Case LawGhana
REGIMANUEL GRAY LIMITED VRS. TEMA WEST MUNICIPAL ASSEMBLY (LC/53/2019) [2024] GHAHC 172 (18 July 2024)
High Court of Ghana
18 July 2024
Judgment
IN THE SUPERIOR COURT OF JUDICATURE, IN THE HIGH COURT ‘B’ HELD IN
TEMA IN THE GREATER ACCRA REGION OF THE REPUBLIC OF GHANA
BEFORE HER LADYSHIP JUSTICE PATRICIA QUANSAH (JUSTICE OF THE HIGH
COURT) ON THURSDAY THE 18TH OF JULY 2024.
SUIT NO: LC/53/2019
REGIMANUEL GRAY LIMITED
PLOT NO. DEV/276 COMMUNITY 14 PLAINTIFF
TEMA & LA BYPASS, LA, ACCRA
VRS
TEMA WEST MUNICIPAL ASSEMBLY
COMMUNITY 18 DEFENDANT
TEMA
(PLAINTIFF SHALL DIRECT SERVICE)
________________________________________________________________
PARTIES ABSENT
________________________________________________________________
JUDGMENT
1. INTRODUCTION
[i] The Plaintiff herein instituted this action against the Defendant for the
following reliefs:
JUDGMENT – REGIMANUEL GRAY vrs TMA
1
i. A declaration that the Defendant by refusing to notify Plaintiff of
either its approval or rejection of Plaintiff’s application for building
permit to develop plot no. DEV/276, Community 14, Tema, three
months after its submission, the said application is deemed to have
been approved by the Defendant.
ii. An order of injunction restraining the Defendant, its assigns, agents,
privies and/or workmen/servants from demolishing or causing any
demolition of any development structure that may be constructed on
plot no. DEV/276, Community 14, Tema, by the Plaintiff.
iii. Any further order(s) as this Honourable Court may deem equitable.
2. FACTS OF THE PLAINTIFF’S CASE
[ii] In its statement of claim and which was subsequently amended, the Plaintiff
averred that it acquired a leasehold interest in some 15.72 acres of land from
TDC Development Company Limited on or about the 28th of May 1992 and
these plots have been described as DEV/276, Community 14, Tema. Per the
Plaintiff, the plots of land have been registered in the Deeds Registry of the
Lands Commission of Ghana as No. 854/1992 in favour of the Plaintiff herein.
[iii] According to the Plaintiff, it subsequently went into effective possession of
same by placing its caretakers on the land to ward off prospective encroachers
and/or trespassers and also commenced the development of what is known as
the second phase of the Plaintiff’s Community 14 residential estates. Sometime
later, the Plaintiff decided to commence the construction of a fence wall around
the remaining plots of land following attempts by trespassers to encroach on
those remaining plots of the land. The Plaintiff therefore submitted its
JUDGMENT – REGIMANUEL GRAY vrs TMA
2
drawings to both TDC and the Defendant for approval. In addition, the Plaintiff
stated it applied and paid for a building permit from the Defendant herein.
The Plaintiff further contended that on the 4th of July 2018, after submitting its
building drawings to the Defendant for approval, the Defendant requested that
the Plaintiff seeks a “No Objection Recommendation and Approval Notice”
from TDC before its permit could be processed. The Plaintiff was thus advised
by the Defendant to purchase new building permit application forms and re-
submit same together with the TDC “No Objection Recommendation and
Approval Notice”. The Plaintiff was said to have complied and it did purchase
the building permit application forms and submitted same to TDC for approval
on the 18th August 2018.
[iv] On the 22nd August 2018, TDC was said to have prepared its “No Objection”
recommendations and submitted same to the Sub-Technical Committee of the
Defendant for further processing of the Plaintiff’s application.
For inexplicable reasons, however, the Defendant has failed and/or neglected
to apprise the Plaintiff of the outcome of the said application although Plaintiff
has complied with all the statutory and administrative requirements imposed
on applicants who apply for building permits within the Tema acquisition area,
where the Plaintiff’s plots of land, as described above, are said to be located.
[v] On account of the delay and the lack of communication to the Plaintiff, the
Plaintiff averred that three months after the submission of the forms, it
commenced the construction of a fence wall around its property but the fence
wall was demolished by the Defendant on the orders of its Municipal Chief
Executive (MCE).
JUDGMENT – REGIMANUEL GRAY vrs TMA
3
The Plaintiff thus conducted enquiries at the Defendant’s office and same was
said to have revealed that the Sub-Committee had approved the Plaintiff’s
application and yet the Defendant had still not issued the Plaintiff with the
requisite building permit.
[vi] The Plaintiff continued to state that further investigations revealed that the
MCE of the Defendant, under the pretext of public interest, had issued
instructions to the Defendant to hold on with the further processing of the
Plaintiff’s application; and this conduct, the Plaintiff stated was arbitrary,
capricious and unconstitutional.
Additionally, in so far as it has been more than three months since the
application for the building permit was submitted to the Defendant and the
Defendant has failed to notify Plaintiff on whether the application has been
approved or refused, the Plaintiff is entitled to commence building and/or
development on the land on the basis that the application has been approved.
[vii] It is on the basis of the above depositions that the Plaintiff prayed for the reliefs
endorsed on the writ of summons and as spelt out above.
3. STATEMENT OF DEFENCE
JUDGMENT – REGIMANUEL GRAY vrs TMA
4
[viii] In its defence, the Defendant contended that the plots of land in dispute,
purportedly acquired by the Plaintiff herein, were in an area beyond a storm
drain and also constituted a road reservation which the Defendant could
develop for the common good and use of all persons under the Defendant’s
jurisdiction.
The Defendant further contended that as the highest administrative and
planning authority in the Municipality, it was mandated to convert land into
good use and was further mandated to issue ‘Building Approval Permits’ to
individuals and institutions, but in the case of the Plaintiff, no such permit had
been issued because the Spatial Planning Committee of the Defendant, chaired
by the Honourable Municipal Chief Executive, had never received any
completed Municipal Assembly application form(s) nor any drawings from
Plaintiff.
[ix] The Defendant added that the submission of any drawings or a ‘No Objection’
recommendation or any other document to the Works Department of the
Defendant, even if the Plaintiff’s claim was true, did not constitute an approval
from the Defendant or the Spatial Planning Committee for a permit.
The Defendant thus denied receiving a “No Objection” recommendation report
in respect of the Plaintiff, stating further that even if the Sub-Technical
Committee of the Defendant had received the “No Objection” report referred
to by the Plaintiff, no recommendation pertaining to the Plaintiff had been
made to the final Planning Authority of the Defendant or its Spatial Planning
Committee.
[x] The Defendant was also mandated, at all material times, to perform its duties
in accordance with the law and against recalcitrant persons and it therefore
JUDGMENT – REGIMANUEL GRAY vrs TMA
5
cannot waive the consequences of a breach of statutory laws of the Defendant,
the status of the offending party notwithstanding. It is in that regard that the
Defendant insisted that it had never done any unlawful act against the Plaintiff
since the Spatial Planning Committee of the Defendant had not seen or received
any application from the Plaintiff; but that it only removed all the illegal
structures in the area within the confines of law.
[xi] Even before engaging in the said demolition works, the Defendant stated it
posted “STOP WORK” signs on the blocks packed on the land; and
subsequently demolished an illegal structure that was offensive to public
policy and the laws regulating the management of the city. Further, the
demolition the Plaintiff complained of was of the foundation of a wall and not
a fence wall. Among others, the Defendant concluded that the Plaintiff was not
entitled to any of the reliefs indorsed on the Writ of Summons.
The Defendant instead counterclaimed for the following:
4. COUNTERCLAIMS OF THE DEFENDANT
a. A declaration that the act of the said demolition was lawful.
b. An order directed at the Plaintiff, its assigns, agents, privies and all
persons claiming title through him howsoever described not to put
any building on the said land again until the Plaintiff has done the
needful by applying as outlined by law.
c. Costs including legal fees.
5. REPLY AND DEFENCE TO COUNTERCLAIM
JUDGMENT – REGIMANUEL GRAY vrs TMA
6
[xii] The Plaintiff filed a Reply and a defence to the counterclaim, joining issues
generally with the Defendant but vehemently denying the material averments
of the Defendant. The Plaintiff reiterated that it indeed submitted application
forms and drawings for permits for two separate projects to the Municipal
Works Engineer of the Defendant, but it was the permit for only one of the
projects that was issued by the Defendant. The Plaintiff proceeded to restate
the procedures it went through in applying for the permit and further stated
that the Defendant cannot deny receiving an application form from the
Plaintiff.
[xiii] Even in response to a petition submitted against the Defendant, the Defendant
was said to have stated therein that it suspended the processing of the
Plaintiff’s application because it received a petition from the residents in the
area. Among others, the Plaintiff reiterated that it was entitled to its claims and
that the counterclaims of the Defendant rather ought to be dismissed.
6. APPLICATION FOR DIRECTIONS
[xiv] Pleadings then came to a close and the following issues were set down at the
Application for Directions stage:
i. Whether or not Plaintiff has a leasehold interest in a 15.72 acre of
land described as DEV/276, Community 14, Tema.
ii. Whether or not the parcel of land in issue constitutes a road
reservation.
iii. Whether or not Plaintiff submitted a duly completed form applying
for a building permit, building drawing and other requisite
document(s) to Defendant in August 2018.
JUDGMENT – REGIMANUEL GRAY vrs TMA
7
iv. Whether or not Plaintiff’s grantor, TDC Development Company
Limited (TDC) submitted No Objection recommendation to the Sub-
Technical Committee of Defendant for further processing of
Plaintiff’s application before Defendant.
v. Whether Plaintiff is entitled to the reliefs endorsed on its writ.
vi. Any other issues(s) arising from the pleadings.
[xv] The following additional issues were also filed by the Defendant:
7. ADDITIONAL ISSUES
1. Whether or not the Defendant can issue a permit for physical
development with conditions or without conditions.
2. Whether or not the Defendant has the mandate to issue permits for
all structures before any building could be constructed under its
superintending authority.
3. Whether or not the Defendant could effect or carry out an instant
prohibition, abatement, alteration, removal or demolition of any
unauthorized development.
4. Whether or not the Defendant can demolish any illegal structure(s)
that encroaches or will encroach on a community right of space and
security or that that interfered or may interfere with the use of the
space.
JUDGMENT – REGIMANUEL GRAY vrs TMA
8
5. Whether or not the Defendant can prohibit the use of any land or
building for a purpose or in a manner that is contrary to an approved
District Development Plan or for disaster prevention.
6. Whether or not in issuing the permit or otherwise, the Defendant
observed the rules and regulations governing same.
7. Whether or not the Sub-Technical Committee of the Defendant, which
visited the parcel in dispute, make any recommendation to the
Spatial Planning Committee for approval of the application.
8. Whether or not the parcel of land in question has been zoned as a
reservation in the Plaintiff’s own development scheme or that of
TDC.
9. Any other issue that emanates from the pleadings of the parties.
The parties were ordered to file their respective witness statements and they
did.
8. WITNESS STATEMENT OF THE PLAINTIFF
[xvi] The Plaintiff’s representative, who for ease of reference will be referred to as
PW1, testified for and on behalf of the Plaintiff. PW1 stated he was the head of
Legal and Administration of the Plaintiff. He then proceeded to testify and
tender in evidence a copy of the lease obtained by the Plaintiff from TDC as
Exhibit A (marked as RGL 1). PW1 added that the lease had been registered at
the Deeds Registry of the Lands Commission as No. 854/1992.
JUDGMENT – REGIMANUEL GRAY vrs TMA
9
[xvii] PW1 further confirmed that the Plaintiff, after going into effective possession
of the land, commenced the development of phase II of its building project and
even gave out some acres of the plot for community development and for the
construction of a community library, police station, a park, local pub etc; all for
the benefit of the residents in the area.
PW1 continued to state that in spite of the above, encroachers and miscreants
continued to trespass on the remaining portions of the Plaintiff’s land and so
the Plaintiff was advised to fence the remaining plot of land; and that was why
the Plaintiff applied to the Defendant for the building permit.
[xviii] PW1 continued to narrate the processes the Plaintiff had to go through to obtain
the permit; adding that since it applied to the Defendant in 2018, the Defendant
has not communicated to the Plaintiff its approval or otherwise of the building
permit applied for.
Coincidentally, however, a second application later made by the Plaintiff to the
Defendant for the construction of a school at Community 18 has been processed
expeditiously by the Defendant; but this application for a building permit for
the construction of a fence wall has not been processed by the Defendant.
[xix] PW1, among others, concluded that for inexplicable reasons, the Defendant has
failed and/or neglected to apprise the Plaintiff of the outcome of the said
application since July 2018 although Plaintiff has complied with all the
statutory and administrative requirements imposed on it for a building permit.
The Plaintiff therefore prayed for the reliefs prayed for.
JUDGMENT – REGIMANUEL GRAY vrs TMA
10
After the testimony of PW1, the Plaintiff closed its case and called no other
witness.
9. WITNESS STATEMENT OF THE DEFENDANT
[xx] The head of Works of the Defendant also testified for and on behalf of the
Defendant as DW1, and in line with the statement of defence, DW1 reiterated
that the records of the Defendant showed that the Plaintiff had not received
any permit from the Defendant to construct any permanent structure on the
Community 14 plots of land.
When the Plaintiff commenced the construction on the land therefore, the
Defendant stated that it put ‘Stop work’ notices on the Plaintiff’s plot but the
Plaintiff ignored the notices; and that was why the Defendant was compelled
to demolish the Plaintiff’s structures.
[xxi] Contrary to the statement of defence however, DW1 admitted that TDC
processed the Plaintiff’s application and gave a ‘No Objection’ report to the
proposed fence wall of the Plaintiff in conformity with TDC’s development
planning scheme. TDC then referred the Plaintiff to the Defendant for the
permit to construct the fence wall.
JUDGMENT – REGIMANUEL GRAY vrs TMA
11
The Defendant thus received the Plaintiff’s application and referred same to
the Physical Planning Department of the Defendant (working as the Spatial
Planning Committee) and added that the Spatial Planning Committee, after its
meeting did not recommend the Plaintiff’s application for approval.
[xxii] That was because after the sub-technical committee’s visit to the Plaintiff’s site,
it was discovered that the land was a reservation and there was also a huge
storm drain on the land per the Plaintiff’s own planned scheme submitted to
the Defendant. The Residents’ Association in the area had also petitioned the
Defendant, that the land in issue included an open space to be used by the
residents in case of environmental hazards and that same space was reserved
as children’s playground. Thus, the Plaintiff’s development would be a huge
risk to the residents. The Plaintiff is not entitled to the reliefs sought, especially
when the Defendant was acting pursuant to its mandate under law. Among
others, the Defendant’s counterclaims should be granted by the Court.
The Defendant also called no other witness and closed it case after DW1 had
been cross-examined. The trial then came to a close.
10. THE LAW ON THE INCIDENCE OF THE BURDEN OF PROOF IN CIVIL
CASES
[xxiii] In the case of Dzaisu v Ghana Breweries Limited [2007-2008] SCGLR 539, the
Supreme Court per Adinyira JSC held, in expounding on the burden of proof
in civil matters held as follows:
“It is a basic principle in the law of evidence that the burden of
persuasion on proving all facts essential to any claim lies on whosoever
is making the claim.”
JUDGMENT – REGIMANUEL GRAY vrs TMA
12
Also, in the case of Ackah v Pergah Transport Limited [2010] SCGLR 728 the
Supreme Court again held that
It is a basic principle of the law on evidence that a party who bears the
burden of proof is to produce the required evidence of the facts in issue
that has the quality of credibility short of which his claim may fail.
[xxiv] In the case of Khoury v. Richter 1958, High Court, Accra, unreported, cited in
Majolagbe v. Larbi [1959] G.L.R. 191 at p. 192. Ollenu J (as he then was) held:
"Proof in law is the establishment of facts by proper legal means. Where
a party makes an averment capable of proof in some positive way, e.g.
by producing documents, description of things, reference to other facts,
instances, or circumstances, and his averment is denied, he does not
prove it by merely going into the witness-box and repeating that
averment on oath, or having it repeated on oath by his witness. He
proves it by producing other evidence of facts and circumstances, from
which the Court can be satisfied that what he avers is true."
11. EVALUATION OF THE EVIDENCE ADDUCED AT THE TRIAL
[xxv] From the trial, it is not in doubt that the Plaintiff herein has acquired all that
piece or parcel of land which the Plaintiff described as No. DEV/276
Community 14, Tema. PW1 tendered in evidence Exhibits A and B (which had
been marked Exhibits RGL 1 and 2) without any objection from the Defendant
to demonstrate that the Plaintiff had lawfully acquired those plots of land.
[xxvi] In its defence, the Defendant averred that it was not in a position to admit or
deny that the Plaintiff had acquired all that plot of land; and even denied at
JUDGMENT – REGIMANUEL GRAY vrs TMA
13
some stage, the said acquisition; but I find that no shred of evidence whatsoever
was adduced by the Defendant to discredit the documentary evidence adduced
by the Plaintiff in proof of its acquisition. In that regard, I am satisfied, on a
balance of probabilities that the Plaintiff has indeed lawfully acquired the plots
of land in contention.
[xxvii] There is also no doubt that the Plaintiff applied to the Defendant for building
permits after the Plaintiff had applied to TDC for a ‘No objection” order to
enable the Plaintiff apply for the permit(s) from the Defendant. That is the
permit(s) in contention and being complained of; and the Plaintiff states that
from 2018 till date, when the application was made, the permit has still not been
granted.
It is the Defendant who is supposed to grant that permit and even though the
Defendant had not yet granted the permit, it proceeded to demolish the fence
wall of the Plaintiff that was constructed on a portion of the Plaintiff’s land. At
paragraphs 6 to 10 of the witness statement of DW1, he testified that the
Defendant indeed demolished the Plaintiff’s structures after warnings to desist
from the construction were allegedly ignored. From the said paragraphs of
DW1’s witness statement, it appears to state that the demolition was done
before the Plaintiff applied for the permits with the Defendant; but the evidence
of PW1 seems to suggest otherwise.
Nonetheless, I shall now proceed to deal with the legal issues set down as
follows:
12. ISSUES I & II AND ADDITIONAL ISSUE 8
JUDGMENT – REGIMANUEL GRAY vrs TMA
14
- Whether or not Plaintiff has a leasehold interest in a 15.72 acre of land
described as DEV/276, Community 14, Tema.
- Whether or not the parcel of land in issue constitutes a road reservation.
- Whether or not the parcel of land in question has been zoned as a
reservation in the Plaintiff’s own development scheme or that of TDC.
[xxviii] This Court already established above that the Plaintiff had lawfully acquired
a leasehold hold interest in the land in dispute and Exhibit A, the TDC
document dated the 28th May 1992 clearly describes the land in question as
having an area of 15.72 acres. No evidence was adduced by the Defendant to
establish otherwise and so I find as a matter of fact that the land leased to the
Plaintiff is indeed 15.72 acres of land.
The Plaintiff further denies that there is a road reservation on any portion of
the land; but the Defendant asserts that there is. In the case of Deliman Oil
Company Ltd v HFC Bank Ghana Ltd [2016] 92 GMJ at page 4, it was held thus:
The very well-known rule of evidence is that proof lies upon him who
affirms or alleges, and not upon him who denies, since, by the nature of
things, he who denies a fact cannot produce any proof. (Emphasis is
mine)
[xxiv] The burden thus shifted unto the Defendant to establish that a portion of the
Plaintiff’s land is a road reservation, but I find that no evidence was adduced
by the Defendant to establish there is a reservation anywhere on the Plaintiff’s
land. Under cross-examination, the Defendant’s Counsel posed the following
questions to the Plaintiff’s representative:
JUDGMENT – REGIMANUEL GRAY vrs TMA
15
Q: The location of the construction is a reservation.
A: That is not correct.
Q: How many of these areas do you have in your planning scheme?
A: It is not a demarcated area per say (sic) however at most
construction side (sic) some parcels are left after development of
some houses to be used for commercial developments. One of
such is a police station.
Q: How many of such parcels do you have in your planning scheme?
A: With the parcel in dispute there is one long stretch measuring
about 3 acres.
Q: I put it to you that the parcel in dispute is not for commercial or
social use.
A: That is not correct.
Q: The parcel of land also was reserved to protect the environment
and pre-existing trees, is that not so?
A: That is not correct.
Counsel for the Defendant again posed the following question under further
cross-examination:
JUDGMENT – REGIMANUEL GRAY vrs TMA
16
Q: At the last adjourned date you disagreed with me vehemently
that the space you are talking about is not a reservation, is that
not so?
A: I indicated that the space in reference was left after development
for social and commercial purposes.
[xxv] Having consistently denied that there was a reservation anywhere on the
Plaintiff’s plot, the Defendant assumed the burden of establishing same; but all
throughout the trial, there was no pictorial evidence or otherwise; for instance,
the lay out of the land etc adduced by the Defendant to show to the Court
where the so-called reservation was on the Plaintiff’s plot. Indeed, there was
also no evidence whatsoever adduced by the Defendant to establish that any
portion of the Plaintiff’s plot was indeed a road reservation.
[xxvi] What the Defendant, per DW1, tendered in evidence was Exhibit 1 series
(marked Exhibit TWRG 1 series), said to be a plan of the area from TDC and
the Plaintiff’s proposed fence wall; and all these documents, I find, were
documents the Plaintiff had submitted to the Defendant during the application
for the permit. (See paragraph 11 of DW1’s witness statement). From Exhibit 1
series, the plots have been clearly demarcated, the roads clearly identified and
there is no mention of any reservation. I therefore hold that there is no iota of
evidence to even remotely suggest that any portion of the land assigned to the
Plaintiff by TDC is a reservation or a road reservation for that matter, even in
TDC’s own plan tendered in evidence by the Defendant.
[xxvii] Additionally, even though the Plaintiff’s representative admitted under cross-
examination that there was indeed a storm drain on the land, once again, I find
that there was no evidence adduced by the Defendant to establish that the
Plaintiff, by its development, was obstructing the said storm drain and/or that
JUDGMENT – REGIMANUEL GRAY vrs TMA
17
any development undertaken on the disputed portion of the Plaintiff’s plots
would adversely affect the residents in the area.
Indeed, DW1 added that the residents had petitioned the Defendant over a
portion of the Plaintiff’s plots that is a road reservation and another portion
that was an open space for the residents; but once again, no iota of evidence
was adduced by the Defendant to establish its claims. Moreover, the TDC has
lawfully sold the plots of land to the Plaintiff; and so I am unsure how the
Plaintiff’s development would affect the community or the alleged reservation.
[xxviii] Again, I find that the Defendant’s own Exhibit 2 series (marked Exhibit TWRG
2 series), Appendix A at page 7 clearly stated
“- Undeveloped
- Site is open space
- Seems to be road reservation (but according to TDC, it is not.)”
(Emphasis is mine)
If the grantors of the land state it is not a reservation, wherein lies the
Defendant’s proof of a road reservation then, from the above?
Even if there was a road reservation, the land had been sold to the Plaintiff in
1992, and so the Defendant has to engage TDC and the Plaintiff if there is the
need to have a road in the area, apart from the ones indicated on the
Defendant’s Exhibits. I am therefore unsure if the Plaintiff’s development
would affect the entire community as the Defendant alleged; and this
uncertainty must inure to the benefit of the Plaintiff herein.
JUDGMENT – REGIMANUEL GRAY vrs TMA
18
I will proceed to deal with the following set of issues:
14. ISSUES III & IV
- Whether or not Plaintiff submitted a duly completed form applying for a
building permit, building drawing and other requisite document(s) to
Defendant in August 2018.
- Whether or not Plaintiff’s grantor, TDC Development Company Limited
(TDC) submitted No Objection recommendation to the Sub-Technical
Committee of Defendant for further processing of Plaintiff’s application
before Defendant.
[xxix] There is no need belabouring the above because DW1 admitted the Plaintiff
submitted application forms but they were not approved. DW1 gave the
answers below under cross-examination:
Q: The application by the Plaintiff was part of the 20 applications?
A: Yes, My Lord. But it was not recommended for approval, My Lord.
Q: What you are saying is that you did not recommend the Plaintiff’s
application to the Spatial Planning Committee for approval?
A: Yes, My Lord.
JUDGMENT – REGIMANUEL GRAY vrs TMA
19
Q: So that only seven applications out of the 20 were not
recommended for approval?
A: Yes, My Lord.
[xxx] It is also obvious that TDC submitted its “no Objection” report to the Defendant
and paragraph 12 of DW1’s witness statement expressly admitted same as
follows:
12. That TDC processed the Plaintiff’s application and gave “No
Objection” to the proposed Fence Wall in conformity to TDC’s
Development Planning Scheme.
However, TDC referred the Plaintiff to the Defendant/ Assembly
to permit to construct. (sic)
[xxxi] TDC therefore, having given the “No Objection” report on the same fence wall,
I again find that the Defendant ought to adduce sufficient evidence to establish
that the Plaintiff was not entitled to the grant of the permit, but once again, no
reasonable explanation and/or justification was adduced by the Defendant for
the refusal of the permit. Therefore, wherein lies the justification of the
Defendant in refusing the Plaintiff’s permit to only construct the said fence
wall?
The testimony of DW1, the minutes of the Committee meetings tendered in
evidence unfortunately do not disclose any reasonable justification for the
refusal of the Plaintiff’s permit, having carefully considered the totality of the
evidence adduced before this Court.
I will proceed to deal with the following set of issues together:
JUDGMENT – REGIMANUEL GRAY vrs TMA
20
15. ADDITIONAL ISSUES 1 TO 7
- Whether or not the Defendant can issue a permit for physical development
with conditions or without conditions.
- Whether or not the Defendant has the mandate to issue permits for all
structures before any building could be constructed under its superintending
authority.
- Whether or not the Defendant could effect or carry out an instant
prohibition, abatement, alteration, removal or demolition of any
unauthorized development.
- Whether or not the Defendant can demolish any illegal structure(s) that
encroaches or will encroach on a community right of space and security or
that that interfered or may interfere with the use of the space.
- Whether or not the Defendant can prohibit the use of any land or building
for a purpose or in a manner that is contrary to an approved District
Development Plan or for disaster prevention.
- Whether or not in issuing the permit or otherwise, the Defendant observed
the rules and regulations governing same.
- Whether or not the Sub-Technical Committee of the Defendant, which
visited the parcel in dispute, make any recommendation to the Spatial
Planning Committee for approval of the application.
JUDGMENT – REGIMANUEL GRAY vrs TMA
21
[xxxii] The above issues are not triable issues and they ought not to have been set
down for the trail because it is obvious to me that the above constitute the
mandate granted to the Defendant by law. There is therefore no doubt
whatsoever in my mind, that the Defendant has to observe its own rules and
regulations in issuing permits and the above issues are not worth discussing.
I will conclude by discussing the following issues:
16. CONCLUSION
- Whether Plaintiff is entitled to the reliefs endorsed on its writ.
- Any other issues(s) arising from the pleadings.
- Any other issue that emanates from the pleadings of the parties
[xxxiii] In discussing the above, for the avoidance of doubt and based on the evidence
adduced before this Court, hinging on the refusal or otherwise of the permit
sought by the Plaintiff herein, I find that no report or proof was furnished by
the Defendant to this Court to demonstrate or even suggest that the Spatial
Committee of the Defendant or any sub-committee, for that matter, did visit
the site for inspection and made recommendations for the refusal of the
Plaintiff’s permits.
No petition(s) from the residents were disclosed and without sufficient
evidence, this Court cannot rely on some petitions, whether spurious or
genuine to make a determination that the Plaintiff is not deserving of the
requisite permit. Also, from the lack of reasonable justification before this
JUDGMENT – REGIMANUEL GRAY vrs TMA
22
Court, I am minded to believe the Plaintiff’s assertions, that the refusal of the
permit may be based on someone’s capricious and arbitrary orders.
[xxxiv] I also have no proof whatsoever, even from the Plaintiff’s own evidence that
the area has been zoned as a reservation. Why then would TDC sell the land
off if it is a reservation? And the Defendant itself confirmed TDC stated it was
not a reservation. In the absence of any valid justification therefore for the
refusal, I find that the Plaintiff’s application has to be properly evaluated and
approved and the permits granted. The Plaintiff is therefore, indeed, entitled
to some reliefs from this Court.
[xxxv] In arriving at the reliefs to be granted to the Plaintiff herein, I would finally rely
on the NATIONAL BUILDING REGULATIONS 1996, (LI 1630), Regulation 8
— Failure of District Planning Authority to Process Application, which
provides thus:
(1) Where a person submits an application for a building permit, the
District Planning Authority shall notify him within 7 days of the
receipt of the application and shall within a period of 3 months
thereafter notify the applicant whether the application is granted
or refused.
(2) An applicant not informed of the grant or refusal of the
application may after the expiry of the 3 months commence
development on the basis that the application is acceptable to
the District Planning Authority.
JUDGMENT – REGIMANUEL GRAY vrs TMA
23
The law is clear, with no ambiguity and there is again no doubt in my mind
that the Plaintiff herein is entitled to the reliefs sought.
[xxxvi] For the foregoing reasons, judgment be and is hereby entered in favour of the
Plaintiff for all the reliefs endorsed on the writ of summons as follows:
i. A declaration that the Defendant by refusing to notify Plaintiff of
either its approval or rejection of Plaintiff’s application for building
permit to develop plot no. DEV/276, Community 14, three months
after its submission, the said application is deemed to have been
approved by the Defendant.
ii. This Court shall further grant an order of injunction restraining the
Defendant, its assigns, agents, privies and/or workmen/servants
from demolishing or causing any further demolition of any
development structure that may be constructed on plot no. DEV/276,
Community 14, Tema, by the Plaintiff.
iii. The Defendant herein, be and is hereby ordered to issue a formal
permit(s) for the Plaintiff in the absence of reasonable justification
for the refusal to issue the permit.
This Court shall further mulct the Defendant in costs of Gh¢30,000.00 in favour
of the Plaintiff herein.
JUDGMENT – REGIMANUEL GRAY vrs TMA
24
SGD.
JUSTICE PATRICIA QUANSAH
HIGH COURT ‘B’
TEMA
GREATER ACCRA REGION.
18TH JULY 2024.
COUNSEL:
PETRINA DEFIA WITH MILLICENT DEDO OSSOM FOR THE PLAINTIFF,
HOLDING O. K. OSAFO BUABENG’S BRIEF
COUNSEL FOR THE DEFENDANT, PATRICE CAESAR SOWAH ESQ. ABSENT
JUDGMENT – REGIMANUEL GRAY vrs TMA
25
Similar Cases
LAGAH AND ANOTHER VRS. BOATENG AND ANOTHER (E8/03/2016) [2024] GHAHC 175 (18 June 2024)
High Court of Ghana82% similar
TSIKATA VRS TEMA DEVELOPMENT CORPORATION & 2 OTHERS (A11/08/19) [2024] GHACC 26 (12 February 2024)
Circuit Court of Ghana80% similar
KOOMSON VRS. AMOATEY AND ANOTHER (GJ/0037/2024) [2024] GHAHC 410 (31 October 2024)
High Court of Ghana79% similar
ASAAM VRS. TEMA DEVELOPMENT CORPORATION(TDC) AND OTHERS (AC/328/2014) [2024] GHAHC 409 (31 October 2024)
High Court of Ghana78% similar
Asaam and Another v Tema Development Corporation and Others (AC/328/2014) [2024] GHAHC 527 (31 October 2024)
High Court of Ghana78% similar