Case Law[2023] ZAWCHC 161South Africa
Umlazi Civils Pty Ltd v Concor Construction t/a Conradie Development and Another (20967/2021) [2023] ZAWCHC 161 (10 July 2023)
High Court of South Africa (Western Cape Division)
10 July 2023
Headnotes
SUMMARY OF PAYMENTS TO DATE
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2023
>>
[2023] ZAWCHC 161
|
Noteup
|
LawCite
sino index
## Umlazi Civils Pty Ltd v Concor Construction t/a Conradie Development and Another (20967/2021) [2023] ZAWCHC 161 (10 July 2023)
Umlazi Civils Pty Ltd v Concor Construction t/a Conradie Development and Another (20967/2021) [2023] ZAWCHC 161 (10 July 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2023_161.html
sino date 10 July 2023
FLYNOTE:
CONTRACT
– Building contract –
Interim
payment certificate
–
Disputes
submitted to arbitration still in progress – Applicant seeking
payment based on certificate – Contention that
certificate
binding admission of indebtedness – Provisions of contract not
giving certificate the character of something
that vests an absolute
or temporarily final right to payment of the amount certified thereby
if there is a dispute – Applicant
cannot obtain enforcement
until the arbitrator has made his award.
Republic
of South Africa
IN
THE HIGH COURT OF SOUTH AFRICA
WESTERN
CAPE DIVISION, CAPE TOWN
Case
no. 20967/2021
Before:
The Hon. Mr Justice Binns-Ward
Hearing:
7 June 2023
Judgment:
10 July 2023
In
the matter between:
UMLAZI
CIVILS (PTY) LTD
Applicant
and
CONCOR
CONSTRUCTION (PTY) LTD
t/a
CONRADIE DEVELOPMENT
First
Respondent
BVI
CONSULTING ENGINEERS
WESTERN
CAPE (PTY) LTD t/a BVI
Second
Respondent
JUDGMENT
Delivered
by email and listing on SAFLII
BINNS-WARD
J:
[1]
In
its notice of motion, the applicant seeks an order against the first
respondent for payment of the sum of R6 725 255.71,
together with interest thereon
a
tempore morae
.
The claim is founded on an interim payment certificate issued in
favour of the applicant, qua ‘Contractor’,
by the second
respondent in terms of a standard form building contract, Conditions
of Contract for Construction for Building and
Engineering Works
Designed by the Employer (1999 edition, as amended) (commonly known
as ‘FIDIC’
[1]
),
to which the applicant and the first respondent are party.
[2]
The second respondent is the ‘Engineer’ appointed by the
first respondent, qua ‘Employer’, for the
purposes of the
contract. The Engineer is responsible in terms of the contract
for issuing interim payment certificates during
the execution of the
construction work, which the Employer, subject to the provisions of
the contract, is bound to honour.
[2]
The
pertinent provisions of the contract appear to be the following:
1.
Clause
3.1, s.v. ‘
Engineer’s Duties
and Authority
’
: ‘
Except
as otherwise stated in these Conditions:
(a)
...
(b)
...
(c)
any
approval ... certificate ...or similar act by the Engineer ... shall
not relieve the Contractor from any responsibility he has
incurred
under the Contract, including responsibility for errors, omissions,
discrepancies and non-compliances.
’
2.
Clause
3.3, in which the parties inserted the following: ‘
In
addition to the actions stipulated in the General Conditions whereby
the Engineer shall first obtain the approval of the Employer,
the
Employer’s approval shall also be obtained before taking any
action under sub-clauses 8.4, 11.9, 13.3, and 20.1 as amended
in
these Particular Conditions.
’
3.
Clause
13.3, s.v. ‘
Variation Procedures
’
,
in which the parties inserted the following: ‘
Each
instruction to execute a Variation, unless the Variation is to be
executed on a Daywork basis, shall be a written instruction
presented
in the form of a Variation Order. The Variation Order shall be
presented to the Employer, who shall signify his approval
before the
order is signed by the Engineer and issued to the Contractor, who
shall acknowledge his acceptance by signing the order.
The Contractor
shall not accept a Variation Order that is not approved and signed by
the Employer
.’
4.
Clause
14.3, s.v. ‘
Application for
Interim Payment Certificates
’
,
which provides that the Contractor shall submit a statement to the
Engineer after the end of each month during the execution of
the
contract setting out, with supporting documentation, the estimated
contract value of the works executed up to the month-end
in question
and reflecting the deduction of amounts certified in all the
preceding payment certificates.
5.
Clause
14.6, s.v. ‘
Issue of Interim
Payment Certificates
’
, which
provides, in its amended form, that the Engineer shall within 14 days
after receiving a statement and supporting documents
in terms of
clause 14.3 from the Contractor issue to the Employer an interim
payment certificate which shall state, with supporting
particulars,
the amount which the Engineer fairly considers to be due.
Insofar as applicable on the relevant facts, clause
14.6 further
provides that an interim payment certificate shall not be withheld,
although ‘
if any thing supplied or
work done by the Contractor is not in accordance with the Contract,
the cost of rectification or replacement
may be withheld until
rectification or replacement has been effected
’
,
or if the Contractor has not carried out any work directed by the
Engineer, the value of such work may be withheld until the work
has
been performed. The subclause also provides that ‘[t]
he
Engineer may in any Payment Certificate make any correction or
modification that should properly be made to any previous Payment
Certificate. A Payment Certificate shall not be deemed to
indicate the Engineer’s acceptance, approval, consent or
satisfaction
’
.
6.
Clause
14.7, as amended, provides s.v. ‘
Payment
’
that
‘[t]
he Employer shall pay to the
Contractor:
(a)
...
(b)
the
amount certified in each Interim Payment Certificate within 35 days
after the Engineer receives the Statement and supporting
documents;
and
(c)
...
.
’
7.
Clause
20.1, s.v. ‘
Contractor’s
Claims
’
, provides for the means
whereby the Contractor is required to pursue any claims it might have
for extensions of time and additional
payments under any of the
provisions of the contract. It provides that payment
certificates will include provision for any
such amounts ‘
as
have been reasonably substantiated as due under the relevant
provision of the Contract
’
.
The parties inserted a provision into the standard form clause as
follows: ‘
If an extension of
time is granted the Contractor shall be paid such time-related
Preliminary and General allowances as are appropriate
having regard
to any other compensation which may already have been granted in
respect of the circumstances concerned. Payment
of costs
additional to the above will only be considered if the costs derive
from claims that fall within the terms of Clause 13
(Variations and
Adjustments) and/or Sub-clause 17.3 (Employer’s Risks)
’
.
8.
Clause
20.2, s.v. ‘
Appointment of the
Dispute Adjudication Board
’
(‘DAB’),
which provides for disputes to be adjudicated by an adjudication
board in accordance with clause 20.4.
The standard terms
contemplated the appointment of a board consisting of either one or
three persons. A single adjudicator
was appointed in terms of
the agreement currently under consideration.
9.
Clause
20.4, s.v. ‘
Obtaining Dispute
Adjudication Board’s Decision
’
provides
for how a decision is to be obtained from the adjudicator(s).
It further provides that if either party is dissatisfied
with the
adjudicator’s determination, it may give notice thereof within
a stipulated period, whereupon the dispute may be
referred to
arbitration. Failing the giving of such notice of
dissatisfaction, the adjudicator’s decision becomes final
and
binding on both parties.
10.
Clause
20.6, s.v. ‘
Arbitration
’
provides
for the ‘final settlement’
[3]
(unless
otherwise agreed by the parties) of any unresolved dispute by
arbitration. It gives the arbitrator(s) ‘
full
power to open up, review and revise any certificate, determination,
instruction, opinion or valuation of the Engineer, and
any decision
of the DAB, relevant to the dispute
’
.
[3]
The
current proceedings concern the applicant’s claim for payment
in terms of (interim) payment certificate no.17, signed
by the
Engineer on 2 November 2021, which purports to be ‘[f]
or
the Period 26/10/2021 to 26.10.2021
’
.
The payment part of the certificate provided as follows:
SUMMARY
OF PAYMENTS TO DATE
DETAILS
OF PAYMENT
General
& Roadworks
Structures
TOTAL
From
page
Total
From
page
Total
Total
of Scheduled Work done to date
P3
46
859 347.12
P3
0
46
859 347.12
Total
of Variations to date
P4
3
267 485.64
P4
2
379 108.03
5
646 593.67
SUBTOTAL
50
126 832.76
2
379 108.03
52
505 940.79
Deduct
Total of Reduced Payment to date
P5
0
P5
0
0
Add
Total Adjustment in Value of Special Materials
P6
0
0
TOTAL
VALUE OF WORK DONE TO DATE
50
126 832.76
2
379 108.03
52
505 940.79
Add
80% of Materials on Site
P7
0
P7
0
0
SUBTOTAL
50
126 832.76
2
379 108.03
52
505 940.79
Deduct
retention of 0% of Total Value of Work to Date (Unlimited)
0
Penalties
Reversed to ZERO days as per Adjudication Ruling 26.10.2021
0
TOTAL
AMOUNT DUE TO DATE
52
505 940.79
Deduct
total of previous payments (excluding VAT)
(46
695 355.87)
NET
AMOUNT DUE FOR PAYMENT IN THIS CERTIFICATE (EXCLUDING VAT)
5
810 584.92
ADD
15% VAT
871
587.74
AMOUNT
NOW DUE (INCLUDING VAT) excluding interest in Penalties
6
682 172.66
Interest
on Penalties Levied as per Calculation supplied
43
083.05
AMOUNT
NOW DUE FOR PAYMENT (INCLUDING VAT & NO VAT on interest
6
725 255.71
The
certificate document makes provision on its face for signature by the
Engineer (or the ‘Engineer’s Representative’),
the
‘Contractor’s Representative’ and the Employer.
The copy of the certificate attached to the founding
papers bears
what purport to be the signatures of the Engineer and the
Contractor’s Representative. There is no indication
that
it was signed by or on behalf of the Employer.
[4]
It
is evident from the certificate and the applicant’s invoice
submitted to the second respondent under cover of a letter
by the
applicant’s attorney, dated 27 October 2021, (annexures UC 6
and UC 7, respectively, to the founding affidavit) that
it is related
to an ‘Adjudication Ruling’ of 26 October 2021.
The uncontested evidence is to the effect
that the adjudication
concerned six claims by the applicant for extensions of time and
associated additional costs. Five
of those claims were advanced
individually and the sixth, brought in the alternative to the
forementioned, was a global claim incorporating
the five individual
claims as a single claim predicated on the Engineer’s alleged
previously given approval of those claims.
The applicant
alleged that the Engineer’s approval of its claims had been
implicit in its approval of a revised timetable
for the execution and
completion of the contract works in terms of what the parties
referred to as ‘the REV 3 Combined Programme’.
[5]
The
adjudicator ruled in the applicant’s favour on the global
claim, and consequently found it unnecessary to pronounce on
the five
individually advanced claims. It is apparent from the
adjudicator’s ruling that he had not investigated the
merits of
the individual claims that had informed the global one. The
basis for the determination was set out in the adjudicator’s
‘Summary of Ruling’. In relevant parts (I have
altered the order of the paragraphs to improve the coherence of
the
summary for present purposes), it went as follows:
‘
Admissible
delays beyond the control of the Contractor:
On
the balance of probabilities in respect of the different
interpretations as well as documentary evidence submitted, I accept
the viewpoint that the REV3 combined programme should form the basis
of the determination of “extra over time” allowed
as a
result of the various delays in the five separate, sometimes
concurrent claims being disputed. Taking into account the “often
dichotomous” submissions made to me by the parties concerned
the Contractor is entitled to compensation for time delays to
the
extent of 135 calendar days, minus 20 calendar days already awarded
for claim number 1 which is not the subject of this
Dispute,
that is a total of 115 calendar days compensation.
The
REV3 Combined Programme
The
REV3 combined programme is valid and forms the basis of the
determination of overall admissible time delays beyond the control
of
the Contractor and also the Date of Completion of the Contract.
Time
for ‘Completion’ Date
In
line with the views of both parties the Date of Completion of the
Contract is accepted as 25th February 2021. Should the Contractor
failed to comply with this Date for the Time for Completion date the
Contractor shall pay delay damages to the Employer to the
extent
specified in the contract documents. However should delay damages
(penalties) have already been imposed on the Contractor
for any other
Date for the Time of Completion date, these penalties should be
reversed together with interest as prescribed below.
Mandate
Despite
the suggestion by the Employer that I should do so, I do not consider
it necessary to “open up and correctly determine”
the
validity of the claims forming this Dispute, since the Engineer on
behalf of the Employer has already ruled that the claims
are valid,
and only the quantum of the relief sought is in the subject of the
notice of Disputes.
Monetary
award
In
respect of the cumulative total of “time delays” for all
the claims forming the subject of this Dispute the Contractor
is
entitled to compensation in the extent of R33 661.06 per day, a
total of R3 871 021.90 (Excluding VAT). In addition
he is
entitled to compensation in the extent of R374 563 (Excluding
VAT) In respect of additional costs for the Covid-19 claim.’
[6]
The
adjudicator’s ruling is dated 25 October 2021. I infer
that the aforementioned date of 26 October 2021 must have
been the
date on which the ruling was delivered to the parties.
[7]
The
first respondent was dissatisfied with the adjudicator’s
ruling. Within the period stipulated in the contract, it
gave
notice of its dissatisfaction and required the disputes to be
referred to arbitration.
[4]
The applicant advanced the same claims at the arbitration, save that
what had been its sixth, or global, claim in the adjudication
proceedings was now cast as its principal claim, with the five
aforementioned individually advanced claims being advanced in the
alternative thereto.
[8]
The
arbitration hearing commenced in January 2023, and the proceedings
were still in progress when the current application was argued.
The arbitration hearing on 25-26 January 2023 was concerned only with
what was described by the first respondent in its supplementary
answering affidavit as ‘certain points
in
limine
’
but characterised by
the arbitrator as ‘interlocutory proceedings’. Of
relevance to the current matter, however,
is the fact that at that
hearing the applicant abandoned what had been its sixth claim before
the adjudicator.
[9]
The
abandonment gave rise to the making of an interim award by the
arbitrator on 26 January 2023. The award, insofar
as
relevant to the current matter, directed the applicant (i.e. the
respondent in the arbitration) to pay the costs of ‘the
interlocutory proceedings’ on 25-26 January 2023 and the costs
incurred up to that date ‘
incurred
in the arbitration insofar as
they
relate to (the withdrawal of) counterclaim 1
’
.
(‘Counterclaim 1’ being what had been the applicant’s
sixth claim in the adjudication proceedings.)
The arbitrator
also set aside the costs order made by the adjudicator and reserved
the issue of costs undetermined in the interim
award for
determination at the end of the arbitration proceedings. As the
applicant’s counsel stressed, however, the
arbitrator
acknowledged in the written reasons given for the interim award that
the applicant’s abandonment of its first
counterclaim in the
arbitration did not exclude the possibility that the applicant ‘
may
be successful in terms of the remainder of the counterclaims
[i.e.
those which had been claims 1 to 5 before the adjudicator]
which
may justify the award made by the adjudicator, but on a different
basis
’
.
[10]
The
first respondent has pointed out in its supplementary answering
affidavit that the set aside adjudicator’s award makes
up
R3 871 021.90 of the
amount certified in the interim payment certificate that the
applicant seeks to enforce in the current
proceedings.
Moreover, according to the first respondent’s uncontroverted
evidence, an amount of R105 000.00 of
the certified amount
comprised the sum of the adjudicator’s fees and those of the
adjudicator nominating body that formed
part of the costs award made
by the adjudicator. (The said sum of R105 000.00 was the
subject of Variation Order 27
and included in payment certificate 17
under that description.) The first respondent contends that it
must follow, in the
context of the interim award made by the
arbitrator, that the applicant ‘
is
not entitled to payment of the amount of R3 976 021.90,
forming part of payment certificate 17
’
.
[11]
In
its supplementary answering affidavit, the first respondent also
detailed the reasons for its contention that it was not liable
to the
applicant in respect of Variation Orders 13, 19 and 20, which had
also been included in payment certificate 17. It
contended that
these variation orders had been non-compliant with the provision of
the building contract that prescribed that instructions
to execute a
variation required presentation to the Employer for its signified
approval before being signed by the Engineer and
presented to the
Contractor. The first respondent maintains that the variation
orders were not approved by it.
[12]
With
reference to the interim award by the arbitrator and the allegedly
misdirected inclusion of the aforementioned variation orders
in the
amount certified for payment in certificate no. 17, the first
respondent contended that the Engineer was authorised by the
building
contract (see the summary of clause 14.6 of the agreement in
paragraph [2]
above) ‘
to
revise payment certificate 17 and consequently the Variation Orders
relating to the Applicant’s claims by correcting the
incorrectly certified amounts
’
.
It referred in this connection to a document identifying itself as
payment certificate 18 that it alleges was issued by
the Engineer to
the applicant on 5 May 2023.
[13]
A
copy of the payment certificate no. 18 and the voluminous
substantiating documentation that accompanied it was attached to
the
first respondent’s supplementary answering affidavit. The
certificate document makes provision for signature by
the Engineer on
5 May 2023, but, in contrast with the position with regard to
certificate 17 (see paragraph [3]
above),
appears not to have been signed by any of the parties at the places
provided.
[14]
The
first respondent describes that payment certificate 18 reversed
variation order 27 and revised variation orders 13, 19 and 20
to
reflect different amounts. It also explained that the revised
certificate reflected what it alleged was the applicant’s
liability for 73 days’ worth of delay damages due in terms of
clause 8.7 of the contract in the total sum of R1 460 000.00,
settlement of which, it had been advised in a letter from the
Engineer to the applicant, dated 18 March 2021, would be
effected
by way of a deduction to be reflected in the next payment
certificate. The nett effect of the aforementioned revisions
was
that payment certificate 18, which, according to its tenor,
purports to be ‘[f]
or the Period
26/10/21 to 25.02.2023
’
reflects
an amount due by the first respondent to the applicant in the sum of
R613 924.07.
[15]
The
first respondent admits liability to the applicant in the
aforementioned sum of R613 924.07 and tenders payment thereof.
[16]
In
its supplementary answering affidavit, the first respondent points
out that the amounts in payment certificate 17 that are in
dispute
stand to be determined in the pending arbitration proceedings.
A hearing on the substantive issues was scheduled
to take place
before the arbitrator at the end of May and the beginning of June
2023 and the court was advised by the first respondent’s
counsel that there was a possibility that the arbitrator might make a
final award before the delivery of judgment in this application.
The first respondent had suggested to the applicant in the
circumstances that the application should stand over or be
withdrawn.
The hearing proceeded before me on 7 June 2023
because the first respondent’s suggestion did not find favour
with the applicant.
[17]
The
first respondent, reiterating its tender to pay the amount of
R613 924.07 to the applicant, seeks the dismissal of the
application with costs on the scale as between attorney and client.
At the hearing, Mr
Mahon
,
who appeared for the first respondent together with Ms
Hammick
,
conceded, however, that he could not resist an order awarding the
applicant its costs (save for those already determined against
the
applicant when the application was previously struck from the roll by
Erasmus J for lack of urgency) incurred up to the date
of the
delivery of the first respondent’s supplementary answering
affidavit. The reasons for that concession will become
apparent
shortly.
[18]
It
will be apparent from what has been said thus far that the bases for
the first respondent’s opposition to the application
have been
described entirely with reference to its
supplementary
answering
affidavit. The affidavit was delivered on 26 May 2023. That
date needs to be contextualised. The application
had originally
been scheduled for hearing on the semi-urgent roll on 24 May 2022
pursuant to an order by the duty judge in the
unopposed motion court
on 23 February 2022. It duly came up before Erasmus J on
the opposed motion roll. After
hearing argument, Erasmus J made
an order on 25 May 2022 striking the application from the roll with
costs on the scale as between
attorney and client. The
registrar thereafter issued a notice of set down, dated 19 January
2023, fixing a hearing date for
17 August 2023. For reasons
that are not apparent on the record that notice of set down was
supplanted by a second notice,
dated 16 March 2023, fixing 7 June
2023 as the hearing date.
[19]
The
first respondent applied at the hearing on 7 June 2023 for the
admission of its supplementary answering affidavit. It
urged in
support of the application that the affidavit contained evidence that
was relevant to the determination of the principal
case that had not
been available when the answering papers were delivered. The
applicant opposed the admission of the supplementary
answering
affidavit. Mr
Sievers
SC,
the applicant’s counsel, pointed out that much of the evidence
contained in the supplementary affidavit had been available
to the
first respondent when its answering affidavit was deposed to.
It seems to me that the only evidence that was not available
when the
answering affidavit was made was that related to the arbitration
hearing in January 2023 and the subsequent issue of payment
certificate 18. Those were critical developments, however, and
it would be unrealistic, and contrary to the interests of
justice,
for the court to decide the application without reference to them.
[20]
It
is also evident, as candidly acknowledged in the first respondent’s
counsel’s heads of argument, that the first respondent
does not
persist in advancing the substantive grounds of opposition set out in
its answering affidavit and relies instead on those
argued on its
behalf based on the content of the supplementary answering
affidavit. Indeed, the concession by the first respondent’s
counsel concerning costs mentioned earlier was predicated, quite
realistically, on that acknowledgment. It also bears mention
that the first respondent jettisoned its originally filed heads of
argument (drafted by different counsel) and relied on substituted
heads that were delivered out of time, only two days before the
hearing.
[21]
The
court exercises a true discretion when it decides in opposed motion
proceedings whether to admit an affidavit outside the three
sets
provided for in Uniform Rule 6. As noted in what is probably
the leading authority in point,
James
Brown & Hamer (Pty) Ltd (Previously named Gilbert Hamer & Co
Ltd) v Simmons, NO
1963
(4) SA 656
(A),
‘[i]
t
is in the interests of the administration of justice that the
wellknown and well established general rules regarding the number
of
sets and proper sequence of affidavits in motion proceedings should
ordinarily be observed. That is not to say that those
general
rules must always be rigidly applied: some flexibility, controlled by
the presiding Judge exercising his discretion in
relation to the
facts of the case before him, must necessarily be permitted
’
.
[5]
To
similar effect, in
Bader
and Another v Weston and Another
1967
(1) SA 134
(C),
Corbett J remarked, ‘
While
I fully agree that litigants on motion ... should not be encouraged
to present their cases in a piecemeal fashion, at the
same time I
consider that the Court should not allow an adjudication of the real
issues in a case to be partially frustrated by
too rigid an adherence
to what is essentially a rule of practice.
’
[6]
It is the latter consideration that has weighed most heavily with me
in my decision that the supplementary answering affidavit
should be
admitted. I am satisfied that there is no attendant prejudice
to the applicant that could be addressed adequately
through an
appropriate order as to costs, and leave to reply to the additional
affidavit if such were sought.
[22]
As
it happened, the applicant did not seek an opportunity to reply if
the supplementary answering affidavit were admitted.
[23]
Mr
Sievers
argued
that an interim certificate constitutes a binding admission of
indebtedness by the employer, similar to an acknowledgement
of debt.
He submitted that, in the absence of a contractual provision to the
contrary, a payment certificate cannot be withdrawn
to correct
mistakes of fact, or a value in it. The applicant’s
counsel argued further that the certificate is not open
to attack
because it was based on erroneous reports or the agent’s
negligence. He contended that even if it were known
that the
certificate is not ‘entirely accurate’ in relation to
either the valuation reflected therein or the amount
due to the
contractor, it would still not be contrary to public policy to
enforce it. He asserted that where the employer
has suffered
damages through the negligent failure on the part of its agent to
draft the certificate correctly, its remedy lay
in an action for
damages against the agent, not in resisting liability to the
contractor by virtue of the erroneously framed certificate.
[24]
Mr
Sievers
advanced
the aforegoing arguments as if they were generally applicable
propositions of law. He called
Randcon
(Natal) (Pty) Ltd v Florida Twin Ests (Pty) Ltd
1973
(4) SA 181
(D)
(which he described as ‘the
locus
classicus
on
payment certificates’),
Ocean
Diners (Pty) Ltd v Golden Hill Construction CC
[1993]
ZASCA 41
(26
March
1993);
1993 (3) SA 331
(AD);
[1993]
2 All SA 260
(A)
and
Joob
Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture
[2009]
ZASCA 23
(27
March 2009);
[2009]
3 All SA 407
(SCA);
2009
(5) SA 1
(SCA)
in aid in support of them. Consideration of those authorities
shows that the cases were decided on their own facts
and with regard
to the contractual provisions that were individually peculiar to
them. Whether the judicial pronouncements
relied on by the
applicant’s counsel could apply in this case depends on the
correspondence between the pertinent provisions
of the contract in
the current matter and those involved in the other matters. One
must also be mindful of what was actually
in issue in those cases.
[25]
It
is evident that what might be understood to have been the intended
statement of a general proposition of law in
Randcon
that
an interim certificate under a building contract has to be treated as
absolute in effect because its rationale is to financially
sustain
the contractor’s or sub-contractor’s ability to continue
with and complete the work was predicated on the learned
judge’s
apprehension of the law as stated by Lord Denning MR in
Dawnays
Ltd v FG Minter Ltd and Another
[1971]
2 All ER 1389
(CA),
[1971]
1 WLR. 1205
.
(The same can be said of the points subsequently made by McEwan J
in
Smith
v Mouton
1977
(3) SA 9
(W)
in numbered paragraphs 2 and 4 at p.13.
[7]
[8]
)
[26]
In
Dawnays
,
which involved a claim by a sub-contractor against the main
contractor, Lord Denning rejected a contention by the contractor that
payment of the sub-contractor’s certified claim could be
resisted because it was the subject of a dispute that had been
referred to arbitration proceedings to be conducted after the final
completion or abandonment of the contract works. The Master
of
the Rolls rejected the argument, saying –
‘
That
seems to me to run counter to the very purpose of interim
certificates. Every businessman knows the reason why interim
certificates are issued and why they have to be honoured. It is
so that that the sub-contractor can have the money in hand
to get on
with his work and the further work he has to do. Take this very
case. The sub-contractor has had to expend
his money on steel
work and labour. He is out of pocket. He probably has an
overdraft at the bank. He cannot
go on unless he is paid for
what he does as he does it. An interim certificate is to be
regarded virtually as cash, like
a bill of exchange. It must be
honoured. Payment must not be withheld on account of
cross-claims, whether good or bad
- except so far as the contract
specifically provides. Otherwise any main contractor could
always get out of payment by making
all sorts of unfounded
cross-claims.’
The
position described by Lord Denning would give a quality of what has
been called ‘temporary finality’
[9]
to
interim payment certificates. They would, unless the contract
expressly provided otherwise, have to be honoured pro
tem, subject
only to a final settlement of accounts
at
the end of the contract
.
[27]
On
my reading of the judgment in
Randcon
,
the learned judge’s apparent approbation of Lord Denning’s
remarks was nothing more than a passing observation in
support of his
rejection of the argument by the defendant in that case that an
interim payment certificate was not a liquid document
for the purpose
of provisional sentence proceedings. The issues before the
judge did not require of him to consider whether
Lord Denning’s
pronouncement bore scrutiny as a general proposition concerning the
legal effect of interim payment certificates.
(The argument
being addressed by the judge in
Randcon
was
not of any relevance in the current matter because the first
respondent, unsurprisingly, did not contest the applicant’s
entitlement to base its cause of action on the certificate, and there
is at this stage no doubt about the correctness of the finding
in
Randcon
that
an architect or engineer’s certificate in terms of the standard
form building contracts will ordinarily be a liquid document
susceptible for use in provisional sentence actions or applications
for summary judgment. That much is now
well-established.
[10]
I am also anxious to make it clear that nothing in this judgment
should be understood to call into question the correctness
of the
court’s decision in
Randcon
,
based on the evidence in that case, to grant provisional sentence
against the defendant.)
[28]
One
year and a day after Van Heerden J handed down judgment in
Randcon
,
the House of Lords, in
Gilbert-Ash
(Northern) Ltd v Modern Engineering (Bristol) Ltd
1974
A.C. 689
,
unanimously disapproved of Lord Denning’s statement in
Dawnay
’
s
case. The learned law lords pointed out that it was
inconsistent with unimpeachable Court of Appeal authority reaching
back to
Robins
v Goddard
(1905)
1 K.B. 294 (CA).
[11]
[29]
The
question before the House in
Gilbert-Ash
was
described by Viscount Dilhorne as follows: ‘
...whether
when under a contract in the R.I.B.A. form an architect has given an
interim certificate the employer is bound to pay
to the contractor
the amount certified without deduction or set off save as permitted
by the contract; and where the architect
has told the contractor the
amount forming part of the total certified attributable to work
executed by a sub-contractor the contractor
is bound to pay that
amount to the sub-contractor without deduction save as permitted by
the sub-contract
’
.
Unsurprisingly, in my respectful opinion, the unanimous view of the
law lords was that the answer in every case would turn
on the
peculiar terms of the contract (or sub-contract) under
consideration. Our jurisprudence is to the same effect.
As McEwan J noted in
Smith
v Mouton
(W)
supra, ‘
...
there is no special law different from the law relating generally to
contracts and their interpretation that applies to building
contracts
and to architects’ certificates issued under them. In
each case the primary consideration ... is the proper
interpretation
of the particular contract before the Court
’
.
[12]
[30]
In
Robins
supra,
in the context of a building contract that provided - as in the
current case - for the determination of disputed questions
by
arbitration, the Court of Appeal rejected the notion that the
defendant was ‘
debarred by the
certificates from setting up bad workmanship on the building and the
introduction of improper materials
’
.
Sir Richard Collins MR said (at p.301), where the contract
provided, as does the one in issue here, that the arbitrator
could
open up, review and revise any certificate, ‘[i]
f
something which purports to be conclusive is made subject to
revision, it loses its quality of finality
.’
Referring to the contrary import of Lord Denning’s
remarks in
Dawnay
,
Viscount Dilhorne said in
Gilbert-Ash
(at
p. 705) ‘…
no
scintilla of authority prior to the decision in
Dawnays
’
case
can be found for the proposition that the amount certified by the
architect in an interim certificate as the value of work
done and
consequently payable to the contractor is in a special position in
that the employer cannot lawfully counterclaim and
set off against
the liability amounts due to him from the contractor
.’
[31]
As
to what might, for want of a better term, be called ‘the
default position’,
Hudson’s
Building Contracts
op. cit. supra,
appears to endorse the following passages in Lord Diplock’s
speech in
Gilbert-Ash
:
‘
It
is, of course, open to parties to a contract for sale of goods or for
work and labour or for both to exclude by express agreement
a remedy
for its breach which would otherwise arise by operation of law ...
[b]ut in construing such a contract
one
starts with the presumption that neither party intends to abandon any
remedies for its breach arising by operation of law, and
clear
express words must be used in order to rebut this presumption
.
In the case of building contracts no question of usage arises to
rebut the presumption ... .’
[13]
(Emphasis provided by the learned author of
Hudson’s
Building Contracts
.)
and
‘
So
when one is concerned with a building contract one starts with the
presumption that each party is to be entitled to all those
remedies
for its breach as would arise by operation of law, including the
remedy of setting up a breach of warranty in diminution
or extinction
of the price of material supplied or work executed under the
contract. To rebut that presumption one must be able
to find in the
contract
clear
unequivocal words
in
which the parties have expressed their agreement that this remedy
shall not be available in respect of breaches of that particular
contract.’
[14]
[15]
(Emphasis provided by the learned author of
Hudson’s
Building Contracts
.)
The
learned author commented (in 1995) ‘
...
there is now and unmistakeable and justifiable trend in more recent
English judicial decisions against according binding force
even to a
final certificate, in the absence of the most explicit wording or
indication in the contract itself (as eg. the use of
contractual
expressions that the certificate is to “final and binding”
or “conclusive evidence”
’
.
[16]
[32]
The
judgment in
Ocean Diners
is
of no assistance to the applicant. That case concerned a final,
not an interim, certificate. The certificate was
issued in
terms of clause 25.5 of the contract in question. Clause 25.7
provided ‘
A final certificate
issued in terms of clauses 25.5 and 25.6 ... shall be conclusive
evidence as to the sufficiency of the said
works and materials, and
of the value thereof
’
.
Smalberger JA held that the employer was, subject only to a limited
number of available defences such as fraud or collusion
between the
agent and the contractor to the detriment of the employer or
non-compliance by the certificate with the prescribed
requirements of
the contract, bound by the agreed-upon conclusive effect of the
certificate. If the employer had suffered
any damages as a
consequence of his agent having drawn the certificate negligently,
its remedy lay in a claim against the negligent
agent.
[33]
The
other authority on which Mr
Sievers
placed
reliance,
Joob
Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture
supra,
also affords no succour to the applicant. In that case, the
defendant’s appeal from the summary judgment granted
against it
in the court of first instance was refused because its defences to
the claims brought against it founded on a series
of interim
certificates issued by the defendant’s principal agent were
either incompatible with the express provisions of
the building
contract, or otherwise palpably bad. The judgment does refer
approvingly to
Randcon
supra,
but only for purpose of illustrating the trite proposition that a
payment certificate gives rise to a separate cause of action.
[17]
In
Thomas
Construction
(supra,
note 10), Botha JA pointed out that nothing more was meant by that
‘
than
that a cause of action couched in such a form is in order from the
point of view of pleading, practice and procedure
’
.
[18]
As mentioned earlier, that point is trite and not in dispute in the
current matter.
[19]
[34]
Contrary
to the thrust of Mr
Siever
s’s
argument, the indications are that our jurisprudence has also come to
reject what Nienaber J, in
Thomas
Construction (Pty) Ltd (in liq.) v Grafton Furniture Manufacturers
(Pty) Ltd
[1986]
2 All SA 357
(N);
1986
(4) SA 510
(N),
called ‘
the
now discredited case of
Dawnays
’
.
The learned judge described Lord Denning MR’s reference to
an interim certificate as the equivalent of cash or
a bill of
exchange as ‘
pure
hyperbole
’
.
He proceeded (at 516B-E SALR), ‘
If
that remark was intended to convey that the certificate is immune
against attack or defence, the comparison is, with respect,
misleading, notwithstanding the apparent deference with which the
expression was quoted in
Smith
v Mouton
[(W),
supra]
...
at 13H. Lord Denning’s construction has certainly not
been universally accepted in our case law ... . The better
view, with
respect, is that all defences remain open to a claim based on an
interim certificate, including set-off or a counterclaim
for damages
for breach of the very contract which spawned the certificate ... .
’
[35]
It
is arguable that what Nienaber J termed the ‘
better
view
’
(a
view obviously dependent on the provisions of the given contract) was
implicitly endorsed by Botha JA in the judgment on appeal
in that
matter.
[20]
There,
with reference to a contention by the appellant’s counsel
(similar to that asserted by Mr
Sievers
)
that the certificate was ‘
sacrosanct
’
,
Botha JA responded, ‘
That
cannot be right. Counsel was elevating the recognition of a
cause of action into a postulate that there can be no answer
to it
’
.
Like Trollip JA in
Smith
v Mouton
(A)
supra, the learned judge found it unnecessary to decide whether there
was any limitation on the type of answer that was permissible.
It
is noteworthy, however, that he did not embrace the appellant’s
counsel’s argument ‘
that
it would be limited to cases of fraud and the like
’
,
and refrained from expressing any doubt concerning Nienaber J’s
statement of the ‘better view’.
[36]
I
described earlier in this judgment
[21]
the
various provisions of the contract between the applicant and the
first respondent that appeared to be most relevant for
the purposes
of the case. None of them gives the interim certificate the
character of something that vests an absolute or
temporarily final
right to payment of the amount certified thereby if there is a
dispute. The adjudication and arbitration
provisions point the
other way. There is nothing in the contract that I have found
or been referred to that indicates that
the employer waived or
abandoned the right to raise any contractual defence that might be
available to it to resist a claim for
payment in terms of an interim
payment certificate.
[37]
It
was not entirely clear to me on the papers whether the issue of the
first respondent’s alleged entitlement to delay damages
is an
issue in the pending arbitration proceedings between the parties.
I was initially inclined to the view that it would
be necessary for
the first respondent to show clearly that it was if it sought to
raise its claim in that regard in opposition
to any obligation to pay
the amount certified in certificate no. 17. Upon reflection,
however, I have concluded that the
question was, with respect,
correctly disposed of by Viscount Dilhorne in
Gilbert-Ash
in
response to a comparable argument by the contractor’s counsel
in that matter. Lord Dilhorne said (at p. 720)
–
‘
Counsel
for the respondent felt compelled to concede, in my view rightly,
that the employer if sued in an action for the amount
stated as due
in an interim certificate. would be entitled to challenge the
certificate on the ground that the work included in
the calculation
of that amount was not properly executed; though counsel contended
that in order to resist payment on this ground
the employer would
have to have already submitted to arbitration the dispute as to
whether or not the certificate was in accordance
with the conditions
of the contract and then to apply for a stay of action under section
4 of the Arbitration Act 1950. The arbitration
clause, however, does
not make an award a condition precedent to a right of action, let
alone a condition precedent to a right
of defence; and I see no
grounds in law to prevent the employer from defending the action by
setting up the contractor’s
breach of warranty in doing
defective work even though this involves challenging the architect’s
certificate that that work
had been properly executed.’
[38]
That
all of the issues raised by the first respondent in opposition to the
application are questions before the arbitrator in any
event seems
implicit in the submission by the first respondent’s counsel
that the need to determine the dispute between the
parties concerning
the applicant’s entitlement to payment of the sum certified in
payment certificate no. 17 would fall away
once the pending
arbitration proceedings were determined. The applicant’s
counsel did not take issue with the submission,
and the applicant did
not seek to respond to the averment in the supplementary answering
affidavit that ‘[t]
he outcome
of
[the]
arbitration
proceedings will be determinative of the present application
’
.
That the pertinent disputes are all before the arbitrator is also
supported by the first respondent’s call upon the
applicant on
9 May 2023 to agree to postpone or withdraw the application because
of the pending arbitration.
[39]
I
appreciate that the cause of action in this application, predicated
on certificate no. 17, is different from the causes of action
in
respect of the claims (and counterclaims) before the arbitrator, but
it nevertheless seems obvious, in the context of the grounds
of
opposition relied on by the first respondent in these proceedings,
that the result of the application necessarily depends on
the
arbitrator’s award. In view of the parties’
agreement that the arbitration will finally settle their disputes,
the applicant cannot obtain enforcement of the disputed payment
certificate, save in respect of the first respondent’s admitted
indebtedness, until the arbitrator has made his award. And once
the arbitrator has made his award, the certificate will be
enforceable only to the extent of its consistency with the award.
[40]
The
applicant would therefore have been well advised to have agreed to
the first respondent’s proposal that the application
be
postponed until after the completion of the arbitration proceedings.
It was misdirected in pressing for judgment in the
application at
this stage. In the absence of an application for postponement
by the applicant or one for a stay by the first
respondent, the court
has been forced into having to give a determinative judgment at an
inopportune time.
[41]
As
the applicant is seeking final relief on motion, the matter falls to
be decided applying the evidential principles rehearsed
in
Plascon-Evans
.
[22]
The court is not in a position to regard the factual premises for the
first respondent’s contestation of payment certificate
17 as so
far-fetched or clearly untenable as to justify being rejected on the
papers. The consequence is that the application
for payment in
the certified amount exceeding the first respondent’s admitted
indebtedness must be dismissed. The dismissal
will have the
effect of an order of absolution from the instance. Any right
that the applicant might have to payment of the
balance of the amount
certified in terms of certificate 17 will be determined by the
arbitrator’s award.
[42]
I
have not found it necessary in the circumstances to decide the
contention that certificate no. 18 superseded the certificate
on
which the applicant sued in the current proceedings. Nothing in
the contract prescribes the form of certificate to be
issued by the
Engineer. It consequently does not seem to matter that the
certificate was not signed. Suffice it to
say, however, that I
doubt that clause 14.6 of the contract invests the Engineer with the
authority to issue a certificate purporting
to correct an earlier
contested certificate that is the subject of pending arbitration
proceedings;
a fortiori
,
if it purports to do so in accordance with the contentions of one of
the parties to those proceedings. It strikes me that
that would
trench impermissibly on the arbitrator’s function concerning
the dispute. I would be reluctant to construe
the contract as
allowing that. I do not think that any such purported
correction or modification could ‘
properly
be made
’
within the meaning
of that phrase in clause 14.6.
[43]
An
order will issue in the following terms:
1.
The
first respondent’s application for the admission of its
supplementary answering affidavit is granted; the first respondent
to
be liable to the applicant for the costs of that application on an
unopposed basis.
2.
The
first respondent is ordered to pay the applicant the sum
of
R613 924.07 pursuant to
interim payment certificate no.17, together with interest thereon
a
tempore morae
in terms of the
contract calculated with reference to clause 14.7 (b) thereof (as
amended).
3.
Save
as provided in paragraph 2, the application is otherwise dismissed.
4.
Save
as otherwise provided in the order made by Mr Justice Erasmus on 25
May 2022, the first respondent is ordered to pay the applicant’s
costs of suit incurred up to and including 26 May 2023, as well as
the costs attendant upon the applicant’s consideration
of the
first respondent’s heads of argument that were delivered out of
time, on 5 June 2023, including the fees of two counsel
where such
were engaged.
5.
The
applicant shall pay the first respondent’s costs of suit
incurred after 26 May 2023, including the fees of two counsel
where
such were engaged.
A.G.
BINNS-WARD
Judge
of the High Court
APPEARANCES
Applicant’s
counsel:
F.S.G.
Sievers SC
J.P.
Steenkamp
Applicant’s
attorneys:
Ryan
Hall Attorneys
Durbanville
Schneider,
Galloon & Reef
Cape
Town
First
respondent’s counsel:
D.
Mahon
C.
Hammick
First
respondent’s attorneys
Tiefenthaler
Attorneys
Waterfall
(Gauteng) and Cape Town
[1]
After
the Fédération Internationale des Ingénieurs-Conseils,
under whose auspices it is published.
[2]
Certain
provisions of the standard form contract were amended in the deed of
agreement concluded between the applicant and
the first respondent,
but none of the amendments is material for the purposes of
determining the application.
[3]
The
wording used in the contract is ‘
the
dispute shall be finally settled
’.
[4]
The
contract in the current matter did not contain a provision like
those described in
Radon
Projects (Pty) Ltd v NV Properties (Pty) Ltd & Another
[2013]
ZASCA 83
(31
May 2013);
[2013]
3 All SA 615
(SCA);
2013
(6) SA 345
(SCA)
at para 3-5 and
Framatome
v Eskom Holdings SOC Ltd
[2021]
ZASCA 132
(1
October
2021);
2022 (2) SA 395
(SCA))
at para 22, which rendered the adjudicator’s decision binding
and enforceable unless and until it was set aside
or altered in
subsequent arbitration proceedings.
[5]
At
p. 660E.
[6]
At
p. 138D.
[7]
McEwan
J acknowledged that the judgment in
Dawnays
case
had been disapproved by the House of Lords in
Gilbert-Ash
(see
paragraph 28 below), and referred in that connection (at pp.14E-15F)
to what he called ‘
the
more difficult question ... whether or not the employer is entitled
to resist a claim for payment of the sum shown in an interim
certificate on the grounds that, by reason of defective work or
delay in completion of the works, the employer has a claim for
damages against the contractor which will extinguish or reduce the
amount of the claim on the certificate
.’
The learned judge refrained from deciding the question because it
had not been argued before him but, later in
the judgment (at
p.17A-B), nevertheless expressed himself in a way that implied that
he would have been inclined, if so required,
to answer it in
accordance with the House of Lords decision. On appeal,
in
Mouton
v Smith
1977
(3) SA 1
(A),
the court (at p.5F) found it ‘
unnecessary,
in the present case, to decide what defences the employer can and
cannot raise if the contractor sues him on an interim
certificate
.’
[8]
In
Nucon
Construction Thaba Nchu (Edms) v Scholtz NO
[2010]
ZAFSHC 141
(8
November 2010), the full court of the Free State Division, with
reference to the said numbered paragraphs in
Smith
v Mouton
(W)
supra, applied the reasoning in
Dawnays
case
without giving any consideration to the subsequent jurisprudential
treatment of that judgment in England and in this
country described
later in this judgment, or to the fact that the Appellate Division,
in its judgments in
Smith
v Mouton
(A)
supra, and
Thomas
Construction
(see
note 10 below), had expressly left open the question of what
defences an employer can raise when sued on an interim
certificate.
[9]
I.N.
Duncan Wallace,
Hudson’s
Building and Engineering Contracts
(11
th
ed.)
vol. 1 at 6.004 and 6.204.
The
textbook is currently in its 14
th
edition,
but, regrettably, and a sign of seemingly ever-diminishing judicial
research resources, the 11
th
edition
and the 2003 First Supplement thereto are the most recent versions
of this important work in the Cape Town High
Court
library.
Hudson’s
use
of the expression ‘
temporary
finality
’ in
that context has been referred to or adopted in judgments in
Australia and Singapore; see
John
Holland Pty Ltd v Schneider Electric Buildings Australia Pty
Ltd
[2010]
QSC 159
at
para 50 and
Vinod
Kumar Ramgopal Didwania v Hauslab Design & Build Pte Ltd
[2017]
SGCA 19
;
[2017]
1 SLR 890
at
para 30.
[10]
Cf.
Mouton
v Smith
1977
(3) SA 1
(A)
at 5D-E,
Thomas
Construction (Pty) Ltd (in liq.) v Grafton Furniture Manufacturers
(Pty) Lt
d
1988
(2) SA 546
(A)
at 562E-F and
Shelgatha
Property Investments CC v Kellywood Homes (Pty) Ltd; Shelfaerie
Property Holdings CC v Midrand Shopping Centre (Pty)
Ltd
1995
(3) SA 187
(A)
at 193A-C.
[11]
In
Beaufort
Developments (NI) Ltd v. Gilbert-Ash NI Ltd and Others
[1998]
UKHL 19
(20
May 1998)
[1998]
UKHL 19
;
;
[1999]
AC 266
;
[1998]
2 All ER 778
[1998] UKHL 19
; ;
[1998]
2 WLR 860
,
Lord Lloyd of Berwick described the judgment in
Dawnays
as
having come ‘
as
something of a surprise in the official referees’ corridor
’
.
He held it out as an example of matters in which the courts had
caused difficulty ‘
by
treating building contracts as if they were subject to special rules
of their own
’
.
[12]
At
p. 12D.
[13]
At
p. 717-718.
[14]
At
p. 718.
[15]
Hudson’s
Building Contracts
op.
cit. vol. 1 at 6.005 (p.730).
[16]
Id
at 6.004 (p. 729).
Hudson’s
Building Contracts
notes
that in certain jurisdictions - Australia, New Zealand and Singapore
are specified - standard contract forms and statutory
provisions
have been adopted to give interim certificates the quality of
‘temporary finality’, thereby more efficiently
achieving
the recognised cashflow related objects of any progress payment
provisions.
[17]
Joob
Joob Investments
at
para 27.
[18]
At
p. 562G.
[19]
See
paragraph 27 above and the authorities cited in fn. 10.
[20]
Cited
in fn 10 above.
[21]
In
paragraph 2.
[22]
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984]
ZASCA 51
;
1984
(3) SA 623
(A)
at 634E-635C.
sino noindex
make_database footer start
Similar Cases
Imvusa Trading 1581 BK v Oudtshoorn Municipality (1708/2017) [2022] ZAWCHC 211 (20 October 2022)
[2022] ZAWCHC 211High Court of South Africa (Western Cape Division)98% similar
Ampcor Khanyisa (Pty) Ltd v City of Cape Town and Others (21512/2021) [2023] ZAWCHC 258 (18 October 2023)
[2023] ZAWCHC 258High Court of South Africa (Western Cape Division)98% similar
Uptown Trading 803 (Pty) Ltd t/a Waterloo Plumbing v Ziningi Properties (Pty) Ltd (13414/24) [2025] ZAWCHC 360 (7 August 2025)
[2025] ZAWCHC 360High Court of South Africa (Western Cape Division)98% similar
Mdanjelwa v Socio Economic Rights Institute of South Africa (3017/2018) [2023] ZAWCHC 192 (3 August 2023)
[2023] ZAWCHC 192High Court of South Africa (Western Cape Division)98% similar
A.C.L v A.P.S and Others (16867/2023) [2023] ZAWCHC 321 (10 November 2023)
[2023] ZAWCHC 321High Court of South Africa (Western Cape Division)98% similar