Case Law[2022] ZAGPPHC 741South Africa
South Durban Community Environmental Alliance and Another v Minister of Forestry, Fisheries and The Environment and Others (17554/2021) [2022] ZAGPPHC 741 (6 October 2022)
High Court of South Africa (Gauteng Division, Pretoria)
6 October 2022
Headnotes
Summary: Application for review and setting aside an environmental authorisation for the construction of a mid-merit combined gas cycle power plant in Richards Bay - applicant entitled to apply for a specific type of facility without applying for the construction of renewable energy power plant in the alternative - upstream greenhouse gas emissions not comprehensively considered at initial first application
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2022
>>
[2022] ZAGPPHC 741
|
Noteup
|
LawCite
sino index
## South Durban Community Environmental Alliance and Another v Minister of Forestry, Fisheries and The Environment and Others (17554/2021) [2022] ZAGPPHC 741 (6 October 2022)
South Durban Community Environmental Alliance and Another v Minister of Forestry, Fisheries and The Environment and Others (17554/2021) [2022] ZAGPPHC 741 (6 October 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2022_741.html
sino date 6 October 2022
FLYNOTES:
PAJA – PUBLIC PARTICIPATION AND LANGUAGE
Administrative
law – Review – Environmental authorisation –
Construction of gas power plant – Shortcomings
in public
participation process – Not catering for isiZulu
speakers in affected areas – Not rendering
decision invalid
– Authorisation not final and project subject to successive
applications – Order catering for
isiZulu in further notices
and participation –
Promotion of Administrative Justice Act
3 of 2000
.
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
(1)REPORTABLE:
NO
(2
)OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
DATE:
6 October 2022
Signature:
Case
No. 17554/2021
In
the matter between:
SOUTH
DURBAN COMMUNITY ENVIRONMENTAL
First Applicant
ALLIANCE
THE
TRUSTEES OF THE GROUNDWORK TRUST
Second Applicant
And
MINISTER
OF FORESTRY, FISHERIES AND THE
First Respondent
ENVIRONMENT
CHIEF
DIRECTOR: INTERGRATED
ENVIRONMENTAL
AUTHORISATIONS,
DEPARTMENT
OF ENVIRONMENTAL
AFFAIRS
Second Respondent
ESKOM
HOLDINGS SOC LTD
Third
Respondent
Coram:
MillarJ
Heard
on: 2 August 2022
Delivered:
6 October 2022 - This judgment was handed down
electronically by circulation to the parties' representatives by
email, by being
uploaded to the CaseLines system of the GD and by
release to SAFLII. The date and time for hand-down is deemed to be
14HOO on 6
October 2022.
Summary:
Application for review and setting aside an environmental
authorisation for the construction of a mid-merit combined gas
cycle
power plant in Richards Bay - applicant entitled to apply for a
specific type of facility without applying for the construction
of
renewable energy power plant in the alternative - upstream greenhouse
gas emissions not comprehensively considered at initial
first
application
-
authorisation granted not final and
subject to conditions which make the efficacy of the entire project
subject to additional linked
and successive applications -
shortcomings in public participation process identified and to be
addressed not rendering decision
invalid
-
application for review dismissed - order
granted to address
shortcomings
in public participation process - award for costs in applicants
favour.
ORDER
IT
IS ORDERED
:
1.
The application for review of the
granting of the EA and dismissal of the appeal in respect thereof is
dismissed.
2.
The respondents are ordered and directed
to:
2.1
Cause a copy of the EA and conditions
attached thereto to be published in the isiZulu language in at least
two newspapers circulating
widely within the Richards Bay area of the
KwaZulu Natal Province.
2.2
Ensure that in respect of all subsequent
linked and ancillary applications for EA's pertaining to the CCGPP,
all written notices
are similarly published in isiZulu as set out in
2.1 above and that in addition, translation facilities are made
available at any
public meetings to enable proper participation by
any person who speaks isiZulu and is not conversant in the English
language.
3.
The respondents are ordered to pay the
applicants costs of the application, jointly and severally, the one
paying the others to
be absolved, on the scale as between
party
and party which costs are to include the costs consequent upon the
employment of two counsel.
JUDGMENT
MILLARJ
1.
The
applicants are both non-profit and non-government organizations that
advocate for environmental justice. They bring the current
application and seek the reviewing and setting aside of the granting
of an environmental authorization
[1]
by the second respondent in favour of the third respondents for the
construction of a mid-merit
[2]
combined cycle gas power plant (CCGPP) in Richards Bay. They also
seek the review of the subsequent refusal of an appeal
[3]
to the first respondent against that decision.
2.
The respondents are the party who
applied for the environmental authorization (EA) - the third
respondent (ESKOM}, the second respondent
to whom the application was
made and who approved it (DEFF) and the first respondent, the
Minister who refused the appeal against
the grant of the EA.
3.
For convenience I will, in this
judgment, refer to the first and second applicants collectively as
SDEC and to the first and second
respondents as DEFF. I will refer to
the third respondent as ESKOM.
4.
The
DEFF and ESKOM oppose the application for review on the basis that
none of the 7 grounds upon which it has been advanced
[4]
can be said to impugn the decision to grant the environmental
authorization or the refusal of the appeal.
5.
The
grounds upon which the granting of the EA was appealed included a
number of grounds
[5]
which are
also grounds upon which the present review has been brought.
THE
STATUTORY SCHEME
6.
The
application brought by the third respondent for an EA for the
construction of the CCGP was brought in terms of the National
Environmental Management Act
[6]
(NEMA). NEMA provides a framework within which such development is to
take place. It recognizes the present economic and climatic
circumstances of the population as well as the consequences of
addressing those circumstances for future generations. It seeks
to
provide a balance for both
[7]
•
7.
NEMA provides a statutory framework for
the minimum conditions attendant upon the granting of EA's as well as
the relevant criteria
to be considered. These are set out in sections
24E and 24O respectively. It is through the lens of these two
sections that the
application by ESKOM and the granting of the EA
with attendant conditions and subsequent appeal and refusal thereof
is to be considered.
THE
DECISION AND THE APPEAL
8.
The decision to grant the EA on 23
December 2019 was not an unqualified one. There are 57 separate
conditions attached to the EA
which qualify and inform the
development for which it was granted.
9.
The conditions fall into three broad
categories and provide
inter a/ia
for
a recordal of statutory obligations (notification to interested and
affected parties and appeal procedures), limitations on
the EA (both
in terms of scope and validity), reporting and notification,
management, operation and site closure and decommissioning.
There are
23 special conditions some of which are relevant to the specific
grounds of review and I will deal with these where apposite
below.
THE
REVIEW
10.
The
present application for review is brought on the basis that the
decisions taken, both the initial one to grant the EA and the
subsequent dismissal of the applicants' appeal are administrative
action. This is not in issue between the parties or that the
present
review is to be considered in terms of the Promotion of
Administrative Justice Act
[8]
(PAJA).
11.
The
seven grounds of review upon which the applicants seek to impugn the
initial decision and refusal of the appeal are predicated
upon a
consideration of the grounds set out in sections
6(2)(b)
[9]
,6(2)(c)
[10]
,6(2)(e)(iii)
[11]
and 6(2)(f)(ii)(cc)
[12]
.
12.
The seven grounds of review are:
12.1.
Inadequate climate change impact
assessment
12.2
Inadequate consideration of need and desirability
12.3.
Failure to consider renewable
alternatives
12.4.
Failure to consider cumulative
environmental impacts.
12.5.
Inadequate public participation
12.6.
Inadequate water resources assessment
12.7.
Inappropriate wetland offset
13.
The seven grounds fall into three
categories. The first is that there was a failure to consider
alternative renewable sources of
power generation and the climate
change impacts of gas {the first, second and third grounds), the
second is noncompliance with
the provisions of NEMA and the
regulations and shortcomings in the environmental impact report (EIR)
and other reports submitted
with the application (the fourth, sixth
and seventh) and the third is the inadequate public participation in
the entirety of the
process (the fifth ground).
14.
Although there is in some instances an
overlap of grounds, broadly speaking the 1st, 2nd, 3rd, 4th and 6th
grounds of review fall
within section 6(2)(b). The 5
th
and 7th grounds fall within section 6(2)(c) and the 7th also within
section 6(2)(e)(iii). It was argued that the cumulative effect
were
all the grounds of review be to be upheld, but also in the event that
one or more only were upheld was that in terms of section
6(2)(f)(ii)(cc), the decision to grant the EA should be set aside.
15.
For convenience I do not intend to deal
with each of the grounds of review under a separate heading but will
do so in the respective
categories in which they fall.
THE
FAILURE TO CONSIDER RENEWABLE SOURCES OF POWER GENERATION AND THE
CLIMATE CHANGE IMPACTS OF A COMBINED CYCLE GAS POWER PLANT
16.
In considering Eskom's application, the
DEFF was required to consider in terms of section 24O(1)(b)(i)
"any
pollution, environmental impacts or environmental degradation likely
to be caused if the application is approved or refused."
17.
It was argued by the Applicants that the
climate change impact assessment was inadequate because:
17.1
Firstly,
it did not consider the use of renewable energy plants as an
alternative to the proposed CCGPP
[13]
.
17.2
Secondly,
it failed to assess the full life-cycle greenhouse gas emissions
which will be caused by the CCGPP in consequence of a
failure to
assess the emissions associated with the extraction of gas and its
transport to the CCGPP in Richards Bay
[14]
.
17.3
Thirdly,
the assessment of the climate change mitigation measures was
inadequate
[15]
and;
17.4
Fourthly,
it failed to assess the resilience of the Power Plant to climate
change
[16]
.
18.
It is not disputed that Eskom, in regard
to the EA sought for the CCGPP at Richards Bay did not in this
specific instance consider
the use of other renewable energy sources
at the particular site. It was submitted on behalf of DEFF and Eskom
that the decision
to apply for an EA for a CCGPP was at a particular
site, a matter eminently within the discretion of the party applying
for such
authorization.
19.
It was disputed that other sources and
in particular renewables such as solar or wind were desirable within
the greater context
of transitioning the Republic from a fossil
fuel-based energy generation system to a sustainable renewable
system. However, it
was argued that this did not mean that each and
every application should be predicated entirely upon the basis that
only renewables
should be considered. It was argued that the CCGPP
was a bespoke type of power generation source in that, firstly it
would fueled
by natural gas sourced, at least in anticipation, from
the recently discovered gas fields off the coast of Mozambique and
secondly,
that it was not designed to nor would it run for more than
a specified number of hours. The whole purpose of the CCGPP was to
provide
emergency power generation for relatively short periods of
time as and when required. On a practical level, none of the
renewable
sources were considered simply because these would not
fulfil the emergency generation role and function that the CCGPP was
intended
for. It is for this reason that the present application for
the EA was made specifically for a CCGPP.
20.
The argument is buttressed when regard
is had to section 240(1)(b) which requires the decision maker to take
into account
"all relevant
factors, which
may
include...."
[my
emphasis]. The section confers upon the decision maker a discretion
as to what may or may not be taken into consideration and
this
discretion must be exercised having regard to the specific
application for which the EA is made.
21.
It was argued by the DEFF that the
approach of the Applicants disregarded the specific role that the
CCGPP will play in the electricity
generation of the country. It is
specifically earmarked, and so approved, as a mid-merit facility to
produce electricity as and
when needed. Furthermore, it was
acknowledged that as coal as an energy source is being phased out,
natural gas is intended to
act as a bridge before renewable
alternatives are fully implemented.
22.
It was argued, that too hasty a
transition to renewable energy may have cataclysmic consequences. By
way of example, I was referred
to the failure of renewable energy
resources that it was stated led to a complete blackout in South
Australia during 2016 and in
Texas in the United States of America,
during September 2021 and February 2022.
23.
It is readily apparent that in
considering the matter, the DEFF considered the reasons why the
application had been made for the
specific EA and hence imposed 2
specific conditions in granting the EA as follows:
"33.
Proof of the availability of liquid natural gas to supply
Richards
Bay Combined Cycle Power Plant must be submitted to the Department,
the Chief Directorate:
Integrated
Environmental Authorizations prior to commencement of construction.
34.
Proof of Transnet SOC Ltd taking responsibility for the construction
of liquid natural gas (LNG) facility and gas pipeline must be
submitted to the Department, the Chief Directorate: Integrated
Environmental
Authorizations prior to commencement of construction.
24.
Having regard to these 2 conditions, the
entire project and the EA granted for it is entirely dependent upon
compliance with these
conditions. While the first is factual - it is
at least at this juncture a matter which falls outside the
jurisdiction of the Republic
and any decision made to grant an EA. It
is however subject to the second which is itself in turn dependent
upon the granting of
a separate EA.
25.
Since the granting of an EA is not the
exclusive domain for renewable energy projects, Eskom was entitled to
submit its application
for the CCGPP without an alternative. Having
said that, the specific exigencies for a CCGPP were considered and
the conditions
referred to above imposed. Accordingly, this ground of
review cannot succeed.
26.
The applicants argued that the
Environmental Impact Report which was submitted in regard to the
CCGPP was required to deal with
all
the environmental impacts
associated
with the project.
27.
On this interpretation, both the
extraction of gas in Mozambique, the shipping of it in international
waters or through the territorial
waters of another or other state/s
or any pipeline constructed and passing through the territory of the
Republic of Mozambique
would fall within the peremptory requirements
of NEMA. These it was argued are the 'upstream' impacts.
28.
I
was referred to Earthlife Africa Johannesburg v Minister of
Environmental Affairs
[17]
('Earthlife') as authority for this proposition. While ordinarily I
agree that this would be the case, the present matter is
distinguishable
by reason of the fact that Earthlife concerned the
construction of a coal fired power station at Lephalale in the
Limpopo Province,
within the Republic and sourcing coal from within
the Republic
[18]
. The present
case concerns a fuel source extracted outside of and to be
transported to the Republic either by sea or by pipeline,
at least
part of which would be through another independent state.
29.
To require such a broad consideration of
'upstream effects' as a precursor to the granting of any EA would
likely create an almost
impossible situation - requiring the making
of any decision on an EA for a project that it was anticipated would
or even may source
fuel from outside the Republic, dependent upon an
assessment to be made, as in the present case, years before any
authorization
for the first step in proceeding with such a project
was even granted and subject to the laws or any changes of another
state.
The specific source of the gas has not been identified nor can
it reasonably be, so far in advance.
30.
The Liquefied Natural Gas (LNG) terminal
infrastructure at the port and the gas supply pipeline to the
boundary fence of the Power
Plant does not form part of the scope of
this assessment, nor does the power line connection to the grid.
31.
This Environmental authorization
application focuses only on this Power Plant and associated
infrastructure inside Eskom's boundary
fence on site 1D of the
Richards Bay IDZ. Consideration of impacts in this regard would need
to be included within the separate
EIA process to be undertaken for
the gas supply infrastructure;
32.
This interpretation is to my mind
entirely consistent with a global view of climate change and the
general purpose for which NEMA
and similar legislation was enacted.
It however is not consistent with the specific purpose of NEMA which
is to recognize that
the context within which NEMA is to be applied
must be informed by the extant needs of the South African population.
33.
Accordingly, Eskom was entitled to apply
for the granting of an EA for the construction of a specific type of
power plant. While
the extraction and delivery of the gas for the
CCGPP, and the attendant GHG emissions, does not fall within the
specific parameters
of the project for which the EA was sought,
specific conditions were nevertheless imposed relating to this
particular concern as
set out in paragraph 23 above.
34.
For the reasons set out in paragraph 24,
the DEFF was cognizant of the concerns relating to the extraction and
transportation of
the gas and the GHG emissions associated therewith
and subjected those concerns to a separate and distinct EA
application. It thus
cannot be said that relevant considerations were
neither brought to the attention of the DEFF nor that they ignored
them or took
irrelevant considerations into account in arriving at
the decision they did on this aspect. The consideration of the GHG
emissions,
as a whole and incorporating both the pipeline as well as
the CCGPP will be considered when the EA for the construction of the
pipeline is sought. The EA for the CCGPP is but the first link in a
chain of EA's required before any construction can commence.
For this
reason, this ground of review cannot succeed.
35.
What of the climate change impacts for
activities to be undertaken at the Richards Bay site and surrounds? A
full assessment of
the climate change impacts of the proposed project
form part of the EIA Report.
36.
The Applicants contended that there was
an inadequate assessment in the climate change measures. The Climate
Change Report considered
the environmental and social costs of the
GHG that will be emitted during construction, operation and
decommissioning of the Power
Plant. The report is comprehensive and
concludes as follows:
''This
study concludes that while the proposed CCPP power plant
as
a
single source will increase the
national greenhouse gas inventory, mitigation options to reduce its
emissions are available. The
most important aspect of the propose(d)
project
is
that it has the potential to enable wider de-carbonization of the
national grid through enabling the update of variable renewable
energy technologies.
As
such
it is suggested here that the proposed CCPP plant be load-following
capability of the plant be used to maximize the update
of
intermittent renewable energy in the South African grid. It is the
view of this report that the proposed CCPP powerplant is
the best
technology option and will not materially result in any direct local
climate change impacts, subject to the implementation
of
appropriate
mitigation measures."
37.
The DEFF respondents specifically
considered all the reports submitted and in particular the Climate
Change Assessment Report. On
appeal, and after having dealt with the
concern over the way in which the report had addressed the climate
change impacts, it was
found that the proposed CCGPP is the best
technology option, that it will not materially result in any direct
local climate change
however subject to the implementation of
mitigating measures such as the switching to alternative biofuels and
carbon capture and
storage.
38.
Thereafter
the Minister, the functionary with the expertise in her Department at
her disposal, came to the conclusion that there
is no merit in this
ground, and rejected the Ground of Appeal. In doing so the Minister
was mindful of the decision in Earthlife
[19]
having been referred to the Judgment by the Applicants in their
appeal.
39.
In
the present case, a proper Climate Change Impact Assessment
[20]
was conducted, a comprehensive report was filed. It was considered by
the Department in the first instance and thereafter by the
Minister
on appeal. Having regard to the full content of the report, the
Minister was satisfied that the proposed project would
not materially
add to the greenhouse gas emissions inventory of the Republic of
South Africa.
40.
Are the conditions attached to the EA to
address the applicants concerns regarding the upstream and other
effects of GHG emissions
arising from the extraction and transport of
the gas of no consequence or practical effect?
41.
It was argued by the applicants that
Earthlife held that it was impermissible to issue an environmental
authorization where the
environmental impact assessment omitted
relevant considerations, subject to a condition which purports to
remedy that shortcoming.
42.
It
was argued firstly, that it was more appropriate to rather adjourn
the application and the applicant must be directed to conduct
the
necessary assessment.
[21]
This
so it was argued was due to the fact the once the EA was issued the
decision maker was functus officio and cannot withdraw
the
authorization even if the subsequent assessments show that the
authorization should not have been granted.
[22]
43.
And secondly, the condition requiring
proof of the availability of gas does not require public
participation in respect of the source
of the gas or for the
assessment of the impacts associated with the source of the gas.
Essentially, so it was argued, this condition
could be fulfilled by
the proof of the availability of any gas irrespective of the
environmental impacts associated with the use
of that gas.
44.
In the present matter, unlike in
Earthlife, there was an EIR submitted with the application. The EA
granted in the present instance
is not a final authorization for the
commencement of the CCGPP without more.
45.
The sourcing and delivery of gas to the
Richards Bay site is a
sine qua non
for the commencement and indeed
efficacy of the entire project. The entire CCGPP project is a chain
which requires every link in
that chain to be joined before the
project can be undertaken at all. It seems to me to be eminently
reasonable that an EA would
be sought in stages, the first being in
respect of the site where the CCGPP is to be constructed.
46.
The imposition of conditions for readily
apparent and distinctly different links in the chain, which
conditions will require that
each link is subject to obtaining an EA
is entirely rational and reasonable.
47.
Such a decision, is reasonable in light
of the particular exigencies of the proposed project and maintains
the oversight of compliance
with NEMA and the Regulations as an
integral requirement before any decision in regard to the project as
a whole, becomes final
and so too this particular ground of review
must fail.
FAILURE
TO ASSESS THE ENVIRONMENTAL AND SOCIAL COST OF EMISSIONS
48.
The parties were in agreement that there
is no universally accepted method to quantify the cost of GHG
emissions. The Applicants
argued that there was an outright failure
to consider these costs notwithstanding there being several
approaches that could have
been adopted.
49.
The DEFF for its part contended that
there had been consideration of these costs but that the EIR and
other specialist reports had
to be viewed holistically on a
consideration of the entirety of what was considered.
50.
Since there is no universally accepted
method to quantify the cost of GHG emissions, it cannot be said that
the DEFF respondents,
in considering the matter and taking a
'holistic view' based on a conspectus of all the reports can be said
to have failed to consider
the cost of GHG emissions or taken
irrelevant considerations into account in coming to the decision that
the overall cost was acceptable.
For this reason, I find that this
ground of review cannot succeed.
INADEQUATE
ASSESSMENT OF RESILIENCE TO CLIMATE CHANGE
51.
An
assessment of climate change impacts of a project must include both
the project's impact on climate change and the project resilience
to
climate change.
[23]
52.
The Climate Report noted that climate
change may cause warming and drought in KwaZulu-Natal and that this
may require the Power
Plant to use seawater for cooling. This is of
course entirely speculative – not as far as climate change
affecting Kwazulu
Natal but as far as whether or not the CCGPP will
require sea water for cooling or other purposes.
53.
The
parties differ in regard to the efficacy of the water usage report
submitted - the applicants contending that the reports obtained
by it
were to be preferred over the report submitted by ESKOM. It is
readily apparent that the reports are premised on differing
assumptions - particularly in regard to the anticipated water
consumption based on operational time. This is a matter that falls
squarely within the domain of the experts
[24]
and this court is not able to prefer one over the other.
[25]
54.
However, the utilization rate of the
CCGPP is limited by a condition attached to the EA which provides
that:
"52.
The facility must operate as a mid-merit, as this is the chosen
operating mode."
and
accordingly, it cannot be said that the DEFF failed to consider
relevant information before it. The condition referred to above
is
mitigatory of the concerns raised by the SDEC expert and so this
ground of review also fails.
ALLOCATION
OF CAPACITY TO OTHER INDEPENDENT POWER PRODUCERS
55.
In September 2020 (before the Appeal
Decision was taken) the Minister of Mineral Resources and Energy
published a determination
("the 2020 Determination") in
terms of section 34 of the Electricity Regulation Act. This
determination catered for the
implementation of the IRP 2019 by
providing for 3000MW of new power generation from gas. However, it
expressly recorded that this
capacity was to be provided by
independent power producers.
56.
It was argued that when granting the EA,
the Minister gave no consideration to the fact that power generation
capacity which Eskom
would provide via the CCGPP had already been
allocated for provision by independent power producers. This is a
matter of policy
which is subject to modification from time to time.
It must be borne in mind that the application for which the EA has
been granted
is not granted on the basis that ESKOM is obligated to
implement the approved project.
# NONCOMPLIANCE
WITH THE PROVISIONS OF NEMA AND THE REGULATIONS AND ALLEGED
SHORTCOMINGS IN THE ENVIRONMENTAL IMPACT REPORT (EIR)
AND OTHER
REPORTS SUBMITTED WITH THE APPLICATION
NONCOMPLIANCE
WITH THE PROVISIONS OF NEMA AND THE REGULATIONS AND ALLEGED
SHORTCOMINGS IN THE ENVIRONMENTAL IMPACT REPORT (EIR)
AND OTHER
REPORTS SUBMITTED WITH THE APPLICATION
FAILURE
TO CONSIDER CUMULATIVE ENVIRONMENTAL IMPACTS
[26]
57.
The
Applicants asserted that the final EIR's assessment of the cumulative
impacts
[27]
associated with
the Power Plant was deficient in that:
57.1
Firstly, that it did not consider the
cumulative impact on air quality of the Power Plant together with the
nearby Mondi Paper Mill
and South 32 Hillside Aluminium Smelter.
These it was argued are significant sources of pollution and should
have been included
as part of the assessment of cumulative impacts.
57.2
Secondly,
that the conditions of the EA do not include any conditions relating
to the assessment of the pipeline's impact. In any
event, if a
subsequent assessment were to show that these impacts indicate that
the Power Plant should not be pursued, the Department
and Minister
and
functus
officio
and
cannot withdraw the EA
[28]
.
57.3
Thirdly, the Final EIR does not consider
the cumulative impacts arising from various other proposed projects
in the area. For example,
the construction of a 400MW gas to power
plant in Richards Bay.
58.
The approach to assess cumulative
impacts requires a holistic view, an interpretation and analysis of
the biophysical, social and
economic systems and is limited by the
current methods used for identifying and analysing
cumulative
effects.
59.
Firstly, as to the air quality having
regard to the Mondi Paper Mill and the Hillside Aluminium Smelter,
the Air Quality Impact
Assessment specifically identified and
assessed the cumulative impact of the proposed facility and ambient
air quality concentrations.
60.
It is to be noted that while Chapter 8
of the final EIR dealt with the cumulative effects of the CCGPP only,
Chapter 9 of the Final
EIR sufficiently dealt with the assessment of
potential cumulative impacts taking into account surrounding
developments. In the
circumstances it cannot be fairly asserted that
there was no consideration taken of the cumulative impacts taking
into account
surrounding developments.
61.
Secondly, while the cumulative impacts
arising from the proposed pipeline were not considered, they were
adequately considered,
and provision made for an assessment of these
in special conditions 33 and 34 attached to the EA. This has already
been discussed.
However generally, in response to these concerns, the
DEFF and ESKOM pointed to the conclusion in the final EIR which
contained
the following conclusions regarding cumulative impacts, and
which found that:
61.1
The CCGPP will not result in
unacceptable loss of threatened of protected plant species;
61.2
It will not result in unacceptable loss
of water resources provided that a suitable wetland and biodiversity
of the plan is adopted
and implemented;
61.3
The CCGPP will not result in the
complete or wholescale change in sense of place and character of the
area nor will the project
result in unacceptable visual intrusion,
largely as a result of the zoning of the site for industrial
development;
61.4
The CCGPP will not significantly
increase the negative impact on socio-economic environment provided
that appropriate mitigation
measures are implemented. In contrast
there will be numerous positive impacts that can be expected as
result of the proposed CCPP
in terms of production and employment
benefits.
61.5
The project as a whole will contribute
towards a reduction in greenhouse gas emissions in general resulting
from an alternative
energy generation perspective when compared to
coal energy generation and will aid the country in meeting the
commitments made
under the COP21 Agreement;
61.6
The project will contribute
significantly to traffic volumes which can be accommodated on the
existing road network.
61.7
The project will not contribute to the
loss of heritage sites as no heritage sites of significance will be
affected by the CCGPP;
and
61.8
The project will not contribute
significantly to the potential impacts on surrounding human
populations and is considered of low
significance.
62.
Accordingly, the cumulative impacts
associated with the construction operation of the proposed Richards
Bay CCGPP and other developments
within the Richards Bay Industrial
Development Zone were considered to be acceptable.
63.
Thirdly
and in regard to the cumulative impact of other proposed developments
within the area, none of the proposed projects received
authorization
and the one that did lapsed.
[29]
There is presently only one project - a 320 MW liquid gas risk
mitigation Power Plant for which Phinda Power Producers sought
authorisation: the application for EA was submitted and granted. The
decision is presently on appeal however the application was
only done
after the final EIR for the CCGPP was concluded.
64.
There is in the circumstances no merit
to the claim that the cumulative environmental impacts, for the CCGPP
itself, were not considered
and so this ground of review also fails.
INADEQUATE
WATER RESOURCES ASSESSMENT
65.
The Seventh Review Ground is that the
Water Resources Assessment ("WRA") was inadequate. The
deficiencies in the WRA were
identified by one of the Applicants'
experts, Dr Day. This report was not available at the time that the
EA was initially granted
and similarly when the decision was taken on
Appeal. This was not one of the grounds of appeal that were proffered
or considered.
66.
The water resources assessment report
that was submitted with the EIR was found to be adequate for the
decision maker to make an
informed decision and also for
consideration of the appeal. It does not behove the applicants to now
raise new matter and seek
to rely on evidence which was not available
to the DEFF when the decision was taken, and the appeal considered.
For this reason,
this ground of review does not succeed.
INAPPROPRIATE
WETLAND OFFSET
67.
The WRA and the Final EIR recommend a
wetland offset to the unavoidable loss of wetlands which will be
caused by the Power Plant.
The applicants take issue with the
provision for the wetland offset, primarily because it does not
impose meaningful obligations
upon ESKOM and secondly because the
plan does not cater for public participation.
68.
The proposed offset plan is subject to a
number of conditions in the EA as follows:
"35.
The preliminary Wetland Offset Plan dated January 2018 (Updated
February 2019 (with Option 2 indicated as the preferred
option must
be finalized in consultation with City of uMhlathuze Local
Municipality and Ezembelo (KwaZulu Natal Wildlife) prior
to
commencement.
36.
The final Wetland Offset Plan must be submitted to the Department,
Chief Directorate: Integrated Environmental Authorizations
for
written approval prior to commencement of the activity.
"
69.
It was argued that neither the DEFF nor
ESKOM point to any meaningful obligation placed on Eskom by the
proposed wetland offset
plan and that there is in reality no
connection between the CCGPP and the proposed offset plan. This is
nothing other than an attempt
to pass off the activities of KZN
Ezemvelo as an offset.
70.
The
EA and the conditions attached to it must be read together with the
obligations imposed upon a person who is the holder of or
issued with
an EA - as set out in sections 24N(7)(a)
[30]
and (d)
[31]
which impose
direct obligations upon ESKOM regarding environmental impacts. It is
thus not correct that there are no obligations
on Eskom and for this
reason this ground of review does not succeed.
71.
None of the conditions which have been
attached to the EA provide for public participation. This aspect will
be dealt with below.
PUBLIC
PARTICIPATION
80.
It
is one of the foundational principles of NEMA that the participation
of all interested and affected parties must be promoted
and the
participation of disadvantaged people must be ensured.
[32]
81.
Section 23(2) of NEMA provides for
"adequate and appropriate
opportunity for public participation in decisions that may affect the
environmenf'.
82.
The
Notice requirements are set out in Regulation 41
[33]
.
They require:
82.1
there must be a notice board
conspicuously placed at the boundary of the proposed site and at any
alternative site. The board must
contain specified information and
must be of a certain size. If the activity in question is a linear
activity or ocean-based activity,
the notice board requirements may
be inappropriate and other arrangements may be agreed upon with the
competent authority;
82.2
written notice must be given to owners
or occupiers that are either adjacent to the site where activity is
to be undertaken or to
any alternative site where activity is to be
undertaken;
82.3
written notice must also be given to the
local councillor, the municipality and any organ of state having
jurisdiction over any
aspect the activity; and any other party
required by the competent authority;
82.4
an advertisement must be placed in at
least one local newspaper or, if the impact of the activity will
extend beyond the boundary
of the local municipality, in at least one
provincial newspaper or national newspaper, or in the Government
Gazette; and
82.5
using reasonable alternative methods, as
agreed to by the competent authority, in those instances where a
person is desirous of
but unable to participate in the process due to
illiteracy; disability;
or any other
disadvantage.
(my underlining)
83.
Regulation 42 provides for the opening
and maintenance of a register of interested and affected parties. The
people listed on the
register include those who have attended
meetings or have submitted written comments as well as those who have
requested that their
names be included on the register. This also
includes
all organs of state with jurisdiction in respect of the activity must
be listed as interested and affected parties.
84.
The
public participation process must be facilitated in a manner that
provides all potential interest and affected parties a reasonable
opportunity to comment on the proposed project.
[34]
85.
The
2017 Public Participation Guidelines
[35]
provide that:
85.1
The level of public participation must
be informed by the characteristics of the potentially affected
parties.
85.2
The method of communication must be an
effective method that will easily reach the intended audiences.
85.3
The language used must provide all
potential interested and affected parties a reasonable opportunity to
comment without unnecessary
difficulty.
86.
The final EIR notes that the most
commonly spoken language in the affected areas is isiZulu (with 79%
of people speaking that language)
and that affected region includes
traditional areas.
87.
Somewhat surprisingly, and despite this
the public participation process did not include any notices, boards,
or advertisements
(whether print or radio) in isiZulu, and there was
no indication of any attempt being made invite consultation directly
by the
non-English speaking communities in traditional areas.
88.
ESKOM
contends that this objection amounts to a "pedantic"
approach. The DEFF contend that these deficiencies should be
overlooked because a public participation process was followed as
part of the local municipality's integrated development plan
and
furthermore no registered interested or affected party requested the
use of any other additional languages
[36]
.
89.
The public participation process that
was followed in the present matter incorporated:
89.1
Two public meetings were convened, a
morning session was held on 27 March 2019 at Empangeni Public Library
and an evening session
was held 26 March 2019 Premier Hotel in
Richards Bay. These sessions were held during the 30-day review
period of the EIA Report
(revision 0). The public meetings were
advertised in The Mercury and the Zululand Observer on 21 March 2019,
as well as in The
Rapport and in The Sunday Times on 24 March 2019.
Registered interested and affected persons and NGO's were notified of
the public
meetings in writing.
89.2
The consultations and public meetings
allowed for a process wherein interested and affected parties were
given opportunity to comment
on, or raise issues relevant to, the EA
application process.
89.3
Key Stakeholder Workshop held at
Richards Bay IDZ with the following participants:
89.3.1
Richards Bay Industrial Development Zone
(RBIDZ);
89.3.2
City of Mhlathuze Local Municipality;
89.3.3
King Cetshwayo District Municipality;
89.3.4
Department of Water and Sanitation;
89.3.5
KwaZulu-Natal DFFE;
89.3.6
Ezemvelo Wildlife;
89.3.7
Mondi;
89.3.8
Transnet; and
89.3.9
Richards Bay Clean Air Association.
90.
Furthermore, it was argued,
throughout the process no interested or affected person requested
notifications and or correspondence
in any other language, including
isiZulu, and this included Groundwork, Friends of the Earth, South
Africa which on 26 August 2019
made various comments on behalf of the
community and in relation to the CCGPP but in any event, because the
municipality followed
a public participation process before the
publishing of its integrated development plan. The project site,
Phase 1D of the Richards
Bay IDZ has been specifically reserved for a
gas plant, and the municipality is in favour of the proposed
development.
91.
Additionally, prior to the scoping
report, ESKOM undertook the Compilation of a Background Information
Document (BID) for the project
in order to provide information
regarding the Richards Bay Power Plant and the EIA process. The BID
was distributed to identified
stakeholders and l&APs, placed at
public places such as libraries and was also made available
electronically on the Savannah
Environmental website.
92.
The DEFF argues that the absence of
publication in isiZulu was never raised by the Applicants, either in
the process of objecting
to the application for the EA, nor in the
appeal lodged to the Minister. It was argued that had it been raised
at any of these
stages, it would have been a simple matter of
remitting it back to the EAP, with an instruction to place
advertisements and publications
in isiZulu.
93.
In
Federation of South African Fly Fishers
[37]
,
in the context of public participation in environmental processes,
this Court held:
"Public
participation in democratic process is not the exclusive preserve of
educated members of society who can read English,
or the privileged
few who have access to the internet. Participative democracy is one
of the foundational values of the Constitution
and everyone should be
encouraged and enabled to participate".
94.
The
DEFF's argument is similar to the argument advanced by Shell
Sustaining
the Wild Coast NPC,
[38]
where
it relied on advertisements placed in newspapers that were in English
and Afrikaans, and not in isiZulu or isiXhosa to notify
the public
about the proposed project. The Court dismissed these arguments,
finding,
inter
alia
:
"...
a
person
who does not know of the process cannot be expected to register and
participate in the process as an interested and affected
person.
[39]
...
those
who cannot read English or Afrikaans were excluded from the
consultation process.
[40]
Meaningful
consultation entails providing communities with the necessary
information on the proposed activities and affording them
an
opportunity to make informed representations.
[41]
"
95.
The arguments of the DEFF and Eskom must
fail. It is self-evident that in the absence of publication in any
language other than
English, it is highly probable anyone who did not
speak English would have become aware of the public participation
process and
register as an interested and affected party.
96.
Furthermore, the making available of
information at either libraries or on the internet has as an express
prerequisite for access
to that information a certain level of
education and ability to access the internet. For those who are not
conversant in English,
notwithstanding that they may be sufficiently
educated and have access to the internet, even this is of no
assistance.
97.
In
the circumstances while the public participation process did comply
procedurally with the requirements for public participation
set out
by NEMA and the EIA Regulations - both in respect of the EA process
generally and specifically regarding the wetland offset,
I find that
it did not do so adequately
[42]
.
There is accordingly some merit in this ground of review.
THE
REMEDY
98.
The present application for an EA for
the CCGP is but the first in a chain of inextricably linked
applications, all of which must
pass muster before there can be any
commencement of construction or implementation of any of the proposed
measures.
99.
It
is probable that further applications, such as that for the gas
pipeline from the port terminal to the CCGPP, will also be subject
to
conditions - at the very least in respect of the assessment of both
upstream and downstream GHG emissions. Those further applications
will take into consideration other linked parts of the total project
for which EA's have been granted. Additionally, all the required
reports were submitted and considered. Where appropriate pertinent
and relevant conditions were attached to the EA and thus it
cannot be
said that there was no
'rational
objective
basis
justifying
the connection made by the administrative decision maker between
the material available and the conclusion arrived
at.
'
[43]
100.
I have found the 1st to 4th and 6th to 7th grounds of review are
without merit and cannot succeed. For the reasons I have stated
above
I am of the view that the 5th ground of review has some merit.
101.
Were it not for my finding that the
present EA for the construction of the CCGPP is the first link in a
chain of successive applications,
the shortcomings in the public
participation process may have warranted setting aside the decision
to grant the EA.
102.
However,
to do so in the present circumstances would not serve either the
interests of any of the parties or for that matter the
public at
large. In my view it would be just and equitable
[44]
to make an order that will ensure proper public participation in all
further, ancillary, and/or linked applications for EA's relating
to
the construction and operation of a CCGPP in Richards Bay. For this
reason the concerns raised by the SDEC and the public’s
right
to participate in the process has not been rendered nugatory
notwithstanding the shortcomings in the public participation
part of
the NEMA process.
COSTS
103.
While the SDEC have not been successful
in their review to set aside the EA in its entirety, they have raised
several important
issues - the most significant of which is that
related to the public participation. While in the present matter the
failure to
advertise and notify the public in a language other than
English is not determinative of participation in the CCGPP project as
a whole - because of the successive and linked applications for EA's
that must still be brought, the cavalier approach of the DEFF
and
Eskom to this aspect is to be deprecated.
104.
It
offers no answer to say that documents would have been furnished or
adverts placed in isiZulu had it been requested. It is self-evident,
as stated in Sustaining the Wild Coast NPC
[45]
,
that if people do not know about a process, then they cannot
participate in it.
105.
The DEFF and Eskom criticized the SDEC
for raising this ground of review in this application and not doing
it sooner. Had it been
raised sooner, they may well have addressed
it, but the fact remains that some 79% of the people directly
affected by the decision
were not given notice in their mother tongue
of the process and invited to participate.
106.
Were it not for the present application,
the failure to ensure a proper and all inclusive public
participation process may
have gone unrecognized in not only the
present application but also in respect of all subsequent and linked
applications for EA's
relating to the CCGPP, the pipeline and other
ancillary facilities.
107.
While
the application for review has not been successful in setting aside
the decision to grant the EA for the CCGPP, it has brought
to the
fore the deficit in the public participation process - an essential
element central to the legitimacy of the entire application
process
[46]
. For this reason,
I am of the view that the costs ought not to follow the result and
that it would be just and equitable that,
costs should appropriately,
in the exercise of my discretion, be awarded in favour of the SDEC.
108.
In the circumstances it is ordered:
108.1
The application for review of the
granting of the EA and dismissal of the appeal in respect thereof is
dismissed.
108.2
The respondents are ordered and directed
to:
108.2.1
Cause a copy of the EA and conditions
attached thereto to be published in the isiZulu language in at least
two newspapers circulating
widely within the Richards Bay area of the
KwaZulu Natal Province.
ii.
108.2.2
Ensure that in respect of all subsequent
linked and ancillary applications for EA's pertaining to the CCGPP,
all written notices
are similarly published in isiZulu as set out in
106.2.1 above and that in addition, translation facilities are made
available
at any public meetings to enable proper participation by
any person who speaks isiZulu and is not conversant in the English
language.
108.3
The respondents are ordered to pay the
applicants costs of the application, jointly and severally, the one
paying the others to
be absolved, on the scale as between party and
party which costs are to include the costs consequent upon the
employment of two
counsel.
A
MILLAR
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION, PRETORIA
HEARD
ON:
2 AUGUST 2022
JUDGMENT
DELIVERED ON: 6 OCTOBER 2022
COUNSEL
FOR THE FIRST AND
SECOND
APPLICANTS:
ADV. A GABRIEL SC
ADV.
I LEARMOTH
INSTRUCTED
BY: REFERENCE:
JACOBSON & LEVY INCORPORATED
MR
J LEVY
COUNSEL
FOR THE FIRST AND
SECOND
RESPONDENTS:
ADV. C ERASMUS SC
ADV.
M VlMBI
INSTRUCTED
BY: REFERENCE:
THE STATE ATTORNEY PRETORIA
MR
LT CHOKWE
COUNSEL
FOR THIRD RESPONDENT: ADV. P JARA·
INSTRUCTED
BY: RENQE FY INCORPORATD
REFERENCE:
MS RENQE
[1]
Granted on 23 December 2019
[2]
Mid-merit electricity generation capacity refers to the generation
of electricity which is adjusted according to the fluctuations
in
demand in the national grid. Conversely, baseload electricity
generating capacity refers to the generation of electricity
continuously for all hours of the day and night in order to satisfy
the minimum demand required in the national grid.
[3]
The appeal was refused on 13 October 2020
[4]
The applicants originally made out a case for 9 grounds of review in
their founding papers but by the time that the application
was heard
they had pared this down to 7 and it is these upon which the
determination of the application was decided.
[5]
The grounds upon which the appeal was brought included that (i)
there was a failure to consider alternatives to the proposed
project, (ii) that a combined gas cycle power plant was neither
necessary nor desirable, (iii) there had been a failure to
adequately consider climate change impacts on the project, (iv)
there had been failure to consider the cumulative impacts of the
project. (v) the authorization had been granted in the absence of
material information, and (vi) that the issue of the authorization
was in contravention of both NEMA and PAJA.
[6]
Act 107 of 1998
[7]
The preamble to NEMA states inter alia that “…
the
State must respect, protect, promote and fulfil the social, economic
and environmental rights of everyone and strive to meet
the basic
needs of previously disadvantaged communities; inequality in the
distribution of wealth and resources, and the resultant
poverty, are
among the important causes as well as the results of environmentally
harmful practices, sustainable development
requires the integration
of social, economic and environmental factors in the planning,
implementation and evaluation of decisions
to ensure that
development serves present and future generations; everyone has the
right to have the
environment
protected, for the benefit of present and future generations
”
[8]
No 3 of 2000
[9]
in terms whereof a mandatory and material procedure or condition
prescribed by an empowering provision was not complied with.
[10]
in terms whereof the action was procedurally unfair.
[11]
in terms whereof the action was taken because irrelevant
considerations were taken into account or relevant considerations
were not considered.
[12]
in terms whereof the action itself was not rationally connected to
the information before the administrator.
[13]
Section 24O(1)(iv)
[14]
Section 24(1)(b)(ii)(bb) & (iv)
[15]
Section 24(1)(b)(ii)(aa) & (bb)
[16]
ibid
[17]
2017 2 ALL SA 519
(GP) para 94
[18]
It is not specifically stated in the judgment that the coal was to
be sourced from within the Republic but given the proximity
of
Lephalale to the Republic’s vast coal resources this was the
likely source.
[19]
The decision in Earthlife is distinguishable from that taken in the
present matter because in that case it was common cause that
no
climate change impact assessment report had in fact been submitted.
(See the judgment at paragraphs [87] and [101]. see also
Pharmaceutical Manufacturers Association of SA & Another: In re
ex parte President of the Republic of South Africa &
Others
[2000] ZACC 1
;
2000
(2) SA 674
(CC) at paras [82] – [83] and [85] – [86].
[20]
Undertaken in accordance with NEMA and the Regulations. The
assessment was, notwithstanding the absence of any nationally
approved
or widely adopted standards, prepared in accordance with,
at least as far as the carbon footprint and GHG’s is
concerned,
in accordance with the ISO/SANS14064-1 standard.
[21]
Earthlife Africa Johannesburg v Min of Environmental Affairs
2017 2
ALL SA 519
(GP) para 107
[22]
ibid
Earthlife paras [113] to [116]
[23]
Ibid Earthlife paras [6], [49] & [95].
[24]
Buffalo Freight Systems (Pty) Ltd v Crestleigh Trading (Pty) Ltd and
Another
2011 (1) SA 8
at para [20]
[25]
Durbanville Community Forum v Minister for Environmental Affairs and
Development Planning, Provincial Government Western Cape,
and Others
2015 JDR 0172 (WCC)
[26]
EIA Regulations, item 1.
[27]
“
The
past, current and reasonably foreseeable future impact of an
activity, considered together with the impact of activities
associated with that activity, that in itself may not be
significant, but may become significant when added to the existing
and reasonably foreseeable impact eventuating from similar or
diverse activities
”.
[28]
Ibid
Earthlife paras. [113] to [116].
[29]
The 2800MW liquid gas Nseleni Independent Floating Combined Cycle
Gas Turbine Power Plant for Anchor Energy (Pty) Ltd; the 2100MW
combined cycle gas for Canopus Energy (Pty) Ltd was refused on 30
May 2016; The Karpowership SA (Pty) Ltd application was refused
on
23 June 2021. Regarding the gas pipeline extension project for which
Sasol Gas Ltd sought authorization, the application lapsed.
[30]
“
(a)
must at all times give effect to the general objectives of
integrated environmental management laid down in section 23”
[31]
“
(d)
must monitor and audit compliance with the requirements of the
environmental management programm
e”
[32]
See NEMA sections 2(4)(f), 23(2)(d) & 24(4)(a)(v)
[33]
Environmental
Impact Assessment Regulations, 2014
published under GN 982 in GG
38282 of 4 December 2014.
[34]
Regulation 41
(6)(b) which specifically provides that “
participation
by potential or registered interested or affected parties is
facilitated in such a manner that all potential or
registered and
affected parties are provided with a reasonable opportunity to
comment on the application or proposed application
.”
[35]
Regulation 41(2) of the EIA Regulations requires that the public
participation process take in account the relevant guideline.
[36]
The public participation process is dealt with in Regulation 41 of
2014 EIA Regulations which indicates that “
where
environmental reporting is done in one of the three regional
languages
,
executive
summaries in the other two languages should be made available, on
request
”.
[37]
The Federation of South African Fly Fishers v Minister of
Environmental Affairs 2021 JDR 2304 (GP), para. 66.
[38]
Sustaining the Wild Cost NPC and Others v Minister of Mineral
Resources and Energy and Others 2022 (2) SA 585 (ECG)
[39]
ibid para 21.
[40]
ibid para 22.
[41]
ibid para 26.
[42]
“
While
the legislation itself may purport to advance the collective good,
the application of legislation in a concrete situation
can often
have adverse effects on individual rights
”
– Administrative Law in South Africa, C Hoexter, Juta &
Co, 2
nd
Edition, 2012, page 53.
[43]
Trinity Broadcasting (Ciskei) v Independent Communications Authority
of South Africa
2004 (3) SA 346
(SCA) – para 21 at 354H-355A.
[44]
Section 8(1)(a)(ii) of PAJA
[45]
Para 94 supra
[46]
s 8(1)(f) of PAJA
sino noindex
make_database footer start
Similar Cases
South Durban Community Environmental Alliance and Another v Minister of Forestry, Fisheries and the Environment and Others (17554/2021) [2023] ZAGPPHC 19 (18 January 2023)
[2023] ZAGPPHC 19High Court of South Africa (Gauteng Division, Pretoria)100% similar
United Democratic Movement and Another v Lebashe Investments Group (Pty) Limited and Others (58969/2018) [2022] ZAGPPHC 833 (4 November 2022)
[2022] ZAGPPHC 833High Court of South Africa (Gauteng Division, Pretoria)98% similar
Durbanvale Trade and Investment (Pty) Ltd v Estate Agency Affairs Board (37135/2012) [2025] ZAGPJHC 837 (22 August 2025)
[2025] ZAGPJHC 837High Court of South Africa (Gauteng Division, Johannesburg)98% similar
South African Municipal Workers Union National Provident Fund v Tlokwe Local Municipality and Others (A129/22) [2024] ZAGPPHC 748 (29 July 2024)
[2024] ZAGPPHC 748High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Mafuwane (28636/2022) [2022] ZAGPPHC 685 (14 September 2022)
[2022] ZAGPPHC 685High Court of South Africa (Gauteng Division, Pretoria)98% similar