of
the Republic of South Africa.
[10]
The sixth respondent is BP Southern Africa Pty (Ltd) (“BP”),
a company incorporated
in accordance with the company laws of the
Republic of South Africa
[11]
The seventh respondent is Astron Energy (Pty) Ltd (“Astron”),
a company incorporated
in accordance with the company laws of the
Republic of South Africa.
[12]
The eighth respondent is Royal Refinery (Pty) Ltd (“Royal”),
a private company
incorporated in accordance with the company laws of
the Republic of South Africa.
[13]
The ninth respondent is the Airline Industry Association of Southern
Africa NPC, a voluntary
association of airline companies.
[14]
The tenth respondent is the Minister of Mineral Resources and Energy,
cited in his official
capacity as the Cabinet member responsible for
energy and whose department is responsible for setting retail fuel
prices.
[15]
The second to tenth respondents are cited for such interest as they
may have in the application.
No substantive relief is sought directly
against them, save for an order as to costs in the event of
opposition.
[16]
On 28 May 2025, Transnet, the second respondent, withdrew its
opposition to the application.
The matter has been since been settled
between the applicant and the second respondent.
[17]
A point in
limine
initially raised was subsequently abandoned
and was not proceeded with.
Grounds
of review
Applicant
submissions
[18]
The applicant lists the following as the grounds of review:
18.1
It is contended that NERSA erred by failing to distinguish between
the different pipelines within
the system and instead regarded them
collectively as a single network. The Applicant submits that this was
unlawful, as the PPA
affords no authority for such an approach.
18.2
The applicant accepts that NERSA acknowledged differences between the
Crude Oil Pipeline (“COP”)
and the Multi-Product Pipeline
(“MPP”). It argues, however, that NERSA nonetheless
relied on the rolled-in tariff methodology
adopted in 2011, which was
no more than a guideline and never a binding rule of law.
18.3
The applicant submits further that, in order to ensure a fair tariff
for COP users, NERSA was
obliged to consider fairness as a material
factor in terms of section 28(2)(a)(ii) of the PPA. Its failure to do
so, it is contended,
renders the decision irrational and unlawful.
18.4
It is also argued that the decision was unreasonable in that NERSA
imposed a uniform tariff across
the system, on the basis of the
rolled-in approach adopted in 2011.
18.5
The applicant refers to the minutes of NERSA’s meetings, noting
that
Sasol’s submissions were absent from the deliberations.
This omission, it contends, supports the conclusion that the impugned
decision is reviewable.
18.6
Lastly, the applicant contends that NERSA’s decision was unfair
and discriminatory,
contrary to section 28(2) of the PPA, and
therefore reviewable under sections 6(2)(b) and 6(2)(f)(i) of PAJA.
[19]
In summary, the applicant’s case is that its submissions were
disregarded, and that
the adoption of the 2011 rolled-in methodology
was inappropriate for the 2023/24 tariff determination. On this
basis, the applicant
contends, the decision is said to be unlawful
and unreasonable.
First respondent’s
submissions
[20]
NERSA averred that the rolled-in methodology was adopted in 2011. As
that decision was
never challenged, it remains valid until set aside
by a court. The present application, it argues, does not constitute
such a challenge.
[21]
NERSA further contended that section 28(1) of the PPA does not
prescribe a tariff-setting
methodology. Its adoption of the rolled-in
approach, consistently applied since 2011, falls within its statutory
discretion.
[22]
NERSA
relies on regulation 4(1)(d) of the PPA,
[5]
which it says confers a discretionary power to determine tariff
increases.
[23]
NERSA submits that it is the duty of the applicant to prove before
the Court that such
discretion was exercised
ultra vires
.
[24]
It argues further that the methodology used is rationally connected
to the purpose of the
PPA. The rolled-in approach, when read with
section 28 of the PPA, is said to strike a fair balance among all
jurisdictional factors
in the provision.
[25]
NERSA adds that Sasol has failed to provide any explanation for its
delay in challenging
the 2011/12 methodology, which it considers
fatal to the Applicant’s case.
[26]
In reply to
the first ground of review, NERSA submits that Sasol’s
contention that each pipeline should be tariffed separately
disregards the holistic approach required to balance the interests of
all stakeholders. The rolled-in methodology, it maintains,
is
consistent with section 28(1) of the PPA and regulation 4(2).
[6]
[27]
In respect of the second ground, NERSA argues that Sasol cannot be
permitted to challenge
the 2011 decision indirectly through the
2023/24 tariff determination. Fairness, it submits, must be evaluated
with reference to
all stakeholders.
[28]
On the third ground, NERSA states that it did consider Sasol’s
written submissions
and the Genesis report, but only insofar that
they were relevant.
[29]
As regards the fourth ground, NERSA argues that section 28(2)(a) of
the PPA does not impose
a rigid criterion by which tariffs must be
mechanically tested. It cannot be interpreted as dictating that the
exclusion of a particular
interest automatically renders a tariff
unfair or discriminatory.
[30]
Lastly, NERSA contends that Sasol’s case rests on its narrow
commercial interest
in the Natref refinery. Its claim that the COP
tariff is unfair merely because MPP costs are higher, NERSA argues,
overlooks the
broader context. It points out that Sasol’s
interests were taken into account in 2011 when the rolled-in
methodology was
adopted, and that there are also circumstances where
COP costs may exceed those of the MPP.
Applicable
legal principles
[31]
In
National
Energy Regulator of South Africa and Another v PG Group (Pty) Ltd and
Others (PG Group (Pty) Ltd)
[7]
the Court held:
[8]
“
The Maximum
Pricing Methodology is not law, but rather a guideline made in
accordance with the empowering legislation. NERSA
thus has
discretion not to rigidly apply the methodology if its application
would lead to irrational or otherwise unlawful results”
It
is now settled law that a pricing methodology is not rigid, but
operates as a guideline.
[32]
The requirement in Sections 28(2)(a)(i)-(vi) of the PPA is central to
this matter. It stipulates
that the tariff charged must be–
i. “based
on a systematic methodology applicable on a consistent and comparable
basis;
ii. fair;
iii.
non-discriminatory;
iv. simple
and transparent;
v.
predictable and stable;
vi. such as
to promote access to affordable petroleum products;”
[33]
It follows that the applicant must establish that NERSA failed to
meet the requirements
of section 28 of the PPA.
[34]
Section 6(2)(f)(ii) of PAJA provides that an administrative action
may be reviewed and
set aside if it is not rationally connected to
the following–
“
(aa) the purpose
for which it was taken;
(bb) the purpose of
the empowering provision;
(cc) the
information before the administrator; or
(dd) the reasons
given for it by the administrator;”
Evaluation
[35]
In my view, it was incumbent on NERSA to demonstrate that no
differences between the COP
and the MPP, and that imposing a single
tariff across both was fair.
[36]
It is
unnecessary, in my view, for Sasol to challenge the 2011 tariff
methodology. As confirmed by
PG
Group (Pty) Ltd
,
[9]
that methodology is no more than a guideline. NERSA’s argument
to the contrary is without merit.
[37]
NERSA nonetheless had the responsibility to show that the tariff set
was fair, reasonable
and rational, and complied with section 28 of
the PPA.
[38]
In
Democratic
Alliance v President of the Republic of South Africa and Others,
[10]
the Constitutional Court held that a failure to consider a relevant
material factor in taking an administrative decision may render
the
decision irrational.
[39]
In my view, there are significant differences between the COP and the
MPP, including differences
in operational characteristics and costs.
The costs associated with the MPP are higher than those of the COP.
[40]
NERSA’s failure to recognise these differences amounts to
non-compliance with section
28(2)(a)(ii) of the PPA, rendering the
tariff unfair to the applicant.
[41]
NERSA misdirected itself by adopting the rolled-in methodology of
2011 and disregarding
the submissions made by Sasol.
[42]
It ought to have given proper consideration to Sasol’s
submissions in favour of separate
tariffs for the COP and MPP in
order to ensure fairness for COP users.
[43]
It is unreasonable for NERSA to impose a single pipeline system
tariff based on the 2011
rolled-in approach. The COP operates
upstream of refining, whereas the MPP is downstream, and the two
pipelines are not physically
connected.
[44]
I am therefore satisfied that the impugned decision is irrational and
unreasonable, and
that it falls to be reviewed and set aside.
Order
[45]
I make the following order:
45.1
The decision made by the first respondent on 23 February 2023,
approving tariffs in respect of
the second Respondent’s
petroleum pipeline system (the impugned decision), is reviewed and
set aside on the grounds set out
in the founding affidavit.
45.2
The impugned decision is remitted back to the first respondent for
reconsideration.
45.3
The first respondent is directed to pay the costs of this
application.
45.4
No order as to costs is made against the second to tenth respondents.
D. MAKHOBA J
JUDGE OF THE HIGH
COURT
PRETORIA
Date
of Hearing:
04–06 August 2025
Judgment delivered:
02/09/2025
APPEARANCES:
For the Applicant:
G
Singh, B Dhladhla, and M Nguta instructed by Mchunu Attorneys
For the First
Respondent:
A
F Arnoldi SC, P Managa, and O Mulaudzi instructed by Mothle Jooma
Sabdia Incorporated
[1]
3 of 2000.
[2]
40 of 2004.
[3]
60 of 2003.
[4]
9 of 1989.
[5]
Regulations in terms of the
Petroleum Pipelines Act 60 of 2003
, GN
R342
GG
30905,
4 April 2008.
[6]
See n.5 above.
[7]
2020 (1) SA 450 (CC).
[8]
i.d n.7 at para 33.
[9]
i.d n.7.
[10]
2013 (1) SA 248
(CC) at paras 36 and 39.
sino noindex
make_database footer start
Similar Cases
Sasol Oil Limited v B-BEE Commission and Others (21415/2020) [2022] ZAGPPHC 431 (14 June 2022)
[2022] ZAGPPHC 431High Court of South Africa (Gauteng Division, Pretoria)99% similar
Sasol Oil (Pty) Limited v Eurozar (Pty) Limited and Others (56719/2021) [2022] ZAGPJHC 17 (19 January 2022)
[2022] ZAGPJHC 17High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Sasol South Africa Limited v Sasol Pension Fund and Others (2025/010962) [2025] ZAGPJHC 1193 (20 November 2025)
[2025] ZAGPJHC 1193High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Sasol Oil and Another v Bitline SA 951 CC t/a Sasol Roodepoort West and Another (2023-052191 ; 2023-052612) [2023] ZAGPJHC 1437 (11 December 2023)
[2023] ZAGPJHC 1437High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Sasol Financing International PLC v Commissioner for the South African Revenue Services (Leave to Appeal) (2018/58410; 2019/66502) [2024] ZAGPPHC 967 (20 September 2024)
[2024] ZAGPPHC 967High Court of South Africa (Gauteng Division, Pretoria)99% similar