Case Law[2025] ZAKZDHC 37South Africa
Bless Joe Trading CC v Ethekwini Municipality (D7596/2020) [2025] ZAKZDHC 37 (11 June 2025)
High Court of South Africa (KwaZulu-Natal Division, Durban)
11 June 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Kwazulu-Natal High Court, Durban
South Africa: Kwazulu-Natal High Court, Durban
You are here:
SAFLII
>>
Databases
>>
South Africa: Kwazulu-Natal High Court, Durban
>>
2025
>>
[2025] ZAKZDHC 37
|
Noteup
|
LawCite
sino index
## Bless Joe Trading CC v Ethekwini Municipality (D7596/2020) [2025] ZAKZDHC 37 (11 June 2025)
Bless Joe Trading CC v Ethekwini Municipality (D7596/2020) [2025] ZAKZDHC 37 (11 June 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAKZDHC/Data/2025_37.html
sino date 11 June 2025
IN THE HIGH COURT OF
SOUTH AFRICA
KWAZULU-NATAL LOCAL
DIVISION, DURBAN
CASE
NO: D7596/2020
In
the matter between:
BLESS
JOE TRADING CC
PLAINTIFF
and
ETHEKWINI
MUNICIPALITY
DEFENDANT
ORDER
In
the premises the following order is made:
1.
The defendant is directed to pay the
market related amount of damages from 1 April 2020 to 17
March 2021 to the plaintiff
which the parties may agree upon or which
the plaintiff may prove.
2.
Interest on the agreed or proved amount
at the rate calculated from 1 April 2020 to date of final payment.
3.
The defendant is to pay the plaintiff’s
costs of the action, including the costs of two counsel, on scale C.
4.
The defendant’s counterclaim is
dismissed.
5.
The defendant is to pay the plaintiff’s
costs of the counterclaim, including costs of two counsel on scale C.
JUDGMENT
Mathenjwa
J
Introduction
[1]
The plaintiff initially brought an application against the defendant
for payment of invoices issued
by the plaintiff in respect of
services rendered in terms of a contract entered into between
the parties. The plaintiff further
claimed damages arising from the
defendant’s failure to restore possession of tents and ablution
facilities which were leased
by the plaintiff to the defendant to
accommodate displaced people.
[2]
On 22 February 2022 the matter came before Kruger J who referred it
to trial. Subsequently the
plaintiff delivered its declaration, the
defendant delivered a plea and the rules provided for in
the conduct of a
trial proceedings were applied. The
defendant further delivered a claim in
reconvention in terms of which it sought an order declaring invalid
the contract entered
into by the parties.
Historical
background
[3]
In April 2019 the defendant experienced devastating flooding
resulting in homelessness amongst
many people who occupied informal
accommodation. In line with its constitutional mandate to provide
shelter, more specifically
emergency housing, the defendant called
for quotations for the provision of temporary emergency accommodation
in the form of tents
and ablution facilities at Tehuis in Umlazi
Township. When calling for quotations the defendant deviated from the
normal procedures
provided for in its Supply Chain Management Policy
(SCM policy) in accordance with clause 36 thereof which
authorises deviation
from normal procurement procedures during
emergency or disaster situations.
[4]
The plaintiff submitted its bid for the provision of services in the
amount of R190 000 per
day for a period of 14 days. The bid
comprised of;
(a)
one quantity of 15 x 30 Marquees;
(b)
one quantity of 15 x 30 flooring;
(c)
eight public toilets;
(d)
six electricity; and
(e)
50 chairs.
The
plaintiff’s bid was successful and it subsequently provided
tent and ablution facilities which accommodated 150 people
at the
site.
[5]
The plaintiff continued to provide services in terms of the original
contract after the expiry
of 14 days. On 31 March 2020, the plaintiff
received an email from the defendant terminating the contract and
indicating that alternative
shelter would be arranged by the
defendant for the people who were occupying the plaintiff’s
tent and other facilities. However,
despite the defendant indicating
that the people would be placed in alternative shelter, the
plaintiff’s marquee and ablution
facilities were not removed
from the premises and the defendant did not provide alternative
accommodation for the people. The plaintiff
continued submitting
invoices for the provision of services to the defendant in
respect of its facilities which was used
by the occupants after
termination of the contract but the defendant failed to pay the
plaintiff’s invoices in respect of
services rendered after 31
March 2020 being the date on which the defendant terminated its
contract with the plaintiff. On the
date of institution of this
proceedings the plaintiff claims for payment of R73 008 000,
plus Vat at 15% and interest.
Issues
at the trial
[6]
The plaintiff called Mr Ndumiso Ndlela, member of the plaintiff
company, who testified that he
was called by one of the defendant’s
employees to come on site behind the Durban City Hall for a
tender briefing. He
attended the briefing together with other service
providers. He was told to submit quotations for a marquee and
ablution services
for 150 people who had been displaced due to the
flooding. He prepared the quotation and submitted it on the same
date. The following
day he was telephonically informed by
the defendant’s employee Ms Balungile Gasa that his bid was
successful
and he had to erect the marquee on site. The following
day, 27 April 2019 he put up the marquee and other facilities. Two
days
after he had erected the tent structure it rained and he was
asked by a municipal councillor Mr Mthembu who was in company of
other
people from the defendant’s disaster management
section to put up water proofing and carpeted flooring to accommodate
the rain. After adding the flooring to the quotation, the
plaintiff’s fees increased from R190 000 to R208
000
per day.
[7]
After the expiry of 14 days the plaintiff continued accommodating the
displaced people in its
tent because the defendant did not have
alternative shelter to accommodate the people. According to
Mr Ndlela the plaintiff
also provided other services to the displaced
people including food at its own cost with no charge to the
defendant. The defendant
continued to pay the plaintiff the amount of
R208 000 per day for services rendered even after the expiry of
14 days, which
was the time period agreed between the parties for the
provision of services. Subsequently Mr Ndlela received an email from
Mr
Ngubane, an employee of the defendant, informing him that
the agreement for provisions of services between the parties was
terminated with effect from 31 March 2020.
[8]
Subsequently on 31 March 2020 Mr Ndlela went to the site to collect
the marquee and other equipment,
but was prevented by the occupants
of the tent from removing it, who angrily told him that they would
not relocate because the
defendant had not provided them with
alternative accommodation. On 27 May 2020 he received an email from
an employee of the defendant,
Mr Patel, asking him to reduce the
daily fee for rendering services by 40 percent to which he did
not agree. On 15 July 2020
he received an email from the defendant’s
attorneys requesting him to remove his tent and other equipment from
the site.
When he went to the site to remove the tent the occupants
again did not allow him to remove it and the equipment. He was
finally able to remove the equipment and the tent as well on17 March
2021 when he was assisted by the defendant who provided security
and
secured the presence of members of South African Police Services on
the site.
[9]
Under cross-examination by the defendant’s counsel Mr Ndlela
stated that he could not remember
the name of the person who called
him to attend the briefing on the site. However, on arrival at the
site he found Mr Mbhele, an
employee of the defendant, addressing the
people. Mr Mbhele told him that once he had completed the quotation
he had to deliver
it at the disaster section of the defendant. When
it was put to him by the defendant’s counsel that one of the
quotations
which he also delivered to Ms Gasa belonged to Crismarly
Trading Pty Ltd in which he was a former director, he
admitted
that he was a former direct of Crismarly, but he had sold it
to one Wiseman. When he was confronted with the fact that in
his quotation and invoice he charged the defendant R14 400 per day
for electricity whereas the electricity was connected to a hostel
where it was supplied by the defendant, he contended that he had an
informal agreement with the people from the hostel to pay them
for
the electricity which was connected to the hostel. When asked whether
he could produce a bill or invoice issued by the hostel
for the
electricity charge he contended that he would pay R5 000 cash
to the hostel for the duration of the contract but
he was not
officially billed for consumption of the electricity at the site.
[10]
When asked whether he informed the defendant that on 31 March 2020 he
was at the site to remove his equipment,
he responded that he did not
do so, neither did he phone the defendant whilst on site to inform it
that he was on site, nor did
he call the police to ask for assistance
because the occupants of the marquee were preventing him from
removing it. He made a second
attempt to remove the equipment on 27
July 2020 after he had received an email from the defendant’s
attorneys informing him
to remove his equipment from the site. When
he was informed by the defendant’s counsel that both employees
of the defendant,
Messrs Ngubane and Patel who were
administering the tender from the side of the defendant never dealt
or communicated with
him but they were communicating with a certain
Mr Msimango on all issues relating to the tender and therefore Ndlela
had no knowledge
of the issues he was testifying about in court, he
contended that he would be present at other meetings between Mr
Msimango and
the defendant’s employees.
[11]
The defendant called Ms Gasa who is the administration manager at the
defendant’s disaster management
unit to testify. She stated
that she received three quotations contained in one envelope that was
delivered by Mr Ndlela to her.
Her manager had phoned informing her
that someone would come and deliver the quotations. She stated that
when the defendant procures
services under an emergency situation
such as in the present circumstances it would call prospective
service providers either among
the service providers they had
previously worked with or ones who had provided similar services to a
provincial department. She
disputed that she called Mr Ndlela to
inform him that his bid was successful and she denied that she
negotiated the terms of the
contract with him. She did not receive
any other quotations other than Mr Ndlela.
[12]
Under cross-examination by the plaintiff’s counsel Ms Gasa
disputed that she communicated with Mr Ndlela
informing him
that his bid was successful but admitted that someone from the
defendant’s office would have phoned him. She
was consistent in
stating that she received the three quotations contained in one
envelop from Mr Ndlela. She confirmed that when
the tender was
awarded to Mr Ndlela during the state of disaster the provision of
clause 36 of the defendant’s
SCM policy on procurement
was properly applied.
[13]
Mr Patel Phalu, the head of the defendant’s department of
human settlement testified that on
31 March 2020 he received
instructions from Mr Ngubane informing him that the plaintiff’s
services with the defendant had
been terminated and he had to
ensure that the people occupying the plaintiff’s tent were
placed in another shelter.
On 31 March he could not relocate
the displaced people because there was no alternative accommodation
available, the country was
under lockdown level five and people were
not allowed to move. He continued looking for a place to move
the people for at
least a period of six months after 31 March 2020.
He also wrote to the plaintiff requesting a reduction of daily fees
because some
of the occupants of the tent had already moved
away from the site and returned to their original places. After the
negotiation
for a reduction failed Mr Patel informed Mr Msimango with
whom he was communicating that the defendant would not continue with
the original contract because the fees charged by the plaintiff was
extremely high.
[14]
Eventually the defendant built houses for the displaced community
about three kilometres away from the site
where they were
accommodated. On 17 March 2021, the people were moved and only then
did the plaintiff remove its tent and
other facilities from the
defendant’s site. Under cross-examination by the plaintiff’s
counsel Mr Patel
said that even if Mr Ndlela were to
remove the tent on 31 March 2020 the defendant would not have placed
the people in an alternative
accommodation because it did not have
such accommodation.
[15]
Therefore,
the issues for determination in this matter are:
(a)
Firstly, whether the continued occupation of the plaintiff’s
marquee and ablution facilities
by the displaced people who were
placed on the property in terms of the lease agreement between the
plaintiff and the defendant
after the termination of the lease
agreement constituted an act of holding over of the plaintiff's
property.
(b)
Secondly, if so, whether the defendant, being a sphere of government
responsible for providing
emergency accommodation to the
displaced people is liable to the plaintiff for the holding over of
its property by the displaced
people.
(c)
Finally, in arriving at a conclusion that the defendant is liable to
the plaintiff for the conduct
of the
displaced
people I have to determine whether the conduct of the
defendant either by omission or action made it practically
impossible
for the plaintiff to take possession of its property after
the termination of the lease agreement.
Analysis
[16]
The fierce debate between the parties was whether the plaintiff was
prevented by the occupants of the tent
to remove and take possession
of the tent. The defendant submitted that the plaintiff voluntarily
refrained from taking possession
of the tent for purposes of
continuing to charge the defendant exorbitant fees while the
displaced people remained
in occupation of the tent. It is worth
mentioning that the only witness called by the plaintiff to support
its version was evasive
and not impressive when answering questions.
However, in light of the evidence by the defendant’s own
witness that even if
the plaintiff was not prevented by the occupants
from removing the tent the defendant would not have moved the people
because there
was no alternative accommodation, the issue of whether
the people remained in the tent because they prevented the plaintiff
from
taking possession thereof has become academic.
[17]
Section 26 of the Constitution grants everyone the right of access to
adequate housing. It is trite that
the provision of emergency
accommodation by government forms part of this right and the
defendant as a sphere of government
is constitutionally obliged to
provide relief to people who are living in ‘intolerable
conditions or crisis situations’.
[1]
It is apposite that the plaintiff leased the tent and other
facilities to the defendant. This was in line with the
constitutional duty imposed on the defendant.
It is a trite principle of our law that ‘the hirer of an
article is obliged to return it in the same condition in which it
had
been at the outset of the period of hire’.
[2]
Therefore, it was incumbent upon the defendant to remove the people
from the tent at the expiration of the agreement to enable
the
plaintiff to take possession of the tent. The defendant, if it had
the will to remove the people from using the plaintiff’s
property, could have secured assistance from law enforcement
agencies. It is understandable that the defendant could not
remove
the people because it had no alternative accommodation to place
them. Therefore, it is the failure by the defendant
to remove
the people from the plaintiff’s tent and place them in
alternative accommodation that resulted in them occupying
the tent
after the defendant had terminated its agreement with the plaintiff.
[18]
It is common cause that the defendant initially informed the
plaintiff that the agreement for accommodating
the displaced people
was terminated with effect from 31 March 2020. It is not in dispute
that after 31 March 2020 the defendant
did not remove the people from
the tent because there was no alternative accommodation available.
Further, it is common cause that
the defendant had approached the
plaintiff for a new contract which would result in a reduction
of fees by 40 percent from
the original contract. The reason for the
reduction being that some of the people who had initially
occupied the property
had moved back to their original accommodation
and the number of people occupying the property had been reduced from
150 to
70. It is further common cause that the parties could
not agree on a new contract with reduced fees. Therefore, the
occupation
of the tent by the displaced people after the cancellation
of the contract constituted a holding over. The people held over the
tents and prevented the plaintiff from taking possession thereof.
[19]
The defendant’s instruction to the plaintiff to remove its tent
knowing that there was no alternative
accommodation to place the
people was a mockery. It is quite clear that the plaintiff would not
have been able to remove people
from the tent when the people did not
have alternative accommodation. If the defendant were genuine about
moving people from the
tent it would have assisted the plaintiff to
do so and make available an alternative accommodation for the
displaced people. I
do not agree with the argument that it was
not the plaintiff’s concern whether there was alternative
accommodation
for the people. This matter involves vulnerable
people who owing to their socio- economic conditions were exposed to
intolerable
conditions, at the peak of the COVID 19 pandemic. It
would not have been humanly possible for the plaintiff to remove them
from
the tent and leave them in an open space with no shelter
over their heads.
[20]
This case is distinguishable from a case where the lessor cancels the
contract and the lessee continues
occupying the leased property
after cancellation thereof. In that instance, the lessor would be
entitled to sue the lessee for
the past rental amount because the
lessee had not vacated the leased premises.
[3]
I agree with Hawthorne’s view that ‘termination of
the lease agreement causes the obligation to pay rent to be
replaced
with an obligation to return the leased thing’.
[4]
Therefore, in the present case where the lessee cancelled the
contract because it disagreed with its terms; attempted to negotiate
for a new contract on different terms; failed to reach agreement with
the lessor about the new contract, but holds
over the
leased property, the lessor’s claim against the lessee
is based on the conduct of the lessee in failing
to return the
leased property to the lessor after termination of the contract.
Consequently, the lessor is entitled to consequential
damages as a
result of the holding over of its property by the lessee.
[5]
[21]
Based on the evidence before court it is not disputed that in 2019
the plaintiff rendered services
to 150 people; in 2020
the number of people was reduced to 70. Thus, the people catered for
by the plaintiff was reduced
by more than a half. In the original
contract the plaintiff charged the defendant the amount of R14 400
daily for electricity consumption
at the site whereas the electricity
was connected at the hostel where it is supplied by the defendant. In
the event that it is
found that the plaintiff charged the defendant
for electricity for which it did not incur costs for its connection
to the site,
that is likely to reduce the daily fee for the
electricity. In the light of the above the court is not able to fix a
market related
costing for the parties because no information was
placed before court in respect thereof.
The
counterclaim
[22]
This brings me to the counterclaim. Regarding the contention by the
plaintiff’s counsel that the defendant
should not be condoned
for the late filing of its counterclaim it is instructive that
Uniform rule 24(1) requires a defendant to
deliver its counterclaim
together with the plea within the prescribed time frame. In the
present matter the plaintiff instituted
the action and the
defendant delivered its counterclaim at the same time with its plea
to the plaintiff’s declaration.
Therefore, the defendant acted
within the time frame prescribed by the rules for delivery of a
counterclaim. In this regard condonation
was not required by the
defendant.
[23]
The defendant’s counterclaim is broadly based on its failure to
comply with the provisions of s 217
of the Constitution, Preferential
Procurement Policy Framework Act
[6]
and SCM policy. A conclusion on whether the award of the
tender to the plaintiff was illegal should be based
on evidence
led before court. The version of the defendant’s own
witnesses is that the tender was awarded in terms
of its SCM
policy which allowed deviation from the normal tender process
during times of emergency and disaster.
It is the defendant’s
own version that neither the Constitution nor any legislation was
contravened when it procured the
plaintiff’s services.
[24]
Despite contending that all three quotations were
delivered by Mr Ndlela to Ms Gasa in one envelop,
the defendant does
not demonstrate how the delivery of three different quotations from
different bidders by one person contravened
the provisions of fair
and transparent procurement of services in terms of the Constitution
and legislation. Mr Ndlela is a former
director of one of the bidding
companies, but he is no longer the director of that company.
[25]
The court does not have to accept the
ipse dixit
of the
defendant’s witness, more particularly because corruption will
only occur if the defendant’s employees collude
with some of
the bidders. It is worth mentioning that particularities of the
tender such as the daily fee of R190 000
which was
ultimately increased to R208 000 for accommodating 150 people and
the daily fee of R14 400 for electricity
supply which was
allegedly connected at the hostel where it was supplied by the
defendant, may raise eye brows. However,
the defendant was in a good
position to investigate these issues and place evidence before court
regarding irregularities committed
during the procurement process,
if any. In light of the defendant’s own witnesses
confirming that the tender process
was correctly followed no
irregularities were committed, and in the absence of any evidence to
the contrary, this court has no
basis to conclude that the
award of the tender to the plaintiff during the state of disaster was
illegal. For that reason,
the counterclaim must fail.
Costs
[26]
There is no reason to deviate from the principle that costs should
follow the results. Therefore, in respect
of the main action the
defendant is liable to pay the plaintiff’s costs which include
the costs of the two counsel, on scale
C. The complexity of the
matter required the attention of two counsel, including senior
counsel. Likewise, the defendant should
bear the plaintiff’s
costs for the counterclaim.
Order
[27]
In the premises the following order is made:
1.
The defendant is directed to pay the
market related amount of damages from 1 April 2020 to 17 March
2021 to the plaintiff
which the parties may agree upon or which the
plaintiff may prove.
2.
Interest on the agreed or proved amount
at the rate calculated from 1 April 2020 to date of final payment.
3.
The defendant is to pay the plaintiff’s
costs of the action, including costs of two counsel, on scale C.
4.
The defendant’s counterclaim is
dismissed.
5.
The defendant is to pay the plaintiff’s
costs of the counterclaim, including costs of two counsel on scale C
.
Mathenjwa
J
Date
of hearing:
17, 18, 19 and 20 March 2025
Date
of judgment:
11 June 2025
Appearances:
Plaintiff’s
counsel:
Mr
I Pillay SC
Assisted
by:
Ms
Z Rasool
Instructed
by:
Anitha
D Chetty & Associate
Defendant’s
counsel:
Ms
K Shazi
Instructed
by:
Luthuli
Sithole Attorneys
[1]
Cape
Town City v Commando and Others
2023 (4) SA 465
(SCA) para 6.
[2]
Mutual
Construction Co (Tvl) (Pty) Ltd v Komati Dam
Joint
Venture
[2008] ZASCA 107
;
2009 (1) SA 464
(SCA) para 6.
[3]
Sapro v
Schlinkman
1948 (2) SA 637
(A) at 644.
[4]
L Hawthorne ‘The nature of the claim for holding over: South
African Law’
Fundamina
16 (2) 2010, 52 at 58.
[5]
Phil
Morkel Ltd v Lawson and Kirk (Pty) Ltd
1955 (3) SA 249
(C) at 254E-F.
[6]
Preferential
Procurement Policy Framework Act 5 of 2000
.
sino noindex
make_database footer start
Similar Cases
Talksure Trading (Pty) Ltd v Naidoo and Another (D4630/2021) [2023] ZAKZDHC 50 (28 July 2023)
[2023] ZAKZDHC 50High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar
Great Afro Trading CC t/a Somerset Cold Storage v Ports Regulator of South Africa and Another (D11098/2021) [2024] ZAKZDHC 71 (14 October 2024)
[2024] ZAKZDHC 71High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar
Sydwell Trading CC and Others v Sean Pillay and Company (Pty) Ltd (4581/2021) [2023] ZAKZDHC 24 (16 May 2023)
[2023] ZAKZDHC 24High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar
Ixia Trading 616 (Pty) Limited v Von Maltitz and Another (D8163/2024) [2024] ZAKZDHC 75 (18 October 2024)
[2024] ZAKZDHC 75High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar
Interlagos Trading (Pty) Ltd and Others v Sundale Free Range Dairy (Pty) Ltd (D8288/2024) [2025] ZAKZDHC 42 (11 July 2025)
[2025] ZAKZDHC 42High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar