Case Law[2026] KEHC 1513Kenya
Shelter Builders Limited v Classico Builders Limited (Civil Suit E477 of 2020) [2026] KEHC 1513 (KLR) (Commercial and Tax) (13 February 2026) (Judgment)
High Court of Kenya
Judgment
REPUBLIC OF KENYA
IN THE HIGH COURT OF KENYA AT NAIROBI
COMMERCIAL AND TAX DIVISION
CORAM: F. MUGAMBI, J
CIVIL SUIT. NO. E477 OF 2020
BETWEEN
SHELTER BUILDERS LIMITED ……..…………………..
PLAINTIFF
VERSUS
CLASSICO BUILDERS LIMITED ………………..…… DEFENDANT
JUDGMENT
Introduction and Background
1. The dispute before me stems from a contractual
relationship between the parties. On 25th January
2016, the defendant entered into a Joint Building
Council (JBC) contract with Ms. A & E Ngugi
Investments Limited (the Employer). Acting as the
main contractor, the defendant subsequently
entered into a subcontract agreement dated 30th
January 2016, under which the plaintiff was
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 1
engaged to execute the works. The subcontract
provided that the plaintiff would be entitled to 90%
of the certified building works payments.
2. The plaintiff confirms that the project commenced
in February 2016, with an anticipated completion
date of September 2017. However, in March 2017,
the project was suspended due to non-payment by
the employer. The plaintiff contends that, by the
time of suspension, the defendant had already
breached its sub contractual obligations, thereby
disrupting the plaintiff’s cash flow and hindering the
progress of the works. As a result, the plaintiff
claims to have suffered losses and expenses and
now seeks judgment against the defendant in the
sum of Kshs. 84,219,146.92, together with interest.
3. This claim is itemized as losses and expenses from
valuation no. 10, recurring preliminaries during
suspension, recurrent head office overheads during
suspension, interest on the contract, unpaid
variations and additional works, loss of profit from
unexecuted works, and interest plus VAT.
4. The defendant disputes the claim through a
Statement of Defence dated 23rd February 2021.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 2
While acknowledging the contractual relationship
and confirming that the project was indeed
suspended, the defendant maintains that it was the
party that incurred costs as a result of the
suspension. The defendant denies breaching its
obligations under the subcontract, maintaining that
all requisite payments were duly made.
5. At the hearing, the plaintiff presented its evidence
through Mr. Rajesh Siyani, a director of the
plaintiff company, and Mr. Charles Kyali
Mutinda, an expert witness. The defendant, in turn,
called Mr. Narani Hirani, a director of the
defendant company. The oral testimonies and
written submissions of the parties align with their
respective pleadings, which I have already
summarized. Accordingly, I will not repeat them in
detail but will refer to them as necessary in my
analysis of the facts and evidence which follows.
Analysis and Determination
The Plaintiff’s Claim of Kshs. 20,796,696/= arising
from valuation number 10.
6. The plaintiff maintains that although both parties
were involved in preparing the payment
applications pursuant to clause 34 of the JBC
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 3
Contract, the defendant did not remit the re-
assessed sums promptly. It states that on 8th March
2017, the parties agreed that the value of work
executed amounted to Kshs. 17,234,970.49.
However, upon submission to the project quantity
surveyor (QS), the works were significantly
undervalued at Kshs. 3,435,594.30, which was
subsequently certified by the project architect
under interim certificate number 10.
7. The plaintiff further asserts that although the
defendant received interim valuation number 10 on
6th April 2017 and interim payment certificate
number 10 on 13th April 2017, these documents
were withheld and only furnished to the plaintiff on
14th November 2018, 587 days later. The
defendant’s contention that the plaintiff’s director
collected the documents in April 2017 is disputed,
as no evidence of receipt has been produced.
Consequently, the plaintiff challenges both the
valuation and the certified amount under interim
payment certificate number 10, which forms the
basis of this head of claim.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 4
8. The plaintiff argues that the defendant failed to
contest interim payment certificate number 10
within the 30-day period prescribed under clause
45.2 of the JBC Contract, thereby giving rise to the
present dispute. It emphasizes that the defendant
bore a duty to promptly notify it of the gross
undervaluation by the quantity surveyors so that
any dispute could be escalated in good time.
Instead, the defendant’s delay and inaction unfairly
prejudiced it. Moreover, the plaintiff maintains that
the sub-contract Agreement between the parties
contains no arbitration clause, therefor entitling it to
seek redress directly before this court.
9. In response to this head of the plaintiff’s claim, the
defendant argues that under the JBC agreement,
the sums certified by the project architect in an
interim payment certificate were conclusive unless
subsequently reopened by an arbitrator appointed
pursuant to clause 45.8. The defendant maintains
that only an arbitrator had authority to interfere
with or revise such certificates, not the parties
themselves. It cautions that entertaining the
plaintiff’s claim would result in conflicting valuations
of the works, thereby creating uncertainty and
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 5
absurdity, particularly in the event the project were
to be sold to a third party.
10. The defendant further disputes the plaintiff’s
assertion that interim certificate number 10 was
only received in November 2018. It points out that
the works had already been suspended in March
2017, making it implausible that the plaintiff would
wait over a year without inquiry. Even if the plaintiff
first saw the certificate in November 2018, the
defendant contends that this reflects indolence on
the part of the plaintiff. By that time, interim
certificate number 11 had already been issued, and
the plaintiff raised no objections to either
certificate. The defendant also notes that its
director wrote to the plaintiff in November 2018
regarding deductions for materials removed from
site after abandonment of works, yet the plaintiff
did not protest or raise concerns about the
certificates.
11. The defendant submits that the plaintiff acquiesced
to the valuations in certificates 10 and 11 and
cannot now seek to dispute them. It further asserts
that all sums due under certificate 10 have already
been remitted. It relies on the evidence on record
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 6
which shows that the plaintiff received a total of
KES 82,955,329.79 between April 2016 and
September 2019, representing full and final
settlement of the builder’s works up to the
suspension of the project.
12. The defendant confirms that the plaintiff does not
dispute receipt of this amount but instead seeks an
additional KES 84,219,146.92, which the defendant
contends is wholly unjustified.
13. In determining the contractual rights and
obligations of the parties, it is necessary to begin
with the settled principle that parties are bound by
the contracts they freely enter into, and it is not the
role of the Court to rewrite or re-engineer those
agreements. This principle was clearly articulated
by the Court of Appeal, in National Bank of Kenya
Ltd V Pipeplastic Samkolit (K) Ltd & Another,
[2001] eKLR where it emphasized that courts must
give effect to the bargain struck by parties, unless
illegality or public policy dictates otherwise.
14. The primary contract in this matter was the JBC
agreement executed between the defendant and
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 7
the employer on 25th January 2016. That agreement
formed the foundation upon which the subcontract
between the plaintiff and the defendant was built.
Clause 9.2 of the JBC contract particularly placed
upon the defendant the responsibility of arranging
for labour and other workmen necessary for the
execution of the works. This allocation of
responsibility implies that the JBC contract was the
central and governing agreement which set out the
rights, duties, and procedures that structured the
project.
15. It also implied that any subcontract entered into by
the defendant could not operate in isolation or
deviate from the framework established by the JBC.
The subcontract was necessarily ancillary, and
designed to facilitate the defendant’s performance
of its obligations under the JBC. In effect, the
subcontract imported the terms and processes of
the JBC by reference, particularly in relation to
payment, valuation, and certification of works. The
plaintiff, though not a signatory to the JBC,
undertook its obligations with full knowledge that its
entitlements were dependent on the defendant’s
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 8
compliance with the JBC and the employer’s
discharge of its payment obligations.
16. Of relevance to the dispute before Court is clause
34 of the JBC contract which provided the
mechanism for processing payments. The agreed
procedure required the contractor to submit
applications for payment to the QS, who would
value the works and forward the valuation to the
architect. The architect would then issue an interim
payment certificate, which would be presented to
the employer for payment within 14 days. PW1
confirmed this process during cross-examination.
17. Importantly, clause 34.8 empowered the architect
to correct or amend any previously issued
certificate, while clause 34.9 declared that the
amount stated in the interim payment certificate
represented the true value of the works properly
executed and materials delivered. Clause 45.1 of
the JBC also contained a deliberately broad
arbitration clause, extending to “any matter or thing
of whatsoever nature arising thereunder or in
connection therewith”.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 9
18. Turning to the relationship between the JBC and the
subcontract, PW2 candidly admitted that although
the plaintiff was not a signatory to the JBC, its terms
nonetheless applied to them as the subcontracted
entity. The conduct of the parties and the
correspondence exchanged throughout the
engagement confirm this position. Indeed, the
subcontract between the plaintiff and the defendant
contained only limited provisions, primarily relating
to payment, because the parties understood that
the JBC was the governing framework.
19. It is further evident that the subcontract was
entered into with full knowledge that the
defendant’s entitlement to payment was dependent
on the employer under the JBC. PW1 confirmed this
point during cross-examination, when he
acknowledged that the suspension of works was
attributable to the employer’s lack of finances
rather than any fault of the defendant. The
plaintiff’s challenge to interim certificate number 10
must therefore be considered in light of the JBC
framework.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 10
20. It is not in issue that the QS reviewed the valuation
and assessed the works at Kshs. 3,435,594.30,
which the architect certified in interim certificate
number 10. Under the JBC Contract, parties
anticipated that an application for payment under
clause 34 was subject to evaluation by the QS and
certification by the project Architect. While the
plaintiff disputes this figure, clause 34.9 makes
clear that the architect’s certificate is conclusive
unless corrected or revised under the contract.
Moreover, clause 45.8 provides that only an
arbitrator has authority to reopen or revise such
certificates. The plaintiff’s reliance on the argument
that there was no arbitration clause in the
subcontract is in my view misplaced, because the
subcontract was inherently tied to the JBC, and
payments to the plaintiff could only flow after
compliance with the JBC process.
21. The implication is that the plaintiff accepted the
subcontract knowing that its performance and
payment were contingent upon the JBC framework.
PW1 and DW1 both admitted to the practice by the
parties whereby he plaintiff participated in the
valuation process and submitted applications for
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 11
payment through the defendant. By doing so, it is
my view that the plaintiff had effectively subjected
itself to the procedures and dispute resolution
mechanisms of the JBC. The subcontract did not
create an independent payment regime but was
tethered to the JBC, which remained the focal
agreement.
22. The plaintiff has not otherwise demonstrated that
the defendant breached any contractual obligation
in relation to certificate 10. The defendant’s role
was limited to submitting the joint valuation to the
QS, which was done. The subsequent alleged
undervaluation was the responsibility of the QS and
architect, not the defendant. The quantification
presented by PW2 of amounts allegedly due under
certificate 10 cannot stand, as it contradicts the
express provisions of the JBC that disputes over
valuations must be referred to arbitration.
23. The duty of courts to respect party autonomy in
arbitration has been firmly established in
jurisprudence. In Nyutu Agrovet Ltd V Airtel
Networks Kenya Ltd, [2019] eKLR, the Supreme
Court emphasized that arbitration is founded on the
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 12
freedom of parties to choose their own forum and
procedure for dispute resolution, and that courts
must uphold this choice save for the limited
statutory interventions provided under the
Arbitration Act.
24. Similarly, in Synergy Industrial Credit Ltd V
Cape Holdings Ltd, [2020] eKLR, the Court of
Appeal reaffirmed that arbitration agreements
embody the parties’ deliberate decision to exclude
ordinary litigation and to resolve disputes privately
and conclusively. These authorities make it clear
that courts are not at liberty to rewrite or disregard
arbitration clauses but that they must give effect to
the bargain struck by the parties, so as to safeguard
the principle of party autonomy.
25. Indeed, the plaintiff acknowledges at page 10 of its
submissions that: procedurally, every other detail
and procedure as far as this project was concerned
was per the main contract. For example, the
procedure for payments was as outlined under
Clause 34 of the main contract.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 13
26. In this regard, the defendant’s position that it did
not declare a dispute or seek arbitration under
clauses 45.1 and 45.2 is consistent with the JBC
contract. Its duty under the subcontract was to
remit 90% of the sums certified, which the plaintiff
has not shown to have been withheld. The evidence
confirms that the defendant received interim
certificate number 10 on 13th March 2017 and
forwarded it to the plaintiff in November 2018.
While the delay in sharing the certificate is
questionable, the plaintiff has not demonstrated
any contractual provision requiring immediate
transmission of certificates to subcontractors, nor
did the plaintiff raise the issue contemporaneously.
It would imply that the late submission may not
have been tied to late payment of the amount due
under that certificate.
27. In fact, interim certificate number 11 was
subsequently issued, and the plaintiff raised no
objection. The plaintiff’s silence until the filing of
this suit undermines its claim of prejudice. The
defendant has shown that the plaintiff received KES
82,955,329.79 between April 2016 and September
2019, representing full and final settlement of
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 14
builder’s works up to suspension. For these reasons
this ground fails.
Claim for Additional Recurring Preliminaries and
Site Overheads - Kshs. 1,566,069.91.
28. The plaintiff’s claim under this head is presented as
additional recurring preliminaries and site
overheads amounting to Kshs. 1,566,069.91. The
plaintiff explains that these were costs incurred at
the project site which, although not tied to specific
construction activities, were essential for the
day-to-day operation and management of the
project.
29. The plaintiff states that this sum arose from
extended preliminaries occasioned by delayed
completion, together with actual recurring site
overheads. According to the plaintiff, the calculation
was based on the number of weeks between the
suspension of works on 24th March 2017 and the
projected practical completion date under the main
contract, namely 18th September 2017. The
plaintiff’s expert applied the agreed preliminaries
figure proportionately to this period, arriving at the
total claim of Kshs. 1,566,069.91.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 15
30. In response to the plaintiff’s assertion, the
defendant argues that the sum claimed as extended
preliminaries and site overheads following the
suspension of works on 24th March 2017 has not
been proven. It took issue with the allegations by
the plaintiff that these were actual costs necessary
for site management, yet no documentary evidence
was produced to substantiate the claim. The
defendant further submits that the plaintiff cannot
rely on clauses of the JBC agreement to which it has
no privity, and criticizes the attempt to include
interest under clause 34.6 while simultaneously
disavowing the JBC in other heads of claim.
According to the defendant, special damages must
be specifically pleaded and strictly proved, and the
plaintiff had failed to meet this legal threshold.
31. Turning to the subcontract agreement between the
plaintiff and the defendant, it is undisputed that the
parties had apportioned responsibility for
preliminary costs. The defendant expressly
undertook to meet expenses relating to temporary
facilities, site offices, telephone, power and water at
a cost of Kshs. 250,000/=, watching and lighting at
Kshs. 500,000/=, and water meter application and
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 16
installation at Kshs. 250,000/=. These obligations
were clearly set out in the subcontract and formed
part of the defendant’s contractual duties. There
was nothing in the subcontract that exempted the
defendant from meeting these preliminary
expenses during the suspension of works. As such,
the circumstances under which the plaintiff claims
to have incurred these costs is uncertain as the
defendant’s duty to discharge them remained intact
irrespective of whether construction activities were
ongoing or temporarily halted.
32. Being a claim for special damages, the burden
rested squarely on the plaintiff to prove that actual
payments were made during the suspension period.
Upon reviewing the expert report presented by
PW2, I note that although the plaintiff’s submissions
characterize this head of claim as based on actual
costs, no documentary evidence was produced to
substantiate the alleged expenses. PW2 candidly
admitted during cross-examination that his
computations were derived from a formula rather
than from receipts or records of actual payments.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 17
33. He further acknowledged that some of the items
included in his report were anticipated expenses
which had not yet been incurred. While I
acknowledge that there is practice of using
formulas within the construction industry to
ascertain loss, I hold the view that for the purposes
of succeeding in a claim such as this, the use of
formulae cannot be justified unless backed up by
supporting evidence.
34. The law is clear that special damages must be
specifically pleaded and strictly proved. The Court
of Appeal in David Bagine V Martin Bundi,
[1997] eKLR, citing Lord Goddard C.J. in Bonham
Carter V Hyde Park Hotel Limited, [1948] 64
TLR 177 emphasized thus:
“Plaintiffs must understand that if
they bring actions for damages it
is for them to prove damage. It is
not enough to note down the
particulars and, so to speak,
throw them at the head of the
court saying ‘this is what I have
lost’, I ask you to give me these
damages; they have to prove it.”
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 18
35. Additionally, the claim by the plaintiff that its
representatives remained on site during the
suspension period as no instructions to demobilize
were ever issued is also unsubstantiated. No
evidence in the form of site records, attendance
logs, or correspondence have been produced to
demonstrate their continued presence on site. It is
further evident from the record that the defendant,
by its letter dated 23rd March 2017, formally notified
the plaintiff of the suspension of works. Once such
communication had been issued, there would have
been no reasonable basis for the plaintiff to retain
workers on site without instructions to continue with
construction activities.
36. The law imposes upon a claimant the duty to
mitigate its loss, and the plaintiff cannot rely on its
own failure to demobilize or reduce unnecessary
expenses as a basis for claiming additional costs.
Simply put, (See Chappell, Smith and Sims, Building
Contract Claims (4 th ed) David Chappell, Blackwell
Publishing, 92):
“A party cannot recover damages
resulting from the other party’s
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 19
breach of contract if it would have
been possible to avoid any
damage by taking reasonable
measures.”
37. As to whether the suspension of the works by the
defendant amounted to a breach of the subcontract,
I note that clause 29 of the JBC contract expressly
envisaged circumstances under which works could
be suspended. The provision recognized suspension
as a legitimate contractual mechanism, not as a
repudiation of obligations. In this case, the
defendant invoked clause 29 and formally
communicated the suspension to the plaintiff by its
letter dated 23rd March 2017. The record is clear
that the suspension was effected in accordance with
the contract and was not arbitrary.
38. Accordingly, I find that the evidence presented by
the plaintiff does not meet the required threshold
for proof of special damages under this heading.
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 20
Claim for Recurrent Head Office Overhead Costs
During the Suspension Period - Kshs.
11,627,424.87.
39. According to the plaintiff, the claim under this
heading relates to its head office overheads rather
than temporary site office expenses. The plaintiff
explained that such costs encompassed items like
rent, utilities (electricity, water, internet), office
maintenance and repairs, as well as salaries and
staff benefits. In computing the amount allegedly
owed, the plaintiff’s expert applied the Hudson’s
formula, a globally recognized method for
apportioning head office overheads and profit to
construction projects. The formula operates by
applying a percentage-based mark-up to direct
costs, thereby incorporating overheads and profit
into the total project price. The plaintiff therefore
contends that the sum claimed represents a fair and
accepted calculation of head office overheads
attributable to the delayed completion of the
project.
40. In response, the defendant submitted that there
was no evidence to demonstrate that the plaintiff
owned or operated a head office, or that it had
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 21
incurred any expenses under that heading. The
defendant argues that the plaintiff was not
contractually bound to the defendant in a manner
that would have necessitated establishing or
maintaining a head office solely for purposes of this
subcontract.
41. More critically, the defendant challenged the
reliance on Hudson’s formula, contending that its
application in this context was misplaced and
unfounded as it had no contractual basis in either
the subcontract between the parties or the JBC
agreement between the defendant and the
employer. The defendant maintained that the
plaintiff’s reliance on estimates and conjectural
calculations could not substitute for documentary
proof such as receipts or records of actual
expenditure.
42. This claim, like the preceding one, falls squarely
within the category of special damages. I note that
the plaintiff pleaded it as actual head office
overheads, and the evidentiary burden remains the
same: special damages must be specifically pleaded
and strictly proved. Applying the principles
established in David Bagine V Martin Bundi
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 22
(supra), the plaintiff’s reliance on the Hudson’s
formula without supporting documentation falls
short of the required threshold. Moreover, the duty
to mitigate loss applies equally to claims of
overheads. Even if the plaintiff maintained a head
office, it was incumbent upon it to demonstrate that
the alleged expenses were directly attributable to
the suspension of works and not general business
costs that would have been incurred regardless. The
absence of such linkage further undermines the
claim.
Claim for Interest on amounts due out of
performed contract, variations, and additional
works – Kshs. 8,281,073/=.
43. In light of the findings already made, this claim is
untenable as it relates to interest on the preceding
sums.
Claim for Loss of Profit due to Unexecuted Works
– Kshs. 24,889,139/=.
44. The plaintiff claims for loss of profit for unperformed
works. It contends that the suspension of works was
indefinite and that the project remains incomplete
to date. It argues that as a result of the suspension,
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 23
it has consequently lost the profits it would have
earned had the contract been completed.
45. The defendant, however, raises an objection, that
the suspension of works was not attributable to its
fault but rather to the employer’s failure to finance
the project. In its view, the subcontract was
frustrated by circumstances beyond its control, and
no liability can attach to it for the plaintiff’s alleged
loss of profits. The defendant further submits that
damages for lost profits must have been within the
contemplation of the parties or foreseeable
consequences of the defendant’s conduct. The
subcontract contains no provision for compensation
of lost profits in the event of suspension, and the
plaintiff has not demonstrated that such damages
were contemplated at the time of contracting.
46. According to Chappell, Smith and Sims (supra,
page 102):
“The starting point in dealing with
a claim under this heading [loss of
profit] is to put the injured party
in the same position, so far as
money can do it, as if the contract
had been correctly performed. In
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 24
recovering such damages, the law
will allow only the recovery of
losses actually suffered or
expense actually incurred.”
47. It has been admitted that after the suspension of
works in March 2017, the project remained
incomplete and was still incomplete up to the time
of filing this suit. This fact is sufficient proof of the
disruption to the works and evidence that the
plaintiff suffered some form of direct loss. However,
the law draws a distinction between disruption and
recoverable damages.
48. Once again, what is recoverable is not the mere fact
of disruption, but the actual profit that the plaintiff
would have earned had the contract been
completed. This position was upheld in Wraight
Ltd V P. H. & T. (Holdings) Ltd, (1968) 13 BLR
27 where the court stated:
“In my judgment, the position is
this prima facie, the claimants are
entitled to recover, as being
direct loss and/or damage, those
sums of money which they would
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 25
have made if the contract had
been performed…”
49. I have carefully reviewed the workings presented by
PW2, the expert witness called by the plaintiff. The
figure of Kshs. 24,889,139.18 was arrived at after
deducting the 10% profit payable to the defendant
under the sub-contract. The figure however
presumes that the entire remaining balance
represented profit that was to be earned by the
plaintiff had the project been completed. This
assumption is fundamentally flawed.
50. From the principles articulated, I am persuaded that
the plaintiff could, in principle, have maintained a
valid claim against the defendant. The defendant, in
turn, would have been entitled to seek
reimbursement of such sums from the employer.
However, any recovery would necessarily be
confined to that portion of the claim which, through
credible and cogent evidence, could be shown to
represent the plaintiff’s actual profit margin.
Without such proof, the claim cannot be sustained.
The plaintiff did not produce any documents to
establish the actual profit it would have earned had
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 26
the contract been completed. Without such
evidence, the court cannot infer profit merely from
formulaic calculations or assumptions. Regrettably,
this limb of the claim is therefore dismissed.
Disposition
51. For these reasons I find that the plaintiff has failed
to discharge the evidentiary burden required to
prove its claims. On costs, given that the plaintiff’s
failure lay in its inability to strictly prove the
quantum of damages claimed, it would be unjust to
burden it with the full costs of the suit given the
genuine disruption it experienced. Accordingly,
each party shall bear its own costs.
DATED, SIGNED AND DELIVERED IN NAIROBI
THIS 13 TH DAY OF FEBRUARY 2026.
F. MUGAMBI
JUDGE
Delivered in presence of:
Ms Mwachonti HB for Ms Anami for the plaintiff
Mr Makau for the defendant
Court Assistant: Lillian
HCCCOMM NO. E477 OF 2020 JUDGMENT Page 27
Similar Cases
Epco Buiders Limited v Kenya Bureau of Standards (Miscellaneous Commercial Application E470 of 2016) [2026] KEHC 1394 (KLR) (Commercial and Tax) (12 February 2026) (Ruling)
[2026] KEHC 1394High Court of Kenya77% similar
Lavington Apartments Limited v Ivory Concepts Limited & 4 others (Environment and Land Case E344 of 2025) [2026] KEELC 530 (KLR) (5 February 2026) (Ruling)
[2026] KEELC 530Employment and Labour Court of Kenya76% similar
Shah & another v Onsongo & 2 others (Civil Case 190 of 2002) [2026] KEHC 1105 (KLR) (9 February 2026) (Ruling)
[2026] KEHC 1105High Court of Kenya76% similar
Salom Enterprises v Shared Interest Society Ltd & another; Shared Interest Society Limited (Plaintiff to the Counterclaim); Salom Enterprises Limited & 2 others (Defendant to the Counterclaim) (Civil Suit E412 of 2020) [2026] KEHC 1511 (KLR) (Commercial and Tax) (13 February 2026) (Judgment)
[2026] KEHC 1511High Court of Kenya76% similar
Munga & another v Bulkon Builders Limited & 3 others (Environment and Land Case 188 of 2018) [2026] KEELC 668 (KLR) (12 February 2026) (Ruling)
[2026] KEELC 668Employment and Labour Court of Kenya75% similar