Case Law[2023] ZAWCHC 233South Africa
Ebesa Architects (Pty) Ltd v City of Cape Town (11824/2022) [2023] ZAWCHC 233 (1 September 2023)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2023
>>
[2023] ZAWCHC 233
|
Noteup
|
LawCite
sino index
## Ebesa Architects (Pty) Ltd v City of Cape Town (11824/2022) [2023] ZAWCHC 233 (1 September 2023)
Ebesa Architects (Pty) Ltd v City of Cape Town (11824/2022) [2023] ZAWCHC 233 (1 September 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2023_233.html
sino date 1 September 2023
IN THE HIGH COURT OF
SOUTH AFRICA
(WESTERN CAPE
DIVISION, CAPE TOWN)
Case No: 11824/2022
In
the matter between:
EBESA
ARCHITECTS (PTY) LTD
Applicant
vs
CITY
OF CAPE TOWN
Respondent
In
re:
THE
CITY OF CAPE TOWN
Plaintiff
and
EBESA
ARCHITECTS (PTY) LTD
First
Defendant
NARKER
AND ASSOCIATES CC
Second
Defendant
NEW
CONSULTING ENGINEERS (PTY) LTD
Third
Defendant
ALWYN
LAUBSCHER AND ASSOCIATES (PTY) LTD
Fourth
Defendant
ZINTATHU-M
CONSTRUCTION SAFETY SERVICES t/a
Fifth
Defendant
SPELLBOUND
TRADING 119 CC
BOSHARD
CONSTRUCTION (PTY) LTD
Sixth
Defendant
Matter Heard on: 7
August 2023
Judgment delivered: 1
September 2023
JUDGMENT
MANTAME
J
Introduction
[1]
This is the application for leave to amend the applicant’s
(“
first defendant
”) plea. On 14 July 2022,
the respondent (“
plaintiff / the City
”) instituted
an action for damages against the applicant and five (5) other
defendants. A notice of bar was served
by the respondent on 24
August 2022. On 5 September 2022, the applicant filed its
special plea and conditional special plea.
On 22 September
2022, the respondent filed its replication to the first defendant’s
special plea and conditional special
plea, and on 02 November 2022 it
delivered its notice to amend its particular of claim.
[
2]
There appears to be no objection raised by the applicant when the
respondent amended its particulars
of claim. On 25 November
2022 and / or 6 December 2022, the applicant proceeded with its
notice of intention to amend its
Conditional Special Plea and plea.
On 9 December 2022, the respondent delivered its notice of objection
to applicant’s
notice of intention to amend. On 19
January 2023, the applicant proceeded with its application for leave
to amend its plea
and conditional special plea which the respondent
opposed on 30 March 2023. It is for these reasons that the
matter served
before this Court.
Background Facts
[3]
The respondent sued the first to sixth defendants for damages
suffered as a result of an alleged
negligence. The action
emanates from two (2) tenders; namely:
3.1
Tender number 269/2012/13 (“
the first tender
”)
awarded to a joint venture, namely Ebesa 372E JV (“
Ebesa
JV
”); and
3.2
Tender number 267Q/2015/16 (“
the second tender
”)
awarded to Boshard Construction (Pty) Ltd (“
Boshard
”).
[4]
The applicant and five (5) other defendants are members of Ebesa JV
who successfully tendered
for the provision of professional services
which had to be executed together with the service, in terms of the
second tender.
In respect of the first tender Ebesa JV was
required to perform the following services:
4.1
the provision of architectural, civil, structural, electrical and
mechanical engineering services, quantity
surveying, acting as
principal agent for the Employer (the City), safety services,
environmental assessment and compliance monitoring,
and related
services.
4.2
responsibility for all professional services required to fulfil the
City’s objectives as advertised
therein.
.
[5]
Ebesa JV was to perform its professional services in three (3) areas,
i.e., North, South and East
of the City during the three (3) year
period commencing on 1 July 2013 until 30 June 2016 with an estimated
value of R50 million
(excluding VAT). The services in terms of
the second tender had to be executed in
tandem
with the
professional services awarded in terms of the first tender. The
second tender was awarded to Boshard commencing
on 1 June 2017 and
ending on 12 June 2018. That did not materialise and the period
was extended.
[6]
In terms of the first tender Ebesa JV was responsible for the
complete project and contract management.
It was the
respondent’s assertion that the applicant and other five (5)
defendants breached some clauses in the agreement
/ joint venture
agreement with regard to the two (2) tenders. As a result of
the negligence, breach of contract and / or
duty of care of the
applicant and the other five (5) defendants in executing their
duties, the respondent suffered damages by incurring
fruitless and
wasteful expenses in the aggregate sum of R6 308 053.17 (six million
three hundred and eight thousand and fifty-three
rand and seventeen
cents) – (VAT included).
Application
for Leave to Amend
[7]
As stated above after an objection was raised by the respondent to
the applicant’s notice
of amendment, the applicant filed an
application for leave to amend.
7.1
In its application for leave to amend the applicant asked the Court
to grant an order in the following
terms:
7.1.1 By
deleting the phrase “
failing which such a dispute would
first be referred to either mediation or adjudication, and then to
arbitration
” in paragraph 2 thereof and by replacing it
with “
failing which such a dispute would be referred to
mediation.
”
7.1.2 By
deleting the phrase “
nor was the dispute ever referred to or
determined by mediation, adjudication or arbitration
” in
paragraph 3 thereof and replacing it with “
nor was the
dispute ever referred to mediation.
”
7.1.3. By deleting
the Prayer and by replacing it with “
Wherefore the first
defendant prays that
the action be stayed pending the
referral to and finalisation of the mediation of any dispute relating
to the plaintiff’s
claims.
”
7.2
That the applicant be granted leave to amend its Plea in the
following manner:
7.2.1
By deleting paragraph 15 thereof and by replacing it with:
“
15.
Other than to deny that the Services Contract was extended, the first
defendant admits the allegations in these paragraphs.
”
7.2.2
By deleting paragraph 23 thereof and by replacing it with:
“
23.
The first to fifth defendants, and not the JV, rendered services to
the plaintiff in respect of the Works.
”
7.3
By deleting the phrase “
Alwyn Laubscher of
” where
it appears in paragraph 24.
7.4
By deleting paragraphs 41 to 43 thereof and by replacing it with:
“
41.
The first defendant admits that:
41.1
The assembly of the video screen wall and the construction of the
surrounding structure was originally designed
and planned with 12
60-inch TV screens;
41.2
Without informing the first defendant or seeking its advice in that
regard, 18 70-inch TV screens were acquired
and utilized to assemble
and construct the video screen wall; and
41.3
Due to the height of the raised floor and the height of the concrete
beam at the top of the surrounding structure,
the video screen wall
was unsuitable and not operationally acceptable to the plaintiff due
to a portion of such wall not being
visible to operator.
42.
The first defendant denies the allegations in this paragraph as same
contradict or conflict with what
is pleaded above.
43.
In particular, the first defendant denies that its conduct or
omissions gave rise to the complaints
of the plaintiff or that it in
any way breached any allegation it may have had to the plaintiff.”
7.5
By deleting the words “
was negligent or
” where it
appears in paragraph 44 thereof.
7.6
By inserting the phrase “
that it is liable for any delay or
losses suffered by the plaintiff, if any
” between “
the
plaintiff
” and “
the first defendant
”
where it appears in the second line of paragraph 44 thereof.
7.7
By deleting paragraph 48 thereof and by replacing it with:
“
48.
The completion of the Works was delayed by numerous factors such as,
inter alia, the requisite building plans were not approved
on time as
the applications for rezoning, subdivision and consolidation of the
properties on which the Works had to be performed
was not timeously
attended to, recorded or registered by the plaintiff.
”
7.8
By deleting paragraph 52 thereof and by replacing it with:
“
52.
Secondly, any defects to or problems with the video screen wall, and
any remedial work that had to be undertaken in that regard,
were not
occasioned by the conduct or omissions of the first defendant.
”
7.9
By deleting paragraph 56 thereof and by replacing it with:
“
56.
Thirdly, any damages allegedly suffered by the plaintiff were not
occasioned by the conduct or omissions of the first defendant.
”
[8]
In raising its objection to paragraph 7.1.1 above, the respondent
stated that Clause 12.2.4 (Part
C1: Agreements and Contract Data
clearly contained the words – Final settlement of dispute is by
litigation, whereas Clause
12.1.2 states that the interim settlement
of disputes is to be by mediation.)
[1]
The proposed amendment is incomplete and inconsistent with the
wording of Clause 12.2.4 of the Contract Data. Such
an
amendment is impermissible to effect and would be prejudicial to the
respondent.
[9]
With regard to paragraph 7.1.2 above, it was stated that Clause
12.2.4 of the Contract Data contains
the words, “or final
settlement by litigation” after the word, ‘mediation.’
The proposed amendment
is incomplete and inconsistent with the
wording of Clause 12.2.4 of the Contract Data. It is therefore
impermissible to effect
an amendment which is prejudicial to the
respondent.
[10] In
respect of paragraph 7.1.3, the respondent objected on the fact that
there is no basis to amend the existing
prayer. The existing
prayer should remain since it specifically refers to a resolution of
the plaintiff’s claim in
terms of Clause 12 of the Conditions
which provides for final settlement by litigation as per Clause
12.2.4 of the Contract Data.
The proposed amendment is
prejudicial to the respondent since it seeks to circumvent the
resolution of the matter by litigation,
as expressly regulated in
Clause 12.2.4 of the Contract Data.
[11]
The respondent objected to the proposed amendment of the applicant’s
plea and stated that, paragraph
7.2.1 above, by the applicant seeks
to withdraw an admission previously made, and that is prejudicial to
the respondent.
With regard to paragraph 7.2.2 above, the
applicant has already identified Alwyn Laubscher as the party in the
joint venture (JV)
appointed as the principal agent in terms of the
Works. The applicant, now seeks to retract that admission.
The amendment
sought is impermissible and therefore prejudicial to
the respondent.
[12] In
its objection to paragraph 7.4 above, the respondent stated that in
paragraph 41 of its plea, the applicant
has already identified either
the sixth defendant,
alternatively
, the third defendant,
alternatively
, both of them, as the parties liable and now it
seeks to retract this admission which is prejudicial to the
respondent. In
paragraph 42 of its plea, the applicant has
admitted the allegations pleaded to and now seeks to withdraw its
admission.
The withdrawal of the admission is prejudicial to
the respondent. In paragraph 43 of its plea, the applicant has
already
identified either the sixth defendant,
alternatively
the third defendant,
alternatively
both of them, as the
parties liable and now seeks to retract this admission which is
prejudicial to the respondent.
[13] In
so far as paragraph 7.5 above is concerned, the respondent, at the
hearing of this matter pointed out
that it does not oppose this
proposed amendment.
[14]
With regard to paragraph 7.6 above, the respondent pointed out that
the applicant has already pleaded to
this paragraph and save for the
denial that it was negligent or breached any of its obligations and
duties to the respondent, the
remaining allegations were admitted.
The applicant’s attempts to further qualify this paragraph is
impermissible and
prejudicial to the respondent. In fact, the
unamended paragraph 37 of the respondent’s particulars of claim
read exactly
the same as its amended particulars of claim except for
the word, ‘negligence’ and this does not constitute a
basis
for the applicant to amend.
[15]
Regarding paragraph 7.7 above, the respondent pointed out that the
applicant has already pleaded to this
paragraph. However, it
now seeks to amend in circumstances where the respondent has not
amended its particulars of claim.
The proposed amendment is
prejudicial to the respondent.
[16]
The respondent’s objection to paragraph 7.8 was premised on the
fact that paragraph 52 of the applicant’s
plea has already
identified either the sixth defendant,
alternatively
, the
third defendant,
alternatively,
both of them as the parties
liable. However, it now seeks to retract this admission which
is prejudicial to the respondent.
[17]
Lastly, in relation to paragraph 7.9 above, the respondent stated
that paragraph 56 of the applicant’s
plea, already identified
either the sixth defendant,
alternatively
, the third
respondent
, alternatively
, both of them as the parties liable
and now the applicant seeks to retract this admission. That is
prejudicial to the respondent.
[18]
However, at the hearing of this application, the applicant indicated
that it no longer seeks relief with
regard to paragraph 7.4, 7.8 and
7.9 above.
Discussion
[19]
The general approach to be adopted in application for amendment has
been set out in numerous authorities.
However, the Court in
Commercial
Union Assurance Co Ltd v Waymark NO,
[2]
has set out clearly in its headnote the principles governing
applications for amendment of pleadings as follows:
19.1
The court has a discretion whether to grant or refuse an amendment;
19.2
An amendment cannot be granted for the mere asking; some explanation
must be offered therefor;
19.3
The applicant must show prima facie the amendment ‘has
something deserving of consideration, a triable
issue.’
19.4
The modern tendency lies in favour of an amendment if such
‘facilitates the proper ventilation of the
dispute between the
parties’;
19.5
The party seeking the amendment must not be mala fide;
19.6
The amendment must not ‘cause an injustice to the other side
which cannot be compensated by costs;
19.7
The amendment should not be refused simply to punish the applicant
for neglect.
19.8
A mere loss of (the opportunity of gaining) time is no reason, in
itself, for refusing the application.
19.9
If the amendment is not sought timeously, some reason must be given
for the delay.
[20]
The applicant postulates that the respondent’s objections to
its proposed amendments are nonsensical
as they are without merit.
For instance, in their first proposed amendment, the applicant
suggests that the settlement of
their dispute should be by way of
mediation. The respondent pointed out to the applicant that it
cannot be, as resolution
of disputes by way of mediation, is reserved
for ‘a settlement of interim disputes.’ The dispute
such as the
one the applicant pleads to is final in nature, and
therefore adjudication and / or litigation is the route to take.
[21] In
addition, the respondent asserted that amendments are not simply
there for the mere taking. A party
seeking an amendment must
make out a case therefore. The applicant has failed to do so.
It will suffer irreparable
prejudice should the amendments be
granted.
[22]
The applicant asserted that the respondent had repeated complaints
that it will suffer prejudice. It
has failed to explain before
this Court how it would suffer such prejudice.
[23]
The respondent stated that prejudice has been interpreted as “
the
fact that an amendment may cause the other party to lose his case
against the party seeking the amendment, is not in itself
‘prejudice’
of the sort which will dissuade the court from granting it.
”
Thus, the fact that the effect of allowing an amendment to a plea
might be to defeat the plaintiff’s claim is
not what is meant
by ‘prejudice’ which cannot be remedied by an appropriate
order of cost. There may, however,
be cases where no terms
would overcome the prejudice which the amendment would cause to the
other party. For example, an
amendment will not be allowed
where it is applied for at such a late stage in the proceedings and
not timeously raised to enable
proper investigation and response
thereto.
[3]
[24]
For instance, it was said, the applicant attempted to withdraw
admissions without any explanation and therefore
borders on
mala
fide
conduct. The proposed amendments do not have as their
purpose the facilitation of the proper ventilation of the issues
between
the parties. Should the proposed amendments be granted
it would cause an injustice to the respondent which cannot be
compensated
by an award of costs and the parties will not be put back
into the position in which they were when the pleading it is sought
to
be amended was filed. Even so, none of the proposed
amendments are consequential upon the respondent having amended its
particulars
of claim.
Analysis
[25]
It is trite that the granting or refusal of an application for the
amendment of a pleading is a matter for
the discretion of the court,
to be exercised judicially in light of all the facts and
circumstances before it.
[4]
An amendment will be held to cause injustice to the other side which
cannot be compensated by costs if the parties cannot
be put back for
the purpose of justice in the same position as they were in when the
pleading it is sought to amend was filed.
[5]
[26] It
is common cause that each case has to be determined on its own
merits. The respondent submitted
that this is a classical case
where amendments, if granted would cause immeasurable prejudice and
will result in an injustice.
The
first
complaint by the
respondent is that the applicant seeks to divert this matter to
mediation proceedings, even though the dispute
is not an interim
one. A dispute would be interim in nature if the Works were
still ongoing and / or continuing. In
a situation where the
Works have been finalised and the respondent now seeks to recoup its
damages, it cannot be said that this
matter should be directed to
mediation. The applicant, by asking for those amendments, seeks
to delay the dispute unnecessarily.
The
second
complaint
is that, the applicant has all but admitted liability and now seeks
to resile therefrom. A party seeking to withdraw
an admission
ought to explain why it wishes to do so and if the other party has
objected to them, it may only be withdrawn with
the leave of the
court.
[27]
The applicant appears to downplay the seriousness of the consequences
to be caused should the proposed amendments
be granted. In
fact, the applicant denies that it made some admissions in its
previous plea. The applicant simply stated
that it intended to
make some rectifications in its plea.
[28]
In fact, I agree with the respondent that what the applicant seeks to
rectify, is in fact a withdrawal of
admission. In
President
– Versekeringsmaatskappy Bpk V Moodley
[6]
,
Hiemstra J opined that “…
though
the approach is the same, the withdrawal of an admission is usually
more difficult to achieve because it involves a change
of front which
requires full explanation to convince the Court of the bona fides
thereof and it is more likely to prejudice the
other party, who had
by the admission been led to believe that he need not prove the
relevant fact and might for that reason have
omitted to gather the
necessary evidence.
”
[29] In
any event, the applicant did not dispute the fact that none of the
amendments are consequential upon the
respondent having amended its
particulars of claim. That is a clear indication that the
applicant simply decided to change
its tact on how it formulated its
defences. The fact that there was no explanation on why these
admissions were withdrawn
demonstrates that the withdrawal of those
admissions was
mala fide.
It does not assist the
applicant to dispute that there was no withdrawal of admissions where
clearly there is.
[30] If
regard is to be had to the original particulars of claim and amended
particulars of claim, the amendments
were insignificant and a large
portion of the original particulars of claim was left unaltered.
In any event, the respondent
denied that the applicant merely sought
to rectify its plea. For instance, the applicant admitted
liability on the part of
the third, and the sixth respondents.
According to the respondent that admission is dispositive of any
defence to the respondent’s
action since on the applicant’s
version the third defendant (and therefore the JV) and the sixth
defendant were the parties
liable for the respondent’s claim.
If those proposed amendments were to be allowed to go through, that
would cause
great prejudice to the respondent. It was said that
the admissions made by the applicant rendered it unnecessary for the
City to prove admitted facts and to lead unnecessary evidence.
As the applicant’s plea is currently framed, there is
no
defence to the respondent’s claim in light of the admissions
made.
[31]
With regard to the amendment of special plea and conditional special
plea (paragraph 1 (1.1-1-3)).
The respondent stated that the
amendment sought is at odds with the wording of the Contract Data.
The resolution of disputes
is contained in the Contract Data and it
does not only refer to “mediation.” The applicant
states that the interim
settlement of disputes was to be by way of
mediation. Since the date of practical completion of the
contract was 17 July
2019, it is therefore common cause that the date
for resolution by mediation referred to has passed. As
mediation was no
longer applicable, the only manner in which the City
could recover its damages as recorded by Clause 12.2.4 on page 68 of
the Contract
Data, is by litigation. Further, had the matter
proceeded to mediation, the respondent’s claim may have become
prescribed
causing further prejudice to the respondents. The
mediation narrative by the applicant is a dilatory tactic to avoid
having
to pay damages for as long as possible. The respondent
was absolutely correct in its analysis of the applicant’s
behaviour
towards its claim.
[32] In
any event, the respondent’s claim was not determinable at the
time the Works were ongoing for submission
of the same for mediation,
adjudication and / or arbitration. It was correctly pointed out that
the respondent’s assessed
loss could only be determined on
practical completion of the contract. This contention, in my
view has merit as the final
settlement of the dispute as contained in
Clause 12.2.4 of the Contract Data, page 68 is by way of litigation.
In my opinion,
this amendment must fail.
[33] In
so far as the amendment of paragraph 15 and 23 of the plea is
concerned, that is paragraph 7.2 (7.2.1
and 7.2.2) above (paragraphs
2. 2.1-2.2), the applicant denies that the Services Contract was
extended. However, the respondent
submitted that the practical
completion date was 17 July 2019. However, in its amended
particulars of claim, paragraph 13
and 13.2, it stated that the
applicant, in its first tender, it acknowledged that it would be
responsible for all professional
services required to fulfil the
respondent’s objectives as advertised therein. The
termination clause made it clear
that the applicant would only cease
when “
all obligations and rights of the Joint Venture and
the Members in connection with the Contract and the Agreement have
ceased.
”
[34]
The respondent stated that in its plea the applicant alleged that the
third and sixth defendants are liable
as per the stated reasons.
This was an outright admission in the plea which it now seeks to
qualify in circumstances where
there is no basis to deny the
extension of the services contract.
[35]
This Court agrees that the applicant’s amendment is tantamount
to a withdrawal of an admission that
was previously made in the
plea. Even though the applicant seeks to argue that the
extension of the contract was not previously
pleaded in the
particulars of claim, the respondent deemed it fit to amend its
particulars of claim to include the extension of
the Contract.
Once more, it does not assist the applicant to state that the initial
particulars of claim did not contain
such allegation. The
particulars of claim have been amended without any objection from the
applicant. What was required
from the applicant, if it intended
to withdraw the admission was to properly motivate and justify such
withdrawal – See
Janisch
(Pty) Ltd v W M Spilhaus & Co (WP) (Pty) Ltd.
[7]
In
President-Versekeringsmaatskappy
Bpk v Moodley (supra)
[8]
Hiemstra J held that a withdrawal requires full explanations ‘to
convince the Court of the
bona
fides
thereof.’
[36] In
my view, it does not suffice for the applicant to simply say it
sought to rectify its plea of its inaccuracy
or mistake. It
appears that in making such submission, it should explain
satisfactorily the basis of such inaccuracies and
mistakes and the
reasons of such withdrawal. In the absence of such full and /
or satisfactory explanation, it follows that
the amendment should
fail.
[37]
With regard to the proposed amendment in 7.3 above (paragraph 2.3),
the respondent persisted that the factual
position is that Alwyn
Laubscher of the fourth defendant was appointed as the principal
agent in respect of the Works. The
applicant having pleaded so,
now impermissibly seeks to retract this allegation without providing
any reasons for doing so.
The applicant, as a member of Ebesa
JV, it must have knowledge of the identity of the principal agent.
I agree with the respondent
that no explanation as to why it was
mistakenly pleaded that Alwyn Laubscher was appointed as the
principal agent. Likewise, this
amendment constitutes a withdrawal of
an admission.
[38]
The applicant advised that it did not persist with its application
for amendment of paragraph 7.4, 7.8 and
7.9 above (paragraphs 2.4,
2.8, and 2.9), and as such it would not be necessary to deal with
them.
[39]
With regard to the proposed amendment in 7.5 above (paragraph 2.5),
it appears that the respondent does not
challenge this amendment.
As such, I see no reason it could not be granted.
[40] In
so far as the amendment in 7.6 and 7.7 above (paragraphs 2.6 and 2.7)
relates to the withdrawal of admissions,
regard should be had to my
analysis at paragraphs 35 and 36 above. For these reasons, this
amendment should fail.
[41]
In
Amod
v South African Mutual Fire and General Insurance Co Ltd,
[9]
Leon J held that, ‘the Court must also consider the question of
prejudice to the other party. If the result of allowing
the
admission to be withdrawn will cause prejudice or injustice to the
other party to the extent that a special order as to costs
will not
compensate him, then the application to amend will be refused.
[42]
The respondent submitted that if this Court would allow these
amendments, then it would be put in a burden
of proving facts which
it would not otherwise have to do. That in itself would cause
prejudice to the respondent. Prejudice
in Oxford Dictionary
refers to “harm or injury that results or may result from some
action.”
[43] In
conclusion, the applicant did not explain fully why it sought the
amendments in its application for amendment.
Its assertion that
it sought to rectify and / or correct its conditional special plea
and plea is not satisfactory. Moreover,
it sought to amend its
pleadings in circumstances where the respondent did not amend its
particulars of claim, in some portions
where it seeks to amend its
plea. Clearly, these proposed amendments constitute a change of tact
after the applicant realised that
there were no defences put forward
in the original plea. The applicant cannot be permitted a
second round of pleading where
no explanation has been put forward.
I therefore find no merit in the proposed amendments.
[44] In
the result, I make the following order:
44.1
The amendment in paragraphs 1 (1.1 – 1.3) of Conditional
Special Plea is refused.
44.2
The amendment in paragraphs 2 (2.1 – 2.3) of the Plea is
refused.
44.3
The amendment in paragraphs 2.4, 2.8 and 2.9 was abandoned by the
applicant. The plea in these paragraphs
will remain in its original
form.
44.4
The amendment in paragraph 2.5 is granted.
44.5
The amendment in paragraphs 2.6 and 2.7 is refused.
44.6 To
the extent that the applicant succeeded in one prayer and the rest
were refused, it should ordinarily
bear the costs of this
application. The applicant is ordered to pay the respondent’s
costs.
MANTAME
J
WESTERN CAPE HIGH
COURT
[1]
Record
page 57
[2]
1995
(2) SA 73 (TK)
[3]
Van
Loggerenberg, DE, Erasmus Superior Court Practice, Vol. 2 2
nd
Ed, at D1 - 334
[4]
Brocsand
(Pty) Ltd v Tip Trans Resources & Others 2021(5) SA 457 (SCA)
para 15 at 463A
[5]
Moolman
v Estate Moolman & Another
1927 CPD 27
at 29. South British
Insurance Co Ltd v Glisson 1963 (1) 289 (D) at 295H; YB vs SB &
Others NNO
2016 (1) SA 47
(WCC) para 10 at 51 A-B
[6]
1964
(4) SA 109 (T)
[7]
1992
(1) SA 167
(C) at 170
[8]
Ibid,
Fn 6 at 110 H – 111 A
[9]
1971
(2) SA 611
(N) at 614 H – 615 A
sino noindex
make_database footer start
Similar Cases
EBESA Architects (Pty) Ltd v City of Cape Town (A143/2024) [2025] ZAWCHC 318 (9 April 2025)
[2025] ZAWCHC 318High Court of South Africa (Western Cape Division)99% similar
EBS International (Pty) Ltd and Another v Wright (19128 / 2020) [2022] ZAWCHC 69 (9 May 2022)
[2022] ZAWCHC 69High Court of South Africa (Western Cape Division)98% similar
Sakhana Construction CC v Strand Junction Retail (Pty) Limited (4219/2022) [2022] ZAWCHC 225 (3 November 2022)
[2022] ZAWCHC 225High Court of South Africa (Western Cape Division)98% similar
J.G.S v S.E.S and Others (Appeal) (A283/2024) [2025] ZAWCHC 543 (17 November 2025)
[2025] ZAWCHC 543High Court of South Africa (Western Cape Division)98% similar
H & I Civil & Building (Pty) Ltd and Another v City of Cape Town and Others (59/24) [2024] ZAWCHC 329 (18 October 2024)
[2024] ZAWCHC 329High Court of South Africa (Western Cape Division)98% similar