Case Law[2025] ZAWCHC 246South Africa
City of Cape Town v Cell C Limited and Others (20689/2018) [2025] ZAWCHC 246 (10 June 2025)
Headnotes
liable for any of their actions.[7]
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2025
>>
[2025] ZAWCHC 246
|
Noteup
|
LawCite
sino index
## City of Cape Town v Cell C Limited and Others (20689/2018) [2025] ZAWCHC 246 (10 June 2025)
City of Cape Town v Cell C Limited and Others (20689/2018) [2025] ZAWCHC 246 (10 June 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2025_246.html
sino date 10 June 2025
#
FLYNOTES:
CIVIL
PROCEDURE – Prescription –
Knowledge
of facts –
Subcontracted
work and damage to stadium – Strict liability claim –
Did not depend on identifying specific wrongdoer
– Had
sufficient knowledge of facts necessary to institute claim against
Cell C – Could have acquired requisite
knowledge of claim
against Huawei through reasonable inquiries – Failure to
make basic inquiries – Deemed to
have had constructive
knowledge of facts from date of damage – Failed to provide
convincing explanation for delay –
Claims prescribed –
Prescription Act 68 of 1969
,
s 12(3).
#
# THE REPUBLIC OF SOUTH
AFRICA
THE REPUBLIC OF SOUTH
AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case
No.: 20689/2018
Before the Hon Madam
Justice Slingers
Hearing:
13 May 2025
Judgment Delivered:
10
June 2025
In the matter between:
THE
CITY OF CAPE
TOWN
Plaintiff
and
CELL
C
LIMITED
First Defendant
HAUWEI
TECHNOLOGIES SOUTH AFRICA (PTY) LTD
Second Defendant
SAAB
GRINTEK TECHNOLOGIES (PTY) LTD
Third Defendant
CORLINE
165
CC
Fourth Defendant
This judgment is handed
down electronically by circulation to the parties’ legal
representatives’ email addresses.
The date of hand-down
is deemed to be 10 June 2025.
JUDGMENT
SLINGERS J
Introduction
[1]
The plaintiff instituted action proceedings
against the defendants wherein it claimed an amount of R909 900.00
together with
interest at ten percent per annum from service of the
summons to date of final payment.
[2]
It was the plaintiff’s pleaded case that:
(i)
during
October 2015 the plaintiff granted the first defendant permission to
access Cape Town Stadium
(‘the
stadium’)
in
order to install infrastructure
(‘the
installation’)
for
the purposes of servicing the first defendant’s customers at
the stadium. This permission was granted for the period
26
October 2015 to 11 December 2015;
[1]
(ii)
the
first defendant appointed the second defendant as its contractor to
do the installation. In turn, the second defendant
appointed
the third defendant who appointed the fourth defendant;
[2]
(iii)
the
second, third and fourth defendants all worked on the installation at
gridline 50 on level 6 of the stadium
[3]
;
(iv)
on 18
November 2015 the plaintiff discovered extensive damage to the
external façade of the stadium which was caused by a
metal
panel which had dislodged from gridline 50 on level 6 of the stadium
and which fell on or through the façade, damaging
same
[4]
;
(v)
at all
material times it was the first defendant’s duty to ensure that
the installation was done without any harm or damage
to the
stadium
[5]
; and
(vi)
inasmuch
as the damage was caused by the second, alternatively, the third,
alternatively the fourth defendant’s action, it
remained the
duty of the first defendant to ensure that no damage was done to the
stadium and it could not rid itself of this duty
by appointing a
contractor.
[6]
[3]
The
plaintiff’s main claim was against the first defendant with an
alternative claim against the second, alternatively the
third,
alternatively the fourth defendant. The alternative claims
against the second, alternatively the third, alternatively
the fourth
defendant were brought in the event that the court found that they
were independent contractors and that the first defendant
could not
be held liable for any of their actions.
[7]
[4]
The first and second defendants
(‘the
defendants’)
invoked a special
plea of prescription. They averred that the cause of action
arose on 18 November 2015 and that the summons
instituting the
proceedings were served on them after 18 November 2015.
Consequently, the plaintiff’s claim against
them prescribed
before the service of summons in terms of
section 11
of the
Prescription Act, Act
68 of 1969.
[5]
Section 11
of the
Prescription Act provides
that:
‘
11
Periods of prescription of debts
The periods of
prescription of debts shall be the following:
(a)
Thirty years in respect of –
(i)
any debt secured by mortgage bond;
(ii) any
judgment debt;
(iii) any debt in
respect of any taxation imposed or levied by or under any law;
(iv) any debt owed to
the State in respect of any share of the profits, royalties or any
similar consideration payable in respect
of the right to mine
minerals or other substances;
(b)
fifteen years in respect of any debt owed to
the State and arising out of an advance or loan of money or a sale or
lease of land
by the State to the debtor, unless a longer period
applies in respect of the debt in question in terms of paragraph (a);
(c)
six years in respect of a debt arising from a
bill of exchange or other negotiable instrument or from a notarial
contract, unless
a longer period applies in respect of the debt in
question in terms of paragraph (a) or (b);
(d)
save where an Act of parliament provides
otherwise, three years in respect of any other debt.’
[6]
The plaintiff’s claim would prescribe within
a period of three years as it falls within the ambit of
section 11(d)
of the
Prescription Act.
[7
]
Aside from invoking the plea of prescription, the
second defendant gave notice of its intention to seek a punitive
costs order against
the plaintiff.
[8]
In replicating to the defendants’ special
plea, the plaintiff pleaded as follows:
‘
The
Plaintiff denies that its cause of action arose on 18 November 2015
or that the debt in question fell due by then.
In amplification of
the aforesaid denial the Plaintiff pleads that although it discovered
that the façade was damaged on
18 November 2015, it did not
know who was responsible for causing the damages as various entities
worked and cleaned at Gridline
50 on Level 6 of the stadium in
November 2015.
These various entities
all blamed one another for the damages and advanced different
theories as to how it occurred and as such
it was impossible to
ascertain the identity of the Plaintiff’s debtor and the facts
from which the debt arises without a
thorough investigation and, in
any event, before 21 November 2015.’
[9]
The parties agreed that the question of
prescription, as raised in the pleadings, be dealt with separately to
the merits of the
plaintiff’s claim. Pursuant to this
agreement the special plea of prescription was set down for
adjudication on 13
May 2025.
The evidence
[10]
The defendants accepted that they bore the duty to
begin and the onus.
[11]
In his opening statement counsel for the first
defendant submitted that the plaintiff sought to impose strict
liability on it in
terms of its pleaded case. This rendered the
actual identity of the defendant / entity who caused the damage
irrelevant.
Furthermore, the first defendant submitted that
section 12(3)
of the
Prescription Act found
no application. As
the plaintiff discovered the loss on 18 November 2015 and served its
summons on 21 November 2018, the
plaintiff’s claim against it
had prescribed.
[12]
Section 12(3)
of the
Prescription Act provides
that:
‘
12(3)
A debt shall not be deemed to be due until the creditor has knowledge
of the identity of the debtor and of the facts
from which the debt
arises: Provided that a creditor shall be deemed to have such
knowledge if he could have acquired it by exercising
reasonable
care.’
[13]
The first defendant closed its case after its
opening statement and without calling any witnesses.
[14]
In his opening statement the legal representative
for the second defendant submitted that there were no grounds on
which the plaintiff
could succeed. It then proceeded to call Mr
Oliver Masiyakurima
(‘Masiyakurima’).
He testified that he was employed with
the second defendant since December 2014 as an ICS service engineer
and that he was responsible
for the network provision.
[15]
He testified that the second defendant was
responsible for the full end-to-end network installation and that it
was contracted by
the first defendant. Masiyakurima testified
that the first defendant was the user and that the second defendant
was responsible
for the implementation.
[16]
Masiyakurima confirmed that he was employed with
the second defendant during 2015 in the same position as that which
he currently
occupies. Masiyakurima confirmed that the
plaintiff appointed the first defendant for works to be done at the
stadium and
in turn the first defendant appointed the second
defendant.
[17]
The second defendant was responsible for the site
survey, installation and the hand over. The second defendant
does not do
the physical work but would appoint another contractor to
do the physical work which it would supervise and monitor.
[18]
On 30 September 2015, Herman Jacobs
(‘Jacobs’)
of the first defendant contacted Kevin Wood
(‘Wood’)
of
the plaintiff in respect of obtaining access to the stadium to
do the final survey. Wood advised Jacobs that the
requisite
safety requirements had to be complied with before access to the roof
could be granted. Wood referred Jacobs to
Danie Erasmus, the
stadium safety officer who would give him more details of the
requisite safety requirements.
[19]
Masiyakurima confirmed that when they attended at
the stadium security would accompany the first defendant’s
employees through
the site and when the attended at level 6 of the
stadium. He also testified that there is a register which must
be completed
upon entry at the stadium. The details of all
persons who were granted entry to the stadium were recorded in the
register.
[20]
Masiyakurima confirmed knowledge of a project plan
which set out important aspects such as details of the project,
deadlines and
milestones. Masiyakurima confirmed that he was
responsible for the design and to ensure that what was reflected on
paper
was the same product which was installed. He also
testified that all the teams relied on him in respect of what to do
and
when to do it.
[21]
Masiyakurima was on site when he received a call
on 18 November 2015. He immediately went gridline 50 on level 6
at the stadium
where he encountered a big white man who was very
upset as a result of the damage he discovered. As Masiyakurima
occupied
a junior position, he called his manager who notified the
first defendant to send a representative to attend on the scene.
Masiyakurima testified that there were representatives from the
plaintiff, the second defendant and other teams at the scene,
including Bidvest and Corline.
[22]
Masiyakurima was taken to a note dated 19 November
2015 which was penned by Shiraz Moosa in his capacity as head of
Safety and Security,
Cape Town Stadium. This note recorded that
it was alleged that the first defendant was the only contractor
working at gridline
50 on level 6 on 18 November 2015 and that it
appeared that a metal panel from level 6 may have caused the damage
to the façade;
that this panel was removed at some stage by
the first defendant; and that it may not have been secured
sufficiently.
[23]
Masiyakurima compiled a report which recorded that
on 18 November 2015 the stadium management stated that the damage was
caused
by the second defendant contractors as they worked on
location. The report contained the second defendant’s
denial
that they were responsible for the damage.
Masiyakurima’s report concluded that there was no conclusive
proof in respect
of who was responsible for the damage.
[24]
After presenting the evidence of Masiyakurima, the
second defendant closed its case.
[25]
Thereafter, the plaintiff called John Wood
(‘Wood’)
who
testified that he was employed by the plaintiff and that he was so
employed during 2015 when he was responsible for internal
infrastructure. Wood confirmed that the plaintiff gave the
first defendant permission to enter the stadium.
[26]
Wood
testified that he was aware that there was a theory that a cherry
picker under the control of Bidvest was responsible for the
damage
[8]
. Under cross
examination by counsel for the first defendant, Wood conceded that it
was never his view that Bidvest and the
cherry picker was responsible
for the damage caused and the consequent loss.
[27]
Wood unconvincingly testified that he would not
know whether the plaintiff investigates the loss of an asset in
writing or only
does so verbally. He went on to testify that he
cannot recall seeing anything or any report which recorded that
Bidvest and
a cherry picker were responsible for the damage caused.
He testified that as far as he knew, no one placed any credibility
in
the theory that Bidvest and the cherry picker caused the damage.
[28]
Wood conceded that there one of four entities
which could be liable for the damage and that he held a meeting with
representatives
of all four entities on the 18
th
of
November 2015.
[29]
Wood testified that he had not seen anything which
changed between 18 November 2015 and 21 November 2015 and that he was
not sure
that anything had changed during this time.
[30]
Wood conceded that it would be easy to determine
which party was at the stadium on a particular day. Although it
was a reasonable
question to ask which contractor removed the panel,
Wood did not pose this question. Similarly, it was a reasonable
question
to ask which contractor replaced the panel but he did not do
so. Wood also failed to ask who was responsible for supervising
the work on level 6.
[31]
When it was put to Wood that any suspicion he had
would have been alleviated by asking the above three questions, he
did not deny
it but responded with a ‘
perhaps’.
He further testified that Mr Van Rensburg would be
the person who dealt with those kind of issues.
[32]
When it was put to Wood that he wanted conclusive
proof of who was to blame for the damage before instituting the
claim, he acknowledged
that the plaintiff had wanted to know who was
responsible for the damage.
[33]
The next witness to testify was Andre Van Greunen
(‘Van Greunen’)
who was the plaintiff’s attorney at the time
of instituting the action proceedings.
[34]
Van
Greunen testified that he authored the letter addressed to the
Sheriff of the High Court, Bellville
(‘the
Sheriff’)
dated
9 November 2018. This letter requested that the summons with
the particulars of claim be served by no later than 18
November
2018
[9]
. Van Greunen
testified that he made this request out of an abundance of caution as
he knew that the plaintiff discovered
the damage on the 18
th
of
November
2015 and he wanted to prevent any possible argument on prescription.
He emphasized that the plaintiff did not know
who caused the damages
on 18 November 2015.
[35]
On 7
January 2019 Van Greunen directed further correspondence to the
Sheriff because he failed to comply with the request to serve
the
summons with the particulars of claim on the first and second
defendants timeously.
[10]
This letter stated
inter
alia
the
following:
‘
2.
You were informed in writing that service must be effected on or
before 18 November
2018 as there may be issues of prescription should
it be served later’
and
‘
6.
This
letter serves to inform you that should our client’s claim be
dismissed on the basis that it has prescribed, our client
will hold
your office responsible for any losses suffered as a result thereof.
Please be advised that our client is claiming
the amount of R909,
900.00 from the defendants. That is also the amount that our
client will seek to recover from your office
should it be required.
If you are insured for claims of these nature, we would suggest that
you advise your insurers accordingly.’
[36]
Van Greunen testified that they had consulted with
people who may be able to shed light on the issues but that no-one
knew who caused
the damages. However, it was unclear whether
the second and third defendants were appointed to the project as
sub-contractors
to the first defendant or as independent contractors.
[37]
In an email dated 5 November 2018, Van Greunen
inquired from Stefanus Landsberg of the second defendant about the
capacity in which
the third defendant was appointed to the stadium
project and whether this was in the capacity of a sub-contractor.
[38]
This inquiry was made almost three years after the
damage was discovered. During the presentation of the
plaintiff’s
case there was no explanation why this inquiry was
not done sooner.
[39]
It was put to Van Greunen that the meeting held on
the day of the incident resulted in the plaintiff having sufficient
information
to institute its action. In response, Van Greunen
testified that had no knowledge of the identities of the persons with
whom
Wood met. Van Greunen was unable to comment and/or respond
when it was put to him that on 18 November 2015 the plaintiff had
sufficient information and/facts to institute proceedings against the
defendants. Alternatively, it could obtain sufficient
knowledge
by making a simple inquiry of asking
who
do you work for.
[40]
It was also put to Van Greunen that in accordance
with
section 12(3)
of the
Prescription Act, prescription
starts to
run when a plaintiff has sufficient knowledge to commence
proceedings, it need not have perfect knowledge necessary to
establish its case.
[41]
The plaintiff closed its case after Wood’s
testimony.
The parties’
arguments
[42]
The first defendant argued that the plaintiff’s
claim against it was a contractual one in terms whereof the first
defendant
accepted a species of strict liability for the conduct of
the second to the fourth defendants.
[43]
The first defendant argued that on the plaintiff’s
pleaded case it was possessed of sufficient facts to determine the
identity
of the debtor in relation to the sum claimed and that it was
irrelevant how the loss was caused as the first defendant would
irrespective
thereof be liable, therefore.
[44]
Further, the commencement of the running of
prescription is not delayed until the claimant has knowledge of all
the facts necessary
to establish its case. On the contrary, the
running of prescription commences when a claimant has all the facts
necessary
to establish the cause of action.
[45]
The second defendant argued that this was a case
of the plaintiff seeking all the facts, evidence and conclusions
before it issued
summons. However, this is not required by law
which requires only the minimum sufficient facts in law. These
facts
were within the plaintiff’s knowledge on 18 November 2015
as it knew everything it needed to know to issue summons.
Therefore, prescription started running on 18 November 2015.
[46]
The second defendant argued that the plaintiff’s
case did not revolve around the identity of the wrongdoer
[47]
Furthermore, it was argued that if the plaintiff
asked three questions, namely (i)who did (ii)what (iii)when, it would
have obtained
the requisite knowledge on 18 November 2015 needed to
institute proceedings. In other words, had the plaintiff acted
reasonable,
it would have obtained the information it required to
issue summons. The plaintiff failed to act reasonably to
acquire the
information it thought necessary to institute
proceedings.
[48]
In the circumstances, the second defendant argued
that the plaintiff’s claim against it had prescribed.
[49]
The plaintiff averred that prescription did not
begin to run by virtue of
section 12(3)
and that prescription did not
start to run on 18 November 2015 as it did not know which party
caused the damage at that stage.
The law
[50]
It is common cause that the period of prescription
for the amount claimed by the plaintiff is three years.
[51]
Prescription
begins to run against a party when it has the minimum facts necessary
to institute action. Consequently, the
running of prescription
is not postponed until such time that a claimant learns of the full
extent of its legal right nor until
such time that a claimant has all
the evidence which it requires to comfortably establish its case.
[11]
[52]
This court has cited with approval the
proposition that time starts to run against a creditor when it has
'the minimum facts that
are necessary to institute action' and that
the running of prescription is not postponed until the creditor
'becomes aware of the
full extent of its legal rights'.
[53]
It
has been held that a debt is due when the entire set of facts which
the creditor must prove in order to succeed with his or her
claim
against the debtor is in place or, in other words, when everything
has happened which would entitle the creditor to institute
action and
to pursue his or her claim. This does not include the legal
conclusions which a litigant seeks to draw from the
facts.
[12]
[54]
Prescription
would start running against a party when there is either knowledge or
awareness of the facts from which the debt arises
as well as the
identity of the debtor. A party would be deemed to have
knowledge of these facts if he/she could have acquired
it by
exercising reasonable care.
[13]
[55]
Whether
or not it could be said that a party failed to exercise reasonable
care would depend on a number of factors and consideration
of all the
circumstances relevant to the claimant’s conduct.
[14]
[56]
The
inquiry into whether a claimant may be deemed to have acquired the
requisite knowledge and whether he/she exercised reasonable
care is
an objective, and not a subjective inquiry. Therefore, the
claimant’s conduct is tested by weighing it against
the steps
which a reasonable person in his or her position would have taken to
acquire knowledge the requisite minimum facts to
enable him/her to
institute his/her claim timeously.
[15]
Discussion
(i)
The plaintiff’s case against the first defendant
[57]
I deal firstly with the plaintiff’s case
against the first defendant.
[58]
Counsel for the first defendant submitted that the
plaintiff’s pleaded case against the first defendant is based
on strict
liability akin to vicarious liability. This is an
accurate description of the plaintiff’s pleaded case against
the
first defendant.
[59]
The facts which are set out in the plaintiff’s
particulars of claim are the same facts which he had at his disposal
on 18
November 2015. Thus, on 18 November 2015, the plaintiff
had the minimum facts it needed to institute proceedings against the
first defendant.
[60]
Therefore, prescription in respect of the
plaintiff’s claim against the first defendant started running
on 18 November 2015.
Consequently, as the summons instituting
proceedings was served on the first defendant after 18 November 2018
being three years
after the claim arose, the plaintiff’s claim
against the first defendant has prescribed.
(ii)
The plaintiff’s case against the second defendant
[61]
I turn now to the plaintiff’s claim against
the second defendant.
[62]
The court is told that the plaintiff did not know
the identity of the party responsible for the damage to gridline 50
on level 6
on 18 November 2015. The court is not told when the
plaintiff discovered the identity of the party responsible for the
damage
to gridline 50 on level 6.
[63]
The evidence has shown that the plaintiff could
have ascertained the minimum facts it needed to institute proceedings
by directing
three simple questions to the parties present at the
meeting held on 18 November 2015 on the site. The
plaintiff had
simply to ask, ‘
who
did what when
’
. There was
no reasonable explanation for the failure to do so. Similarly,
there was no explanation why the plaintiff,
through its attorney,
only made inquiries in respect of the capacity in which the third
defendant was appointed to the installation
project, almost three
years after the damage was discovered.
[64]
Therefore, it cannot be said that the plaintiff
exercised reasonable care. Had the plaintiff exercised
reasonable care, it
could have acquired the minimum facts it needed
to institute proceedings.
[65]
Consequently, the plaintiff is deemed to have this
knowledge on 18 November 2015. Therefore, the summons
instituting the plaintiff’s
claim had to be served on the
second plaintiff by 18 November 2018. It was not.
Consequently, the plaintiff’s
claim against the second
defendant has prescribed.
[66]
Based on the papers filed on record and the
evidence presented, it is evident that nothing changed in the
plaintiff’s knowledge
pertaining to the incident from 18
November 2015 and 21 November 2015.
[67]
The plaintiff instituted proceedings against the
defendants with the same total of knowledge it had on 18 November
2015. This
is conclusive of the fact that the plaintiff was
aware of / had knowledge of the facts it needed to institute its
claim against
the defendants were within its knowledge on 18 November
2015. Therefore, prescription started to run on 18 November
2015,
which meant that the plaintiff’s summons had to be served
on the defendants by 18 November 2018.
[68]
It is clear from the plaintiff’s pleaded
case that it still does not know which defendant was responsible for
causing the
damage. Thus, it instituted its claim in the form
of a main claim against the first defendant with alternative claims
against
the other defendants. The lack of knowledge pertaining
to the identity of the actual wrongdoer who was responsible for the
damage was, therefore, clearly not a requisite factor necessary for
the institution of the plaintiff’s claim.
[69]
It is clear from Van Greunen’s evidence and
his correspondence directed to the Sheriff that the plaintiff knew
that the summons
had to be served by 18 November 2018, failing which
its claim would prescribe. His evidence that he wanted the
sheriff to
serve the summons before the 18
th
of
November 2018 out of abundance of
caution and to prevent the invocation of prescription was
unconvincing and improbable.
[70]
Notwithstanding that the plaintiff knew that its
claim had prescribed and the warning by the second plaintiff, it
proceeded with
instituting its claim against the second defendant.
[71]
In the circumstances, the second defendant’s
pray for punitive costs are reasonable.
Orders
[72]
Therefore, I make the following orders:
(i)
the first defendant’s special plea of
prescription is upheld as the plaintiff’s claim against the
first defendant has
prescribed;
(ii)
the plaintiff’s claim against the first
defendant is dismissed with costs, which cost shall be on scale B;
(iii)
the second defendant’s special plea of
prescription is upheld as the plaintiff’s claim against the
second defendant
has prescribed;
(iv)
the plaintiff’s claim against the second
defendant is dismissed with costs, which costs shall be on an
attorney – client
scale on scale B.
SLINGERS, J
[1]
Paragraph
7 of the amended particulars of claim, page 6
[2]
Paragraph
8 of the amended particulars of claim, page 6
[3]
Paragraph
9 of the amended particulars of claim, page 6
[4]
Paragraph
10 of the amended particulars of claim, pages 6-7
[5]
Paragraph
12 of the amended particulars of claim, page 7
[6]
Paragraph
13 of the amended particulars of claim, page 7
[7]
Paragraph
15 of the amended particulars of claim, page 8
[8]
The
cherry picker was apparently used by Bidvest to clean the stadium.
[9]
Page
58 of the plaintiff’s bundle
[10]
Page
61 of the plaintiff’s bundle
[11]
Minister
of Finance and Others v Gore NO
2007
(1) SA 111
(SCA) at para [17]; See also
President
of the Republic of South Africa and Another v Tembani and Others
2025
(2) SA 371
(CC) at para [86]
[12]
Truter
and another v Deysel
[2006] ZASCA 16
;
2006
(4) SA 168
(SCA) at paras [16] and [17];
Le
Roux and Another v Johannes G Coetzee & Seuns and Another
[13]
Le Roux
and Another v Johannes G Coetzee & Seuns and Another
2024 (4) SA 1 (CC)
[14]
Brand v
Williams
1988
(3) SA 908
(C) quoted with approval in
Le
Roux and Another v Johannes G Coetzee & Seuns and Another
[15]
Leketi
v Tladi NO
2010
JDR 0329 (SCA)
sino noindex
make_database footer start
Similar Cases
City of Cape Town v Those Persons Identified in Annexure A and Another (14732/2024) [2025] ZAWCHC 490 (24 October 2025)
[2025] ZAWCHC 490High Court of South Africa (Western Cape Division)100% similar
City of Cape Town v Johannes Rooyen and Another (A23/2025) [2025] ZAWCHC 507 (31 October 2025)
[2025] ZAWCHC 507High Court of South Africa (Western Cape Division)100% similar
City of Cape Town and Others v Master of the High Court, Cape Town and Others (2025/207083) [2025] ZAWCHC 586 (12 December 2025)
[2025] ZAWCHC 586High Court of South Africa (Western Cape Division)100% similar
City of Cape Town v Hussain and Others (Appeal) (A268/2024) [2025] ZAWCHC 171 (17 April 2025)
[2025] ZAWCHC 171High Court of South Africa (Western Cape Division)100% similar
City of Cape Town v Hearne and Others (5453/2022) [2024] ZAWCHC 253 (10 September 2024)
[2024] ZAWCHC 253High Court of South Africa (Western Cape Division)99% similar