Case LawGhana
SMITHCROWN GHANA LTD VS AVNASH INDUSTRIES GHANA LTD. (H1/156/2019) [2022] GHACA 169 (15 December 2022)
Court of Appeal of Ghana
15 December 2022
Judgment
IN THE SUPERIOUR COURT OF JUDICATURE
IN THE COURT OF APPEAL
ACCRA-GHANA
CORAM: ADJEI, J.A
MERLEY, J.A
BAAH, J.A
SUIT NO.H1/156/2019
Date: 15th December,2022
SMITHCROWN GHANA LTD. ---- PLAINTIFF/APPELLANT
VRS.
AVNASH INDUSTRIES GHANA LTD. -- DEFENDANT/RESPONDENT
J U D G M E N T
ADJEI, J.A:
1
The Plaintiff/Appellant dissatisfied with the decision of the High Accra, rendered on 18th
May, 2017 which dismissed all its reliefs as unproven filed an appeal against same to this
Court on 11th August, 2017. The trial Judge also dismissed the counterclaim filed by the
Defendant as unproven, but it did not appeal against the dismissal of its counterclaim.
The brief facts of the case were that the Defendant, which is a Ghanaian registered
company, awarded a contract through competitive bidding to the Plaintiff to construct a
rice mill at a place known as Changnayili in Tamale. The agreement between the parties
was governed by a written agreement executed on 12th November, 2021, and titled
"Contract Agreement for Civil, Structural, Mechanical, and Electrical Works for Rice
Plant at Village Changnayili Tamale." The above-mentioned agreement was admitted
into evidence as exhibit "C". There was another document containing the bills and
quantities for the project prepared by Secmec Consultants PVT Ltd., Architects and
Planners in association with Nel-Arc Consult and Beau Sackey & Associates Ltd., and
quantity surveyors dated October 2021, which was also admitted into evidence as exhibit
"D" Exhibit "D" is captioned exhibit "D".
The total project cost was Gh¢8,250,000.00 and was to be completed within four months
and two weeks, which were to be reckoned from the date of either the release of the
mobilization fund or from the date of handing over of the site, whichever was earlier. The
agreement further provided that if the work was delayed arising from reasons beyond
the control of the Plaintiff, and same is accepted by the Defendant, the Plaintiff could seek
an extension of time in writing from the Engineer - in - charge at the site, subject to the
final and binding decision of the Defendant on the matter.
The defect liability period is six months to be reckoned from the date of issue of certificate
of completion by the Engineer –in- charge. There was another proviso that should the
Plaintiff fail to complete the work and clear the site on or before the agreed schedule or
any extended date of completion, a penalty was to be paid at certain agreed rates.
2
The Plaintiff could not comply with the agreement entered into between the parties and
defaulted on most of the conditions. The Defendant equally breached some of the
conditions of the agreements.
The Plaintiff on 5th June, 2013 sued the Defendant for several reliefs including a
declaration that the agreement entered between them on 12th November, 2011 whose life
span was four and half months commencing from the date of the release of the
mobilization fund or from the date of handing over which one whichever was earlier was
in existence and was therefore entitled to some payments arising under same. The
Defendant resisted the Plaintiff’s claim and counterclaimed against it, inter alia, that the
Plaintiff was in breach of the agreement and was therefore entitled to damages against it.
The trial High Court Judge dismissed both the claim and counterclaim, which provoked
the appeal before this Court. The Plaintiff, dissatisfied with the decision of the trial High
Court, filed an appeal against same. The grounds of appeal are as follows:
“a. The judgment is against the weight of evidence.
b. The learned trial Judge erred in discounting the evidential value of Exhibit ‘E’
which error has occasioned the appellant a substantial miscarriage of justice.
c. The learned trial judge, with respect clearly erred in the face of crucial evidence
on record that the claim for the retained amount of Gh¢412,000.00 was not due
when he ironically but rightly had found that same was in the form of a bond
or security against defect liability.
d. The learned trial Judge grievously erred when he made a finding that the effect
of issuing certificates for payment under the contract for “Practical
Complexion” did not guarantee automatic and unimpeded payment if there
existed liability to be made good by Smithcrown.
3
e. The learned trial judge erred in making a finding that the job the appellant did
was riddled with several defects, in spite of overwhelming evidence on record
to the contrary, which error has occasioned the appellant a substantial
miscarriage of justice.
f. The learned trial Judge grievously erred in holding that within the terms of the
agreement the Respondent (AVNASH) was justified in withholding the
payments for part of valuation “5” and the whole of valuation “6”.
g. The learned trial Judge erred, in his finding, contrary to overwhelming evidence
on record, that it was the poor workmanship that resulted in the collapse of
the steel structure and this error has inter alia occasioned the appellant a
substantial miscarriage of justice”.
We address ground (a) of the appeal, the omnibus ground of appeal, and we are required
to evaluate the entire evidence on record and correct all errors committed by the trial
High Court. We have to examine all the errors committed by the trial Court Judge in
respect of the evaluation of material evidence, which were improperly evaluated material
evidence not evaluated at all, legal issues that required factual evidence to be resolved
and were not properly resolved, and the improper application of the standard burden of
proof in accordance with the law and which has occasioned a miscarriage of justice.
The plethora of cases on the principle stated above include Owusu-Domena v. Amoah
[2015-2016] 1 SCGLR and Tuakwa v. Bosom [2001-2002] SCGLR 686. The Defendant
paid the mobilization fund to the Plaintiff on 7th December 2011 but the latter took
possession of same in the first week of January 2012, contrary to the agreement that which
provides that time was to be reckoned from the date of the release of the mobilization
advance or from the date the site was to be handed over to the contractor, whichever is
earlier.
4
Looking at the agreement, the four and a half months within which the contract was to
be executed commenced from 7th December, 2011, when the mobilization advance was
paid to the Plaintiff. There was a further condition that if there is a delay, the decision of
the Defendant on the issue shall be final and binding.
There was a penal provision in the agreement to ensure that the Plaintiff completed the
work on schedule. The Plaintiff was to pay a penalty of one (1) percent of the contract
value to the Defendant if it failed to complete the work and it delayed for one week; three
percent if it delayed for the second week; and five percent if it delayed beyond the second
week unless the time was extended by the Defendant.
The Plaintiff was required to submit the R/A Bills in a prescribed form on a monthly basis
on or before the date of every month fixed for the same, and the Defendant shall pay
same within seven working days after receipt of a certified bill from the Architect. The
parties, through their representatives, and the Architect, were to jointly measure the work
done on the 25th of each month upon a written request by the Plaintiff within a minimum
of 48 hours in advance. The Plaintiff contended that the work done was valued at
different stages and that valuation No. 5 was delayed and that full payment of same has
not been made by the Defendant.
Furthermore, as a result of the delay, payment for valuation 6 is still outstanding, and
according to the Plaintiff, several demands made for same have fallen on deaf ears. The
other outstanding payments to be made were in respect of the retention of GH¢404,500.00
and tax deductions of GH¢300,000 .00. The Defendant, in its evidence through James
Bentie, admitted that the outstanding balance to be paid on valuation 6 and part of
valuation 5 was GH¢918, 731.30, but it was not happy with the work done on valuations
5
5 and 6, even though they were certified by the engineers and architects appointed by the
Defendant on site.
Apart from the payments stated above, the Plaintiff was further claiming for an amount
of GH¢1.4 million, representing the loss of income from the other component of the work
the Defendant re-awarded to another contractor without its consent, and GH¢1.7 million
as special damages emanating from the cost of maintenance of equipment and money
spent on employees.
The Defendant in its evidence admitted that part of the external works which originally
formed part of the contract awarded to the Plaintiff were re-awarded to another
contractor, thereby reducing the value of the contract awarded to the Plaintiff from
GH¢8,250,000.00 to GH¢7,850,000.00. In June 2012, the Defendant further awarded a
contract to the Plaintiff to construct an international steel structure costing
GH¢2,253,612.05, bringing the total cost of the entire contract to GH¢10,103,612.05; which
the Plaintiff is required to prove that it executed the entire contract to enable it to claim
the entire amount.
During cross examination of the witness called by the Plaintiff, the Defendant suggested
to him that the amount of money payable to the Defendant was dependent upon the total
value of the contract executed by it, and the response was positive, and therefore put the
burden of proof on the Plaintiff to prove the work done by it. When Samuel Oloruntoba
was under cross-examination, the following questions were posed and answered
accordingly:
“Q. So this amount in essence means that you will be paid GH¢8,250,000.00
at the end of the contract.
6
A. Yes, either reduce or increase.
Q. At the end of the day the total amount you will receive will depend on
the total value of contract you executed, is that not it.
A. It is true
Q. So it means this contract is not lump necessarily a lump sum contract.
A. The contract is not lump sum contract it could decrease or increase.
Q. So it is true that the total amount to be paid is dependent on the total
work done and valued.
A. Yes, my lord.
Q. As you stand here you received a total of GH¢6,349,611.44.
A. I don’t know the actual amount but I know we have received something
like that.
Q. I am putting it to you that you have received a total of GH¢6,349,611.44.
A. I do not know the exact amount but I said we have received some amount
of money.
Q. You are saying that the contract is not completed as at now.
A. Exactly
Q. And you agree with me that the retention fee is paid at the end of the
contract.
A. Yes, my lord after six months.
Q. When there is no defect?
A. Yes my lord.”
Sections 11(4) and 12 of the Evidence Act, 1975 (N.R.C.D. 323) require the person who has
the burden of proof, such as the Plaintiff in an instant appeal, to prove its case on the
preponderance of probabilities. The cases on the above subject matter, including
Adwubeng v. Domfeh [1996-97] SCGLR 660 and Effisah v. Ansah [2005-2006] SCGLR
7
943, have crystallised the statutory position in sections 11(4) and 12 of the Evidence Act,
1975 (N.R.C.D. 323) that where the burden of proof in civil matters is on a party, that
party is required to prove its case by a preponderance of probabilities, and there is no
exception to this rule unless the issue to be resolved in a civil matter is of criminal nature,
such as fraud or forgery, which requires proof beyond a reasonable doubt. There is no
doubt that the work has been delayed, and as of now, the work has not been completed.
The Plaintiff attributed the late start of the contract to the Engineer appointed by the
Defendant. The Defendant’s representative in his evidence in chief stated in clear terms
that the delay was occasioned by the Defendant. He testified as follows:
" ..... The delay was caused by them because the site was not ready for the
construction work to start and because there was additional work on site. So, the
delay is coming from the Engineer."
There is overwhelming evidence on record that the Defendant paid the mobilization fund
to the Plaintiff on 7th December, 2011 and the Plaintiff delayed by going to the site as
agreed between them in the written contract until the first week in January 2012. The
clause 4 of the contract which was tendered as exhibit "D" on the commencement date
provides as follows:
"The time for completion for this project is 4.5 months and will be reckoned from
the date of the release of the mobilization advance or from the date of handing
over the site, whichever is earlier."
8
I am satisfied that the Plaintiff delayed the commencement of the project for barely a
month as the mobilization fund was paid to it on 7th December, 2011 and failed to prove
that the Defendant rather put in an impediment on its way to move unto the site.
From the evidence on record, particularly the evidence of the Plaintiff’s representative, it
is established that part of the structure collapsed when the project was still under
construction. The Plaintiff gave two reasons which occasioned the collapsed of the
structure and attributed it to storm and the fact that the construction was under
construction and was never completed due to lack of money to buy materials to complete
same. The Plaintiff’s representative testified on that issue under evidence in chief as
follows:
“Q. They also contend that your poor workmanship contributed to the collapse
of the entire scale structure leading to the delay of the entire project, what is
your reaction to that.
A .It is never true, my lord. The collapse was caused by two reasons:
"1. There was a storm at that time, and that was when we even had a plane crash
in Ghana in 2012.
2. It is because the construction was never completed and we were expecting
them to make payment on our valuation so that we can have some of these
materials to complete the work, but they did not pay. So, when the storm came,
it nearly collapsed the construction. So, if they had paid us early, we would have
finished the work. The agents were on site, and they never complained about
our work."
9
I find that the work was not completed by the Plaintiff’s own agent and was not therefore
entitled to the total cost of the contract sum. I dismiss ground (a) of the appeal as
unmeritorious, as the Plaintiff failed to prove that the trial High Court Judge committed
any factual or legal error in his evaluation of the evidence on record.
I find that exhibit "E" was issued by the Defendant’s site Engineer to award additional
contract to the Plaintiff to execute the internal structural steel works. There is evidence
on record that the internal structures constructed by the Plaintiff collapsed. The Plaintiff’s
representative under cross examination admitted that part of the internal structure
constructed by the Plaintiff collapsed but it was not all. Therefore, no payment would be
made on the internal structures until they are fixed and approved for payment.
On the whole, the Plaintiff did, in most cases, shoddy work as asserted by the Defendant
and was not entitled to payments until they were fixed, but the Plaintiff failed to adduce
evidence to prove that the other part of the contract for which it had not been paid went
through valuation and payments were not made. The agreement was that payments were
to be made by the Defendant to the Plaintiff depending on the work executed and valued,
and not in respect of the entire contract.
However, there is no evidence that the Plaintiff completed same and submitted the
valuation for payment, and I dismiss grounds (b), (d), (e), and (f) as unmeritorious. I must
say that grounds (b), (d), (e), and (f) of the appeal come under the omnibus ground of
appeal, and were largely discussed under it, and could have been dismissed under that
ground.
There are overwhelming evidence on record to the effect that the Plaintiff did not
complete the work and payment was made upon submission of valuation approved by
10
both parties. Furthermore, part of the structure collapsed as a result of shoddy work done
by the Defendant. The defendant's evidence stated above indicated that if the structure
had been completed, it would not have been demolished by the storm. The Plaintiff
should have protected the structure from collapsing by completing that part of the
structure that could not have withstood the storm.
I further dismiss ground (c) of the appeal as unmeritorious, as the Plaintiff’s witness
admitted that the retention fee is to be paid after six months at the end of the contract
where there is no defect. The work was not completed, and from the evidence, several
defects have been found by the Defendant, and the retention amount cannot be paid to
the Plaintiff.
I find as a whole that the Plaintiff, who has the burden to prove its case on the
preponderance of probabilities, failed to prove the actual work done by it, and the appeal
fails in its entirety. The Plaintiff failed to prove that it completed the work without defects
and was not paid, and further failed to prove that there were particular parts it completed
without defect and was paid for them. The Defendant was justified in failing to pay the
retention fee as the defects detected were not rectified and would have acted contrary to
their agreement. The Plaintiff is not entitled to the tax deducted by the Defendant from
the payments made, as the Defendant is mandated by law to withhold and pay the tax to
the Ghana Revenue Authority.
The Plaintiff’s representative, in his evidence in chief, made a demand for the sums of
GH¢404,500.00 and GH¢300,000.00 being retention fees and tax deductions, respectively,
and from the evidence on record, it was not entitled to any of them. He testified as
follows:
11
"Yes, we have a retention of GH¢404,500.00, and apart from that, we also had tax
deductions, and we did not receive the retention from the government, and it is
about GH¢300,000.00."
The Plaintiff failed to make a case for the retention of the amount claimed, as the evidence
on record disclosed that the defects were not corrected to satisfy the condition precedent
for payment of the retention to be made. Furthermore, the withholding taxes are
supposed to be paid on behalf of the Plaintiff to the Ghana Revenue Authority, and the
Defendant cannot claim ownership to it.
The uncontroverted evidence on record is that both parties breached the contract
executed between them, and the Plaintiff who initiated the breach and continued with it
shall not be entitled to damages for breach of contract. The Plaintiff, who is invoking
equity, has come before it with tainted hands.
I dismiss all the grounds of appeal filed by the Plaintiff. I affirm the judgment of the trial
High Court Judge delivered on 18th May, 2017 and dismiss the appeal in its entirety.
(SGD.)
DENNIS DOMINIC ADJEI
JUSTICE OF THE COURT OF APPEAL
(SGD.)
WOOD,J.A I agree MERLEY WOOD
JUSTICE OF THE COURT OF APPEAL
12
(SGD.)
BAAH,J.A I also agree ERIC BAAH
JUSTICE OF THE COURT OF APPEAL
COUNSEL
• C.K. KOKA FOR PLAINTIFF/APPELLANT
• CECIL TETTEY FOR DEFENDANT/RESPONDENT
13
Similar Cases
SAMUEL KWABENA OPOKU VS CARANA COPRATIONS (H1/123/23) [2023] GHACA 139 (13 July 2023)
Court of Appeal of Ghana83% similar
Addo Atuah & Co. v African Automobile Ltd. (J4/55/2020) [2025] GHASC 13 (19 March 2025)
Supreme Court of Ghana82% similar
JUSTICE Y. ABDULAI VS ECOBANK GH. LTD (H1/229/2020) [2023] GHACA 234 (9 March 2023)
Court of Appeal of Ghana82% similar
NTAADU VRS BOAKYE (J4/32/2024) [2024] GHASC 54 (11 November 2024)
Supreme Court of Ghana82% similar
WELBECK VRS ACHEAMPONG (J4/71/2023) [2024] GHASC 35 (10 July 2024)
Supreme Court of Ghana81% similar