Case Law[2023] ZAWCHC 72South Africa
JVZ JV and Others v City of Cape Town (4873/2022) [2023] ZAWCHC 72 (13 April 2023)
High Court of South Africa (Western Cape Division)
13 April 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2023
>>
[2023] ZAWCHC 72
|
Noteup
|
LawCite
sino index
## JVZ JV and Others v City of Cape Town (4873/2022) [2023] ZAWCHC 72 (13 April 2023)
JVZ JV and Others v City of Cape Town (4873/2022) [2023] ZAWCHC 72 (13 April 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2023_72.html
sino date 13 April 2023
IN THE HIGH COURT OF
SOUTH AFRICA
(WESTERN CAPE
DIVISION, CAPE TOWN)
Case Number: 4873 / 2022
In the matter between:
JVZ
JV
First Excipient
JVZ
CONSTRUCTION (PTY)
LTD
Second Excipient
SR
CIVIL CONTRACTORS (PTY)
LTD
Third Excipient
and
THE
CITY OF CAPE
TOWN
Respondent
Coram:
Wille, J
Heard:
15 March 2023
Delivered:
13 April 2023
JUDGMENT
WILLE, J:
Introduction:
[1]
This is an exception at the instance of the excipient applicants.
The parties
will be referred to as the plaintiff and the defendants
as they were referenced in the particulars of the claim as formulated
by
the plaintiff. The plaintiff instituted an action against
the defendants for the repayment of monies paid by the plaintiff
to
the defendants according to a decision made by an adjudicator in
respect of claims by the defendants arising from a written
construction agreement.
[1]
[2]
The plaintiff alleged that it breached the agreement with the
defendants by giving
them written notice to cease work and vacate the
construction site.
[2]
This
work on the site had commenced about a month before the notice to
cease the work and exit the site. The plaintiff’s
case is
that their later conduct amounted to a repudiation of the agreement,
alternatively, a breach of the agreement with the
defendants.
[3]
This is where the defendants differ. The plaintiff avers that
the defendants
then submitted a claim to the plaintiff on account of
the plaintiff’s breach and the delays attributable thereto
under the
agreement for an extension of time, payment of additional
time related items and payment of proven additional costs due to
delays
attributable to the plaintiff. The defendants’
position is that they made an election to enforce the agreement.
These two opposing positions result in a material difference in the
compensation awarded to the defendants. This is what this exception
is all about.
[4]
The plaintiff says the defendants are only entitled to financial
compensation because
of a breach of the agreement by the plaintiff on
account of the delay caused by the plaintiff’s breach and that
this compensation
translates into the form of a penalty. Put in
another way, the defendants are to be financially recompensed only
regarding
damages suffered on account of delays attributable to a
breach of the agreement by the plaintiff calculated regarding a
prescribed
formula related to the actual damages suffered.
[5]
The argument is that billed rates do not represent actual costs.
When a claim
is activated according to an extension of time regarding
a delay attributable to a breach of the agreement, this operates as a
penalty stipulation. Thus, the defendants are consequently
prohibited by legislative intervention from receiving both the
penalty and damages or the latter instead of the penalty.
[3]
By elaboration, the plaintiff avers that the court is empowered to
reduce the penalty and accordingly seeks a reduction.
[6]
The defendants
say that on a proper
construction of the agreement read with the correct application of
our jurisprudence on contract law, the defendants
are entitled to
pursue a claim where a failure or delay on the part of the plaintiff
(in fulfilling any necessary obligation to
enable the works to
proceed following the agreement) takes place. This is then the
defendants’ case and claim.
[7]
Further, it is submitted on behalf of the defendants that it cannot
be seriously contended
that there was a breach of the agreement by
the plaintiff in fulfilling a necessary obligation to which the
plaintiff is in any
event contractually bound. In simple terms,
the question is raised about the precise identity of the alleged
breach of the
agreement by the plaintiff.
Context:
[8]
The plaintiff notified the defendants in writing that, according to
them, the agreement
was void and unenforceable and that the
defendants were instructed to cease all work and vacate the
construction site.
[4]
This
was because an ‘appeal authority’ had concluded that the
underlying basis for the agreement with the defendants
was absent and
the agreement was set aside.
[9]
Thus, this ‘appeal authority’ concluded that the
agreement between the
plaintiff and the defendants was at an end and
had no force or effect. The defendants disputed the validity of
this finding.
This finding was subsequently overturned by way
of a court order. The court declared the tender awarded to the
defendants
and the agreement to be of full force and effect.
[10]
In summary, the appeal authority’s decision was reviewed and
set aside. Thus, the
plaintiff averred that the notice issued
to the defendants to cease work and vacate the site represented a
repudiation, alternatively,
a material breach of the agreement.
It is positively pleaded by the plaintiff that: (a) the defendants
suffered a delay in
practical completion (b) the defendants incurred
proven additional costs from a failure or delay on the part of the
plaintiff,
and (c) that the defendants are, therefore contractually
entitled to make claims only following a specified clause in the
agreement.
[5]
The
defendants say they are entitled to an extension of time for
circumstances of any kind whatsoever, that they extended
the date of
practical completion and, are therefore entitled to claims following
an extension of time as defined in a different
clause in the
agreement.
[6]
[11]
On the pleadings, it is a matter of common cause that the defendants
were entitled to an extension
of time and that the plaintiff granted
the same to the defendants. Because of this, the defendants say
that on a proper construction
of the agreement, they are entitled to
be paid such additional time-related general items, including for
non-working days, if applicable,
as are appropriate with any other
compensation which may already have been granted in respect of the
circumstances concerned.
[12]
Thus they argue that the clause relied upon by the plaintiff must be
read together with the clauses
upon which they depend. This, in
effect, means that a claim is permitted where practical completion is
delayed due to a failure
or delay on the part of the plaintiff in the
fulfilling of the necessary obligations to enable the works to
proceed (an extension
of time for practical completion) together with
any additional proven costs in terms of the agreement.
[13]
The defendants’ case is that, as a matter of pure logic, they
are entitled to claim for
an extension of time for circumstances of
any kind whatsoever which may occur, and they may claim an extension
in terms of the
clause in the agreement relied upon by the plaintiff.
[14]
Herein lies the rub. The difference is that on the plaintiff’s
version, any claim
is limited to an extension of time and recovery of
proven costs
incurred due to a failure of or delay by the
plaintiff. On the contrary, the defendants aver that their
claims are not limited
to a claim for extension of time (and not
additional proven incurred costs) but for any circumstances
whatsoever. They argue
that, undoubtedly, it is so that a
prerequisite for their claim is the application for an extension of
time and not a failure or
delay by the plaintiff. This is the
very issue that bears further scrutiny.
Consideration:
[15]
It is submitted on behalf of the defendants that when an extension of
time is granted, they are
entitled not only to recover proven actual
incurred costs but rather to be paid for additional time-related
general items.
The submission is made that this is not a claim
for damages. Instead, the agreement provides a mechanism that
is employed
to pay the defendants for time-related items as the
contract period has been extended.
[16]
Put another way, the defendants were paid for the extended period and
not because of a breach
or the damages that may have been caused.
Thus, this does not involve a penalty stipulation as the
defendants are paid for
a longer time, employed for a longer time,
and paid at a pre-agreed rate. The claim by the defendants
against the plaintiff
was never to recover a penalty and damages.
Thus, they say the provisions of the Act find no application. The
plaintiff
argues that only proven additional costs incurred can be
claimed, and because of this, the provisions of the Act find
application.
Jurisprudence:
[17]
Our jurisprudence indicates that a clause in a civil engineering
contract placing an obligation
on an employer to hand over the
construction site to a contractor cannot be invoked to render a
subsequent deprivation of possession
to be a breach of contract.
[7]
This is because, among other things, an obligation to hand over the
site has reference to the inception of a contract and
initial access
to the site. Once this possession is given, this duty is
discharged, and the said clause has no other function
in the
execution of the contract. Therefore, any subsequent
deprivation, if wrongful, would give rise to an action in terms
of
the contract. On this, I agree.
[18]
Further, it is well-established law that a contractor who is vested
with contractual remedies,
in addition, retains all common law
remedies, especially in any claim for damages, unless this is
expressly excluded.
[8]
In
these circumstances, the plaintiff delayed in fulfilling a necessary
obligation to enable the works to proceed, which
(in my view) was
sufficient on its own, together with the agreed extension of time for
the plaintiff’s claims. No breach
of contract is
established or even required.
[19]
The case for the plaintiff is that because of the application of the
Act, the defendants are
not entitled to claim a penalty as well as
damages or claim damages in place of the penalty as there is no
provision for this species
of claim. This is the core exception
raised by the defendants. They say the pleadings by the
plaintiff on this score
amount to a penalty stipulation in terms of
the Act.
[20]
A penalty stipulation essentially means that any person, in respect
of an act or omission in
conflict with a contractual obligation, who
is liable to pay a sum of money for the benefit of any other person,
either by way
of penalty or as liquidated damages, shall (subject to
specific provisions) be liable to pay an amount of money, called a
penalty.
If, upon hearing a claim for a penalty, it appears to
the court that such a penalty is out of proportion to the prejudice
suffered
by the creditor because of the act or omission in respect of
which the penalty was stipulated, the court may reduce the penalty.
This has been interpreted to mean a claim for a penalty or the return
of a penalty.
[9]
[22]
It is a prerequisite that the claim be based on a penalty stipulation
unless the clause in question
constitutes a penalty.
[10]
Most significantly, the liability to pay must derive from a breach of
contract. Otherwise, the stipulation relied on
would not
qualify as a penalty. I say this because it is impermissible to
regard as a penalty stipulation, a contractual
term which provides
for payment in the event of the premature termination of the contract
and which became enforceable incidentally
due to a breach of
contract.
[11]
[23]
It is against this canvass that I am enjoined to look at the pleading
excepted to as it stands.
No facts outside those stated in the
pleadings may be considered. No reference may be made to any
other document.
[12]
To
disclose a cause of action, a plaintiff must plead every material
fact that would be necessary for the plaintiff to prove
to obtain a
judgment.
[13]
[24]
Put in another way, it is impermissible to plead a conclusion of law
in the absence of the material
facts giving rise to it having been
pleaded. This goes to the principle of the question of whether,
as a matter of law, the
allegations in the particulars of the claim,
adequately interpreted, make out a cause of action.
[14]
This principle applies only to material allegations of fact. It
does not extend to inferences and conclusions not warranted
by the
material allegations of fact.
[15]
[25]
At the outset of the argument, I raised with counsel for the
defendants if the exception contended
for did not essentially concern
questions about the interpretation of the agreement between the
plaintiff and the defendants. In
response, it was emphasized
that the exception raised to the claims by the plaintiff were, in
essence, fact-bound and concerned
facts which were not in dispute.
On this, I agree.
[26]
I say this, among other things, because of the following penchant
remarks made when dealing with
‘fact-bound’ exceptions:
‘…
the
response to an exception should be like a sword that cuts through the
tissue of which the exception is compounded and exposes
its
vulnerability
…’
[16]
Conclusion:
[27]
For all these reasons, the claims currently
formulated by the plaintiff are subject to exception. I also
accept that some
of the averments made by the plaintiff in the
particulars of the lawsuit could have (and should have) been pleaded
with more clarity
and precision. This is considering the multiple
provisions in the agreement between the plaintiff and the defendants.
[28]
The following order is granted, namely that:
1.
The exceptions are upheld at the instance of the defendants.
2
The plaintiff is afforded leave to amend its claims within a period
of twenty
(20) court days from the date hereof.
3.
The costs of and incidental to the exception proceedings shall stand
over for
determination by the trial court.
E. D. WILLE
Cape Town
[1]
The
agreement.
[2]
This
on the 6 August 2019.
[3]
Section
1(1) and 2(1) of Act 15 of 1962 (the “Act”).
[4]
This
on 6 August 2019..
[5]
Clause
10.1 of the agreement.
[6]
In
terms of clause 5.12.1 of the agreement.
[7]
Imprefed
(Pty) Ltd v National Transport Commission
1993 (3) SA 94
(A) at 104 E-G.
[8]
Group
Five Building Ltd v Minister of Community Development
[1993] ZASCA 75
;
1993 (3) SA 629
(AD) at 651 D-E.
[9]
Portwig
v Deputation Street Investments (Pty) Ltd
1985
(1) SA 83 (D) at 88 E-F.
[10]
Sun
Packaginng (Pty) Ltd v Vreulink
[1996] ZASCA 73
;
1996 (4) SA 176
(AD) at 182 H-I.
[11]
De
Pinto and Another v Rensea Investments (Pty) Ltd
1977 (2) SA 1000 (A)
[12]
Baliso
v FirstRand Bank Ltd t/a Wesbank
2017 (1) SA 292
(CC) at 303 E.
[13]
Trope
v South African Reserve Bank
[1993] ZASCA 54
;
1993
(3) SA 264
(A) at 273 A-C.
[14]
Amalgamated
Footwear and Leather Industries v Jordan & Co Ltd
1948 (2) SA 891
(C) at 893.
[15]
Natal
Fresh Produce Growers’ Association v Agroserve (Pty Ltd
1990 (4) SA 749
(N) at 755 A.
[16]
Telematrix
(Pty) Ltd t/a Matrix Vehicle Tracking v Advertising Standards
Authority SA
at 466 A.
sino noindex
make_database footer start
Similar Cases
J.V.R v Director General of Home Affairs and Others (12111/24) [2025] ZAWCHC 69; [2025] 2 All SA 927 (WCC) (19 February 2025)
[2025] ZAWCHC 69High Court of South Africa (Western Cape Division)98% similar
T.S v J.V.C.P and Another (20783/24) [2025] ZAWCHC 325 (1 August 2025)
[2025] ZAWCHC 325High Court of South Africa (Western Cape Division)98% similar
Z.K.M v V.A.M (13924 / 2022; 16505 / 2018) [2023] ZAWCHC 2 (17 January 2023)
[2023] ZAWCHC 2High Court of South Africa (Western Cape Division)98% similar
S.M.W NO v J.J.W And Others (13122/2019 ; 8222/2020) [2025] ZAWCHC 575 (10 December 2025)
[2025] ZAWCHC 575High Court of South Africa (Western Cape Division)98% similar
L.V.Z v A.V.Z (18151/24) [2024] ZAWCHC 365 (12 November 2024)
[2024] ZAWCHC 365High Court of South Africa (Western Cape Division)98% similar