Case Law[2024] ZAGPPHC 1381South Africa
Afriforum NPC v National Energy Regulator of South Africa and Another (2024/061972) [2024] ZAGPPHC 1381 (5 December 2024)
High Court of South Africa (Gauteng Division, Pretoria)
5 December 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 1381
|
Noteup
|
LawCite
sino index
## Afriforum NPC v National Energy Regulator of South Africa and Another (2024/061972) [2024] ZAGPPHC 1381 (5 December 2024)
Afriforum NPC v National Energy Regulator of South Africa and Another (2024/061972) [2024] ZAGPPHC 1381 (5 December 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_1381.html
sino date 5 December 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
CASE
NO: 2024-061972
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
Date:
5 December 2024
SIGNATURE:
In
the matter between:
AFRIFORUM
NPC
Applicant
and
NATIONAL
ENERGY REGULATOR OF SOUTH AFRICA
First Respondent
SOUTH
AFRICAN LOCAL GOVERNMENT ASSOCIATION
Second Respondent
JUDGMENT
DE
VOS AJ
[1]
AfriForum seeks interim execution of an order pending an appeal.
[1]
The appeal will be heard by a Full Bench of this Court, most likely
in the second term of 2025. AfriForum seeks the interim execution
of
the order in the public interest and aims to prevent municipalities
from charging end-users unlawful electricity tariffs pending
an
appeal process.
[2]
The application is opposed by NERSA, the energy regulator responsible
for approving
electricity tariff increases. NERSA persists in its
stance that the tariffs are lawful and contends that the requirements
of interim
execution have not been met. SALGA, which represents the
interests of more than one hundred and fifty municipalities, agrees
with
AfriForum that the tariffs are unlawful but submits that
AfriForum has not met the test for interim execution.
[3]
The context of the dispute is the methodology NERSA is required to
apply to determine
electricity tariff increases. The Electricity
Pricing Policy mandates municipalities to conduct cost-of-supply
studies, and section
27(h) of the Electricity Regulation Act 4 of
2006 states that NERSA's methodology must comply with the Policy.
Read together, the
legislation and the policy mandate that NERSA’s
methodology must be premised on cost-of-supply studies.
[4]
AfriForum and SALGA are in agreement that NERSA's methodology must be
based on cost-of-supply
studies. NERSA initially accepted that its
methodology must be based on cost-of-supply studies, but in the face
of non-complying
municipalities, did away with requiring
cost-of-supply studies and settled for a cost-breakdown methodology
for the 2024/2025 financial
year. It is common cause that NERSA's
current methodology does not require a cost-of-supply study.
[5]
AfriForum challenged NERSA’s methodology for determining tariff
increases for
the 2024/2025 financial year, as the methodology did
not require cost-of-supply studies. This Court concluded that NERSA’s
2024/2025 methodology did not require a cost- of-supply study, and
consequently, the methodology was unlawful. The judgment is
Afriforum
NPC v National Energy Regulator of South Africa (“AfriForum v
NERSA”)
.
[2]
It is in this order that AfriForum requests the Court to execute
pending an appeal.
[6]
This Court’s order in
AfriForum
v NERSA
was not the first time NERSA’s methodology has been declared
unlawful. In
Nelson
Mandela Bay Business Chambers NPC and Another v National Energy
Regulator and Others
,
[3]
NERSA’s methodology for the financial years of 2021/2022 and
2022/2023 was declared unlawful. The order of invalidity was
suspended for a year to provide NERSA a grace period to get its house
in order. This means this Court has in
Nelson
Mandela Bay
in 2022 and again in
AfriForum
v NERSA
in 2024 declared NERSA’s methodology unlawful.
[7]
It is in this context, after two successful challenges to NERSA’s
methodology,
in
Nelson Mandela Bay
and
AfriForum v NERSA
,
that Afriforum now approaches the Court seeking interim execution of
the order pending the appeal. Afriforum wants to stop NERSA
and the
municipalities from imposing unlawful tariffs on end-users for yet
another financial year. AfriForum submits that if this
Court does not
grant the interim execution, then there will be no end to NERSA
employing an unlawful methodology. The harm to the
public is that
they will continue to pay inflated and unlawful tariffs not based on
the actual cost of supply of electricity.
[8]
Afriforum points to a perpetuation of unlawfulness by NERSA, year
after year. The
difficulty is that a successful challenge to the
methodology is, according to NERSA, overtaken by its subsequent
tariff decisions.
Take the matter before this Court as an example;
the matter was argued in the last week of June 2024 in relation to
NERSA's methodology
for determining tariffs for the 2024/2025
financial year. The order declaring the methodology unlawful was
handed down on 28 June
2024, two days after the hearing of the
matter. However, during the week the matter was heard, NERSA was
considering and approving
new tariff increase applications for the
2024/2025 financial year. NERSA contends that its tariff decisions
for 2024/2025 overtake
the challenge to its methodology –
rendering the court order moot. NERSA pleads that the order of this
Court "will not
regulate the next tariff approval cycle".
[4]
NERSA contends that if a party wishes to challenge the tariffs, they
must bring a formal review of the tariff decisions.
[9]
AfriForum points out that NERSA makes this argument, knowing that
such a review of
the tariff decisions cannot be finalised before the
next financial year, at which stage NERSA will announce the new
tariffs again.
AfriForum submits that if there is no interim
execution, it means that despite a successful challenge to the
methodology, consumers
will continue to pay inflated and unlawful
tariffs, year after year, with NERSA yearly blocking any challenge to
its unlawful methodology
by relying on mootness.
[10]
AfriForum is concerned that NERSA and the municipalities will
continue to charge inflated and
unlawful tariffs and that they will
continue to escape accountability for this unlawful conduct.
Afriforum's concern has a historical
basis, as this is what NERSA has
now done
twice
against judgments that its methodology is unlawful. In
Nelson
Mandela Bay
,
NERSA argued that before Kubushi J in relation to the 2021/2022 and
2022/2023 financial years, the issue had become moot. Her
Ladyship
Justice Kubushi recorded NERSA's submission in the judgment as
follows: "The submission made by NERSA is that serious
material
events have overtaken the relief which the applicants are seeking in
these proceedings."
[5]
The
material events before Justice Kubushi were that NERSA had made a new
tariff decision for the next financial year. Now, for
the second
time, for this financial year 2024/2025, NERSA again submits that
this Court’s order in
AfriForum
v NERSA
- declaring NERSA’s methodology unlawful in June 2024 - was
overtaken by NERSA 2024/2025 tariff decisions.
[11]
AfriForum’s case is the use of an unlawful methodology will
persist – and whilst
NERSA keeps applying an unlawful method
and then raising the subsequent tariff determination as a mootness
argument – end-users
will pay unlawful tariffs for forever
long. To break this never-ending cycle of unlawfulness, AfriForum
requests the Court to grant
interim execution. AfriForum contends
that bar such interim execution, there will be no other way to stop
NERSA from applying a
method that is unlawful.
[12]
Having set out the motivation for the application, I consider the
legal requirements for the
relief AfriForum seeks.
Statutory
framework
[13]
An appeal of a final order suspends the operation of the order. As
the appeal may change the
outcome, the immediate execution of the
order has the potential to cause enormous harm to a party that may
ultimately be successful.
[6]
A
clear example is when a court ordered the execution of an eviction
order pending its appeal.
[7]
The
practical effect is that the occupiers were subject to eviction and
the irreparable harm that would cause – despite the
fact that
they might overturn their eviction on appeal. To prevent harm to a
party that might be successful on appeal, the general
rule is that an
appeal suspends the operation of the order.
[14]
At common law, unless the Court, in the exercise of a discretion,
ordered otherwise, an application
for leave to appeal and an appeal
pursuant to leave being granted suspended the operation of the
order.
[8]
It was not open to the
successful party to execute on, or otherwise act pursuant to, that
order.
[9]
This common law rule
and the power to grant an execution order is now expressly embodied
in s 18(1), read with
s 18(3)
, of the
Superior Courts Act 10 of 2013
.
[15]
The grant of leave to execute is constrained by the requirements that
it may only be granted
if there are exceptional circumstances if the
applicant will suffer irreparable harm if it is not granted, and if
the grant will
not cause the respondent to suffer irreparable harm. A
further safeguard against the risk of harm being caused by an
execution
order is the automatic right to an urgent appeal given by
s
18(4).
Pending such an appeal, the statute expressly provides in
s
18(4)(iv)
that the operation of the suspension order is itself
suspended.
[10]
[16]
The first jurisdictional fact to be proven by an applicant seeking
interim execution is the existence
of exceptional circumstances.
Courts have always eschewed any attempt to lay down a general rule as
to what constitutes exceptional
circumstances.
[11]
The reason is that the enquiry is factual. There is a helpful summary
in the
MV
Ais Mamas
[12]
that has been endorsed by the Supreme Court of Appeal
[13]
and the Constitutional Court.
[14]
In the context of
s 18(3)
, the exceptional circumstances must be
something that is sufficiently out of the ordinary and of an unusual
nature to warrant a
departure from the ordinary rule that the effect
of an application for leave to appeal or an appeal is to suspend the
operation
of the judgment appealed from. It is a deviation from the
norm.
[15]
The exceptional
circumstances must arise from the facts and circumstances of the
particular case.
[17]
Furthermore,
section 18(3)
requires the applicant for an execution
order to establish that the respondent will not suffer irreparable
harm if the order is
granted and the absence of harm to the
respondent. The law does not require a balancing exercise.
[16]
Instead, the requirements of irreparable harm to the applicant and no
irreparable harm to the respondent, unlike the common law
position,
do not involve a balancing exercise between the two but must both be
established on a balance of probabilities. If the
applicant cannot
show that the respondent will not suffer irreparable harm by the
grant of the execution order, that is fatal.
It is unnecessary to
decide whether, in those circumstances, the Court would be empowered
to grant other relief pending the hearing
of the appeal in order to
protect the applicant's position.
[18]
Our courts have also indicated that discretion is retained after
considering the specific statutory
requirements. In
Justice
Alliance
[17]
it was held that the Court has a broad discretion to grant or refuse
an execution order once the statutory requirements are satisfied
and
that prospects of success in the appeal have a role to play in
considering the exercise of that discretion. Similar dicta appear
in
UFS v
Afriforum
[18]
and
Ntlemeza
[19]
- though in these cases, the record in the main appeal was not before
this Court, and the appeals had perforce to be decided without
the
full record or any consideration of the merits of the main appeals.
[19]
The most recent authority by an appellate Court is that of the
Supreme Court of Appeal in
Tyte
Security Services CC v Western Cape Provincial Government and Others
(“Tyte”)
.
[20]
In
Tyte
,
the Supreme Court of Appeal recognised two elements that had not
previously been emphasised concerning
Rule 18(3)
applications.
[20]
The first is that exceptional circumstances become an overarching
requirement and that the factors
to be considered, the absence of
irreparable harm to the respondents and the presence of irreparable
harm to the applicants, are
not sealed off from each other and not be
considered as hermeneutically sealed. The issue which the Supreme
Court of Appeal was
called on to consider was whether the applicant
for an execution order has to establish three separate, distinct and
self-standing
requirements, namely:
first
,
exceptional circumstances;
second
,
that it will suffer irreparable harm if the order is not made; and,
third
,
the party against whom the order is made will not suffer irreparable
harm if the order is made.
[21]
[21]
The Supreme Court of Appeal held –
“
Even accepting
that the legislature has employed the words 'in addition [to
exceptional circumstances] proves on a balance of probabilities'
in
s
18(3)
, it would be passing strange that if an applicant comes short
in respect of either the second or third requirements it would
nonetheless
still be able to successfully meet the exceptional
circumstances threshold. The use of the words 'in addition proves' in
s 18(3)
ought not to be construed as necessarily enjoining a court to
undertake a further or additional enquiry. The overarching enquiry
is
whether or not exceptional circumstances subsist. To that end, the
presence or absence of irreparable harm, as the case may
be, may well
be subsumed under the overarching exceptional circumstances enquiry.
As long as a court is alive to the duty cast
upon it by the
legislature to enquire into, and satisfy itself in respect of
exceptional circumstances, as also, irreparable harm,
it does not
have to do so in a formulaic or hierarchical fashion.”
[22]
[22]
The second is that the applicant bears the onus to prove the
jurisdictional facts of
section 18(3)
on a balance of probabilities;
there may be instances where the respondents attract something akin
to an evidentiary burden. The
Court must, when considering the
jurisdictional facts, consider that –
“
The enquiry into
each can thus hardly be mutually exclusive, particularly because as
far as the
third
is concerned, unlike the
second
,
the onus cast upon an applicant would be to prove a negative, in
accordance with the usual civil standard. This suggests that,
as with
the exceptional circumstances enquiry, a court considering both the
second
and
third
must have regard to all of the facts and circumstances in any
particular case. Insofar as the
third
goes, although
s 18(3)
casts the onus (which does not shift) upon an
applicant, a respondent may well attract something in the nature of
an evidentiary
burden. This would be especially so where the facts
relevant to the
third
are peculiarly within the knowledge of the respondent. In that event,
it will perhaps fall to the respondent to raise those facts
in an
answering affidavit to the
s 18
application, which may invite a
response from the applicant by way of a replying affidavit.”
[23]
[23]
It is within this statutory framework that the application must be
considered. The starting point
is whether the applicant has proven
exceptional circumstances on a balance of probabilities.
Exceptional
circumstances
AfriForum’s
case
[24]
AfriForum submits that neither SALGA nor NERSA has taken issue with
the declaration of unlawfulness
in their applications for leave to
appeal. AFriForum submits that exceptional circumstances allow for
execution if the appeal does
not go to the heart of the order
appealed against. The limited scope of the leave to appeal itself
constitutes an exceptional circumstance.
This further indicates that
the unlawfulness of NERSA's methodology is not truly in dispute.
[25]
AfriForum further submits that a conservative estimate is that an
appeal will be heard in the
second half of 2025, after the start of
the 2025/2026 financial year. If the order is suspended, the public
will remain remediless,
and NERSA and those municipalities that did
not conduct and support their applications for the 2024/2025
financial year with the
cost of supply studies will have escaped the
consequences of unlawful conduct to the detriment of the public.
[26]
AfriForum submits that it will be exceptional if a party acting in
the public interest, who takes
action to prevent illegality from
continuing, is left remediless in the present circumstances.
[27]
Afriforum submits that the impact of a refusal of execution means
that by the time the appeal
is heard, the horse would have bolted –
and NERSA and the guilty municipalities will escape accountability in
a way that
is detrimental to the public. Afriforum contends that it
is extremely exceptional if a party acting in the public interest
takes
timeous and urgent actions to stop illegality – but, due
to an appeal process, is deprived of an effective remedy, year after
year, particularly where there is no real dispute regarding the
unlawfulness.
NASA's
case
[28]
NERSA denies that AfriForum has proven exceptional circumstances.
[29]
NERSA contends that AfriForum has ignored that exceptional
circumstances are a fact-based inquiry,
and the second is that
prospects of success are a relevant consideration in the Court's
determination of the existence of exceptionality.
These two factors,
namely NERSA, have been neglected by AfriForum, as they present an
insurmountable difficulty in AfriForum’s
case.
[30]
NERSA submits that
Tyte
did not establish a new legal
principle – and that AfriForum must still prove on a balance of
probabilities:
first
, exceptional circumstances;
second
,
that it will suffer irreparable harm if the order is not made; and,
third
, the party against whom the order is made will not
suffer irreparable harm if the order is made. This emphasises that
NERSA is
a fact-based inquiry. NERSA submits that AfriForum has
failed to make out such a fact-based case.
[31]
NERSA referred the Court to
Ntlemeza
v Helen Suzman Foundation and Another
[24]
specifically, paragraph 35, which held that
section 18
(1) entitles a
court to order otherwise 'under exceptional circumstances'.
Section
18(3)
provides a further controlling measure, namely, a party seeking
an order in terms of
s 18(1)
is required 'in addition' to prove on a
balance of probabilities that he or she will suffer irreparable harm
if the Court does
not so order
and
that the other party will not suffer irreparable harm if the Court so
orders.
[32]
NERSA submits this must be considered with
Tyte
, which held –
“
It is important to
recognise that the existence of ‘exceptional circumstances’
is a necessary prerequisite for the exercise
of the Court's
discretion under
s 18.
If the circumstances are not truly
exceptional, that is the end of the matter. The application must fail
and falls to be dismissed.
If, however, exceptional circumstances are
found to be present, it would not follow, without more, that the
application must succeed.”
[25]
[33]
Read together; this means that if a party has not proven exceptional
circumstances, they do not
even get in the door of
section 18(3).
NERSA points to Afriforum's founding affidavit, which has specific
headings addressing prospects of success, irreparable harm and
the
absence of irreparable harm to the respondents – but no heading
dealing with exceptional circumstances. This submits
NERSA, is fatal
to AfriForum’s case. Without establishing exceptional
circumstances – AfriForum cannot request the
Court to grant
execution as the first jurisdictional fact is absent. NERSA submits
that
Tyte
did not disturb this legal principle.
SALGA’s
case
[34]
SALGA contends that AfriForum has not proved that exceptional
circumstances exist to justify
a departure from the general rule. An
analysis of AfriForum’s founding affidavit shows that AfriForum
relies on ordinary
factors in its attempt to make out a case in which
exceptional circumstances exist to justify the relief it seeks.
[35]
SALGA accepts that in its application for leave to appeal, SALGA does
not contest the declaration
of invalidity granted by this Court. The
fact that SALGA does not contest the declaration of invalidity has
been SALGA's position
even during the hearing of the main
application. This factor is not unusual considering the position
adopted by SALGA in this litigation.
Accordingly, it does not
constitute an exceptional circumstance for the purposes of
section
18(1)
of the
Superior Courts Act.
The
finding of exceptional circumstances
[36]
Exceptional circumstances are a necessary prerequisite for the
exercise of the Court's discretion.
If the circumstances are not
truly exceptional, it is the end of the matter. If the circumstances
are exceptional, it does not
follow without more that the application
must succeed.9
[37]
The bar is high, as AfriForum has to prove there is “something
markedly unusual or specially
different about this case”. The
Supreme Court of Appeal in
Ntlemeza
stated that ‘the
legislature has set the bar fairly high’. Therefore, a heavy
onus is placed on the applicant.
[38]
The Court considers the facts of this case in light of the onus. It
weighs with the Court that
consumers have been overpaying for a long
time and that tariffs are increasingly unaffordable. This fact was
not disputed before
Kubushi J in Nelson Mandela Bay and similarly was
not disputed before this Court in
Afriforum v NERSA
.
[39]
The Court also considers that the tariffs paid for electricity affect
every household and every
business in this country. If it is
unaffordable, as is the common cause before this Court, it affects
the ability of people to
access the host of amenities electricity
affords them, from having light to study with to being able to cook
food and stay warm.
Electricity provides ways in which people can
exercise other rights. If it is unaffordable, it affects the ability
to exercise
a variety of fundamental rights. In addition, the
financial viability of businesses is affected by the price of
electricity, particularly
small businesses. There is little to
gainsay that the tariffs paid for electricity – which is at the
heart of this application
– have a massive effect on homes and
businesses throughout the country. The number of people affected by
this application
itself indicates that exceptional circumstances
exist.
[40]
It weighs with the Court that this is not the first time NERSA’s
methodology has been declared
unlawful. In addition, NERSA has been
given an opportunity to address the unlawfulness of its methodology
in a previous judgment.
Yet, it has not done so despite being
provided more than a year to do so. This also evidences exceptional
circumstances.
[41]
It also weighs with the Court that NERSA has now twice used the same
excuse to avoid the impact
of such a finding. Before Her Ladyship
Kubushi J and in this matter, NERSA claimed mootness. It also appears
to the Court that
what renders the case exceptional is the unending
cycle of consumers paying unlawful tariffs, year-after-year –
with its
custodian claiming mootness repeatedly.
[42]
SALGA submits that the unlawfulness of conduct is not in and of
itself sufficient to ground exceptional
circumstances. In fact,
submits SALGA, it is par for the course that an unlawful act is
permitted to continue pending an appeal
as the default position is
that an appeal suspends the operation of the order – as the
unlawfulness yields to other considerations
of legal certainty and
the prevention of harm.
[43]
The argument is sound but does not hold where the unlawfulness renews
yearly and has been ongoing
for close to two decades, particularly in
circumstances where the national custodian – NERSA - has failed
in its task to
act as a regulator and has instead bent to permit
unlawfulness to continue. The unlawfulness, in this case, is not
once-off, nor
did it abate when the Court declared it so: rather,
NERSA’s conduct is not only unlawful but it is repeated,
persistent and
continuous.
[44]
In addition, the appeal is not aimed at the finding of unlawfulness –
and so the parties
do not seek to disturb the finding of
unlawfulness. The limited scope of the appeal weighs with the Court
as an exceptional circumstance.
Here, NERSA’s reliance on
mootness requires consideration. The defence, even if accepted, is
not the end of the matter. Both
Her Ladyship Kubushi J
[26]
and this Court
[27]
held that
even if the matter is moot – that is not the end, as moot
matters are often considered if they raise important
public interest
considerations – which are at play in this case.
[45]
The Court finds that exceptional circumstances do arise in this case
and considers whether AfriForum
has proven irreparable harm to the
public.
Irreparable
harm to the public
AfriForum’s
case
[46]
Afriforum submits that if interim relief is not granted, the public
will suffer irreparable harm.
Currently, tariff increases are being
granted on the basis of an unlawful methodology. All accept that the
tariffs being charged
this year are higher than the tariffs being
charged last year. AfriForum submits that the unlawful tariffs which
the public has
been paying for the five months since the judgment was
handed down and the unlawful tariffs they will be paying for the next
seven
months constitute harm. There can be no doubt about this. The
question AfriForum asks is if this harm is irreparable.
[47]
AfriForum contends that in the face of neither SALGA nor the
municipalities being able to give
an assurance that they will be able
to refund the public if the appeal fails, the public will suffer
irreparable harm if the order
continues to be suspended.
[48]
AfriForum explains that its impetus for approaching the Court is what
SALGA told the Supreme
Court of Appeal in its application for special
leave. SALGA pleaded in its bid for leave to appeal that if the High
Court orders
are not set aside, then –
“
a question is
going to arise as to whether the municipalities must reverse those
charges and if so, how that reversal must happen
considering the
large number of municipal electricity consumers and the
practicalities of doing that”.
[49]
AfriForum submits that SALGA offers no solution to this problem, nor
does it say what the possible
solutions may be. AfriForum contends
that the only reasonable inference is that neither SALGA nor the
municipalities are able to
give the Court or the end- users of
electricity the assurance that, should they continue to charge and
collect higher rates if
the High Court order eventually stands, they
will be able to reimburse the end-users. This clearly demonstrates an
essential reason
why the High Court order should be executed. Had
there been a solution – then the municipalities would have told
SALGA of
the solution, and it would have told this Court.
[50]
The inability to ensure that end-users will be refunded is clear
evidence of irreparable harm
to be suffered by the end-users, being
“the very public for whom AfriForum has fought throughout these
proceedings”.
[28]
[51]
To this should be added the irreparable harm in the form of failed
businesses and industries,
including small industries that will not
survive due to these inflated tariffs, on top of which NERSA has now
allowed a further
12% increase. Moreover, AfriForum pleads that many
electricity users buy prepaid electricity, most of them are poor.
There is simply
no way that municipalities can reimburse them.
[29]
[52]
Afriforum submits there are five specific reasons why the harm to the
public is irreparable.
First
, none of the actual
municipalities have entered the fray and said that they can refund
members of the public and, if they can –
how they intend to do
so.
Second
, NERSA has not provided any counter to the
allegation that the harm to the public is irreparable, and it has not
even attempted
to do so.
Third
, SALGA comes to the defence of
the Municipalities, but what it said in the application for special
leave in the Supreme Court of
Appeal is that a question is going to
arise: How can it reverse any payments in light of the large number
of municipalities and
the practicalities? SALGA has not provided an
answer to this question. Now, in this Court, in opposition to
section
18(3)
, SALGA contends that they can pay the monies back. However,
SALGA does not go on to explain how to "consider the large
number
of municipalities involved and the practicalities thereof”.
[53]
Fourth
, Afriforum posts a scenario. If one were to assume that
Municipalities have the intention to pay back, how would they do so?
There
will have been some form of a refund or a credit to those who
were charged and paid unlawful tariffs. The issue is where the funds
to pay back this money will come from: not from the officials'
pockets, not from NERSA, and not from SALGA. The money comes from
the
same people from whom it was taken in the first place - the
end-users. A municipality will be able to rectify it in the next
financial year through the provision of a cost of supply study where
a municipality can play open cards that it had unlawfully
collected
tariffs and now must pay back those tariffs that had nothing to do
with the cost of electricity. A municipality can also
budget for such
a refund or credit. Regardless, either way, the money is being
collected from the same people who overpaid for
electricity in the
first place. To abuse an idiom: it is robbing Peter to pay Peter.
[54]
Fifth
, in the face of SALGA’s case that the
Municipalities are about to fail and therefore a just and equitable
remedy would be
to suspend the operation of invalidity for another
financial year, the question then arises – how will these
failing municipalities
pay back unlawful tariffs?
[55]
These five points, submit AfriForum, indicate exceptional
circumstances and evidence of irreparable
harm to the public.
[56]
AfriForum compares its position to that of the applicant in
Tyte
,
in respect of which the Supreme Court of Appeal said: “Inasmuch
as the second contract is due to terminate in June 2025,
there is
every prospect that, by the time the appeal comes to be heard, and
irrespective of the outcome, Royal will be left remediless.”
[30]
As the applicant in
Tyte
could not get a remedy, a delay in its remedy meant it was no longer
effective; similarly, the public would be left remediless
due to an
effluxion of time.
NASA's
case
[57]
NERSA submits that AfriForum has not produced any evidence of
irreparable harm to the people
which it represents. AfriForum simply
complains, in general terms, about inflated tariffs without producing
evidence of how such
tariffs will cause irreparable harm. The correct
position is that if the applications for leave to appeal are
dismissed, the relevant
electricity customers will have a remedy
against the relevant municipalities to recover the alleged inflated
amounts. No case has
been made by AfriForum as to why the people it
represents cannot be refunded the alleged inflated amounts. In
addition, no case
has been made by AfriForum to prove that the
relevant municipalities will never have the requisite financial
wherewithal to refund
the affected customers the alleged inflated
amounts.
[58]
NERSA’s position is that the approved tariffs, in terms of the
2024/2025 tariff decisions,
have not been impugned in review
proceedings. In such review proceedings, the Court can grant a just
and equitable remedy if the
tariffs are found to be unlawful. The
harm, if any exists, is not irreparable.
[31]
SALGA’s
case
[59]
SALGA has pleaded that –
“
if SALGA and NERSA
are not successful on appeal in due course, and municipalities have
charged their electricity customers unlawful
tariffs, and
municipalities are ordered to refund them the difference,
municipalities will have to refund them”.
[60]
The pleaded position from SALGA is that if there has been an
overcharge – then the municipalities
must credit or refund the
consumers.
[61]
There is no suggestion in AfriForum’s founding affidavit that
the affected municipalities
will not have the financial wherewithal
to refund such difference.
[32]
Irreparable harm is harm for which there is no remedy. In this case,
the remedy is a refund, and no case has been made to
suggest that the
affected municipalities will not be able to make the necessary
refunds.
[33]
[62]
SALGA refers to an announcement from AfriForum on 22 August 2024 in
which it calls on the public
to claim back monies from the
municipalities for the unlawful tariffs. Before SALGA relied on this
document, the Court ascertained
that there was no objection to any
party to SALGA being granted leave to hand up a document. SALGA's
submission is that there is
a remedy – to claim back monies
from the Municipalities – and that AfriForum is aware of this
remedy and that it is
available to the public. SALGA submits this
document to prove that AfriForum is aware that there is the
possibility to claim back
any overpayment.
Finding
that the applicant has not proven irreparable harm to the public
[63]
In
Afriforum
[34]
The Constitutional Court stated that the harm that must be
established is some "discernable or intelligible disadvantage or
peril that is capable of legal protection” and that it is “the
tangible or intangible effect of deprivation or adverse
action taken
against someone.” The Court continued:
"Irreparable implies
that the effects or consequences cannot be reversed or undone.
Irreparable therefore highlights the irreversibility
or permanency of
the injury or harm. That would mean that a favourable outcome by the
Court reviewing allegedly objectionable conduct
cannot make an order
that would effectively undo the harm that would ensue should the
interim order not be granted."
[35]
[64]
Harm becomes irreparable if, through suffering the delay of the law,
the successful litigant
loses the fruit of their litigation. This is
called "irreparable" damage, meaning that money obtained at
trial may not
compensate for the harm.”
[36]
If damages – or some other relief – provide adequate
compensation and the respondent is in a position to pay them,
then
ordinarily, the harm will not be irreparable.
[65]
AfriForum bears the onus to prove the absence of a remedy. It relies
mainly on SALGA's open-ended
question to the Supreme Court of Appeal
in the application for leave to appeal, where SALGA indicates that a
question of a remedy
will arise. The statement by SALGA to the
Supreme Court of Appeal is not a concession that there will be no
remedies. It merely
states that the question will arise – which
it most certainly will. A party indicating that litigation will raise
a question
of remedy does not mean that they have conceded that the
remedy does not exist.
[66]
In any event, SALGA has answered the question in this Court:
Consumers will be credited or refunded.
The answer appears in more
than one place in the answering affidavit and submissions and was
made again in open Court.
[67]
The Court considers that SALGA has pleaded that it will remedy the
unlawfulness - if the appeal
is upheld. Specifically, in paragraphs
2.25 of its answering affidavit, SALGA said:
"2.25 If SALGA and
NERSA are not successful on appeal in due course, and municipalities
have charged their electricity customers
unlawful tariffs, and
municipalities are ordered to refund them the difference,
municipalities will have to refund them. There
is no suggestion in
AfriForum’s founding affidavit that the affected municipalities
will not have the necessary financial
wherewithal to refund such
difference.”
[68]
In addition, SALGA has pleaded that it is not correct that “the
public will remain remediless.”
The correct position is simply
that if the application for leave to appeal or an appeal is not
successful, the relevant municipalities
will have to credit their
customers or refund their customers who are now being charged
increased electricity tariffs as provided
for in their 2024/2025
financial year budgets.
[69]
SALGA has stated unequivocally that relevant customers could be
refunded, or their customers'
accounts could be credited with the
difference between what they are paying now and what the appeal Court
will say they should
have been paying. Based on this fact, the
contention that the harm will not be remedied cannot be sustained.
[70]
For as long as it is not suggested that the affected municipalities
will not be able to make
such refunds as they may be ordered to make,
there is no factual basis for this Court to conclude that any person
is going to suffer
irreparable harm if leave to execute is not
granted. SALGA has identified the specific remedy, which is a refund,
and no case has
been made to suggest that the affected municipalities
will not be able to make the necessary refunds.
[71]
SALGA has furthermore identified the means of achieving this remedy
being through the crediting
their electricity accounts. Accordingly,
SALGA has contradicted AfriForum’s case that the harm to the
public is irreparable.
[72]
The Court also accepts NERSA’s argument that a review of the
tariff-decisions, if such
a case is launched, allows for just and
equitable relief. Notionally, relief exists for the harm which the
public is suffering.
[73]
On this basis, the Court finds that AfriForum has not been able to
prove that the harm is irreparable
in these circumstances.
[74]
The absence of irreparable harm, means that AfriForum has not met its
onus and that the matter
is to be dismissed on this basis alone. The
Court however notes the importance of a full set of reasons and
following a belt-and-braces
approach addresses the remaining
considerations.
Absence
of irreparable harm to respondents
AfriForum’s
case
[75]
AfriForum then addresses the absence of irreparable harm to the
respondents. AfriForum submits
that they will not suffer any harm at
all – let alone irreparable. AfriForum submits that there is a
clear and logical link
between the irreparable harm suffered by the
public and the fact that the municipalities will suffer no harm. If
there is a shortfall,
then municipalities can make good for it in the
next budget. However, they will have to do this lawfully based on
cost-of-supply
studies.
[76]
AfriForum pleads that NERSA and SALGA have not specified what harm
they will suffer – save
for NERSA having to pay SALGA’s
costs. AfriForum pleads that there can be no such harm. If the order
is given effect, if
municipalities charge the lower rates as it
should and if the municipalities have a shortfall at the end of the
financial year
(which is not an inevitability), first, it will be of
their own doing, second, they will have to account to all as to the
reasons
why they find themselves in that situation (which favours
constitutional accountability) and, third, municipalities will be
able
to rectify the situation in the following year’s budget.
As such, they will not suffer irreparable harm – even if there
is a shortfall.
[77]
This submission must be seen in the context of two courts having
found that municipalities have
been charging inflated electricity
tariffs for years. And neither SALGA nor NERSA have taken issue with
this allegation.
[78]
AfriForum then relies on the findings of
Tyte
to submit that
this is the type of case where evidence which falls under
personal/exclusive knowledge of the Municipalities or
the respondents
creates an evidentiary burden to show they will suffer irreparable
harm if the order is not suspended.
[79]
AfriForum accepts it bears the overall onus of proof but submits that
this is a case where the
respondents attracted an evidentiary burden
to provide the Court with proof that in the event of the applications
for leave to
appeal failing, they have the intention to and the means
to refund the public and the manner in which this will be done. They
have
not done so. NERSA has not attempted to do so. SALGA has not
demonstrated such harm.
SALGA’s
case
[80]
SALGA submits that as the applicant bears the onus of proof, it was
under an obligation to provide
evidence in relation to every
municipality to show the absence of irreparable harm.
[81]
SALGA has pleaded that the conclusion that the respondents will not
suffer irreparable harm can
only be made if the impact of the order
sought upon each of them has been assessed. AfriForum has not
conducted any such assessment
and cannot state, as a fact, that the
respondents will not suffer irreparable harm if the order is in
operation and executed.
[82]
SALGA rejects it has attracted an evidentiary burden to show it, or
the municipalities will suffer
irreparable harm. SALGA contends that
to impose an evidentiary burden on it would be akin to reversing
Plascon-Evans
. As these are motion proceedings in which SALGA
is a respondent, they ought not to attract an onus.
[83]
SALGA pleads that AfriForum, not SALGA, must “investigate the
financial position of all
the affected municipalities and then
produce evidence that leave to execute will not result in irreparable
harm to such municipalities.”
[37]
AfriForum, as it bears the onus, should have obtained "the
necessary evidence from the affected municipalities, their customers
and Eskom, to prove, on a balance of probabilities, that leave to
execute will not cause them irreparable harm.
[38]
[84]
SALGA pleads that this would include an assessment of: the cost at
which the respondent municipalities
procure bulk electricity from
Eskom; network operating costs; retail operating costs; expenses
relevant to the supply of electricity
to customers; sales forecasts;
the rate at which the respondents charge their electricity customers
for electricity supplied to
them; whether the rate at which the
respondents charge their electricity customers enables them to
recover the cost at which they
procure bulk electricity from Eskom;
the respondent municipalities’ financial ability to service
their Eskom current account
with what they charge their electricity
customers and what they have projected to recover from such
customers; the impact of the
respondent municipalities not being able
to service their Eskom current account on their ability to provide
other services for
which they are constitutionally obliged to provide
and the consequences of the respondent municipalities not being able
to provide
other services, which they are in law required to provide,
as a result of them not being able to recover the full costs at which
they procure bulk electricity from Eskom.
[39]
[85]
SALGA submits that one of the orders granted by the Court is that
municipalities must charge
their electricity consumers in accordance
with their 2023/2-24 tariffs. These tariffs do not allow
municipalities to recover the
full amount that they paid to Eskom for
the procurement of bulk electricity at Eskom's 2024/2025 tariffs
because they were not
designed to do so.
Section 15
of the ERA
entitles Municipalities to recover their full costs of supplying
electricity to their customers together with a reasonable
margin.
[86]
SALGA rejected that it had attracted an evidentiary burden –
and submitted that even if
it had – it had, it had met such an
onus.
NASA's
case
[87]
NERSA's case on irreparable harm broadly accorded with SALGA's
opposition. The actual dispute
on this front is between SALGA and
AfriForum.
Absence
of irreparable harm for the respondents
[88]
The Court accepts Afriforum’s submission that the
municipalities will not suffer harm,
as for years, possibly decades,
the municipalities have been charging inflated tariffs. In addition,
the 2023/2024 financial year’s
tariffs were unlawful, as
Kubushi J permitted the municipalities to charge the unlawful tariffs
whilst they get their houses in
order. In addition, the
Municipalities have been charging unlawful tariffs for the past five
months of this financial year 2024/2025.
Even if the Court granted
the 18(3), the municipalities that have not done cost of supply
studies can still charge the inflated
2023/2024 tariffs. There is no
basis presented on which it can be contended that the municipalities
will suffer irreparable harm.
[89]
The Court has considered SALGA's opposition. Essentially, what SALGA
requires from AfriForum
is for each municipality that did not conduct
a cost-of-supply study, to prove that the municipality will not
suffer irreparable
harm. This, submits SALGA must occur despite
AfriForum pointing out to the common cause fact that Municipalities
have been charging
inflated rates for years.
[90]
In addition, not one municipality opposed the 18(3) and none of them
entered the fray in the
application for special leave to the Supreme
Court of Appeal.
[91]
The Court finds in accordance with
Tyte
that the
municipalities attracted, in these circumstances, an evidentiary
burden. The information falls exclusively in the municipalities'
knowledge and AfriForum has provided enough of a case to give rise to
such an evidentiary burden.
[92]
It also weighs with the Court that, unlike in
Tyte
, the
respondents in this case are organs of state and NERSA. They attract
an additional obligation to be transparent with their
customers and
with the Court. NERSA has a specific role as custodian and regulator.
It is not enough for state organs to say AfriForum
must prove facts
which fall within the municipalities' knowledge – in
circumstances where one would expect the municipalities
to play open
cards with the Court.
[93]
In any event, even if the respondents had been able to prove harm,
the Court finds it is not
irreparable. The Court finds nothing to
gainsay AfriForum’s submission that if there is any harm to the
municipalities –
they can make up for such harm in their next
financial year's budget. However, this would have to be done in terms
of a cost-of-
supply study and a lawful determination of electricity
costs. Neither SALGA nor NERSA have indicated that any such losses
could
not be repaired through a budget determination which caters for
it. On the common cause facts – the harm, if any, to be
suffered
by the Municipalities and the respondents before the Court
is reparable.
[94]
In these circumstances, the Court finds that the harm, if any, is
plainly not irreparable.
Discretion
and prospects of success
[95]
Having concluded that the requirements for interim execution has not
been met, the Court declines
the application.
[96]
The Court notes that in Knoop the Court referred to a residual
discretion to grant or refuse
execution – and that at this
stage, the prospects of success must be considered. On the basis that
the Supreme Court of Appeal
has granted leave to appeal, this Court
must accept that another Court has concluded that there are
reasonable prospects of success.
As AfriForum has failed to prove
that the public will suffer irreparable harm, this consideration does
not alter the outcome of
the case.
Costs
[97]
There was no allegation on the papers that AfriForum’s case was
brought vexatiously or
with mala fides. AfriForum has litigated this
matter in pursuance of the public’s interest and seeking to
enforce fundamental
rights. It attracts the protection of the
Bio-Watch
principle and no basis has been provided to deviate
from the principle. In these circumstances there is no order as to
costs.
Order
[98]
The Court orders:
a) The application for
interim execution is dismissed with no order as to costs.
I
de Vos
Acting
Judge of the High Court
Delivered:
This judgment is handed down electronically by uploading it to the
electronic file of this matter on CaseLines. As a
courtesy gesture,
it will be e-mailed to the parties/their legal representatives.
Counsel
for Afriforum:
Etienne Botha
Instructed
by:
Marjorie Van Schalkwyk, Hurter & Spies
Counsel
for NERSA:
Terry Motau, SC
Realeboga Tshetlo
Instructed
by
Prince Mudau & Associates
Counsel
for SALGA:
Kennedy Tsatsawane SC
Kgomotso Kabinde
Instructed
by:
H M Chaane Attorneys
Date
of the hearing:
29 November 2024
Date
of judgment:
5 December 2024
[1]
Afriforum seeks the interim execution of all aspects of the order
except for those dealing with costs (paragraph 8) and with
future
financial years (paragraph 4).
[2]
(2024/061993) [2024] ZAGPPHC 638 (8 July 2024)
[3]
(63393/2021) [2022] ZAGPPHC 778 (20 October 2022)
[4]
NERSA’s AA, para 25
[5]
Kubushi J para 33
[6]
Knoop para 1
[7]
Philani-Ma-Afrika and Others v Mailula and Others [2009] ZASCA 115;
2010 (2) SA 573 (SCA); [2010] 1 All SA 459 (SCA).
[8]
Knoop para 2
[9]
South Cape Corporation (Pty) Ltd v Engineering Management Services
(Pty)
1977 (3) SA 534
(A) (South Cape Corporation) at 544H-545G.
[10]
Knoop para 2
[11]
Knoop para 46
[12]
MV Ais Mamas: Seatrans Maritime v Owners MV Ais Mamas and another
2002 (6) SA 150
(C) at 156E- 157
[13]
Knoop para 46
[14]
Liesching and Others v The State [2018] ZACC 25; 2019 (4) SA 219
(CC)
[15]
University of the Free State v Afriforum and Another (929/2016)
[2016] ZASCA 165
;
[2017] 1 All SA 79
(SCA);
2018 (3) SA 428
(SCA)
(17 November 2016) (“UFS v Afriforum”) para 13
[16]
UFS v Afriforum para 13
[17]
The Minister of Social Development Western Cape & others v
Justice Alliance of South Africa & another
[2016] ZAWCHC 34
paras 26-29
[18]
UFS v Afriforum para 15
[19]
Ntlemeza v Helen Suzman Foundation and Another (402/2017)
[2017]
ZASCA 93
;
[2017] 3 All SA 589
(SCA);
2017 (5) SA 402
(SCA) (9 June
2017)
[20]
(479/2024)
[2024] ZASCA 88
;
2024 (6) SA 175
(SCA) (7 June 2024)
[21]
Tyte para 9
[22]
Tyte para 14
[23]
Tyte para 15
[24]
402/2017)
[2017] ZASCA 93
;
[2017] 3 All SA 589
(SCA);
2017 (5) SA
402
(SCA) (9 June 2017)
[25]
Tyte para 11
[26]
Kubushi J para 33
[27]
South African Local Government Association and Another v Afriforum
NPC (2024-061993) [2024] ZAGPPHC 826 (19 August 2024) at paras
60 -
63
[28]
AfriForum FA para 35
[29]
AfriForum FA paras 36 and 37
[30]
Tyte para 25
[31]
NERSA AA para 29
[32]
SALGA AA para 2.25
[33]
SALGA AA apra 2.27
[34]
City of Tshwane v Afriforum [2016] ZACC 19
[35]
Id para 59
[36]
Hoffmann-La Roche & Co AG and Others v Secretary of State for
Trade and Industry, Lord Wilberforce
[37]
SALGA AA para 2.13
[38]
SALGA AA para 2.14
[39]
SALGA AA para 3.8
sino noindex
make_database footer start
Similar Cases
Afriforum NPC v National Energy Regulator of South Africa and Others (2025/137620) [2025] ZAGPPHC 1305 (4 December 2025)
[2025] ZAGPPHC 1305High Court of South Africa (Gauteng Division, Pretoria)100% similar
Afriforum NPC v National Energy Regulator of South Africa and Others (2024/061993) [2024] ZAGPPHC 638 (8 July 2024)
[2024] ZAGPPHC 638High Court of South Africa (Gauteng Division, Pretoria)100% similar
Afriforum NPC v National Energy Regulator of South Africa and Others (2025/137620) [2025] ZAGPPHC 1176 (31 October 2025)
[2025] ZAGPPHC 1176High Court of South Africa (Gauteng Division, Pretoria)100% similar
Afriforum NPC v City of Tshwane Metropolitan Municipality and Others (2025/090751) [2025] ZAGPPHC 1223 (18 November 2025)
[2025] ZAGPPHC 1223High Court of South Africa (Gauteng Division, Pretoria)100% similar
Afriforum NPC and Others v Van Der Walt and Others (54318/2021) [2024] ZAGPPHC 4 (16 January 2024)
[2024] ZAGPPHC 4High Court of South Africa (Gauteng Division, Pretoria)100% similar