Case Law[2023] ZAGPPHC 2South Africa
Blue Water Creek Homeowners Association v Kanniah and Others (A96/2020) [2023] ZAGPPHC 2 (9 January 2023)
High Court of South Africa (Gauteng Division, Pretoria)
9 January 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 2
|
Noteup
|
LawCite
sino index
## Blue Water Creek Homeowners Association v Kanniah and Others (A96/2020) [2023] ZAGPPHC 2 (9 January 2023)
Blue Water Creek Homeowners Association v Kanniah and Others (A96/2020) [2023] ZAGPPHC 2 (9 January 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_2.html
sino date 9 January 2023
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
CASE
NO.: A96/2020
REPORTABLE:YES/NO
OF
INTEREST TO OTHER JUDGES: YES/NO
REVISED:
09/01/23
In
the matter between
BLUE
WATER CREEK HOMEOWNERS
ASSOCIATION
(Registration
Number: 2005/001197/08)
Applicant
And
SIVALINGUM
KANNIAH
First Respondent
NIRMALA
KANNIAH
Second Respondent
COMMUNITY
SCHEMES OMBUD SERVICE
Third Respondent
ADJUDICATOR
- (K. BLEIJS N.O.)
COMMUNITY
SCHEMES OMBUD SERVICE
Fourth Respondent
IN
RE:
SIVALINGUM
KANNIAH
First Appellant
NIRMALA
KANNIAH
Second Appellant
and
BLUE
WATER CREEK HOMEOWNERS ASSOCIATION First
Respondent
(Registration
Number: 2005/001197/08)
COMMUNITY
SCHEMES OMBUD SERVICE
Second Respondent
ADJUDICATOR
(K.
BLEIJS N.O.)
COMMUNITY
SCHEMES OMBUD SERVICE
Third Respondent
JUDGMENT
MANAMELA
AJ
INTRODUCTION
[1.]
The Applicant issued an application to have
the first and second respondents’ appeal in terms of section
57(1) of the Community
Schemes Ombud Service Act, 9 of 2011 (“the
CSOS Act”), set aside and to have the Adjudication Order dated
17 October
2019 made an order of Court.
[2.]
The Applicant is a Homeowners’
Association, to whom the First and Second Respondents are members by
virtue of being property
owners within a community scheme. The Third
and Fourth Respondents are cited as interested parties, having been
involved in the
subject case under appeal.
[3.]
The First and Second Respondents’
Notice of Appeal was served on 20 March 2020. The basis of this
application is that the
Respondents’ Notice of Appeal was
served out of time and that the First and Second Respondents failed
to prosecute the appeal.
[4.]
The
application is opposed. The First and Second Respondent appeared in
person. The basis of opposition is unclear, at the very
least the
First and Second Respondents relies on the applicant’s failure
to enforce the adjudication order in accordance
with section 56(2) of
the
CSOS Act
[1]
.
[5.]
The first and second respondents launched
an appeal in terms of section 57(1) of
the
CSOS Act
, against the following order:
“
1.
The Applicant’s application is dismissed.
2. The Applicant is
ordered to and compelled to:
2.1. Build a spray on
Erf 27 Blue Creek Homeowners Association as required by the
Respondent’s Directors, which is 3 x 3mm,
in accordance with
safety requirements according to road reserve widths, within 60 days
of date of this order.
2.2. Pay to the
Respondent the fines and penalties as charges in accordance with the
MOI and the Rules;
2.3. Henceforth comply
with the Memorandum of Incorporation the Rules and Aesthetic
Guidelines made in terms thereof;
2.4. There is no order
Costs”.
FACTUAL BACKGROUND
[6.]
The First and Second Respondents
submitted an application for dispute resolution in
terms of section 38 of the CSOS Act, on 20 June 2018.
[7.]
On 18 February 2019, the Applicant filed
its answer to the First Respondent’s CSOS complaint.
[8.]
The
Adjudicator
made an order in terms of section 53(1) of CSOS Act.
[9.]
The issues which were dealt with by the
CSOS Adjudicator are:
9.1. Firstly, whether a
spray must be opened in the Respondents’ garden wall in terms
of municipal regulations and the architectural
guidelines of the
Applicant; and
9.2. Secondly, whether
the Applicant is lawfully entitled to charge the fines and penalties
that have been imposed on the Respondents
for contravening the Rules
of the Applicant.
[10.]
On 1 November 2019, the CSOS Adjudication
Order was served on the Applicant as well as the First and Second
Respondents, in terms
of which the First and Second Respondents
complaint was
dismissed.
[11.]
On 12 November 2019, the Applicant served a
copy of the Adjudication Order on all its members via e-mail, which
e-mail the First
Respondent acknowledged receipt of on 18 November
2019.
[12.]
On 21 November 2019, the Applicant
addressed a letter to the First Respondent requesting that they abide
by the adjudication Order
within the prescribed 30-day period. The
First and Second Respondent failed and/or refused to comply with the
Adjudication Order.
[13.]
On 20 March 2020,
In response, the
First and Second Respondents’ eastwhile attorneys confirmed
that they filed an appeal against the adjudicator’s
order with
regards to the building penalties imposed. At that stage, the appeal
was already late.
[14.]
On 3 April 2020, the First and Second
Respondents’ erstwhile attorneys, namely Barnard Inc, served a
copy of the Respondents’
Notice of appeal on the Applicant’s
erstwhile attorneys, namely AM Theron Inc.
[15.]
On 6 April 2020, the Applicant’s attorneys addressed a
letter to the Respondents’ attorneys, noting that the
Respondents’
Notice of Appeal was served out of time. This is
by virtue of Section 57(2) of the CSOS Act, which states that an
appeal against
an order must be lodged within 30 days after the date
of delivery of the order of the adjudicator.
[16.]
On 22 April 2020, the Respondents’ attorneys noted in
their letter that an application for condonation would follow in due
course. No application for condonation was ever filed by the First
and Second Respondents and no further steps was taken to prosecute
the appeal.
[17.]
The Applicant elected to enforce its rights against the order
and instituted this application, which was served on the Respondents
on the 20
th
of January 2022.
ISSUES OF
DETERMINATION
The issues to be
considered are:
[18.]
Whether the Respondents’ Notice of Appeal
dated 19 March 2020 should be set aside due to their failure and/or
refusal to file
their Appeal timeously and due to their failure
and/or refusal to prosecute their appeal within a reasonable time
period.
[19.]
Whether the CSOS Award dated 17 October 2019
(Marked Annexure “X” to the Notice of Motion) should be
made an Order of
Court.
LEGAL FRAMEWORK
[20.]
The
objective of the Community Schemes Ombuds Service Act 9 of 2011
(“CSOS Act”), is to
provide
for the establishment of the Community Schemes Ombud Service; to
provide for its mandate and functions; and to provide for
a dispute
resolution mechanism in community schemes; and to provide for matters
connected therewith. One of the purposes set out
in the CSOS Act, is
to provide for a dispute resolution mechanism in community
schemes
[2]
.
[21.]
Community schemes are defined in the CSOS Act as
any scheme or arrangement in terms of which there is shared use of
and responsibility
for parts of land and buildings, including but not
limited to a sectional titles development scheme, a share block
company, a home
or property owner‘s association, however
constituted, established to administer a property development, a
housing scheme
for retired persons, and a housing cooperative…‘
[22.]
In terms of section 56 of the CSOS Act, an order
handed down by an adjudicator must be enforced as if it were a
judgment of the
High Court or Magistrate Court, depending on the
jurisdiction. The relevant court official must, upon lodgement of the
order, register
it as an order of such court.
[23.]
Chapter 3 of the CSOC Act, provides for the
procedure to be followed in the case of dispute.
[24.]
Section 57 (1) of CSOS Act provides that an
applicant, the association or any affected person who is dissatisfied
by an adjudicator’s
order, may appeal to the High Court, but
only on a question of law. (2) An appeal against an order must be
lodged within 30 days
after the date of delivery of the order of the
adjudicator. (3) A person who appeals against an order, may also
apply to the High
Court to stay the operation of the order appealed
against to secure the effectiveness of the appeal.
[25.]
An appeal in terms of s 57 is not a ―civil
appeal within the meaning of the
Superior Courts Act 10 of 2013
.
ANALYSIS
[26.]
It
is common cause that the first and second respondent files a
complaint with the Fourth Respondent in terms of section 38 of the
CSOS Act
[3]
.
[27.]
The adjudicator granted an order on 1 November 2020. The appeal had
to be served on or before 1 December 2020. It is
common cause that
the case launched by the First and Second Respondents was
unsuccessful. The First and Second Respondent were
informed of the
right to appeal within 30 days in terms section 57(1) of the CSOS
Act.
[28.]
The
proper manner in which such an appeal should be brought in the
circumstances is upon notice of motion supported by affidavit(s),
which should be served on the respondent parties by the sheriff.
[4]
Neither
the CSOS Act nor the Uniform Rules of Court prescribe a procedure for
bringing an appeal as contemplated in section 57 of
SCOS Act.
[29.]
In
Stenorson
and Talikan Administration CC v Linton Park Body Corporate and
Another
2021 SA 651
the
court dealt with the process to be followed when launching an appeal,
where the court stated that
“
an
appeal against the order may not be made after 30 days have
lapsed
[5]
.
[30.]
The First and Second respondents conceded
in their heads of argument that “
it
came to their knowledge that the CSOS adjudication order is not
appealable as there are no questions of law to appeal”.
The
Respondents made a clear concession that the appeal has lapsed and
that the adjudication order has to take effect.
[31.]
The Applicant made a clear indication that it would not
condone a late appeal, in its letter dated 6 April 2020. No
application
for condonation for was sought.
[32.]
What
may be sought in terms of section 57 is an order from this court
setting aside a decision by a statutory functionary on the
narrow
ground that it was founded on an error of law. The relief available
in terms of section 57 is closely analogous to that
which might be
sought on judicial review. The appeal is accordingly one that is most
comfortably niched within the third category
of appeals defined in
Tikly
and Others v Johannes NO and Others
1963 (2) SA 588
(T) at 590 –
591
[6]
.
[33.]
Once a concession is made by the Respondents that the appeal was not
file timeously and that the is no point of law
to warrant an appeal,
the first and second respondents should have complied with the
adjudicator’s order.
[34.]
The First and Second Respondents relies on the fact that the
Applicant did not lodge a copy of the order, with the Registrar
of
the High Court, as contemplated in section 56(2) of CSOS Act. The
said provision does not prescribe a period within which the
order
should be lodged. The first and second Respondents were still bound
to comply with the order and had to comply with it within
the
timeframe stated in the order. Section 56(2) only kicks in upon
failure to comply.
[35.]
The First and Second Respondents misdirected themselves that by
virtue of the fact that the Applicant launched this
application, they
had an opportunity to resume with the appeal, which was not
prosecuted after notice of appeal.
[36.]
The First and Second Respondents argues that the delays relating to
the impact of COVID-19 and lock-down around March
2023 should be
taken into account to allow the appeal to be heard out of time. This
argument bears no legal basis.
Review
as an alternative relief
[37.]
Having
notices that the order is not appealable, the first and second
respondents in their answering affidavit opted to change to
a review
application without making specific reliance to the relevant
provisions under
the
Promotion of the Administrative Justice Act
[7]
.
[38.]
The application for review was launched 885 days
after they became aware of the adjudication. The requirement is that
it must be
launched within 180 days, they launched it 885 days late.
[39.]
The first
and second respondent did not seek any condonation for lateness in
accordance with section 9 of PAJA.
When
the delay is longer than 180 days, a court is required to consider
whether it is in the interests of justice for the time period
to be
extended
[8]
.
The SCA in Opposition to
Urban
Tolling Alliance v The South African National Roads Agency Limited
(90/2013)
[2013] ZASCA 148
(SCA)
,
held that -
“
45.
Absent any extension under section 9, the 180-day time bar precludes
us from entertaining the direct challenge by way of a review
application
”
[40.]
The
standard to be applied in assessing delay under both PAJA and
legality is thus whether the delay was unreasonable
[9]
.
Moreover, in both assessments the proverbial clock starts running
from the date that the applicant became aware or reasonably
ought to
have become aware of the action taken.
Unfortunately,
I am also precluded from entertaining the review application out of
time without any reasons for condonation.
[41.]
It
is trite law that, where there is no explanation for the delay, the
delay will be undue
[10]
CONCLUSION
[42.]
I find that the Applicant has made out a case for the relief sought,
the First and Second Respondents failed and/or
refusal to file and to prosecute their appeal within a reasonable
time period, and
it the lights of that, the CSOS Award dated 17
October 2019 (Marked Annexure “X” to the Notice of
Motion) should stand.
COSTS
[43.]
Unlike in the adjudication proceedings, I find it appropriate to
grant an order of cost on a punitive scale, the First
and Second
Respondents had no legal basis to persist with the opposition of this
declaratory order, knowing that the adjudication
order was not
appealable. It may also be possible that they were advised against
this opposition and decided to proceed regardless.
ORDER –
The following order is
order-
1.
The First and Second Respondents’
appeal in terms of section 57(1) of the Community Schemes Ombud
Service Act, 9 of 2011 (“the
CSOS Act”) is set aside;
2.
The Adjudication Order dated 17 October
2019 is made an order of Court, that –
The
First and Second Respondents ordered to –
2.1. Build a spray on Erf
27 Blue Creek Homeowners Association as required by the Respondent’s
Directors, which is 3 x 3mm,
in accordance with safety requirements
according to road reserve widths, within 60 days of date of this
order.
2.2. Pay to the
Respondent the fines and penalties as charges in accordance with the
MOI and the Rules.
2.3. Henceforth comply
with the Memorandum of Incorporation the Rules and Aesthetic
Guidelines made in terms thereof.
3.
The First and Second Respondents are liable
for costs on attorney and client scale.
P
N MANAMELA
ACTING
JUDGE OF THE HIGH COURT
GAUTENG
DIVISION, PRETORIA
Date
of hearing: 24 August 2022
Judgment
delivered: 9 January 2023
APPEARANCES:
Counsels
for the Applicant:
Adv. NG Louw
Attorneys
for the Applicant:
JV Rensburg Kinsella Inc Attorneys
The
first and second Respondents: Appeared In
Person
[1]
Section
56(2) of the Community Schemes Ombud Services Act 9 of 2011 - If an
adjudicator’s order is for the payment of an
amount of money
or any other relief which is beyond the jurisdiction of the
magistrate’s court, the order may be enforced
as if it were a
judgment of the High Court, and a registrar of such a Court must, on
lodgement of a copy of the order, register
it as an order in such
Court.”
[2]
Section
2(c) of CSOS Act
[3]
38.
(1) Any person may make an application if such person is a party to
or affected materially by a dispute. (2) An application
must be—
(a) made in the prescribed manner and as may be required by practice
directives; (b) lodged with an ombud; and
(c) accompanied by the
prescribed application fee. (3) The application must include
statements setting out— (a) the relief
sought by the
applicant, which relief must be within the scope of one or more of
the prayers for the relief contemplated in section
39; (b) the name
and address of each person the applicant considers to be affected
materially by the application; and (c) the
grounds on which the
relief is sought. (4) If the applicant considers that the
application qualifies for a discount or a waiver
of adjudication
fees, the application must include a request for such discount or
waiver.
[4]
Ibid
paras 25-26
[5]
Stenorson
and Talikan Administration CC v Linton Park Body Corporate and
Another 2021 SA 651
[6]
Trustees,
Avenues Body Corporate v Shmaryahu and Another 2015 (4) SA 566 (WCC)
[7]
Section
7(1) of PAJA - Any proceedings for judicial review in terms of
section 6(1) must be instituted without unreasonable delay
and not
later than 180 days after the date on which the proceedings are
completed or on the date on which the person concerned
was informed
of the administration, administrative action.
[8]
Section
9(2) of PAJA -
[9]
City
of Cape Town v Aurecon South Africa (Pty) Limited [2017] ZACC 5;
2017 (4) SA 223 (CC); 2017 (6) BCLR 730 (CC)
[10]
Khumalo
v Member of the Executive Council for Education, KwaZulu Natal
[2013] ZACC 49
;
2014 (5) SA 579
(CC);
2014 (3) BCLR 333
(CC)
sino noindex
make_database footer start
Similar Cases
Twin Rivers Homeowners Association NPC v Siyanda Sabelo Trading (Pty) Ltd (2024/008136) [2025] ZAGPPHC 968 (28 August 2025)
[2025] ZAGPPHC 968High Court of South Africa (Gauteng Division, Pretoria)97% similar
Sable Hills Waterfront Estate Homeowners Association (NPC) and Others v Companies and Intellectual Properties Commission and Others (053716/2024) [2025] ZAGPPHC 110 (29 January 2025)
[2025] ZAGPPHC 110High Court of South Africa (Gauteng Division, Pretoria)97% similar
Waterkloof Boulevard Homeowners Association (Association Incorporated under Section 21) v Yusuf and Another (028945/2022) [2023] ZAGPPHC 737 (28 August 2023)
[2023] ZAGPPHC 737High Court of South Africa (Gauteng Division, Pretoria)97% similar
Blue Valley Golf and Country Estate Homeowners Association v Maphanga (2018/44865) [2025] ZAGPPHC 906 (19 August 2025)
[2025] ZAGPPHC 906High Court of South Africa (Gauteng Division, Pretoria)97% similar
Blue Bulls Company (Pty)Ltd vs Mega Burst Oils and Fuels (Pty)Ltd (2021/18739) [2022] ZAGPJHC 314 (21 April 2022)
[2022] ZAGPJHC 314High Court of South Africa (Gauteng Division, Johannesburg)97% similar