Case Law[2024] ZAGPPHC 1365South Africa
Inyatsi Construction S A Limited v National Department of Public Works and Another (2165/19) [2024] ZAGPPHC 1365 (23 December 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 1365
|
Noteup
|
LawCite
sino index
## Inyatsi Construction S A Limited v National Department of Public Works and Another (2165/19) [2024] ZAGPPHC 1365 (23 December 2024)
Inyatsi Construction S A Limited v National Department of Public Works and Another (2165/19) [2024] ZAGPPHC 1365 (23 December 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_1365.html
sino date 23 December 2024
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
Case no:
2165/19
REPORTABLE:
NO/YES
OF
INTEREST TO OTHER JUDGES: NO/YES
REVISED.
DATE 23/12/2024
SIGNATURE N V KHUMALO J
In
the matter between:
INYATSI
CONSTRUCTION S A LIMITED
Applicant
and
THE
NATIONAL DEPARTMENT OF PUBLIC WORKS
1
ST
Respondent
AND
SOMAMA CONSTRUCTION CC
2
ND
Respondent
This Judgment was handed
down electronically by circulation to the parties’
representatives by email. The date and time of
hand-down is deemed to
be 23 December 2024.
JUDGMENT
N
V KHUMALO J
Introduction
[1]
T
he Applicant in this matter seeks an order
against the 1
st
Respondent,
the National Department of Public Works, for the payment of the
amount of R5,982,785.19 (Five Million Nine Hundred Eighty-two
Thousand, Seven Hundred and Eighty-five Rand and Nineteen Cents),
payable in terms of an issued and certified Final Certificate
Payment
(“FCP”) no 30 dated 9 January 2018, which became due and
payable on 30 January 2018, together with the contractual
default
interest rate applicable as determined by the Minister of Finance.
The
Parties
[2]
The Applicant is In
yatsi Construction (South
Africa) Ltd, a company duly incorporated in accordance with the
company laws of South Africa. The 1
st
Respondent is the National Department of Public Works, Eastern Cape,
a national department as contemplated in terms of Schedule
1 of the
Public Service Act 1994 (Proclamation 103 of 1994) read with section
239 of the Constitution 108 of 1996 (“the Constitution”).
[3]
The 2
nd
Respondent is Somama Construction CC, a close corporation duly
incorporated in accordance with the laws of South Africa. The
Applicant
and 2
nd
Respondent are a Joint Venture which came into being pursuant to a
written agreement concluded between them on 2 September 2011
and
amended on 8 February 2012. Therefore, for the purposes of this
Application, the Applicant and the 2
nd
Respondent will be together referred to as the “Joint Venture
”.
Background
Facts
[4]
The Applicant is, on behalf of the Joint Venture, seeking an order
against the 1
st
Respondent for the payment of the amount
in the Final Payment Certificate.
[
5
]
On 8 November 2011, the 1
st
Respondent awarded a tender to the Joint Venture under tender no:
046573 and contract no: MTUNMU/1 with reference no: 19/2/4/2/2/6958
concluded between the parties (that is the Joint Venture and the 1
st
Respondent) in respect of a heritage upgrade of the Nelson Mandela
Museum project. The initial sum of the contract was set at an
approximate value of R32 347 824.72 (Thirty-Two Million Three Hundred
and Forty-Seven Thousand Eight Hundred and Twenty-Four Rand
and
Seventy-Two Cents), inclusive of 14 % Vat subject to adjustment.
[6]
The agreement comprised of several documents to the tender, inter
alia, the Notice and Invitation
to Tender, Letter of Acceptance,
Offer and Acceptance and the contract data JBCC Principal Building
Agreement (Edition 4.1 March
2005) the JBCC Series 2000 which
governed and formed the basis of the contract. The
JBCC
Principal Agreement comprised of inter alia, the following
t
erms:
1.
The JBCC principal building agreement would be applicable to the
contract between the Joint Venture and
the 1
st
Respondent;
2. The Principal
Agent appointed to act as an agent of the First Respondent is
Impendulo Architects (Pty) Ltd;
3. The initial
contract price sum was R 32,347,824.72 (Thirty-Two Million Three
Hundred and Forty-Seven Thousand Eight Hundred
and Twenty-Four Rand
Seventy-Two Cents) inclusive of 14% VAT subject to adjustments per
what was reflected on the works order,
and the Bills of Quantities
Document;
4. The Joint
Venture was appointed to construct the upgrade of the Nelson Mandela
Museum situated at the corner of Nelson
Mandela Drive and Owen Street
Mthatha;
5. Clause 34.0 of
the JBCC as amended by the state clause and the contract regulated
the final account payment thereof together
with interests thereon as
provided in the annexures;
6.
The Principal Agent would issue the Final Payment Certificate within
7 (seven) calendar days of being
advised that the final account has
been accepted, though not before the issue of the Certificate of
Final Completion.
7.
The 1
st
Respondent would pay the Joint Venture the amount
certified in the Final Payment Certificate within 21 days of the date
of issue
of the Final Payment Certificate.
[7]
The Joint Venture commenced with the construction work on 8 November
2011, which was the commencement
date in accordance with the
contract, and duly complied with all its obligations as they arose
from the terms of the project.
[8]
On 5 December 2014, Impendulo Architectures (Pty) Ltd (“the Principal
Agent”)
furnished the Joint Venture with the Certificate of
Practical Completion.
[9]
The Joint Venture received the Certificate of Works Completion from
the Principal Agent on 8 February
2016. On 24 May 2017 the
Certificate of Final Completion was received from the Principal
Agent.
[10]
The Principal Agent issued a Final Payment Certificate owed to the
Joint Venture in terms of the provisions
of the contract, On 9
January 2018, which is due within 21 calendar days.
[11]
Despite the demand having been made on 3 October 2018, the 1
st
Respondent failed to make payment on the Final Payment Certificate.
In March 2019, the Applicant launched an application on behalf
of the
Joint Venture claiming payment of the issued Final Payment
Certificate. The Applicant was of the opinion that it is entitled
to
pursue legal proceedings on behalf of the Joint venture in terms of
clause 5.4 of the Joint Venture. It cited itself as the
1
st
Applicant and 2
nd
Respondent as the 2
nd
Applicant.
[12]
Clause 5.4 of the Joint Venture reads:
“
It is agreed that
INYATSI will be responsible for the accounting, secretarial, legal
and other administrative work required by the
Joint Venture. A fee of
1.00% of the contract sum will be paid for this service.”
[13]
The 1
st
Respondent did not agree with the interpretation
of clause 5.4, as a result, raised various points in
limine.
One of them included a non-joinder, which led to the Applicant
instituting a joinder application to join Somma as the 2
nd
Respondent and filing a supplementary affidavit. The main Application
was enrolled for hearing on 15 May 2023.
Issues
Arising
[14]
Whether the Final Payment Certificate constitute a debt in terms of
Institution of Legal Proceedings Against
Certain State Organs Act 40
of 2002, or a liquid document?
Legal
framework on Tenders
[15]
An act of issuing tenders by the State in South African law is
regarded as an administrative action,
[1]
however, once the tender is processed, and pursuant to the parties
being awarded the tender, the parties enter into
a
contract which governs their obligations towards one another.
[2]
A contract as such, is an agreement entered into between two or more
parties to create a legal obligation or obligations, and as
a result
it is binding and reciprocal.
[3]
[16]
Hence the court in
Mohabed’s
Leisure Holdings (Pty) Ltd v Southern Sun Hotel Interests (Pty)
Ltd
[4]
highlighted the importance of contractual obligations and stated
that:
“
The
privity and sanctity of contract entails that contractual obligations
must be honoured when the parties have entered into the
contractual
agreement freely and voluntarily. ...
”
[5]
[17]
In essence, the doctrine of the privity and sanctity of contracts
requires that the parties to the contract
honour the obligations of
the contract, as long as the contract is entered into feely and
voluntarily.
[6]
It is only where
a party demonstrates that a contract is prejudicial due to fraud or
unreasonableness that there can be a deviation
from honouring the
terms of the contract.
[7]
[18]
In cases where an agreement is entered into between a contractor in
the building or engineering construction
industries and an employer,
such contract is referred to as a building and engineering contract,
and it is governed by the
Joint Building Contracts Committee
(JBCC) which regulates the relationship between the employer, the
contractor and the Principal
Agent.
[8]
The contract exists where one party called a builder, or a contractor
agrees to build or perform engineering work for another.
[9]
[19]
During the building and engineering contract, the employer appoints
an architect or an engineer who acts
as the employer’s agent
for specific purposes.
[10]
In
terms of the Joint Building Contracts Committee JBCC Series 2000, the
Principal Agent issues payment certificates, these certificates
include amongst others, the Final Payment Certificate which is issued
at the conclusion of work and may be regarded as final certificate
for payment.
[11]
Analysis:
Whether the claim for the settlement of a Final Payment Certificate
constitute a debt in terms of the Institution of Legal
Proceedings
Against Certain Organs of State Act?
[20]
The 1
st
Respondent raises a point in
limine
that
there is the absence of consent to the legal proceedings from its
side, on the ground that the 1
st
Respondent was not
notified about the application in terms of section 3 of the
Institution of Legal Proceedings Against Certain
Organs of State Act
40 of 2002 (the Act), and since this claim constitute a debt, the
application is not properly brought before
the court.
[21]
Furthermore, the 1
st
Respondent submits that the Applicant
did not make any demand in terms of the provision of the Act. The
Applicant only made reference
to an email which referred to clause
31.9 of the main agreement in terms of which the employer is to pay a
contractor within 21
days of the calendar. According to the 1
st
Respondent, the email did not constitute a demand for payment,
therefore in the premises of the aforesaid, the Applicant is not
entitled to relief under this application.
[22]
In terms of the Act debt is defined as:
[12]
“
Any
debts arising from any cause of action-
(a)
which arises from delictual, contractual or any other liability,
including a cause of action which relates to or arises from
any—
(i)act
performed under or in terms of any law; or
(ii)omission
to do anything which should have been done under or in terms of any
law; and
(b)
for which an organ of state is liable for payment of damages.”
[13]
[23]
To establish whether a claim is a debt in terms of the Act, the court
in
Director
General
Department of Public works v Kovac Investments
[14]
held that there are two legs to the enquiry of debt in terms of the
Act. One leg requires that a debt must arise from a contractual,
delictual or any other liabilities, the other is that it must render
the state organ liable for damages.
[24]
The court further held that if a claim is for specific performance,
then it does not constitute debt on the
basis that the claim is
stemming from a contract entered between the parties, not a claim for
damages arising from breach of contract.
[15]
[25]
The court in such claims therefore needs to apply the two legs of the
enquiry to establish whether a claim
constitute a debt in terms of
the Act. The court must enquire into whether there has been a breach
of contract; whether there is
a liability for a specific performance,
or whether there is a liability for payment of damages arising from
the contract, and whether
the state organ is liable. If the court
finds that there is a claim for specific performance, the claim will
not constitute a debt
in terms of the Act.
[26]
This application does not constitute a debt in terms of the Act as
the 1
st
Respondent argues. The application is based on specific performance,
which warrants performance from the 1
st
Respondent under the contractual obligations. Furthermore, since the
claim does not constitute debt in terms of the Act, there
is no basis
or ground to issue a demand or acquire a consent from the 1
st
Respondent before a relief is sought.
[16]
Whether
the Final Payment Certificate constitute a Liquid Document?
[27]
Applicant contends that the status of the Final Payment Certificate
is equivalent to that of an acknowledgement
of debt and a liquid
document. It is therefore required that the 1
st
Respondent
effect the payment of the Final Payment Certificate issued on 9
January 2018 by the 1
st
Respondent‘s Principal
Agent. The amount of the Final Payment Certificate should have been
effected into the Joint Venture’s
bank account which was opened
nineteen (19) months after the issue of the Final Payment
Certificate.
[28]
The court in
Randcon
(Natal)
(Pty) Ltd v Florida Twin Estates
Ltd
[17]
which
is an authority in terms of the certificates issued by the Principal
Agents who act on behalf of employers, held that: “the
issued
certificates constitute liquid documents on the basis that they are
issued upon a proper construction of a contract.”
[29]
The definition of a liquid document
was
laid down in
Twee
Jonge Gezellen (Pty) Ltd v Land
and
Agricultural Development Bank of SA,
[18]
the court held that:
“
In
principle, however, a document is liquid if it demonstrates, by its
terms, an unconditional acknowledgement of indebtedness in
a fixed or
ascertainable amount of money due to the plaintiff. Many
different sorts of documents have been found to qualify
as “liquid”
in terms of this definition and therefore sufficient to found
provisional sentence. They include acknowledgments
of debt, mortgage
bonds, covering bonds, negotiable instruments, foreign court orders
and architects’ progress certificates.
”
[19]
[30]
Notably, the Final Payment Certificate is
considered by our courts as an acknowledgement of debt as rightly
reflected by the Applicant, pointing out that in
Joob
Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture
[20]
,
the court, with reference to
Ocean
Diners (Pty) Ltd v Golden Hill Construction CC
[21]
,
held that
:
“
[27]
… A final payment certificate had to be treated as a liquid
document because it was issued by the employer's agent,
with the
consequence that the employer was in the same position it would have
been in if it had itself signed an acknowledgment
of debt in favour
of the contractor. Relying further on the Randcon case (at 186G
188G), the learned judge held that similar reasoning
applied to
interim certificates. The certificate thus embodies an obligation on
the part of the employer to pay the amount contained
therein and
gives rise to a new cause of action subject to the terms of the
contract. It is regarded as the equivalent of cash.
The certificates
in question all fall within this ambit.
[28]
Stocks held three liquid documents, the equivalent of
acknowledgements of debt. It could have proceeded to obtain
provisional
sentence on them but chose to apply for summary
judgment.”
[31]
The Final Payment Certificate No. 30 confirmed and certified by the
1
st
Respondent’s Principal Agent, is equivalent to an
acknowledgment of debt by the 1
st
Respondent. In circumstances where the 1
st
Respondent as the employer fails or refuses to pay an authorized and
correctly issued Final Payment Certificate, the Applicant
as the
contractor has remedies in law to enforce payment.
[22]
Some of the remedies include specific performance
[23]
and provisional sentences
[24]
which enforces fulfilment of obligations on the defaulting party.
[32]
The onus to prove the probabilities of the case where an Applicant is
in possession of a liquid document
lies with the Respondent, the
Twee
Jonge
Gezellen
case further held that:
“
But
a defendant who relies on a defence which goes beyond the liquid
document is required to produce sufficient proof of that defence
to
satisfy the court that the probability of success in the principal
case is against the plaintiff before provisional sentence
can be
refused. If there is no balance of probabilities either way with
regard to the principal case, the court will grant provisional
sentence. It follows that if there is a balance in favour of the
plaintiff, provisional sentence will also be granted. There is
no
closed list of defences on which a defendant can rely. Examples in
practice of defences going behind the liquid document are
numerous.
They include the defence: that the plaintiff never advanced the
amount claimed; that the liquid document was tainted
with illegality;
or that the document had been obtained by fraud.”
[25]
[33]
The Final Payment Certificate issued and certified by the 1
st
Respondent’s Principal Agent on the 9 January 2018, under the
authority of the 1
st
Respondent and in terms of the contract serves as a liquid document.
The
legal position in that instance is that where a person is armed with
a liquid document, he is ordinarily entitled to a provisional
sentence thereon.
[26]
The 1
st
Respondent failed to prove on a balance of probabilities against the
authenticity of the certificate or any sufficient proof that
the
claim lacked chances of success.
Clause
34.10 of the JBCC agreement between the parties
[34]
The basis of this application is founded on the payment of the Final
Payment Certificate which was issued
by the 1
st
Respondent’s Principal Agent on the 9 January 2018. Clause
34.10 of the JBCC as amended by the state clause and the contract
regulates the payment of the final account, together with interests
thereon. The express words of clause 34.10 are that:
“
The employer
shall pay the contractor the amount certified for payment in the
Final Payment Certificate within seven (7) calendar
days of the date
of issue of the Final Payment Certificate.”
[35]
In terms of the contract between the parties, the 1
st
Respondent’s Principal Agent, acting under the authority of the
1
st
Respondent, issued some 29 Interim Certificates
before, and payment was effected in terms of the agreement issued and
the certificates.
Later, the Principal Agent issued a Final Payment
Certificate which is still outstanding, due to failure by the 1
st
Respondent to effect a payment. The Final Payment Certificate has
attracted contractual interest.
[36]
The agreed terms of the contract according to clause 34.10, states
unequivocally that the amount of the Final
Payment Certificate shall
be paid to the contractor within seven (7) days of the date of the
issue of the Final Payment Certificate.
[37]
The 1
st
Respondent contends that it made two payments due
to the arbitration proceedings that took place between the 1
st
Respondent and the 2
nd
Respondent during April 2017. The
sum of R1 652 391,05 (One Million Six Hundred and Fifty-two Thousand
Three Hundred and Nighty-one
Rand and Five cents) in total was paid
on 1 December 2018 and 2 March 2019 to the Second Respondent
respectively. Thus, the amount
in respect of the main application
should be subtracted from the arbitration award.
[38]
The Applicant contends that it was not made aware of the arbitration
proceedings. The 1
st
Respondent has not proved the payment
of the arbitration award and that the payment is not recorded in the
Interim Certificates.
The alleged payment was not made in terms of
the contract awarded to the Joint Venture in accordance with the
Final Payment Certificate
issued with reference to clause 34 by the
1
st
Respondent ‘s Principal Agent.
[39]
The Applicant’s claim is for payment of the outstanding Final
Payment Certificate. The arbitration
proceedings and payment made by
the 1
st
Respondent as a result of the arbitration
proceedings do not form part of the proceedings
in casu
on the
basis that the 1
st
Respondent does not indicate any issued
certificate for such a payment.
Conclusion
[40]
Considering the circumstances of the matter, the 1
st
Respondent appointed the Principal Agent to act on its behalf, it
bound itself through the agency of the Principal Agent to perform
under the obligations of the contract and make payments upon the
issue of the certificates.
[41]
The Applicant commenced with the project and fulfilled the terms of
the obligations, which led to the issue
of interim certificates which
were paid, except for the Final Payment Certificate issued on the 9
January 2018.
[42]
The 1
st
Respondent on the other hand, failed to fulfil its
contractual obligations in terms of the JBCC Contract, by failing to
timeously
effect payment of the Final Payment certificate to the
Joint Venture which also attracted contractual default interest.
[43]
It is therefore just that the 1
st
Respondent fulfil its
contractual obligations and effect the payment of the Final Payment
Certificate, including the contractual
default interest as calculated
by the Minister of Finance.
[44]
Under the circumstances, the following order is made:
1.
The 1
st
Respondent is to pay the amount of R5,982,785.19 (Five Million Nine
Hundred Eighty-two Thousand, Seven Hundred and Eighty-five
Rand and
Nineteen Cents) in terms of the issued and certified Final Payment
Certificate no 30 dated 9 January 2018, together with
the contractual
default interest rate applicable, as determined by the Minister of
Finance.
2.
The 1
st
Respondent to pay the costs.
N
V KHUMALO J
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION
For Applicant:
Adv A J Gleddining
Instructed by:
C D De
Villiers
Email:
caroline@cdvlaw.co.za
;
theresa@cdlaw.co.za
For 1
st
Respondent:
Adv S Bofilatos SC
Instructed by:
The State Attorney
Email:
sonwabiso@gmail.co.za
[1]
De la Harpe S and Roos R, ‘Good Governance in the Procurement:
A South African Case Study’ (Jan 2008) PELJ Vol 11.
[2]
De la Harpe S and Roos R, ‘Good Governance in the Procurement:
A South African Case Study’.
[3]
Van Rensburg ADJ,’ Nature of a Contract ‘(31 October
2014) LAWSA Vol 9,295.
[4]
[2017]
ZASCA 176.
[5]
Id at
para
23.
[6]
Mohabed’s
Leisure Holdings (Pty) Ltd v Southern Sun Hotel Interests (Pty) Ltd
at
para
23.
[7]
Baedacia
321 CC and Others v Trustees for the time being of Oregan Trust and
Others
[2020] ZA CC 13
2020 (5) SA 247
(CC) 2020(9) BCLR 1098 (CC) at para
37.
[8]
The Joint Building Contracts Committee NPC Principal Building
Agreement Edition
4.1 March 2005.
[9]
Ramsden
PA,
McKenzie
‘s
Law of
Building and Engineering Contracts and Arbitration,
(7
th
edition Juta 2014)1.
[10]
Ramsden PA,
McKenzie
‘s
Law of
Building and Engineering Contracts and Arbitration,
137.
[11]
Ramsden PA,
Mckenzie
‘s Law of Building and Engineering Contracts and Arbitration
,
205-206.
[12]
Institution of Legal Proceedings Against Certain Organs of State Act
40 of 2002
.
[13]
Section 1
Institution of Legal Proceedings Against Certain Organs of
State Act 40 of 2002
.
[14]
SA 646(GNP) at para 7.
[15]
Id at para 10.
[16]
Randcon
(Natal)
(Pty) Ltd v Florida Twin Estates
Ltd
1973
(4) SA 181
at
p184.
[17]
1973
(4) SA 181
at
para 188.
[18]
2011(3)
SA 1 CC.
[19]
Id
at para 15.
[20]
2009
(5) SA 1 (SCA)
[21]
[1993]
ZASCA 41
## [22]Souter
v T & T Building Contractors CC(A532/09) [2011] ZAWCHC 220 para 17.
[22]
Souter
v T & T Building Contractors CC
(A532/09) [2011] ZAWCHC 220 para 17.
[23]
Ramsden PA,
Mckenzie
‘s
Law of
Building and Engineering Contracts and Arbitration,
87.
[24]
Id para 15.
[25]
Id para 21.
[26]
Randcon
(Natal) (Pty) Ltd v Florida Twin Estates
Ltd
1973
(4) SA 181
at p190.
sino noindex
make_database footer start
Similar Cases
Kgalemo Construction CC and Others v Small Enterprise Finance Agency SOC Ltd (54791/2021) [2024] ZAGPPHC 1179 (19 November 2024)
[2024] ZAGPPHC 1179High Court of South Africa (Gauteng Division, Pretoria)98% similar
Construction Education and Training Authority (CETA) v V2 Digital (Pty) Ltd and Another (2025/024691) [2025] ZAGPPHC 242 (6 March 2025)
[2025] ZAGPPHC 242High Court of South Africa (Gauteng Division, Pretoria)98% similar
Leatile Construction and Projects CC v Christo Bekker Inc Attorneys and Another (13850/23) [2024] ZAGPPHC 212 (19 March 2024)
[2024] ZAGPPHC 212High Court of South Africa (Gauteng Division, Pretoria)98% similar
Builda Construction Cape Proprietary Limited v Verveen and Another [2023] ZAGPPHC 178; 018498/13 (22 March 2023)
[2023] ZAGPPHC 178High Court of South Africa (Gauteng Division, Pretoria)98% similar
Khavhakone Construction Group (Pty) Ltd v Housing Development Agency and Another (22632/2022) [2024] ZAGPPHC 1281 (5 December 2024)
[2024] ZAGPPHC 1281High Court of South Africa (Gauteng Division, Pretoria)97% similar