Case Law[2023] ZAWCHC 200South Africa
DB Property Development Company (Pty) Ltd v Executive Mayor Stellenbosch Municipality and Others (15274/2021) [2023] ZAWCHC 200 (10 August 2023)
High Court of South Africa (Western Cape Division)
10 August 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2023
>>
[2023] ZAWCHC 200
|
Noteup
|
LawCite
sino index
## DB Property Development Company (Pty) Ltd v Executive Mayor Stellenbosch Municipality and Others (15274/2021) [2023] ZAWCHC 200 (10 August 2023)
DB Property Development Company (Pty) Ltd v Executive Mayor Stellenbosch Municipality and Others (15274/2021) [2023] ZAWCHC 200 (10 August 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2023_200.html
sino date 10 August 2023
IN THE HIGH COURT OF
SOUTH AFRICA
(WESTERN CAPE
DIVISION, CAPE TOWN)
Case No:
15274/2021
In
the matter between:
DB
PROPERTY DEVELOPMENT COMPANY (PTY) LTD
Applicant
and
EXECUTIVE
MAYOR: STELLENBOSCH MUNICIPALITY
First
Respondent
DIRECTOR:
PLANNING AND ECONOMIC DEVELOPMENT
Second
Respondent
STELLENBOSCH
MUNICIPALITY
Third
Respondent
Coram:
Justice J Cloete
Heard:
24 and 25 July 2023
Delivered
electronically:
10 August 2023
JUDGMENT
CLOETE
J
:
Introduction
[1]
The applicant (“DB”) is a
property development company. In its final amended relief DB seeks
the review and setting
aside of a decision taken by the first
respondent (“Executive Mayor”) on 24 May 2023
dismissing an appeal against
two conditions of the land use approval
decision of the second respondent (“Director”) of 22 June
2021. In the
event it is successful, DB asks that the appeal be
referred back to the Executive Mayor for reconsideration. The
respondents agree
that if the review succeeds a referral back (or
remittal) is the appropriate remedy, but differ from DB in respect of
the direction
it seeks as part of that remittal.
[2]
DB’s
attack on the lawfulness of certain provisions in the 2020/21
Development Charges Policy (“MDC Policy”) of
the third
respondent (“Municipality”) has fallen away, since it was
premised on a finding by the court that the MDC
Policy is a binding
legislative instrument. In light of the Supreme Court of Appeal
decision in
Sasol
,
[1]
cited with approval by the Constitutional Court in
Rivonia
Primary School
,
[2]
there is no longer any dispute that ‘
a
policy serves as a guide to decision-making and cannot bind the
decision-maker inflexibly’.
The two disputed
conditions
[3]
These relate to development charges imposed
on the approval of DB’s land development application. DB
accepts that its planned
development will have an impact on municipal
bulk infrastructure and that it is obliged to contribute towards that
infrastructure,
which includes water, sewerage, stormwater,
solid-waste, roads and community services.
[4]
The first condition challenged is the
amount imposed as a development charge for municipal road
infrastructure. It is common cause
that DB’s property, Portion
43 of Farm No.65, Stellenbosch Division (“the Property”)
is situated in the Koelenhof
area of the Municipality approximately
7km northwest of Stellenbosch Town. The surrounding road network,
namely Bottelary Road
(M23) and the R304, are provincial roads in
which the development is embedded. As determined by DB’s road
engineers, it will
effectively be a secondary user of the municipal
(as opposed to the provincial) road infrastructure. In a nutshell, DB
takes issue
with the conclusion by the Director, and subsequently by
the Executive Mayor, that
all
the trips to be generated by its development will distribute to the
Stellenbosch Town (municipal) impact zone.
[5]
DB’s main contention is that contrary
to the applicable statutory framework, what it is being asked to pay
as a development
charge for municipal roads has not properly taken
into account the demand (or impact) which its proposed development
will have
on the municipal road infrastructure, given the
development’s location within the provincial road
infrastructure. DB contends
that the MDC Policy and Municipality’s
Development Charges Tariff Tables, which together determine the
approach and quantification
of development charges, constitute a
policy and a guideline, not a rigid statutory framework to be applied
inflexibly.
[6]
It submits that when making their decisions
at first instance and on appeal, both decision-makers however
fettered their discretion,
and mechanically calculated the
development charges for municipal roads according to the approved
land uses by using the tariff
tables for the Stellenbosch Town impact
zone, which includes Koelenhof, despite the development’s
traffic only having a secondary
impact on the municipal road
infrastructure. DB submits that in doing so, the decision-makers
failed to apply their minds properly
to its reduced utilisation of
municipal roads, which required them to deviate from the MDC Policy
and adjust the development charge
accordingly.
[7]
In the answering affidavit the respondents
contended that the MDC Policy has the status of subordinate
legislation and cannot be
deviated from by decision-makers without
violating the principle of legality (as mentioned above they no
longer maintain this stance).
The respondents however persist in
their contention that neither decision-maker had an “unfettered”
discretion to circumvent
the formula prescribed by the MDC Policy;
and that to the extent the aforementioned policy does ‘
impose’
a discretion on them, it is limited and
in the particular circumstances such discretion ‘
was
not activated’.
[8]
The second condition challenged is that in
the approval the Municipality made a very substantial reduction in
the amount of the
development charges credit granted to DB as a
condition of a previous approval (“the 2018 approval”)
from R25 490 015.44
(15% of the total development charges
imposed pursuant to the 2018 approval) to R1 447 158.39 (2%
of the total development
charges of R81 708 331.11
imposed). DB maintains that the Municipality’s previously
granted credit remains valid
until set aside, and the current credit
should have been calculated inclusive of DB’s vested rights.
The respondents dispute
the previously granted credit should have
been taken into account.
The statutory
context of development charges
[9]
The approval of a land development
application ordinarily results in new development that increases the
demand on municipal external
engineering services. An applicant for
land development is responsible for the provision and installation of
internal engineering
services whereas a municipality is responsible
for the provision of external engineering services such as water,
sewerage, electricity
and municipal roads. Development charges are a
once-off capital contribution an applicant pays to a municipality
towards the capital
costs of the municipal external engineering
services needed to service an applicant’s increased demand on
these services.
[10]
The
Spatial Planning and Land Use Management Act
[3]
(“SPLUMA”) authorises the promulgation of provincial
legislation to regulate the provision of engineering services
and the
imposition of development charges including the calculation thereof.
In turn s 40 of the provincial legislation, namely
the Western
Cape Land Use Planning Act
[4]
(“LUPA”) provides for the imposition of conditions on
approvals, the following provisions being relevant to the matter
at
hand:
‘
40
Conditions
(1)
When a municipality approves a land
use application subject to conditions,
the
conditions must be reasonable conditions and must arise from the
approval of the proposed utilisation of land.
(2)
Conditions imposed in accordance
with subsection (1) may include, but are not limited to, conditions
relating to-
(a)
the provision of engineering
services and infrastructure;
(b)
the … payment of money;…
(3)
Subject to subsection (12), a
condition contemplated in subsection (2)(b) may
require
a proportional contribution to municipal public expenditure according
to the normal need therefor arising from the approval
,
as determined by the municipality in accordance with
norms
and standards
as may be
prescribed…
(5) When
determining the contribution contemplated in subsection… (3)…,
a municipality
must have regard to at least
-
(a)
the municipal service infrastructure and amenities for the land
concerned that are needed for the approved land
use;
(b)
the public expenditure on that infrastructure and amenities for the
land concerned that are needed for the approved
land use;
(c) the
public expenditure on that infrastructure and those amenities that
may arise from the approved land use;
(d) money
in respect of contributions contemplated in subsection (3) paid
in the past by the owner of the land
concerned; and
(e) money
in respect of contributions contemplated in subsection (3) to be
paid in the future by the owner of the
land concerned…
(12)
A municipality
may, if
appropriate, depart
from
contributions determined in accordance with subsections (3) and
(5).’
(Emphasis
supplied).
[11]
It is common cause there are no prescribed
‘
norms and standards’
as envisaged in s 40(3). What is apparent on a plain reading of
s 40 is that the focus of any development charge to be
imposed
is
municipal
expenditure (both on the municipal service infrastructure and the
amenities arising from the land use approval); and the Municipality
has an overriding discretion to deviate from contributions determined
in accordance with s 40(3) and (5) if it considers this
appropriate.
[12]
On
20 October 2015 the Municipality promulgated its Land Use Planning
By-Law (“the Planning By-Law”)
[5]
implementing SPLUMA and LUPA to regulate the use and development of
land within its jurisdiction. The relevant sections of the
Planning
By-Law are s 66 and s 83, and the pertinent subsections
essentially replicate s 40 of LUPA.
[13]
Section 83(2) of the Planning By-Law
prescribes that external engineering services for which development
charges are payable must
be set out in a policy and reviewed annually
by the Municipality; and s 83(3) stipulates that the amount of
development charges
payable by an applicant must be calculated in
accordance with that policy.
[14]
The Municipality duly adopted the MDC
Policy. It is revised and implemented annually on 1 July each
year. In making the first
instance decision the Director applied the
2019/20 policy, and in dismissing the appeal the Executive Mayor
applied the 2020/21
policy. The parties are now
ad
idem
that it is only the Executive
Mayor’s decision which is the subject of review, and that she
correctly had regard to the 2020/21
policy when making her decision.
The impugned
decision
[15]
It
is not necessary to consider any explanations given by the
respondents in the answering affidavit which are at variance with,
or
attempt to amplify, the reasons for the Executive Mayor’s
decision, since this would amount to an impermissible
ex
post facto
justification therefor:
Nersa
v PG Group.
[6]
For convenience I will refer to the formulation of the grounds of
appeal as they appear in the Executive Mayor’s decision.
The
first ground: The discretion in the policy was not applied in
calculating the roads development contributions.
[16]
The Executive Mayor reasoned as follows:
‘
The
Appellant argued that the discretion in Clause 9 of the…
Policy has not been exercised when calculating the Development
Charges for this development. However clause 14 should be read in
conjunction with clause 9. Clause 14.1 reads as follows: “Development
Charges will be applied based on the impact of services by the
increase in land use rights and/or intensification of land use
leading to increased demand, irrespective of the geographical
location of the development. For example, the traffic generated by
a
development located along a provincial road, will ultimately end up
on the Municipality’s road network that link to the
provincial
roads. The same applies to the additional stormwater runoff that ends
up in downstream municipal networks and river
courses, increase in
demand and the bulk supply of water, and sewer and solid waste
disposal.”
This clause
specifically guides officials as to how to deal with applications for
developments along provincial roads to ensure
that the principles of
consistency in decision making and administrative justice can be
better complied with…
The Developer argued
that only 30% of trips have an impact on Stellenbosch Municipality
roads and DCs should therefore only be 30%
of the Roads DC
calculated. The traffic impact assessment was done during the covid
pandemic and it’s not clear if the traffic
patterns during this
period reflect the true usage of the roads. Even without taking this
into account, clause 14.1 of the Development
Contribution Policy
already deals with this issue.
Furthermore: 6% of
trips come to/from Klapmuts, which means this traffic also impacts on
the Stellenbosch municipal road network
(Stellengate Boulevard and
the future Potbelly road that intersects with the R44 are municipal
roads). This illustrates that their
argument of 30% cannot be
substantiated and nullifies the argument that clause 9, was not taken
into account.’
[17]
Given that the 2020/21 MDC Policy refers to
“paragraphs” and not “clauses” I adopt the
same terminology.
Paragraph 8.3 obliges the Municipality, for
purposes of calculation of the bulk services component of a
development charge, to
(a) determine a unit cost for each
municipal
infrastructure service; and (b) (i) apply a formula aimed at
determining the impact of the
proposed
land use
on those services; and (ii)
calculate the amount payable by multiplying the unit cost by the
estimated proportion of the
municipal
infrastructure services that will be utilised by that proposed
development.
[18]
Paragraph 9 provides that notwithstanding
paragraph 8.3 the Municipality may
at
its own instance
or on request of a
developer, increase or reduce the amount of the bulk services
component of a development charge to reflect the
actual cost of
installation in four specified instances. One of these (paragraph
9.1.3) is where the actual usage of a particular
land development
varies significantly from the approved tariff tables, and where the
actual usage is motivated by a professional
engineer and can be
justified by means of recognised guidelines and/or industry norms and
standards. In the present matter it is
common cause that two such
reports by a professional engineer appointed by DB were before the
Executive Mayor when she made her
decision.
[19]
As reflected in the Executive Mayor’s
decision, paragraph 14.1 stipulates that development charges will be
applied based on
the impact on services by the increase in land use
rights and/or intensification of land use leading to increased demand
irrespective
of the geographical location of the development. It appears that in
reaching her decision the Executive Mayor not only considered
paragraph 14.1 to be an overriding provision, but also that it
removed the discretion explicitly conferred on a decision-maker
in
land use approvals, not only in terms of binding legislative
instruments (s 40(12) of LUPA and s 66(4) of the Planning
By-Law) but also in paragraph 9 of the MDC Policy itself.
[20]
As is evident from her reasoning she took
the view that the purpose of paragraph 14.1 is to guide officials in
dealing with applications
for developments along provincial roads,
and that the motivation provided by DB was a side issue of little, if
any, significance
(the parties accept that in any event the traffic
impact assessment was not performed during the Covid-19 pandemic).
However paragraph
14.1 only refers to a development along a
provincial road as an example, and that example assumes that in all
instances –
i.e. without exception – traffic generated by
every such development will ‘
ultimately
end up’
on the municipal road
network linking the provincial roads, irrespective of a development’s
geographical location. This might
be so, but it ignores the
underlying principle of proportionality, which in turn may be
departed from to reflect the actual cost
in an appropriate case.
[21]
Interpreting
paragraph 14.1 as the Executive Mayor appears to have done renders
paragraph 9.1.3 nugatory. In addition paragraph
9 makes no mention
that the discretion conferred therein is subject to paragraph 14.1;
the heading of paragraph 14 itself reads
‘
Other
Principles to be Applied’
from which it is evident that a “balancing act” is
required; and indeed the Executive Mayor herself acknowledged that
paragraph 14.1 ‘
should
be read in conjunction with’
paragraph 9. Accordingly, and having regard to the settled principles
of interpretation,
[7]
it follows
that the Executive Mayor impermissibly fettered her discretion in
reaching her decision.
[22]
I accept of course that it is the
Municipality’s prerogative to adopt a policy which, in the
words of the Executive Mayor,
is aimed at ensuring ‘
that
the principles of consistency in decision-making and administrative
justice can be better complied with’.
But in doing so the Municipality has itself stipulated that the
approach to the calculation of development charges is informed,
amongst others, by the guiding principles in clause 4 of the MDC
Policy:
22.1
Equity and fairness which require that ‘
(d)evelopment
charges should be reasonable, balanced and practical so as to be
equitable to all stakeholders. The key function of
a system of
development charges is to ensure that those who benefit from new
infrastructure investment, or who cause off-site impacts,
pay their
fair share of the associated costs’
; and
22.2
Spatial and economic neutrality which implies that ‘
(d)evelopment
charges should be calculated where possible on a sectoral or
geographic scale to more accurately approximate costs
within a
specific impact zone’.
[23]
At the risk of repetition it is not for the
court to prescribe to the Municipality how it should achieve these
goals, or how its
decision-makers should properly exercise their
discretion. But what cannot be sanctioned is an impermissible
fettering of that
discretion. Accordingly the first review challenge
must succeed.
The second ground:
2018 DC credit based on 5.8ha Industrial zoning vs 2019 DC credit
based only on the GLA of the existing buildings
[24]
The Executive Mayor reasoned as follows:
‘
1.
The Development Charges credit determined during 2018 was based on
the 5.8ha industrial
zoning that was then in place. This stems from
the application for an extension of validity of the 2014 approval (in
terms of LUPO)…
2.
At the time, the Development Charges applied in terms of LUPO was
determined
and based on the existing rights, and not on actual
payment received for Development Charges. No payments were ever made
in this
regard.
3.
The subsequent application for approval in 2019, was in terms of
SPLUMA, in terms
of which, the Municipality only gives credit for
actual payments received or for approved buildings already
constructed of which
the impact has already been absorbed in the
municipal infrastructure… The relevant sections of SPLUMA are
listed below.
4.
The principles as contained in paragraph (b) (i) (v), (c) (i) and
(ii), needs
to be taken into account…’
[25]
SPLUMA
came into effect on 1 July 2015. Prior thereto land use planning
applications in the Western Cape were governed by the Land
Use
Planning Ordinance (“LUPO”).
[8]
For present purposes it is not necessary to determine whether the
Executive Mayor was correct in stating that development charges
applied in terms of LUPO were determined and based on existing rights
and not on actual payment received for development charges.
What is
relevant is the Executive Mayor’s reliance on s 7(b)(i),
(v), (c) (i) and (ii) of SPLUMA which read as follows:
‘
Development
principles:
7. The following
principles apply to spatial planning, land development and land use
management…
(b) the principle of
spatial sustainability, whereby spatial planning and land use
management systems must---
(i) promote land
development that is within the fiscal, institutional and
administrative means of the Republic…
(v) consider all
current and future costs to all parties for the provision of
infrastructure and social services in land developments…
(c) the principle of
efficiency, whereby---
(i) land development
optimises the use of existing resources and infrastructure;
(ii) decision-making
procedures are designed to minimise negative financial, social,
economic or environmental impacts…’
[26]
During argument counsel for the respondents
fairly conceded that one searches in vain in the subsections of
SPLUMA relied upon by
the Executive Mayor for any reference to a
statutory limitation imposed upon the Municipality to determine a
development charges
credit based only on actual payments received or
approved buildings already constructed; and that trying to place some
sort of
interpretation on the word ‘
fiscal’
in s 7(b)(i) is at best speculation. Put simply, the decision by
the Executive Mayor on this score was materially influenced
by an
error of law and on this ground alone it must be reviewed and set
aside.
[27]
I accordingly do not intend dealing with
DB’s argument that the calculation of the 2020 development
charges credit must take
into account the 2018 credit, since on the
Executive Mayor’s own reasoning this did not inform her
decision. It is open to
DB to renew this argument when the matter is
reconsidered.
Conclusion and
costs
[28]
For sake of completeness it should be
mentioned that in their answering affidavit the respondents
challenged the attack on the lawfulness
of certain provisions in the
MDC Policy as being moot, given that it has since been superseded by
subsequent versions. It is no
longer necessary to consider this since
that declaratory relief sought by DB has, as previously stated,
fallen away.
[29]
Given my conclusion that the decision of
the Executive Mayor dismissing the appeal falls to be reviewed and
set aside a remittal
must follow. DB seeks a direction that she must
appoint, in terms of s 81(10) of the By-Law, an independent
registered professional
road engineer who is not employed by the
State, with no less than 10 years’ experience in practice and
the calculation of
development charges, for purposes of assisting her
in reconsidering her decision. However as pointed out by counsel for
the respondents
this is something which lies only within the
authority of the Executive Mayor since s 81(10) reads that
‘
(t)he Appeal Authority may
appoint a technical advisor to advise or assist it with regard to a
matter forming part of the appeal’.
He submitted that DB should, in the circumstances, make application
to the Executive Mayor to invoke s 81(10) in due course.
[30]
DB has been substantially successful and in
the circumstances costs should follow the result.
[31]
The following order is made:
1.
The decision of the first respondent
of 24 May 2021 dismissing the applicant’s appeal against the
following incorporated in
condition 2.3.26 of the second respondent’s
decision of 22 June 2021 is reviewed and set aside:
1.1
the condition set out in the
memorandum of the Directorate: Infrastructure Services (Mr T King)
dated 17 February 2020 (“the
Infrastructure Memorandum”)
and in Annexure DC to the Infrastructure Memorandum, determining the
extent of the development
charges payable by the applicant in respect
of municipal road infrastructure; and
1.2
the condition determining the extent
of the development charges credit, as recorded in the covering page
of the Infrastructure Memorandum,
which credit translated into the
amount of R1 447 158.39;
2.
The appeal referred to in paragraph
1 above is remitted to the first respondent for reconsideration; and
3.
The respondents shall pay the costs
of this application, including the costs of two counsel, save for the
wasted costs incurred
by the postponement on 20 February 2023
occasioned by the registrar, in respect of which each party shall
bear their own costs.
J I CLOETE
For
applicant
:
Adv
S Rosenberg SC with Adv A Erasmus
Instructed
by
:
Stadler
& Swart Inc. (Ms A Vosloo)
For
respondents
:
Adv
A Montzinger
Instructed
by
:
TNK
Attorneys (Ms J Barnes)
[1]
MEC
for Agriculture, Conservation, Environment and Land Affairs v Sasol
Oil (Pty) Ltd and Another
2006 (5) SA 483
(SCA) at para [19].
[2]
MEC
for Education, Gauteng Province and Others v Governing Body, Rivonia
Primary School and Others
2013 (6) SA 582
(CC) at para [54]; see also
Akani
Garden Route (Pty) Ltd v Pinnacle Point Casino (Pty) Ltd
2001
(4) SA 501
(SCA) at para [7].
[3]
No.
16 of 2013.
[4]
No
3 of 2014.
[5]
Provincial
Gazette 7512 of 20 October 2015.
[6]
2020
(1) SA 450
(CC) at para [39]; see also
National
Lotteries Board and Others v South African Education and Environment
Project
2012
(4) SA 504
(SCA) at paras [27] to [28].
[7]
Natal
Joint Municipal Pension Fund v Endumeni Municipality
2012 (4) SA 593
(SCA) at para [18].
[8]
No
15 of 1985.
sino noindex
make_database footer start
Similar Cases
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2025] ZAWCHC 292 (14 July 2025)
[2025] ZAWCHC 292High Court of South Africa (Western Cape Division)98% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (Leave to Appeal) (17470/2014) [2025] ZAWCHC 453 (3 October 2025)
[2025] ZAWCHC 453High Court of South Africa (Western Cape Division)98% similar
Renown Properties (Pty) Ltd v Esus-2-Group (Pty) Ltd t/a The Korner Gilles Blanc and Others (A 295/2024) [2025] ZAWCHC 105 (13 March 2025)
[2025] ZAWCHC 105High Court of South Africa (Western Cape Division)98% similar
Goodfind Properties (Pty) Ltd v Blake and Others (12653/2022) [2023] ZAWCHC 183 (28 July 2023)
[2023] ZAWCHC 183High Court of South Africa (Western Cape Division)98% similar
Goodfind Properties (Pty) Ltd v Kennedy and Others (9919/2022) [2023] ZAWCHC 307; [2024] 1 All SA 751 (WCC) (30 November 2023)
[2023] ZAWCHC 307High Court of South Africa (Western Cape Division)98% similar