Case Law[2025] ZAWCHC 427South Africa
Tempani Construction (Pty) Ltd v Minister of Public Works and Infrastructure (16571/2024) [2025] ZAWCHC 427 (15 September 2025)
Headnotes
Summary: Contract- parole evidence rule-integrated clause
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2025
>>
[2025] ZAWCHC 427
|
Noteup
|
LawCite
sino index
## Tempani Construction (Pty) Ltd v Minister of Public Works and Infrastructure (16571/2024) [2025] ZAWCHC 427 (15 September 2025)
Tempani Construction (Pty) Ltd v Minister of Public Works and Infrastructure (16571/2024) [2025] ZAWCHC 427 (15 September 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2025_427.html
sino date 15 September 2025
IN THE HIGH COURT OF
SOUTH AFRICA
(WESTERN CAPE
DIVISION, CAPE TOWN)
Case no:16571/2024
In the matter between:
TEMPANI CONSTRUCTION
(PTY) LTD
Applicant
And
THE MINISTER OF PUBLIC
WORKS AND INFRASTRUCTURE
Respondent
Heard: 17 March 2025
Delivered:
15 September 2025
Summary:
Contract- parole evidence rule-integrated clause
ORDER
Counter claim dismissed.
Orders sought by
applicants granted.
# JUDGMENT DELIVERED
ELECTRONICAL
JUDGMENT DELIVERED
ELECTRONICAL
NZIWENI J
Introduction
[1]
In this application, the applicant seeks to make the final award,
made in its favour by the adjudicator on 28 June 2024, an
order of
this court. This relief is sought in terms of Rule 6.2.2 of the
JBCC Adjudication Rules. The applicant also seeks
the relief from
this Court on the grounds that the parties had agreed [in an
Adjudication Agreement entered between the parties]
to resolve their
disputes
only
by
an adjudication mechanism. The relief that is sought by the applicant
is directed squarely towards making the adjudicator’s
award
final and a definite determination upon the subject between the
parties.
[2]
Accordingly, the applicant asserts that the parties did not reach an
agreement that created a right to ‘appeal’
the
adjudicator’s determination through the mechanism of
arbitration.
[3]
On the other hand, the respondent asserts that the parties set forth
a two-tiered mechanism for resolving disputes or disagreements
between themselves. According to the respondent, both the mechanisms
were memorialised in written contracts.
[4]
The respondent opposes this application on the basis that the parties
agreed to both adjudication and arbitration mechanisms.
The
respondent holds the firm view that the two-tiered mechanisms were
set forth in the event that any party is not satisfied with
the
adjudicator’s determination, it would be able to take the
adjudicators finding to arbitration as envisaged in the Addendum
Contract.
[5]
It is common cause between the parties that the Addendum Contract
upon which the respondent relies, was only signed on behalf
of the
respondent.
[6]
The dispute in this case centers around whether the parties agreed on
adjudication and arbitration to govern their disputes
arising out of
the JBCC contract. And whether the integration clause in the JBCC
Contract precludes proof of the Addendum Contract.
[7]
The respondent has also launched a counter application. In the
counter application, the respondent seeks a declaratory order
declaring that the parties have agreed to both adjudication and
arbitration; alternatively, the arbitrator’s findings should
be
set aside.
[8]
The reliefs that are sought in this matter by the parties are related
to the factual background of the matter. It is thus critical
to
present a review of the background facts to frame the context
relevant to decide this matter. In fact, it is necessary to sketch
the events forming the background to the dispute. It is also
significant to note that quite an amount of the factual background
to
these proceedings is not in dispute and I turn, therefore, to that
factual background.
Factual background
[9]
The controversy between the parties has a long history that needs to
be briefly stated. The Applicant entered into a building
contract
with the respondent (“the Department”) for the
construction of a community day centre in Delft (“the
Delft
project”). The genesis to the present dispute between the
parties is the outstanding monies for the construction of
the Delft
project. As mentioned previously, the adjudicator made a
determination against Department. Inter alia, the adjudicator
determined that the Department is to pay the applicant the sum of R10
420 365.61 (plus VAT). The date of final completion of the
Delft
project was in August 2017.
[10]
According to the applicant, despite
receiving demand, the Department has not made payment of the amount
due in terms of the adjudicator’s
determination, and the
Principal Agent has refused to amend the final account and to issue a
final certificate in accordance with
the determination.
[11]
As I have previously observed, the order sought by the Applicant in
these proceedings is pursuant to Rule 6.2.2 of the JBCC
Adjudication
Rules. Rule 6.2 of the Adjudication Rules states the following:
“
6.2
Either party may:
6.2.1 Within five (5)
days, in writing, request the adjudicator to correct any patent
clerical, typographical or arithmetical error
or clarify any
ambiguity in the determination. Such party shall simultaneously
furnish the other party with the copy of such request.
The
adjudicator shall comply with such request within a further five (5)
working days.
6.2.2 Apply to the High
Court for the enforcement of the determination. The parties shall
accept the jurisdiction of such court.”
[12]
This matter involves three separate instruments. The first one is the
JBCC contract
and the other ones are the Adjudication
Agreement and the Addendum Contract
.
JBCC Contract
[13]
The JBCC contract has an integration clause that provides as follows
:
“
1.8
This agreement is the entire contract between the parties regarding
the matters addressed in this agreement. No presentations,
terms
conditions or warranties not contained in this agreement shall be
binding on the parties.
No agreement or
addendum varying, adding to, deleting or cancelling this agreement
shall be effective unless reduced to writing
and signed by the
parties
.” Own underlining.
[14]
On 31 May 2023, the applicant’s attorneys addressed a letter,
to amongst others, the Department’s attorneys, seeking
changes
in the process for dispute resolution. The letter read in part as
follows:
“
DISPUTE
HAS ARISEN
4. It is evident from the
content of your letter that a dispute has arisen between the parties
and that such dispute stands to be
resolved by way of dispute
resolution mechanisms provided for in the contract.
ALTERNATIVE DISPUTE
RESOLUTION MECHANISMS
5. Our client is of the
opinion that the parties will not be able to resolve this dispute by
way of Mediation. In this regard, we
record as follows:
5.1. Mediation is not a
precondition in the contract for Adjudication /
Arbitration to commence.
5.2. Mediation is
unfortunately relatively unsuccessful where a public body is
concerned as it is challenging to ensure that the
parties at the
Mediation have an adequate mandate and discretion to settle a matter.
5.3. This specific
dispute is not capable of being mediated as the parties legal
positions are diametrically opposed.
6. Having said that, our
client is committed to the resolution of the dispute in the most
expeditious, practical and cost-effective
manner.
7. In order to achieve
this objective, our client would like the parties to refer the matter
(sic) Adjudication. However, due to
the legal complexity of the
dispute, Adjudication in its unadulterated form is not appropriate as
it is in both parties interest
that they are guided by legal
professionals.
8. Kindly advise whether
the DPW will agree as follows:
8.1.
That the dispute is referred to Adjudication.
8.2.
. . .
8.3
. . .
8.4
. . .
9. Should the DPW not be
prepared to have this dispute adjudicated (on the above basis), then
the matter must be resolved by way
of arbitration proceedings.
10. Arbitrations are far
more adversarial, lengthy and costly by nature . . .
11. In the event that the
DPW insists on Arbitration, we suggest that DPW select one of the
four advocates.
12. Kindly take
instruction and revert within the next 10 days.
13. Should we receive no
response, it is our instruction to follow the usual approach to have
an arbitrator appointed by Association
in terms of the contractual
provision applicable”.
[15]
On 09 June 2023, the Department’s attorneys replied to the
applicant’s attorneys letter, pointing out the following:
“
2.
We herewith confirm that our client has made the following
recommendations to the Department:
2.1
The dispute be referred to adjudication. Should this be unsuccessful,
the matter should then go to arbitration;
2.2 . . .
2.3 That the normal rules
of adjudication apply;
2.4 . . .
3. It is our instructions
that our client is still awaiting the feedback from the Department
regarding the above recommendation.
We trust you find the
above in order and will revert as soon as confirmation is received
from Department.”
[16]
On 08 December 2023, the Department’s representative emailed
the applicant’s representative the Addendum contract
requesting
the applicant to complete and to sign the Addendum contract. The
Addendum contract is only signed by the Department,
and it also
reflects that it was signed [by the Department] on 10 November 2023.
[17]
The Adjudication Agreement concluded between the parties was signed
by both parties in January 2024.
[18]
On 12 July 2024 the Department’s legal representative wrote a
detailed letter to the applicant’s representative
reading in
part as follows:
“
To
this end we draw your attention to the attached letter of Schroter
Attorneys, . . . addressed to yourself on 09 June 2023, in
which they
informed your office of the following . . .
5. On the strength of the
recommendation and after consulting its internal legal advisors, the
Department accordingly agreed to
amend the agreement to make
provision for the standard dispute resolution clauses,
of
adjudication and arbitration
. To this end the attached amended
addendum to the agreement was signed . . . and emailed to you . . .
for countersigning.
6. As a result, the
Department has always approached this dispute on the basis that
should adjudication not be successful, the matter
could be referred
to arbitration, upon notice of dissatisfaction of the adjudication
determination by any of the parties.
7. Considering the above
. . .the above actions taken by the Department in amending the
initial agreement to make provision for
adjudication and
arbitration
reflect
the true intention of the parties to resolve this
dispute.
8. we note your
instructions that your client does not consent to arbitration, but we
do think that such instructions are not properly
considered,
as
your client has already consented to arbitration
. My own
emphasis.
Clause
40 of the contract stated that any dispute between the parties that
cannot be resolved inter se, the parties would refer
the matter to be
resolved through litigation.
[19]
Pursuant to the conclusion of the JBCC [building contract], the
parties entered into an Adjudication Agreement by which they
decided
to refer the disputes between them to adjudication. The parties also
agreed that their Adjudication Agreement would be
governed by the
JBCC Adjudication Rules.
[20]
On 28 June 2024, the adjudicator made a determination in the
following terms:
6.1. The Department is to
pay the Applicant the sum of R10 420 365.61 (plus VAT);
6.2. The principal agent
appointed on the project by the Department Equity Studio (Pty) Ltd
(“A”), was found to have
been incorrect in rejecting the
Claimants claims for an adjustment of the contract value.
6.3. That the amount of
R10 420 365.61 (plus VAT) is to be included in the final account on
the project and that a final payment
certificate was to be issued.
6.4. The final payment
certificate is to be issued immediately.
6.5. The Department is to
pay the costs of the adjudication including the adjudicator’s
costs and the Claimant’s costs
on a party-and- party basis.
[21]
In a letter (“letter of
dissatisfaction”) to the adjudicator dated 5 July 2024, the
Department advised that it was dissatisfied
with the determination
and that it intended to refer the dispute to arbitration.
[22]
The Applicant responded to the letter of dissatisfaction by the
Department, by email in which it [Applicant] stated
inter
alia
:
“
That
the building contract did not provide for the determination to be
referred to arbitration (due to the Department being dissatisfied
therewith, or at all for that matter”). The Department does not
enjoy a contractual right to refer the dispute to arbitration.
If the
Department is “
dissatisfied
”
with the determination, then the dispute to be referred to
litigation, unless the parties agree otherwise.
Since the Applicant is
not prepared to consent to an arbitration process, the Department
would need to proceed with litigation.”
[23]
On 12 July 2024, the Department’s attorney sent the applicant’s
attorneys an email. See paragraph 18 of this judgment
for the
contents of the
email.
[24]
The email also stated that when the parties referred the matter to
Adjudication, the Department did so with an understanding
that the
standard dispute resolution clauses of adjudication and arbitration
would apply. To buttress this contention, the Department
emphasised
that a written addendum to the building contract that was prepared
and signed by the Department on 10 November 2023.
However, the
addendum was not counter signed by the Applicant.
[25]
On 15 July 2024, the Applicant’s attorneys sent an email to the
Department’s attorneys asserting, amongst others,
that the
applicant disputes the Department’s construction of the
agreement between the parties. In the email, the applicant
denies the
existence of an arbitration agreement (in writing or otherwise) and
that there was no binding amendment to the contract
to provide for
arbitration. The email further states that the default position
remains litigation as per the original contract
between the parties.
Parties’
submission
a.
Applicants’ submissions
[26]
According to the applicant, in this case, it is common cause that the
final account should have been issued in January 2016.
The final
account was only delivered seven years later in February 2023. The
applicant avers that this was a breach of contract.
Due to the late
issuance, the applicant was kept out of pocket, in respect of
substantial outstanding amount [several millions
of rands]. To
address this, in 2018, the applicant then launched an urgent
application to get the outstanding amounts. After an
order was
granted in 2019, it took another four years for the Departments’
agents to issue a final account.
[27]
At the time when the final account was issued, in terms of the
building contract, the procedure for the resolution of disputes
was
through litigation. After the issuance of the final account,
disputes arose between the parties in respect of monies
that the
applicant alleged should have been included in the final account. The
Applicant’s attorneys proposed that the parties
should refer
these disputes for adjudication. This led to the parties concluding
an Adjudication Agreement in January 2024.
[28]
An adjudicator was appointed, and an adjudication hearing was held.
At the end of June, the Adjudicator delivered his determination.
According to the applicant, the Department refused to comply with the
determination. The applicant asserts that the
Department
took the position that the matter should at that stage be referred to
arbitration without any legal basis for that position.
[29]
The applicant drew this Court’s attention to the amendment to
the Standard Contract in relations to dispute resolution
by means of
the State Provisions. According to the applicant, the conventional
procedures [Adjudication and Arbitration] were removed
from the
Standard Contract and replaced with litigation.
[30]
The applicant is of the view that it is significant that this Court
should have regard to the amendment of the Standard Provisions
in
relation to dispute resolution by means of the State Provisions.
[31]
The applicant then asserts that the parties then amended clause 40
that stipulated that litigation was the only option. And
that shortly
after the issuance of final account, disputes arose [applicant
contended that this is so because certain amounts it
was entitled to
were not included in the final account].
[32]
According to the applicant, it was never the applicant’s
intention to refer the arising disputes for arbitration. The
applicant asserts that one, if not the primary, reason behind
adjudication mechanism is that it is a short, inexpensive, and
relatively
easy process as opposed to arbitration and litigation.
[33]
The applicant further contends that the Department’s assertion
falls foul of the parole evidence rule. To this end, the
applicant
contends that the Department intends to rely on extrinsic evidence to
add or alter the provisions of an agreement. It
is also the
applicant’s contention that it is not for the department to
tell the court what the intentions of the parties
were, but the
court’s duty.
[34]
Further, it is the applicant’s contention that the Department’s
reliance on the Addendum Contract is still born
as the clause 1.8 of
the JBCC Contract has a non-variation clause. The applicant contends
that the respondent’s reliance
on the Addendum Contract is
legally unsustainable as it was not signed by both parties as
required by clause 1.8 of the JBCC. It
is further the applicant’s
contention that the applicant refused to sign the Addendum Contract.
[35]
It is the applicant’s contention that even on the Department’s
case, the Addendum Contract had to be signed by
both parties to have
any effect, as reflected by the email dated 08 December 2023, from
Grant de La Cruz. The applicant further
asserts that the
Addendum Contract also specifically stipulates that all pages of the
Addendum Contract must be initialed in the
same way as the original
bid document.
[36]
The applicant further argued that the fact that the Department was
unsuccessful in its attempt to get the Addendum Contract
signed by
the applicant is important as far as context is concerned.
[37]
Mr de Villiers, SC on applicant’s behalf, made it very clear
during his submissions that at no stage during communication
between
Mr Pienaar [on behalf of the applicant] and Ms Hossain on behalf of
the Department] regarding finalisation of the Adjudication
Agreement,
did Ms Hossain refer to the Addendum Contract.
[38]
Counsel for the applicant earnestly points out that the Addendum
Contract was never part of the negotiations that culminated
in the
conclusion of the Adjudication Agreement.
[39]
According to the applicant, the first relevant context in this matter
is the letter dated 31 May 2023, from the applicant’s
attorney,
advising that the parties should not refer the matter to arbitration.
[40]
Mr de Vivier SC argues and stresses that the background context in
this matter, provides the strongest evidence supporting
the
applicant’s contention that the Adjudication Agreement is the
binding agreement between the parties. According
to the
applicant’s counsel, the following background context is
necessary to fully understand the intentions of the parties:
a.
That the parties agreed on the dispute
resolution provision in the JBCC.
b.
That the applicant communicated its
preferred choice that is adjudication.
c.
That at that relevant stage, a normal
underlining purpose of adjudication and arbitration no longer
existed, as the building had
been completed and the final account had
been issued.
d.
That Mr de La Cruz’s attempt to
introduce the Addendum came out of the blue and he was informed that
the applicant would not
sign the Addendum.
e.
During the final stage of the negotiations,
Ms Hoosain never referred to the Addendum.
[41]
According to the applicant, the proposal was that the Adjudicator was
meant to be the final arbiter of the parties’ disputes.
[42]
In the replying affidavit, the applicant refers to the Addendum as an
abandoned attempt to amend the JBCC contract. As such,
so the
argument ran, the respondent cannot rely on the unsigned Addendum to
elevate it to be above Adjudication Agreement.
b.
The Department’s submission
[43]
In essence, the Department wants to prove existence of a separate
Arbitration contract, as a valid and binding agreement between
the
parties. According to the Department’s counsel, the crucial
aspect which the applicant did not take the court to its
confidence
is the failure to reveal the existence of the Addendum in its
founding papers.
[44]
According to the Department, the Adjudication Agreement is only a
part of the agreement between the parties. Mr R Stelzner,
SC, counsel
for the Department, vehemently argued that the whole of the agreement
was broader and that the Adjudication Agreement
was not to be the
sole dispute resolution mechanism. Thus, the Department argued that
from purpose and context of this matter it
is clear that the
Adjudication Agreement was not meant to be the sole dispute
resolution mechanism.
[45]
Department asserts that the Addendum contract
is
fundamental part of determining whether
the applicant is entitled to enforcement of the adjudication award or
not and that depends on the interpretation of the Adjudication
Agreement.
[46]
According to Mr
Stelzner SC,
the parole evidence
rule does not prevent a party from telling the court what the whole
agreement was.
The
Department argues that the parole evidence does kick in when only
parts of the agreement are placed before the court.
It
is the Department’s contention that the Adjudication Agreement
is not the sole memorial of the parties’ transaction
in this
suit. According to the Department, the Department is seeking to
place the full picture, full content and full context
before the
court in order to assess what the Adjudication Agreement is.
The argument continues to state that the Adjudication
Agreement needs
to be seen in the context of that which preceded it and for the
purpose for which it was signed.
[47]
It is also the Department’s submission that the parties agreed
to amend the JBCC contract and agreed to other dispute
resolution
mechanism. It was contended on behalf of the Department that JBCC
Contract postulates litigation and alternatively adjudication
and
arbitration.
[48]
According to the Department, the applicant wishes that this Court
should ignore the history and the context and just look at
the
Adjudication Agreement. It is the Department submission that should
this Court scrutinise the context too closely, the case
of the
applicant would collapse in its entirety.
[49]
It was submitted on behalf of the Department that what it argued for
the respondent is not in conflict with what is provided
for in the
Adjudication Agreement.
[50]
The Department’s counsel also relied on the email dated 08
September 2023, from Mr Botha to the applicant. He argued
that
the applicant cannot come and argue that there was no Addendum
Contract signed by both parties but there was an Adjudication
Agreement.
[51]
It was contended on behalf of the respondent that what is crucial
about the Addendum Contract are two things, the first one
is that the
dispute resolution by litigation clause was substituted by
adjudication. According to the Department, the Addendum
that is
signed on behalf of the Department provides for a full dispute
resolution mechanism.
[52]
It was argued on behalf of the Department that in terms of clause
40.5# of the JBCC, should a party be dissatisfied with the
decision
of the adjudicator, the dispute which is a subject matter of
dissatisfaction shall be finally resolved by the arbitrator.
[53]
According to the Department, subsequent to the decision to have a
full dispute resolution mechanism, the acting head of the
legal
department of the Department was presented with the Adjudication
Agreement and they signed it. It is argued that the
Adjudication Agreement ‘s context is the Addendum signed on
behalf of the Department previously and the purpose is to resolve
the
dispute first by way of adjudication if one of the parties is
dissatisfied with the adjudication, then by way of 40.5# of the
JBCC.
[54]
It is submitted on Department’s behalf that when the applicant
states that it never agreed to the Addendum Contract as
they never
signed it, that means
that there is no
amendment of the JBCC Contract,
as the
Department made it clear that
the only
amendment that was mandated was one as provided for in the Addendum
.
According to the Department, the Addendum was sent to the applicant’s
attorney and the applicant’s attorney signed
the Adjudication
Agreement. And in so doing the applicant’s attorney only dealt
with part of the agreement. So the argument
continues, as a result,
there was a partial integration of the whole parties’
agreement. It is the argument of the
Department that the
applicant deliberately signed part of the agreement.
[55]
According to the Department, the context shows that the Addendum
identified that there would be a process of adjudication and
arbitration. Thereafter the parties signed the Adjudication Agreement
to deal with the adjudication part. Having committed themselves
to
adjudication as
part of adjudication and
arbitration
, the applicant cannot come
and argue that the whole arbitration
requirement
falls away.
[56]
According to the Department, the parties agreed to both adjudication
and arbitration mechanisms. Further, the Department contends
that
when the parties agreed to amend the building contract, it was
amended to cater for both adjudication and arbitration.
[57]
The Department argues that it is opportunistic of the applicant to
seek an order from this Court for payment for claims that
are in
excess of R10 million. It was further submitted on the
Department’s behalf that it was a self-serving omission
on the
part of the applicant not to sign the Addendum Contract and this
creates a deception. It was contended that, when
the Department
signed the Adjudication Agreement, it was not informed that the
applicant was refusing to sign the Addendum. When
Mr Stelzner SC drew
this Court’s attention to the email from Charlton Botha to Sean
Pienaar, dated 26 September 2023, he
argued that the email conveys
that the adjudication process meant to be part of a broader agreement
that was still in the process
of being vetted and needed to be
mandated and sanctioned.
[58]
According to the Department, the parties started to deal with a
specific component of the process, the Adjudication Agreement.
The
Department counsel submitted that the Department thought that the
addendum was signed and that is why the Department signed
the
Adjudication Agreement.
[59]
The Department’s counsel emphasised the point that the context
of the whole agreement is broader. Counsel on behalf
of the
Department, submits that this Court is going to find the context
leading up to the two documents [Adjudication Agreement
and the
Addendum] in the letter sent to the applicant’s attorneys from
Mr Grant de La Cruz, the chief architect, on 8 December
2023. The
counsel further argues that the letter highlights and emphasises the
fact that the only amendment the Department is going
to be prepared
to agree to is the one that is mandated by the Department. The
Department maintains that the only amendment that
was mandated was
the one provided for in the Addendum Contract.
[60]
It is the Department’s counsel’s argument that
if
the applicant maintains that they never agreed to the Addendum
contract, then there is no amendment of the JBCC Contract
.
Then the amendment contemplated by the Adjudication Agreement was not
effected. The Department submits that this is the case because
there
was a partial integration of the old parties’ agreement.
[61]
Mr Stelzner SC further asserts that nowhere in the Adjudication
Agreement would this Court find that it [the Adjudication Agreement]
is the only method to resolve disputes.
[62]
The Department submits that the adjudicator did not address the
defences raised by the Department and simply ignored them or
did not
engage with them. As such, the award by the adjudicator was plainly
erroneous.
Evaluation
[63]
The Addendum Contract by its terms it was intended to provide for a
process of adjudication followed by arbitration should
either party
be dissatisfied with the decision given by the adjudicator. And was
intended to amend and supplement the original
contract [JBCC].
[64]
The rules for interpreting contracts are well-settled and are laid
out in plethora of authorities. In this matter,
this
Court is expected to give effect to the mutual intention of the
parties as it existed at the time of contracting, so far as
the same
is ascertainable. It is common cause between the parties that the
building contract JBCC only made provision for litigation.
That the
Adjudication Agreement is silent on arbitration. It is also common
ground that the Department unilaterally drafted and
signed an
Addendum Contract.
[65]
The issue for determination is what the agreement was between the
parties. Put differently, whether the Adjudication Agreement
denotes
the full agreement between the parties.
Integration
[66]
The applicant asserts that the parties in the Adjudication Agreement
expressly bargained for only Adjudication. On the other
hand,
the
Department fervently contends that the Adjudication Agreement only
expresses certain terms of their agreement rather than the
agreement
in its
entirety.
[67]
In this regard, this Court has to amongst others, determine as to
whether:
a.
the Adjudication Agreement appears on its
face to be a complete agreement;
b.
whether the Addendum contract directly
contradicts the Adjudication Agreement; and
c.
would the Addendum Contract tend to deceive
this Court.
[68]
It is significant to note that when
the parties to an agreement express their intention that ought to be
the complete expression
of their agreement. And that should signify
that integration had occurred. Ordinarily, the presence of an
integration clause in
an agreement will be quite convincing factor,
if not decisive one, on the issue of integration. In essence, this
denotes
that the
agreement concluded between the parties may not be contradicted by
evidence of other agreements.
[69]
In the present application, the
Adjudication Agreement does not contain an integration clause. In
this regard, the applicant argues
that it is the integration clause
in the JBCC contract that bars the proof of the Addendum Contract.
[70]
During the making of a contract parties are at liberty of rejecting
or accepting a bargain offered. To that end, parties are
at liberty
to make unjust contracts. And when an unjust contract is concluded
between the parties, a party cannot expect the courts
to amend the
terms that prove unsatisfactory or unjust.
The parties’
intention
[71]
The applicant’s counsel submits that the evidence the
Department wants to rely on in respect of the unsigned Addendum
is
extrinsic evidence. The applicant says the assertion that the
applicant accepted the Addendum that was signed by the Department
is
untrue. The applicant asserts further that the Addendum was sent to
applicant’s director, who refused to sign the document
because
that was not what the parties agreed to.
[72]
It is well-established that the intention of the parties in any
agreement is determined from the language used by the parties
in the
agreement or from their conduct in relation thereto. It is also a
well-settled interpretation principle that a court cannot
create a
contract the parties did not intend to conclude or to insert language
one or both parties now wish had been included.
In fact, in the
interpretation of a contract, a court is tasked with giving effect to
the mutual intention of the parties at the
time of the conclusion of
the contract.
[73]
In this case, there is no impasse about the meaning of a particular
word or phrase. It is well established that if the contract’s
language is unambiguous, then the ordinary sense of the wording must
prevail in its interpretation. No party in this matter argued
that
the terms of the JBCC Contract, the Adjudication Agreement and the
Addendum Contract are ambiguous.
[74]
And it is not in dispute that the JBCC Contract contains an
integration clause. By necessary implication the integration clause
in the JBCC Contract is applicable to Adjudication Agreement.
When
the court is faced with the duty to interpret an agreement, the
interpretation has to have effect to the parties’ intent
.
In this matter, the parties have a different take on the terms to
which they agreed to. As asserted by the Department that the
applicant as the party seeking to enforce the Adjudication Agreement
bears the onus of proving that the contract it seeks to enforce
is
valid contract and its terms.
[75]
The applicant did not sign the Addendum Contract and thus contends
that it is not bound by it as it never assented to the terms
of the
Addendum Contract. The Department asserts that the Addendum Contract
was executed to further modify the JBCC and constitute
a valid
modification of the original JBCC Contract. The Department further
asserts that they would not have signed the Adjudication
Agreement
absent the Addendum Contract. In essence, the Department argues that
the existence of the Addendum Contract demonstrates
a latent
ambiguity within the Adjudication Agreement.
[76]
According to the Department, the Adjudication Agreement is
incomplete. Thus, there is partial integration.
[77]
To give effect to each part of the contract, [the terms of the
agreement] the entire agreement is to be taken holistically
and not
in a piecemeal fashion. Or, putting it in another way, no clause is
to be taken in isolation. It is also well settled that
putting a
contract in writing ensures clarity about what the parties’
obligations are and what they are biding themselves
to. When parties
reduce a contract in writing, the intention of the parties is to be
ascertained from the writing alone
,
if
possible
. Hence, the written
contract, in general, is said to be the sole memorial of the
agreement between the parties.
[78]
Thus, a clear written agreement
may
triumph over any negotiations or conditions related to it that
preceded or accompanied the execution of the contract. Hence, the
parole evidence rule entails that evidence that is intended to
contradict the terms of the written agreement is not allowed. In
fact, it is trite that a court cannot consider extrinsic evidence of
any prior agreement
or verbal agreement to vary or contradict the clear and unambiguous
terms of a written, integrated contract. But to this general
rule
[the parole evidence rule], there are exceptions.
Exception to the
parole evidence rule
[79]
AJ Kerr, in The Principles of the Law of
Contract
6 ed (2002) at 348,
highlighted the point that it is better to look at the parole
evidence rule as a question of the integration
of parts into a whole.
The learned author further states the following:
“
Thus
in National Board (Pretoria) (Pty) Ltd and another v Estate
Swanepoel, Botha JA approved the following statement in Wigmore
on
Evidence: This process of embodying the terms of a jural act in a
single memorial may be termed the integration of the act,
ie its
formation from scattered parts into an integrated documentary unit.
The practical consequences of this is that its scattered
parts,
in
their former and inchoate shape, do not have any jural effect;
they
are replaced by a single embodiment of the act.
In other words:
When a
jural act is embodied in a
single memorial
, all
other utterances of the parties on that topic are legally immaterial
for the purposes of determining what are the terms of
their act”.
[80]
The learned authors
Schwikkard & van
Der Merwe 3rd Edition
462 -463 states:
“
There
are several qualifications and exceptions to the general rule
excluding parole evidence. Some of these are not truly
exceptions, but rather instances which fall outside the scope of the
rule. Where for instance, a written contract is not intended
to cover
the terms of the transaction all-inclusive, evidence of further oral
terms is not precluded. The rule does not apply to
a document which
contains a mere narration of an event, and which does not constitute
a jural act; nor does the rule exclude evidence
which throws light on
the true nature of the transaction referred to in a written document.
. . Parole evidence may for instance,
be admissible of a collateral
agreement and additional terms and subsequent oral variations, but
not where writing is a requirement
of law, and such evidence seeks to
contradict the written instrument. A similar result arises
where the contract contains
a clause to the effect that no variation
or rescission of the contract shall be valid unless it is reduced to
writing. But that,
of course, is not due to the operation of the
parole evidence rule. Curiously, even contracts that are required by
law to be in
writing can be cancelled orally.”
[81]
In this case, the Department seeks this Court to consider the facts
and circumstances surrounding the execution of the agreements
to
determine as to whether the contract is fully integrated or partially
integrated. On the other hand, the applicant strongly
asserts that
the parole evidence rule does not allow this Court to do that.
Factors relevant to this consideration include
the following:
a.
Clause 2 of the Adjudication Agreement
states the following:
“
The
parties agree that
the disputes
between them (referred to in paragraph 4 below) be resolved by
adjudication in terms of this agreement.
b.
Clause 4 of the Adjudication Contract
states that:
“
ADJUDICATION
DISPUTES”
The parties confirm that
the disputes to be determined in this Adjudication relate to the
construction contract (JBCC) concluded
between the parties in
relations to the construction of the Delf Community Day Centre.”
c.
Clause 5 of the Adjudication Agreement
provides the following:
“
RULES
GOVERNING THE ARBITRATION
5.1 The JBCC Adjudication
Rules January 2020 edition, published by the Association of
Arbitration of Southern Africa (“the
Rules”).
5.2 The parties confirm,
as envisaged in clause 5.4.3 of the Rules, that they agree that both
parties shall be entitled to be represented
by practising attorneys
(and advocates) at the Adjudication.”
[82]
This court has a difficult task of deciding whether the parties had a
true meeting of the minds and how to resolve the parties’
disagreement.
[83]
As previously mentioned, the Adjudication Agreement does not contain
a clause that states that its terms are the complete and
final
agreement between the parties. Thus, the question that begs is
whether it is an integrated agreement. There is also
no
indication that the Adjudication Agreement is conditional or that the
parties did not intend to be bound by its terms. The question
that
aptly arises is whether the Addendum Contract is a separate and
unrelated contract.
[84]
It is so that the JBCC Contract contains a clause that states the
following:
“
1.8
This agreement is the entire contract between the parties regarding
the matters addressed in this agreement. No presentations,
terms
conditions or warranties not contained in this agreement shall be
binding on the parties. No agreement or addendum varying,
adding to,
deleting or cancelling this agreement shall be effective unless
reduced to writing and signed by the parties.”
[85]
Obviously the JBCC Contract contained an integrated clause. It
categorically specifies that it may be amended only by a written
instrument signed by all of the parties. The Adjudication Agreement
does not mention anything about arbitration and does not include
any
clause that alludes to an Addendum Contract.
[86]
A contract is completely integrated if on its face it is plain that
the parties intended the writing to be a final and total
expression
of their agreement. Similarly, a contract that appears to be
unambiguous on its face may still contain a latent ambiguity
that can
only be exposed by extrinsic evidence. Hence, in order to determine
whether extrinsic evidence is admissible, the test
is not whether on
its face, the contract and its meaning appear to the court to be
unambiguous, but whether the evidence offered
is relevant to prove a
meaning to which the language of the instrument is reasonably
susceptible.
[87]
More importantly, it is not correct to exclude relevant extrinsic
evidence that would explain the meaning of a written contract
unless
it is possible to determine the meaning the parties ascribed to the
words from the contract alone.
[88]
In this matter, the Department is arguing that the existence of the
Addendum Contract exposes and demonstrates the ambiguity
of the
Adjudication Agreement. The counsel on behalf of the Department
vehemently asserted that the Addendum Contract is merely
a partial
integration of the agreement that was intended by the parties. The
Department’s case reveals that the Adjudication
Agreement and
the Addendum Contract are still scattered parts of the parties’
intentions. As such, so the argument continues
the Adjudication
Agreement cannot be regarded as integral documentary unit, as it does
not set out the entire agreement between
the parties. The
Department’s argument postulates that when this Court has made
a determination that these two jural acts
are embodied in a single
memorial, whether apart [the Adjudication process] or both
[Adjudication and Arbitration], the parole
evidence rule will only be
applicable then. I agree. In order to determine the intention of the
parties, this court needs to have
regard to both instruments and the
history leading to them.
[89]
According to the applicant, other aspects that are crucial to the
context of this matter are the following:
a.
the response provided by the Department’s
attorney in response to the applicant’s letter dated 31 May
2023, which stated
that the dispute should be referred to
adjudication and should adjudication be unsuccessful, the dispute
should go for arbitration.
b.
the telephone conversation between Schröter
attorneys [ Department’s attorneys] and Mr Pienaar [on behalf
of the applicant]
where the two agreed to refer the matter the matter
to adjudication.
c.
A further aspect related to context is the
email dated 08 September 2023, from Charlton Botha, on behalf of the
Department, which
indicated that it was the Department’s stated
position that the parties must attend to this matter by means a
formal amendment
signed by all the parties. The applicant submits
that it is significant to note that the issue of formalities was
discussed when
the subject of discussion was the draft Adjudication
Agreement.
d.
On 26 September 2023, an email from Mr
Botha to Mr Pienaar amongst others, indicated that the Department was
not yet in a position
to advance with the adjudication process, as
the agreement was meant to be signed by both parties.
Mutual
assent
[90]
This Court cannot enforce a contract unless it is
able to determine what in fact the parties have agreed to. To
begin with,
the court is precluded from interfering or making a
contract for the parties, as parties are free to choose if they want
to contract,
with whom and on what terms. The court, however, will
enforce a binding contract between the parties. The essence of a
contract
is a meeting of the minds.
[91]
Accordingly, mutual assent as a material
prerequisite must be manifested. For a valid contract to exist,
each party needs
to have a serious and deliberate intention to
contract or to be legally bound by the agreement, the animus
contrahendi (See
Fleet Africa (Pty) Ltd v Nijs
(JA9/15)
[2017] ZALAC 8
; (2017) 38 ILJ 1059 (LAC);
[2017] 5 BLLR 450
(LAC) (20
January 2017) at paragraph 21 and
Scottish
Union & National Insurance Co Ltd v Native Recruiting Corporation
Ltd
1934 AD 458
at 465). The parties must
also be ad idem (or have the meeting of the minds) as to the terms of
the agreement. Obviously,
absent the animus contrahendi between the
parties or from either of them, no contractual obligations can be
said to exist and be
capable of legal enforcement.’ See Nijs
supra.
[92]
First and foremost, in this case, there is no doubt that the JBCC
Contract prescribes a method of acceptance. The JBCC contract
is a
standard contract that was prepared by the Department. The
Department requires that this Court should turn a blind eye
to the
failure to comply with the prescribed method of acceptance. This is
because the Department asserts that it was not meant
to be bound only
by the Adjudication Agreement as its validity was conditional upon
the conclusion of the Arbitration Contract.
[93]
In
the circumstances of this case, this contention is unsound. This
Court cannot ignore unambiguous contractual undertakings. To
do so
would be to create an act without legal significance.
[94]
The parties agreed before the amendment of the JBCC Contract that
writing and signatures constitute a formality. The Adjudication
Agreement appears to be carefully and formally drafted. It is
detailed and gives an impression that it was drafted by a person
knowledgeable about the subject matter.
[95]
There is no evidence in this matter to prove that the applicant
induced the respondent to believe that it agreed on the two-tier
dispute resolution mechanisms. Instead, the evidence reveals that the
applicant refused to sign the Addendum Contract when the
Department
requested it to do so. There is also no evidence or a suggestion that
the applicant made a tacit waiver of signing as
the prescribed method
of acceptance for a valid formation of the agreement.
[96]
What the Department is seeking from this Court is that this Court
should strain the law or the facts of this matter to find
that the
parties had a meeting of mind to have a two-tier dispute resolution
mechanism.
[97]
This then begs the question as to what constitute a written
agreement? As far as the Addendum Contract is concerned, the
applicant
was provided with a draft that embodied in writing all its
terms. The issue with the Addendum Contract is that it was not signed
by the applicant.
[98]
To begin with, it is trite that not every agreement constitutes a
contract. It is my firm view that the proof that a party
has
expressed its unconditional assent to a contract cannot only be
proven by the mere existence of a written instrument. Thus,
when the
parties have expressed their intentions and reduced them into a
written document, that does not necessarily mean that
a valid
contract has been concluded even if it is signed by the parties.
Unconditional assent to the terms of the written agreement
must be
proven if required.
[99]
Equally, a signed written contract is not always an indication of a
valid agreement between the parties. In this matter, there
is
prescribed mode and formalities for acceptance of a contract. And
signatures are one of them. Accordingly, the parties
in terms
of the JBCC contract agreed that agreements between them would be
concluded only upon signature by both parties.
[100]
In
Pillay v
Shaik
2009
4 SA 74
(SCA) [2012] at para 50, the following was stated:
“
In
my opinion it is clear from
Goldblatt v
Freemantle
, supra, and the authorities
cited therein that, in the absence of a statute which prescribes
writing signed by the parties or their
authorised representatives as
an essential requisite for the creation of a contractual obligation
(something that does not apply
here), an agreement between parties
which satisfies all the other requirements for contractual validity
will be held not to have
given rise to contractual obligations
only
if there is a pre-existing contract between the parties which
prescribes compliance with a formality or formalities before
a
binding contract can come into existence
.
That this is so is clear,
for example, from C W Decker's annotation on Van Leeuwen's
Roman
Dutch Law
4.2 sec 1 (not sec 2 as Innes CJ says at 129) where he
pointed out (Kotzé's translation, 2 ed, vol 2, p 12) that we
no longer
uphold the distinction drawn in Roman law between real,
verbal, literal and consensual contracts because all contracts with
us
are made with consent. With regard to written contracts he
referred to an observation by Samuel Strykius (
Modern Pandect
2.14.7) as follows:
'. . . we must regard the
written
contracts as distinct, in so far as we should bear in
mind that although the writing does not constitute the essentiality
of the
contract, which is contained in the mutual consent of the
parties, they may nevertheless agree that their verbal agreement
shall
be of no effect until reduced to writing, in which case the
agreement cannot before signature have any binding force, although
there exists mutual consent; and it cannot be said that the writing
served not in perfecting the transaction, but only as proof
thereof .
. ., since here it is agreed that the consent should not operate
without the writing, which must be observed as a legitimate
condition.”
My own emphasis.
[101]
It is evident that the circumstances in the
Shaik
matter
were different to this one, hence, the doctrine of quasi assent is
not applicable in this case. This becomes clear when the
following is
stated in the Shaik matter, supra, at para 52.
[102]
Unlike in the
Shaik
matter, in the present case there were clearly no agreements between
the parties that the mutual consent between them would not
operate in
the absence of a document embodying its terms signed by both buyer
and seller.
Conclusion
[103]
Even though an integration may be partial as well as complete, in
this matter, when regard is had to paragraph 1.8 of the
JBCC
contract, the correspondence written by the applicant to the
Department and the Adjudication Agreement, it becomes clear that
the
parties intended that the Adjudication Agreement to express their
final and complete terms in the agreement in its entirety
rather than
certain terms. Thus, the Adjudication Agreement shows that the
parties have agreed to it as a complete and final embodiment
of the
terms of their agreement. Thus, the extrinsic evidence cannot be used
to contradict its terms.
[104]
In this case, as previously
mentioned, the JBCC contract categorically states the requirements
for a valid contract. And one of
them is the signing by the parties.
The applicant did not sign the Addendum Contract, and as such the
Addendum Contract did not
come into existence. Consequently, the
applicant is not bound by it. Even the Department for that matter is
not bound by the terms
of the Addendum Contract.
[105]
Having considered the above, I conclude that the Adjudication
Agreement is a completely integrated document. As such, there
is
nothing in this case to convince this Court that the existence of the
Adjudication Agreement depends on the validity
of the Addendum
Contract.
Parties are at liberty to
conclude agreements that are good and bad. The courts in ensuring and
upholding freedom of contract enforce
all voluntary agreements
concluded between the parties. The exception to freedom of contract
is contracts that offend public policy.
Accordingly, I disagree with
the Department’s submission that the applicant is snatching at
a bargain in circumstances where
it knows or should have known that
it is not entitled to what that it is claiming.
[106]
As far as the attack levelled against the Adjudicator’s
determination is concerned, this Court does not have power to
interfere with the finding of the adjudicator, as the parties have
agreed that their disputes would be determined by the adjudicator.
[107]
Because of my findings, the counter claim of the Department cannot be
sustained.
Costs
[108]
In light of the facts of this matter, I am not convinced that the
opposition of the Department was not warranted. Additionally,
the
matter warranted the employ of senior counsel.
[109]
In the result, I make the following order:
a.
The respondent’s counter claim is
dismissed
b.
The determination of MR Howard Boetcher
dated 28 June 2024 is made an order of this Court
c.
The respondent is ordered to pay the costs
of suit on scale C.
CN
NZIWENI
JUDGE OF THE HIGH
COURT
APPEARANCES
For the applicant
:
Adv. P de B. VIVIER SC
Attorneys
:
Enderstein Malumbete In.
SW
Pienaar
For the first
respondent
:
Adv. R STELSNER SC
Adv. A
NACERDIEN
Attorneys
:
Office of the State Attorney
Aayesah
Hoosaim
sino noindex
make_database footer start
Similar Cases
Temmies and Another v S (Appeal) (A35/2025) [2025] ZAWCHC 184; [2025] 3 All SA 876 (WCC) (29 April 2025)
[2025] ZAWCHC 184High Court of South Africa (Western Cape Division)98% similar
Sakhana Construction CC v Strand Junction Retail (Pty) Limited (4219/2022) [2022] ZAWCHC 225 (3 November 2022)
[2022] ZAWCHC 225High Court of South Africa (Western Cape Division)98% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (Leave to Appeal) (17470/2014) [2025] ZAWCHC 453 (3 October 2025)
[2025] ZAWCHC 453High Court of South Africa (Western Cape Division)98% similar
Chiware v Tusk Construction Support Services Pty Ltd and Others (16056/2023) [2025] ZAWCHC 379 (25 August 2025)
[2025] ZAWCHC 379High Court of South Africa (Western Cape Division)98% similar
TMT Services and Supplies (Proprietary) Ltd t/a Traffic Management Technologies v City of Matlosana and Another (21070/2024) [2025] ZAWCHC 582 (10 December 2025)
[2025] ZAWCHC 582High Court of South Africa (Western Cape Division)98% similar