Case Law[2024] ZAGPPHC 531South Africa
Bosch Munitech (Pty) Ltd v Govan Mbeki Municipality (33425/16) [2024] ZAGPPHC 531 (6 June 2024)
Headnotes
that: “The accounting officer or accounting authority must ensure that the documentation and general conditions of contract are in accordance
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 531
|
Noteup
|
LawCite
sino index
## Bosch Munitech (Pty) Ltd v Govan Mbeki Municipality (33425/16) [2024] ZAGPPHC 531 (6 June 2024)
Bosch Munitech (Pty) Ltd v Govan Mbeki Municipality (33425/16) [2024] ZAGPPHC 531 (6 June 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_531.html
sino date 6 June 2024
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
1. REPORTABLE: NO
2. OF INTEREST TO OTHER
JUDGES: NO
3. REVISED
6 June 2024
CASE NO: 33425/16
In
the matter between:
BOSCH
MUNITECH (PTY) LTD
Plaintiff
And
GOVAN
MBEKI MUNICIPALITY
Defendant
This judgment is issued
by the Judge whose name is reflected herein and is submitted
electronically to the parties/their legal representatives
by email.
The judgment is further uploaded to the electronic file of this
matter on CaseLines by the Judge or her Secretary. The
date of this
judgment is deemed to be 06 June 2024.
JUDGMENT
COLLIS
J
INTRODUCTION
1]
In the present action the plaintiff claims
payment
in the amount of R 16 969 144-69 together with interest.
[1]
The plaintiff alleges that on 1 October 2013, it accepted an offer
from the defendant to conclude a contract to execute civil
engineering works for the refurbishment of the eMbalenhle Water
Works.
[2]
This was done pursuant to a competitive bidding process.
2]
The Plaintiff initially instituted an application in this Court under
case number 88360/2014 on 11 December 2014,
[3]
seeking the very same relief it now seeks in this action. That
application was finalised and the judgment of the Court is set out
in
Bosch Munitech (Pty) Ltd v Govan Mbeki Municipality.
[4]
3] In order to succeed
with its present claim, the plaintiff bears the
onus
of proof
on a balance of probabilities.
4]
The defendant denies that it concluded a valid and lawful contract
with the plaintiff.
[5]
It asserts that any agreement concluded with the plaintiff is
indisputably and clearly inconsistent with section 217 of the
Constitution
and the statutory prescripts that give effect
thereto.
[6]
5]
The defendant is a municipality and an organ of state in the local
sphere of government.
[7]
The defendant attacks the validity and legality of the procurement
contract concluded between it and the plaintiff.
6] The defendant has in
addition to its plea, mounted a counterclaim. It is the plaintiff’s
contention that the defendant
has unreasonably delayed its
counterclaim and that any contract concluded with it must be declared
invalid. The defendant in turn
requests this Court to determine a
just and equitable relief as per section 172(1)(b) of the
Constitution.
7]
In response to the counterclaim of the defendant, the plaintiff
raised a special plea of prescription.
[8]
The defendant asserts that the special plea is without merit. Section
172(1)(b) of the Constitution affords the court wide powers
to grant
any just and equitable order, and as such the provisions of the
Prescription Act
[9]
cannot restrict the constitutional powers granted to courts per
section 172(1)(b).
8] The defendant resists
the claim on the basis that the plaintiff was aware of the illegality
or should reasonably have known.
For this reason, the defendant
contends that the evidence objectively confirms that the plaintiff
was not an unsuspecting party
that unwittingly entered into an
unlawful contract with the municipality.
9] It is common cause
that the plaintiff never provided any service. The plaintiff’s
claim is for expenses relating to site
establishment and standing
time, not construction. It is further not in dispute that the
defendant received no definite or tangible
benefit or advantage.
LOCAL GOVERNMENT
STATUTORY PROCUREMENT FRAMEWORK
10]
In order to determine the dispute between the parties, it will be
apposite to have regard to the statutory regulatory framework
applicable to contracts concluded at local government level. The
Constitution recognises the right of municipalities to “govern”,
of its own initiative the local government affairs of its community,
subject to national and provincial legislation, as provided
for in
the Constitution.
[10]
11]
One of the constitutional objects of local government is the
provision of services to communities in a sustainable manner.
[11]
The Constitution instructs municipalities to structure and manage
their administration to prioritise the basic needs of the community
and to promote the social and economic development of the
community.
[12]
12] The mismanagement of
municipal funds impacts a municipalities’ ability to provide
services in a sustainable manner. The
irresponsible, inefficient, or
negligent use of funds undermines the prospect of the defendant
achieving its constitutional objectives.
Government procurement has
huge economic and political significance. The importance of
government procurement is illustrated by
the fact that it is afforded
constitutional status.
(a)
Constitutional Status of Government
Procurement
13] Section 217 of the
Constitution places an obligation on the defendant when contracting
for goods and services to do so following
a system that is fair,
transparent, competitive and cost-effective.
14] Section 217 is not
the only provision of the Constitution that impacts government
procurement. By way of example, section 33
provides for the right to
‘just administrative action’ and sections 215, 216, 218
and 219 require National Treasury
to introduce uniform norms and
standards to ensure transparency and expenditure control measures.
(b)
Statutory Regulation of Municipal
Procurement
15] The legislature has
adopted various statutory instruments to give effect to the
constitutional status of government procurement.
At local government
level, the most important are:
15.1
Municipal Systems Act 32 of 2000 (the
“Systems Act”);
15.2
Municipal Finance Management Act 56 of 2003
(the “MMFA”);
15.3
Municipal Supply Chain Management Regulations
(“the SCM
Regulations”)
[13]
;
15.3
Preferential Procurement Policy Framework
Act 5 of 2000
(the
“PPPFA”) and the Preferential Procurement Regulations,
2011 (“the PPR”).
[14]
15.4
The Municipalities Supply Chain Management
Policy (“the SCM
Policy”).
(c)The
Defendant’s SCM Policy
16]
Section 111 of the MFMA places an obligation on every Municipality to
implement a SCM Policy. The SCM Regulations establish
the framework
for a municipalities’ SCM Policy. The policy must reflect the
constitutional principles of section 217(1).
[15]
Once adopted, a municipalities SCM Policy applies to the procurement
of goods and services by a municipality from non-state
contractors.
[16]
17]
It is the responsibility of the Defendant’s Municipal Manager
to take all reasonable steps to ensure that the Defendant’s
SCM
Policy is implemented.
[17]
The Defendant’s municipal council must delegate such additional
powers and duties to the Municipal Manager to enable him
to discharge
the supply chain management responsibilities in terms of the MFMA,
SCM Regulations and SCM Policy. The Defendant’s
SCM Policy is a
public document to which parties wishing to participate in the tender
process have right of access.
(d)
Relevant National Treasury Guidelines
18] In terms of Section
168 of the MFMA, the Minister of Finance may make regulations or
guidelines on supply chain management issued
by the National
Treasury.
19]
The SCM Guide is part of the constitutional and legislative
framework. The SCM Guide forms part of the provisions that empower
and/or limit the power of public bodies in the procurement of goods
and services. It is not merely an internal prescript that may
be
ignored or disregarded by organs of state procuring goods and
services.
[18]
20]
In the matter of Allpay Consolidated Investment Holdings (Pty) Ltd
and Others v Chief Executive Officer, South African Social
Security
Agency, and Others,
[19]
the Constitutional Court held that:
“
The
accounting officer or accounting authority must ensure that the
documentation and general conditions of contract are in accordance
with the instructions of the National Treasury and that the bid
documentation includes evaluation and adjudication criteria,
including
criteria prescribed by the Procurement Act and the
Board-Based Black Economic Empowerment Act (Empowerment Act).”
[20]
21] Validity of Bids an
extract of the SCM Guide is quoted hereunder for ease of reference:
“
Bidders
should be required to submit bids valid for a period specified in the
bidding documents. This period should be sufficient
to enable the
institution to complete the comparison and evaluation of bids, review
the recommendation and award the contract.
An
extension of bid validity, if justified in exceptional circumstances,
should be requested in writing from all bidders before
the expiration
date. The extension should be for the minimum period required to
complete the evaluation, obtain the necessary approvals
and award the
contract. In the case of fixed price contracts, requests for second
and subsequent extensions should be permissible
only if the request
for extension provides for an appropriate adjustment mechanism of the
quoted price to reflect changes of inputs
for the contract over the
period of extension. Bidders should have the right to refuse to grant
such an extension without forfeiting
their bid security, but those
who are willing to extend the validity of their bid should be
required to provide a suitable extension
of bid security, if
applicable.”
[21]
22] The above-mentioned
statutory instruments do not prescribe fixed times for tender
validity periods. Rather, guidance is provided
on how the period
should be determined. Provision is further made for the extension of
the tender validity period by agreement
before the initial period
lapses.
Tender Invitation and Bid
Submission
23]
To the matter at hand and at or during April 2013 the defendant
published an advertisement calling for tenders for “
UPGRADING
OF eMBALENHLE WASTE WATER TREATMENT WORK: CIVIL, MECHANICAL AND
ELECTRICAL ENGINEERING WORKS”
(Employer Tender Number: 8/1-66/2012) (the “Tender”).
[22]
The tender invitation stipulated that a compulsory clarification
meeting would be held on 5 April 2013. The closing date for the
submission of bids was Friday, 26 April 2013.
[23]
24] The tender validity
period was 120-days, calculated from the closing date. Therefore, the
Defendant’s Municipal Manager
had to formally award the tender
to the successful bidder no later than 26 August 2013.
25]
The Defendant’s Agent, WorelyParsons, extended the closing date
from 26 April 2013 to 3 May 2013. The Defendant denies
WorelyParsons’
authority to extend the closing date to 3 May 2013. In this regard
the Plaintiff explicitly pleads that the
tender validity period
lapsed (the tender was not awarded within the 120-days) and further
that the Plaintiff’s tender was
no longer capable of
acceptance.
[24]
It is further not in dispute that the Plaintiff submitted its bid to
the Defendant on 3 May 2013.
Tender Specifications
26]
The Tender is comprised of six volumes.
[25]
The “Conditions of Contract for Construction for Building and
Engineering Works Designed by the Employer (hereinafter referred
to
as the “Construction Contract” or “FIDIC”)
[26]
also formed part of the Tender Documents and contract.
[27]
27]
The
‘Standard Conditions of Tender’
[28]
must be read together with the ‘Tender Data’.
[29]
The Tender Data lists amendments to clauses in the Standard
Conditions of Tender. The Tender Data further has precedence if there
is any ambiguity or inconsistency. Clause 2.16 of the Standard
Conditions of Tender addressed the “Tender Validity
Period”.
[30]
It reads as follows:
“
2.16
Tender Offer Validity
2.16.1 Hold the tender
offer(s) valid for acceptance by the Employer at any time during the
validity period stated in the tender
data after the closing times
stated in the tender data.
2.16.2 If requested by
the Employer, consider extending the validity period stated in the
tender data for an agreed additional period.”
28] The Tender Data
further added to clause 2.16.1 by providing:
“
F.2.16.1
Add the following clause:
‘
If
the tender validity expires on a Saturday, Sunday or Public Holiday,
the tender shall remain valid and open for acceptance until
the
closure of business on the following working day.’
F.2.16.3 Add the
following new clause:
‘
Except
that should the Tenderer unilaterally withdraw his tender during this
period, the Employer shall, without prejudice to any
other rights he
may have, be entitled to accept any less favourable tender for the
Works from those received, or to call for fresh
tenders, or to
otherwise arrange for execution of the Works and the Tenderer shall
pay on demand any additional expense incurred
by the Employer on
account of the adoption of the said causes, as well as either a
difference in costs between the tender withdrawn
(as corrected) in
terms of clause 3.9 of the Conditions of Tender, and any less
favourable tender accepted by the Employer, will
difference between
the tender withdrawn (as corrected) and the costs of the execution of
the Works by the Employer as well as any
other amounts the Employer
may have to pay to have the Works completed.”
[31]
29]
The tender documents further included the “C1.1 Form of Offer
and Acceptance (the “Form of Offer”).
[32]
The Form of Offer confirms that the employer (the Defendant) has
solicited offers to enter into a contract for the procurement
of the
refurbishment works, consisting of civil, mechanical and electrical
engineering works. The Form of Offer confirms that by
submitting the
offer, the tenderer (the Plaintiff) has accepted the conditions of
Tender.
30]
In
casu
the plaintiff’s offer was signed by Mr. McCarley, the
Plaintiff’s Managing Director, on 26 April 2013, before
submitting
the tender on 3 May 2013.
[33]
Mr McCarley did not testify during the trial.
31] Under the offer price
in the Form of Offer signed by Mr McCarley, the following is
recorded:
“
This
offer may be accepted by the employer by signing the acceptance part
of this form of offer and acceptance and returning one
copy of this
document to the Tenderer before the end the period of validity stated
in the tender data, whereupon the Tenderer becomes
the party named as
the contractor in terms of the conditions of contract identified in
the contract data.”
[34]
32] Under the heading
“Acceptance” the Form of Offer stipulates that by signing
the Form the employer (the Defendant)
accepts the tenderer’s
(the Plaintiff) offer. It further states:
“
Acceptance
of the Tenderer’s Offer shall form an agreement between the
Employer and the Tenderer upon the terms and conditions
contained in
this agreement and in the contract that is the subject of this
agreement.”
[35]
33] The Form of Offer
requires that any deviations must be recorded in the schedule of
deviations attached to the Form, failing
which they shall not be
valid. It is common cause that the schedule of deviations contained
in the Form of Offer was never completed.
More specifically, the
following was not recorded in the schedule of deviations:
33.1
the 120-day tender validity was extended
beyond 31 August 2013;
33.2
that the scope of the tender had been
restricted to the civil works, and the price accordingly adjusted; or
33.3
amendments to the requirements for the
acceptance of the offer and any additional terms not envisaged in the
Tender Documents.
34]
WorleyParsons was appointed as the Defendant’s Agent for the
Tender,
[36]
and acted as such during the tender validity period. Only once the
contract was signed could WorleyParsons act as the Engineer.
35] During the tender
process, meant to culminate in the award of the Tender, WorleyParsons
assumed the mantle of Agent. Its authority
and powers were limited to
those specified in the Tender Documents, specifically the Standard
Conditions of Tender and the Tender
Data.
36] Clause 1.4 of the
Standard Conditions of Tender describes the Agent’s role in the
tender adjudication process as follows:
“
Each
communication between the employer and a tenderer shall be to or from
the employer's agent only, and in a form that can be
read, copies and
recorded. Writing shall be in the English language. The employer
shall not take any responsibility for non-receipt
of communications
from or by a tenderer. The name and contact details of the employer's
agent are stated in the tender data.”
[37]
37]
As mentioned above, the “Conditions of Contract for
Construction for Building and Engineering Works Designed by the
Employer
(Construction Contract of FIDIC)
[38]
formed part of the Tender. The successful bidder was required to sign
the Construction Contract once the tender was awarded. In
this
regard, the following clauses from the Construction Contract are
relevant and not in dispute:
“
1.1.1.1
"Contract"
means the Contract Agreement, the Letter of Acceptance, the Letter of
Tender, these Conditions, the Specification, the Drawings,
the
Schedules, and the further documents (if any) which are listed in the
Contract Agreement or the Letter of Acceptance.
1.1.1.3
"Letter
of Acceptance"
means the letter of formal acceptance, signed
by the Employer, of the Letter of Tender, including any annexed
memoranda comprising
agreements between and signed by both Parties.
If there is no such letter of acceptance, the expression "Letter
of Acceptance"
means the Contract Agreement and the date of
issuing or receiving the Letter of Acceptance means the date of
signing the Contract
Agreement.
1.1.2.4
"Engineer"
means the person appointed by the Employer to act as the Engineer for
the purposes of the Contract and named in the Appendix to
Tender, or
other person appointed from time to time by the Employer and notified
to the Contractor under Sub-Clause 3.4 [Replacement
of the Engineer].
38] The Construction
Contract (FIDIC) further includes various annexures and forms that
the Plaintiff and the Defendant must complete
and sign,
inter
alia
, the “Letter of Tender”, “Appendix to
Tender”, “Contract Agreement”, and Dispute
Adjudication
Agreement.
39] In this regard the
following definitions is noteworthy:
“
Engineer”
supra
, the
Construction Contract requires that the Engineer be named in the
“Appendix to Tender”, which is attached to the
Construction Contract. Concerning the authority granted to the
“Engineer”, clause 3.1 of the Construction Contract
provides:
“
The
Employer shall appoint the Engineer who shall carry out the duties
assigned to him in the Contract. The Engineer's staff shall
include
suitably qualified engineers and other professionals who are
competent to carry out these duties.
The Engineer shall have
no authority to amend the Contract.
The Engineer may exercise
the authority attributable to the Engineer as specified in or
necessarily to be implied from the Contract.
If the Engineer is
required to obtain the approval of the Employer before exercising a
specified authority, the requirements shall
be as stated in the
Particular Conditions. The Employer undertakes not to impose further
constraints on the Engineer's authority,
except as agreed with the
Contractor.”
COMMON CAUSE FACTS
40] The following appears
to be the common cause facts between the parties:
40.1
Neither the plaintiff, nor the defendant,
signed the Construction Contract/FIDIC. In this regard, the plaintiff
did not present
any evidence that the Construction Contract was
signed;
40.2
The
written contract was not attached to the Plaintiff’s amended
Particulars of Claim. The only copy of the contract before
this Court
is the unsigned version attached to the Defendant’s opposing
affidavit in the summary judgment application, as
Annexure “MM5”.
[39]
40.3
The Plaintiff did not plead any of the
terms and conditions of the Construction Contract/FIDIC in its
Particulars of Claim;
40.4
Once the tender validity period expired,
WorleyParsons appointment as Agent came to end per the tender
documents;
40.5
Even if it is accepted that WorleyParsons
was entitled to make a new offer on behalf of the defendant, as
pleaded by the plaintiff,
WorleyParsons could only obtain the powers
and obligations afforded to the Engineer once the Construction
Contract/FIDIC was duly
completed and signed by both parties.
41] The Defendant
purposefully refers to WorelyParsons as its “Agent” in
its Plea and Counterclaim. At no stage does
the Defendant refer to
WorelyParsons as the “Engineer”. Furthermore, the
Defendant admitted that WorelyParsons had
been appointed as its Agent
and that WorleyParsons had been appointed to represent the Defendant
in the conclusion of the Tender,
as advertised.
42] The Defendant
explicitly pleaded that WorelyParsons was not appointed, nor did it
have any authority, to conclude any contract
that constituted a
deviation from the Defendant's SCM Policy. The plaintiff’s
failure to appreciate the distinction between
the role of the “Agent”
juxtaposed to the “Engineer” is apparent from its
Particulars of Claim.
43] It is on this basis
that the defendant had argued that WorleyParsons could not approve
payment certificates in terms of the
Construction Contract/FIDIC,
absent a duly executed and signed Construction Contract.
APPOINTMENT OF THE
PLAINTIFF AS CONTRACTOR
44] On Friday, 30 August
2013 the Defendant’s Bid Adjudication Committee (the “BAC”)
resolved to recommend to
the Defendant’s Municipal Manager:
44.1
That the Plaintiff be appointed as the
contractor for civil works at the value of R40 24 107.47, incl 5 %
escalation, 10 % contingency
and 14 % VAT;
44.2
That
Piet Bok Konstruksie BK be appointed for electrical and mechanical
works at the value of R22 281 298.79, incl 5 % escalation,
10 %
contingency and 14 % VAT.
[40]
45]
On 31 August 2013, the Municipal Manager signed a letter addressed to
the technical director of WorleyParsons.
[41]
The letter confirmed the appointment of the Plaintiff and further
instructed WorleyParsons as follows:
“
We
request you to issue the letter of award to the successful bidders on
our behalf. We further request you to facilitate the site
handover of
the site to both contractors upon acceptance of our offer of award
and submission of all the necessary documentation
in accordance to
the conditions of contribution for building and engineering works
designed by the employer published by FIDIC
FIRST EDITION 1999 of the
construction contract (Redbook).”
46] The Defendant’s
right to divide the work between the two service providers is not in
dispute. The aforesaid was also confirmed
by the Plaintiff’s
sole witness, Mr du Toit.
47] It is further
important to be mindful of the fact that that the Municipal Manager’s
letter is titled “BID NO 8/3/1-66/2012
REFURBISHMENT OF
eMBALENHLE WASTE WATER TREATMENT WORKS – APPOINTMENT OF
CONTRACTOR(S).” The letter of appointment
does not refer to the
lapsed tender validity period or a “new offer”. The
letter is also silent on the extension of
the tender validity period
beyond 120-days.
48]
The appointment letter was subsequently dispatched to the Defendant’s
agent on 6 September 2013.
[42]
49]
In reply to receipt to the letter, WorleyParsons on 20 September
2013, sent a letter to the Plaintiff titled “CONTRACT
NO:
8/3/1-66/2012: REFURBISHMENT OF eMBALENHLE WASTE WATER TREATMENT
WORKS.
[43]
The letter confirms the Plaintiff’s appointment for the civil
works under contract 8/3/1-66/2012 and attaches the Municipal
Manager’s letter in confirmation. The letter requests the
Plaintiff to:
“
6.
Please indicate in writing your acceptance of this offer although the
validity of the tender has
already expired.”
ACCEPTANCE OF APPOINTMENT
AS CONTRACTOR
50] On 1 October 2013 the
Plaintiff forwarded a letter titled “CONTRACT NO 8/3/1-66/2012
REFURBISHMENT OF eMBALENHLE WASTE
WATER TREATMENT WORKS: CIVIL,
MECHANICAL AND ENGINEERING WORKS, Letter of Acceptance” to
WorleyParsons’ technical director.
The letter confirmed that:
“
Your
letter of appointment dated 20 September 2013 refers.
As per
point 6 of your letter I hereby confirm acceptance of the offer as
per your updated letter despite the expiration of the
tender
validity.”
[44]
51] On 3 October 2013 the
Plaintiff’s board of directors resolved as follows:
“
That
Anton du Toit in his capacity as director is hereby authorised to
sign the Govan Mbeki Municipality: Contract 8/3/1-66/201:
REFURBISHMENT OF THE eMBALENHLE WASTE WATER TREATMENT WORKS –
CIVIL, MECHANICAL AND ELECTRICAL ENGINEERING on behalf of the
company.”
[45]
52]
On 4 October 2013, a site meeting was held. The meeting was attended
by representatives of WorelyParsons, the Plaintiff and
Piet Bok
Konstruksie.
[46]
The minutes of the meeting further clearly record the commencement
date of the contract as 8 October 2013. No representative of
the
Defendant attended the meeting.
53] On 7 November 2013,
the Defendant’s Municipal Manager signed a “C1.1 Form of
Offer and Acceptance”. The offer
part of the Form was completed
by specifying the amount mentioned in the WorleyParsons letter of
appointment, dated 20 September
2013. The Plaintiff’s Managing
Director signed the offer in the required space on 21 November 2013.
54] The offer signature
block was signed and completed by Mr McCarley, beneath the lesser
price of R 40 246 107,47 written in manuscript,
on 21 November 2013.
The signature block for the acceptor was left blank but witnessed by
Mr Mtshali on 7 November 2013, and the
schedule of deviations,
although including no agreed deviations, was signed by the Municipal
Manager, Mr Mahlangu and also dated
7 November 2013.
PLEADED CASE OF THE
PLAINTIFF
55]
It is common cause that the tender validity period had lapsed.
However, the Plaintiff claims that a 'new offer' was made by
the
Defendant, which it accepted. Consequently, the Plaintiff’s
case is that a new contract was entered into and concluded
with the
Defendant.
[47]
The admission is summarised as follows in paragraph 3.14 of the
Particulars of Claim:
“
When
the Engineer, acting on behalf of the Defendant, addressed Annexure
"E" hereto to the Plaintiff, the aforementioned
120 day
validity period pertaining to the Plaintiff's tender had expired and
the Plaintiff's tender, which constituted an offer
by the Plaintiff
to the Defendant, was no longer capable of acceptance by the
Defendant in the terms of, or on the basis of, the
original
Invitation to Tender issued by the Defendant or the Offer made by the
Plaintiff in terms thereof.”
[48]
56] The Plaintiff further
pleads that the alleged new 'offer' incorporates all the terms and
conditions contained in the tender
documents. The distinction between
the Tender and this new offer is the exclusion of certain
unfavourable terms and the inclusion
of favourable terms and
conditions.
57] A reading of the
common cause facts above confirms that the evidence does not support
the Plaintiff’s claim of a new contract
or offer.
58] During the trial, the
Plaintiff’s witness believed that it had accepted the award of
the Tender, albeit on a reduced scope.
59] The Plaintiff’s
case has always been that the material terms and conditions of the
Tender were no longer applicable to
the Plaintiff’s acceptance
of the Defendant’s alleged offer. In its Particulars of Claim,
the Plaintiff pleaded as
follows:
“
3.18.
The material terms and/or conditions of the Plaintiff's tender, which
were no longer applicable to the Plaintiff's acceptance
of the
Defendant's new offer set out in Annexure "E" hereto,
consisted of, inter alia, the following:
3.18.1.
…
3.18.2.
…
3.18.3. The manner in
which the contract would be concluded between the Plaintiff and the
Defendant would no longer be as described
in the Invitation to Tender
and/or the Plaintiff's tender but would be by the written acceptance
by the Plaintiff of the Defendant's
offer as set out in Annexure "E"
hereto.
3.18.4. The provision by
the Defendant to the Plaintiff of a fully completed Form of Offer and
Acceptance, (i.e. all the pages thereof),
signed by the Plaintiff and
the Defendant, would not be a jurisdictional pre-requisite for the
creation of a vinculum juris between
the parties and the appending of
signatures by or on behalf of the Plaintiff and the Defendant to the
Form of Offer and Acceptance
would serve merely as facilitation of
proof that a vinculum juris had already been established between the
parties.
3.18.5. None of the terms
and/or conditions of the Plaintiff's original tender and/or the
Defendant's Notice of and Invitation to
submit a tender would apply
which, by their very nature, given the lapsing of the tender validity
period and the Defendant's new
offer to conclude a contract with the
Plaintiff in respect of a limited portion of the Plaintiff's original
tender, would apply.”
EVIDENCE PRESENTED ON
BEHALF OF THE PLAINTIFF
60]
As mentioned, the Plaintiff in order to succeed carried the
onus
on a balance of probability. In this regard, it called a single
witness, namely Mr Du Toit. In essence Mr. Du Toit could not testify
that the Construction Contract/FIDIC was duly signed and completed by
the respective parties albeit that the demand for payment
by the
Plaintiff was made in terms of the FIDIC contract.
61] In fact, the majority
of his evidence dealt with the disputed signed “Form of Offer
and Acceptance”.
62] In this regard his
evidence on point was the following: The Plaintiff’s counsel
referred Mr du Toit to the unsigned copy
of the Construction/FIDC
contract attached to the Defendant’s Opposing Affidavit in the
Summary Judgment earlier proceedings.
In this regard he testified to
the terms and conditions of the contract.
63] Mr Du Toit, was
specifically referred to the incomplete contract, attached to the
summary judgment application (Annexure “MM5”)
and not a
signed Construction Contract/FIDIC. On point his testimony was as
follows:
“
Mr
Potgieter: This
deals with the obligations of the tender to pay the contractor,
and
it says that the employer should pay to the contractor the amount
specified in the interim payment certificate within 36 days
after the
engineer received the statement and supporting documents.
Now, this FIDIC document
has been amended, and that period is now 35 days not so?
Mr du Toit:
Yes.”
64] Based on this
evidence, it is evident that Mr du Toit accepted that all payments
subsequent to the Plaintiff’s alleged
appointment were
regulated by the Construction/FIDIC Contract that formed part of the
Tender documents.
65] Mr du Toit however
was unclear on the actual contract that was concluded or what the
terms and conditions of said contract were.
During cross-examination,
he responded as follows:
“
Mr
Botes: Yes. Now that’s what the
municipality want to achieve because we are, we want to be
responsible,
we want to do the right thing, and in the end of the
day, if monies are due while then, it must be paid. If monies are not
due,
will obviously can’t be paid. Now against that backdrop,
the first agreement upon which the Plaintiff rely in this application
you will recall was an agreement that was allegedly entered into and
concluded during November 2013. Do you remember that?
Mr du Toit:
Yes. I remember the offer was extended, yes, by Mr Nico Wiid.”
66] Mr du Toit was
further specifically asked during cross-examination if he could
identify the contract upon which the Plaintiff
relied for its claim.
In this regard, he testified:
“
Mr
Botes: Yes, the agreement the contract that
came into existence in November 2013.
Mr du Toit:
I am sure of November, when was the .... when did the ... did Nico
Wiid, on behalf of the employer,
issued the offer to Bosch Munitech
was the 20
th
of September, I recall so, and then in my
reply which I think was the 30
th
October we accepted, I
would think the 30
th
October the agreement came into place
between the parties and that form the contract. So that is a contract
as you refer to. But
then again, I am a layman I am not an attorney.
So that is what is being referred to so.
Mr Botes:
I am not asking you for your opinion, I am just establishing two
things. One the Plaintiff’s
case and two, listen carefully the
true facts; that’s all I am interested in. Are we on the same
page?
Mr du Toit:
Yes, I can testify to the facts that I am aware of.”
67] When questioned
further on the conclusion date for the contract, Mr du Toit’s
testified as follows:
“
Mr
du Toit: Again, the date is for the court to decide where
a contract came into existence but based on my understanding,
that
would be the formal offer of acceptance that was signed on the 21
st
alternatively November alternatively the day that we accepted your
client’s offer the 30
th
of October when I wrote the letter saying I accept your offer based
on these terms then the contract came into existence. That
is my
understanding of the contract, Sir, and that is where you can find
it.
Mr Botes:
My answer, my question, is actually very straightforward and easy. I
just want you to assist
Her Ladyship and direct Her Ladyship’s
attention to the written agreement that the Plaintiff relies upon
where in paragraph
4 of Mr McCarley’s affidavit. It's all I
want.
Mr du Toit:
That would be the entire tender document that has been signed after
the formal offer. That would be,
not all of it is in here, but the
formal offer will be the basis of it, and that is in these documents.
Would you like me to find
the page?”
68] Significant to Mr du
Toit testimony further is that he unequivocally testified that to his
knowledge, there had been no general
extensions issued to all the
tenderers:
“
Mr
du Toit: My Lady, whatever the recording says, I was
clear in my mind, and I will clarify if that make matter easier.
Like, I told Mr Botes, no, there was not a general extension issued
to all tenderers. There was an offer made to me based on a
Bid
Adjudication Committee that was that made their findings within the
120 days; the offer was made to me for me to accept or
reject. It is
my understanding that I am well within my rights to accept that offer
which I did.
So
that is my statement, and yes, as you clearly stated no there was no
extension of the closing date for all bidders. I was made
an offer
based on a municipal adjudication that was made within the 120 days.
What that legally means is beyond me.”
69] Based on what has
been stated aforesaid, it is clear that Mr du Toit was under the
impression that he was accepting an offer
originating from the Bid
Adjudication Committee’s recommendation during the tender
validity period.
70] From the above the
conclusion to be drawn is that Mr du Toit believed that an offer was
made to the Plaintiff in terms of the
Tender.
71] Differently put, Mr
du Toit accepted and understood that the Plaintiff was concluding a
contract in terms of the Tender and
not a contract based on a “new
offer”.
72] As to the limited
scale of the tender award, Mr du Toit confirmed during his evidence
in chief and again during cross-examination,
that the Defendant was
entitled to split the Tender as it did per the tender documents and
specifications. There was therefore,
nothing untoward regarding the
Defendant’s decision to divide the scope of work.
73] Mr du Toit during his
testimony further confirmed that the amounts claimed were only for
standing time and site establishment
costs. The payment certificates
that were approved by WorleyParsons were not for construction works
performed by the Plaintiff.
It is therefore be common cause that the
Defendant never received any benefit.
74]
Mr Du Toit’s evidence also differs to the pleaded case of the
plaintiff. The following extract of his testimony is indicative
thereof. When questioned on the allegations made in the Particulars
of Claim by the Defendant’s counsel, he stated:
“
Mr
du Toit: My Lady, I have said I don’t agree with
it.
I said if we look at this
practically again, I am not an attorney. What I understand from these
things again, I did not write this.
I am called as a witness on facts
to which I testify here today.
My understanding of that,
if you understand the contract in all of those volumes obviously 2,
3, 4, 5 whatever as it pertains to
the technical data and drawings,
those will obviously be applicable in the original contract or
commercial section of a tender
there would be very few pages
applicable to the execution thereof, which is normally the contract
data and the special conditions
of contract which refer to FIDIC
which refers to the execution of a contract and in there, there would
have been the duration for
us to complete this contract, for example,
would be 2 years. By that would refer to a complete award.
Mechanical, civil and electrical.
So for me, what I read
from this is that, yes, those all need to be revisited because we
were only awarded the civil portion. By
that so yes, the contract
still exists within the FIDIC Redbook. That didn’t go away.
We are not now doing
another form of contract. I think that would be silly to say that. So
yes, that still pertains there are sections.
I mean, we can page
through the whole thing, and I can tell you what I think exactly
should be applicable and what I understood
on this and what was
executed was ok you doing civils gives us your program.
So the requirement must
be I must give program of works within a certain amount of days. So
they the original program, which was
civil, mechanical, electrical,
for example, My Lady, that no longer applies, because it was not
awarded that.
So again, my
understanding of this is, its take all of that away. We don’t
throw the document away. The pertinent facts that
spoke to a full
scope of work need to be revisited. In line with partial award made,
in line with what was allowed in the tender,
in line that would talk
to the days for completion, the new program, integration with etc. So
mean I can run through it. So, so
that is my response to that.
No, we don’t throw
the whole thing away. We threw away the pertinent items within the
contract data that spoke to the entire
contract and apply that to the
portion of the contract that was awarded. That is my understanding.
So that is what I am saying
I disagree with you. We don’t know
longer do it under FIDIC/Redbook. It's still a Redbook. It's just the
terms of that need
to be agreed based on the award.”
75] Albeit that Mr Du
Toit was extensively cross-examined by counsel for the Defendant, Mr
Du toit was never given an indication
that his factual evidence will
be refuted by any witnesses to be called by the Defendant.
76]
The lack of any indication by the Defendant’s counsel in
cross-examination to Mr. Du Toit that any of his factual evidence
would be impeached has consequences. They are well recognized and the
following quote is of relevance:
“
[
61] The
institution of cross-examination not only constitutes a right, it
also imposes certain obligations. As a general rule it
is essential,
when it is intended to suggest that a witness is not speaking the
truth on a particular point, to direct the witness’s
attention
to the fact by questions put in cross-examination showing that the
imputation is intended to be made and to afford the
witness an
opportunity, while still in the witness-box, of giving any
explanation open to the witness and of defending his or her
character. If a point in dispute is left unchallenged in
cross-examination, the party calling the witness is entitled to
assume
that the unchallenged witness’s testimony is accepted as
correct. This rule was enunciated by the House of Lords in Browne
v
Dunn and has been adopted and consistently followed by our courts.
[62] The rule in
Browne v Dunn is not merely one of professional practice but ‘is
essential to fair play and fair dealing
with witnesses’. It is
still current in England and has been adopted and followed in
substantially the same form in the Commonwealth
jurisdictions.
[63] The precise
nature of the imputation should be made clear to the witness so that
it can be met and destroyed, particularly
where the imputation relies
upon inferences to be drawn from other evidence in the proceedings.
It should be made clear not only
that the evidence is to be
challenged but also how it is to be challenged. This is so because
the witness must be given an opportunity
to deny the challenge, to
call corroborative evidence, to qualify the evidence given by the
witness or others and explain contradictions
on which reliance is to
be placed
.”
[49]
77] The above approach to
be adopted was not followed during the cross-examination of the
Plaintiff’s witness.
DEFENDANTS’ PLEADED
CASE
78]
The Defendant’s pleaded case in a nutshell, is the
following:
78.1
The Defendant’s Agent did certain things that he was not
empowered to do and nor could they be delegated to the Defendant’s
agent. They were thus null and void.
78.2
Procurement legislation and/or the Defendant’s own
procurement policy was not followed and thus no valid contract could
have
been concluded between the parties.
78.3
In the premises:
78.3.1 No
certificates could or should have been issued by the Defendant’s
Agent.
78.3.2 Any
certificates that had been issued were invalid and of no legal
effect.
78.3.3 Payments of
certificates that had occurred had been made in error.
78.4 The specific details
underlying the aforementioned defences raised by the Defendant can
best be summarized as follows:
78.5
The
Defendant is a Municipality, a Local Government and an Organ of
State.
[50]
78.6
In the
premises, when procuring goods and services pertaining to the tender
in question in this case, the Defendant was obliged
to comply with
various legislation consisting of Acts and Regulations as well as the
Defendant’s Supply Chain Management
Policy.
[51]
78.7
Whilst
admitting that Worley Parsons was indeed appointed as the Defendant’s
Agent the Agent was not authorized to extend
the closing date for the
submission of Bids in reaction to the Defendant’s tender
invitation.
[52]
78.8
The
Plaintiff failed to submit a tender before 12h00 on Friday 26 April
2013.
[53]
78.9
The tender
validity period was stipulated to be 120 days which had to have been
calculated from the closing date in the tender invitation
viz
26 April 2013.
[54]
78.10
The
Defendant had been obliged to award the tender within a period of 120
days
viz
by 24
August 2013,
[55]
but, even if
it is found that the extension of the closing date to 3 May 2013 is
valid, no award of the tender to the Plaintiff
occurred within 120
days calculated from 3 May 2013.
[56]
78.11
A valid
award of a tender could only be made within the 120 days by the
Defendant signing the Form of Offer and Acceptance before
the expiry
of the 120 days and same never occurred. Consequently, no valid
contract could ensue.
[57]
In
this regard the Defendant relies specifically, on the provisions of
C1.1 of the Form of Offer and Acceptance and even quoted
same.
[58]
78.12
In
particular the Defendant pleaded that as soon as the 120 day period
had expired without the Defendant awarding a tender the tender
process had been completed and the Defendant was no longer free to
negotiate with the Plaintiff as the process would no longer
be
transparent, equitable or competitive.
[59]
78.13
Any
negotiations with the Plaintiff “to extend the validity period”
was not equitable or competitive.
[60]
This was because it would be unfair to other tenderers if the tender
was not awarded within the 120 day period.
[61]
78.14
When the
Defendant’s Bid Adjudication Committee resolved to award a
portion of the tender to the Plaintiff and when the Defendant’s
Municipal Manager wrote the letter instructing the Defendant’s
Agent to make an offer to the Plaintiff the said Committee
and
Municipal Manager had not been aware that the 120 day period had
already expired.
[62]
78.15
When the
Plaintiff had accepted the offer made by the Defendant, as set out in
the Defendant’s Agent’s letter, the Plaintiff
had been
aware that acceptance of same would result in an illegal, invalid and
null and void,
ab
initio,
contract which would bestow no rights and the Plaintiff had acted
mala
fide
and unlawfully.
[63]
79]
It is on this basis that the Defendant had raised among others a
legality challenge to the Plaintiff’s claim.
THE
PLAINTIFF’S REPLY TO THE DEFENDANT’S PLEA:
80]
In its reply the Plaintiff placed all of the alleged non-compliances
and/or lack of authority of the Defendant’s Agent,
in dispute
but also pleaded that any breaches of same which were proven did not
justify a conclusion that no valid contract was
concluded.
[64]
The Plaintiff also specifically pleaded that the conclusion of the
contract was preceded by a valid competitive bidding process.
[65]
81]
The Plaintiff furthermore referred the Defendant to specific clauses
of the Defendant’s own Standard Conditions of Tender
which
militate against the Defendant’s defences.
[66]
The Plaintiff averred that the Defendant’s interpretation of
the validity period of 120 days was incorrect and pleaded the
correct
interpretation of same.
[67]
Pertaining to the Defendant’s reliance upon an alleged
jurisdictional pre-requisite for the conclusion of a valid contract,
(i.e. the signing of certain papers within a certain period of time),
the Plaintiff pleaded that the Defendant’s interpretation
of
same was incorrect and same merely regulated the formalization of a
contractual document once a tenderer’s tender had
resulted in
the conclusion of a contract.
[68]
82]
Pertaining to the Defendant’s attempt to rely upon the lack of
authority of the Defendant’s Agent the Plaintiff
repeated the
Plaintiff’s alternative basis for its claim against the
Defendant as raised in the Plaintiff’s final particulars
of
claim.
[69]
83]
The Plaintiff also referred to the Plaintiff’s reliance on
ostensible authority.
[70]
THE
DEFENDANT’S COUNTERCLAIM
84]
In addition to its plea the Defendant had also filed a counterclaim.
The Defendant’s counterclaim is for repayment of
those monies
paid by the Defendant to the Plaintiff in accordance with the first
five certificates issued by the Defendant’s
Agent certifying
that the Defendant had been liable to pay the said amounts to the
Plaintiff.
[71]
85]
The Defendant’s counterclaim raises no new issues that were not
raised by virtue of the Defendant’s plea to the
Plaintiff’s
final particulars of claim. The basis of the counterclaim remains the
alleged illegality of the contract between
the parties for want of
compliance with procurement legislation, regulations and policies. It
is contended by the Defendant that
it is just and equitable within
the meaning of section 172(1)(b) of the Constitution that the
Plaintiff be ordered to repay those
monies paid by the Defendant to
the Plaintiff.
[72]
86]
The purported sense of wrongfulness of the Plaintiff pertaining to
the conclusion of the contract is once again raised.
[73]
87]
Of particular importance is the averment by the defendant that “
The
contravention of the statutes as set out in the Defendant’s
plea are not merely of a technical nature. The irregular and
invalid
nature of the award and contract constitutes against the public
good
”.
[74]
THE
PLAINTIFF’S PLEA TO THE DEFENDANT’S COUNTERCLAIM
88]
In the first instance the Plaintiff pleaded that any claim for
repayment of the monies paid by the Defendant to the Plaintiff
has
prescribed.
[75]
This plea
relies upon dates about which there can be no debate as they appear
ex facie
the
pleadings.
89]
As far as the merits of the Defendant’s counterclaim is
concerned the Plaintiff raised no new issues than those raised
in the
Plaintiff’s final particulars of claim and reply to the
Defendant’s plea to the Plaintiff’s final particulars
of
claim. As a matter of fact, the Plaintiff referred to many portions
of the final particulars of claim.
[76]
90]
The Plaintiff did, however, raise the following specific issues in
the Plaintiff’s plea to the counterclaim:
90.1
The
Defendant had ratified the conduct of the Defendant’s agent in
respect of those aspects which the Defendant contended
that the said
Agent had not been authorized.
[77]
90.2
The
professed ignorance of the Defendant’s Bid Adjudication
Committee and Municipal Manager about the lapsing of the 120 day
period constituted unilateral errors which the Defendant could not
rely upon when it came to the conclusion of the contract.
[78]
90.3
The
Defendant’s counterclaim constituted nothing more than an
attempt to “
self-review
”
the Defendant’s actions
[79]
and because the Defendant had been guilty of inordinate delay in
seeking such relief it is not just and equitable to grant the
Defendant such relief especially bearing in mind the particular facts
in
casu
.
[80]
90.4
Any
lament by the Defendant about the Plaintiff not having built anything
was due to the Defendant’s fault.
[81]
90.5
The
equitable relief contemplated in section 172(1)(b) of the
Constitution was not intended to assist an Organ of State guilty of
culpable conduct such as the defendant is guilty of
in
casu
.
[82]
90.6
It
would not be in the interests of public policy but would amount to a
grave injustice to deprive the Plaintiff of the amounts
claimed in
the Plaintiff’s
particulars
of claim.
[83]
The Plaintiff
averred that depriving the Plaintiff of the amounts claimed would
simply encourage Organs of State to continue to
act culpably and
wrongfully and in a lackadaisical manner to the detriment of third
parties and the public because such conduct
would be seen to have no
consequences.
[84]
THE
DEFENDANT’S REPLY TO THE PLAINTIFF’S PLEA TO THE
COUNTERCLAIM:
91]
The Defendant elected to respond to the Plaintiff’s plea to the
counterclaim as follows:
91.1 “The
counterclaim is not one in terms of any common law enrichment action.
[85]
91.2
Because the
relief claimed in the counterclaim is dependent upon the Court first
declaring the contract between the Plaintiff and
the Defendant
invalid, (and, by necessary implication, it is averred that same has
not yet occurred), the jurisdictional pre-requisite
for requesting
repayment of the monies paid by the Defendant to the Plaintiff first
has to be met and only then will the Defendant’s
cause of
action for equitable relief, arise. Consequently, prescription could
not yet commence running.
[86]
91.3
The
Prescription Act cannot restrict the wide powers which a Court has to
grant equitable relief.
[87]
91.4
The
principles of estoppel, ostensible authority and/or quasi-mutual
assent find no application because they are aimed at making
lawful
that which is unlawful.
[88]
91.5
The
question of delay is irrelevant and the Court is obliged to declare
the contract unlawful.
[89]
91.6
The alleged
unlawful conduct of the Plaintiff is reiterated
[90]
and consequently it is just and equitable to grant the relief claimed
in the counterclaim.”
92]
In determining the issues in dispute, it is important to note that
the Defendant presented no evidence before this Court. In
support of
its case it mainly relied on the evidence presented by the
Plaintiff’s witness and its pleaded case.
93]
A litigant however is not only required to merely plead its case but
would also be required to present evidence either viva
voce or
through documents to prove its case.
THE
FOLLOWING FACTS WERE PROVEN DURING THE TRIAL
94]
In the present matter, the following facts were proven during the
trial:
94.1 Du Toit put the
Plaintiff’s tender together and submitted the Plaintiff’s
tender timeously on 3 May 2013.
94.2 The tenders were
opened after the extended closing time and this occurred in
accordance with the Defendant’s standard
conditions of tender
by reading out the tenders.
94.3
The
Defendant did not reject any tenders on the basis that they were
late, as required to be done by the Defendant’s Standard
Conditions of Tender.
[91]
94.4
There were
only two tenderers who qualified bearing in mind the values at which
the tenders came in and the requirement that the
tenderers should
qualify according to their CIDB grading.
[92]
94.5 The Tender
Invitation informed all tenderers that the components of the tender,
(i.e. Civil, Mechanical and Electrical), could
be split, (i.e.
awarded to different tenderers).
94.6 The tender validity
period of 120 days was extended by the Defendant’s designated
Agent
[93]
informing all
tenderers by means of e-mail communications commencing on 10 April
2013 that the tender closing date had been extended
to 3 May 2013 at
12h00.
[94]
94.7
The only
means of communicating with the Defendant was via the Defendant’s
aforementioned Agent.
[95]
94.8
The
Defendant made an offer to the Plaintiff to conclude a contract on
mutatis
mutandis
the terms contained in the original tender by issuing an offer letter
to the Defendant.
[96]
94.9 The Plaintiff
accepted the offer contained in the last mentioned letter by
means of a letter dated 1 October 2013.
[97]
94.10 At no time until
litigation commenced did the Defendant ever disavow anything done by
the Defendant’s Agent or contend
that there was no valid
contract due to any lack of authority of the Defendant’s Agent.
94.11 At a site meeting
the Form of Offer and Acceptance reflecting the reduced scope of the
works in respect of which the Plaintiff
and the Defendant had
contracted was finalized by the Plaintiff signing same after the
Defendant’s representatives had previously
signed same.
[98]
94.12
The
Plaintiff was given possession of the site where the works had to be
constructed and there was even a “
soil-turning
”
ceremony reported in the press.
[99]
94.13 Ever since the
Plaintiff sent the letter of acceptance of the Defendant’s
offer to conclude a contract in respect of
a reduced scope of works
various steps were taken by the parties with a view to execute the
contract that they had concluded. These
consisted of
inter alia
:
94.13.1 The signing of
the said Form of Offer and Acceptance.
94.13.2 The obtaining, at
great cost, by the Plaintiff of the necessary guarantees and the
provision of same to the Defendant.
94.13.3 The incurring of
costs by the Plaintiff pertaining to
inter alia
security and
housing.
94.13.4 The conclusion by
the Plaintiff of contracts with sub-contractors who would perform
certain of the obligations which the
Plaintiff had to perform.
94.13.5 The Plaintiff
moving onto site.
94.13.6 The Defendant’s
Agent certifying claims for payments made by the Plaintiff.
94.13.7 The payment by
the Defendant of the first five payment certificates.
94.13.8 Meetings aimed at
attempting to alleviate the Defendant’s professed financial
difficulties pertaining to the financing
of the project forming the
subject matter of the contract.
94.13.9 A request by the
Technical Manager of the Defendant to the Plaintiff not to cancel the
contract despite the Defendant’s
breach of contract.
94.13.10 At no stage did
the Defendant ever contend that:
The
Defendant had no intention to conclude a contract with the Plaintiff,
(i.e. had no
animus contrahendi
), as averred by the Defendant
in the Defendant’s opposition to the application launched by
the Plaintiff against the Defendant
which was adjudicated upon
Murphy, J. In this earlier application, Murphy J had found that the
contract was invalid for want of
compliance with procurement
Legislation, Regulations or Policies.
95]
It is common practice that tender validity periods at times get
extended.
95.1 The purpose of
tender validity periods is to bind tenderers to hold their offer open
for a period of 120 days during which
period they cannot withdraw
their offers and during which period the Defendant can enforce a
contract by simply accepting the tenders
within the 120 days.
95.2 When the 120 tender
validity period had expired the Plaintiff had the right to elect to
accept any offer made outside that
period to the Plaintiff or to
reject same.
95.3 The Plaintiff
elected to accept the Defendant’s tender contained in the
letter by the Defendant’s Agent dated 20
September 2013 and did
so by addressing the letter of acceptance of the Defendant’s
offer dated 1 October 2013 to the Plaintiff.
95.4 A contract was
concluded upon the Plaintiff having notified the Defendant, as
aforementioned, that the Defendant’s offer
had been accepted by
the Plaintiff.
95.5 When addressing the
letter dated 20 September 2013 to the Plaintiff the Defendant’s
Agent had not made an offer to conclude
a contract himself but had
rather simply conveyed the Defendant’s offer to the Plaintiff
and consequently there had been
no transgression of any prohibition
against the delegation of powers from municipal officials to a third
party such as the Defendant’s
Agent.
95.6 The Defendant had
not issued a general extension of the tender validity period.
95.7 The Defendant did
not accept any offer made by the Plaintiff but rather made an offer
to the Plaintiff.
95.8 Du Toit did not
agree that the Defendant had been obliged to recommence the tender
process simply because the Defendant had
elected to split the
components of the work to be done between the Plaintiff and Piet Bok
Konstruksie. The Defendant had been entitled
to split the award and
same was contemplated in the Tender Invitation issued to all
tenderers.
95.9 The charging for
standing time was in accordance with the terms of the contract
between the parties and it had been agreed
as a line item in the Bill
of Quantities of which extracts were attached to each claim for
payment. No further breakdown was given
because nobody called for it
and the Defendant’s Agent certified the Plaintiff’s
entitlement to same and thereby the
reasonableness of same.
95.10 The Defendant’s
Agent remained throughout, from the tender process to the execution
of the contract, the representative
of the Defendant.
95.11 Du Toit did not
agree that the defendant had simply extended an offer pertaining to
the 120 day period and pointed out that
the scope of works which the
Defendant wanted the Plaintiff to do, had also changed.
95.12 There had been no
collusion between the Plaintiff and other tenderers as suggested by
the Defendant. The e-mails referred
to in cross-examination
pertaining to enquiring from other entities involved in the same
industries whether they were interested
in undertaking a joint
venture with or becoming partners of the Plaintiff and nothing more.
This practice is common and there is
nothing wrong with same. The
Tender Invitation permits for joint ventures.
95.13
The split
of certain components referred to in the Tender Invitation between
the Plaintiff and Piet Bok Konstruksie resulted in
a savings for the
Defendant in excess of R5 million when the total of the amounts of
the two offers contained in the letter at
p. 11-120 are added up and
compared to the Plaintiff’s total amount of the Plaintiff’s
tender.
[100]
95.14 At no stage, prior
to the commencement of litigation between the parties, did the
Defendant or anyone else contend that because
the Defendant’s
Municipal Manager had signed at the wrong place on the Form of Offer
and Acceptance at the wrong place, there
was no contract between the
Plaintiff and the Defendant.
95.15The signature by the
Defendant’s Municipal Manager on the page of the Form of Offer
and Acceptance dealing with deviations
is inexplicable where there
had been no deviations. There had been no other reason for the
Defendant’s Officials, consisting
of the Technical Manager and
the Municipal Manager, to sign the Form of Offer and Acceptance
except to record, formally, the conclusion
of the contract between
the parties.
95.16
The Form of
Offer and Acceptance was signed at the site hand-over as envisaged by
the Defendant.
[101]
95.17
What
the contract documents consisted of is set out in the Tender
Invitation.
[102]
ANALYSIS
96]
In determining the issues in dispute, the first point of departure is
the legality challenge made by the Defendant against the
validity of
the contract.
97]
If the Defendant is unsuccessful with the legally challenge this will
be the end of the matter. This is so because all the issues
raised by
the Defendant in its plea and counterclaim are raised in support of
the legality challenge. By way of example, the following
issues fall
away if it is found that the legality challenge should not be
entertained:
97.1 The alleged lack of
authority of the Defendant’s Agent in extending the closing
date for the submission of tenders.
97.2 Any other alleged
lack of authority of the Defendant’s Agent.
97.3 The failure by the
Defendant to notify the Plaintiff of its decision to award a portion
of the scope of works to the Plaintiff
within 120 days from whatever
date of closing for the submission of tenders, is found to be
applicable.
97.4 The non-compliance
with any Legislation, Regulations or Procurement Policies.
97.5 The alleged
unfairness to other tenderers resulting from the conclusion of the
contract with the Plaintiff.
97.6 Any equitable
relief.
98]
In a legality review an Organ of State requests a Court to declare
its own actions of no legal consequence and validity. Where
such
actions have resulted in a contract such as the present matter, the
Organ of State requests that the contract be declared
invalid and of
no legal force and effect.
99]
In its plea and counterclaim, the Defendant pleaded its legally
challenge.
[103]
100]
In the Buffalo-decision, the Constitutional Court held as follows:
“
Courts have the
power in a legality review to refuse an application where there is an
undue delay in initiating proceedings
…”
[104]
101]
In
casu
there has been undue delay by the Defendant in
initiating proceedings constituting a legality review/challenge.
Herein, it is common
cause between the parties that the contract
between them were concluded, during October 2013, precisely seven
years before the
legality challenge was initiated.
102]
In determining the date from which it must be decided whether or not
there has been undue delay in initiating legality challenges
“…
the
proverbial clock starts running from the date that the Applicant
became aware or reasonably ought to have become aware of the
action
taken
”.
[105]
103]
Undoubtedly, the Defendant has always been aware of “
the
action taken
” in concluding the contract with the
Plaintiff.
104]
As previously mentioned, the Plaintiff initially issued an
application for payment on certificates before Murphy J during 2014.
Having done so, it follows that at the earliest it is this date that
the Defendant became aware of any legality challenge it wishes
to
have mounted in respect of the contract and it is noteworthy that
throughout the Defendant had been legally represented by its
current
set of attorneys.
105]
As such, it must therefore follow, that the Defendants’ clock
so to speak started to run at the earliest from 2014, which
is
approximately seven years before the legality challenge was first
launched.
106]
The Defendant before Court has proffered no explanation as to the
reason why it took so long to launch the legality challenge
and in
the absence of any explanation whatsoever by the Defendant pertaining
to the obvious undue delay the Court is entitled to
assume that there
is no reason at all or that the Defendant is not able to be honest as
to the real reasons for the delay.
107]
In a similar previous matter, (albeit that the delay was in that case
merely 20 months), the Constitutional Court remarked
as follows:
“
The fact that
the MEC has elected not to account for the delay, despite having had
the opportunity to do so at multiple stages in
the litigation, can
only lead one to infer that she either had no reason at all or that
she was not able to be honest as to her
real reasons
.”
[106]
108]
When it comes to an Organ of State, Courts require more from them
than from a private litigant. The following remarks illustrate
this:
“
Had the matter
been brought by a private litigant, this aspect of the test
[107]
might weigh less heavily. However, given that the MEC is responsible
for the decision, that she is obliged to act expeditiously
in
fulfilling her constitutional obligations, and that she should have
within her control the relevant resources to establish the
unlawfulness of the decision she impugns, the unreasonableness of the
unexplained delay is serious
.”
[108]
109]
Herein, the Defendant had, albeit from only the time when an attorney
and counsel were first consulted with a view to oppose
the
Plaintiff’s application that served before Murphy, J, within
the Defendants’ control the relevant resources to
establish the
unlawfulness of the decision the Defendant seeks to impugn.
110]
In the absence of any explanation being placed before this Court to
explain in full the delay, the inescapable conclusion to
be drawn is
that either no reasons exist to explain the delay or that the
Defendant was not honest to explain the real delay. On
either
proposition this Court cannot come to the assistance of the
Defendant.
111]
On its delay it is significant to note that the Defendant had pleaded
as follows in its reply to the Plaintiff’s plea
to its
Counterclaim:
111.1
“…
the
Honourable Court is obligated to declare it unlawful/invalid. This,
notwithstanding, an unreasonable delay in seeking the relief
sought
in the Counterclaim
”.
[109]
111.2
“
Even
if no explanation for the delay exists the Honourable Court is still
compelled to declare any agreement entered into between
the Plaintiff
and the Defendant unlawful, where the unlawfulness is not in
dispute
”.
[110]
112]
This Court having concluded that the legality review was unduly
delayed, is however, not the end of the matter.
113]
A Court further however has a discretion to overlook delay.
[111]
There must, however be a basis for a Court to exercise its discretion
to overlook the delay.
[112]
114]
The basis for a Court to exercise its discretion to overlook delay
“…
must
be gleaned from the facts made available or objectively available
factors
”.
[113]
115]
One of the considerations a Court will consider is the
potential
prejudice to affected parties and the possible consequences of
setting aside the impugned decision
[114]
116]
Thus “…
the
nature of the impugned decision
”
has to be considered,
[115]
and so too “…
the
extent and nature of the deviation from constitutional prescripts
…”
[116]
will play a vital role
when it comes to whether or not a Court should condone undue delay.
[117]
117] In this regard it is
the Plaintiff’s stance that there had not been a deviation from
constitutional prescripts whereas
the Defendant contends otherwise.
The mere submission that there had been a deviation from
Constitutional prescripts however, does
not suffice. More would be
required and no argument can merely be made without any evidence to
support same.
118]
Absent such evidence, it follows that this Court cannot exercise its
discretion to come to the assistance of the Defendant
to condone the
undue and unreasonable delay in launching the legality
review/challenge.
119]
A further consideration however to consider when deciding to overlook
delay is the conduct of an Applicant.
[118]
This is particularly true for State Litigants seeking to review their
own decisions for the simple reason that often they are best
placed
to explain delay.
[119]
120]
In the present matter the Plaintiff had argued that the conduct of
the Defendant in casu is reprehensible. The Defendant deliberately
roped the Plaintiff into a contract which it must, of necessity have
known the Defendant could not fulfil. After all the Defendant
can be
presumed to have known what monies the Defendant had and would have
had available to pay for the performance of the Plaintiff’s
obligations in terms of the contract.
[120]
121]
Absent any explanation counsel had further argued, it is manifestly
reprehensible to rope a third party into a contract knowing
full well
that that third party would incur costs and obligations vis-à-vis
subcontractors whilst knowing full well that
one would not be able to
pay the third party. This conduct will universally be condemned not
only as reprehensible but as also
despicable. As if this was not
enough, the Defendant thereafter, once again presumably knowing what
the Defendant’s budgetary
constraints were, did not play open
cards with the Plaintiff and did not cancel the contract due to an
inability to perform due
to a lack of funds, but strung the Plaintiff
along for months knowing full well that the Plaintiff would reserve
and allocate resources
to perform in terms of the contract.
122]
Counsel had further argued, to add salt to injury, the Defendant
thereafter sought to defeat the Plaintiff’s claims by
lying to
Court. In its affidavit opposing the application which served before
Murphy J, the Defendant contended under oath that
there had never
been an intention on the Defendant’s behalf to conclude a
contract with the Plaintiff, (i.e. there had never
been
animus
contrahendi
).
[121]
123]
It is on this basis that counsel had argued that it hardly behoves
any submissions, that the whole sequence of events up to
the
cancellation of the contract by the Plaintiff, is reconcilable only
with a conclusion that the Defendant indeed intended to
conclude a
contract and thus had the necessary
animus contrahendi
. The
fact that due to Counsel’s ingenuity interesting legal
arguments have been advanced as to why there had never been a
valid
binding contract can never detract from what the intention of the
Defendant had always been.
124]
In the present matter as already stated earlier, the Defendant only
belatedly, after many years, mounted a legality challenge
in which it
sought to justify the relief claimed by the Defendant by impugning
the character of the Plaintiff in the pleadings
only to jettison such
impugning when the Defendant’s counsel placed it on record,
whilst cross-examining Mr Du Toit, that
the Defendant was not
contending that the Plaintiff had done anything wrong in concluding
the contract with the Defendant. What
however remains glaringly
absent in these proceedings is any evidence presented by the
Defendant to explain its undue delay.
125]
The Defendant before Court had argued that mounting a legality
challenge should be condoned, if it has been determined that
a
Court’s hands are bound, if it is common cause that the
contract is unlawful due to a failure to comply with constitutional
prescripts.
[122]
126]
It is this principle which the Defendant relies upon for its stance
taken that it matters not that the delay was undue and
it matters not
that no explanation is given for the said delay.
[123]
To the matter at hand however, it is not common course that the
contract is unlawful.
127]
On the defence raised of a legality review, this Court therefore
concludes that this Court has a discretion not to entertain
a
legality review subject to the considerations recorded in that
decision.
128]
Furthermore, in casu, all of the facts militate against the Court
exercising its discretion to condone the undue delay by the
Defendant
and in the absence of condonation being granted, it follows that the
Defendants defence has not been proven.
129]
Based on this Court’s refusal to condone the undue and
unreasonable delay in launching the legality review, I hold the
view
it is dispositive of the defences raised to the Plaintiff’s
claim. It must therefore follow that the Defendant cannot
also
succeed with the Counterclaim it has instituted.
130]
In addition, given that the Court has accepted the Plaintiff’s
version which is not refuted by objective evidence on
the merits, the
defence on the merits must also fail. Consequently, the Defendants’
Counterclaim is dismissed with costs.
ORDER
131]
In the result the following order is made:
131.1 The
Plaintiff’s claim is granted with costs inclusive of the costs
of Senior Counsel.
131.2 The Defendant
is to pay the Plaintiff payment of the amount of R 16 969 144.69
as certified in payment certificates
numbers 6-13 and retention
certificate number 14.
131.3 Payment of
the amount of R 8 785 710.86 as loss of profit.
131.4 Payment of
interest on the amount of R 16 969 144.69 calculated
a
tempore morae
at 3% above the rate of interest SARB charges
commercial banks from time to time.
131.5 Payment of
interest at the prescribe rate of interest
a tempore morae
on
the amount of R 8 785 710.86.
131.6 The
Defendant’s legality challenge to the validity of the contract
is dismissed with costs.
131.7 The
Defendant’s counterclaim is dismissed with costs inclusive of
the costs of Senior Counsel.
C.J
COLLIS
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION PRETORIA
APPEARANCES:
Counsel
for Plaintiff : Adv.
T.A.L.L. Potgieter SC
Instructed
by:
Friedland Hart Solomon &
Nicolson Attorneys
Counsel
for Defendant: Adv. FW Botes SC and Adv. E
Van As
Instructed
by:
Cronje
De Waal – Skosana Inc Attorneys
Date
of Hearing:
15 September 2022
Date
of Judgment:
06 June 2024
[1]
Caselines
- Pleadings Bundle, Part 1: 007-29.
[2]
Caselines
- Pleadings Bundle, Part 1: 007-13, Para 3.17 of Particulars of
Claim.
[3]
Caselines - 011-40a: Trial Bundle: Notice of Motion.
[4]
2015 JDR 2066 (GP).
[5]
Caselines
- Pleadings Bundle, Part 4: 007-230, Para 8.4 and Para 10.2 of
Amended Plea and Counterclaim.
[6]
Chapter 11 of the “
Local
Government: Municipal Finance Management Act, Act 56 of 2003”
(“the MFMA”), read together with the and “
Municipal
Supply Chain Management Regulations”
>,
promulgated under
section 168(1)
of the MFMA, and published in
General Notice No 868 in Government Gazette GG 27636 of 30 May 2005.
(“the SCM Regulations”).
See further the Defendant’s
“
Supply
Chain Management Policy”
(“the SCM Policy”) adopted in compliance with section
111 of the MFMA; as well as the Treasury Guidelines on supply
chain
management issued by the National Treasury in terms of section 168
of the MFMA.
[7]
Section 40 (1), read with Chapter 7, and more specifically section
151(1), as well as section 239 of the Constitution.
[8]
Caselines
- Pleadings Bundle: 007-257 to 259.
[9]
Notably, section 12 of the
Prescription
68 of 1969
.
[10]
S151(4) Constitution of the Republic of South Africa, 1996. See also
S4(1)(a)
Local Government: Municipal Systems Act, 32 of 2000
.
[11]
Section
152(1)(b).
[12]
S153(A)
Constitution as further reflected in section 50(2) and 51(c)
of the Municipal Systems Act, 32 of 2000.
[13]
Adopted per section 168(1) of the MFMA. Published in General Notice
No 868 in Government Gazette GG 27636 of 30 May 2005.
[14]
Promulgated under section 5 of the PPPFA and published in General
Notice No R502 in Government Gazette 34350 of 8 June 2011
[15]
Section 112(2) MFMA.
[16]
Section 110(1)(a) MFMA.
[17]
Regulation 4(1)(a) of SCM Regulations.
[18]
Allpay
Consolidated Investment Holdings (Pty) Ltd and Others v Chief
Executive
Officer,
South African Social Security Agency, and Others,
2014 (1) SA 604
(CC) at para 40.
[19]
2014
(1) SA 604 (CC).
[20]
Para
37 at Pg 618.
[21]
Supply
Chain Management, A Guide for Accounting Officers/Authorities as
published by National Treasury, Pg 39.
[22]
Caselines - Trial Bundle: 011-6, Tender Advertisement.
[23]
Bosch Munitech judgment, para 3
[24]
Caselines
- Pleadings Bundle, Part 1: 007-12, Para 3.14 of the Particulars of
Claim.
[25]
Caselines - Trial Bundle: 011-7, Tender Data.
[26]
FIDC, 1
st
Edition, 1999 of the Construction Contract.
[27]
A copy of the Conditions of Contract is attached to the Plaintiff’s
summary judgment application. Caselines: Summary Judgment
Application – 013-84 to 213.
[28]
Caselines - Trial Bundle: 011-39, “T1.3: Standard Conditions
of Tender”.
[29]
Caselines - Trial Bundle: 011-7, “T1.2: Tender Data”.
[30]
Caselines - Trial Bundle: 011-44.
[31]
Caselines - Trial Bundle: 011-10 to 11.
[32]
Caselines - Trial Bundle: 011-17: “C1.1: Form of Offer and
Acceptance”.
[33]
Caselines - Trial Bundle: 011-18.
[34]
Caselines - Trial Bundle: 011-18.
[35]
Ibid.
[36]
Caselines - 011-7: Trial Bundle: T1.2: Tender Data, Clause F1.4.
[37]
Caselines
- Trial Bundle: 011-41, clause 1.4 of Standard Conditions of Tender.
[38]
FIDC, 1
st
Edition, 1999 of the Construction Contract.
[39]
Caselines - Summary Judgment Application: 013 to 213.
[40]
Caselines - Trial Bundle: 011-120.
[41]
Caselines - Trial Bundle: 011-121.
[42]
Caselines - Trial Bundle: 011-123, para 6(a), attachment to 20
September 2013 letter.
[43]
Caselines - Trial Bundle: 011-122 to 123.
[44]
Caselines - Trial Bundle: 011-124.
[45]
Caselines - Trial Bundle: 011-128.
[46]
Caselines - Trial Bundle: 011-129, Minutes of Meeting held on 4
October 2013.
[47]
Caselines - 007-12: Pleadings Bundle: Para 3.14 and 3.15 of
Particulars of Claim.
[48]
Caselines
- 007-12: Pleadings Bundle: Para 3.14 of Particulars of Claim.
[49]
President
of the Republic of South Africa and Others v South African Rugby
Football Union and Others
2000 (1) SA 1
(CC), p. 36, par. [61] –
[63].
This
decision is, colloquially, known as simply the SARFU, decision.
[50]
P.
7-222, par. 2.2.
[51]
P.
7-223, par. 3.2.
[52]
P.
7-225, par. 4.1.2 and p. 7-226, par. 4.2.
[53]
P.
7-225, par. 4.1.1 read with par. 5.1 at p. 7-226 and par. 5.3 as
well as par. 6 at p. 7-228.
[54]
P.
7-225, par. 4.1.3.
[55]
P.
7-226, par. 5.3.
[56]
P.
7-227, par. 5.4.
[57]
P.
7-227, par. 5.5.
[58]
P.
7-227, par. 5.4.2.
[59]
P.
7-228, par. 7.2.
[60]
P.
7-228, par. 7.3.
[61]
Ibid
.
[62]
P.
7-229, par. 8.1.
[63]
P.
7-231, par. 9.8 read with p. 7-230, par. 9.2 and p. 7-232, par. 9.9.
The last sentence of par. 15.3 at p. 7-235 is particularly
apposite
when it comes to the Defendant’s contention that the Plaintiff
had done something wrong.
[64]
P.
7-245, par. 2.2.
[65]
P.
7-246, par. 2.3.
[66]
P.
7-248, par. 5.2.
[67]
P.
7-249, par. 5.2.4.
[68]
P.
7-250, par. 5.2.5.
[69]
Vide
e.g. p. 7-246, par. 3.2; p. 7-248, par. 5.2; p. 7-251, par. 7.2; p.
7-253, par. 10.2 and p. 7-254, par. 11.2.
[70]
P.
7-254, par. 11.2.
[71]
P.
7-241, par. 19.3.1 and prayer 2 at p. 7-242.
[72]
Ibid
.
[73]
P.
7-240, par. 19.2 and p. 7-241, par. 19.3.2.
[74]
P.
7-241, par. 19.5.
[75]
P.
7-257, par. B1.
[76]
Vide
e.g.
p. 7-261, par. 3.2; p. 7-262, par. 3.3.6 and p. 7-266, par. 4.1.
[77]
P.
7-261, par. 3.3.
[78]
P.
7-266, par. 4.1.
[79]
P.
7-268, par. 8.2.1.
[80]
P.
7-268, par. 8.2.2.
[81]
P.
7-269, par. 9.2.2.
[82]
P.
7-269, par. 10.2.
[83]
P.
7-270, par. 11.2.
[84]
P.
7-271, par. 11.3.
[85]
P.
7-275, par. 3.2.
[86]
P.
7-275, par. 3.2.
[87]
P.
7-275, par. 3.3.
[88]
P.
7-277, par. 6.
[89]
P.
7-279, paras. 9.1 and 9.2.
[90]
Vide
e.g.
p. 7-277, par. 5.4 and p. 7-280, par. 10.2.
[91]
And, as shall be illustrated when the Defendant’s submissions
are made, as required by the Defendant’s Supply Chain
Management Policy.
[92]
This
appears at p. 11-6 in the Defendant’s Tender Invitation.
[93]
P.
11-7 clause F.1.4.
[94]
Which
is borne out by the e-mails at p. 11-928 a.f. and p. 11-104 to
11-111.
[95]
This
is borne out by p. 11-41 clause 1.4.
[96]
To
be found at p. 11-122, (which is also Annexure “E” to
the POC at p. 7-116).
[97]
To
be found at p. 11-124, (which is also annexure “F” to
the POC at p. 7-118).
[98]
The
document is to be found at p. 11-158 to 11-161.
[99]
The
press report appears at p. 11-134.
[100]
An
amount of R62 527 406.26 versus the amount of R67 861 297.95.
[101]
P.
11-123, par. 4.
[102]
P.
11-422.
[103]
The
Defendant’s final plea and the Defendant’s counterclaim
both saw the light of day only as recently as 14 October
2021. Vide
p. 7-243 where service of the said pleadings is recorded.
[104]
Buffalo
City Metropolitan Municipality v ASLA Construction (Pty) Ltd
2019
(4) SA 331
(CC), par. [53].
[105]
ASLA,
supra
,
p. 345, par. [49].
[106]
Khumalo
and Another v MEC for Education, KwaZulu-Natal
2014 (5) SA 579
(CC),
p. 595, par. [51].
[107]
i.e.
undue delay.
[108]
Khumalo
supra
,
p. 595D – E.
[109]
P.
7-279, par. 9.1 of the Defendant’s reply to the Plaintiff’s
plea to the
Defendant’s
counterclaim.
[110]
P.
7-279, par. 9.2 of the Defendant’s reply to the Plaintiff’s
plea to the Defendant’s counterclaim.
[111]
ASLA,
supra
p. 346, par. [53].
[112]
ASLA,
ibid
.
[113]
ASLA,
supra
ibid
.
[114]
ASLA,
supra,
p. 346, par. [54].
[115]
ASLA,
supra
,
p. 347, par. [55] and p. 348, par. [56] – par. [58].
[116]
ASLA,
supra
,
p. 348C.
[117]
This
is why it was submitted in par. 26
supra
that not every failure to tick every single box of procurement
legislation, Regulations and procurement policies justifies
entertaining a legality review/challenge.
[118]
ASLA,
supra,
p. 349, par. [59].
[119]
Ibid
.
[120]
There
is a long existing and well-established presumption and rule of law
that a person is taken to have known what it was his
duty to have
known.
Vide
Cape
Town Municipality v Paine
1923 AD 207
, p. 232.
[121]
P.
11-590, the last three lines of paragraph 8.1, par. 8.2.
[122]
ASLA,
supra
,
p. 360, par. [101].
[123]
P.
7-279, paras. 9.1 and 9.2.
sino noindex
make_database footer start
Similar Cases
Nkowana v H J Bosch and Sons (Pty) Ltd (A203/2023) [2024] ZAGPPHC 542 (14 June 2024)
[2024] ZAGPPHC 542High Court of South Africa (Gauteng Division, Pretoria)98% similar
Hi Tec Nuts (Pty) Ltd and Another v CSARS (34051/2021) [2024] ZAGPPHC 254 (11 March 2024)
[2024] ZAGPPHC 254High Court of South Africa (Gauteng Division, Pretoria)98% similar
Belcotech (Pty) Ltd v Placea 80 CC t/a Cafe 41 and Others (2024-052608) [2025] ZAGPPHC 872 (8 August 2025)
[2025] ZAGPPHC 872High Court of South Africa (Gauteng Division, Pretoria)98% similar
Matabicho (Pty) Ltd v Gauteng Provincial Liquor Board and Others (111703/2023) [2024] ZAGPPHC 1241 (29 November 2024)
[2024] ZAGPPHC 1241High Court of South Africa (Gauteng Division, Pretoria)98% similar
Bondev Midrand (Pty) Ltd v Van Blerk and Others (909/2014) [2024] ZAGPPHC 704 (12 July 2024)
[2024] ZAGPPHC 704High Court of South Africa (Gauteng Division, Pretoria)98% similar