Case Law[2025] ZAKZDHC 85South Africa
Vumani Civils CC v Ridgeside P4 Residential Estate (Pty) Ltd (D2259/2025) [2025] ZAKZDHC 85 (12 December 2025)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Kwazulu-Natal High Court, Durban
South Africa: Kwazulu-Natal High Court, Durban
You are here:
SAFLII
>>
Databases
>>
South Africa: Kwazulu-Natal High Court, Durban
>>
2025
>>
[2025] ZAKZDHC 85
|
Noteup
|
LawCite
sino index
## Vumani Civils CC v Ridgeside P4 Residential Estate (Pty) Ltd (D2259/2025) [2025] ZAKZDHC 85 (12 December 2025)
Vumani Civils CC v Ridgeside P4 Residential Estate (Pty) Ltd (D2259/2025) [2025] ZAKZDHC 85 (12 December 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAKZDHC/Data/2025_85.html
sino date 12 December 2025
IN THE HIGH COURT OF
SOUTH AFRICA
KWAZULU NATAL
LOCAL DIVISION, DURBAN
CASE NO.: D2259/2025
In the matter between:
VUMANI
CIVILS CC
Applicant
and
RIDGESIDE P4
RESIDENTIAL ESTATE (PTY) LTD
Respondent
JUDGMENT
Olsen
J:
[1]
This application
concerns the question as to whether the claims made
by the applicant, Vumani Civils CC, against the respondent, Ridgeside
P4 Residential
Estate (Pty) Ltd, have prescribed. The respondent
appointed the applicant as civils contractor for the construction of
the civil
engineering infrastructure required for a development known
as the Enigma Private Estate. This was done in August 2018. The
contract
was written and comprised, insofar as relevant to the
present proceedings, a document headed “Contract Data”,
which
is to be read with the General Conditions of Contract for
Construction Works, Third Edition (2015), issued by the South African
Institution of Civil Engineering.
[2]
Practical completion
of the works was achieved on 5
th
July
2019. The defects liability period expired, and, according to the
applicant, “factual” contractual completion
was achieved,
on or about 19
th
November 2020.
[3]
Clause 5.16.1
of the general conditions provided as follows.
“
5.16.1
The works shall not be considered as completed in all respects until
a final approval certificate
has been delivered by the employer’s
agent to the employer and the contractor stating the date on which
the works were completed
and defects corrected, all in accordance
with the contract.
Such final approval
certificate shall be delivered by the employer’s agent as soon
as practical after the completion of the
whole of the works, or the
expiration of the defects liability period, if such a period is
prescribed, or as soon thereafter as
any works ordered during such
period pursuant to clauses 5.14.4, 7.7 and 7.8 shall have been
completed in accordance with the contract.
Full effect shall be given
to this clause notwithstanding any previous entry on the permanent
works or the taking possession of,
working in or using thereof or any
part thereof, by the employer;
provided that the issue
of the final approval certificate shall not be a condition precedent
to the payment to the contractor of
the second half of the retention
money in accordance with clause 6.10.5.1 and 6.10.5.2.”
[4]
The final payment
certificate is intended to follow the issue of a
final approval certificate. The relevant clause is clause 6.10.9,
being a replacement
clause recorded in the contract data. It reads as
follows.
“
Within 14 days of
the date of final approval as stated in the final approval
certificate, the tenderer shall deliver to the engineer
a final
statement of all monies due to him (save in respect of matters in
dispute, in terms of clauses 10.3 to 10.11 and not yet
resolved). The
engineer shall within 14 days issue to the employer and the tenderer
a final payment certificate, the amount of
which shall be paid to the
tenderer within 30 days of the approval of the final payment
certificate by the employer, after which
no further payments shall be
due to the tenderer (save in respect of matters in dispute, in terms
of clauses 10.3 to 10.11 and
not yet resolved).”
[5]
The respondent’s
agent in terms of the contract was a firm of
consulting engineers, BMK Consulting Engineers. At some stage after
practical completion
of the works had been achieved the respondent
and BMK came to be in dispute with one another, as a result of which
BMK refused
to do any further work. That left the applicant without a
final approval certificate, and consequently without a final payment
certificate. This application was launched on or about 26 February
2025. The principal relief sought constituted orders directing
the
respondent to issue a final approval certificate and a final payment
certificate, and to make payment in accordance with the
final payment
certificate. In the alternative the applicant sought an order for
payment of a sum of R11 571 544.57 “in
terms of
Payment Certificate 4-Rev1 issued by the engineer”. The origin
of the alternative prayer will be apparent from the
brief account I
furnish of what transpired between about 2020 and the commencement of
the present proceedings.
[6]
According to
the founding affidavit in about February 2022, despite
the fact that it had not received a final approval certificate, the
applicant
delivered its final statement to “the engineer”,
indicating the applicant’s version of what the final payment
certificate would look like. The engineer concerned was DG Naidoo and
Associates, a firm of consulting engineers. Correspondence
put up
with the answering affidavit suggests that exchanges between the
applicant and DG Naidoo and Associates must have predated
February
2022. Nothing turns on that issue.
[7]
DG Naidoo and
Associates subsequently made an assessment of what
would be owing under a final payment certificate. It was rejected by
the applicant.
Further exchanges between the applicant and DG Naidoo
and Associates produced an assessment at a higher figure, being the
one of
some R11,5 million which is the subject of the applicant’s
alternative prayer in these proceedings. Although it is not stated
as
clearly as one would have thought it would be, as I understand the
answering affidavit the respondent does not agree with the
figures
produced by DG Naidoo and Associates.
[8]
The position
adopted by the respondent was made clear to the
applicant as early as February 2020 when a letter was sent to the
applicant containing
the following paragraphs.
“
6.
We are committed to settle the full amount due to Vumani
once
the work is certified as complete, and once the payment certificates
are duly certified
.
7.
We have instructed Dees Naidoo of DG Naidoo and Associates
to
conduct an audit of all of the work
undertaken by yourselves and that of BMK on the project.
8.
Regrettably BMK abandoned the work and refused to attend
to any
further work on our behalf. We had no alternative but to appoint an
independent engineer
to
assess and audit the work
.”
(My underlining.)
[9]
The respondent
adopted the same stance in its answering affidavit. It
pointed out that the applicant was wrong to present its exchanges
with DG
Naidoo and Associates as if that firm had been appointed as
the respondent’s agent in terms of the contract. It had been
appointed merely to audit work already done, and, presumably, the
claims made by the applicant as to what should be reflected in
a
final payment certificate. A confirmatory affidavit delivered by Mr
Naidoo of that firm confirms that it was not appointed as
the agent.
It did not replace BMK. In reply the applicant accepted that it may
have misunderstood the nature of the relationship
between the
respondent and DG Naidoo and Associates. Mr Voormolen SC, who argued
the case on behalf of the applicant, accordingly
directed his
submissions at the grant of the principal relief, namely the delivery
of the missing certificates. The prayer for
relief along those lines
was refined during the course of argument, inter alia to include an
order directing the respondent to
appoint a new agent under the
provisions of the contract, who would be empowered to consider the
issue of a final approval certificate
and a final payment
certificate. The respondent’s answer to that claim is that the
right to receive such certificates has
prescribed. It is indisputable
that very much more than three years has elapsed since those
certificates were due to have been
produced in whatever form they
ought properly to have taken.
[10]
Clause 3 of the general conditions
deals with the subject of the
employer’s agent. The appointee must be “a registered
professional in a built environment
profession that is appropriate to
the scope of work”. The function of the employer’s agent
is to administer the contract
as agent of the employer. Where the
agent is to exercise any discretion, or make or issue any ruling, he
is obliged to consult
with the contractor and the employer in an
attempt to reach agreement, and failing such agreement, to act
impartially and make
a decision in accordance with the contract.
[11]
No dispute has been raised over
the proposition that it is the
respondent’s right to appoint a new employer’s agent in
the event of the original appointee
failing for whatever reason to
take any further part in the administration of the contract. It was
not disputed in argument before
me that the right must be one coupled
with a duty to make an appointment. The contrary argument would imply
a right on the part
of the employer unilaterally to deprive the
contractor of its rights, the enforcement of which is dependant upon
decisions made
impartially through the exercise of the expertise of a
professional engineering consultant.
[12]
In terms of
s 10
of the
Prescription Act, 68 of 1969
, a “debt
shall be extinguished by prescription after the lapse of the period
which in terms of the relevant law applies in
respect of the
prescription of such debt.” In terms of
s 12
the prescriptive
period begins to run when the debt is due. The respondent’s
argument that the applicant’s claim for
the production of the
certificates has prescribed rests in the first instance upon the
proposition that the applicants right to
the professional assessment
and consequent issue of the certificates constitutes a “debt”
as contemplated by
section 10
of the
Prescription Act. The
applicant
argues that it does not.
[13]
In
Electricity Supply Commission v Stewarts and Lloyds of SA (Pty)
Ltd
1981 (3) SA 340
(A) at 344 the then Appellate Division
endorsed the proposition that a debt, for the purposes of the
Prescription Act, is
“that which is owed or due; anything (as
money, goods or services) which one person is under obligation to pay
or render
to another”.
[14]
However in
Desai N.O. v Desai and others
[1995] ZASCA 113
;
1996 (1) SA 141
(A),
the court held, after observing that the term “debt” is
not defined in the
Prescription Act, that
it has a “wide and
general meaning, and includes an obligation to do something or
refrain from doing something.” The
confusing aspect of that
judgment is that
Electricity Supply Commission
was cited as
one of the authorities for the proposition stated in
Desai
.
[15]
The issue was taken up
by the Constitutional Court in
Makate
v Vodacom Ltd
2016 (4) SA 121
(CC) where the court was concerned
with a claim for an order compelling the defendant to negotiate
with the plaintiff on
the subject of reasonable remuneration. In
dealing with the issue of prescription the court held (at paragraph
93) as follows.
“
To the extent that
Desai
went beyond what was said in
Eskom
it was decided in error. There is nothing in
Eskom
that remotely suggests that ‘debt’ includes every
obligation to do something or refrain from doing something, apart
from payment or delivery.”
[16]
The question here is whether
the contractual obligation of the
respondent to see to the appointment of an employer’s agent
under the contract, and consequently
the production of the two
certificates in question, constitutes a ‘debt’, in the
sense that it should be regarded as
an obligation in the nature of
money, goods or services to be paid, delivered or rendered by the
respondent to or for the applicant.
In my view the obligation does
not fall into that category. The obligation here is to maintain and
observe the structural regime
laid down by the contract for its
implementation. No delivery of money or service is required of the
respondent. The certificates
in question are to be produced by an
independent third party. What is required of the respondent is that
it should play its part
in ensuring that such a person is in office,
and able to perform the functions required of him or her, including
the assessment
of the need for and the content of the two
certificates the applicant requires before it can pursue a claim for
payment against
the respondent.
[17]
Ms Ploos van Amstel for the
respondent sought to counter the
conclusion that the principal relief sought by the applicant does not
constitute a debt capable
of prescribing, by relying on the principle
applied in
Uitenhage Municipality v Molloy
[1997] ZASCA 112
;
1998 (2) SA 735
(SCA). In that case the court considered a claim by a worker for
remuneration for work performed by him on Sundays, and in overtime,
which work had been performed considerably in excess of three years
before the commencement of the proceedings to recover such
payment.
The worker resisted the proposition that his claim had prescribed
upon the basis that, although the payments making up
the claim were
due at the end of each month during which such work had been
performed, the debts were not “due” for
the purposes of
the
Prescription Act because
they were not then “recoverable”.
They were said not to be recoverable unless a certificate had been
issued to the
worker under
s 30(3)(a)
of the Basic Conditions of
Employment Act, 3 of 1983. Such a certificate had only been issued
shortly before the commencement of
the proceedings. An analysis by
the court of the provisions of the Basic Conditions of Employment
Act, 1983 led to the conclusion
that the debts were “due”
at the time the work had been performed, and that prescription had
commenced to run accordingly,
despite the fact that the certificate
in question had not yet been obtained.
[18]
The argument for the respondent,
as I understand it, is that the
final payment to the applicant was due not later than upon the
expiry, or shortly after the expiry,
of the defects liability period;
that such payment was clearly a debt as contemplated by the
Prescription Act; and
that the prescriptive period of three years
began to run from when the debt was due, whether or not the final
approval certificate
and the final payment certificate had been
issued. In the circumstances the claim for the certificates is
futile, as the purpose
of their production, (ultimately payment of
the balance of the contract price), is the enforcement of a claim
which has in the
meantime prescribed.
[19]
Two judgments cited in
Uitenhage Municipality
as authority for
the proposition applied there are instructive.
Benson and
another v Walters and Others
1981 (4) SA 42
(C) concerned the
need for an attorney and client bill to be taxed before an attorney
could sue its client for payment. It was
held that the need for
taxation did not delay the commencement of prescription. The
principle was put as follows.
“
Our courts have
consistently held that a creditor is not able by his own conduct to
postpone the commencement of prescription”.
The Master v I L Back
& Co Ltd
1983 (1) SA 986
(A) concerned the prescription of a
claim for Master’s fees in insolvent estates, which had to be
“assessed by the
Master”. All it took, once the gross
value of the estates had been established, was a little arithmetic to
establish the
amount payable. The principle was stated as follows.
“
If all that is
required to be done to render the debt payable is a unilateral act by
the creditor, the creditor cannot avoid the
incidence of prescription
by studiously refraining from performing that act.”
[20]
The majority judgment in
Trinity Asset Management (Pty) Ltd v
Grindstone Investments 132 (Pty) Ltd
2018 (1) SA 94
(CC)
furnishes another example of the principle. It concerned the question
as to when an obligation to repay a loan payable within
30 days of
demand is regarded as due for the purpose of the
Prescription Act.
The
judgment stressed that the creditor has the sole power to demand
performance at any time.
“
[105] It is
this fact – that the creditor has the exclusive power to demand
that performance be made when the creditor
so chooses – that
has given rise to the general rule applying to loans “payable
on demand”, namely that prescription
begins to run when the
debt arises, unless there is a clear indication to the contrary.”
[21]
In my view the soundness of
the respondent’s argument must be
determined in the light of the provisions of the contract.
[22]
The provisions of the contract
governing the final payment due to the
contractor are set out in clause 6.10.9. The clause contemplates a
process. The contractor
must deliver to the engineer a final
statement of the monies alleged to be due to the contractor. The
engineer must assess the
correctness of the claim and issue a final
payment certificate reflecting the engineer’s determination of
what is payable.
The next step in the process is approval of the
final payment certificate by the employer. Payment follows that.
However, in terms
of the clause this process for determining the
amount payable, and for fixing a time for payment, does not commence
until there
is final approval reflected in the final approval
certificate. Insofar as the final approval certificate is concerned,
clause 5.16.1
is clear.
“
The works shall
not be considered as completed in all respects until a final approval
certificate has been delivered by the employer’s
agent to the
employer…”.
The condition for the
commencement of the process for the determination of the final
payment due to the contractor is not completion
of the works, but the
expression of an opinion by the engineer that the works are complete.
They cannot be “considered as
completed” unless that
expression of opinion is reflected in the engineer’s final
approval certificate. If it is withheld,
because the engineer does
not support the view that the works are complete, there will be no
final payment certificate.
[23]
In those circumstances can it
be said that the facts of the present
matter fall into the same category as those considered in the
judgments referred to above?
Is there a unilateral act (or rather, a
unilateral omission) on the part of the applicant (ie the failure to
enforce the production
of the certificates earlier) which cannot be
allowed to delay the running of prescription in respect of the final
payment? I answer
these questions in the negative. The first point to
be made is that there is only one unilateral act (or rather omission)
which
has obstructed the determination of the amount which is payable
by the respondent to the applicant, and the rendering of the payment
of it due. It is the omission on the part of the respondent to
appoint a consulting engineer to the office of employer’s
agent. Even if the respondent corrected that omission, a series of
determinations, two on the part of the appointed agent and one
on the
part of the respondent itself, would be necessary in order to reach a
determination as to what is payable by the respondent
to the
applicant for completion of the works. It is not actual completion,
but certified completion which would set in motion the
further
assessments by each of the engineer and the respondent as to what is
payable. The determination of the right to a final
payment
certificate, and the quantum of it, can hardly be classified as mere
“procedural conditions” (see
Uitenhage Municipality
at 741); or as the equivalent of the submission of a bill for
taxation (see
Benson)
; or as the simple arithmetic exercise to
be performed by the creditor in
The Master v I L Back and Co Ltd
.
[24]
The institution of the present
proceedings, the delay in which the
respondent argues is a unilateral act which should not be recognised
as a legitimate obstruction
to the commencement of the running of
prescription on the ultimate claim for payment, only opens the way to
implementation of the
contractual provisions which would ultimately
determine whether the applicant is entitled to a final approval
certificate because
the works are complete; and what the amount of
that payment should be.
[25]
I accordingly conclude that
prescription is not an obstacle to the
grant of the principal relief sought by the applicant. I make the
following order.
1.
The respondent is directed to appoint an “Employer’s
Agent” as contemplated in clause 1.1.1.16 of the General
Conditions of Contract for Construction Works published by the South
African Institution of Civil Engineering (2015, Third Edition)
(the
“GCC”) within 30 days of the date of this order and shall
notify the applicant as contemplated in that clause.
2.
The respondent shall do all things necessary on its part to enable
the Employer’s Agent thus appointed to
(a)
deliver
the final approval certificate in terms of clause 5.16.1 of the GCC;
(b)
issue
the final payment certificate in terms of clause 6.10.9 of the
contract data in the GCC.
3.
The respondent shall thereafter make a decision whether or not to
approve the final payment certificate as contemplated in clause
6.10.9 of the GCC contract data, within 30 days of the final payment
certificate being issued, and notify the applicant of its
decision
forthwith.
4.
If the respondent approves the final certificate it shall pay the
amount thereof to the applicant within 30 days of such approval.
5.
The respondent shall pay the costs of this application, and
counsel’s fees may be taxed on scale C.
Olsen
J
Case
Information:
Date
of hearing:
3 November 2025
Date
of Judgment:
12 December 2025
Counsel
for the Applicant:
A V Voormolen SC
Instructed
by:
NCA Attorneys
8 Sinembe Park
La Lucia Ridge Office
Estate
REF: T
Naidoo/DRamuther/R174L
Tel: 031 566 5271
Email:
theveena@nca-attorneys.co.za
;
litigation1@nca-attorneys.co.za
Counsel
for the Respondent:
Z Ploos van Amstel
Instructed
by:
Cox Yeats Attorneys
Ncondo Chambers
Vuna Close
Umhlanga Ridge, Durban
Ref: 069V00800000008
Tel: 031 536 8500
Email:
sjames@coxyeats.co.za
;
tgovender@coxyeats.co.za
;
cpretorrius@coxyeats.co.za
sino noindex
make_database footer start
Similar Cases
W.S v N. V (D376/2020 ; D1062/2021) [2025] ZAKZDHC 35 (6 June 2025)
[2025] ZAKZDHC 35High Court of South Africa (KwaZulu-Natal Division, Durban)97% similar
S v Ndlovu and Others (CCD46/2019) [2023] ZAKZDHC 20 (26 April 2023)
[2023] ZAKZDHC 20High Court of South Africa (KwaZulu-Natal Division, Durban)97% similar
VZ Contractors CC v King Cetshwayo District Municipality and Others (5056/2021) [2023] ZAKZDHC 72 (9 March 2023)
[2023] ZAKZDHC 72High Court of South Africa (KwaZulu-Natal Division, Durban)97% similar
Vea Road Maintenance and Civils (Pty) Ltd v South African National Roads Agency SOC Limited and Another (D7913/2023) [2023] ZAKZDHC 87 (20 November 2023)
[2023] ZAKZDHC 87High Court of South Africa (KwaZulu-Natal Division, Durban)97% similar
S v Majola and Others (CC D13/2024) [2025] ZAKZDHC 40 (20 June 2025)
[2025] ZAKZDHC 40High Court of South Africa (KwaZulu-Natal Division, Durban)97% similar