Case Law[2025] ZAGPPHC 1082South Africa
Rand Water Board v Rautenbach and Another (A270/24; 4654/2019) [2025] ZAGPPHC 1082 (6 October 2025)
High Court of South Africa (Gauteng Division, Pretoria)
6 October 2025
Headnotes
the appellant had consented to the construction of the structures which
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 1082
|
Noteup
|
LawCite
sino index
## Rand Water Board v Rautenbach and Another (A270/24; 4654/2019) [2025] ZAGPPHC 1082 (6 October 2025)
Rand Water Board v Rautenbach and Another (A270/24; 4654/2019) [2025] ZAGPPHC 1082 (6 October 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_1082.html
sino date 6 October 2025
SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
FLYNOTES:
PROPERTY – Encroachment –
Consent
–
Correspondence
expressed no objection in principle and attached site plans –
Interpreted as implicit consent –
Conduct created a
reasonable impression of consent – Letters constituted
written consent when read as a whole –
Granted consent to
encroachments through correspondence and attached site plans –
Respondent entitled to rely on estoppel
as requirements were
satisfied – Order compelling inspection and compliance with
statutory duties justified –
Appeal dismissed.
IN THE HIGH COURT OF SOUTH AFRICA
GAUTENG DIVISION, PRETORIA
CASE NO: A270/24
CASE NO. A QUO: 4654/2019
(1)
REPORTABLE: YES/
NO
(2)
OF INTEREST TO OTHER JUDGES: YES/
NO
(3)
REVISED.
SIGNATURE
DATE
6/10/2025
In
the Full Court Appeal of:
RAND
WATER
BOARD
Appellant
and
RAUTENBACH,
IANTHE FLORENCE
First Respondent
TSHWANE
METROPOLITAN MUNICIPALITY
Second Respondent
JUDGMENT
CORAM
MOLOPA-SETHOSA J, FRANCIS-SUBBIAH J AND LABUSCHAGNE J
[1]
The Rand Water Board (the “appellant”) is an organ of
State
established in terms of the Water Services Act,108 of 1997,
which has a pipeline servitude that runs through Woodhill Golf Estate
in Pretoria to supply the residents of Pretoria East with sufficient
water. The appellant alleges that the home and the pool
on the
first respondent’s property encroach on the appellant’s
16 meter servitude and onto a 2 meter buffer zone on
the side of the
servitude, thereby preventing the appellant from installing a second
pipeline. The first respondent passed away
in 2023 and was
represented at trial and in the appeal by her duly appointed
executor.
[2]
In the Court
a quo
the appellant sought an order in motion
proceedings that the first respondent be directed to demolish the
encroachment, failing
which the Sheriff should do so. As an
alternative, a declarator was sought that the first respondent has
spoliated the appellant
of its undisturbed possession of the
servitude, including a 2 meter buffer zone on each side thereof.
[3]
The matter came before Neukircher J who referred to matter to trial.
The
matter proceeded to trial before Swanepoel J who held that the
appellant had consented to the construction of the structures which
it now contends need to be demolished.
[4]
The first respondent brought a counterclaim based on an allegation by
the plaintiff
in its founding affidavit that the existing pipeline
has not been maintained and is at serious risk of bursting. In
the counterclaim
the first respondent sought an order, that the
appellant should inspect the pipeline and report to the first
respondent and to
the Court whether the pipeline is safe, and if not,
the appellant should state what precautions are to be taken to
minimise the
danger. The first respondent also sought a
declaratory order that the appellant had consented in writing to the
development
in its current form, alternatively that the first
defendant be granted consent for the current encroachment as provided
for in
the notarial deed of servitude.
[5]
Swanepoel J dismissed Rand Water’s claim on the basis of
consent having
been given and upheld the counterclaim in part,
directing Rand Water to inspect the pipeline and to comply with its
statutory duties.
[6]
This is the appeal against the dismissal of the claim and the
granting of the
counterclaim by Swanepoel J. The appeal is with leave
of the SCA, Swanepoel J having refused leave to appeal.
THE SERVITUDE
[7]
On 9 December 1997 a servitude was registered over the remainder of
Portion 2[…]
of the Farm Garsfontein 3[…], Registration
Division JR, Gauteng in favour of the Rand Water Board, granting it
the right
to convey water and to transmit water over a strip of land
situated on the aforesaid property, 16 meters wide and measuring a
total
of 2,5887 hectares in extent, as denoted on Surveyor General
Diagram 9450/1982 with the letters ABCDEFGHJKLMNP. The area is
defined as the “strip” in the Deed of Servitude
K7429/1997S. The rights of the appellant include the right to
patrol, inspect, maintain, repair, remove and relay the pipeline and
its accessory equipment on the strip, including a right of
way and a
right of ingress and egress from the property.
[8]
The provision pertaining to offending structures in the buffer strip
of 2 metres
is in paragraph 2, which reads:
“
2. There
shall be no structures erected, parking allowed, trees planted or
material placed or deposited on or
over the strip, or within 2 (two)
meters thereof, and the depth of cover over the pipeline shall not be
materially altered, without
written consent from Rand Water, which
consent shall not be unreasonably withheld.”
[9]
The 16 meter strip (“the strip”) is 1.6 km long and has a
2 meter buffer zone on either side.
[10]
In the Court
a quo
uncontested evidence of a surveyor, Mr
Matsobane Dolo established that the first respondent’s home
does not encroach onto
the servitude. It does however encroach
0.34 meters into the buffer zone for a total area of 1.25 square
meters and the first
respondent’s swimming pool encroaches by
1.65 meters onto the buffer zone, for a total area of 6.32 square
meters.
[11]
The appellant contended that due to the encroachments it is unable to
lay a second pipeline
on the northern side of the existing pipeline,
which is on the far side of the existing pipeline from the first
respondent’s
home.
[12]
The Court
a quo
found that the appellant’s servitude
extends to the strip, but not to the buffer zone. As far as the
buffer zone is
concerned, the appellant merely have the right to
insist that the buffer zone is not encroached upon. It however
does not
have the right of use of the buffer zone for purposes of
laying the pipeline. That has to take place within the strip of
16 meters.
[13]
This point alone would be dispositive of the appellant’s case
in the Court
a quo
, but the Court
a quo
assumed in
favour of the appellant that it had the same rights in respect of the
buffer zone as it has in respect of the strip.
[14]
The Court then proceeded to determine whether written consent had
been granted by the appellant
as envisaged by Clause 2 of the Deed of
Servitude for the encroachments in the buffer zone.
THE FACTS
[15]
The salient facts pertaining to the dimensions and location of the
servitude and the encroachments
are not challenged on appeal. The
dispute on appeal relates to whether Rand Water consented to the
encroachments. In paragraphs
[10] to [14] of the judgment
a quo
Swanepoel J sets out the relevant facts with reference to the
documents which are here repeated:
“
[10]
On 28 November 2005 the architects, acting on behalf of the developer
of the property, Nuclei Lifestyle
Design, sought consent from the
plaintiff (Rand Water-our insertion)) for the development of the
property. The material part
of the letter reads as follows:
‘
DEVELOPMENT OF ERF 4[...]
P[...] P[...] X[...]
The registered letter received from
The City of Tshwane City Planning
PRETORIA AMENDMENT SCHEME 9196: ERF
4[...] P[...] P[...] [...]
states in annexure B of Amendment
Scheme 9169/.8:
‘
all the conditions
imposed by Rand Water shall be complied with to the satisfaction of
the municipality.’
·
Firstly could you please forward us all the conditions referred to
by the municipality, and
·
Secondly also have a look at the site development plan attached
and let us know if this will be acceptable for Rand Water.”
[11]
Attached to the letter was a site plan reflecting the envisaged
development. The plan reflected
the 16 meter wide strip, but it
did not reflect the 2 meter buffer zone. All six of the
relevant homes, including the first
defendant’s home (Unit […])
are reflected on the plan, and clearly, all encroach into the buffer
zone, and one also
encroaches into the servitude by approximately 10
cm.
[12]
On 8 December 2005 the plaintiff replied to the architect’s
letter. The reply commenced
with the words: ‘Your letter
of 28 November 2005
and
the accompanying plan
,
refer
(my emphasis)’.
The letter recorded
that the proposed development was in close proximity to the
servitude. It also recorded that the plaintiff intended
to lay a
second pipeline along the servitude. Furthermore, the plaintiff
recorded that it required unimpeded access to the
pipeline at all
times. It also dealt with certain requirements relating to
fencing, and a number of other prohibitions.
Significantly, the
letter did not refer at all to the buffer zone. It simply
recorded that the plaintiff was the holder of
a 16 meter wide
servitude in terms of Deed of Servitude K7429/97. Attached to
the letter was an annexure “
A”
,
and the first defendant’s architects were specifically referred
to Clause 1.3 thereof. The material part of the letter
reads as
follows:
“
Rand Water has no objection
in principle to the proposed development provided than in addition to
the abovementioned requirements,
all the relevant conditions in the
enclosed copy of annexure “A” are complied with and
accepted in writing by your
client and/or the owner.
[13]
It is common cause that the letter of 8 December 2005 is a consent to
the development of the
property on the conditions set out therein and
in annexure “A” to the letter. The first question
is what conditions
were imposed upon the developer and secondly
whether the plaintiff consented to the erection of buildings in the
buffer zone.
The plaintiff says that he did not consent to an
encroachment into the buffer zone, and that the reference in the
letter to Clause
1.3 of annexure “A” makes it clear that
no construction was allowed to take place in the buffer zone.
The plaintiff
led the evidence of Ms Paleka Mashele, who testified
that she was a Senior Civil Technologist in the plaintiff’s
employ.
She denied that the plaintiff had consented to the
erection of structures in the buffer zone. She relied upon
Clause 1.3
of annexure “A” to justify her view.
Clause 1.3 reads as follows:
‘
No service (e.g. Fibre Optic
Cables / Telecommunications Cables) running parallel to Rand Water’s
pipeline/s, no box, manhole,
structure supporting any services,
footing of any pylon, pill or stay wire and no stormwater culvert /
or appurtenances shall be
within 2 meters of Rand Water’s
pipeline/s or on Rand Water’s servitude/s or proposed
servitude/s or discharge thereon
unless the written permission of
Rand Water has been obtained. Rand Water’s final approval
needs to be obtained.
Such services must be outside Rand
Water’s servitudes.’
[14]
On 22 February 2008 the owner’s consulting engineers wrote a
further email to the plaintiff,
again attaching a plan showing the
layout of the proposed development. This plan also did not show
the buffer zone, but it
clearly showed that the houses were to be
erected partially on the area of the buffer zone, and that one home
would also encroach
onto the strip (by 3 cm). On 6 March 2008
the plaintiff replied to the email. It pointed out that the
plaintiff had
previously commented on the proposed development, and
it simply repeated the conditions set out in the plaintiff’s
letter
dated 8 December 2005. Once again, a reference is made
to annexure “A”, and particular to Clause 1.3 thereto.
No reference is made to the buffer zone. The relevant part of
the letter reads as follows:
‘
No structures including
gazebos, patios, splash pools, etc. will be allowed
within
Rand Water’s servitude
(referred to Clause 1.3 of
attached annexure “A”) (my emphasis)’.”
[16]
The appellant contends that Clause 1.3 must be interpreted to have
conveyed to the
developer that the erection of any structures on the
buffer zone was prohibited.
[17]
The Court
a quo
found that the appellant had approved the
development on two separate occasions with express reference to the
site plan. The first
was prior to construction. That site plan
indicated, as set out supra, where encroaching structures would
appear on the buffer
zone. Even assuming that the appellant had
the right to use the buffer zone (which was found not to be the case)
the Court
a quo
found that the appellant was on the facts
estopped from asserting its rights. It was bound to the
representation of consent as contained
in its responses to
applications for consent as set out supra.
[18]
The reference to estoppel as a defence would only arise if the
appellant had not
in fact consented. As the question of consent
is determined by the Court’s interpretation of Clause 1.3 and
clause
2 of the Deed of Servitude as quoted supra, a finding that
there was consent is dispositive of the matter.
THE COUNTER APPLICATION
[19]
In paragraphs [77] to [79] of the founding affidavit the deponent for
Rand Water states:
“…
as a result of
these obstructions or encroachments, at the point of the
encroachments, it has been rendered impossible to undertake
patrols,
inspections, remove or lay further pipelines, as the applicant now
urgently seeks to do … In fact, in the
normal course,
the pipeline network is exposed to corrosion from stray current
sources, corrosive soils and microbiological corrosion,
which results
in metal loss and threatens the integrity of the pipeline …
Upon a likely and resultant pipeline burst, the
consequences will
certainly be catastrophic and deadly, owing to the high volume of
water and the pressure through which it will
flow out, in particular,
considering the close proximity of the encroaching structures to the
pipeline.”
[20] The
Court
a quo
found that, as these averments emanated from the
appellant, and as it had expressed no intention of maintaining the
pipeline in
the normal course, that a need for the interdict had been
established.
THE APPELLANT’S CONTENTIONS
ON APPEAL
[21]
The crux of the appellant’s contentions is that, on a proper
construction of
Clause 2 of the Deed of Servitude, the appellant
could only consent to any development, both in the strip or servitude
and buffer
zone, in writing. The appellant contends that the
Court
a quo
erred and ought to have found that firstly there
was no application to develop the buffer zone, and secondly, that
there is no written
consent to develop the buffer zone.
[22]
In the alternative, the appellant contends that Clause 2 of the Deed
of Servitude reigns
supreme and that Clause 1.3 of the annexure “A”,
being a subsidiary document “
cannot be used to make or
render the terms of the Deed of Servitude unworkable or to make the
servitude impractical and ineffective.”
[23]
In respect of the granting of the counterclaim, the appellant
contends that the Court
a quo
erred in misconstruing the
dangers referred to. The appellant contends that the risks to
the pipeline are created by the encroachment
and not by the failure
to maintain or inspect the pipeline.
On the issue of costs, the appellant
contends that the Court
a quo
erred in awarding costs of two
counsel. It contends that the Court
a quo
failed to
exercise a discretion in respect of costs.
[24]
During argument, counsel for Rand Water sought to interpret the
aforesaid letters of 8
December 2005 and 6 March 2008 without
reference to the site plan, that was annexed to each of the letters,
contending that it
was impermissible to refer to the site plan.
[25]
As far as the counterclaim is concerned, the appellant argued that
the affidavit evidence
relied on by the court as the basis for the
order granted a quo was not before the trial court. Those affidavits
served before
Neukircher J but were not “in evidence”
before Swanepoel J.
DISCUSSION
[26]
The appellant advanced a position on appeal at variance with the
evidence that served before
Swanepoel J in contending that clause 1.3
of its standard terms and conditions in respect of servitudes cannot
be used to interpret
clause 2 of the Deed of Servitude. At trial Ms
Mashele based her case for the absence of consent on clause 1.3 (see
par [13] of
the judgment
a quo
, quoted supra in par [15]). She
was however only employed by Rand Water in March 2013. Her
interpretation of documents is therefore
a retrospective
interpretation of documents written prior to her employment by Rand
Water.
[27]
Swanepoel J correctly found that clause 1.3 prohibits structures
within two meters of the
pipeline and not within two metres of the
pipeline servitude. The latter would have included the buffer zone.
But grammatically
the prohibition related to structures within close
proximity to the pipeline. The evidence is therefore not on point.
[28]
It is trite that documents need to be interpreted using the three
guiding principles
set out in
Natal Joint Municipal Pension Fund v
Endumeni Municipality
[2012] ZASCA 13)
at par (17 - 26) of text,
context and purpose.
[29]
The appellant’s interpretation exercise pertaining to consent
to encroachments
as envisaged by clause 2 the Deed of Servitude is
difficult to understand. The appellant made much of the fact that the
letters
by Rand Water reflected early in the document that the
encroachments were in close proximity to its servitude of pipeline.
That
alone is advanced as an indicator that there was not consent. In
addition, it was argued that the annexed site plan could not be
referred to as part of the interpretation of the letters concerned.
[30]
The aforesaid approach falls fouls of two principles of
interpretation. The first
is that a document needs to be read as a
whole. The second is that, where Rand Water itself attaches the site
plan as part of its
response, that site plan becomes part of the
document, or at least provides context for the response. Whether the
annexure is seen
as part of the letter as a matter of text alone, or
whether it merely provides context, both approaches point to its
inclusion
in the interpretation of the letter.
[31]
Rand Water’s argument on consent ignores the fact that the Rand
Water letters
of 2005 and 2008 were responses to enquiries whether
the layout on the site plan would meet with Rand Water’s
approval. And
both letters express no objection in principle and
attach the very site plan in question. To craft a negative response
in such
circumstances is to ignore the context of the response and
its content, read as a whole.
[32]
The finding of the court a quo on the presence of consent, as
envisaged in clause
2 of the Deed of Servitude, for the structures in
the buffer zone cannot be faulted. That is dispositive of the crux of
the appeal.
[33]
On a belts and braces approach, the court a quo entertained an
alternative
basis of consent based on an estoppel. It found that,
even if there were some subjective
reservatio mentalis
on the
issue of consent, that Rand Water gave a negligent representation of
consent, based on which the structures were erected
in the buffer
zone. Having acted to her detriment, in reliance on such
representation being made, by constructing the encroachments
in the
buffer zone, the first respondent is entitled to hold Rand Water to
its representation of consent.
[34]
The only issue in respect of the estoppel is whether the requirement
imposed in certain
authorities that the representation had at least
to be negligent, had been established. The authorities on estoppel
include a limited
fault requirement. The requirements for an estoppel
do not expressly require fault-In
Aris Enterprises (Finance)
(Pty)(Ltd) v Protea Assurance Co Ltd
1981 (3) SA 274
(A) the
following is stated at 291B:
“
Finally,
I come to the estoppel point. Appellant's counsel agreed that the
estoppel contended for by him was an instance of estoppel
by
representation. The essence of the doctrine of estoppel by
representation is that a person is precluded, i.e. estopped, from
denying the truth of a representation previously made by him to
another person if the latter, believing in the truth of the
representation, acted thereon to his prejudice (see Joubert,
The
Law of South Africa
vol
9 para 367 and the authorities there cited). The representation may
be made in words, i.e. expressly, or it may be made by conduct,
including silence or inaction, i.e. tacitly (
ibid
para
371); and in general, it must relate to an existing fact (
ibid
para
372).”
[35]
The
representation in question must have the capacity to mislead a
reasonable man (
Ibid
at 292E)- i.e. the failure to correct a wrong impression reasonably
created can result in the invocation of an estoppel.
[36]
In
this instance the letters from Rand Water created a clear impression
that consent to the location of specific encroachments detailed
in a
site plan was being given in 2005 (and later confirmed in 2008 in
respect of a slightly amended and annotated site plan).
A reasonable
man would interpret the letters in this manner and the failure to
correct that impression timeously would be negligent
as reliance on
the misrepresentation was foreseeable.
[37]
Although
unnecessary on the facts, the court a quo correctly applied the
principles of estoppel as an alternative approach. As there
was
consent there is no need to consider the scenario that was pleaded by
the first respondent, in its third counterclaim, i.e.
that consent
was unreasonably withheld and that an order to that effect should be
granted.
THE COUNTERCLAIM
[38]
Counsel for
Rand Water contended that, as the sole source for the granting of the
counterclaim was the content of certain paragraphs
of Rand water’s
founding affidavit in the motion proceedings, the court a quo erred
as those affidavits were not evidence
before the trial court. That
would distinguish a referral to trial from a referral to evidence
where the affidavits are still before
court as the proceedings remain
motion proceedings.
This distinction is important since
the consequences are different, as was highlighted by the Supreme
Court of Appeal in
Lekup Prop Co No 4 v Wright
2012 (5)
SA 246
SCA at [32]:
'[32] … It will be
recalled that the appellant initiated motion proceedings and that the
matter was referred to trial
after the respondent had filed his
answering affidavit. At the trial the respondent was allowed to read
from that affidavit and
did so, extensively. That was not the correct
procedure. … Affidavits filed may of course be used for
cross-examination
and also as proof of admissions therein contained,
but (save to the extent that they contain admissions) they have no
probative
value; and in the absence of agreement, they do not stand
as the witness's evidence-in-chief or supplement it. …
A referral
to trial is different to a referral to evidence, on
limited issues. In the latter case the affidavits stand as
evidence, save
to the extent that they deal with dispute(s) of fact;
and once the dispute(s) have been resolved by oral evidence, the
matter is
decided on the basis of that finding together with the
affidavit evidence that is not in dispute.
[39]
What distinguishes the aforesaid position is that the first
respondent in claim 1
of her counterclaim quoted in full at par 85 of
the counterclaim the content of par 77-80 of the founding affidavit
of Rand Water,
which Rand Water admitted in the plea to that
counterclaim. Those paragraphs were therefore common cause before the
trial court.
[40]
The trial court therefore did not err in this regard. There is no
basis for interfering
with the partial granting of the counter
application.
COSTS
[41]
Counsel for the appellant contends that the court a quo did not apply
its mind by
ordering it to pay the costs of two counsel.
[42]
This submission was made while counsel for the appellant was leading
junior counsel
in the appeal. It was submitted that that is an
irrelevant consideration as the complexity of the issues determine
the costs. Two
counsel were thought to be justified by both parties.
While that is not a conclusive consideration, it is relevant. In
addition,
the court regards the issue to be sufficiently important to
the estate of the late Ms Rautenbach to employ two counsel. This
dispute
with Rand Water has had the effect of depressing the value of
her property and the administration of her estate. There are many
other adjacent properties for which this is a test case. It is
therefore an important issue in the community whose properties are
subject to the servitude in that area.
[43]
Having considered both arguments before this court, and taking into
consideration all factors;
and in the light of what is stated above,
it is proposed that an order in the following terms be made:
ORDER
[44]
In the premises the following order is made:
1.
The appeal is dismissed with costs, such costs to include the costs
of
two counsel, on Scale C
EC LABUSCHAGNE
JUDGE
OF THE HIGH COURT
I agree
L M MOLOPA-SETHOSA
JUDGE
OF THE HIGH COURT
I
agree
R
FRANCIS-SUBBIAH
JUDGE
OF THE HIGH CO
URT
APPEARANCES:
FOR
APPELLANT:
INSTRUCTED
BY:
FOR
RESPONDENT:
INSTRUCTED
BY:
sino noindex
make_database footer start
Similar Cases
Rand Water Board v Rautenbach and Another (4654/2019) [2022] ZAGPPHC 497 (13 July 2022)
[2022] ZAGPPHC 497High Court of South Africa (Gauteng Division, Pretoria)99% similar
Rand Water v Taroline (Pty) Ltd and Others (2024-124556) [2025] ZAGPPHC 571 (4 June 2025)
[2025] ZAGPPHC 571High Court of South Africa (Gauteng Division, Pretoria)99% similar
Department of Water and Sanitation v Klerksdorp Irrigation Board (90569/2019) [2022] ZAGPPHC 850 (7 November 2022)
[2022] ZAGPPHC 850High Court of South Africa (Gauteng Division, Pretoria)98% similar
Minister of Water and Sanitation v Limphota Housing CC (Leave to Appeal) (17766/2023) [2025] ZAGPPHC 346 (1 April 2025)
[2025] ZAGPPHC 346High Court of South Africa (Gauteng Division, Pretoria)98% similar
Minister of Water and Sanitation v Fumile Advisory Services (Pty) Ltd and Others (60250/2018; 86068/2018) [2025] ZAGPPHC 399 (14 April 2025)
[2025] ZAGPPHC 399High Court of South Africa (Gauteng Division, Pretoria)98% similar