Case Law[2025] ZAGPPHC 1230South Africa
Engie-Pele Sannaspos Solar PV Consortium and Another v Director General of Mineral Resources and Energy and Others (114928/2024) [2025] ZAGPPHC 1230 (21 November 2025)
Headnotes
Summary:
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 1230
|
Noteup
|
LawCite
sino index
## Engie-Pele Sannaspos Solar PV Consortium and Another v Director General of Mineral Resources and Energy and Others (114928/2024) [2025] ZAGPPHC 1230 (21 November 2025)
Engie-Pele Sannaspos Solar PV Consortium and Another v Director General of Mineral Resources and Energy and Others (114928/2024) [2025] ZAGPPHC 1230 (21 November 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_1230.html
sino date 21 November 2025
SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
CASE
NO.: 114928/2024
(1)
REPORTABLE:
YES
/ NO
(2) OF
INTEREST TO OTHER JUDGES:
YES
/ NO
(3)
REVISED
DATE: 21/11/2025
SIGNATURE
In the matter between:-
ENGIE-PELE
SANNASPOS SOLAR PV CONSORTIUM
First
Applicant
SANNASPOS
SOLAR PV (PROPRIETARY) LIMITED
Second
Applicant
v
THE
DIRECTOR GENERAL OF MINERAL RESOURCES
AND
ENERGY
First
Respondent
ABSA
BANK LIMITED
Second
Respondent
IPP
OFFICE
Third
Respondent
THE
MINISTER OF ELECTRICITY AND ENERGY
Fourth
Respondent
NATIONAL
TREASURY
Fifth
Respondent
DEVELOPMENT
BANK OF SOUTH AFRICA
Sixth
Respondent
THE
MINISTER OF MINERAL RESOURCES
AND
ENERGY
Seventh
Respondent
THE
DEPARTMENT OF MINERAL RESOURCES
AND
ENERGY
Eighth
Respondent
Heard
on:
04
September 2025
Delivered:
21 November
2025 -
This judgment was handed down electronically by circulation to the
parties' representatives by email, by being uploaded
to
the
CaseLines
system
of the GD and by release to SAFLII. The date and time for hand-down
is deemed to be 14:00 on 21 November 2025.
Summary:
1.
The core dispute for
determination is when did the Preferred Bidder Guarantee lapse. The
parties presented differing interpretations
as to how the “Bid
Validity Period” is determined in accordance with the bidding
documents, primarily in the RFP and
the Signed Implementation
Agreement as well as the Preferred Bidder Guarantee.
2.
The rules of
interpretation have been settled by our higher courts, namely in the
Endumeni
and
Fidelity
Security Matters
cited
in the judgment.
3.
On interpreting the
relevant documents referred to, together with the language used, the
context and the purpose for which they
were prepared and in the eyes
of a reasonable commercial person. I find that the Preferred Bidder
Guarantee lapsed when they Signed
Implementation Agreement lapsed.
4.
The Consortium has
further met the requirements for both declaratory relief and final
interdictory relief.
ORDER
It is ordered:-
1.
The Preferred Bidder Guarantee lapsed on 30 November 2023;
2.
The Director-General of Mineral Resources (the DG) and the Department
of Mineral
Resources and Energy are directed to release the Preferred
Bidder Guarantee by returning it to the first applicant,
alternatively
to ABSA, and are further interdicted and prohibited
from making any demands in terms of the Preferred Bidder Guarantee;
3.
ABSA is directed not to make any payment pursuant to any demand
issued under
the Preferred Bidder Guarantee; and
4.
The first, third, fourth and seventh respondents are ordered to pay
the costs
of this application on Scale C, which costs are consequent
upon the employment of two counsel.
JUDGMENT
KOOVERJIE
J
[1]
This matter turns on the interpretation of the Preferred Bidder
Guarantee which was
issued by Absa Bank in the sum of R15 million in
favour of the first respondent, the Director-General of the
Department of Mineral
Resources and Energy (“the DG”).
The core issue for determination is when did Preferred Bidder
Guarantee lapse?
For the purposes of this judgment, the
applicants will be referred to as the “
Consortium”
and the first respondent as the “Department”.
[2]
The applicants essentially seek relief to the following effect:
2.1
a declaratory order confirming that the Preferred Bidder Guarantee
lapsed on 8 December
2022, alternatively on 30 November 2023;
2.2
an interdict against the Department from making any demand under the
Preferred Bidder Guarantee
and release same to the first applicant,
alternatively the second respondent.
BACKGROUND
[3]
The following facts are not in dispute. In October 2021, the
first applicant,
Engie-Pele Sannaspos Solar PV Consortium (“the
Consortium”) was appointed as a preferred bidder in terms of
the Department’s
renewable energy programme, namely the
Renewable Energy Independent Power Producer Procurement Programme
(“REI PPPP”).
This was part of a competitor tender
process which was initiated by the Independent Power Procurement
Programme Office (“the
IPP Office”). The objective
was to make provision for private sector investment in the
grid-connected renewable energy
generation.
[4]
The Consortium was required to incorporate a special purpose vehicle
(“the SPV”),
namely Sannaspos Solar PV (Proprietary)
Limited, which was to carry out the Consortium’s obligations.
[5]
To confirm the appointment as a preferred bidder, the Consortium was
required to lodge
a Preferred Bidder Guarantee in an amount of
R200,000.00 per megawatt of the contracted capacity in relation to
each project in
favour of the Minister as set out in the Request for
Proposal (“the RFP”)
[1]
.
Such Preferred Bidder Guarantee was issued by ABSA in the sum of R15
million in favour of the Department on the 25
th
of November 2021.
[6]
The Preferred Bidder Guarantee (Guarantee) stipulated that it would
remain valid and
effective from the date of issue, being 25 November
2021 until the expiry of the bid validity period (as it may be
extended in
terms of the RFP).
[7]
This entailed that the Preferred Bidder Guarantee remains valid and
extant for the
duration of the bid validity period and lapses at the
expiry of such period. It was further stipulated that the
meaning of
the term “Bid Validity Period” in the
Preferred Bidder Guarantee should be determined with reference to the
meaning
of “Bid Validity Period” in the RFP.
[8]
By virtue of the Guarantee, ABSA irrevocably and unconditionally
undertook to pay
the Department the guarantee on demand, on the basis
that the Preferred Bidder was notified by the Department that its
Preferred
Bidder status has been revoked. The calling up of the said
guarantee was however subject to the interpretation afforded to the
term of the “bid validity period”.
[9]
Upon the lodgment Guarantee, the Consortium was required to finalise
regulatory requirements
and sign certain contracts that were
incorporated in the RFP in order to achieve Commercial Close and
terminate the “Bid
Validity Period”.
[10]
The contracts included the Template Private Purchase Agreement with
Eskom, the Template Implementation
agreement with the Department
(Appendix M to the RFP) which in effect guarantees Eskom’s
payments and provides direct contractual
obligations and undertakings
between the Department and the Preferred Bidder.
THE
PREFERRED BIDDER GUARANTEE
[11]
The wording in the Preferred Bider Guarantee is relevant to the
dispute between the parties and
reads:
“
Whereas
the Department of Mineral Resources and Energy of the Government of
the Republic of South Africa (“the Department”)
has
issued a Request for Qualifications and Proposals for New Generation
Capacity under the REIPP Procurement Programme, Tender
No:
DMRE/001/2021/22 (as amended) (“RFP”) in respect of the
finance, construction, operation, and maintenance of renewable
energy
generation facilities adopting any of onshore wind or solar
photovoltaic technologies for the purpose of entering into,
inter
alia,
an Implementation Agreement
with the Department and a Power Purchase Agreement with a buyer
.
AND
WHEREAS pursuant to the RFP, the Department has selected Engie
Sannaspos Solar SPV (“Preferred Bidder”) as the Preferred
Bidder in the Fifth Bid Submission Phase of the REIPP Procurement
Programme;
AND
WHEREAS the Department requires the Bidder to provide an on demand
guarantee in favour of the Department in the amount of R15,000,
000.00 (Fifteen Million Rand Only) (“Guarantee Amount”)
to secure certain undertakings or obligations of the Bidder
as
Preferred Bidder under the RFP in terms of clause 26.2 (Preferred
Bidder Guarantee) of Part A (General Requirements, Rules and
Provisions) of the RFP;
AND
WHEREAS we, Absa Bank Limited, Registration Number 1986/004794/06
(“Bank”) have agreed to issue this guarantee to
secure
such undertakings and obligations of the Preferred Bidder (“Preferred
Bidder Guarantee”).
NOW
THEREFORE:
1.
the Bank, duly represented by Karabo Bogatsu and Gilda Antonio in
their capacities
as BGI Case Managers being duly authorized to sign
this Preferred Bidder Guarantee, hereby irrevocably and
unconditionally guarantees
and as a primary obligation undertakes to
pay the Department without objection or argument amounts not
exceeding in aggregate the
Guarantee Amount, such payment(s) to be
made by the Bank upon first written demand by the Department being
received at the Bank’s
counter, situated at Absa Towers North,
1[...] C[...] Street, Johannesburg, 2001, attention Karabo
Bogatsu/Boipelo Moche, declaring
that the Preferred Bidder has:
1.1
breached any law relating to the REIPP Procurement Programme or been
disqualified from any
part of the REIPP Procurement Programme as a
result of its actions or omissions;
1.2
failed to
comply timeously
with any conditions contained in
the letter or appointment as a Preferred Bidder;
1.3
failed to
comply timeously
with a request for information
and/or documentation by the Department as contemplated in the RFP;
1.4
failed to pay the budget quotation fee
within the time period
specified by the Department in the RFP or in the letter of
appointment as Preferred Bidder;
1.5
failed to sign the PPA, Implementation Agreement, Direct Agreement,
Independent Engineer
Agreement and the Connection Agreements
within
the time period
specified in clause 8.4 (Timetable of the Fifth
Bid Submission phase of the REIPP Procurement Programme) of Part A
(General Requirements,
Rules and Provisions) of the RFP in respect of
the relevant Bid Submission phase, as such time period may be
extended by the Department
on written notice to the Preferred Bidder;
1.6
having signed the PPA, Implementation Agreement, Direct Agreement,
Independent Engineer
Agreement and the connection Agreements, failed
to pay the Development Fee in accordance with clause 2.1 of the
Implementation
Agreement or failed to comply with the requirements of
any information or documentation request, or of any protocol issued
by the
Deparmtne including in relation to the submission to the
Department of the computer model which is to be attached to the
Implementation
Agreement as Schedule 5 (Financial Model) following
Financial Close;
1.7
failed to extend the term of the
Preferred Bidder Guarantee as required by the RFP; or
1.8
been notified by the Department that its status as preferred Bidder
has been revoked for
any reason.
2.
More than 1 (one) demand may be
made under this Preferred Bidder Guarantee, provided
that the
aggregate amount payable shall not exceed the Guarantee Amount.
3.
…
4.
This
Preferred Bidder Guarantee shall be valid and effective from
the date of its issue until the earlier of (a) the expiry of the Bid
Validity Period (as it may be extended in terms of the RFP):
and
(b) the later of the date of payment of the Development Fee in
accordance with clause 2.1 of the Implementation Agreement, and
the
date on which the preferred Bidder complies with the requirements of
any protocol issued by the Department in relation to the
submission
to the department of the computer model which is to be attached to
the Implementation Agreement as Schedule 5 (Financial
Model),
following Financial Close, provided that once Financial Close has
been reached on the Preferred Bidder’s Project,
item (a) no
longer applies and this Preferred Bidder Guarantee shall remain valid
until the later of the events described in item
(b) hereof.
5.
The Preferred Bidder Guarantee shall remain valid during the period
described
above notwithstanding the Bidder’s insolvency,
winding-up, liquidation, business rescue, dissolution or
deregistration, whether
provisionally or finally.
6.
Notwithstanding the above provisions, this Preferred Bidder Guarantee
shall terminate
and be returned to the Bank within fifteen (15)
Business Days of payment of an amount or amounts which, in aggregate,
equal the
Guarantee Amount, or of expiry of the Preferred Bidder
Guarantee as set out above.
7.
This Preferred Bidder Guarantee shall be governed by the laws of the
Republic
of South Africa, and the parties hereto consent and submit
for the benefit of the Department to the non-exclusive jurisdiction
of the North Gauteng High Court of South Africa.”
[12]
In terms of Clause 19.5.1 of the RFP, the arrangement was that the
Preferred Bidder accepts the
terms and conditions once:
12.1.
the bidder fee is paid into the bank account designated by the
Department as provided with the Guarantee;
12.2.
the preferred bidder accepts the terms and conditions of the
appointment as bidder, and;
12.3.
the Preferred Bidder Guarantee is issued.
[13]
Clause 26.2.4 of the RFP further stipulated that the Guarantee was
“valid and effective”
for a period from the date of issue
of the Guarantee until the earlier of (a) the expiry of the Bid
Validity Period (as extended
from time to time); and (b) the later of
the date on which the Bidder complies with certain requirements.
[14]
The wording in Clause 4 of the Guarantee is premised upon the wording
in Clause 26.2.2.4 namely
that the Guarantee shall be:
“
valid
and effective from the date of its issue until the earlier of (a) the
expiry of the Bid Validity Period (as it may be extended
in terms of
the RFP)”.
This
entailed that the Guarantee would lapse when the “bid validity
period expires”.
[15]
The RFP anticipated that the preferred bidders should achieve
Commercial Close within four months
of appointment as preferred
bidders. However, this was not the case in respect all the
preferred bidders, which included
the Consortium. The
Department effected amendments to the Template Implementation
Agreement which resulted in the Signed
Implementation agreement.
[16]
The Consortium in fact signed the Implementation Agreement on 8
December 2022 and was required
to meet the suspensive conditions and
achieve Commercial Close by 7 April 2023.
[17]
As it failed to do so the Department again extended the period by
which the Consortium was required
to meet the suspensive conditions
and achieve Commercial Close which was 30 November 2023. Since
the Consortium could not
achieve commercial close by this date and
the execution of the Implementation Agreement therefore lapsed.
Notably the 30
November 2023 was the last extended date.
[18]
The Consortium holds the view that the Preferred Bidder Guarantee
lapsed and requested the Department
to return the guarantee.
The Department held a different view, namely that the Preferred
Bidder Guarantee had not lapsed.
[19]
The Department nevertheless persisted in calling up the Guarantee and
eventually caused a handwritten
demand to be delivered to ABSA,
calling up the guarantee. Due to the Department’s stance,
the applicants instituted
these proceedings in the month of October
2024.
ANALYSIS
[20]
It is evident from the contentions raised by the parties that they
bear different interpretations
as to when they Guarantee lapsed. The
relevant documents include the RFP, the Preferred Bidder Guarantee
and the Signed Implementation
Agreement. The correct approach to
interpretation has been enunciated and confirmed by our higher
courts.
[21]
More recently in the
Fidelity
Security
matter
[2]
the Constitutional
Court affirmed the approach set out in
Endumeni
[3]
.
At
paragraph 34, the court outlined the following:
“
(a)
Words in a statute must be given
their
ordinary grammatical meaning
unless to do so would result in an absurdity.
(b)
This general principle is subject to three interrelated riders:
a statute must
be interpreted
purposively
; the relevant
provision must be properly
contextualized
; and the statute
must be construed
consistently with the Constitution
, meaning
in such a way as to preserve its constitutional validity.
(c)
Various propositions flow from this general principle and its
riders. Among
others, in the case of ambiguity, a meaning that
frustrates the apparent purpose of the statute or leads to
results
which are not businesslike or sensible results should not be
preferred where an interpretation which avoids these unfortunate
consequences is reasonably possible
. The qualification
“reasonably possible” is a reminder that Judges must
guard against the temptation to substitute
what they regard as
reasonable, sensible or businesslike for the words actually used.
(d)
If reasonably possible, a statute should be interpreted so as to
avoid a lacuna (gap)
in the legislative scheme.”
[22]
Interpretation should therefore be afforded in the context of the
language, context and purpose
for which the documents came to light.
In summary:
22.1
the ordinary words of grammar, the context in which the provisions
appears, the apparent purpose to
which it is directed and the
material known to those contracting must be considered;
22.2
furthermore the process should be objective and a sensible meaning is
to be preferred rather than that
is unbusinesslike or insensible or
undermines the current purpose of the document;
22.3
a court should also not substitute meanings and interpretation to
what it regards as reasonable, sensible
or businesslike with the
words actually used.
Endumeni
extrapolated that:
“…
In
a contractual context it is to make a contract for the parties other
than the one they in fact made. The ‘inevitable
point of
departure is the language of the provision itself’, read
in context and having regard to the purpose of the
provision and the
background to the preparation and production of the document.”;
22.4
contracts are to be interpreted to ascertain the intention of the
parties and what the parties attended
to achieve.
[4]
[23]
In general, a “Bid Validity Period” is the period within
which the bidder agrees
to keep the offer legally binding. The
purpose of subscribing to a “Bid Validity Period” is to
enable bidders to commit
to not withdraw from the bid for a specified
period. The period of the bid validity must therefore be clearly
stated in the bidding
documents.
[24]
It is necessary to appreciate the context and purpose of the
respective bidding documents. The
RFP constituted a formal invitation
to the bidders to submit their bid responses for the supply of energy
to the buyer. The RFP
had set out the rules of participation in the
REIPP Procurement Programme and provided further information so as to
enable the
bidders to prepare comprehensive and competitive bid
responses in respect of their projects in terms of the procurement
programme.
[25]
On the other hand, it enabled the Department to assess the bid
responses in a manner where the
bidders would be assessed with regard
to specific outlined criteria. More importantly it enabled the
Department to select preferred
bidders and facilitate commercial
close.
[26]
Notably the RFP does not constitute an offer to enter into a
contractual relationship with any
bidder but serves to solicit bid
responses to enable the department to select the preferred
bidders
[5]
.
[27]
In terms of the Signed Implementation Agreement the parties agreed
that the seller would undertake
the projects in compliance with the
terms and conditions set out in such agreement as well as the PPA
(Power Purchase Agreement)
[28]
It was further agreed that the written Signed Implementation
Agreement constituted their agreement
in its entirety.
[29]
The Consortium took no issue with the proposition that the Preferred
Bidder Guarantee should
be interpreted with reference to the term
“Bid Validity Period” as set out in the RFP. However, it
is the interpretation
of the term in context that is placed in
dispute.
[30]
The “Bid Validity Period” is defined in the RFP as …
“
one year following the date of the bid submission, which
period is automatically extended upon a bidder’s appointment by
the
Department as a Preferred Bidder until
Commercial
Close
”
:
30.1
“
Commercial Close
” is defined in the RFP “
as
the effective date as defined in the Implementation Agreement”
;
30.2
“
Implementation Agreement
" is defined in the RFP as
“
Implementation Agreement to be entered into between the
seller and the Department, a template of which is provided in
Appendix “M”
(Implementation Agreement) in Volume 2
(Legal Requirements of this RFP)”
.
[31]
The Consortium’s initial argument was that the effective date
must be determined in terms
of the Template Implementation Agreement
which is the date on which the agreement was signed between the
parties
[6]
, 8 December 2022.
This contention, in my view, has no merit as the RFP made provision
for the parties to enter into a Signed Implementation
Agreement
[7]
.
SIGNED
IMPLEMENTATION AGREEMENT
[32]
The Consortium’s alternative argument was that if the term “Bid
Validity Period”
is to be considered in terms of the Signed
Implementation Agreement, then the suspensive conditions outlined in
Clause 3 of the
agreement have cut off dates.
[33]
Its understanding was that the suspensive conditions had to be met by
the end of the Commercial
Close period, originally set at 120 days
from the “Signature Date” but then extended to 30
November 2023, the “Bid
Validity Period” therefore
expired on 30 November 2023. If the suspensive conditions are
fulfilled before or by 30 November
2023, then the Bid Validity Period
expires.
[34]
Accordingly, if the suspensive conditions were not fulfilled on or
before the date of the Commercial
Close period, that is 30 November
2023, the agreement lapses and the Department would have no claim
against the applicant arising
from the non-fulfillment of the
suspensive conditions. Accordingly, the Preferred Bidder Guarantee
also lapsed. The Department
in these circumstances cannot call up the
guarantee.
[35]
The Department submitted that it had amended the “bid validity
period” in terms of
Briefing Note 1. The definitions of the
significant terms in the Signed Agreement clearly differed from the
Template Implementation
Agreement.
It
was in dispute that the relevant terms were amended and/or inserted,
namely:
35.1
“
Commercial Close
” was now defined as
“the date on which the last of the suspensive conditions
referred to in Clause 3.1 of this Agreement
is fulfilled being on or
before the expiry of the “Commercial Close” period;
35.2
the Commercial Close Period
(not defined in the RFP)
a definition was defined as “the period of one hundred and
twenty (120) days from “Signature
Date” as may be amended
in accordance with the provisions of the Implementation Agreement
from time to time”;
35.3
“
Signature Date
” was defined as “the
date this Agreement has been duly executed by each of the parties;
35.4
“
Effective Date
” was defined as “the
date on which the suspensive condition set out in Clause 3 …
are fulfilled as demonstrated
by the notice from the Department to
the buyer and the seller pursuant to clause 3.3.3 below”.
[36]
Clause 3 was further inserted in the Signed Implementation Agreement
and read:
“
SUSPENSIVE
CONDITIONS, ADJUSTMENT TERMS OF ENERGY RATES AND TERM
3.1
Suspensive conditions
3.1.1
Save for the provisions of this clause 3
(Suspensive
Conditions, Adjustments of Energy Rates and Term), clause 1
(Definitions and Interpretation), clause 9 (Notices), clause
15
(Assignment), clause 19 (Dispute Resolution), clause 20 (Liability),
clause 0 (Confidentiality), clause 0 (Governing Law and
Jurisdiction), clause 23 (Notices), clause 24 (Warranties) and clause
25 (Miscellaneous),
which shall be of immediate force and effect,
this Agreement is subject to the fulfilment of the following
suspensive conditions,
on or before the expiry of the Commercial
Close Period
:
3.1.1.1
the Seller obtaining and/or confirming receipt of
all Consents
required for the commencement with the Construction of the Project
including the required environmental authorization(s)
in terms of the
Environmental Laws;
3.1.1.2
the execution of the Direct Agreement, the Independent
Engineer
Agreement and any other Project Documents by all parties thereto; and
3.1.1.3
the issue of the Notice of Amendments to the PPA
charge Rates by the
Department pursuant to clause 3.2.3.1
…
.”
[37]
Furthermore Clause 3.3 clearly stipulated that if there was
non-fulfilment of the suspensive
conditions within a prescribed time
period, the implementation agreement shall no longer be of any force
or effect between the
parties and neither party shall have claim
against the other arising from the non-fulfilment of the suspensive
conditions referred
to in clause 3.1. Clause 3.3 reads:
“
3.3
Suspensive Condition Fulfilment
3.3.1
If this Agreement does not become unconditional
on or before the
expiry of the Commercial Close Period then
:
3.3.1.1
this agreement shall no longer be of any force or effect between
the Parties
; and
3.3.1.2
save as aforesaid,
neither Party shall have any claim against the
other arising from the non-fulfilment of the suspensive conditions
referred to in
clause 3.1
.
…
.
3.3.3
Upon fulfilment of the suspensive
conditions listed in clause 2.1,
the Department shall notify the Buyer and the Seller by completing
and submitting the notice as
attached in Schedule 11 (Form of IA
Effective Date Notification).”
[38]
Notably the parties are
ad idem
regarding their interpretation
insofar as the lapsing of the Signed Implementation Agreement was
concerned particularly with reference
to Clause 3.
[39]
The Department's understanding of the amendments effected as per the
signed Implementation Agreement
was that:
39.1
the Preferred Bidders were required to fulfil the suspensive
condition within 120 days from the date
of signature of the
Implementation Agreement;
39.2
the entirety of the Implementation Agreement would become fully in
force and effect if the suspensive
conditions in clause 3 were
fulfilled by the Preferred Bidder within 120 days, that is in the
Commercial Close Period;
39.3
in the event that the suspensive conditions are not fulfilled within
the 120 days the Implementation
Agreement would be of no force and
effect. The agreement therefore lapses;
39.4
the Commercial Close would be achieved on the date on which the last
of the suspensive conditions in
3.1 were fulfilled. That date
could either be before the 120
th
day or on the 120
th
day.
[40]
The parties however differ as to when the Preferred Bidder Guarantee
lapsed. The Department argued
that although the Signed Implementation
Agreement lapsed on 30 November 2023, the provisions of the RFP
regulating the relationship
between the parties remain in extant.
The “Bid Validity Period” only expires on reaching
“commercial close”
and not the failure to reach
“commercial close”. This entails that the Guarantee
remains valid until the suspensive
conditions are fulfilled. This is
when “commercial close” is achieved.
[41]
It was explained that when the Signed Implementation Agreement
lapsed, the
status quo
between the parties is revived, namely
that provision of the RFP regulating the relationship between the
parties finds application.
The Department advised that it could
amend, vary or modify the RFP. In this regard the Bid Validity Period
was then amended to
the date when the suspensive conditions become
fulfilled.
[42]
To motivate this reasoning the Department referred to Clause 30 of
the RFP which deals with the
topic “Bid Validity and Extension
of Bid Validity Period”. The term Bid Validity Period is
defined in the RFP
as “
the period identified as the Bid
Validity Period in Clause 30”.
Clause
30 which stipulates:
“
30.1
all Bid Responses constitute an irrevocable binding offer by the
Bidder to the Department;
30.2
Bid Responses must remain valid and binding for 365 (three hundred
and sixty five) calendar days from
the relevant bid submission date
(Bid Validity Period);
30.3
on appointment as a Preferred Bidder,
the
Bid Validity Period will be deemed to have automatically been
extended until Commercial Close and all bid responses must remain
valid and binding for such period
.”
[8]
[43]
In my view the correct approach when interpreting Clause 30 is that
it must be read together
with the definitions of the relevant terms
referred to in the RFP. The Department's interpretation that
Commercial Close is achieved
when the suspensive conditions are
fulfilled is contrary to understanding the RFP in context.
[44]
The term “commercial clause” clearly makes reference to a
cut off date:
44.1
Clause 30.3 states that “the Bid Validity Period will be deemed
to have automatically been extended
until
Commercial Close
”;
44.2
the term “
Commercial Close
” is defined as “
the
Effective Date as defined in the Implementation Agreement”
;
44.3
the term “
Commercial Close
” as defined in the
Signed Implementation Agreement refers to a specific date. It
reads:
“
Means
the date on which the last of the suspensive conditions referred to
in clause 3.1 (suspensive conditions, adjustment or energy
rates on
or before the expiry of the
Commercial
Close Period
(reference is again
made to a stipulated time period in which the suspensive obligation
had to be made)”;
44.4
if one then notes the definition of “Commercial Close Period”,
it reads “
a period of one hundred and twenty days (120 days)
from signature date, as may be amended in accordance with the
Implementation Agreement
.”
;
44.5
it is not in dispute that the extended date was 30 November 2023 in
terms of the Signed Implementation
Agreement and has the cut off
date;
44.6
furthermore as per the Signed implementation Agreement the term
“Effective Date” makes
reference to Clause 3.3.3 which is
the time bound. Clause 3.1 also refers to a cut off period that is
“on or before the expiry
of the commercial close period”;
44.7
at all relevant times and on the respondents’ version, the
Signed Implementation Agreement was
the effective agreement between
the parties;
[45]
In light of the aforesaid analysis I find that the Signed
Implementation Agreement lapsed when
the “Bid Validity Period”
expired. Furthermore, the lapsing of the Signed Implementation
Agreement entails the lapsing
of the Preferred Bidder Guarantee.
[46]
It would clearly be contrary to the customary understanding of the
performance guarantee if the
Department is able to call on the
Preferred Bidder Guarantee when the agreement lapsed. The very
logic of performance guarantees
would be defeated if the Department
can call up the guarantee when there are no performance obligations
on the part of the applicant.
There is no risk left to be
secured if the underlying project obligations have lapsed entirely.
It could therefore never
have been intended between the parties that
Preferred Bidder Guarantee was not time bound.
[47]
Furthermore, the Department’s argument that the briefing notes
amended the definition of
“Commercial Close” in the RFP,
unassailable. The Department submitted that an amendment was
effected to change
the determination of the Bid Validity Period to
the date on which the suspensive conditions become fulfilled as per
the Signed
Implementation Agreement.
[48]
The Consortium correctly illustrated that this argument is
unmeritorious in that:
48.1
the Department could not amend the RFP in the manner they alleged;
48.2
the Briefing Notes issued by the Department did not amend the RFP in
the way the Department contended;
48.3
the term “Bid Validity Period”, as
mirrored in the Preferred Guarantee envisaged a cut off period.
[49]
The Consortium identified the relevant provisions in the RFP, which
prohibited the Department
from amending same namely:
49.1
Clause 4.6 does not make provision for the RFP to be amended and
reads:
“
Volume
2 (Legal Requirements) contains copies of the
legal
agreements
that will (
subject
to any subsequent amendments issued by the Department
)
be required to be entered not by the Project Company of a Preferred
Bidder and the counter-parties, if applicable, namely, an
Implementation Agreement, a PPA, a Direct Agreement, a Transmission
Agreement or a Distribution Agreement, an Independent Engineer
Agreement and a Connection Direct Agreement.”
;
49.2
Clause 36.1.18 further prohibits the Department from amending the RFP
once the Consortium was appointed
as a Preferred Bidder and reads:
“
36.1.18
The Department deserves the right to amend the RFP, the
Implementation
Agreement, the PPA, the Direct Agreement, the
Independent Engineer Agreement and Connection Agreements
at
any time prior to the execution of those agreements
,
and the Department shall not be liable to any Bidder or Preferred
Bidder for any consequences, claims or costs arising from any
of
these actions.”
;
49.3
Clause 25.6 of the Signed Implementation Agreement provided that the
Agreement contains a whole agreement
between the parties and
supercedes any prior written or oral agreement between them. Clause
25.6 stipulated:
“
25.6.1
This agreement contains the whole agreement between
the parties in
respect of the subject matter hereof and supersedes any prior written
or oral agreement between them;
25.6.2
Each party acknowledges and agrees that it is
not entering into this
agreement in reliance on and shall have no rights of action against
the other party in respect of any assurance,
promise, undertaking,
representation or warranty made by the other party at any time prior
to the “Signature Date”
unless it is expressly set out in
this agreement.”
;
49.4
In addition, Clause 25.2 allows for amendments or variation provided
same are in writing and agreed
to by both parties. It reads:
“
This
agreement may not be released, discharged, supplemented, interpreted,
amended, varied or modified in any manner except by an
instrument in
writing signed by a duly authorized officer or representative of each
of the parties of this agreement.”
[50]
On my interpretation, particularly having regard to the language,
context and purpose together
with the intention of the parties, the
only plausible conclusion I arrive at is that the guarantee lapsed
when the agreement lapsed.
In particular:
50.1
The objective of a Performance Guarantee, was for ABSA to provide the
beneficiary, the Department,
with protection against counter party
risk, that is the risk of performance failure by the applicants of
obligations they were
required to fulfil.
50.2
The Signed Implementation Agreement as the effective agreement
between the parties stipulated that
if the suspensive conditions were
not fulfilled on or before the expiry date of the Commercial Close
Period of 30 November 2023,
the said agreement would no longer have
any force and effect. Consequently, the Department would have no
claim against the Consortium
arising from the non-fulfilment of the
suspensive conditions. Accordingly, ABSA’s guarantee can also
not be called up.
50.3
The wording in the Preferred Bidder Guarantee in fact made provisions
for bidders to comply within
a time period hence the reference to the
word “timeously”.
[51]
When interpreting the bid documents a unitary exercise is necessary
where the court must consider
the language used and ascertain what a
reasonable person would have understood therefrom. The Supreme Court
of Appeal in
ABSA
Bank Matter
[9]
acknowledged in the reasoning set out by the English courts
in
Society of Lloyds v Robinson
[10]
where it expressed:
“
Loyalty
to the text of a commercial contract instrument, or document read in
its contextual setting is the paramount principle of
interpretation.
But in the process of interpreting the meaning of the language of a
commercial document the court ought to generally
favor a commercially
reasonable construction. The reason for this approach is that a
commercial construction is likely to give
effect to the intention of
the parties. Words ought therefore to be interpreted in the way
in which a reasonable commercial
person would construe them. And the
reasonable commercial person can safely be assumed to be unimpressed
with technical interpretations
and untrue emphasis on niceties of
language”.
[52]
The applicant sensibly pointed out that banks will not issue
open-ended on-demand guarantees
without timelines. They would never
have consented to issue a guarantee where the expiry date is
indefinite.
DECLARATORY
RELIEF
[53]
The Consortium sought declaratory relief to the effect that the
Preferred Bidder Guarantee lapsed
either on 8 December 2022
alternatively on 13 November 2023.
[54]
It is settled law that for a party to succeed in obtaining
declaratory relief certain requirements
have to be met. The two-stage
process outlined by the Supreme Court of appeal in
Cordiant
[11]
finds
application. I have to be satisfied, firstly that the Consortium has
an interest in the existing or continued right or obligation
and
secondly, I am required to exercise my judicial discretion.
[55]
I am satisfied that the Consortium has an interest in the matter. In
the event ABSA is called
upon to make payment in terms of their
Preferred Bidder Guarantee, the Consortium would be financially
affected in terms of its
obligations in terms of the counter
guarantee concluded. The Consortium would be responsible to settle
the guarantee if ABSA is
compelled to pay it over to the Department.
[56]
The Consortium motivated its reputation would also be compromised. An
adverse finding will affect
its future participation in procurement
programmes with government.
FINAL
INTERDICTORY RELIEF
[57]
The Consortium has met the requirements for final interdictory relief
namely:
57.1
it has a clear right;
57.2
harm or injury is reasonably apprehended;
57.3
there is no alternative recourse for the Consortium.
[58]
The Consortium submitted that it has a public law and a contractual
rights in terms of 26.3 of
the RFP for the release and return by the
Department of the Preferred Bidder Guarantee. The issuing of
the RFP by the Department
constitutes a public decision,
alternatively an administrative decision.
Clause
26.3 of the RFP provides:
“
Unless
the Department has notified the Bidder or Preferred Bidder in terms
of Clause 26.4 that it intends calling on the Bid Guarantee
or the
Preferred Bidder Guarantee, the Department will return the Bid
Guarantee or Preferred Bidder Guarantee as applicable within
15
business days of its expiry.”
[59]
Hence if the relief sought is not granted, the Department can call on
the ABSA guarantee.
The Department contended that the dispute
could have been ventilated in the review application, hence there is
an alternative remedy.
In response, the Consortium demonstrated that
argument that an order of this court was necessary, without such
order the Department
could call up the guarantee. In addition, the
Department refused to give an undertaking to wait for the final
adjudication of the
review application before calling on the
Preferred Bidder Guarantee. As a result, the Consortium was
left with no option.
[60]
In the premises, the Consortium is successful in this application.
COSTS
[61]
In exercising my discretion, I apply the general rule that costs
should follow the result.
The applicant as the successful
party, is entitled to its costs. The first, third, seventh and
eighth respondents are ordered
to pay the costs consequent upon the
appointment of two counsel jointly and severally on Scale C.
H.
KOOVERJIE
JUDGE
OF THE HIGH COURT
GAUTENG DIVISION,
PRETORIA
Appearances
:
Counsel
for the applicant:
Adv.
P Rood SC
Adv.
D Sive
Instructed
by:
Fasken
(Bell Dewar Incorporated)
Counsel
for the 1
st
, 3
rd
, 4
th
,7
th
and 8
th
respondent:
Adv.
N Maenetje SC
P
Sokhela
Instructed
by:
Ledwaba
Mazwai Attorneys
Date
heard:
04
September 2025
Date
of Judgment:
21
November
2025
[1]
The
Request for Qualification and Proposal for new generation capacity
under the REIPP procurement programme was issued for the
fifth Bid
Submission stage.
[2]
Minister
of Police v Fidelity Security and Others 2023 (3) SA BCLR (CC)
[3]
Natal
Joint Municipal Pension Fund v Endumeni Municipality
2012 (4) SA 593
(SCA) at paragraph 18
In
the matter of
Endumeni
,
at paragraph [18], the court stated:
“
[18]
The present state of the law can be expressed as follows.
Interpretation is the process of
attributing meaning to the words
used in a document, be it legislation, some other statutory
instrument, or contract, having
regard to the context provided by
reading the particular provision or provisions in the light of the
document as a whole and
the circumstances attendant upon its coming
into existence. Whatever the nature of the document,
consideration must be
given to the
language
used in the light of the ordinary rules of grammar and syntax; the
context in which the provision appears
;
the apparent purpose to which it is directed and the material known
to those responsible for its production. Where more
than one
meaning is possible each possibility must be weighed in the light of
all these factors.
The
process is objective not subjective. A sensible meaning
is to be preferred to one that leads to insensible or unbusinesslike
results or undermines the apparent purpose of the document.
Judges must be alert to,
and
guard against, the temptation to substitute what they regard as
reasonable, sensible or businesslike for the words actually
used
.
To do so in regard to a statute or statutory instrument is to cross
the divide between interpretation and legislation...”
[4]
Novartis
SA Ltd v Maphili Trading (Pty) Ltd
2016 (1) SA 518
(SCA) at para 27
to 28
[5]
Clause
3 of the RFP
[6]
University of Johannesburg v Auckland Park Theological Seminary
2021
(6) SA 1
(CC) at paragraph 66.
The
principle enunciated in the
University
of Johannesburg
matter has relevance:
“
A
court interpreting a contract has to, from the onset, consider the
contract’s factual matrix, its purpose, the circumstances
leading up to its conclusion, and the knowledge at the time of those
who negotiated and produced the contract.”
[7]
Clause
2.1.83 of the RFP
[8]
My
underlining
[9]
ABSA
Bank Limited v Rosenburg and Another
[2024] ZASCA 58
(24 April 2024)
[10]
Society
of Llyod’s v Robinson [1999] AER (comm) 545
[11]
Cordiant
Trading CC v Daimler Chysler Financial Services
2005 (5) SA 205
SCA
sino noindex
make_database footer start
Similar Cases
Sibeko v S and Another (Appeal) (A839/2016) [2025] ZAGPPHC 407 (23 April 2025)
[2025] ZAGPPHC 407High Court of South Africa (Gauteng Division, Pretoria)98% similar
Engel N.O. and Others v Tax Faculty NPC and Others (037648/23) [2024] ZAGPPHC 940 (20 September 2024)
[2024] ZAGPPHC 940High Court of South Africa (Gauteng Division, Pretoria)98% similar
Manyeleti Consulting SA (Pty) Ltd v Fikeni NO and Others (Appeal) (A374/2023) [2025] ZAGPPHC 1287 (27 November 2025)
[2025] ZAGPPHC 1287High Court of South Africa (Gauteng Division, Pretoria)98% similar
Sibeko v S and Another (A839/2016) [2025] ZAGPPHC 811 (29 July 2025)
[2025] ZAGPPHC 811High Court of South Africa (Gauteng Division, Pretoria)98% similar
S.S.N. obo N.M. and Another v Road Accident Fund (34316/2020) [2025] ZAGPPHC 615 (17 June 2025)
[2025] ZAGPPHC 615High Court of South Africa (Gauteng Division, Pretoria)98% similar