Case Law[2024] ZAGPPHC 303South Africa
Mmamoleboge Investments CC and Other v Crimson Properties 351 (Pty) Ltd and Others (23731/2018) [2024] ZAGPPHC 303 (4 April 2024)
High Court of South Africa (Gauteng Division, Pretoria)
4 April 2024
Headnotes
"in resolving factual disputes in a civil case, particularly when it comes to an evaluation of the witnesses for the party who bears the onus. The proper approach in resolving factual disputes where there are two irreconcilable versions is that the court should also have regard to the probabilities inherent in the respective conflicting versions".
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 303
|
Noteup
|
LawCite
sino index
## Mmamoleboge Investments CC and Other v Crimson Properties 351 (Pty) Ltd and Others (23731/2018) [2024] ZAGPPHC 303 (4 April 2024)
Mmamoleboge Investments CC and Other v Crimson Properties 351 (Pty) Ltd and Others (23731/2018) [2024] ZAGPPHC 303 (4 April 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_303.html
sino date 4 April 2024
REPUBLIC
OF SOUTH
AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION,
PRETORIA)
Case no: 23731/2018
REPORTABLE
OF INTEREST TO OTHER
JUDGES
REVISED
DATE: 04/04/2024
In the matter between:
MMAMOLEBOGE
INVESTMENTS
CC First
Plaintiff
KOPANO
CREATIVE
CONCEPTS
CC Second
Plaintiff
KGONI TRADING CC t/a
KGONI CIVILS & ENGINEERING Third
Plaintiff
and
CRIMSON PROPERTIES 351
(PTV) LTD
t/a
CRIMSON KING DEVELOPMENTS
First Defendant
APIL & ASSOCIATES
ARCHITECTS
&
PROJECT MANAGERS
Second
Defendant
INSIKA
QUANTITY SURVEYORS (PTY) LTD
Third Defendant
ONE
G
SERVICES
(PTY)
LTD
Fourth
Defendant
MEMBER
OF THE EXECUTIVE COUNCIL,
DEPARTMENT
OF
HUMAN SETTLEMENTS, GAUTENG
Fifth
Defendant
HEAD
OF DEPARTMENT,
DEPARTMENT
OF HUMAN
SETTLEMENTS,
GAUTENG Sixth
Defendant
JUDGMENT
(The matter was heard
on open court but judgment is delivered by uploading the judgment
onto the electronic file of the matter on
Caselines and the date of
the judgment is deemed to be the date of uploading it onto Caselines)
Before:
HOLLAND-MUTER
J:
[1] The
Plaintiffs claim payment from the First Defendant, the amounts
alleged by the Plaintiffs to be outstanding
under the construction
contract entered onto between the Plaintiffs and the First Defendant.
The outstanding amounts claimed are
R 2 677 868-20
(First
Plaintiff);
R 21.27 868-20
(Second Plaintiff) and
R
2 092 868-20
(Third Defendant). These amounts are claimed as
standing time fees and contract adjustment fees as prepared and
presented to the
Department (Fifth and Sixth Defendants).
(Par
25 of the Declaration,which is different from par 26; the Court
awarding theformer-see Vat Issue).
[2] The
First Defendant was appointed by the Fifth Defendant (referred to as
the 'Department'') to construct
subsidized houses in Westonaria,
Westonaria situated in the West Rand District in Gauteng.
[3] The
First Defendant appointed the First Plaintiff on 12 September 2012;
the Second Plaintiff on 27 September
2012 and the Third Plaintiff
also on 12 September 2012 to undertake the construction of the
subsidized houses.
[4] The
Plaintiffs were appointed in terms of a standard contract of the
Joint Building Contracts Committee
(JBCC, also known the Principal
Building Agreement Standard JBCC 2000 Series Edition 5.0), with the
Department as Employer and
the First Defendant as the Contractor.
[5] The
First Defendant does not deny (i) being appointed by the Department;
(ii) that it appointed
the Plaintiffs as subcontractors and (iii) that the Plaintiffs were
appointed in terms of the JBCC Agreement
and that the Plaintiffs
received their respective appointment letters.
[6] It
is also common cause that the Department issued an oral instruction
during 2013 (whilst the construction
was still underway and not
completed), to suspend all construction activities for reasons not
related to the construction work
done by the Plaintiffs. The
Department specifically requested that the contractors remain on site
during the cessation of construction
to prevent any damage be caused
by disgruntled members of the local community and for the Contractors
to protect material on site.
[7] Mr
Manala on behalf of the Plaintiffs made the court aware that the
matter was initially issued the application
in the motion court
before it was referred to oral evidence and trial and that the costs
thereof was reserved for the trial court
to adjudicate. I could not
find any reference to any such application on the electronic file of
the matter on Caselines but for
two court orders where the First
Defendant argued an exception against the Declaration filed on behalf
of the Plaintiffs substantiated
by two court orders. The fact that
the Plaintiffs issued a Declaration later indicates that the original
application was referred
for oral evidence. The Plaintiffs (i) were
visited with a cost order for the wasted costs occasioned by a
postponement and (ii)
that the First Defendant's exception was
dismissed with costs. I have no other indication on reserved costs to
address in this
hearing. I see no need to address any other
outstanding cost issues in this matter.
EVIDENCE:
[8] The
court finds it not necessary to repeat the evidence in detail but
rather to concentrate on important
aspects favouring the case of each
party. The court is well aware of the approach to evidence where it
is faced with contradicting
versions. the test is well founded in
Stellenbosch Farmers' Winery Group Ltd and Another v Martell Et
Cle and Others
2003 (1) SA 11
SCA at par (5-7)
as reiterated in
Dreyer v AXZS Industries
2006 (5) SA 548
SCA at 558 C-G
where
it was held that
"in resolving factual disputes in a civil
case, particularly when it comes
to
an evaluation of the
witnesses for the party who bears the onus. The proper approach in
resolving factual disputes where there are
two irreconcilable
versions is that the court should also have regard
to
the
probabilities inherent in the respective conflicting versions".
[9] The
court will also make a finding on credibility of the witnesses, any
contradictions in the respective
versions, external contradictions
pleaded and the probabilities or improbabilities of a version. The
court will search for reliabilities
in the factors mentioned, the
demeanour of the witnesses and other relevant aspects to safeguard
when accepting or rejecting a
version. The facts before the court
need be examined and after weighing all aspects, find on a version.
[10] The
uncontested issues before the court are the following:
•
The
Department issued a cessation order, the cessation remained in place
for about 9 months;
* The
Plaintiffs were requested by the Department to remain on site for
various reasons;
* The
cessation was for reasons beyond the control of the Plaintiffs. The
First Defendant made some noise
about sub-par construction by the
Plaintiffs but no evidence was tendered to substantiate this
allegation. This allegation is unfounded
and rejected.
* The
cessation was ended some nine months after implemented, and according
to the Plaintiffs, the parties
at a meeting a week after the
cessation
was ended, where the
issue of standing time and price adjustment was discussed. The First
Defendant elected not to present any evidence
denying this aspect.
[11] The
Plaintiffs called two witnesses and the First Defendant only one
witness. The other Defendants did
not participate in the proceedings
but Plaintiffs do not seek any relief against them. They were cited
to prevent any unnecessary
delays and the attendance of the
Department's representatives were secured to possibly testify should
the need arise. The Plaintiffs
called Samuel Themba and Melitha
Molebane Modibe while the First Defendant called only Anet Nagel to
testify. Modibe is employed
by the Fifth Defendant.
[12] The
court finds it very strange that the First Defendant elected and/or
failed to call any direct witnesses
as to the negotiations between
the parties leading to the conclusion of the original agreement. More
important, no evidence was
tendered by the First Defendant to
contradict the now uncontested evidence by Themba about the two
meetings after the cessation
of construction by the Department and
the later continuing by the Plaintiffs to complete the construction.
[13] The
uncontested evidence of Themba is that the Department requested the
cessation of the construction
and that the contractors remain on site
to protect the already constructed houses and the guard against any
damage to be caused
by members of the community and to safeguard
building material already on site was confirmed by Modibe. The First
Defendant did
not call on any of its people to contradict this
version. This evidence by Themba is uncontested.
[14] Me
Modibe, the representative of the Department, testified that the
Department indeed ordered the cessation
of the construction for
reason beyond the doing of the Plaintiffs. The request to cease with
construction was because of beneficiary
related issues with the
community experienced by the Department. This request was forwarded
to the First Defendant who conveyed
it to the Plaintiffs. She also
made no mention that the cessation was also necessary because of poor
workmanlike performance by
the Plaintiffs. The First Defendant
pleaded such reason but tendered no evidence to support the
allegation.
[15] Themba
testified that at the first meeting was held at the head office of
the First Defendant a week
after the cessation was uplifted, and it
was accepted that the Plaintiffs were entitled to claim standing time
and adjustment of
prices of the original contract. The reason that
because of the long cessation, prices increased and expenses were
incurred to
inter alia safeguard the site during the cessation. This
evidence is uncontested by the First Defendant. Themba's version that
the Plaintiffs submitted their claim, together with supporting
documents, to the Principle Agent as they were obliged to do in terms
of the JBCC Agreement, was never contradicted by evidence.
[16]
Modibe
confirmed during her evidence that the Department received such claim
on behalf of the Plaintiffs from the principle agent
of the First
Defendant (the Fourth Defendant) and that the Department received,
considered, approved and ultimately paid the claims
of the
constructors. She was adamant that although payment was made to the
First Defendant, the Plaintiffs were entitled to payment.
Her
evidence is undisputed and accepted. The Fourth Defendant was
appointed as the First Defendant's Principle Agent on the project.
[17] Nagel
was the quantity surveyor appointed by the First Defendant but she
was not present at any of the
two meetings after construction
resumed. Her evidence with respect is riddled with improbabilities.
She inter alia denied that
the calculation that she prepared was for
the Plaintiffs but insisted it was only a generalized calculation to
determine a daily
average of costs upon being asked to do so by the
Project Manager. She averred it was prepared for the First Defendant.
This makes
no sense as the Plaintiffs were the contractors and
not the First Defendant.
[18] Her
explanation as to why the names of the three Plaintiffs appeared on
her calculation but that it
was to the benefit of the First Defendant
is without any substance. The inherent improbability is that why
would the First Defendant
benefit from the cessation called upon the
Plaintiffs.
[19] She
could not deny the version of the First Plaintiff that it was the
main point of discussion on the
two meetings after construction
resumed that the Plaintiffs would be able to claim standing time and
adjustment of prices as provided
for in clauses 29.2.3 and 32.5 &
32.5.1 of the JBCC Agreement providing for payment of compensation to
a contractor for delay
not occasioned by a contractor's conduct.
[20] She
further testified that her report was on all accounts intended for
use as supporting a claim for
adjustment of contract price and
standing time
but
this was only in relation to the developer
and not the contractors. Her assumption makes no sense and is
rejected.
[21] She
testified that she made the calculations merely conducting a
generalized calculation at the request
of the Project Manager for an
"unspecified purpose". This is also farfetched and cannot
stand the test for reliability.
She tried to further down side her
calculation averring that she only prepared the first and the last
pages thereof and that Dougall
Wesley.
[22] This
does not make any sense at all. when perusing the
Quantity
Surveyors report supporting the Standing Time Claim
(annexure
A)
as on Caselines 04-58, it is clear that she was the author and
that she addressed it for the attention of Dougal Wesley
(representing
the Fourth Defendant). The court would have expected
Wesley to testify if this was true. As is, she is the author thereof.
[23] The
calculation is clearly for the time related preliminary and general
(P&G) cost as per contractor,
as calculated by her. See p 58
Caselines 04-61. The reasonable inference from this document is that
the calculation was done with
regard to the three contractors (the
Plaintiffs} and not in the interest of the First Defendant.
[24] A
further mysterious improbability in her evidence was that her
calculations were solely based on the
contract figures of the
Plaintiffs but insisted that it was done to claim compensation for
the Developer and not the Plaintiffs.
Even worst for her is that she
accepted the tables relating to professional and ancillary fees due
to the professional team.for
contract price adjustment and standing
time, expenses and loss. I fail to understand her reasoning that it
could be for the benefit
of the developer (First Defendant) when the
expenses and loss were for the account of the contractors
(Plaintiffs).This assumption
of her is stillborn.
[25] Even
if Nagel was of the view that the claims were not premised on any
calculation of input from the
Plaintiffs, she calculated at a market
related rate and if that was her view, she did not need any
information from the Plaintiffs
although she accepted the standing
time delay of 270 days (nine months) as claimed by the Plaintiffs.
[26] I
fail to understand how it can be argued that Nagel was an honest and
credible witness. When comparing
her version with that of Themba,
there is but only one choice to accept the version of Themba to be
true and to reject her version.
[27] The
court is satisfied that the Plaintiffs succeeded in proving that the
First Defendant is indebted
towards them. In par 29 below mention is
made to payments made by the First Defendant towards the Second and
Third Plaintiffs in
the amounts of R 550 002-27 and R 585 000-00
respectively. This result in that the First Defendant is still
indebted towards the
Plaintiffs in the amounts of R 2 667 868-20
(First Plaintiff); R 2 117 865-93 (Second Plaintiff) and R 2 092
868-20 (Third Plaintiff).
These payments were not made as part of the
amount(s) due in terms of the final certificates with regard to the
initial agreement.
If it was, the First Defendant ought to have
pleaded it and tendered the necessary evidence to satisfy the burden
of he who alleges
payment needs to prove. This did not happen.
PRESCRIPTION:
[28] The
calculation is dated 14 August 2014, and the initial application was
issued during December 2016,
well within two years from the claims
for standing time arising. A copy of the original urgent application
was handed up as exhibit
"C" during the trial and is
sufficient proof that the claims were instituted within time to erupt
prescription. The First
Defendant did not lead any evidence to
bolster this defence. The defence of prescription cannot fly.
VAT
CLAIM:
[29] The
Plaintiffs abandoned any claim for VAT during the trial proceedings
and the court need not attend
thereto further.
CLAIM
FOR
INTEREST:
[30] The
Plaintiffs claim interest at the prescribed rate ("a
tempore
morae'J
In terms of section 31.10 of the JBCC agreement, the
Defendant ought to make payment of amounts due within 31 calendar
days. The
First Defendant received payment for the claimed standing
time from the Department on 19 September 2016. Payment was therefor
due
on 22 October 2016.
[31] The
First Defendant made interim payments towards the Second and Third
Plaintiffs in the amounts of
R 550 002-27 and R 585 000-00
respectively before 22 October 2016. No payment was made towards the
First Plaintiff in this regard.
FULL
AND
FINAL
SITTLEMENT:
[32] The
First Defendant pleaded that it final payment certificates
in full
and final settlement of all claims under the PBA in October 2014
were
accepted by the Plaintiffs and thereby compromised their claims under
the PBA. It was put to Themba that by accepting the final
certificates in October 2014, any reliance on the alleged claims for
standing time and cost adjustments were compromised by the
acceptance
of the certificates by the Plaintiffs. Themba denied this.
[33] The
First Defendant initially pleaded in tis par 13.2 of the Plea that
the
Plaintiffs never attended the stages of practical works
completion, and no certificates to that effect were ever issued to
the plaintiffs.
This is clearly in contradiction with the
argument that final certificates were issued and a compromise
reached.
[34] A
further contradiction between the plea and the written arguments is
that the First Defendant pleaded
in par 13.2.3 of the plea that
the
certificates of final completion and final accounts were solely
issued
to
the plaintiffs in order
to
terminate the
plaintiffs' involvement in the project and
to
finalize the
parties' contractual relationship and all claims between the
parties".
This was not substantiated by any evidence during
the trial.
[35] The
final certificates were issued after the work was finalised and has
no relation to the additional
claim for standing time as set out in
the claim therefore
and
approved by the
Department. Modise's evidence is clear that the cessation was not
because of any conduct by the Plaintiffs and they
should be rewarded
therefore. This is a mere last futile grasp by the First Defendant to
escape liability. This defence is rejected.
[36] The
Department only made payment in the amount of R 10 566 036-43 towards
the First Defendant on 19
September 2016. The certificates of final
completion were issued during October 2014 long before any claim for
standing time was
considered or approved and paid by the Department.
COSTS:
[37] The
purpose of an award of costs to a successful litigant is to indemnify
the party for the expenses
which he to which he was put through
having been compelled to initiate action or defend action.
Herbstein
& Van Winsen, The Civil Practice of the Supreme Court of South
Africa 4
th
ed p 701.
[38] The
award of costs is within the discretion of the court.
Herbstein &
Van Winsen supra p 703.
In exercising its discretion, the court
will as a general rule award costs to the successful party. Success
is determined by looking
at the substance of the judgment. A court
may also in exceptional cases, depart form the normal rule and award
costs against a
successful party. This is seldom done and will entail
special circumstances to prevail. I am of the view that there is no
need
to depart from the general rule to award costs to the successful
party.
Herbstein & Van Winsen supra p 704.
[39] The
court will further consider the scale on which the awarded costs is
taxed or agreed. The normal
scale is a party-and-party-scale. This
will be awarded if no special circumstances exist to depart therefrom
and to award costs
on a punitive scale such as on
attorney-and-client-scale. This may be when for instance the court
wants to voice its disapproval
with the conduct of a party or its
representative against whom the cost order is granted. I am of the
view no grounds exist to
award costs on a punitive scale.
[40] Having
considered the case as a whole, I am of the view that costs on a
party-and-party-scale is the
appropriate scale. After considering all
aspects of the matter (inclusive of the pleadings, the evidence and
documents on Caselines,
the Plaintiffs' claims are awarded with costs
on a party-and-party scale.
ORDER:
The First Defendant Is
ordered to pay the following:
1. Pay
the First Plaintiff the amount of R 2 677 868-20.
2. Pay
the Second Plaintiff the amount of R 2 127 868-20.
3. Pay
the Third Plaintiff the amount of R 2 092 868-20.
4. The
First
Defendant
is
to
pay
Interest
on
the
said
amounts
in
1,
2
&
3
a
tempore morae
as
from 22 October 2016 until date of last payment.
5.
The First Defendant is to pay the costs of the Plaintiffs on a
party-and-party scale.
6. No
order is made with regard to the Second to Sixth Defendants
HOLLAND-MUTER
J
JUDGE
OF THE PRETORIA
HIGH COURT
MATTER HEARD ON 20 &
21 NOVEMBER 2023
Written Heads of
Arguments filed:
Obo Plaintiffs: 24
November 2023
Obo
First
Defendant:
1
December
2023
Obo Plaintiffs: 5
December 2023
Judgment uploaded onto
Caselines: 4 April 2024
TO: NKONDO
ATTORNEYS OBO THE PLAINTIFFS
law@nkondoattorneys.co.za
ADVM MANALA
VENTER
&
VON
ABO
INC
080
FIRST
DEFENDANT
info@tintingers.co.za
ADV
CA
BOONZAAIER
NO
APPEARANCES OBO SECOND
TO
SIXTH DEFENDANTS
(Uploaded onto Caselines)
sino noindex
make_database footer start
Similar Cases
Mamokebe Investments (Pty) Ltd v Minister of Mineral and Energy and Others (2025/036849) [2025] ZAGPPHC 414 (22 April 2025)
[2025] ZAGPPHC 414High Court of South Africa (Gauteng Division, Pretoria)99% similar
Kgaphola Investment Holdings (Pty) Ltd v Great North Transport Limited (38767/2007) [2024] ZAGPPHC 937 (6 September 2024)
[2024] ZAGPPHC 937High Court of South Africa (Gauteng Division, Pretoria)99% similar
Madi Investments (Pty) Ltd v African Tanacity (Pty) Ltd and Another (2023/071165) [2024] ZAGPPHC 382 (19 April 2024)
[2024] ZAGPPHC 382High Court of South Africa (Gauteng Division, Pretoria)99% similar
Thusanyo Investments (Pty) Ltd v Maduo Supply & Projects CC (39913/20) [2022] ZAGPPHC 95 (24 February 2022)
[2022] ZAGPPHC 95High Court of South Africa (Gauteng Division, Pretoria)98% similar
Zimele Investment Enterprise Company (Pty) Ltd v South African National Roads Agency Ltd and Others (36023/2021 and 36024/2021) [2022] ZAGPPHC 541 (20 July 2022)
[2022] ZAGPPHC 541High Court of South Africa (Gauteng Division, Pretoria)98% similar