Case Law[2022] ZAGPPHC 903South Africa
Cargo Movers (South Africa) (Pty) Ltd v Transnet SOC Limited (64902/2016) [2022] ZAGPPHC 903 (17 November 2022)
High Court of South Africa (Gauteng Division, Pretoria)
17 November 2022
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2022
>>
[2022] ZAGPPHC 903
|
Noteup
|
LawCite
sino index
## Cargo Movers (South Africa) (Pty) Ltd v Transnet SOC Limited (64902/2016) [2022] ZAGPPHC 903 (17 November 2022)
Cargo Movers (South Africa) (Pty) Ltd v Transnet SOC Limited (64902/2016) [2022] ZAGPPHC 903 (17 November 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2022_903.html
sino date 17 November 2022
IN
THE HIGH COURT OF SOUTH AFRICA
# (GAUTENG
DIVISION, PRETORIA)
(GAUTENG
DIVISION, PRETORIA)
Case
Number: 64902/2016
REPORTABLE:
OF
INTEREST T OTHER JUDGES:
In
the matter between:
CARGO
MOVERS (SOUTHERN AFRICA) (PTY) LTD
PLAINTIFF
and
TRANSNET
SOC LIMITED
DEFENDANT
JUDGMENT
MAUBANE
AJ
Delivered:
This judgment was handed down electronically by circulation to the
parties' legal representatives by e-mail. The date
and time for
hand-down is deemed to be I0h00 on 17
TH
NOVEMBER 2022.
# INTRODUCTION
INTRODUCTION
[1]
The plaintiff, a private company duly incorporated and registered in
terms of the
Companies Act 71 of 2008
, instituted an action against
the defendant, a state-owned company duly incorporated and registered
in terms of the
Companies
Act 71 of 2008
.
# THE
PLEADINGS
THE
PLEADINGS
[2]
On its particulars of claim, the plaintiff
alleged and stated the following: -
2.1
On or about 22 September 2014 the defendant
issued a request for proposal (RFP) for tipping of containers at
Grootvlei Power
Station
using specialized 4x8 mining tipper vehicles.
2.2
On the 31
st
December 2014 the defendant made
an offer to the plaintiff to provide the defendant with services for
tipping coal containers at
Grootvlei Power Station pending the
conclusion of a 2-year contract between the plaintiff and the
defendant.
2.3
As alleged by the plaintiff, on or about the
13
th
January
2015, and at or near Durban, the plaintiff duly represented by Mr N
Naidoo accepted the defendant's offer and in the premises,
a written
agreement was concluded between the plaintiff and defendant, the
relevant express, alternatively tacit, further
alternatively
implied terms were as follows:
2.3.1
Plaintiff was identified as the
preferred bidder for the provision of services for tipping coal
containers at Grootvlei Power Station,
2.3.2
Defendant wished to contract the
plaintiff for the provision of the service which, if mutually agreed
by the parties, would be documented
and effected in accordance with a
two-year contract "(Agreement)" between the parties,
2.3.3
The LOA (letter of award) would remain
in force until the agreement is signed by the plaintiff and the
defendant or until 60 days
have elapsed from date of issue of the
LOA, whichever event should occur first,
2.3.4
Pending finalization of the agreement,
the plaintiff
will
commence to provide the services at a rate stipulated in
Section
3(Pricing
and Delivery Schedule) to the RFP,
2.3.5
Should negotiations between the
plaintiff and the defendant break down for any reason, the plaintiff
may immediately invoice the
defendant for all reasonable actual costs
incurred prior to that date and such amount shall become due and
payable by the defendant
[3]
It is further alleged and stated in the
particulars of claim that the plaintiff and the defendant implemented
the terms of the LOA,
and,
3.1
The plaintiff provided the defendant
with the services,
3.2
The plaintiff complied in all other
respects with the terms and
conditions
of the LOA,
3.3
The plaintiff and the defendant
continued to negotiate in an attempt to finalize the terms of the
agreement until 1
st
March
2015,
[4]
The plaintiff further alleged that:
4.1
negotiations between the plaintiff and
the defendant broke down on or about the 28
th
February 2015 which was prior to
the date upon the LOA 's lapsing 60-day period;
4.2As
alleged, the defendant was obliged to pay plaintiff the reasonable
actual costs incurred by the plaintiff,
4.3
The actual reasonable actual costs incurred by the plaintiff prior to
the 28
th
February
2015 amounts to R6,914,138.19, amount of R6,914,138.19 of which
comprised of:
4.3.1
the reasonable actual costs incurred by the
plaintiff in implementing the terms of the LOA prior to the 28
th
February 2015,
4.3.2
excludes contract fees and related costs paid
to the plaintiff by the defendant in terms of the LOA,
4.3.3
costs incurred by the plaintiff that are
related
to the LOA and the implementation thereof by the plaintiff, and
4.3.4
represents a provisional amount that will be
qualified with more accuracy upon receipt of an expert report.
[5]
It was further alleged in the particulars of claim that the plaintiff
invoiced the defendant for payment of the plaintiffs reasonable
actual costs incurred prior to the 1
st
March 2015 and the
defendant was in breach of the terms of the LOA, failed and/or
refused to pay the plaintiff such costs in the
amount of
R6,914,138.19 or any part thereof.
[6]
Claim number 2 as alleged and stated in the
particulars of claim arose as follows: -
6.1
From the 2
nd
March 2015, onwards until the 31
st
July
2015 the plaintiff and the defendant (duly represented) continued
negotiations aimed at concluding an agreement similar to
that
contemplated in the LOA, and the plaintiff in the meantime continued
to provide the services to the defendant.
6.2
On or about the 20
th
July 2015, the negotiations
between the parties again broke down and with effect from the 31
st
July 2015 the plaintiff ceased to
provide the services to the defendant, and the defendant requested
the plaintiff to respond to
an urgent request for quotation,
6.3
It was further alleged by the plaintiff that on
or about the 1
st
August
2015 and at a place currently unknown to the plaintiff one or more of
the defendant's employees (the identity of whom was
then unknown to
the plaintiff) intentionally and in a dishonest manner manipulated
the tender process to ensure that the tender
contemplated in the
defendant's urgent request for quotation be awarded to an entity
known as XMoor Transport (PTY) ILtd (also
referred to as Crossmoor)
6.4
The defendant's employee(s) intentionally and
in a dishonest manner manipulated the tender process by (amongst
others):
6.4.1
calculating the points based on the plaintiffs BBBEE certification on
the basis that the plaintiff level of certification
was level 9
whereas the plaintiffs level of certification was to the knowledge of
the defendant's employee(s) in fact level 3,
6.4.2
ignoring the fact that Crosmooìs tender was noncomplaint
in
that it provided for a price escalation in the event of a variation
in the diesel base rate whereas the defendant's Emergency
Tender
stated that the quotation should be based on a month-to-month basis
at a flat rate and not have fuel variations.
[7]
The plaintiff further alleged that, at all
relevant times:
7.1
A legal duty rested on the defendant to
adjudicate the awarding of the Emergency Tender in a manner that is
fair as is contemplated
in
Section 33(1
) of the Constitution of the
Republic of South Africa and not to act in a dishonest manner,
7.2
The Defendant's employee(s) who adjudicated the
awarding of the emergency tender, acted in the course of the
defendant's business
and within the scope of his/her/their authority.
[8]
But for the dishonest and intentional breach of
the legal duty by defendant's employee(s) in the manner set out
above, awarded the
emergency tender to the plaintiff and the
plaintiff would have continued with emergency tender until at least
of the 2-year period
contemplated in the LOA on 1
st
December 2016.
[9]
Accordingly, the plaintiff claims an amount of
R8,276,838.29 representing the profit the plaintiff would have
realized but for the
dishonest and intentional awarding of the
emergency tender to Crossmoor and not the plaintiff and such claimed
amount is calculated
on the basis that: -
9.1
The plaintiff would have transported at least
40 000 tons of coal per month as a rate of R56,50 per ton,
9.2
The plaintiff would have realized a monthly
profit equal to 22,89
0
/0
of the total income derived from providing the transportation
services to the Defendant,
9.3
The plaintiff would have continued with the
emergency tender until the expiry of the 2-year period contemplated
in the LOA on the
1
st
December
2016.
9.4
The plaintiff duly gave notice to the defendant
as contemplated in Section 3(1) of the Institution of Legal
Proceedings against
Certain Organs of Sate Act, Act 40 of 2002 and
the period of 30 days contemplated in Section 5(2) of the Act had
expired.
[10]
On the 6
th
April 2021 the plaintiff amended
some paragraphs of its particulars of claim more importantly the
amount in claim 1, was amended
to R4 904 228,25
[11]
The defendant, in its amended plea raised a
special plea in that the claim has prescribed, and thereafter pleaded
to the plaintiffs
particulars of claim.
[12]
In its special plea, the defendant specifically
pleaded that the plaintiffs claim has prescribed, in that, a period
of more than
three years has lapsed, since the plaintiff was aware,
alternatively, ought to have been aware of the facts giving rise to
its
claim against the defendant, and as such the plaintiff claimed,
as against the defendant three years after the alleged debt arose
and
according to the defendant the claim has prescribed in terms of
Prescription Act 68 of 1969
.
[13]
In addition to special plea, the defendant
pleaded to the plaintiffs particulars of claim. The defendant denies
that it is owing
the plaintiffs as alleged, in that: -
13.1
The
defendant paid the plaintiff for services that were rendered within
the course and scope of the LOA, based on the plaintiffs
price offer
and in accordance with the terms of the LOA,
13.2
During
subsistence of the LOA, the plaintiffs issued invoices for services
rendered and was paid for such services in accordance
with the price
offer,
13.3
The
plaintiff is not entitled to payment of additional amounts separately
from the payments that have already been made for services
rendered.
13.4
The
plaintiff is not entitled to claim payment for costs that is
allegedly incurred in rendering the services to Transnet, separately
from the cost which it has already recovered from Transnet based on
its bid price as such payment would be in contravention of
Section
217(Procurement
for goods or services by organs of State) of the
Constitution and the Procurement Manual,
13.5
All
the costs that were due and payable to the plaintiff in accordance
with the LOA and the Procurement Manual were paid to the
plaintiff
once it had rendered the services and issued its invoices for
services rendered,
[14]
The defendant further pleaded that: -
14.1
the
parties did not sign the agreement contemplated in the LOA on or
before the expiry of 60 days of the defendant issuing the LOA
as
contemplated in the LOA and accordingly the LOA expired in accordance
with its own terms on the 1
st
March 2015, and further the
negotiations between the parties broke down on the 1
st
March 2015.
14.2
The
defendant further pleaded that on or about the I st August 2015, the
defendant lawfully awarded the Emergency Tender to Croosmoor
Transport (PTY) Ltd and it denied allegation of dishonesty and
manipulation leveled against it by the plaintiff. At the commencement
of trial, the court was informed that the plaintiff was no longer
continuing with claim 2 and as such claim 1 was to proceed and
be
dealt with.The matter was set down for hearing from the 12
th
April 2021 to the 14
th
April 2022.
# EVIDENCE
EVIDENCE
The
plaintiff led the evidence of the under-mentioned witnesses who
testified as follows:
Mr
Maclachlan
[16]
He testified that he is the director of Tengwa Africa Limited. He
told the court that his company entered into a joint venture
with the
plaintiff which had to render a service to the defendant. He further
told the court that the plaintiff had to render interim
service of
collecting and tipping coal at Grootvlei Mine. Trucks had to be used
for such services.
[17]
The interim rendering of service by the plaintiff to the defendant
would be effected pending the conclusion of a final contract
between
the plaintiff and the defendant. According to the witness's evidence,
the interim service was based on a letter of award
(LOA) both parties
signed. He told the court that the purpose of the LOA was to document
the intentions of the parties in respect
of the required services,
and it would remain in force until the final agreement of a two year
plus two-year deal was signed or
until sixty days have lapsed.
[18]
The letter of award was signed by A Mabena on
behalf of the defendant and Mr N Naidoo on the31st December 2014 and
13
th
January
2015 respectively, and the sixty days period lapsed at the beginning
of March 2015.He further told the court that after
sixty days period
had elapsed the contract continued in good faith. The rendering of
service continued beyond sixty days period
with a hope that they
would sign a final agreement. He further told the court that there
was no reason to stop because, he thought
everything was moving along
quite nicely and the services they were rendering were in line with
what was required.
[19]
He further stated that the plaintiff complained
about the minimum tonnage supplied and they were struggling with
petrol costs and
as such they asked for a revised rate. The fuel
price had increased. There was exchange of
correspondence
between the parties and defendant threatened to suspend the services.
[20]
The witness further testified that Tengwa
Africa purchased the tippers in terms of servicing plaintiff and the
latter had to service
the defendant. According to the provisions of
letter of award, in the event there was breakdown between the parties
for any reason,
the plaintiff may immediately invoice the defendant
for reasonable actual costs incurred prior to the date of lapse of 60
day period
and such amount shall become due and payable by defendant.
[20]
The witness further testified that they bought
trucks, hired drivers, and leased premises based on letter of award.
He thought that
should negotiations break down; they would be able to
recover reasonable costs, and as such being a reasonable transaction
it warranted
the risk of buying what was quite expensive equipment to
service the contract.
[21]
He further told the court that the coal tipping
fees was paid, and their claim was only based on the exist costs. The
trucks had
to be sold at a lower amount, penalties had to be paid to
the financiers, the leased property and the drivers had to be paid
because
of premature termination of the contract.
[22]
The witness further testified that some of the
invoices were in the name of Tengwa Africa not in the name of the
plaintiff because
the Tengwa Africa was providing service for
plaintiff as they were contracted by the plaintiff. The payment of
rendering service
to the defendant had to be paid to the plaintiff
because it was the plaintiff which had a contract with the defendant.
It was further
told by the witness that Tengwa Africa had to receive
payment from the plaintiff for services rendered to the defendant on
the
plaintiff 's behalf. The witness further conceded that the
plaintiff should pay Tengwa Africa because the latter spent money on
behalf of the plaintiff.
[23]
Mr. Maclachlan further told the court that his
company did not submit a bid proposal to defendant and further
admitted to the court
that the plaintiff and Tengwa Africa are two
separate entities. He further admitted that there was no relationship
between the
defendant and Tengwa Africa and as such Tengwa Africa had
no claim against the defendant. He further accepted that the
arrangement
that Tengwa had with the plaintiff did not involve the
defendant. [24] The witness further testified that according to the
bid
document, the plaintiff was not allowed to subcontract, and it
would be rendering service itself. The witness emphasized to the
court that Tengwa Africa rendered services to the plaintiff and the
plaintiff rendered the services to the defendant. He further
told the
court that Tengwa Africa could not seek to recover costs incurred by
rendering services to the defendant for the plaintiff.
He further
testified that Tengwa 's BBBEE certificate was not submitted to the
defendant when the plaintiff submitted its bid proposal
because
Tengwa Africa was not part of the bid proposal. He said that Tengwa
would perform the services which were required by the
defendant, and
firstly, they entered into a joint venture with the plaintiff and the
plaintiff had outsourced the services to Tengwa
Africa.
[25]
He further testified that he was not patt of
the people who authorized and signed the letter of award and as such
could not confirm
that the agreement between the plaintiff and the
defendant was extended beyond 60 day period. He further testified to
the court
that after expiry of 60 days and the final agreement not
having been signed by the plaintiff and the defendant, the contract
continued
in good faith.
[26]
He further told the court that a cession was
concluded between Cargo and I-IBS which later changed its name to
Tengwa Africa. The
witness admitted that the cession was not signed
by the cessionary. He told the court that in the event the court
found that the
cession in question is a valid document, then it
shuold be considered to be between the plaintiff and Tengwa Africa
and not between
Tengwa and the defendant. The witness conceded that
the actual reasonable services fee for the service rendered has been
paid and
only amount due was for exist costs. He further conceded to
the court that the amount ceded was not the actual amount owed by the
defendant.
Mrs.
Cecilia Marriot
[27]
The witness testified that she was working for
"ETG", the holding company of Tengwa Africa. She told the
court that she
went to Balfour to negotiate for the retrenchment of
the drivers. She further told the court that she was not on Tengwa
Africa's
payroll. She told the court that she was to negotiate for
retrenchment of 26 drivers who were hired to drive 13 trucks. She
said
that the plaintiff received a message, on the week of the 27
th
July 2015, that the plaintiff had
to let go off the contract because of the defendant's issues with
finance and non-performance.
She further testified that the drivers
were then given retrenchment notifications. The drivers were offered
severance pay of one
week's salary per year by the witness on behalf
of Tengwa Africa. Tengwa Africa had to bring a human element when
giving the drivers
severance package of one week in a year even
though they were employed for less than a year.
[28]
The reason why they offered to pay severance
package to the drivers was because they were part of the Bargaining
Council. She told
the court that the drivers were offered pay of one
week (August salary) and leave pay. Each of the drivers was paid an
amount of
R10 628.41 as severance benefit. She further told the court
that the plaintiff was just their supplier and did not have any
relationship
apart from that.
[29]
She further told the court that there were
employments contract entered into between Tengwa Africa and the
retrenched employees,
but the contracts were not shown to the court,
as such she could not confirm terms of the contract. As a result of
the non-availability
of employment contract to the court she could
not confirm whether the employees were employed on a fixed term or on
permanent basis
and if they were entitled to severance pay. She
further testified that Tengwa Africa fell under National Bargaining
Council for
the Road Freight Logistics Industries Collective
Agreement of which in terms of the collective agreement, an employee
is entitled
to the severance pay of one week for every completed
year. She told the court that since the employees worked for only six
months,
they were not entitled to severance pay.
Mrs.
Annika Louise Bothma
[30]
Mrs. Bothma testified that she is internal
legal counsel for EDG group, and she attends to all the South African
companies secretarial
work based in South Africa. The witness was
called to explain the group structure. She told the court that I-IBS
group changed
to Tengwa Holdings and Tengwa Holdings is held by ETG
Agro Products, and Agro Products is in turn held by ETG Investments.
The
ETC, which is based in Mauritius, is the holding company of
entire group of companies. She further testified that Tengwa Africa
is held by Tengwa Holdings as a subsidiary. She told the court that
HBS Group changed its name to Tengwa Holdings last year, that
is
2021. The witness further told the court that as much as these
companies are related as subsidiary and a holding company, they
are
separate legal entities.
Mr.
Daniel John Stephen
[31]
The witness testified that he was the managing
director of Tengwa Africa (Pty) Ltd. He told the court that the
Grootvlei Project
was run by and operated by Tengwa Africa of which
's main line of business was running a trucking
business
across the borders of South Africa and was also involved in Grootvlei
Project. He further testified that his company supplied
equipment and
ran the transporting of coals coal for the plaintiff on the Grootvlei
coal project. Their company's main business
is running close to
hundred trucks mainly to Zimbabwe and Zambia transporting fertilizer
and grain. In the cause of running their
business, his company got
the Grootvlei project to supply coal to the Belfour Power Station. He
said that only South African citizens
were employed to drive the
trucks for the Grootvlei project. Tengwa Africa deployed 13 trucks
and 26 drivers for the Grootvlei
Project. According to the witness,
the truck operated on a 24hour service. He further told the court
that she bought the trucks
and deployed them on the proviso that
"they" would be allocated a certain minimum tonnage that
"they" needed
to move to make the operation work. The court
was further told by the witness that they exited the contract because
the defendant
could not supply the minimum tonnage and as they could
not be able to meet their basic minimum costs. He further told court
that
they existed the contract without having secured a long-term
deal. He further told the court that beside supplying trucks and
drivers,
they rented a depot and housed the drivers, he further
testified he and Mr. Maclachlan negotiated to the exit the project
seeing
that it was not working. They negotiated with Daimler to get
them out of the lease agreement. The company's operation manager
Collin
Herman negotiated for the exit from depot. The witness further
testified that his company had a contract with the defendant. The
company was not given a twoyear contract as anticipated. He further
told the court that his company made a joint bid with the plaintiff
and the plaintiff was the one who negotiated with the plaintiff and
company provided the equipment and service to the plaintiff.
He told
the court that in the event they incurred costs they should claim
from the plaintiff and the plaintiff had to claim from
the defendant.
He said that his company took Zimbabwean drivers from Polokwane to
Balfour to "get the project going, as they
would later get the
South African drivers on the Grootvlei project". He further told
the court that given the fact that they
started with eight Zimbabwean
drivers of the 26 drivers that ultimately worked on the project not
all of them would have worked
for the five months' period. He further
testified that he could not tell the court what the termination
penalty was in the event
of any exit.
Mr.
Heinrich Wilhelm Reganass
[32]
The witness testified that he has a master's degree in business in
Leadership. He came to the
court to testify as an expert witness. The
witness was examined on the composition of the amount claimed by the
plaintiff. He told
the court that he prepared the report he was being
examined on. He further testified that according to his findings, the
total
amount due to the plaintiff by the defendant was R2 678 948,06.
The amount claimed, comprised of the penalty due to Kempston Finance,
loss on the sale of the trucks (depreciation and loss on selling the
trucks), retrenchment costs, lease rental, auditors fees
(costs
charged by the auditors to get to the tax directives from SARS to
determine what tax must be paid on the retrenchments and
packages).
He further testified that he analyzed Miss Naidoo (the defendant's
expert witness) and found out that their respective
reports had a
difference of R900 000 which was occasioned by Mr. Naidoo's deduction
of the residual value, which was supposed not
to have been done, and
other difference was that Miss Naidoo calculated the depreciation
value at 25% meanwhile he calculated it
as 33%. He further told the
court that there were other differences, but they were insignificant
to dwell much on. He further told
the court that he sourced the
information for the preparation of the report from certain
individuals by the names of Monier and
Amal, being the account and
financial manager of Tengwa Africa respectively. The court was
further told that he scrutinized the
financial records of Tengwa
Africa and identify the costs that resulted as due to the termination
of the transport services and
further verify the costs against
available sourced occurrence. According to him the trucks were bought
for R15 813 685,42 and sold
for R13,65 million and accordingly, there
was a shortfall of an amount of R2 163 685.42.
[33]
The witness was also taken through the payment
made to the retrenched
26
truck drivers. He said that he was informed about the exact figures
of their monthly salaries and the figures provided by Tengwa
Africa
tallied with the tax directives that was applied for, for each
employee. The witness further testified that he assessed,
and checked
the report given to him by Tengwa Africa and in the event he relied
on the wrong facts then the court should not rely
on his opinion
based on incorrect facts. He further told the court that the
plaintiff and the defendant established an agreement
which confirmed
that services to be rendered by the plaintiff to the defendant was
for the period of 24 months of which it was
incorrect. He further
stated in his report that the plaintiff terminated the transport
services, of which there was a 24-month
contract with a possible
extension between the parties. It is worth noting that there was no
24 months' contract entered into by
the parties. He conceded that the
thirteen trucks were bought by Tengwa Africa, and not by the
plaintiff and as such the costs
claimed were incurred by Tengwa
Africa. He further told the court that the plaintiff and Tengwa
Africa are separate entities with
separate legal personalities. He
told the court that "these were the costs of Tengwa and Tengwa
has a claim against Cargo
(referring to the plaintiff) in terms of
the law and quantification of the costs in terms of the agreements,
maybe found like by
the court would be an amount that Cargo (the
plaintiff) can recover from Transnet (the defendant) based on the
costs that the plaintiff
expended in that period." He accepted
that in terms of double entry system, in accounting only Tengwa
Africa and the plaintiff
are the entities to be considered to the
exclusion of the defendant. He further admitted to the court that he
did not produce and
reference any clause showing that the lease
agreement was for a period of 24 months. He conceded that he could
not show the court
that the lease agreement had a penalty clause. The
witness further told the court that the penalty calculating on the
exist costs
of the trucks were incorrect because he made calculation
as if they were purchased on the same date whilst it was not the
case.
The witness further agreed that his calculation of the
depreciation on all the 13 trucks was incorrect because they were not
brought
to business at the same time and his calculations were as if
they were bought and brought to business at the same time. Insofar
as
the payment made to each retrenched employee, the witness told the
court that he did not know what constitutes severance pay,
and what
constitutes leave pay. He further stated that he did not know what
the monthly salary rate of each driver was, the rate,
which was used
to calculate the severance pay, paid to each employee. He did not
consider whether those employees were entitled
to severance pay. He
said that he prepared the report without all the information which
was exposed to him during testimony at
court.
Johannes
Herman Collen
[34]
Mr. Collen testified that he was an Operations
Manager of Tengwa Africa,
and
the latter was the preferred supplier of the plaintiff. The sole
purpose of Tengwa Africa was to transport coal from Belfast
to
Grootvlei Power Station. The demand for coal deliveries was hectic.
He told the court that Tengwa Africa was not involved in
obtaining
the tender from the defendant. He further told the court that
delivery of a minimum of 40 000 tonnes per month was contemplated.
They had the vehicles which could transport more than 40 000 tonnes.
He told the court that the service awarded was interim as
there was
no final tender agreed upon. There was a clause in the letter of
award which stated that in the event plaintiff and the
defendant's
negotiations break down, then the plaintiff would invoice for
reasonable actual costs. Thirteen vehicles with specialized
frame on
the back were used to tip and deliver coal to Grootvlei Mine as per
the parties 's agreement. Those vehicles were specially
built and
were not accessible on the market.
[35]
After the deal went sour due to non-agreement
on the 24 months or 48 months agreed upon, he had to sell those
vehicles and told
the court that the vehicles were not regular on the
market. The vehicles could not be utilized in any other operations
and as such
had to be sold. They had to take the price that was given
and had to sell them at a loss.
[36]
He further told the court that they had to pay
penalties as a result of early exit from the lease agreement. The
drivers were retrenched,
and they had to pay the drivers for such
retrenchment. He further testified to the court that the rendering of
the service commenced
on the 25
th
February 2015, and the service had
to be rendered for a period of 24 months at R15 000.00 per month. He
further told the court that
the party were not entitled to terminate
the contract before the initial lease period i.e., before lapse of 24
months. In the event
both parties agreeing on early termination
whoever initiates the termination will be charged the cancellation
fee of 50% of the
balance of the lease. He said that the lease
agreement was terminated 17 months before the actual date and as such
they had to
pay for the remainder of their lease period. He said that
they employed South African drivers, and the Zimbabwean drivers were
only employed to convey the vehicles from Polokwane to the contract
side.
[37]
He told the court that he did not have
knowledge about the agreement that was entered into between the
plaintiff and the defendant.
He further told the court that Tengwa
Africa was not part of the agreement, as per letter of award, between
the plaintiff and the
defendant. He does not know what was submitted
by the plaintiff to the defendant to be awarded the contract. He
acknowledged that
the arrangement that the plaintiff might have with
Tengwa Africa did not apply to the defendant and Tengwa's agreement
is only
confined to the plaintiff. He further told the court that
since the agreement was between the plaintiff and the defendant, he
cannot
dispute that there was no agreement between the plaintiff and
the defendant that the plaintiff would be given a two-year contract
plus two years with guaranteed tonnages.
[38]
The witness further told the court that he
relied on the inserted in script and believed that there were two
years plus 2 years
guaranteed contract. He further told the court
that the plaintiff at no stage told Tengwa Africa to incur the costs
which the latter
would claim. The witness further made an admission
to the court that any costs incurred by Tengwa Africa could not be
recovered
from the defendant, and that there was no promise that
indeed a 24-month contract would be concluded. He further told the
court
that it was unreasonable for Tengwa Africa to buy all those
trucks and employ 26 drivers, rent a property for two years whilst on
the interim contract. He however disagreed that it was unreasonable
to acquire all these assets in circumstances where there was
no
guarantee that they would have 24-month contract, reason being that
there was an interim contract that they had to honor. He
told the
court that, in terms of the letter of award, the contract was valid
for 60 days. He understood that it was unreasonable
for any
contractor who has at most 60 day contract to procure services and
goods for 24 months period, and as the operation manager
he was just
following seniors 's instructions. He further said that it was not
unreasonable to employ truck drivers as permanent
staff meanwhile
having an interim contract.
[39]
He further told the court that Tengwa Africa
invested its resources based on what the plaintiff told it, to the
extent that Tengwa
Africa suffered losses based on the plaintiff 's
information. He admitted that Tengwa Africa had to look at the
plaintiff for payment,
for service rendered, and not from the
defendant.
[40]
Reference was made to the employment contracts
of the truck drivers and the retrenchment packages paid to them. The
witness told
the court that the truck drivers worked for about five
months, and they were paid for one week for a completed year, despite
the
fact that they did not complete a year of employment. The witness
further confirmed that Tengwa Africa was not 100% black owned
and as
such it did not qualify to be on the Grootvlei Project as it was not
compliant with level 3 BEE status. He also accepted
that in terms of
the defendant's bidding policy 100% subcontracting was prohibited. He
further told the court that the plaintiff
was the preferred bidder to
provide vehicles on that specific contract and there was no
relationship between the defendant and
Tengwa Africa. He told the
court that the initial agreement was to deliver a minimum of 40 000
tonnes of coals per month. He further
testified to the court that the
contract did not stop after the 60 days period, but it continued up
until the end of July 2015
and Tengwa Africa were paid about RI 1m
for the service rendered.
Mr.
Nurian Solomon Naidoo
[41]
The witness testified that he is the managing
director of the plaintiff. He told the court that his company was
identified by the
defendant as a preferred bidder. It was
contemplated that as the preferred bidder his company would be
awarded a 2+2-year contract
and 40 000 tonnes of coal would be
delivered to Grootvlei Mine. The court was told that the transport
money was paid, and it was
not an issue to for this court to
deliberate on. He told the court that from February 2015 to July 2015
an amount of RI 1m was
paid to the plaintiff by the defendant for the
interim contract. He further told the court that the plaintiff had
never bill for
less than 40 000 tonnes per month. To his knowledge
they always transported less than 40 000 tonnes but both parties
agreed that
the plaintiff should invoice for the minimum of 40 000
tonnes even if less than 40 000 tonnes was transported. He further
testified
to the court that they had to acquire trucks to run the
interim service. He told the court that initially the plaintiff had
to
provide 6 trucks and it transpired that the plaintiff had to
transport between100 and 120 000 tonnes and as such the trucks had
to
be increased to 13.
[42]
The interim service did not cease after the
lapsing of 60 days period nor when 2+2 years contract was not signed.
The interim contract
went on until the end of July 2015. He confirmed
to the court that the letter of award stated that should negotiations
between
the parties break down for whatever reason, the plaintiff
should invoice the defendant for reasonable actual costs. He further
testified that on the 10th of February 2015 and the 16
th
of
February they bought 12 trucks,
that is 6 on each day. The trucks were purchased by Tengwa Africa The
trucks bought were not normal
type of trucks. They were purpose
built. The plaintiff employed local truck drivers, those residing at
Balfour. The plaintiff had
to
transport 4000 tonnes of coal daily, with the capacity of 13 trucks
and 26 drivers on 24-hour operation. He told the court that
they
raise a complaint with defendant that they were not transporting 40
000 tonnes of coals as per agreement and as such they
were battling
to break even.
[43]
In the middle of June 2015, he met the
defendant lamenting about the increase of fuel price. In that
meeting, they also talked about
tonnages and prices. He made a
proposal of a revised structure of the Grootvlei project. He told the
court that because of the
challenges he was encountering with the
project he wanted to have a further meeting with the defendant, and
should they not get
the response, they would have no option but to
suspend the service by 30
th
June
2015. The defendant responded to him by stating that a different
approach was required to make the project a success and he
told them
an alternative should be discussed and considered. He told the court
that he wrote the letter to the defendant stating
that they acted in
good faith, meeting all the requirements and obligations, but they
could not take losses anymore. He said to
the defendant that the
operation was based on 13 vehicles at 60 000 to 80 000 tonnes per
month, however the volumes were not the
case and as such it was not
sustainable to carry on without them going bankrupt. He told the
court that he was still hopeful of
getting to a final agreement. He
said they resumed the services at Grootvlei and it could only be kept
going for 7 days until all
the matter has been addressed and
resolved. He was then advised by Mr. Nyiko Nkuna, Transnet engineer,
to give clarity of what
he meant by suspension of services, whether
he meant to cancel the contract or suspending the services and if he
was not cancelling
the contract he should resume with the operation
as of 15
th
July
2015. He eventually ran out of steam and left the scene. Based on the
letter of award he invoiced for reasonable costs and
was not paid. He
said that he was claiming from the defendant because when he started
the project, he gave it to Tengwa Africa
as he was travelling up and
down between Australia and South Africa. He told the court that the
proceeds of this claim would go
to Tengwa Africa as it had made a
loss.
[44]
When he submitted bid to the defendant, he had
about 24 years as a businessman. He acknowledged to the court that a
person who advertised
the bid would not have to buy the equipment and
the resources to render the service. He said when submitting the bid,
he provided
the price for acquiring trucks, employees, and everything
that he needed to render the service. He told the court that a person
who bid for the defendant's service should not be a person who would
need to be provided with trucks and equipment. He further
confirmed
to the court that the bid was assessed on functionality, which is the
ability to provide the required service. He further
told the court
that he accepted the terms of RFP, and it formed part of a binding
contract between the plaintiff and the defendant.
He said he
submitted a bid and was identified as a preferred bidder and was
issued with a letter of award. He further confirmed
that the
plaintiff did not buy any truck, but Tengwa Africa did.
[45]
He told the court that he was the one who
inserted a minimum 40 000 tonnes per month on the LOA. He disputed
that he put the handwritten
inscription after Mr. Mabena signed the
letter of award. He further told the court that the defendant paid
him a minimum of 40
000 tonnes per month irrespective of whether he
delivered less than 40 000 tonnes per month. It was put and shown to
him that,
Mr. Mabena signed the document on the 31
st
December 2014, and he only signed
it on the 13
th
January
2015. He reluctantly admitted to the court that it was in fact true
and when Mr. Mabena signed the document as it did not
have
handwritten inscription. The handwritten inscription was not
initialed or signed by both parties as shown to the court and
the
witness accepted that. He said that the pricing schedule which was
provided by the defendant did not mention that a minimum
of 40 000
tonnes would be provided by the plaintiff He further admitted that in
terms of the RFP, no alterations, additions, or
deletions must be
made and as a result his insertion of minimum 40 000 was
impermissible. He said that the defendant never gave
them 40 000
tonnes per month, but instead gave them 20 000 tonnes per month. The
witness further testified that the terms of the
LOA was incorporated
in the RFP of which there was no undertaking by the defendant to
provide 40 000 to 60 000 tonnes of coals.
He said he wrote to the
defendant and informed it that he got its tonnage numbers wrong and
wanted more tonnes. He told the court
that what was in terms of the
RFP, was bound by the price that he proposed to the defendant
regardless of whether it was correct
or not.
[46]
He further testified that he had a telephonic
conversation with the defendant on the 3
rd
July 2015, wherein the defendant
said it was not prepared to commit itself to paying revised rates
that he proposed, and further
said that should he provide services at
the quoted price in the RFP, the defendant would be prepared to sign
the final agreement
by next week. He further told the court that the
defendant told him that the final agreement could not be concluded
because the
defendant had to stick to what he needed for the quoted
price. He further testified to the court that he understood that
after
the lapse of 60-day period there was binding obligation on the
plaintiff to provide services to the defendant. According to him,
60-day period lapsed on the 3
rd
March 2015 and any agreement,
engagement that might be between the parties could not have been in
terms of the LOA.
[47]
He told the court that the plaintiff submitted
the triple BEE certificate to the defendant and according to the bid
they submitted,
Tengwa Africa 's triple BEE
certificate
was not submitted, and further alluded to the court that the
plaintiff was not allowed to use a subcontractor. He did
not disclose
to the plaintiff that Tengwa Africa would be rendering or executing
the contract. He further admitted that he did
not tell the defendant
that he would be subcontracting the services, and further told the
court that the plaintiff would solely
be servicing the contract.
Having conceded that, he accepted that it was prohibited to
subcontract the services as it was contrary
to the RFP. He further
accepted that Tengwa Africa had a lower BEE rating as compared to his
company, and according to the RFP
it was prohibited to subcontract
more than 25% of the contract. He was aware that there was no
agreement between the parties which
extended the 60-day period, and
he further told the court that, in terms of prescripts and rules, the
defendant should have an
authorized person to conclude its agreement,
in that case Mr. Aaron Mabena was the person authorized to do so. The
authorized person
should then reduce the agreement in writing and
then the agreement should be signed by both parties. He further told
the court
that there was no agreement signed after the expiry of
60-day period.
[48]
He further told the court that he knew that
according to the defendant's applicable policies, when entering into
any agreement,
there should be prior advice of the relevant services
department. When the contract is modified there must be the first
written
advice of the legal service department and all amendments to
the contract must be approved by the manager who originally signed
the initial contract and in that instance was Mr. Aaron Mabena.
[49]
At a later stage of the trial the witness was
shown a copy of the LOA, which was signed by Mr. Mabena, without both
their signatures
on the handwritten inscription. Contrary to his
earlier testimony, he said that he put inscription on the LOA and
sent it back
to Mr. Mabena. He told the court that since there was no
agreement between the defendant and Tengwa Africa, any costs incurred
by Tengwa Africa could not be recoverable from the defendant. He said
that during February 2015 they transported 17 000 tonnes and
charged
a minimum of 40 000 tonnes which the defendant paid, and the payment
was not reclaimed by the defendant. He said that if
they could have
transported more than 40 000 tonnes they would have adjusted their
invoices to be more than the minimum of 40 000.
He was with Tengwa
Africa's consultant, Mr. Denin Moodley when he made handwritten
inscription and Mr. Mabena was in Koedoespoort,
the defendants base).
He told the court that after he had inserted that amendment on the
LOA, he then emailed it to Mr. Mabena.
Mr.
Lukas Venter
[50]
The witness testified that he was a parts
manager at Mercurius Motors in 2015. He was part of the people
involved in selling of
the trucks to Tengwa Africa. The 13 trucks
were resold to Mercurius Motors, and each was paid for R1.5m. He said
that since trucks
were purpose-built, their market was very slim. He
further told the court that those trucks were bought, from them, in
the beginning
of 2015. The trucks were resold to them because of the
expiry of the contract and their usage was not required anymore and
they
could not find buyers for them. The plaintiff then closed its
case and the defendant applied for absolution from the instance and
same was not granted with a proviso that reasons will be given at a
later stage.
After
the closing of the plaintiff 's case the defendant applied for
absolution from the instance of which the court dismissed and
stating
that reasons for dismissal will be given at a later stage.
# ABSOLUTION
OF THE INSTANCE
ABSOLUTION
OF THE INSTANCE
[51]
The
test for absolution, to be applied by a trial court at the end of the
plaintiff 's case, was formulated in Claude Neon Lights
(SA) Ltd v
Daniel
[1]
at
409G-H wherein the learned judge said:
"when
absolution from the instance is sought at the close of the plaintiff
's case, the test to be applied is not whether the
evidence led by
plaintiff establishes what would be required to be established, but
whether there is evidence upon which a court,
applying its mind
reasonably to such evidence, could or might (not should, nor ought
to) find for the plaintiff. "
[52]
It
was also stated in Gordon Lloyd Page & Associates v Rivera and
Another
[2]
at
par 2 wherein the court said:
"This
implies that the plaintiff has to make out a prima facie case- in the
sense that there is evidence relating to all the
elements of the
claim- to survive without such evidence no court could find for the
plaintiff . .. As for as inference from the
evidence are concerned,
the inference relied upon by the plaintiff must be reasonable one,
not the only reasonable one... The test
has from time to time been
formulated in different terms, especially has been said that the
court must consider whether there is
"evidence upon which a
reasonable man might find for the plaintiff, "
[53]
In Osman Tyres and Spares CC and Another v ADT Security (Pty) Ltd
[3]
the
court said that:
"The
fact that a defendant had at that stage not yet given evidence, is
often a cogent factor to be taken into account, particularly
where
the facts are within the peculiar knowledge of the defendant and the
plaintiff has made out a case to answer. In those circumstances
a
plaintiff should not lightly be deprived of his remedy without the
court first hearing what the defendant has to say. "
The
plaintiff presented evidence before court, on the face of it the
defendant had a case to answer. For instance, the plaintiff
told the
court that the defendant knew about the existence of Tengwa Africa
which had a joint venture with the plaintiff. This
piece of evidence
was later refuted by Mr. Mabena who said he only became aware of
Tengwa Africa during evidence in court.
# DEFENDANTS
WITNESSES
DEFENDANTS
WITNESSES
Mr.
Aaron Mabena
[54]
The witness testified that he is currently
employed by Transnet Engineering as manager, Governance and
Compliance. His duties are
to review, to ensure that the goods and
service are procured within the prescribed Transnet frameworks,
prescribed delegation of
authority and they could comply to all
legislative requirements as prescribed by Section 217 of the
Constitution of the Republic
of South Africa and various acts such as
PFMA, and triple EEA. The defendant issued a tender on the open
market for provision of
goods and services, inter alia for tipper
trucks for tipping coals between a mine and a power station. He
further told the court
that the defendant issued RFP with the
objective to source for the service from service provider that was
capable of servicing
the defendant with tipper trucks. He said that
the defendant's expectation was to receive high level of delivery of
service of
the agreed quality and should be rendered within the
profitability margins that the defendant expected to deliver the
service for.
According to the witness, the required minimum threshold
for the service provider to be regarded as competent before they do
the
price evaluation was 60%
[55]
The service provider should render quality and
reliable service, based on the viable agreement entered into by the
parties. He further
told the court that in terms of RFP the service
provider has had to have technical capacity and the ability to render
service.
The prospective bidders were requested to submit three years
of audited financial statements, which would have been used by the
evaluation committee of the defendant to assess the financial
stability of the service provider.
[56]
He said that the plaintiff stated in the tender
document that it was not going to subcontract any portion of the
service should
it be awarded the contract. He said that in the event
the service provider was to subcontract any portion of the contract
it should
declare to that effect, and such subcontractor must submit
its triple BEE certificate to the defendant. He further said that the
service provider should not subcontract more than25% of the contract.
Thirdly, the service provider should not subcontract to another
entity with a triple BEE that is not in the same as theirs or better
than theirs. He further testified that the plaintiff deviated
from
the terms and conditions of RFP as well as its own (plaintiff)
submission in making declaration that it would not subcontract
the
service.
[57]
Regarding Mr. Naidoo's handwritten inscription,
he said that he became aware of it during these proceedings. He said
that when an
offer is made to the would-be service provider, he would
sign first then the would-be service provider would then sign in the
event
it is happy with content and in that regard the contract would
have been entered into. After signing the LOA, he personally emailed
it to Mr. Naidoo on the 31
st
December 2014 and did not receive
any response from Mr. Naidoo.
[58]
He further testified that the LOA had two
conditions. The first condition was that its duration was either
valid for 60 days or
alternatively the 60-day period would lapse once
a formal agreement was entered into and as such that agreement would
supersede
the LOA. Should 60-day period lapse without the parties
concluding the agreement, the letter of award would lapse. He said
that
the RFP stated that the service provider would be paid contract
fees which comprised of fuel, rental of offices, staff and overtime
as such fees would be interim pending the signing of the final
contract or lapse of 60-day period whichever comes first. He said
that in the event negotiations breaks down before expiry of 60 days
and the final contract not signed, then the would-be service
provider
would be paid according to what it has rendered to the defendant, and
the payment would be regarded as the contract fees.
He said that the
defendant could and should not have to pay Tengwa Africa for the
usage of trucks, lease of the property, salary
of the drivers and the
shortfall on the sale of the trucks. The defendant had only to pay
for services rendered as per LOA hence
the defendant had paid the
plaintiff for the tonnages delivered. The parties' expectations were
that during of 60 day period, the
final agreement would be concluded,
and in the event the agreement was not concluded, the letter of award
would lapse.
[59]
The witness further told the court that the RFP
documents expressed the Transnet 's requirements regarding the nature
of the vehicles
that would have to be acquired, and it is also
expressed what would be looked at in terms of assessing durability
and suitability
to render the service. He further testified that the
plaintiff was awarded the tender as it reached all the requirement as
per
his submission of the RFP. The plaintiff was awarded the contract
because the bid it submitted showed and confirmed its readiness
to
start with the contract; and it further stated that it had capacity
to deliver and had previous experience.
[60]
He said that insofar as Mr. Naidoo's
handwritten inscription was concerned, the defendant would have not
agreed to that because
if indeed there was an agreement to effect
amendment by way of the inscription, then he should have
countersigned the amendment
so made. In case that the parties wish to
amend the agreement, the agreement must be referred to the
Adjudication Committee to
change the amount of the tones to be
delivered by the service provider. He further told the court that for
any contract to be signed
and sent out, the defendant's legal
department must have to peruse that contract and a manager who has
authored the contract may
not conclude the
contract
and sign it off without delegated authority of Adjudication
Committee. In case of amendments being effected, legal department
has
to be consulted and agreed to and after its approval then the manager
concerned may sign the document.
[60]
He further told the court that all the
contracts should be in writing. He disagreed that the contract was
tacitly extended beyond
60-day period, and further said that the
Adjudication Committee should have agreed to the extension and
manager who had delegated
authority would have to formally sign off
the extension which would have to be in writing. He said to the court
that it did not
happen. The contract continued beyond the lapse of 60
days period and payment was made to the plaintiff, but he told the
court
that pricing of the amount tendered for, could not be amended
after the tender has closed. The LOA must be read in conjunction with
the RFP. He further told the court that the payment made to the
plaintiff for the 40 00 tonnes meanwhile it delivered less was
irregular and should be paid back to the defendant.
Miss
Vashney Naidoo
[61]
The witness testified that she is subcontracted
to BDO, an international advisory and audit firm. She has been an
independent contractor
to BDO since around October/November 2019. She
performed the review analysis of evidence and drafting of the
defendant's report
regarding the contract the plaintiff and the
defendant were involved in regarding transportation of coal. She told
the court that
she specializes in investigative and forensic
accounting.
[62]
She dealt with the quantification of the loss
the plaintiff alleged to have
suffered,
as a result of the termination of the tipping contract. She was
instructed by the defendant to analyze and critique the
report
prepared by the plaintiffs expert, Mr. Regenass. She told the court
that she was critical of Mr Regenass terming of his
report "forensic
report" as there were specific methodology, protocols, and
approaches that one would apply in forensic
work which should be
documented in detail and Mr. Regenass report was short of that.
According to the witness, in the forensic
report, one would have
cited sources outlining complete scope of review and cite all
references. She further told the court that
one's full mandate should
also be stated in their report. During the preparation of her report,
she found that there were missing
documents in plaintiffs expert's
report which would affect the quantification of
the
claimed amount. She also realized that the lease agreement was
incomplete. The incomplete lease agreement impacted the calculation
of the termination on the amount and there was missing information
with respect to calculation of the drivers 's remuneration and
as a
result there was an impact on the calculation of retrenchment
packages. The penalty interest calculation would have required
certain instalment sale agreements which were also missing. She
further told that Mr. Regenass's report did not state the disposal
date of assets in certain instances, as well as the start and end
dates or the purchase states of the vehicles.
[63]
She further testified that Mr. Regenass's
report did not state the connection between the plaintiff and Tengwa
Africa. Mr. Regenass
did not, in his report, provide any explanations
as to how Tengwa Africa incurred losses, if any how the losses were
qualified
and quantified. Against the defendant. Mr. Reganass's
report is silent on how the expenses incurred by Tengwa Africa is
being claimed
against the defendant in terms of the accounting policy
of debit and credit system. She said that when calculating
depreciation,
the assets should be owned and be in the name of the
plaintiff. She further said that Mr. Regenass's report was deficient
in explaining
how the costs incurred by Tengwa Africa was considered
reasonable actual costs incurred by the plaintiff. She said that Mr.
Reganasse
did not state the depreciation value of the
vehicles,
further he did not state how the carrying value was arrived at and
did not stat the source of the selling value.
She
further told the court that the retrenchment packages were not
calculated. The directives spoke about 28 employees and Mr. Regenass
spoke about 28 employees. Further it has to be noted that the
employees did not work for a year and as such they should not have
been paid one a week retrenchment package in a year. She further told
the court that besides the fact that Tengwa Africa is a separate
entity which could not claim payment from the defendant,
the
plaintiff could not prove its claim against the defendant for lease,
loss on selling of trucks, retrenchment packages and auditor's
fees.
# ANALYSIS
ANALYSIS
[64]
On the 2
nd
October 2014, the plaintiff and
the defendant signed request for proposal (RFP) for tipping of coal
containers at Grootvlei Power
Station using specialized 4x8 mining
tipper vehicles. Both parties were represented by Mr. Naidoo and Mr.
Mabena respectively.
The RFP, which was confirmed and consigned by
Mr. Naidoo and Mr. Mabena, amongst others, stated that the plaintiff
should not sub-contract
its services, as it was prohibited for a
successful bidder to subcontract more than 25%of the value of the
contract to another
entity which does not have an equal or higher
BBBEE status level than successful it. It was further contained in
the RFP form that
in the event the successful bidder wishes to
subcontract its services, the subcontractor should be disclosed in
the RFP. The subcontractor
should also submit its BBBEE certificate.
During trial both the Mr. Naidoo, (the plaintiff 's witness) and Mr.
Mabena, (the defendant
's witness) told the court that the RFP should
be read in conjunction with letter of award (LOA) which was signed by
both parties
respectively. The plaintiff, according to the LOA, was
confirmed and identified as preferred bidder, and it was further
stated
that the LOA will remain in effect until the agreement is
signed by both parties, or until 60 days have elapsed from the date
of
issue of the LOA, whichever event should occur first.
[65]
Both parties told the court that negotiations
broke down within 60 days of the issue of LOA.
CESSION
[66]
The plaintiff also tried to rely on the
cession, and on closer look of the cession the court noticed that the
amount mentioned on
the cession is not the amount claimed from the
defendant, and further the cession is not fully signed and therefore
it does not
take the court any further. Further than that, the
plaintiffs counsel did not mention the cession issue in his oral nor
written
heads of argument.
# SUB-CONTRACTING
SUB-CONTRACTING
[67]
It is further worth noting that the plaintiff
subcontracted 100% of its service to Tengwa Africa, did not disclose
Tengwa Africa
as a partner nor state Tengwa Africa "s BBBEE's
status in the RFP form. Mr. Naidoo told the court that the plaintiff
made
Tengwa Africa to do the work as he was travelling a lot
overseas. All the plaintiffs witnesses conceded that the damages
claimed
by the plaintiff were Tengwa Africa 's damages and once paid
were going be transferred to Tengwa Africa.
[68]
It
is common cause that plaintiff and Tengwa Africa are two separate
legal entities. In Salomon v Salomon & Co Ltd
[4]
the
court found that once a company is legally incorporated it must be
treated like any other independent person with its right
and
obligation appropriated to it, and it has its own rights and
liabilities. In Airport Cold Storage (Pty) Ltd v Ebrahim and
Others
[5]
at
paragraph 7, the court confirmed that:
"one
of the most fundamental consequences of incorporation is that a
company is a juristic entity separate from its members,
the court
does not have general discretion simply to disregard the existence of
a separate corporate identity whenever it considers
it just or
convenient".
My
emphasis is that it is also separated from any other entity. It
should sue or be sued as a separate entity.
[69]
The court in Avena NP Incorporated in France v Eskom Holdings SOC
Limited
[6]
par
38, stated that a company that has submitted a tender can enjoy
rights and obligations arising from the award of the tender
and that
another company, even if it is related to the bidder, or forms part
of the same group, cannot claim rights and obligations
arising from
the tender process. Tengwa's costs are not the plaintiffs costs.
Simply put and as testified by the plaintiff 's witnesses,
Tengwa
Africa should claim from the plaintiff. Mr Naidoo admitted that
Tengwa Africa did everything in respect of servicing the
contract
between the plaintiff and the defendant despite admitting that it was
not allowed to do so at envisaged in the RFP.
# COSTS
INCURRED BY THE PLAINTIFF
COSTS
INCURRED BY THE PLAINTIFF
[70]
Evidence presented before court by both parties, through documents
and orally was that the plaintiff was paid about RI 1m for
service
rendered. There is no dispute that the LOA should be read together
with the RFP. All the plaintiff 's witnesses including
Mr. Naidoo
admitted to the court that the costs incurred by Tengwa Africa should
be claimed from the plaintiff not the defendant.
Further Miss Naidoo,
the defendant 's expert, told the court that the claim was not only a
legal issue but also taking accounting
system in consideration, the
double entry was not applied against the defendant, as the
transactions were between the plaintiff
and Tengwa Africa to the
exclusion of the defendant. The plaintiff's witnesses testified that
even if it was to be accepted that
plaintiff subcontracted the
service to Tengwa Africa, by so doing the arrangement could not
create privity of contract between
Tengwa Africa and the reference to
that effect is made to Concrete Construction (Pty) Ltd v Keidan &
Co (Pty) Ltd, Minister
of Public Works and Land Affairs v Group Five
Building Ltd
[7]
(A)
at 471.
## PRESCRIPTION
PRESCRIPTION
[71]
The defendant raised a plea of prescription in
that the plaintiff amended its particulars of claim on the 5
th
May 2021, claiming costs
purportedly incurred between March 2015 and September 2015. Before
then, the plaintiff claimed the costs
incurred prior to the expiry of
the LOA. The LOA lapsed on the 1
st
March 2015, and such expiry date
was confirmed by the plaintiff witnesses. Maclachlan further told the
court that the contract continued
after the 60-day period had lapsed,
because the contract, was based on good faith.
[72]
Prescription is dealt with by
Prescription Act
68 of 1969
. In terms of
Section 1
1
(d) a prescription of a debt
shall be three years.
Section 1
1
(d) should be read with
Section
12(1)
and (3).
Section
12(1)
states that subject to the provisions of subsections (2)(3) and
(4), prescription shall commence to run as soon as the debt is due.
Section
12(3)
states that a debt shall not be deemed to be due until the
creditor
has knowledge of the identity of the debtor and of the facts from
which the debt arises provided that a creditor shall
be deemed to
have acquired it by exercising reasonable care.
A
debt is regarded as something owed or anything which a person is
under an obligation to pay or render to another see Off-beat
Holiday
Club and Another v Sanibona Holiday Spa Shareblock Limited
[8]
[9]
)
and includes a delictual claim.
[73]
In Truter and Another v DeyseP the court said
that:
"Section
12(3) of the Act requires knowledge only of the material facts from
which the debt arises for the prescriptive period
to begin running-it
does not require knowledge of the relevant legal conclusions (i.e.,
that the known facts constitute negligence)
or of the existence of an
expert opinion which supports such conclusions. "
[74]
It
was further stated in Minister of Finance v Gore N. 0
[10]
that:
"This
court has, in a series of decisions, emphasised that time begins to
run against the creditor when it has the minimum
facts that are
necessary to institute action. The running of prescription is not
postponed until a creditor becomes aware of the
full extent of its
legal right. "
[75]
[11]
It
was further emphasized by the court in Mtukunya v Minister of Police
ll
that
it was not necessary for the plaintiff to know that the conduct of
the defendant was wrongful and actionable because those
were legal
conclusions. Setting the bar high for prescription, the court said,
would be tantamount to abolishing it because the
only trained lawyers
would be familiar with legal conclusions.
[76]
It
was also held in BMW Financial Services (SA) (Pty) Ltd v Harding and
Another
[12]
SA
716 at par 9 that:
"Section
11 of the Prescription Act, 68 of 1968, provides that a debt",
like that of the first defendant, "becomes
prescribed after a
period of three years from the date which the debt becomes due and
payable or
becomes
claimable"
[77]
In
the present case the LOA lapsed on the last day of February 2015, and
the plaintiff amended its particulars of claim on the 5
th
May
2021 claiming what it terms "exist costs" as alluded by the
plaintiff 's expert. In Deloitte Haskins & Sells Consultants
(Pty) Ltd v Bowthorpe Hellerman Deutsch (Pty) Ltd
[13]
at
532H emphasized that from a procedural substantive point of view
prescription starts to run from the time of amendment and
introduction
of a new cause action. Plaintiffs witnesses confirmed
that the 60-day period lapsed on the 28
th
February
2015 whilst other plaintiff 's witnesses told the court that it
lapsed on I
st
March
2015, and the present claim was initiated more than three years after
the plaintiff amended its particulars of claim.
[78]
The plaintiff contended that it rendered
service to the defendant, well after the lapse of the LOA, between
March 2015 and July
2015 and claimed paymentfor
costs incurred as result. It is clear to the court that by September
2015, the plaintiff was aware, alternatively, ought to
have been
aware of the facts giving rise to its claim against the defendant.
[79]
By the time the plaintiff amended its
particulars of claim the period of 3 years had passed.
TACIT
EXTENSION OF THE LOA
[80]
Mr. Naidoo stated in his discovered affidavit
that "the 60-day period expired on the 3
rd
March 2015 and it follows that
date onwards, none of the parties were bound by the terms of LOA".
He further stated that after
the expiry of 60-day period" Cargo
was no longer under obligation to continue to provide transportation
services to Transnet.'
The notion of tacit extension of the 60-day
period stand to fail, as the Mr. Naidoo, told the court that he
always believed that
the LOA had terminated on the 3
rd
March 2015 and was no longer
binding on the parties. According to Mr. Maclachlan, the confirmation
of service to the defendant,
beyond the expiry of 60-day period was
based on good faith and did not mean that the LOA had been extended.
Mr. Mabena 's testimony
which was uncontested was that all the
contracts 's alterations and amendments should be reduced in writing
and concluded by the
person with the necessary authority and his
testimony in that regard was also not disputed. He told the court
that the handwritten
inscription on the LOA and as such the insertion
was invalidly made by Mr. Naidoo. Summing up both parties' evidence,
the court
must consider the objective interpretation and meaning the
provisions of the RFP and the LOA, and it must further consider
whether
the RFP and the LOA should be read separately to the
exclusion of the other. Mr. Mabena, being the author of both the RFP
and LOA,
told the court that both documents are intertwined and could
not be read separately from each other. This piece of evidence was
not contested. The LOA clearly states that should negotiations
between the parties break down for any reason, the service provider
may immediately invoice the defendant for all reasonable actual costs
incurred prior
to
the date and such amount become due and payable by the defendant. The
ordinary meaning of actually incurred is "an expense
or a loss
to be deductible, it must be actually incurred" "expenditure
'actually incurred during the performance of the
project, and for the
costs to be deemed eligible, should have a monetary value."
[81]
Actual
is defined as "existing in fact, real, now, current
(Commissioner for Inland Revenue v Golden Dumps (Pty) Ltd
[14]
),
at 117 C-E. There is no dispute by both parties about to the meaning
of actual costs, however the dispute is whether the cost
incurred by
Tengwa are supposed to be paid by the defendant. All the plaintiff 's
witnesses conceded to the court that the only
costs that they were
testifying were the costs incurred by Tengwa Africa and not by the
plaintiff. They further conceded that the
defendant and Tengwa Africa
are two separate entities with separate juristic personalities. Mr.
Naidoo conceded that the plaintiff
subcontracted 100% of its work to
Tengwa, which did not submit triple BEE certificate to the defendant,
and further conceded that
the subcontracting of the service was
invalid as envisaged by the RFP. He further told the court that there
was no relationship
between Tengwa Africa and the defendant. Mr.
Mabena told the court that he only became aware of Tengwa Africa when
the matter was
heard in court and that peace of testimony was not
disputed. In the event Tengwa Africa incurred actual costs, it should
those
costs should be claim from the plaintiff not the defendant as
confirmed and stated by all the plaintiffs witnesses.
[82]
In
Tradevest 041 (Pty) LTD t/a Tradevest Logistics v Banzi Trade 40
CC
[15]
the
court held at par 73 that:
"it
is trite that a contracting party which claims damages arising from
breach of contract must prove that it actually suffered
damages or
loss.
In
order to succeed in that regard, the injured party would ordinary be
permitted to prove its damages by comparing the extend of
its
patrimony as a consequence of the breach with the position it would
otherwise have been in had the breach not occurred. "
My
emphasis is that the Tengwa Africa should claim from the plaintiff.
It is my considered view that the plaintiff failed to prove
its case
on a balance of probabilities and as a result the following order is
made:
## THE
ORDER
THE
ORDER
The
Plaintiffs claim is dismissed, and,
1.
The Plaintiff is ordered to pay costs, as on party and party scale
including counsel 's fees.
MAUBANE
AJ
ACTING
JUDGE OF THE
HIGH
COURT
GAUTENG
DIVISION, PRETORIA
APPEARANCES:
PLAINTIFF’S
COUNCIL: ADV
JO WILLIAMS
PLAINTIFF’S
ATTORNEYS: MR
ANTON HAMMAN
DEFENDANT’S
COUNCIL: ADV
KUTUMELA
DEFENDANT’S
ATTORNEYS: MR
DANIEL NYATSANZA
MS
RETHABILE MOKGATLE
[1]
1976 (4) SA 403 (A).
[2]
2001 (1) SA 88 (SCA).
[3]
(1174/2018) [20201 ZASCA 331,
[2020] 3 All SA 73
(SCA) (3 APRIL
2020).
[4]
[1897 AC] 22.
[5]
[2007] ZAWCHC 25
;
2008 (2) SA 303
C.
[6]
2017 (6) SA 621
[7]
[1955)
4 All SA 296
(A) and [19991 3 A LL SA 467 (A).
[8]
2017(5) SA 9(CC) at par 32.
[9]
(4) SA 168 (SCA at 16.
[10]
2007(1) SA 11 (SCA) at par 17.
[11]
2018(5) SA 22(CC) of par's 62-63.
[12]
(2007) 4A 11
[13]
[1990] ZASCA 136, 1991 (1) SA 525 (A)
[14]
1993 (4) SA 110 (A
[15]
[2021] 4 All SA 552
(WCC)
sino noindex
make_database footer start
Similar Cases
Cargo Carriers Proprietary Limited v Broad-Based Black Empowerment Commission and Others (76000/2019) [2022] ZAGPPHC 38; [2022] HIPR 190 (GP) (28 January 2022)
[2022] ZAGPPHC 38High Court of South Africa (Gauteng Division, Pretoria)98% similar
Imperial Logistics Advance (Pty) Ltd v Remnant Wealth Holdings (Pty) Ltd (33585/2020) [2022] ZAGPPHC 786 (14 October 2022)
[2022] ZAGPPHC 786High Court of South Africa (Gauteng Division, Pretoria)98% similar
Imperial Logistics Advance (Pty) Ltd v Master of the High Court, Pretoria and Others (2023/054694) [2025] ZAGPPHC 737 (24 July 2025)
[2025] ZAGPPHC 737High Court of South Africa (Gauteng Division, Pretoria)98% similar
Brima Logistics (Pty) Limited v Road Accident Management Corporation (2025-227233) [2026] ZAGPPHC 19 (26 January 2026)
[2026] ZAGPPHC 19High Court of South Africa (Gauteng Division, Pretoria)97% similar
Nelson Logistics CC and Another v Freightliner Finance and Insurance a Division of Mercedes-Benz Financial Services South Africa (Pty) Ltd (50025/2019) [2022] ZAGPPHC 988 (15 December 2022)
[2022] ZAGPPHC 988High Court of South Africa (Gauteng Division, Pretoria)97% similar