Case Law[2026] KEELRC 281Kenya
Rambukwella v Dl Koisangat Estate Limited (Cause E025 of 2024) [2026] KEELRC 281 (KLR) (29 January 2026) (Judgment)
Employment and Labour Relations Court of Kenya
Judgment
REPUBLIC OF KENYA
IN THE EMPLOYMENT AND LABOUR RELATIONS COURT
AT ELDORET
CAUSE NO. E025 OF 2024
USSANGA WIJERATNE RAMBUKWELLA..…………...
CLAIMANT
VERSUS
DL KOISANGAT ESTATE
LIMITED ....................RESPONDENT
JUDGMENT
1. The Claimant instituted this claim vide a Memorandum of
Claim dated 5th June 2024 seeking payment of his salary
arrears from the Respondent.
2. The Claimant contended that he was engaged by the
Respondent as the General Manager – Technical Operations,
under a Consultancy Contract dated 13th June 2022, for a
cumulative period of twenty-four (24) months, commencing
on 13th June 2022 and expiring on 13th June 2024.
3. He avers that his remuneration package comprised a
consolidated monthly fee of USD 4,094, subject to applicable
taxes payable to the Government of Kenya, for each
completed month of service. The fees were payable at the
1
ELD ELRC E025 OF 2024 JUDGMENT
end of every month, less any advances previously taken by
the Claimant.
4. It is the Claimant’s case that he performed his duties
diligently and in accordance with the terms of the contract
but the Respondent failed to pay his remuneration for the
period from February 2024 to June 2024, resulting in an
outstanding total of USD 21,131.86
5. The Claimant states that he made several written demands
to the Respondent seeking payment of the outstanding
salary arrears, but the Respondent neither responded nor
effected payment.
6. The Claimant avers that his contract was set to expire on 13th
June 2024 and that he required the outstanding salary to
facilitate his relocation back to Sri Lanka, his home country.
He asserts that the Respondent’s failure to pay his due
salary constitutes a breach of the employment contract and
a violation of the Employment Act, 2007.
7. The Claimant particularised his claim as follows:-
i. Unpaid salary for February 2024……………..…….
3,889.30
2
ELD ELRC E025 OF 2024 JUDGMENT
ii. Unpaid salary for March
2024……………………….3,889.30
iii.Unpaid salary for April
2024………………………….3,889.30
iv.Unpaid salary for May
2024……………………….....3,889.30
v. Unpaid salary for June 2024 (pro-rated)……….
….1,685.36
8. The Claimant further avers that despite numerous attempts,
the Respondent has failed or refused to pay his terminal
dues, which he tabulated as follows:
Arrears Net Amount in USD
February………………………………………………………3,889.30
March…………………………………………………….…..3,889.30
April……………………………………………………….…..3,889.30
May…………………………………………………………..….3,889.30
June……………………………………………………..……..1,685.36
Encashment of unavailed leave………………………….3,889.30
21,131.86
Relocation Costs
Relocation to Sri-Lanka……………………………………..8,990
3
ELD ELRC E025 OF 2024 JUDGMENT
Airfare for Claimant& Family ………………………..…....2,200
11,190
9. The Claimant therefore prays for the following:-
i. The Respondent do issue the Claimant with a Certificate
of Service.
ii. A Mandatory injunction do issue to compel the
Respondent by themselves, their servants and/or
agents or any one authorized by them or claiming under
them to pay the sum of USD 32,321.86 as the final dues
of the Claimant.
iii. A Mandatory injunction do issue to compel the
Respondent by themselves, their servants and/or
agents or any one authorized by them or claiming under
them to issue a certificate of service to the Claimant.
iv. Damages in USD 10,000 for late payment.
v. An Order do issue to compel the Respondents by
themselves, their servants and/or agents or any one
authorized by them or claiming under them to permit
the Claimant to continue residing in the company-
provided accommodation and be allowed to retain and
use the company-provided vehicle until the full and final
4
ELD ELRC E025 OF 2024 JUDGMENT
settlement of all dues, including but not limited to
unpaid salary, severance pay, and any other
contractual.
vi. An Order that the Respondent, its agents, or any other
representatives be restrained from interfering with the
Claimant's use of the company residence and vehicle
during the period until the final settlement is
completed.
vii. An order that the personal effects of the Claimant be
shipped prior to his and his family's exit from Kenya.
viii. Any other damages that this court may find just.
ix. Cost of the suit and interest thereon at court rates
10. The Respondent filed a Response to the Memorandum of
Claim dated 3rd February 2025, in which it averred that the
Claimant was engaged as an independent contractor
pursuant to a Consultancy Contract dated 13th June 2022.
The Respondent stated that, under the terms of the contract,
it was obliged to pay the agreed consultancy fee only upon
submission of a duly prepared and signed invoice by the
Claimant, and that to date, the Claimant has not submitted
any signed invoices in respect of the amounts claimed.
5
ELD ELRC E025 OF 2024 JUDGMENT
11. The Respondent asserted that the Claimant failed to
diligently perform his duties, particularly in aligning cash flow
processes, which failure led to the company experiencing
financial and operational hardships from the year 2023 to
date. The Respondent further averred that it was the
Claimant’s responsibility to ensure that salaries, including his
own, were paid on time, a duty which he allegedly abdicated,
resulting in the accumulation of employee salary arrears and
adversely affecting not only the Claimant but also the
welfare of the Respondent’s employees.
12. The Respondent further contended that the Claimant failed
in his duty to align factory operations, resulting in a
significant decline in production and operational capacity
during his tenure. It was also averred that, as the officer
responsible for financial management, the Claimant was fully
aware of the company’s financial position but failed to
regularize the remittance of statutory deductions, thereby
prompting enforcement action by the Kenya Revenue
Authority and causing further disruption to the company’s
operations.
6
ELD ELRC E025 OF 2024 JUDGMENT
13. In response to the allegation made by the Claimant that he
made several written requests for payment, the Respondent
asserted that the Claimant has never submitted duly
prepared and signed invoices for the services allegedly
rendered.
14. The Respondent stated that the Consultancy Contract
expressly provided that, upon termination, the Claimant was
obliged to immediately return to the Respondent all property
belonging to the Respondent that was in his possession or
control. The Respondent further contended that the
Claimant’s failure to surrender company property, coupled
with his failure to submit invoices for terminal dues,
constitutes a breach of the terms of the contract.
15. According to the Respondent, pursuant to Clause (e) of the
consulting contract, the Claimant is personally liable to
indemnify it for all losses, damages, and expenses incurred
as a result of the Claimant’s breach of contract, including
failure to surrender the company-provided motor vehicle and
laptop.
16. The Respondent also averred that the contract between the
parties clearly provided that any disputes or disagreements
about the contract such as its validity, meaning, or ending
7
ELD ELRC E025 OF 2024 JUDGMENT
ought to be resolved through friendly discussions or
arbitration. They argued that the issues raised in this case
fall under that part of the contract.
17. The Respondent therefore prayed that the Claim be
dismissed with costs.
18. At the hearing, the Claimant testified as CW1 on his behalf
while the Respondent called its Human Resource Director, Mr
Kariuki who testified as RW1.
19. The Claimant adopted his witness statement, recorded on 8th
December 2024, as his evidence-in-chief and relied on the
documents filed in support of his case. He testified that he
was never informed by the Respondent that his performance
was unsatisfactory. He stated that he resigned from
employment as a result of persistent salary arrears.
20. During cross-examination, the Claimant stated that, pursuant
to the terms of his employment contract, he was required to
return company property, which he had not yet done. He
testified that he had prepared and submitted a
comprehensive handover report. The Claimant further
asserted that he submitted invoices for the period February
to June 2024. He confirmed receipt of Kshs 500,000 from the
8
ELD ELRC E025 OF 2024 JUDGMENT
Respondent, which was paid through his advocate on record
following an order to that effect by the court. He also stated
that, among the reliefs sought, he prayed for an order
compelling the Respondent to pay airfare and relocation
costs, and that under the contract of employment, he was
entitled to demobilisation costs to facilitate his return to Sri
Lanka, subject to prior approval by the Respondent’s
Executive Chairman.
21. On re-examination, the Claimant asserted that he prepared a
handover report and that Mr. Kariuki acknowledged receipt
of the said handover report.
22. The Respondents witness, Mr. Daniel Kariuki adopted his
witness statement recorded on 3rd February 2025 as his
evidence in chief. He testified that upon the lapse of the
Claimant’s consulting contract, the Claimant was required to
surrender all company property and execute an undertaking
confirming compliance, which he had failed to do. He stated
that the Respondent was not aware of the whereabouts of
the company motor vehicle in the Claimant’s possession.
RW1 also testified that the Claimant failed to perform his
duties as stipulated in the contract, thereby exposing the
Respondent to financial distress.
9
ELD ELRC E025 OF 2024 JUDGMENT
23. On cross-examination, the Respondent’s witness averred
that the Claimant’s engagement ended by effluxion of time.
He admitted that no performance review reports were
produced to demonstrate that the Claimant underperformed
and that no warning letters were issued to the Claimant. He
further stated that the Claimant wrote several letters
demanding payment of his salary, which were not honored
due to the Respondent’s financial constraints. He further
stated that the Respondent has not deliberately withheld the
Claimant’s dues but was unable to pay due to financial
challenges.
24. At the close of the Respondent’s case, parties were directed
to file written submissions. The Claimant’s submissions are
dated 1st December 2025 while the Respondent’s
submissions are dated 9th December 2025.
Analysis and Determination
25. I have considered the pleadings, the evidence adduced by
the parties and the submissions on record as well as the
authorities cited. The issues that present themselves for the
court’s determination are: -
10
ELD ELRC E025 OF 2024 JUDGMENT
i. Whether the engagement between the parties herein
was an employment contract or a consultancy
arrangement;
ii. Whether the Claimant is entitled to salary arrears as
claimed;
iii. Whether the Claimant is entitled to demobilization
costs;
iv. Whether the Claimant is entitled to continue occupying
the Respondent’s property;
v. Whether the Claimant is entitled to general damages.
Whether the engagement between the parties was an
employment contract or a consultancy arrangement
26. The Claimant pleaded that he was engaged as a General
Manager – Technical Operations under a Consultancy
Contract dated 13th June 2022. Although the Respondent
claimed that the relationship between it and the Claimant
was a Consultancy Contract, and thus outside the jurisdiction
of this court, the Claimant averred in his pleadings and
evidence that the Claimant’s engagement evidenced an
employment relationship as the Claimant was responsible for
11
ELD ELRC E025 OF 2024 JUDGMENT
internal management functions ordinarily performed by an
employee.
27. This issue was the subject of the ruling of this court dated
10th July, 2025 where this court held that the relationship
between the Claimant and the Respondent herein was that
of employer and employee even though the terminology
used in the contract was that of consultant.
28. This issue is thus already determined.
Whether the Claimant is entitled to salary arrears as claimed
29. The Claimant contends that the Respondent failed to pay
him his salary for the period February to June 2024. In its
defence, the Respondent admitted non-payment of the said
salaries but submitted that payment was conditional upon
the Claimant submitting duly prepared and signed invoices
which the Claimant allegedly did not provide.
30. The Claimant however, testified that he prepared and
submitted all requisite invoices for the period in question and
further submitted a comprehensive handover report, which
was acknowledged by the Respondent. The Respondent’s
witness, RW1, conceded during cross-examination that the
Respondent owed the Claimant the claimed salaries but
12
ELD ELRC E025 OF 2024 JUDGMENT
attributed non-payment to financial constraints. It was
further confirmed that a partial payment of Kshs 500,000
had been made to the Claimant through his advocate,
pursuant to an order of this court following an application by
the Claimant.
31. The Claimant testified that he prepared and submitted
invoices to the Respondent. That he further wrote demand
letters for payment of his outstanding salary. This evidence
was not controverted.
32. In the circumstances, I find that the Claimant has established
a prima facie entitlement to the salary arrears for the period
February to June 2024. The Respondent’s financial
challenges do not absolve it of its contractual obligation to
pay for services duly rendered under the consultancy
contract.
33. It is therefore my finding that the Claimant has discharged
the burden of proving that he rendered the services under
the contract and that he is entitled to the payments for the
period February to June 2024 totaling USD 21,131.86 less the
partial payment already made.
13
ELD ELRC E025 OF 2024 JUDGMENT
Whether the Claimant is entitled to relocation and
repatriation costs
34. The Claimant has sought for relocation and repatriation costs
totaling to USD 11,190. He pleaded and testified that upon
expiry of his engagement, he was entitled to demobilisation
costs to facilitate his return to Sri Lanka. He further stated
that under the terms of the contract, such costs were
payable subject to approval by the Respondent’s Executive
Chairman. On its part, the Respondent contended that the
Consultancy Contract did not provide for relocation or
repatriation costs upon expiry by effluxion of time.
35. The Claimant was engaged from outside the jurisdiction and
deployed to Kenya for the sole purpose of executing the
Respondent’s project. Upon completion of the contract by
effluxion of time, the Claimant was required to exit the
country and disengage from the project location.
36. In the instant case the contract between the Claimant and
Respondent expressly provided for mobilization and
demobilization costs at Article 5 of the Addendum No. 01 of
the contract dated 15th December, 2022 which provides:
a) Expenses
14
ELD ELRC E025 OF 2024 JUDGMENT
o The company shall bear the relocation costs for
the consultant for his mobilization and
demobilization subject to prior approval by the
Executive Chairman of such expenses in writing.
37. In the circumstances, I am satisfied that the Claimant is
entitled to demobilization fees as provided in his contract.
The Claimant however did not justify the sum of USD 11,190
claimed. He did not give a breakdown of the same.
Whether the Claimant is entitled to continue occupying the
Respondent’s property
38. The Claimant sought orders permitting him to continue
residing in the Respondent’s company-provided
accommodation and to retain use of the company motor
vehicle pending full settlement of his dues. The Respondent’s
witness, RW1 testified that the provision of housing, motor
vehicle, and laptop was strictly tied to the subsistence of the
consulting contract which ended on 13th June 2024 and that
upon expiry of the contract, the Claimant was obligated to
immediately surrender all company property and complete
the clearance process.
15
ELD ELRC E025 OF 2024 JUDGMENT
39. The Respondent contended that the Claimant’s continued
occupation of the property and use of the motor vehicle and
laptop amounted to unjust enrichment and had compelled
the Respondent to incur replacement costs.
40. Taking into consideration the circumstances of this case,
especially that the Claimant was an expatriate who had
come from his country to work for the Claimant, the fact that
the Claimant’s contract provided for repatriation costs to be
borne by the Respondent, and having determined that the
Respondent failed to settle the Claimant’s accrued
consultancy fees and demobilisation costs upon completion
of the contract, the Court is satisfied that requiring the
Claimant to immediately vacate the company provided
accommodation and to surrender the motor vehicle before
settlement of his dues would occasion undue hardship and
would unjustly benefit the Respondent, who has failed to
meet his obligations under the contract and failed to pay the
Claimant’s entitlements.
41. Accordingly, I hold that the Claimant shall continue
occupying the Respondent’s company-provided
accommodation and to retain use of the company motor
16
ELD ELRC E025 OF 2024 JUDGMENT
vehicle strictly pending full settlement of the amounts
awarded herein, whereupon the Claimant shall immediately
surrender all company property and complete the clearance
process.
Whether the Claimant is entitled to general damages
42. It is settled law that general damages are not payable for
breach of contract unless specifically provided for. The
contract herein ended by effluxion of time and did not
provide for liquidated damages or penalties for delayed
payment. The claim for USD 10,000 as damages for late
payment therefore fails.
43. Consequently, judgment is entered for the Claimant in the
following terms: -
i. The Claimant is awarded USD 21,131.86 as consultancy
fees arrears for the period February to June 2024 less
Kshs 500,000.
ii. The parties shall address the court on the sum of USD
11,190 demobilization costs by way of written
submissions.
iii.Pending full settlement of the sums awarded herein, the
Claimant shall be permitted to continue occupying the
17
ELD ELRC E025 OF 2024 JUDGMENT
Respondent’s company provided accommodation and to
retain use of the company motor vehicle, upon which
full settlement the Claimant shall immediately
surrender all company property and complete the
clearance process.
iv.The Respondent shall issue the Claimant with a
Certificate of service.
44. The Respondent shall pay the Claimant’s costs of this suit.
45. Interest shall accrue at court rates from date of filing suit till
payment in full.
DATED, SIGNED AND DELIVERED VIRTUALLY ON
THIS 29TH DAY OF JANUARY, 2026
MAUREEN ONYANGO
JUDGE
18
ELD ELRC E025 OF 2024 JUDGMENT
Similar Cases
Banking Insurance Finance Union (Kenya) v Guardian Bank Limited (Cause 634 of 2019) [2026] KEELRC 381 (KLR) (16 February 2026) (Judgment)
[2026] KEELRC 381Employment and Labour Relations Court of Kenya79% similar
Miseh v Migori County Assembly Service Board (Cause 373 of 2017) [2026] KEELRC 36 (KLR) (21 January 2026) (Judgment)
[2026] KEELRC 36Employment and Labour Relations Court of Kenya78% similar
Munanu v Equity Bank (K) Limited (Cause 1295 of 2018) [2026] KEELRC 204 (KLR) (28 January 2026) (Judgment)
[2026] KEELRC 204Employment and Labour Relations Court of Kenya78% similar
Omwoyo v Debenham & Fear Limited (Employment and Labour Relations Cause E124 of 2022) [2026] KEELRC 376 (KLR) (16 February 2026) (Judgment)
[2026] KEELRC 376Employment and Labour Relations Court of Kenya78% similar
Ogugu v All Pack Industries Limited & another (Cause 773 of 2011) [2025] KEELRC 3659 (KLR) (17 December 2025) (Judgment)
[2025] KEELRC 3659Employment and Labour Relations Court of Kenya74% similar