Case Law[2026] KEHC 1400Kenya
Hunkar Trading Co Limited v Total Kenya Limited (Civil Suit 111 of 2017) [2026] KEHC 1400 (KLR) (Commercial and Tax) (13 February 2026) (Judgment)
High Court of Kenya
Judgment
Judgement Milimani HC Civil Suit No. 111 OF 2017
REPUBLIC OF KENYA
IN THE HIGH COURT OF KENYA AT MILIMANI
COMMERCIAL AND TAX DIVISION
CIVIL SUIT NO. 111 OF 2017
HUNKAR TRADING CO. LIMITED .................... PLAINTIFF
VERSUS
TOTAL KENYA LIMITED ................... DEFENDANT
JUDGEMENT
1. This matter involves a commercial dispute situated at the intersection of
contract law, the statutory regulation of the energy sector, and the common law
torts of detinue and conversion.
2. The Plaintiff approached this court by way of a Plaint dated 15 March 2017,
subsequently amended on 30 December 2020. The Plaintiff, a limited liability
company incorporated in Kenya, is engaged in the business of filling, trading,
and distributing LPG cylinders. The Plaintiff alleges that the Defendant, a
leading oil marketing multinational, illegally confiscated and detained 4,425 of
the Plaintiff’s LPG gas cylinders. The Plaintiff contends that this detention
constitutes an illegal seizure, detinue, trespass to goods, and economic
sabotage, effectively crippling its business operations by removing its essential
tools of trade from circulation.
3. The Plaintiff seeks the following reliefs against the Defendant:
(a) A mandatory injunction directing the Defendant to hand over all the
Plaintiff's cylinders it is holding, namely 2,528 6kg cylinders and 1,895
Page 1 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
13kg cylinders, after testing, verification, repairing, painting, and re-
validation at the Defendant's cost.
(b) An order for the Defendant to pay the costs of testing, verification, and
repair.
(c) In the alternative, judgment for the sum of Kshs. 14,588,093.75, being the
assessed replacement cost of the cylinders.
(d) A permanent injunction restraining the Defendant from withholding the
Plaintiff's cylinders.
(e) General damages for detinue, trespass to goods, economic sabotage, and
unfair trade practice.
(f) Interest and costs.
4. The Defendant entered appearance and filed a Statement of Defence and
Counterclaim dated 29 November 2017, which was subsequently amended on
18 June 2021. The Defendant admits to withholding the cylinders but vigorously
defends the action on the basis of a right of lien. The Defendant avers that the
Plaintiff is indebted to it in the sum of Kshs. 6,732,922.22, arising from cylinder
exchange deficits accumulated between 2014 and 2016. The Defendant
contends that under the common law and by virtue of the Plaintiff's
acquiescence, it was entitled to retain the cylinders until the outstanding debt
was fully extinguished.
5. By way of Counterclaim, the Defendant seeks judgment against the Plaintiff for
the sum of Kshs. 6,732,922.22 plus interest at commercial rates, and a
mandatory injunction compelling the Plaintiff to pay the outstanding sum.
6. The suit proceeded to hearing. The Plaintiff called Mr. Jackson Kariuki
Kahungura (PW1), its Chairman and Director, as its sole witness. The
Defendant called Ms. Soila Kigera (DW1), its Legal Officer, as its sole witness.
The Court has had the benefit of comprehensive trial bundles, witness
statements, and the submissions.
Page 2 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
Background
7. The dispute is anchored in the operations of the LPG Cylinder Exchange Pool,
a mechanism established under Regulation 14(1) of the Energy (Liquefied
Petroleum Gas) Regulations, 2009 (Legal Notice No. 121 of 2009). The
purpose of the pool was to facilitate the liberalization of the LPG market by
allowing consumers to exchange cylinders of any brand at any retail outlet,
thereby promoting competition and consumer convenience.
8. Both the Plaintiff and the Defendant were members of this Exchange Pool and
signatories to the LPG Cylinder Exchange Pool Agreement dated 1 February
2012 (hereinafter "the Agreement") and the associated LPG Cylinder Exchange
Pool Operations Procedures (hereinafter "the Operations Procedures").
9. Under the Agreement and Operations Procedures, the movement of cylinders
was strictly regulated. When a consumer returned an empty cylinder belonging
to Brand A, for example Hunkar, to a retail outlet owned by Brand B, for
example Total, Brand B was obligated to accept it. Brand B would then transport
the cylinder to a designated collection point. Brand A was then required to
collect its cylinders from the collection point within a specified timeframe. If
Brand B collected more of Brand A's cylinders than Brand A collected of Brand
B's, a financial deficit would arise. The clearinghouse mechanism required the
net deficit to be settled via invoice.
10. It is common ground that between June 2015 and March 2016, the Plaintiff
accumulated a significant deficit in its account with the Defendant. The
Defendant issued invoices which remained unpaid beyond the stipulated credit
period.
11. By a letter dated 10 March 2016, the Defendant wrote to the Plaintiff demanding
settlement of an outstanding balance of Kshs. 7,772,458.58, noting that Kshs.
Page 3 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
4,994,501.74 was overdue. The letter threatened legal action if payment was
not made within 14 days.
12. In response, the Plaintiff did not settle the debt in cash. Instead, it forwarded ten
post-dated cheques totalling approximately Kshs. 5.9 million to the Defendant.
These cheques were dated to mature between April 2016 and December
2016.
13. The Defendant, by a letter dated 6 April 2016, rejected this mode of payment.
The Defendant returned six of the post-dated cheques, arguing that the
Agreement required payment within 35 days of invoicing and that the issuance
of post-dated cheques spanning eight months was an impermissible unilateral
extension of the credit period. The Defendant demanded immediate payment
via current cheques or Electronic Funds Transfer (EFT).
14. Following the impasse, a meeting was held between the parties on 4 July
2016. Minutes or subsequent conduct indicate that during this meeting, the
Defendant informed the Plaintiff of its decision to withhold the Plaintiff’s
cylinders until the debt was fully settled. The Plaintiff’s witness, PW1, admitted
in cross-examination that he attended this meeting and came to an
arrangement regarding the holding of cylinders.
15. Consequently, the Defendant retained possession of 4,425 cylinders belonging
to the Plaintiff. The Plaintiff, despite admitting the existence of the debt (though
disputing the interest component), failed to clear the balance. Instead, on 16
March 2017, the Plaintiff instituted this suit, alleging that the retention of the
cylinders was illegal and claiming the replacement value of the goods.
The Plaintiff’s Case
16. The Plaintiff’s case is premised on the sanctity of the statutory and contractual
framework governing the Exchange Pool. PW1 submitted that the Agreement
provided a self-contained code for the handling of cylinders. He relied heavily
Page 4 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
on Clauses 12.6, 12.7, and 15 of the Agreement, which mandate that a member
holding another member’s cylinders must return them to a collection point within
7 days.
17. The Plaintiff argues that the Agreement provides specific penalties for non-
compliance, including monetary fines for holding cylinders beyond 14 days. The
Plaintiff contends that the Defendant’s resort to self-help by seizing cylinders to
enforce a debt was ultra vires the Agreement and constituted the tort of detinue.
18. On the debt, the Plaintiff admits that amounts were owed but argues that the
Defendant levied illegal penal interest not sanctioned by the Energy Regulatory
Commission (ERC). The Plaintiff asserts that by rejecting the post-dated
cheques, the Defendant acted maliciously to manufacture a default and justify
the continued strangulation of the Plaintiff’s business—conduct the Plaintiff
terms economic sabotage.
19. Regarding damages, the Plaintiff claims Kshs. 14,588,093.75 as special
damages. The logic advanced is that the cylinders, having been held in open
storage for over seven years, have been exposed to the elements (sun, rain,
corrosion) and are now effectively scrap. The Plaintiff claims the cost of
replacing these cylinders as a total loss.
The Defendant’s Case
20. The Defendant submits that the Plaintiff is a recalcitrant debtor who seeks to
use the judicial process to avoid legitimate obligations. The Defendant
emphasizes that the debt of Kshs. 6,732,922.22 is indisputable and was
admitted by PW1 under oath.
21. The Defendant’s central legal defence is the right of lien. It argues that under
the common law, a person in lawful possession of goods is entitled to retain
them until debts associated with those goods (or the general balance of
account in a commercial relationship) are paid. The Defendant cites Unibilt
Page 5 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
Kenya Ltd v Mukhi and Sons Ltd 2 EA 340 to support the proposition that a
lien is a shield that entitles the creditor to retain possession.
22. Furthermore, the Defendant relies on the doctrine of estoppel by acquiescence.
It argues that during the meeting of 4 July 2016, the Plaintiff was expressly
informed of the retention of cylinders and did not object, thereby effectively
agreeing to the lien as security for the debt. Having induced the Defendant to
believe the arrangement was acceptable, the Plaintiff cannot now sue for
detinue.
23. On damages, the Defendant argues that the Plaintiff has failed to strictly prove
the special damages as required by law (citing Capital Fish Kenya Ltd v
Kenya Power & Lighting Company Ltd eKLR). The Defendant points out that
no valuation report, expert evidence, or purchase invoices were produced to
substantiate the claim that the cylinders are destroyed or to prove their value.
Analysis & Determination
24. Having carefully considered the pleadings, the evidence adduced, and the
detailed submissions by counsel, I find that the following issues fall for
determination:
a) Whether the Plaintiff is indebted to the Defendant, and if so, is the
imposition of interest lawful;
b) Whether the Defendant possessed a lawful Right of Lien over the
Plaintiff’s cylinders, either by statute, contract, or common law;
c) Whether the detention of the cylinders constitutes the tort of Detinue or
Conversion;
d) Whether the Plaintiff has proved its claim for Special Damages
amounting to Kshs. 14,588,093.75 to the required standard of strict proof;
e) Whether the Plaintiff is entitled to General Damages for economic
sabotage or unfair trade practice;
f) What reliefs are appropriate in the circumstances?
Page 6 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
The Indebtedness and Interest
25. The existence of the debt is the fulcrum upon which the Defendant’s
Counterclaim and defence of lien rests. I must first determine the validity and
quantum of this debt.
26. The LPG Cylinder Exchange Pool Operations Procedures provide a clear
mechanism for the settlement of exchange deficits. Clause 4 (Cylinder
Exchange Methodology), particularly sub-clauses (viii) and (ix), stipulates:
(viii)...the member who has collected more cylinders than they have
received will be entitled to payment for the cylinders in deficit at the
prevailing quarterly refundable deposit that has been set.
(ix) The member will then invoice for the cylinders that are in deficit
and payment should be received within 35 days from the date of
invoice. After 35 days, an interest will be levied at the rate of 2% per
month.
27. The evidence before the court establishes that the Defendant issued invoices to
the Plaintiff for deficits accrued between 2014 and 2016. The
Defendant’s Statement of Account (Exhibit 5) shows a running balance
culminating in the counterclaim amount.
28. The Plaintiff’s witness, PW1, made unequivocal admissions during cross-
examination. When asked about the debt, he stated:
Page 7 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
"I do not owe them the money... Reconciliation was done and the outcome was
that the plaintiff made some payment to the defendant by 10 post dated
cheques. The cheques amounted to 5,978,156/=.".
29. However, in the same breath, he admitted:
"The cheques were post dated. They were between 13 April and 13
December... I have never made the payment to date. I did not have the cash at
the time they made the demand.".
30. By issuing cheques for approximately Kshs. 5.9 million, the Plaintiff admitted
liability for at least that amount. The contention regarding interest appears to be
the only point of divergence.
31. I have examined the Operations Procedures. They expressly authorize the levy
of interest at 2% per month on overdue invoices. This is a contractual term
binding on all members of the Pool. The Plaintiff cannot now claim that the
interest is illegal or unauthorized when it is explicitly provided for in the
governing document signed by the parties. The rate of 2% per month (24% per
annum) is consistent with commercial rates for unsecured debts and is not
penal in nature.
32. Furthermore, the Plaintiff’s argument that the Defendant acted maliciously by
rejecting post-dated cheques is legally unsound. A cheque is a bill of exchange
payable on demand (Section 73 of the Bills of Exchange Act). A post-dated
cheque is, in essence, a request for credit. The Agreement required payment
within 35 days of the invoice. The Plaintiff’s attempt to pay via cheques dated
up to December 2016 was a unilateral attempt to vary the contractual terms. A
creditor is not obliged to accept a payment method that differs from the contract
unless they expressly agree to the variation. The Defendant was within its rights
to reject the post-dated cheques and demand immediate payment of the
overdue sums.
Page 8 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
33. The Defendant has pleaded a specific sum of Kshs. 6,732,922.22 in its
Counterclaim. The Plaintiff has not tendered a forensic audit or an alternative
calculation to challenge the arithmetic of this figure, beyond a general denial. In
civil litigation, where a specific liquidated sum is pleaded and supported by a
statement of account, and the debtor admits indebtedness generally but fails to
particularize the error, the Court is entitled to enter judgment for the proved
sum.
34. I, therefore, find that the Plaintiff is indebted to the Defendant in the sum
of Kshs. 6,732,922.22. The Defendant succeeds on this limb of the
Counterclaim.
The Right of Lien
35. The most contentious legal issue in this suit is whether the Defendant was
entitled to withhold the Plaintiff’s cylinders as security for this debt. The
Defendant asserts a right of lien.
36. A lien is a right at common law for a person in possession of goods belonging to
another to retain possession until a debt due to him is satisfied. Halsbury’s
Laws of England, 4th Edition, Vol 28, Para 502 defines it as:
A right at Common Law in one man to retain that which is
rightfully and continuously in his possession belonging to
another until the present and accrued claims of the person in
possession are satisfied.
37. Liens are generally classified into particular liens and general liens. A particular
lien arises where the debt was incurred in respect of labor or skill applied to
the specific goods retained, for example, a mechanic repairing a car). A general
lien is a right to retain goods for a general balance of account between the
parties. General liens are not favored by the common law because they
interfere with the free flow of commerce and grant a priority to one creditor over
Page 9 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
others without public notice. They typically arise only by custom of trade or
by express contract.
38. In this case, the Defendant did not apply labour or skill to improve the cylinders;
it merely held them as part of the exchange pool logistics. Therefore,
a particular lien does not arise. The Defendant must rely on a general lien.
39. The Defendant relies heavily on Unibilt Kenya Ltd (Under Receivership) v
Mukhi and Sons Ltd 2 EA 340. In that case, the Court upheld a lien exercised
by a clearing and forwarding agent over a client’s goods. However, a close
reading of Unibilt case reveals a critical distinction: the contract in that
case expressly provided that the Defendant "shall have a general as well as a
particular lien on all goods for unpaid account".
40. In the present case, I have scoured the LPG Cylinder Exchange Pool
Agreement and the Operations Procedures. There is no express
clause granting members a lien over competitors' cylinders for unpaid exchange
deficits.
41. The relationship between the parties is governed not just by contract, but by
the Energy (Liquefied Petroleum Gas) Regulations, 2009. The Exchange Pool
is a statutory creation designed to ensure the interoperability of cylinders for the
benefit of the public.
42. Clause 12.6 of the Agreement mandates:
"A member who has collected cylinders belonging to another member shall at
his own cost transport the said cylinders to a designated collection point within
7 calendar days."
43. Clause 12.7 is prohibitory:
Page 10 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
"A member is also prohibited from holding other members cylinders (outside of
the initial 7 days) at any other location except a designated collection point."
44. Clause 15(d) forbids members from:
"Procuring the removal or withdrawal of another member's cylinder from
circulation or in any other way from being accessible to the owner..."
45. Further, the Operations Procedures prescribe specific penalties for holding
cylinders beyond 14 days (Kshs 50,000 per outlet) and for withdrawing
competitors' cylinders (Kshs 1,000,000).
46. The legal maxim expressio unius est exclusio alterius (the expression of one
thing implies the exclusion of another) is applicable here. The regulatory
scheme expressly provides remedies for non-payment of debts: invoicing and
penal interest (2% per month) (Clause 4(ix)). It also provides for the suspension
or expulsion of defaulting members. It does not provide for a lien. On the
contrary, it expressly penalizes the retention of cylinders.
47. Where a contract, and subsidiary legislation, imposes a positive statutory duty
to return goods within a specific time (7 days), that duty is inconsistent with the
existence of a common law right to retain the goods indefinitely. The statutory
mandate to circulate cylinders overrides the common law right of lien, especially
where the lien would defeat the public policy objective of the Regulations
(ensuring LPG availability).
48. I, therefore, find that the Defendant did not have a statutory or contractual right
of lien. The detention of the cylinders was, prima facie, a breach of the
Agreement and the Regulations.
Estoppel by Acquiescence
Page 11 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
49. However, the analysis does not end there. The Defendant argues that the
Plaintiff agreed to the lien. DW1 testified that at a meeting on 4 July 2016, the
Plaintiff was informed of the decision to withhold cylinders and did not object.
50. PW1 admitted this in cross-examination:
"We discussed how we would make payments and the cylinders. They told me
that they would hold the cylinders until the payment was made. I came to an
arrangement with them.".
51. This brings into play the equitable doctrine of estoppel. By coming to an
arrangement in July 2016, the Plaintiff effectively consented to the Defendant's
possession of the cylinders as security for the debt. This consent validated the
Defendant's possession at that material time, shielding the Defendant from
liability for detinue for that period. The principle of volenti non fit injuria applies.
52. However, a lien, or a consensual retention arrangement, is a right of defence
and not a right of action (Unibilt case). It is a shield, not a sword. It entitles the
creditor to hold the goods, not to keep them forever or allow them to rot.
Furthermore, consent can be withdrawn.
53. When the Plaintiff demanded the return of the cylinders and subsequently filed
this suit on 16 March 2017, it effectively revoked any consent or arrangement
previously made. At that point, the Defendant’s continued retention of the
cylinders—in the face of the statutory prohibition and the Plaintiff's demand—
became unlawful. The Defendant should have sought to attach the cylinders
through judicial process rather than engaging in indefinite extra-judicial self-
help.
54. I, therefore, hold that while the Defendant's possession was initially consensual
(between July 2016 and March 2017), it became unlawful upon the filing of this
Page 12 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
suit. The Defendant had no valid lien to justify the detention for the subsequent
seven years.
Detinue and Conversion
55. The tort of Detinue consists of the wrongful withholding of the plaintiff's goods. It
requires the plaintiff to prove that they have an immediate right to possession
and that the defendant, having possession, refused to return the goods upon
demand.
56. The tort of Conversion involves dealing with goods in a manner inconsistent
with the rights of the true owner, intending to deny the owner's right or to assert
a right inconsistent with it.
57. Having found that the lien was not sustainable in law after the revocation of
consent, the Defendant’s continued refusal to return the 4,425 cylinders
constitutes Detinue. The Plaintiff is the undisputed owner of the brand and the
cylinders. The Defendant is holding them without a valid legal justification.
58. In Kenya Breweries Ltd v Godfrey Odoyo [2010] eKLR, the Court of Appeal
affirmed that in an action for detinue, the plaintiff is entitled to the return of the
goods or their value, plus damages for their detention. The court emphasized
that demand and refusal are essential elements, both of which are present
here.
Special Damages
59. The Plaintiff seeks Kshs. 14,588,093.75 as special damages, representing the
replacement cost of the 4,425 cylinders. The Plaintiff argues that due to the
long detention in open weather conditions, the cylinders are wholly destroyed or
depleted and must be replaced.
60. It is a cardinal principle of law that special damages must be specifically
pleaded and strictly proved. This principle was famously articulated by Lord
Page 13 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
Bowen in Ratcliffe v Evans 2 QB 524 and has been consistently applied by
Kenyan courts.
61. In Capital Fish Kenya Ltd v The Kenya Power & Lighting Company Ltd
[2016] eKLR, the Court of Appeal held:
“...it is trite law that special damages must not only be specifically pleaded, they
must also be strictly proved with as much particularity as circumstances permit.
See National Social Security Fund Board of Trustees vs Sifa International
Limited (2016) eKLR, Macharia & Waiguru vs Muranga Municipal Council
& Another (2014) eKLR and Provincial Insurance Co. EA Ltd vs Mordekai
Mwanga Nandwa, KSM CACA 179 of 1995 (ur). In the latter case this Court
was emphatic that
“… It is now well settled that special damages need to be specifically
pleaded before they can be awarded. Accordingly, none can be awarded
for failure to plead. It is equally clear that no general damages may be
awarded for breach of contract …”.
62. I have examined the evidence tendered by the Plaintiff to support this colossal
claim of Kshs 14.5 million. The evidence is woefully deficient. The Plaintiff did
not produce a single invoice, Local Purchase Order (LPO), or receipt showing
the purchase price of a 6kg or 13kg cylinder. The figure of Kshs 14.5M appears
to be a mathematical estimate based on unproven unit costs. PW1 testified that
the cylinders were kept in the open. However, no expert report was tendered.
There is no inspection report from the Kenya Bureau of Standards or a licensed
cylinder validator confirming that the cylinders are scrap. Steel cylinders are
durable assets; they can often be re-validated, sandblasted, and repainted. To
claim 100% replacement cost without technical evidence of total loss is to ask
the Court to speculate.
63. Under Sections 107-109 of the Evidence Act, the burden of proof lies on the
Plaintiff. The Plaintiff has failed to discharge this burden.
Page 14 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
64. Furthermore, the Plaintiff had a duty to mitigate its loss. The Plaintiff admitted
owing money. It could have paid the Kshs 6.7M debt to secure the release of its
Kshs 14.5M assets. By refusing to pay an admitted debt for years, the Plaintiff
contributed to the situation where its assets remained in the Defendant's
custody.
65. Consequently, the claim for Kshs. 14,588,093.75 fails for lack of strict proof. I
cannot award a specific sum of money as replacement cost when neither the
cost of the item nor the fact of its total destruction has been proved by
documentary evidence.
General Damages and Economic Sabotage
66. The Plaintiff claims general damages for economic sabotage and unfair trade
practices.
67. In Peter Mark Gershom Ouma v Nairobi City Council [1976] KR 304, the
Court held that where a legal right is invaded, general damages may be
awarded even without proof of specific pecuniary loss. The Court awards
damages for the invasion of the legal right.
68. The Plaintiff has suffered the loss of use of its tools of trade for over seven
years. This is a violation of its property rights under Article 40 of the
Constitution. The detention of 4,425 cylinders from a smaller player in the
market by a dominant player like the Defendant does have the effect of
distorting competition, which the Energy Act and the Competition Act seek to
prevent.
69. However, the term ‘economic sabotage’ suggests a malicious intent to destroy.
The evidence here suggests a commercial dispute gone wrong. The Defendant
Page 15 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
was attempting to recover a valid debt. The Plaintiff was refusing to pay. Both
parties dug in their heels.
70. While I have found the detention post March 2017 to be unlawful, the Plaintiff’s
own conduct in defaulting on the debt and acquiescing to the initial
arrangement significantly mitigates the Defendant’s culpability. The Plaintiff is
not a clean hands litigant.
71. Taking all factors into account, I find that an award of nominal general damages
for the tort of detinue is appropriate to vindicate the Plaintiff's proprietary rights.
I assess this at Kshs. 500,000/=. This figure aligns with awards in similar cases
of wrongful retention of goods where special damages were not proved.
72. Accordingly, judgment is entered in the following terms:
(i) A mandatory injunction is hereby issued compelling the Defendant to
release and hand over to the Plaintiff all the 4,425 LPG
Cylinders (comprising 2,528 6kg cylinders and 1,895 13kg cylinders), as
is, currently in its possession within 30 days from the date of this
Judgment.
(ii) The Plaintiff's claim for special damages of Kshs. 14,588,093.75.
(iii) The Plaintiff is awarded general damages for detinue in the sum of Kshs.
500,000/=.
(iv) On the counterclaim, Judgment is entered for the Defendant against the
Plaintiff for the sum of Kshs. 6,732,922.22, being the outstanding debt.
(v) This sum shall attract interest at court rates from the date of filing the
Counterclaim until payment in full.
Page 16 of 17
Judgement Milimani HC Civil Suit No. 111 OF 2017
(vi) The monetary award in favor of the Plaintiff shall be set off against the
monetary award in favor of the Defendant.
(vii) The Defendant shall not levy execution for the monetary judgment until it
has fully complied with Order (i) above.
(viii) Each party shall bear its own costs of this suit.
Dated and Delivered at Nairobi this 13 day of February 2026
HELENE R. NAMISI
JUDGE OF THE HIGH COURT
Delivered on virtual platform in the presence of:
For the Plaintiff: Mr Kangethe
For the Defendant: Mr Biko Angwenyi
Court Assistant: Lucy Mwangi
Page 17 of 17
Similar Cases
Gulf African Bank Limited v Bidqron Limited & 2 others (Civil Suit E255 of 2019) [2026] KEHC 1430 (KLR) (Commercial and Tax) (13 February 2026) (Judgment)
[2026] KEHC 1430High Court of Kenya81% similar
Abdulle v Houten & another; Java House Limited & another (Third party) (Commercial Case E158 of 2023) [2026] KEHC 1391 (KLR) (Commercial and Tax) (12 February 2026) (Judgment)
[2026] KEHC 1391High Court of Kenya77% similar
Equity Bank (Kenya) Limited v Ng’ang’a; Muinde & 3 others (Interested Parties) (Civil Case E839 of 2021) [2026] KEHC 1207 (KLR) (Commercial and Tax) (5 February 2026) (Ruling)
[2026] KEHC 1207High Court of Kenya77% similar
Mwangi & another v Omondi (Commercial Case E278 of 2025) [2026] KEHC 1152 (KLR) (Commercial and Tax) (5 February 2026) (Ruling)
[2026] KEHC 1152High Court of Kenya77% similar