Case Law[2022] ZAGPPHC 587South Africa
Siemens (Pty) Ltd v Passenger Rail Agency of South Africa (19845/2021) [2022] ZAGPPHC 587 (15 July 2022)
High Court of South Africa (Gauteng Division, Pretoria)
15 July 2022
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2022
>>
[2022] ZAGPPHC 587
|
Noteup
|
LawCite
sino index
## Siemens (Pty) Ltd v Passenger Rail Agency of South Africa (19845/2021) [2022] ZAGPPHC 587 (15 July 2022)
Siemens (Pty) Ltd v Passenger Rail Agency of South Africa (19845/2021) [2022] ZAGPPHC 587 (15 July 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2022_587.html
sino date 15 July 2022
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG DIVISION,
PRETORIA)
REPUBLIC
OF SOUTH AFRICA
Case
Number:
19845/2021
REPORTABLE:
NO
OF
INTEREST TO OTHER JUDGES: NO
REVISED:
NO
DATE:
14 July 2022
In
the matter between:
SIEMENS
(PTY)
LTD
Applicant
(Registration
number: 1923/007514/07)
And
PASSENGER
RAIL AGENCY OF SOUTH AFRICA
Respondent
JUDGMENT
JANSE
VAN NIEUWENHUIZEN J:
[1]
This application pertains to a contract entered into between the
parties in terms
of which the applicant had to install certain
hardware for the respondent in respect of signalling at its railway
system for a
trial process.
[2]
The applicant alleges that it performed in terms of the agreement and
claims payment
in the amount of R 33 993 092, 00 for the
services rendered. The respondent opposes the claim on several
grounds, which
grounds will be dealt with
infra
.
The
applicant’s claim
[3]
The parties are and have been involved in various contracts,
including the upgrade
of the Gauteng railway system and
infrastructure which commenced during April 2011 (“Gauteng
Upgrade Agreements”).
During the course of the project, the
parties entered into discussions for the possible implementation of
the European Train Control
System Level 2 (“ETCS”) system
as supplied and installed by the applicant.
[4]
To this end and on 25 March 2015, the applicant made a proposal to
the respondent
in respect of the ECTS system. The relevant portion of
the offer for present purposes, entails that the applicant will
support
the respondent by providing and installing a trial ETCS L2
solution at two stations on the Gauteng rail network for the testing
of the respondent’s new rolling stock. The respondent will
offset the cost of the ETCS Trial against any possible penalties
that
may be due on other contracts. Any price difference will be paid to
the applicant in the event that the applicant is not awarded
the
contract for the Gauteng ETCS rollout.
[5]
On 7 May 2015, the respondent represented by Piet Sebola (“Sebola”)
responded
to the proposal in writing. In the introductory paragraph
of the letter the respondent stated that it “
herewith wish
to record our further understanding of how the Trial ETCS and RBC
will be implemented as set out in your offer of
25 March 2015.”
[6]
The following is stated in respect of the cost of the project:
“
1.4
Siemens is currently installing a signalling system on PRASA’s
rail network in Gauteng (“the Signalling
Project”) and
wishes to assist PRASA with this trial at no upfront cost to PRASA.
The cost of the trial system is an amount
of R 39, 000, 000
(thirty-nine million Rand only).
1.5
Siemens has also experienced some milestone delays in the
implementation of the Signalling Project which are
agreed to have
attracted penalties in the amount of R 5, 006, 908 (five million, six
thousand, nine hundred and eight Rand only).
This penalty amount will
be offset against the cost of the Trial System so that the Agreed
Cost of the Trial is as follows:
Offer Price (Excl VAT)
Cost of the Trial
System
R 39, 000, 000
Less Penalties as at
March 2015
R 5 006 908
Agreed Cost of the
Trial
R 33, 993, 092
…
.
1.8
PRASA will, in due course, issue an open and competitive tender
process inviting bidders who have the technical
capacity to install
the train control system on its network. In the event that Siemens is
not appointed in this competitive tender
process to install the train
control system in the Trial Track and the Trial System is still in
working order, PRASA will procure
that Siemens is paid the Agreed
Cost of the Trial.
1.9
In the event that no competitive tender process has been initiated
and/or there is no decision by PRASA on
the competitive tender
process, the parties shall agree on the terms of payment of the
Agreed Cost of the Trial by no later than
30
th
September
2016.”
[7]
In response and on 14 May 2015 the applicant addressed a letter to
the respondent
recording the following:
“
Siemens
acknowledges receipt of your letter dated 7 May 2015. We confirm that
we shall proceed to implement the RBC trial –
agreement in
accordance with our 25 March 2015 – offer, and the
aforementioned letter.”
[8]
The applicant stated that it had complied with its obligations in
terms of the agreement
and that the test project was completed.
[9]
The process of finalising the installation, however, took longer than
anticipated
and the completion date foreshadowed in terms of the
agreement was not met. The project was finally signed off on 15
December 2016.
[10]
In anticipation of the completion of the project and on 19 May 2016,
the respondent published
a tender for the automatic train signalling
system. The tender period was initially extended and later cancelled
on 14 June 2018.
[11]
Nothing transpired further until the applicant in a letter dated 13
August 2019 requested the
respondent to provide confirmation of the
release date of the tender. On 28 August 2019, the respondent
indicated that it was preparing
to release a new tender.
[12]
A new tender was not forthcoming and on 23 October 2019 the applicant
addressed a letter to the
respondent in respect of payment for work
done. The relevant portion of the letter reads as follows:
“
It
was further agreed between the parties …that in the event that
Siemens is not appointed in PRASA’s competitive tender
process
for the PICS tender – which Siemens accepts will have to comply
with all prevailing procurement laws on a fair and
transparent basis-
then PRASA will procure and pay Siemens the Agreed Cost of the Trial
to the value of R 33, 993, 092 plus the
VAT.
In circumstances where
the parties have not yet met and agreed on the payment terms, we will
appreciate your proposal in that regard,
alternatively, provide
Siemens with the necessary Purchase Order for the amount ….to
enable us to invoice accordingly, accepting
that the amount will be
payable within 30 days.”
[13]
The letter was not met with a positive response and was followed up
by a letter dated 17 March
2020 to which an invoice was attached, a
further letter of demand dated 13 August 2020 and a final letter of
demand dated 20 December
2020.
[14]
Payment was still not forthcoming which led to the launching of the
present application.
The
respondent’s response
[15]
The respondent opposes the relief claimed by the applicant and
launched a counter application
in which it prays for the agreement
(the counter offer dated 7 May 2015) to be declared unlawful and for
the agreement to be reviewed
and set aside.
[16]
The respondent did not take issue with the factual allegations of the
applicant’s claim.
The defences raised by the respondent were
all points of law, to wit:
In
limine:
Prescription
[17]
The respondent contends that the claim has prescribed, i.e that the
right to claim within the
three-year period prescribed in section
11(d) of the
Prescription Act 68 of 1969
, has lapsed, in the
following circumstances:
17.1 because the
project was finally signed off on 15 December 2016, the applicant
knew or ought to have reasonably known
in December 2016 that the
respondent owed the amount claimed herein;
17.2 although the
debt became due and payable on 15 December 2016, as there were no
terms of payment allowing for the delay
of payment of the due amount,
the present proceedings were only launched on or about 20 April 2021,
more than four years after
the due date.
Inchoate
agreement
[18]
In the alternative, the respondent maintains that the agreement
between the parties was an agreement
to further agree and as a result
the agreement is void and unenforceable.
The
agreement is invalid on the ground of legality
[19]
The respondent maintains that the purported agreement relied upon by
the applicant does not comply
with the constitutional and statutory
prescripts applicable to procurement of goods and services by an
organ of state.
[20]
Furthermore and according to the respondent, the procurement of the
ETCS system does not comply
with the Supply Chain Management Policy
of the respondent. Sebola was not authorised to negotiate, approve
and conclude an agreement
outside the supply chain management
process.
CONTENTIONS
ON BEHALF OF THE PARTIES AND DISCUSSION
Prescription
[21]
In answer to the prescription claim, the applicant contends that the
parties were to agree to
the terms of payment by 30 September 2016.
This agreement was, however, reached on the basis that the test
project will be completed
as per the agreed date, being 31 January
2016.
[22]
As the test project was not completed by the intended completion
date, extensions were agreed
upon by the parties, which resulted in
the final handover date of 15 December 2016.
[23]
The tender was published on 19 May 2016 and finally withdrawn on 14
June 2018. The date on which
the applicant realised that it would not
be awarded the tender was therefore 14 June 2018 and the application
was launched on 20
April 2021, being a date within the three-year
period.
[24]
The agreement between the parties postulated two scenarios pertaining
to payment:
24.1 in the event
that Siemens is not appointed in the competitive tender process,
PRASA will procure that Siemens is paid
the Agreed Cost of the Trial;
and
24.2 in the event
that no competitive tender process has been initiated and/or there is
no decision by PRASA on the competitive
tender process, the parties
shall agree on the terms of payment of the Agreed Cost of the Trial
by no later than 30
th
September 2016.
[25]
The first scenario did not eventuate.
[26]
The second scenario did. On 30 September 2016 there was no decision
by the respondent on the
competitive tender process. The fact that
the parties agreed on the extension of the contract period does not
impact on the clear
wording of the terms of payment.
[27]
The parties did not agree on the terms of payment on 30 September
2016, which entail that amount
payable due in terms of the contract
became due on completion of the performance of the applicant, i.e 15
December 2016.
[28]
To enforce payment the applicant had to demand (interpellation)
payment by a specific date within
the three year period.
[29]
In the result, I agree with the respondent that the applicant’s
claim has prescribed and
the point
in limine
must succeed.
[30]
Should I, however, be wrong in the aforesaid finding, I proceed to
consider the remainder of
the defences and the counter claim.
Inchoate
agreement
[31]
This defence is directed at the second scenario discussed
supra
,
to wit:
“
in
the event that no competitive tender process has been initiated
and/or there is no decision by PRASA on the competitive tender
process,
the
parties
shall agree
on the terms of payment of the Agreed Cost of the Trial by no later
than 30
th
September 2016.
[32]
The respondent contends that this portion of the agreement contains
an agreement to agree on
the terms of payment and the agreement is as
a result not enforceable.
[33]
The principle that an agreement to conclude another agreement is
unenforceable was confirmed
in
Free
State and others v Firechem Free State (Pty) Ltd
2000
(4) SA 413
(SCA) at para [35]:
“…
An
agreement that the parties will negotiate to conclude another
agreement is not enforceable, because of the absolute discretion
vested in the parties to agree or disagree.”
[34]
This is, however, not the position in
casu
. The parties only
agreed to reach agreement on one aspect of the contract, to wit; the
terms of payment.
[35]
The first enquiry in determining whether the contract between the
parties is valid, is whether
the parties have agreed on the essential
terms of a
locatio conductio operis.
[See:
Southernport
Developments (Pty) Ltd v Transnet Ltd
[2005] All SA 16
(SCA)]
[36]
The essential terms of a
locatio conduction operis
are:
36.1 the work to be
performed;
36.2 the
renumeration payable; and
36.3 the time for
performance.
[See:
Group Five
Building Ltd v Minister of Community Development
[1993] ZASCA 75
;
1993 (3) SA 629
(A)].
[37]
The agreement between the parties provides for:
37.1 the scope of
work to be performed;
37.2 the contract
amount payable;
37.3 the completion
date of the project.
[38]
Once these essentials for a valid contract have been agreed upon
between the parties, failure
to agree on the terms of payment does
not invalidate the contract. [See:
Southernport Developments (Pty)
Ltd v Transnet Ltd, supra
para [6]].
The
illegality of the agreement
[39]
A contract concluded between parties is invalid if one of the parties
to contract did not have,
by virtue of a statutory provision, the
necessary power to enter into the contract. [See:
Municipal
Manger: Qaukeni Local Municipality and Another v FV General Trading
CC
2010 (1) SA 356
SCA par [16];
Premier Free Stae and Others
v Firechem Free State (Pty)
2000 (4) SCA par [30]]
[40]
In
Provincial Government of the Eastern Cape and Others v
Contractprops 25 (Pty) Ltd
[2001] 4 All SA 273
(A), Department of
Education, Culture and Sport in the Eastern Cape Province “the
Department”) entered into two lease
agreements with Contraprops
25 (Pty) Ltd (“Contracrprops”). The Department decided
after three years to terminate the
lease agreements on three months’
notice. When Contractprops challenged the termination, the Department
submitted that the
lease agreements are invalid because it entered
into the leases without the Tender Board established by the Tender
Board Act (Eastern
Cape), 2 of 1994 having arranged the hiring of the
premises in terms of section 4(1) of the Act.
[41]
The supreme Court of Appeal upheld the challenge and the lease
agreements were declared invalid.
[42]
In
casu
the respondents rely on the following legislative
instruments in challenging the validity of the agreement:
42.1 section 217
(1), (2) and (3) of the Constitution;
42.2 section (2),
45(a) and 51(1) of the Public Finance Management Act, 1 of 1999
(“PFMA”) ;
42.3 National
Treasury Regulations on procurement of goods and services;
42.4 National
Treasury Procurement Guidelines; and
42.5 The
respondent’s Supply Chain Management Policy.
[43]
Section 217(1) provides that when the respondent contracts for goods
or services, it must do so in
accordance with a system which is fair,
equitable, transparent, competitive and cost-effective. Section 217
(2) and (3) are not
applicable to the facts in
casu
.
[44]
The object of the is contained in section, to wit, to “
secure
transparency, accountability, and sound management of the revenue,
expenditure, assets and liabilities of the institutions
to which this
Act applies.”
[45]
It is common cause that the PMFA is binding on the
respondent.
[46]
Section 45 is applicable to other officials and provides that “
An
official in a department, trading entity or constitutional
institution –
(a) must ensure that
the system of financial management and interim control established
for that department, trading entity or constitutional
institution is
carried out within the area of responsibility of that official:”
[47]
Section 51(1) provides for the general responsibility of accounting
authorities. The relevant
portion reads as follows:
“
Section
51(1) - An accounting authority of a public entity-
(a)
must ensure that
the public entity has and maintains-
(iii)
an appropriate
procurement and provisioning system which is fair, equitable,
transparent, competitive and cost-effective;”
(e)
must take effective and appropriate disciplinary steps against any
employee of the public entity who-
(i)
contravenes or fails to comply with a provision of the Act
(ii)
commits an act which undermines the financial management and internal
control system of the public
entity; or
(iii)
makes or permits an irregular expenditure or a fruitless and wasteful
expenditure:”
Section
2 5(1) relied upon by the respondents, establishes a National
Treasury that consists of the Minister of Finance, as the
head of
Treasury and the national department or departments responsible for
financial and fiscal matters
[48]
I pause to mention that section 86 of the PMFA provides for offences
by and penalties to be imposed
on accounting officers.
[49]
The respondent did not refer to any specific provision/s on which it
relies in National Treasury
Regulations on procurement of goods and
services and the National Treasury Procurement Guidelines.
[50]
Insofar as the respondent relies on its Supply Chain Management
Policy (“the Policy”),
clause 11.3.3 is applicable, to
wit:
“
Unsolicited
bids are generally prohibited unless approved for consideration by
the GCEO. In approving their consideration, the GCEO
shall take the
following into account:
•
That
the unsolicited bid is a unique concept or offering
•
That
the offering of the bid cannot be provided efficiently through
competitive bidding process
•
That
there are no suppliers in the market that can provide a similar
offering without copying from the unsolicited bid.”
[51]
The acronym
GCEO
stands for the Group Chief Executive Officer.
It is common cause that Sebola was not the GCEO when he accepted the
applicant’s
unsolicited bid and entered into the agreement.
[52]
In view of the aforesaid, the respondents contends that the agreement
was concluded outside the
respondent’s policy in contravention
of the Constitution, legal and regulatory prescripts regulating
procurement of goods
or services by a public entity and an organ of
State and is in the result, unlawful and invalid
ab initio.
[53]
It is clear from the aforesaid, that Sebola did not have the power to
enter into the agreement
on behalf of PRASA. In doing so Sebola acted
ultra vires
the legislative framework pertaining to the
procurement of services and the agreement is as a result, invalid.
[54]
The applicant did not seriously dispute the aforesaid submissions by
the respondent, but in answer
relied on estoppel.
[55]
Estoppel, however, does not assist the applicant.
This much is clear from
Provincial Government of the Eastern Cape
and Others v Contractprops 25 (Pty) Ltd, supra
at para [11]
–[13]:
“
[11]
……It remains to consider an alternative contention
advanced by counsel for respondent: estoppel. There are formidable
obstacles in the way of a successful invocation of estoppel.
However,
even if it be assumed in favour of respondent that estoppel was
pertinently raised in the papers (the matter came before
the court a
quo by way of motion proceedings) and that all the necessary factual
requirements for the doctrine to be applicable
were canvassed, this
is not a case in which it can be allowed to operate. It is settled
law that a state of affairs prohibited
by law in the public interest
cannot be perpetuated by reliance upon the doctrine of estoppel. (See
Trust Bank van Afrika Bpk v
Eksteen
1964
(3) SA 402
AD
at 411 H – 412 B.)
[12]
This is such a case. It was not the Tender Board which conducted
itself in a manner which led respondent to act to its detriment
by
concluding invalid leases of property specially purchased and altered
at considerable expense to suit the requirements of the
Department.
It was the Department. If the leases are, in effect, “validated”
by allowing estoppel to operate, the Tender
Board will have been
deprived of the opportunity of exercising the powers conferred upon
it in the interests of the taxpaying public
at large. Here again the
very mischief which the Act was enacted to prevent would be
perpetuated. (Cf Strydom v Die Land-en Landboubank
van SA
1972
(1) SA 801
(AD)
at 815 E – F.)
[13] This is not a
case in which “innocent” third parties are involved. It
is a case between the immediate parties to
leases which one of them
had no power in law to conclude and had been deprived of that power
(if it ever had it) in the public
interest. The fact that respondent
was misled into believing that the Department had the power to
conclude the agreements is regrettable
and its indignation at the
stance now taken by the Department is understandable. Unfortunately
for it, those considerations cannot
alter the fact that leases were
concluded which were ultra vires the powers of the Department and
they cannot be allowed to stand
as if they were intra vires. “
[56]
The respondent’s defence of illegality must, therefore,
succeed.
COUNTER
APPLICATION
[57]
The counter claim is not in the alternative, but a substantial
application for a declarator and
a review.
[58]
The subject matter of the dispute between the parties, however, falls
within the law of contract
and not within the realm of administrative
law.
[59]
In view of the finding that the contract is, due to illegality,
unenforceable, a further declarator
in the same terms is, in my view,
untenable and stands to be dismissed with costs.
ORDER
In the premises, the
following order is issued:
1.
The application is
dismissed with costs, which include the costs of two counsel.
2.
The counter application
is dismissed with costs, which include the costs of two counsel.
N.
JANSE VAN NIEUWENHUIZEN
JUDGE
OF THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
DATE
HEARD PER COVID19 DIRECTIVES:
29
April 2022 (Virtual hearing)
DATE
DELIVERED PER COVID19 DIRECTIVES:
15
July 2022
APPEARANCES
For
the Applicant:
Adv A E Bham SC & Adv I L Posthumus
Instructed
by:
ENSafrica
Counsel
for the First Respondent: Adv G Badela
Instructed
by:
MJS inc. Pretoria
sino noindex
make_database footer start
Similar Cases
QS Online (Pty) Ltd v Minister of Public Works (24718/2021) [2022] ZAGPPHC 236 (13 April 2022)
[2022] ZAGPPHC 236High Court of South Africa (Gauteng Division, Pretoria)98% similar
Johannes v S (A146/2018) [2022] ZAGPPHC 391 (8 June 2022)
[2022] ZAGPPHC 391High Court of South Africa (Gauteng Division, Pretoria)98% similar
Lolafon (Pty) Ltd v Gauteng Provincial Liquor Board and Another (2023-046515) [2023] ZAGPPHC 584 (13 June 2023)
[2023] ZAGPPHC 584High Court of South Africa (Gauteng Division, Pretoria)98% similar
FLM SA (Pty) Ltd and Others v Gauteng Provincial Liquor Board and Others (Leave to Appeal) (17958/22) [2022] ZAGPPHC 591 (10 August 2022)
[2022] ZAGPPHC 591High Court of South Africa (Gauteng Division, Pretoria)98% similar
Sparepro (Pty) Ltd v National Regulator for Compulsory Specifications and Others (38549/2022) [2024] ZAGPPHC 527 (4 June 2024)
[2024] ZAGPPHC 527High Court of South Africa (Gauteng Division, Pretoria)98% similar