Case Law[2023] ZAWCHC 77South Africa
Lead Engineering and Projects (Pty) Ltd v Swe Repco SA (Pty) Ltd and Others (16567/2022) [2023] ZAWCHC 77 (18 April 2023)
High Court of South Africa (Western Cape Division)
18 April 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2023
>>
[2023] ZAWCHC 77
|
Noteup
|
LawCite
sino index
## Lead Engineering and Projects (Pty) Ltd v Swe Repco SA (Pty) Ltd and Others (16567/2022) [2023] ZAWCHC 77 (18 April 2023)
Lead Engineering and Projects (Pty) Ltd v Swe Repco SA (Pty) Ltd and Others (16567/2022) [2023] ZAWCHC 77 (18 April 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2023_77.html
sino date 18 April 2023
IN
THE HIGH COURT OF SOUTH AFRICA
WESTERN
CAPE DIVISION, CAPE TOWN
Case
number:16567/2022
In
the matter between:
LEAD
ENGINEERING AND PROJECTS (Pty) Ltd
Applicant
and
SWE
REPCO SA (Pty) Ltd
First
Respondent
SOLAR
CAPITAL (Pty) Ltd
Second
Respondent
SOLAR
CAPITAL ORANGE (Pty) Ltd
Third
Respondent
JUDGMENT
DELIVERED ELECTRONICALLY ON 18 APRIL 2023
RALARALA
AJ
1.
INTRODUCTION
[1]
This matter was served before me on an urgent basis. The applicant
sought
an order directing that the respondents
restore the applicant’s access and or possession of the project
site situated approximately
53 kilometres North East of
Loeriesfontein, (“the Project Site”).
[2]
The applicant, Lead Engineering and Projects (Pty) Ltd (‘LEP’)
has been
engaged in electrical, mechanical and civil works on a solar
project ("the project"). The respondents ‘Repco’,
‘Solar’ and ‘Orange’ are subsidiaries under
Phelon Energy Group Limited and are all engaged in the project.
Orange is the company that leases the land on which the project is
situated. Orange contracted Repco as a principal contractor.
Repco in
turn sub-contracted LEP to work on the project in terms of a written
contract ("the subcontract
agreement
").
2.
THE FACTUAL MATRIX
[3]
The applicant commenced the work on the project site in July 2021 in
terms of the
subcontract. On 15 September 2022, Repco terminated the
subcontract agreement it had with LEP and thereafter, denied LEP and
its
employees access to the project site. Repco made allegations of
conduct by LEP that Repco regarded as amounting to a repudiation
of
the subcontract agreement
.
Repco claimed inter alia:
-
that LEP failed to complete the works by 27 August as per the
subcontract agreement, which caused severe financial losses on the
project to the detriment of Repco;
-LEP
submitted claims belatedly and incorrectly which claims are denied by
Repco;
-LEP
repeatedly failed to furnish an accelerated plan with the latest
request contained in Repco’s correspondence to LEP dated
12
September 2022;
-No
proper inventory and system of stock recording all equipment
delivered to the project site as well as its use on site was kept,
a
responsibility that fell squarely on LEP.
[4]
LEP refuted Repco's claim that the applicant’s actions
amounted
to a repudiation of the subcontract
agreement
.
LEP brought a spoliation application on an urgent basis seeking an
order
that
the
respondents
be ordered to restore access or possession of the project site to
LEP. The application was struck off the roll on 11
October 2022 for
lack of urgency. Pursuant thereto, the matter was enrolled on the
semi-urgent roll on 09 February 2023.
[5]
Meanwhile, LEP launched a second application on 02 November 2022
under case number 18461/2022 ("the second application").
The second application was brought for similar relief but confined
itself to the site establishment, housing its containers and
the
movables located on-site rather than the entire project site. The
court considered the second application and an order was
granted on
25 November 2022, however, the issue of costs stood over for
determination till
09
February 2022.
3.
ISSUES FOR DETERMINATION
[6]
This court is enjoined to determine the following disputed issues:
[6.1]
Whether LEP had possession of the project site when the respondents
denied LEP access to the project site. If LEP had such
possession was
the respondents' conduct unlawful?
[6.2]
Whether LEP had a lien over the project site?
4.
SUBMISSIONS BY THE PARTIES
[7]
LEP contends that on 29 July 2021, a notice to proceed with
the
work
on
the project site was issued by Repco's representative Louise Phelan
and signed by Hendrick Jacobus Engela on behalf of LEP. LEP
avers
that subsequent thereto, LEP established itself on the project site.
According to LEP, their site establishment was extremely
substantial
and comprised of 9 (nine) office structures, a board room, ablution
facilities, electrical power supply and 75KVA generator
machinery, as
well as 2432 complement of tools with fencing to secure the site
establishment.
[8]
It
was
further submitted that the project site is secured by numerous gates
controlled and patrolled by Repco and Solar’s security
representatives
.
Mr Ellis
who
appeared for the applicant further asserted that to gain access to
the project site,
two
security checkpoints must be passed.
Mr
Ellis contended that
subject to certain legislated health and safety requirements, the
applicant and its employees and contractors
have
always enjoyed free and unfettered access to and from the project
site.
[9]
It
was further
contended
that Repco is indebted to LEP in an amount of R84,073,000.00 for work
performed of which a portion thereof the respondents
dispute, and
payment thereof is still outstanding. Mr Ellis argued that LEP has a
lien over the project site, therefore has security
for the claims.
Counsel further contended that on 16 September 2022, the respondents
barred LEP from the project site after a purported
cancellation of
the contract on 15 September 2022, which LEP disputes.
[10]
In LEP’s heads of argument, counsel advanced an argument to the
effect that, the respondents
do not dispute that they barred LEP from
the Project site and (at least initially) its property, plant and
equipment on site without
recourse to legal process and consent. In
amplification of this argument, it
was
further
contended that the respondents’ opposition is grounded on the
dispute that LEP had possession of the site and its
associated
structures and equipment on the project site.
[11]
According to LEP, the respondents untruthfully contended that its
actions were done based on
the contractual regime which excluded any
form of possession by LEP, and that access was within the
respondents’ absolute
discretion. This, LEP argued, is in
contrast with clause 10.5 of the subcontract agreement which
expressly stipulates that:
“
save
for reasons beyond Repco’s reasonable control, Repco must
provide to the subcontractor (LEP) all rights of access to
and
possession of the project site on or before the Commencement date.”
[12]
It is on the basis of clause 10.5 that LEP contends that it is
abundantly clear that there existed
the sameness of minds from the
inception of the subcontract agreement, that LEP would have access to
and possession of the Project
site, albeit not exclusive.
[
13]
Meanwhile,
the
respondents in their answering affidavit assert that Repco and Solar
were at all times in joint and exclusive possession and
control of
the project site. The respondents aver that LEP and other
subcontractors were always subject to being granted access
to the
site which at all times remained at the absolute discretion of Orange
and its security services, as instructed by Repco.
Repco, it is
contended, is the main contractor whose function is to project manage
the entire construction to ensure that various
subcontractors
cooperate properly, to achieve a harmonious execution of the
construction and commissioning of the plant.
[14]
According to the respondents, numerous other subcontractors are
involved on the project site,
in the circumstances, only Repco and
Orange have possession of the Project Site. Thus, the applicant and
all other subcontractors
have the same level and type of access to
the site. It is further averred that LEP had no keys to the project
site in its possession
and access thereto was at the discretion of
Repco.
[15]
To justify the conduct displayed by the respondents on 15 and 16
September 2022, they rely on
innumerable subcontract agreement
clauses. For the sake of brevity, paragraph 47 of their answering
affidavit
states
:
“
If
the applicant failed to submit notices required under clauses 5.1 to
5.4 within the times required, or fails to comply with any
other
notice required, under the subcontract regarding the event (including
Force Majeure Event, the notice under clause 5.4) then:
47.5.1
the applicant has no entitlement to an extension of time; and
47.5.2
the applicant must comply with the requirements to perform the Works
by the Time of Completion. [clause 5.8]
47.6
Repco may terminate the contract immediately, without prejudice to
any other rights or remedies that it may have, if (inter
alia):
47.6.1
The applicant abandons the subcontract works, or repudiates the
subcontract [clause 8, and 8.1.4];
47.6.2
The applicant substantially or repeatedly materially breaches any
obligations assumed under the subcontract [clause 8, 8
.1.10].
47.7
Upon termination of the subcontract under clause 8 .1, Repco may, if
the applicant is on the site, expel the applicant and
Repco may
complete the subcontract works with itself or by engaging any third
party [clause 8.8.1]
47.8
The subcontract contains general clauses relating to the ‘whole
agreement, no representations no variations’, and
no ‘no
extension of time or indulgences ‘, ‘no waiver ‘[clause
28]”
[16]
Based on the aforementioned clauses, the respondents submit that the
applicant failed to establish
the necessary possession requirement
and accordingly, the application should fail.
5.
APPLICABLE LEGAL PRINCIPLES AND DISCUSSION
5.1
Was the Applicant unlawfully dispossessed?
[17]
It is well established in our law that the
mandament van
spolie
remedy is designed to prevent recourse to self-help. It
seeks to prevent people from taking the law into their own hands. The
requirements
are that the dispossessed person had possession of a
kind which warrants the protection accorded by the remedy and that he
was
unlawfully dispossessed. Essentially, all that must be proved is
the fact of prior possession and that the possessor was deprived
unlawfully. Unlawfully here means without agreement or recourse to
law.
[18]
For the applicant to be successful in the bid for a spoliation
relief, there ought to have been a
disturbance of possession without
consent and against the will of the applicant.
Bischoff
and Others v Welbeplan Broedery (Pty)Ltd
2021 (5) SA 54
(SCA);
Ivanov v North
West Gambling Board and Others
2012
(6) SA 67
(SCA) paragraph [19];
Blendrite
(Pty) Ltd and Another v Moonisami and Another
2021 (5) SA 61
(SCA) para 6.
[19]
In
Impala Water Users Association v Erasmus Lourens NO and 20
Others
2004 JDR 0235 (SCA), the court stated:
"I
am accordingly of the view that the court a quo correctly held that
rights capable of protection by spoliation proceedings
had been
interfered with in the present case.
It is accordingly necessary
to consider whether such interference is to be regarded as lawful so
that no spoliation can be held
to have taken place. In this regard,
the first question to be discussed is whether, as the court a quo
found, the onus rested on
the appellant to show that its actions were
covered by the provisions of section 59(3). In the George
Municipality case, supra
(at 271E), Milne
JA expressly approved a
statement by Friedman J in the court of first instance in that case
which read as follows: 'It is a fundamental
principle in our law that
a person may not take the law into his own hands and a statute should
be so interpreted that it interferes
as little as possible with this
principle.' Applying this principle, I agree with the judge a quo
that section 59(3) can only be
invoked when the water use charge the
non-payment of which triggers the power to restrict the supply of
water to the user is legally
payable. Indeed, I did not understand
counsel for the appellant to dispute this proposition." (my own
underlining).
[20]
In
the present matter, it is common cause
that
Repco locked LEP and its employees out of the project site,
subsequent to Repco's transmission of a letter cancelling the
subcontract agreement and LEP’s receipt thereof. In the letter,
Repco states
inter
alia
:
-
That applicant failed to complete the works by 27 August 2022 as per
agreement.
-
Applicant belatedly and incorrectly submitted claims for an extension
of time.
-
Applicant’s failure to complete the works as per agreement is
causing severe losses on the project.
-
The applicant failed to provide any acceleration plan despite several
requests from the respondents.
[21]
The case of
ATM
Solutions (Pty) Ltd v Olkru Handelaars CC and Another
2009 (4) SA 337
(SCA), in my view, is apposite in this matter. In
that matter, ATM Solutions installed an ATM in Olkru’s
convenience store,
Kwikspar. Olkru disconnected ATM Solution’s
machine and replaced it with ABSA’s ATM. ATM Solutions brought
an urgent
application for spoliatory relief against both Olkru and
ABSA. The claim against ABSA was brought on the basis that it was a
co-spoliator,
having facilitated the immediate replacement of ATM
Solutions’ ATM in Kwikspar with its own. The High Court refused
the application
for a spoliation order on the basis that ATM
Solutions had nothing more than a contractual right to have its
machine in place at
Kwikspar, and that the
mandament
is not the appropriate remedy for the enforcement of contractual
rights.
On
appeal, it was held that the relief sought by ATM Solutions which was
restoring and reconnection of its ATM machine in Kwikspar
premises
amounted to no more than an order for specific performance of the
contract. The SCA dismissed the appeal with costs. See
also
Eskom
Holdings
SOC LTD v Masinda
2019
(5) SA 386
(SCA).
[22]
Reverting to the facts of the present case, while the respondents
claim that LEP had no possession
of the project site, clause 10.5 of
the subcontract agreement unequivocally conferred possession of the
project site to LEP to
enable the performance of the works. Based on
clause 10.5 Repco granted LEP possession of a specific portion of the
project site,
enabling LEP to perform work based on the subcontract
agreement. Thus, it is not permissible that Repco, Solar and Orange
selectively
rely on certain and not on all clauses of the subcontract
agreement. This is evenly pertinent to LEP, as the entire subcontract
agreement is binding to both parties. Equally perceptible from
the subcontract agreement, categorically in clause 8.1, Repco
is
entitled to immediately terminate the subcontract agreement due to
default on the part of the subcontractor.
[23]
Most significantly, it was set out prominently in the letter of 15
September 2022, that LEP’s
conduct constitutes a repudiation of
the subcontract agreement. It was further stated that such
repudiation was being accepted
by the respondents and alternatively
to the extent necessary, Repco was terminating the subcontract
agreement in terms of clause
8.1 of the subcontract
agreement
.
Pursuant to the 15 September 2022 letter, around 8 am on 16 September
2022, Repco denied LEP access to the Project site. At the
hearing of
this application, the parties were
ad
idem
that
the applicant’s response to the termination letter was sent to
the respondents after 10 am on 16 September 2022. The
16 September
2022 letter written by LEP to Repco, disputed that LEP has repudiated
the subcontract agreement.
[24]
It
must be noted that at the time LEP’s possession and access to
the project site were denied by Repco, Repco was unaware
of LEP’s
stance with regard to the repudiation or termination of the
subcontract agreement. However, the view I take is that
in denying
LEP access to the project site, Repco was acting in accordance with
the terms of the subcontract agreement.
[25]
Mr Ellis on behalf of LEP advanced an argument to the effect
that, even though clause 8.1 permits Repco to expel
LEP, Repco was
not entitled to carry out the expulsion unlawfully. The argument went
on to say; the right may be there but the
due process had to be
followed. Mr Ellis further contended that consent by LEP is not
pleaded by Repco and thus cannot be relied
upon. As already indicated
in the
preceding
paragraph, Repco in their answering affidavit relied on clause 8.1 of
the subcontract agreement
,
and the contents of the 15 September 2022 letter referred to by LEP
in their founding papers
.
In my considered view, Repco’s reliance
on the terms of the subcontract is a clear demonstration that Repco
followed due process. In my mind, LEP's argument is untenable,
as
both parties are bound by the terms of the subcontract agreement,
hence when LEP signed the subcontract they consented to expulsion
from the project site (in the circumstances described in the letter
of 15 September 2022
).
From all the evidential material placed before court, it is
consistently contended that the applicant failed to adhere to the
material terms of the subcontract agreement and the respondent
decided to terminate the agreement in terms of clause 8.1
[26]
Most
importantly,
the parties agreed that: LEP will be conferred possession of the
project site, albeit not exclusive possession; upon the termination
of the contract the first respondent may expel LEP from the Project
Site. At the hearing of the matter, counsel for LEP when granted
an
opportunity to address the court on clause 8.1 of the subcontract
agreement
which
is annexure ‘FA4’ to the applicant’s founding
affidavit, argued that the clause is irrelevant to the matter.
[
27] In my view, the significance of clause 8.1 of
the subcontract agreement is that it deals with the termination
of
the subcontract agreement and empowers Repco to expel LEP from the
project site, which is what Repco has done leading LEP to
bring this
application. Not only is it relevant, in my view it
is
dispositive
to
the matter. More so, Repco disputes that the applicant had exclusive
possession of the Project site and this contention finds
support in
clause 10.5.3 of the subcontract agreement, dealing with access and
possession of the project site.
[28]
In
De Beer v Zimbali Estate Management
Association (Pty) Ltd and Anothe
r
2007 (3) SA 254(N)
para 54 to 55, considered the type of possession
protected by
mandament van spolie
and found that possession must be exclusive in the sense of being to
the exclusion of others. For applicant to exercise physical
control
of the premises, applicant must have the only key to the premises.
[29]
In this matter, it remains uncontroverted that more than 10 (ten)
subcontractors enjoyed a similar
kind of possession of the project
site at the relevant period, as they had to bring material, tools and
equipment on site for purposes
of performing their contractual
obligations and leave these items on site for the duration of the
work. Ostensibly LEP possessed
no keys at the time, enabling
voluntary access to the project site, save for keys to its own
containers with the material, tools
and equipment, access to the
project site was provided by Repco’s security personnel.
[30]
Notwithstanding the dispossession and denying LEP of access to the
project site, it is clear
that Repco acted on the strength of an
undisputed cancellation of the sub-contract agreement. The argument
by counsel for LEP,
that cancellation of a contract does not take
away possession from LEP, is opportunistic in that the parties have
agreed that where
the subcontract has been terminated, the
contractor, (in this case, Repco) may expel the subcontractor(LEP)
from the project site.
An intended consequence is that, with the
termination of the contract, Repco exercising the discretion
conferred by the subcontract
agreement
expelled
LEP from the project site, thus LEP’s possession of the site
has ceased for it was a right based on the subcontract.
From the
foregoing, it is plain that Repco acted within the ambit of the
subcontract agreement and its conduct was informed and
guided by the
written subcontract agreement. Thus the dispossession was lawful and
LEP is not entitled to the remedy sought.
[31]
Furthermore, in considering the applicable legal framework, it is
abundantly clear that LEP sought
to restore possession of the project
site, a right based on a contract. Evidently, LEP was conferred
possession of the project
site in terms of the contract, albeit not
exclusive, as there were other subcontractors involved in the project
site. Similarly
evident, is that such possession is a purely
contractual right and therefore not protected by
mandament van
spolie
. The respondents conduct in denying LEP access and
possession of the project site was lawful, as LEP had consented
thereto when
the parties concluded the subcontract.
Mandement van
spolie
does not protect contractual rights and cannot be used to
enforce specific performance of a contract.
5.2
Did LEP have a lien over the project
site?
[32]
LEP in the founding affidavit also asserted that they were exercising
a lien over the project
site for works done but not paid at the time
of the expulsion from the project site. While in their replying
affidavit, it was
asserted that LEP was exercising a lien over the
project site for works completed but not paid for at the time the
spoliation took
place and was completely caught off guard by the
respondents' forcible and wrongful conduct, in an attempt to defeat
its lien.
LEP relied on
Wightman t/a JW Construction v
Headfour (Pty) Ltd and Another
2007 (2) SA 128
(C) at 145 B:
"
It
appears settled law that a temporary absence such as occurs at the
end of a working day or over a weekend does not interrupt
a builder's
lien where the builder or contractor remains engaged in the work and
continues to assert his occupation of the site."
I
must also stress the fact that this High Court decision was reversed
by the Supreme Court of Appeal in
Wightman t/a JW Construction v
Headfour (Pty) Ltd and Another
[2008] ZASCA 6
;
2008 (3) SA 371.
[33]
The first respondent opposes the relief of a
lien and contends that the requirements of the creation
of a lien:
Money or labour must have been expended by one person on a thing
belonging to another; A lien is only created and retained
as long as
the
retentor
remains in possession of the thing;
Possessio
civilis
is
not required, but only physical control over the thing to hold it as
security. Mr Kuschke for the respondents, further argued
that LEP has
never held the site as security for its claim for payment. On this
point, Repco relied on the case of
Investec
Bank v The Master of the High Court and Others WCHC Case number
2668/2012
(unreported
judgment )10 April 2012 at [3]. In this
matter
Binns - Ward J
held
the following:
"The
sufficiency of physical control required in a given case falls to be
determined objectively the determinant criteria being
effectiveness
against adverseness to, the rights of the owner, who continues to
live in the building while maintenance is effected
to it, that the
repairer of a house would normally be regarded as acquiring
possessory lien over the house' (Cape Tex Engineering
Works at 532
fin, citing United Building Society v Smmokler's Trustees,
1906 T.S
623
at 627; Beetge v Drenka Investments( Isando ))Pty)Ltd 1964 (4)
SA62(W)at 68 to 69, and Lee and Honore, South African Law of
Property, p 44).
”
[34]
LEP was expelled from the project site. As such,
LEP no longer has any possession of the site as a result
of lawful
dispossession, thus it could not rely on a lien hypothec. For all the
reasons set out above, it follows that the application
must be
dismissed.
6.
THE ORDER
[35]
The following order is accordingly
granted:
[35.1]
The application is dismissed with costs.
[35.2]
The costs include the costs of the first and second applications and
the costs of two counsels.
RALARALA NE
ACTING JUDGE OF THE
HIGH COURT
WESTERN CAPE DIVISION
Counsel
for the Applicant:
Adv P
ELLIS SC
Adv
E MALHERBE
Instructed
by
MORNE
COETZEE ATTORNEYS
Counsel
for Respondents
Adv L
KUSCHKE SC
Adv
M VAN STADEN
Instructed
by
ANDERSEN
ATTORNEYS
sino noindex
make_database footer start
Similar Cases
Engineering Industries Pension Fund and Another v Pioneer Mechanical CC and Another (13568/2020) [2022] ZAWCHC 215 (3 June 2022)
[2022] ZAWCHC 215High Court of South Africa (Western Cape Division)99% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (Leave to Appeal) (17470/2014) [2025] ZAWCHC 453 (3 October 2025)
[2025] ZAWCHC 453High Court of South Africa (Western Cape Division)99% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2025] ZAWCHC 292 (14 July 2025)
[2025] ZAWCHC 292High Court of South Africa (Western Cape Division)99% similar
South African Legal Practice Council and Another v Nonxuba and Others (10313/2021) [2022] ZAWCHC 105 (18 April 2022)
[2022] ZAWCHC 105High Court of South Africa (Western Cape Division)99% similar
South African Legal Practice Council v Engelbrecht (23138/2023) [2025] ZAWCHC 468 (10 October 2025)
[2025] ZAWCHC 468High Court of South Africa (Western Cape Division)99% similar