Case Law[2013] UGSC 29Uganda
National Social Security Fund and Another v Alcon International Limited (Civil Appeal No 15 of 2009) [2013] UGSC 29 (8 February 2013)
Supreme Court of Uganda
Judgment
THE REPUBLIC OF UGANDA
CIVIL APPEAL NO 15 OF 2009
BETWEEN
APPELLANTS
AND
ALCON INTERNATIONAL LIMITED :: RESPONDENT
JUDGMENT OF ODOKI, CJ
This is an appeal against the decision of the Court of Appeal
dismissing an appeal brought by the appellants against the
respondent.
IN THE SUPREME COURT OF UGANDA
AT KAMPALA
[Appeal from the decision of the Court of Appeal of Uganda (Mpagi-Bahigeine,
Twinomujuni and Kavuma JJ.A) dated 25 August 2009, in Civil Appeal No 2 of
2008]
1. NATIONAL SOCIAL SECURITY FUND}
2. W. H SSENTOOGO T/A SSENTOGGO}
& PARTNERS }
(CORAM: ODOKI, C.J, TSEKOOKO,
AND KISAAKYE, JJ. S.C)
Background to the Appeal:
The brief facts of the case are that on 21 st July 1994, the respondent,
Alcon International Ltd entered into a contract with the 1 st
Respondent, the National Social Security Fund (NSSF) to erect and
KATUREEBE, KITUMBA
I
2
The respondent pleaded collusion and fraud, and sought various
orders including declaration that the termination of the contract and
On 30 th November 1998, the respondent filed HCCS No. 1255 of 1998
against the appellants jointly for wrongful termination of the contract.
In Paragraph 11 of its amended plaint, the respondent accused the
1 st appellant of failure to utilize the remedy of arbitration pursuant to
Clause 36 of the contract. The respondent stated that as a result of
the 1 st appellant ’ s failure to accept the request for arbitration within
the stipulated time, the respondent wrote to the East African Institute
of Architects at Nairobi, Kenya, to intervene. It later transpired that
the said institute was dormant and no action was ever taken.
complete a partially constructed structure on Plot No.1 Pilkington
Road, Kampala. Construction work started and the second appellant,
W.H. Ssentoogo, trading as Ssentoogo and Partners, was contracted
as the project architect. The contract was varied from time to time
leading to a supplementary contract on 8 June 1996. Due to
extensive variations and changes, the 1 st appellant on 21 November
1997 granted an extension of the time to the respondent to complete
the project by 31 st May 1998.
On various dates on 11 th December 1997 and 30 th April 1998, the 1 st
Appellant wrote to the respondent giving notice of termination of
contract under Clause 25(i) of the contract, citing defaults allegedly
committed by the respondent which the latter denied. Following
incessant disputes between the parties, the 1 st appellant terminated
the contract on 15 th May 1998.
V
“ 1.
2.
3.
4.
3
breach of the co-financing agreement were wrongful, null and void, as
well as special and general damages. " •" ■ •
That if the parties fail to agree to an independent
arbitrator, the applicant shall refer the matter to the
Chairman of the East African Institute of Architects
to appoint an Arbitrator in accordance with Clause
36 of the contract. ”
the
from
That the parties agree on an Independent
Arbitrator within 14 days from the date hereof i.e
14/06/99
Subsequently, the respondent applied by way of chamber summons,
for temporary injunction restraining the appellants from committing
any further breach of the contract and injury under the contract, by
awarding or executing the contract to another contractor. It was
sought to maintain the status quo at the site so as to allow the
respondent or its other authorized agents to make an inventory, to
. • * . . • • • • ’
value and measure the work done and to value all the various
properties belonging to the respondent.
On 14 th June 1999, the learned trial judge refused to grant the
temporary injunction but instead ordered that the matters in conflict
between the parties be referred to arbitration. .The learned trial judge
made the following orders:
That a temporary injunction should not be
issued against the respbndents/defendants to
restrain them from interfering with
applicants/plaintiffs property and
committing further breach of contract.
That the main suit be stayed and the matter be
referred to arbitration
4
Dissatisfied with the dismissal, the applicants appealed to the Court
of Appeal on several grounds : which included complaints that the
learned judge erred in law and fact in not holding that she had erred
in law in staying the suit and in referring the matter to arbitration, that
the learned judge erred in law and in fact in not holding that the
arbitration was improperly procured, and in holding that there were
errors on the face of the record, among others. The Court of Appeal
dismissed the appeal. Hence this appeal.
The appellants protested the order and filed a notice of appeal, but
the appeal was never prosecuted.
The appellants refused to concur to the appointment of an Arbitrator.
The respondent referred the matter to the President of the East
African Institute of Architects (EAIA). The President of East African
institute of Architects appointed an Arbitrator. The respondent filed
its claim, the appellants filed a defence and the respondent made a
reply thereto and arbitration proceedings commenced.
*
On 20 th September 2001, the appellants filed Miscellaneous
Application No 417/2001 seeking the removal of the arbitrator on
grounds of bias. The appellants later on 15 November 2001 filed
another application, Arbitration Cause No 4 of 2001, to set aside the
Arbitral Award on grounds that there were errors of law on the face of
the record, that the Arbitrator misconducted himself and that therefore
the arbitration was improperly procured. Both applications were
consolidated and dismissed on 30 th September 2003.
i.
The four grounds which were argued were framed as follows:
"1.
2.
3.
4.
5.
5
At the hearing of the appeal the first appellant was represented by
Mr. G.S. Lule, Mr. Barnabas Tumusinguzi, Mr. David Nambale, Ms
Patricia Mutesi and Ms Brenda Ntambirwaki. The 2 nd appellant was
represented by Dr J Byamugisha. The respondent was represented
by Mr. Enos Tumusiime, Mr. M Kabega and Mr. Ronald Oine.
The learned Justices of Appeal erred in law in
holding that the learned Judge did not err in law
in staying the suit and referring the matter to
arbitration.
(a) The learned Justices of Appeal erred in law in
holding that the arbitrator did not misconduct
himself."
The learned Justices of Appeal erred in law in
upholding an arbitration award that was
obtained illegally and contrary to public policy.
The appellants appealed to this Court on fifteen grounds but during
the hearing of the appeal only the first three and the fifth grounds
were argued and the rest were abandoned.
The learned Justices of Appeal erred in law in
upholding an arbitration award for breach of
contract to the respondent in the absence of a
cause of action against the Appellants.
GROUND 1: ABSENCE OF CAUSE OF ACTION
1.
2.
3.
4.
th
6
Alcon International Ltd Kenya is struck off the
record of Civil Appeal No.2 of 2004.
Alcon International Ltd Uganda had the power to
instruct advocates.
Alcon International Ltd Kenya had no power to
instruct a firm of advocates.
Alcon International Ltd Kenya had no locus
standi in Civil Appeal No.2 of 2004, that was
Civil Appeal then pending in the Court of Appeal
of Uganda, or any more than thirty cases filed
on behalf of Alcon International Ltd Uganda still
pending in Courts.
Arguments of Parties:
The first ground of appeal is that the learned Justices of Appeal erred
in law in upholding an arbitration award for breach of contract to the
respondent in the absence of a cause of action against the
appellants. Mr. Tumusingize learned counsel for the first appellant,
submitted that according to the pleadings the first appellant entered
into a contact on 21 st July 1994 with Alcon International Ltd, a
company incorporated in the Republic of Kenya with the address of
Enterprise Road Industrial Area, P.O. Box 4169, Nairobi. Despite
this, the Court of Appeal in Civil Application No 50 of 2007 found that:
This ruling was delivered on 18 tn February 2008 before the
substantive appeal was heard in the Court of Appeal on 5 th April
2009. Therefore, by the time the appeal was heard in the Court of
Appeal, the respondent was Alcon International Uganda.
7
It was counsels ’ contention that therefore at the same time the Court
of Appeal heard the appeal, Alcon International that had filed the sit,
the one that went for arbitration and the one that was in the Court of
Appeal before it was substituted was the Alcon International
incorporated in Kenya.
Learned counsel pointed out that apart from the building contract,
there was a co-financing agreement between NSSF and the same
Alcon International incorporated in Kenya. He argued that the thrust
of the plaint was for breach of Contract and orders sought for
damages for wrongful termination of contract. These were the same
grounds argued during the arbitration and the contracts provided the
basis upon which the arbitrator gave his award.
He submitted that the issue then was whether at the time the Court of
Appeal heard the appeal, Alcon International Uganda did have any
cause of action in the circumstances. The . answer according to
learned counsel was no because they were never a party to the
contract. They could only have had a cause of action by pleading
assignment because that is where they would have derived their
right. According to Clause 17 of the building contract, any
assignment would have required the consent of NSSF. The clause
reads ‘ The contract shall not without the consent of the
employer (NSSF) assign the contract. ’ Therefore the only way
Alcon Uganda could have derived a cause of action would have been
with the consent of NSSF.
8
I
It was counsel ’ s contention that at the time the Court of Appeal sat to
hear the appeal, the respondent Alcon International Uganda that had
been substituted could never have had a cause of action on the
pleadings as they were because the pleadings were pursuant to a
contract to which Alcon International Uganda was never a party. He
concluded that the only means through which they would have had a
cause of action, the assignment, was contrary to the signed contract
and was never pleaded, and was never proved.
Mr. Tumusiime for the respondent, submitted that at all times Alcon
International Ltd referred to as a private limited liability company
Mr. Tumusinguzi referred to the case of Lindens Gardens Trust
Lenestat Sludge Disposals Ltd (1994) AC 85 (1993) 3 A II ER 417
case which considered a prohibition clause that prohibited
assignment in similar terms to this Clause 17. He pointed that the
holding in the case was that where an assignment is done .first of all
as a point of law there is a prohibition on assigning the burden of a
contract, secondly that where an assignment is done where there is a
prohibition in contravention of a clause, then there cannot be an
effective assignment, and thirdly on that point it also gives the
rationale of why there is that prohibition because simply a party has
contracted to deal with party A and it has contract with party A
because of the expertise or the skills. He argued that if that party has
got to bring another party then it is only critical that its consent must
be sought because you cannot know whether the other party brings
to the table the same skill and experience that this other party is
coming with.
9
NSSF ‘ recognised Kultar Hanspal as the Managing Director of
Alcon International the Ugandan company and did not ever
correspond with Davinder Hanspal who is the Managing
Director of the Kenyan company.
All correspondences between NSSF and Alcon were addressed
to the Managing Director Kultar Hanspal Alcon International
Ltd, P.O. Box 9598, Kampala and not 47160, Nairobi.
All payments were made by NSSF to Alcon International Ltd
Uganda and it is to this company that the notice of termination
of contract were sent.
carrying on the business of construction in Kampala. This was the
same description used in the High Court Civil Suit 1255 of 1998 and
in the arbitration. It never described itself as Alcon International
Kenya.
Learned counsel maintained that the issue of cause of action can be
answered by a simple question of who constructed Workers ’ House?
To counsel that is where the cause of action is derived from. In Civil
Application No. 50 of 2007, he argued, the Court ‘ established beyond
doubt that it ’ s not a Kenyan company but a Uganda company which
performed the construction contract with NSSF. Furthermore he
contended that,
10
Learned counsel admitted that contrary to what was stated in High
Court Civil Suit 1255 of 1990, it was not Alcon Uganda that had
signed the construction contract but it was assigned to them. They
The instructions to the law firm Tumusiime, Kabega and Co.
were by letter from the Directors of this company in Uganda.
The attached minutes of meetings of Alcon International with
NSSF clearly show who was attending meetings.
Mr. Kultar Hanspal and Mr. Rajesh Kent were charged with
failing to pay workers in Uganda after the termination of this
contract.
All financial statements of Alcon Kenya for the period of the
contract do not show that Alcon Kenya had any assets of any
kind or any operations in Uganda.
k i
Counsel argued that the Court of Appeal accepted the evidence of
Rajesh and Manjit Kent that shortly after the signing of the contract
an arrangement was reached in the Hanspal family whereby the
construction of Workers ’ House would be done by Alcon International
Uganda which would take responsibility for all assets and liabilities
arising from the building contract. Counsel for the respondent
maintains that there is a lot of evidence to corroborate the evidence
of the assignment of the construction contract. Mr. Kultar Hanspal ’ s
affidavit clearly states that the assignment was brought to the
attention of the management of NSSF.
11
I
He also maintained that a cause of action emanates from the monies
owed to them by NSSF to whom a loan of US$1,248,000 was given
and not repaid. The arbitrator also found that there was a sum of
US$3,435,727 owed to Alcon for the work done and not paid. Before
the termination of the contract, the respondent had plant machinery
and materials worth US$ 2.781.528.52. These were confiscated by
the appellant and have never been returned. There was also loss of
opportunity where the land arbitrator made a provision for 50% as
apportionment of loss of profit.
Despite the fact that the company in Uganda did not have the track
record in construction, the Managing Director of the Kenyan company
was the same person who moved to Uganda and started the
company here therefore as far as experience and resources are
concerned, it was the same human being who had that experience in
Kenya who was translating that experience that was needed in
Uganda. The project ’ s quantity surveyor confirmed that the
contractor successfully completed 19 floors and the consultants were
satisfied.
stated that by virtue of the assignment, they took themselves right in
the shoes of the signatory of that contract. The assignment was
made before the first brick was laid. There was a co-financing
agreement that was also signed by Alcon International Kenya before
construction commenced and a supplementary agreement in 1996
that was signed by Alcon Kenya and equally assigned to Alcon
Uganda.
I
12
I
Counsel pointed out that Mr. Kultar Singh himself stated in his
affidavit that the Government of Uganda insisted that they wanted a
company with a track record in construction which is why the contract
was executed by Alcon International Ltd of Enterprise Road, Nairobi.
Counsel also submitted that this ground should not have been
brought as a ground of appeal as it had never been brought before
the court before. After the decision in Civil Application No 50 of 2007,
the appellants had the opportunity to challenge the decision but they
did not do so. The Court of Appeal could not deal with the matter
because it was functus oficio and rule 22 of Court of Appeal Rules
was not applicable. The appellant therefore slept on their rights, he
concluded. He prayed that the first ground of appeal should fail; ; .
In response to arguments made by learned counsel for the
respondent, counsel for the 1 st appellant maintained that the contract
was signed between themselves and Alcon. Kenya and all letters
were addressed to Alcon International which had an address in
Kampala, but this is the norm for any company doing business within
the country. There is also nothing within the contract that denotes
that the word contractor would refer to assignees, administrators or
successors in title. There was no account titled Alcon International
Uganda to which NSSF paid money into and it also never paid any
money into a Kenyan Bank. The co-financing agreement was
between Alcon International Kenya and NSSF, the contract
termination letter was sent to the Alcon address in Kampala because
any company doing business in the country will have a local address.
h
B
II
I
R
13
0
!
n
I:
ii
h
Ii
|i
Counsel asserted that if there is evidence that counsel for the
respondent was aware that Alcon Uganda was the ones actually
doing the construction then the respondent would not have gone
ahead to file pleadings that portrayed the plaintiff and subsequently
the claimant as Alcon International Kenya because the plaint was
based on breach of contract, which was executed by Alcon
International Kenya. Counsel for the appellant maintained that NSSF
was not privy to any of this information at the time.
He goes on to say that the subject contract had nothing whatsoever
to do with Alcon International Uganda or Alcon International UK.
I
Turning to the alleged assignment, learned counsel submitted that if it
is true that the assignment was done ‘ even before the first brick was
laid ’ , why then would Alcon Kenya sign the supplementary agreement
in 1996 almost 2 years after the date of the contract since the proper
course of action would have been that Alcon Uganda had assumed
all the rights. Apart from the case earlier referred to which clearly
demonstrates that there can be no assignment under Clause 17,
counsel made reference to Emden ’ s Construction Law which states
that "there can be no effective unilateral assignment of the
burden of a contract. A contractor A cannot without the consent
of his employer B assign the burden of the contract to another"
If the cause of action had been in the assignment the defence would
have been different and the arbitration would not have proceeded the
way it did.
I
I!
0
0
14
0
f!
The arbitration was based on various clauses within the contract such
as Clause 25 which set the grounds and procedures for the
termination of the contract by the employer. The arbitrator found that
‘ the termination of the contract was in breach of Clause 25 of the
contract. ’ The damages awarded were also based on details within
the contract such as the employer ’ s use of the contractor ’ s
equipment. Based on the available evidence, both the High Court in
Miscellaneous application No.4 17 of 2001 and the Court of Appeal in
Civil Appeal No 02 of 2004 upheld the arbitration award. It was not
until Court of Appeal Civil Application No 50 of 2007 when the
manipulation of company names by the Hanspal Family came to light
that the court decided that Alcon International Limited (Kenya) has no
locus standi in Civil Appeal No.2 of 2004 and should be struck off.
Consideration of The Submissions and the Law:
The appellants contend that the respondent (Alcon International
Limited, Uganda) has no cause of action because the basis of this
suit is the contract that was signed between the first appellant (NSSF)
and Alcon International Limited, Kenya, of which Alcon (Uganda):was
not a party.
This finding was based on the evidence that it was Alcon International
Limited (Uganda) that had constructed Workers House. The Court
still found that Kultar Hanspal had signed the contract on behalf of
Alcon International Limited (Kenya). Counsel for the respondent,
Alcon International Limited (Uganda), admitted that it was indeed
Alcon International Limited (Kenya) that signed the contract, the co
financing agreement and the supplementary agreement.
1. - '
I
n
n
o
15
1
What is clear from this quotation is that while assignment or indeed
novation is permitted by law, there still has to be a fulfillment of the
elements necessary for a valid contract. There must be offer and
Taking into account the above facts, I am of the view that the cause
of action is derived from the contract and therefore it is the Alcon
International Limited (Kenya) that can make a claim in this regard.
It should be noted that Alcon International Limited (Uganda) then
changed its case and pleaded assignment instead of performance
instead. A valid assignment would give them locus standi to bring
this claim. The issue of assignment of contract was dealt with in Civil
Application No 50 of 2007 and the conclusion of the Court of Appeal
was that the Alcon which signed the contract is not the Alcon that
performed the contract. The respondent explains this by stating that
there was an assignment of the contract, following an agreement
within the Hanspal family that despite not having been successful
during the tendering process, Alcon Uganda would perform the
contract. In Halsbury ’ s Laws of England, 4 th edition, Vol. 9, it is
stated:
u
"As a rule, a party to a contract cannot transfer his
liability under that contract without the consent of the
other party There is however, no objection to the
substituted performance by a third person of the
duties of a party to the contract where those duties
are not connected with the skill, character, or other
personal qualifications of that party. ..... by the
consent of all parties, liability under a contract may
be transferred so as to discharge the original
contract. Such a transfer is not an assignment of a
liability but a novation of the contract. ”
I
I
li
B
II
I '
H
16
0
n
According to this authority, the assignment did not fulfill the
requirements necessary in order to be construed as legal assignment
J
The same case also held that “ an attempted assignment of
contractual rights in breach of a contractual prohibition is
ineffective to transfer such contractual rights ... if the law were
otherwise, it would defeat the legitimate commercial reason for
inserting the contractual prohibition, viz, to ensure that the
original parties to the contract are not brought into direct,
contractual relations with third parties. ”
The Linden Gardens Trust ltd vs Lenesta Sludge Disposals Ltd
and Others case (supra) further clarifies this when it states that
“ Clause 17 of the JCT form of building contract prohibited the
assignment of any benefit of the contract ... and an attempted
assignment of contract rights in breach of the contractual
prohibition in Clause 17 was ineffective to transfer any such
contractual right to the assignee."
acceptance between the parties, and there must be an intention to
create legal relations. All these require both parties to be aware of
whom they are contracting with. The principle upholds the doctrine of
the privity of contract which states that ‘ a contract cannot confer
rights, or impose obligations on strangers to it. ’ It is also clear that
there has to be consent from both parties, which makes the
arrangement within the Hanspal Family, without the knowledge of
NSSF an invalid assignment.
I
I
II
17
|-
i
The respondent contended further that it has a cause of action based
on the money it loaned to NSSF which includes 1.248.000/= which
was given and not repaid the sum of US$ 3.435.727 that the
arbitrator found was owed to Alcon for the work done and not paid,
and the US$ 2.781.528.52 for the plant machinery and materials that
were confiscated by the 1 st appellant and have never been returned.
There was also loss of apportionment where the learned arbitrator
made a provision for 50% as apportionment of loss of profit.
Counsel for the respondent also maintained that .they had a cause of
action because they performed the contract. The respondent relies
on the affidavits of Rajesh and Ranjit Kent as proving the assignment
as well as the finding of the court in Civil Application No 50 of 2007
that it is established beyond doubt that it is not a Kenya company but
the Uganda company which performed the construction contract with
NSSF.
Counsel also submitted while Alcon International Limited (Uganda)
may have constructed the building, legally, they have no cause of
action since they did not sign the contract. Without a valid
assignment either, NSSF may not owe Alcon (Uganda) anything.
They might be able to bring a case against Alcon International
(Kenya) for the money owed, based on whatever internal agreement
they claim they had.
by law. Therefore Alcon (Uganda) cannot base their claim on
assignment.
I
I - '
I
II
II
I!
II
18
n
The money that was loaned to NSSF was awarded at arbitration for
breach of the Co-Financing Agreement. It has since then come to
light, and been acknowledged by counsellor the respondent that it
was in fact Alcon Kenya that signed the Co-Financing Agreement as
well as the contract. For that reason, Alcon Uganda is not entitled to
that money.
The respondent also argues that this ground should not have been
brought as a ground of appeal as it had never been brought before
the Court of Appeal. After the decision in Civil Application No 50 of
2007, the appellants had the opportunity to challenge the court but
they did not do so. They would have been able to raise some of the
issues before in the Court of Appeal before that Court became
functus officio and Rule 2(2) of Court of Appeal Rules was not
applicable. The appellants slept on their rights. The appellants on
the other hand maintain that this issue was already brought up in the
Court of Appeal Civil Application No 149 of 2010 but was dismissed
because the matters were subjudice in the Supreme Court and
NSSF did not dispute or rebut the claim regarding around the plant
machinery and materials. Since it has been proved that it was Alcon
Uganda that built Workers House, it is likely that material they used
was theirs. Rajesh Kent in his affidavit stated that NSSF had
promised to hand over the equipment once the work was done but
has never done so. Since there has been no evidence presented to
disprove this, Alcon Uganda could claim the cost for their plant
machinery and materials.
r
For these reasons, I would allow the first ground of appeal.
[
fl'
fl'
fl
19
fl
p
Arguments of Parties:
The second ground of appeal is that the learned Justices of Appeal
erred in law in upholding an arbitration award that was obtained
illegally or contrary to public policy. Ms. Mutesi for the 1 st Appellant
GROUND 2: AWARD OBTAINED ILLEGALLY OR CONTRARY TO
PUBLIC POLICY
Taking these matters into consideration, I am of the opinion that in
the interest of justice and taking into account the fact that the matter
could not be heard the Court of Appeal as it was subjudice in the
Supreme Court, it is important that it is heard here in this Court.
It must be emphasized that the matter could not be raised earlier
because of the fraud and misrepresentation perpetrated by the
respondent as we shall see later in this judgment.
therefore now that they are before the Supreme Court, it is only fair to
have them considered and resolved.
r ; •
r
The Court of Appeal found that it was functus officio and therefore
Rule 2(2) of the Court of appeal rules did not apply. The Court
therefore found that it did not have powers ‘ to entertain an
application that seeks orders to consider matters that the court
and other lower courts have already pronounced themselves on
(resjudicata) or are pending to be pronounced upon by the
Supreme Court (subjudice). ’ - ■■:■■■■ •:
i
(b)
(i)
I'
I
J
(1)
If
(2)
If
If
20
If
n
Learned counsel referred to Blacks Law Dictionary 6 th edn at page
163, for the definition of “ improper ” as something incorrect,
unsuitable or irregular or something which is fraudulent or otherwise
wrongful. She contended that the record shows that the respondent
in obtaining the arbitral award conducted itself in a manner that was
improper and which amounted to fraudulent conduct and which is an
illegality in the eyes of the law. She argued that there were two main
aspects of this ground of appeal, namely that; ,
The respondent fraudulently misrepresented itself in order to
obtain the award.
“ 1 (2) An arbitral award may be set aside by the Court
only if -
The respondent was found to have been manifestly fraudulent
in obtaining the contract itself.
the court finds that-
the award is in conflict with the
public policy of Uganda."
submitted that under Section 12 of the Arbitration Act where an
arbitrator has misconducted himself or an award has been improperly
procured, the Court may set it aside. She cited Section 34 of
Arbitration and Conciliation Act which provides: . . , ■
(vi) the arbitral award was procured by
corruption, fraud or undue means or there
was evidence of partiality or corruption in
one of the arbitrators; or
i
I
n
n
She submitted that these are all findings of fact arrived at by a court
law.
Learned counsel further submitted that this Court defined fraudulent
intent in the case of Fredrick Zaabwe vs Orient Bank & Others Civil
Appeal No 04/2006, as ‘ ‘ an intentional perversion of truth for the
purpose of inducing another in reliance upon it to part With
some valuable things belonging to him or to surrender a legal
right. A false representation as a matter of fact whether by
words or by conduct by false or misleading allegations or by
concealment of that which deceives and is intended to deceive
another so that he shall act upon it to his legal injury. ”
‘ ‘ An intentional perversion of truth for the purpose of
inducing another in reliance upon it to part with some
valuable thing belonging to him or to surrender a
legal right. A false representation of a matter of fact,
whether by words or by conduct, by false or
misleading allegations, or by concealment of that
which deceives and it is intended to deceive another
so that he shall act upon it to his legal injury.
Anything calculated to deceive, whether by single act
or combination, or by suppression of truth, or
suggestion of what is false, whether it is by direct
falsehood or innuendo by speech or silence, word of
mouth, or look or gesture ...... a generic term,
embracing all multifarious means which human
ingenuity can devise, and which are resorted to by
one individual to get advantage over another by false
suggestions or by suppression of truth, and includes
all surprise, trick, cunning, dissembling, and any
21
The Court in that case also cited the definitions provided in Blacks
Law Dictionary , 6 th edition, page 660 on the issue of fraud as
follows:
L- ’
I
The same Dictionary defines the word “ fraudulent ” as
I!
n
22
0
n
Counsel maintained that the respondent ’ s fraud is proved by
reference to the findings of the Court of Appeal in Civil Application No
50 of 2007. As these are findings of a Court they are no longer at the
level of allegations but are findings of fact that have never been
appealed against in that application.
The Court found that:
NSSF entered into an agreement with Alcon International
Kenya, but Alcon International Uganda executed the building
contract.
“ To act with “ intent to defraud ’ ’ means to act willfully,
and with the specific intent to deceive or cheat;
ordinarily for the purpose of either causing some
financial loss to another, or bringing about some
financial gain to oneself. ’ ’
unfair way by which another is cheated, dissembling,
and any unfair way by which another is cheated,
“ bad faith ” and “ fraud ” are synonymous, and also
synonymous of dishonesty, infidelity, faithfulness,
perfidy, unfairness, etc
As distinguished from negligence, it is always
positive, intentional. It comprises all acts, omissions
and concealments involving a breach of a legal or
equitable duty and resulting in damage to another.
And includes anything calculated to deceive, whether
it be a single act or combination of circumstances,
whether the suppression of truth or the suggestion of
what is false whether it be by direct falsehood or by
innuendo, by speech or by silence, by word of mouth,
or by look or gesture ....... ’ ’
fl
fl
23
fl
n
Concealing its identity as Alcon International Uganda from the
arbitrator, the High Court and thereby preventing the claim and
the suits from being properly determined.
Alcon International Uganda constructed Workers ’ House and it
is the one that filed Civil Suit No 1255 of 1998 but it is not the
one that signed the contract, that was'Alcon Kenya , and they
concealed this material fact.
Misrepresentation of filing and prosecuting the suit and
arbitration claim by describing itself as a party as Alcon
International Kenya, and by describing itself as a party to the
subject contracts.
There was manifest deceit in those actions of
misrepresentation, there was concealment that was misleading
and the arbitrator acted on those misrepresentations to give a
benefit to the respondent who had been described as another
person.
Both companies applied for the contract. NSSF said it
specifically wanted to deal with Alcon Kenya based on its past
record which Alcon Uganda did not have. Although this was
made clear, after Alcon Kenya won the contract, it immediately
assigned it to Alcon Uganda in an internal family arrangement.
An award which was procured like that by fraudulent
misrepresentation would be illegal and contrary to public policy.
u
I
u
n
24
I!
p
Mr. Tumusiime for the respondent disagreed with the submissions of
learned counsel for the 1 st appellant. He maintained that an arbitral
award can only be challenged under S.12 of the old Arbitration Act
The finding of the Court was that NSSF had insisted on using a
company with a track record of construction which Alcon
Uganda did not have which is why Alcon Kenya was used in
order to win the contract.
On the basis of these findings by the Court of Appeal, Ms. Mutesi
submitted that the arbitral award should be set aside having been
obtained by fraud. She contended that fraud is an illegality and that
"a Court of law cannot sanction that which is illegal ” as held in
the case of Makula International vs His Eminence Cardinal
Nsubuga & Another, Civil Appeal No 4/1981 (CA) and Active
Automobile Spares Ltd vs. Crane Bank Ltd, Civil Appeal No
21/2001 (SC).
The assignment itself was fraudulent as it was a collusion
between the two Alcons without the knowledge of NSSF and
therefore cannot be the basis of any claim. In Farm
International Ltd, Ahmed Farah vs Mohamed Hamid Farih
Civil Appeal No 16/1993, the Supreme Court cited the principle
that “ No court will allow a person to keep an advantage
which he has obtained by fraud. Fraud unravels everything
the Court is careful not to find fraud unless it is distinctly
pleaded and proved but once it proved it vitiates contracts,
judgments and all transactions whatsoever. ”
I!
25
n
F
On the issue of whether the respondent obtained and sustained the
contract through corruption and bribery and whether it can be allowed
to take any advantage of the claim, counsel submitted that the
learned arbitrator agreed with the respondent and relied on Order 6
Rule 2 of the Civil Procedure Rules. He decried the lack of
particulars, pleading and evidence to confirm these allegations of
fraud, corruption and bribery and therefore dismissed the issue.
Counsel maintained that appellants had the opportunity to amend
their pleadings and plead fraud but they did not do so. He submitted
that in Stephen Lubega vs Barclays Bank , Civil Appeal No. 2/92 the
He argued that counsel for the 1 st appellant had made no reference
whatsoever to the words error of law on the face of the record. Even
if the appellants had a right under s.12 of the Arbitration Act, Rule 7
of the Arbitration Rules gave them only 8 weeks to apply to set aside
the award. He pointed out that it has been 11 years and under S 34
of Cap 4 they would have had 30 days. Counsel submitted further
that the appellants had attempted to bring a similar argument in Misc.
App. No. 149 of 2010 but the application was struck out by the Court
of Appeal. -
(Cap 55) or under S.34 of the Arbitration and Conciliation Act (Cap 4).
He submitted that the appellant proceeded under S.12 on the
grounds that the award was obtained illegally and contrary to public
policy. This is erroneous because under S 12 the award can be set
aside only where: the award is improperly procured or; the arbitrator
has misconducted himself and by extension where there is an error of
law, on the face of the record.
I
p
26
n
n
In reply, learned counsel for the 1 st appellant argued that though the
respondent claims they never described themselves as Alcon Kenya,
the plaint presented shows that the respondent was a party to the
contract. The Court of Appeal itself found that there were a lot of
"dubious practices in the dubious dealings of the Hanspal
family. A few examples include the manipulation of names of
their companies in a manner calculated to confuse any tax
authorities or those individuals and entities they deal with. ’ One
court clearly stated that “ fraud must not only be pleaded, it must
be particularised." He argued that it is settled law that a party is
bound by its pleadings as these define issues in controversy to be
adjudicated upon.
Counsel referred to the case of Fredrick Zaabwe Case (supra) which
was relied on by the appellant, and submitted that the court states
that “ a false representation of a matter of fact whether by words
or conduct by false or misleading allegations or by concealment
of that which deceives and is intended to deceive another so
that he shall act upon it to his legal injury. ” The Court went on to
state that the term “ legal injury" comprises all acts, omissions and
concealments involving a breach of a legal or equitable duty and
resulting in damage to another. Counsel contended that the
appellant has never alleged that he lost anything. He submitted that
fraud is a serious allegation and the particulars must be pleaded and
proved. Order 6 Rule 3 goes into detail about what must be shown:
time, place etc. None of these have been pleaded. He prayed that
the second ground be allowed. ■
I!
H
27
r
F
of the ways this was done was through the interchanging of Directors
particularly the Managing Director of Alcon Uganda, who is also a
Director in Alcon Kenya, on whose behalf he signed the contract.
She reiterated her submissions that no evidence has been provided
of the assignment apart from the affidavits of the Directors who have
been proved to be not credible.
Counsel argued further that all the various misrepresentations by the
respondent amount to fraud. When the Court asked counsel “ has
your case now changed that you are pleading as assignee and
not beneficiary?" He answered yes. This was a material fact that
was concealed in order to obtain a benefit and was therefore
fraudulent. She submitted further that the Court of Appeal in its ruling
On the issue of whether the conduct of the respondent amounts to
what is contrary to public policy, counsel cited the Kenya case of
Christ for All Nations vs Apollo Insurance Co. Ltd (2002) 2 EA
366 in which the issue of setting aside of an arbitrator award was
considered, the court stated that “ public policy would cover
anything that was either inconsistent with the Constitution or
the Laws of Kenya or whether written or unwritten, that was
against the national interest of Kenya or was contrary to Justice
and morality. With regards to morality the Judge said 7 would
again without seeking to be exhaustive include such
consideration as whether the award was induced by corruption
or fraud whether it was founded on a contract contrary to public
morals. ’ It was her contention that an award that is induced by fraud
or fraudulent misrepresentation is against public policy.
I!
n
28
B
F
in Application No 50 of 2007, noted that under the laws of. Uganda
these practices would be considered criminal. She pointed out that
the Penal Code criminalizes the action of false pretence and in as far
as the definition of public policy includes anything that is contrary to
the laws whether written or unwritten, then by going to court and
withholding information that misleads a judicial officer into giving you
a benefit that conduct is contrary to public policy. She submitted that
as far as the pleadings are concerned the respondent specifically
claimed to be a party to the contract which it later on in the Court of
Appeal admitted that it was not. She contended that this would
amount to the offence of perjury which is criminalised under S.94 of
the Penal Code Act.
She concluded that as regards the standard of proof required for
fraud, what was presented was based on findings fact of a court
which have not been appealed against and are therefore not
reversible. She contended that there is ho higher authority than the
court. Therefore the appellant was relying on findings of fact of a
court on who signed the contract and who instituted the suit, and the
court itself found that the contract tender was fraudulently won. She
prayed that the award be set aside as it was obtained by fraud and
fraud vitiates everything.
Learned counsel submitted further that although certain issues were
raised about the ground of appeal not falling within S.12, this section
still states that an award that is improperly procured may be set
aside. Therefore an allegation of illegality in procuring that award
falls squarely within S.12 because fraud is an illegality.
(2)
(b)
11
29
I
The first issue that must be dealt with is whether this appeal is barred
by limitation. Under the above Section counsel for the respondent
submitted that Under S.12 Cap 55 of the Arbitration Act, Rule 7 of the
Under the old arbitration Act (Cap.55) an arbitral award could be set
aside by the Court where the arbitrator has misconducted himself or
an arbitration has been improperly procured.
An application for setting aside the arbitral award may not be made
after one month has elapsed from the date on which the party making
that application has received the arbitral award or if a request has
been made under Section 33, from the date on which that request
had been disposed of by the arbitral award.
Consideration of Submissions and the Law:
The complaint in this ground of appeal is that the learned Justices of
Appeal erred in law in upholding an award that was obtained illegally
and contrary to public policy. Section 34 of the Arbitration and
Conciliation Act (Cap 4) provides inter alia, -
■>
An arbitral award may be set aside by the court
only if -
(a) the party making the application furnishes
proof that -
(vi) The arbitral award was procured by
corruption, fraud or undue means or
there was evidence partiality or
corruption in one or more arbitrators;
■ or . ■ ’ . ■:
The court finds that -
(ii) the award is in conflict with the
public policy of Uganda
I
30
I .
k
^Jb
One of the principles of law stated in Makula International (supra) is
that as long as there is an illegality it can be raised at any time as "a
court of law cannot sanction that which is illegal. ” Counsel for the
appellant maintains that the arbitral award was procured by
fraudulent means, which is an illegality which this court must act
Arbitration rules gave them only 8 weeks to apply to set aside the
award. It has been 11 years. Under S 34 of Cap 4 they would have
had 30 days. The arbitral award was dated 21 March 2001. But for
the appellant it is contended that this situation is different as once a
matter is on appeal then time cannot be said to be running against
something that was not even pleaded, as was stated in Makula
International (supra). This is in reference to Misc. Application No
149 of 2010 of the Court of Appeal which was also referred to by
counsel for the respondent who maintains that the issue was not
addressed. Counsel for the 1 st appellant argues that the reason why
this happened was because the matter was pending before the
Supreme Court and was therefore subjudice.
In Makula International Case the Court stated that as long as there
is some matter of illegality discovered it can be raised at any time
even if the appeal itself is totally incompetent. Counsel further
submitted that all these facts came to the knowledge of the 1 st
appellant after the Court of Appeal had made a judgment and it was
late in the proceedings in 2008 that these facts first came to light.
Therefore there was no opportunity for this challenge to be made in
the lower Court. It is for this Court allowed this ground to be added on
the amended Memorandum of appeal.
In Alcon International Ltd vs Kampala Associated Advocates
Civil Application No 50 of 2007, the Court of Appeal made the
following serious remarks regarding the conduct of the respondent:
Counsel for the respondent refers to the decision in Stephen Lubeqa
vs Barclays Bank (supra) where the court stated that ‘ fraud must
not only be pleaded, it must be particularized. ’ But counsel for
the 1 st appellant has made referenced the various incidences that
prove that the actions by Alcon International of substituting one
. company with another were a planned operation. The appellants also
proved this allegation by reference to admissions made by the
Directors of Alcon that assignment was made after a discussion
within the family members only.
upon. I agree and hold that due to the fact that the fraud was
discovered on appeal, the appellants were not barred from raising it
in this Court. The Alcon Managers and Directors knew this fact which
is why they concealed it. This conduct cannot be anything other than
a deliberate concealment of pertinent information.
“ There are a lot of dubious practices in the business
dealing of the Hanspal family. A few examples
include the manipulation of the names of their
companies in a manner calculated to confuse tax
authorities and those individuals and entitles they
deal with and the manner in which they contrived to
fraudulently win the Workers House construction
tender bid. Under the laws of Uganda, these
practices would be considered criminal. The worst
culprits of them are Kultar and Davinder Hanspal.
The two since 1971 crookedly registered and
manipulated dubious companies variously called
31
I
I
32
The issue of fraud or illegality in this case revolves around the identity
of Alcon International Ltd. As it became apparent in Civil Application
No 50 in the Court of appeal, the Alcon that signed the contract is not
the Alcon that performed the contract. The respondent explains this
by stating that there was an assignment of the contract, following an
agreement within the Hanspal family that despite not having been
successful during the tendering process, Alcon Uganda would
perform the contract.
However, while assignment or indeed novation are permitted by law,
there still has to be a fulfillment of the elements necessary for a valid
contract. I agree with counsel for the 1 ?t appellant that there must be
offer and acceptance between the parties, and there must be an
intention to create legal relations. All these require both parties to be
aware of who they are contracting with. Therefore to create a legal
assignment, notice in writing of the assignment must be given to the
debtor, or other person liable to make the payment in order to entitle
the assignee to bring an action for the money or the debt. This
principle upholds the doctrine of the privity of contract which states
that a contract cannot confer rights, or impose obligations on
t
Alcon International ltd (Kenya) (two companies),
Alcon International Ltd Uganda (originally Alcon
International Ltd (UK). The activities and the demise
of their other companies, namely Allied Concrete
Works and allied Contractors Limited are not known.
Nevertheless, we hold the view that these men are not
credible at all and they can only tell some truths by
accident. The evidence of Rajesh and Ranjit Kent as
corroborated by numerous documents attached to
the various affidavits of all the witnesses is
preferable."
I
I
I
33
I
The identity of Alcon is at the crux of the issue because according to
the 1 st appellant, Alcon fraudulently misrepresented itself not only at
the contracting stage but also during the performance of the contract,
and throughout the subsequent legal proceedings.
strangers to it. In this case it was necessary to have consent from
both parties, which makes the arrangement within the Hanspal family,
without the knowledge of NSSF fraudulent.
Black ’ s Law Dictionary (supra) defines fraud as “ An Intentional
perversion of truth for the purpose of inducing another in
reliance upon it to part with some valuable thing belonging to
him or to surrender a legal right. ” Fraud requires a willful act and
is therefore distinguishable from a negligent misrepresentation. A
representation is fraudulent not only when the person making it
knows it to be false, but also when he ought to have known or must •
be taken to have known that it was false. In this case, there has been
an admission by the respondent that the decision to have Alcon
Uganda do the actual construction of Workers House despite Alcon
Kenya having won the tender was made exclusively within the
Hanspal family. The reason why this information was hidden from
NSSF was because NSSF had already evaluated Alcon Uganda
during the tendering process and had deemed it incapable of fulfilling
the contract to the required standard. This was not just a case of
work being delegated to another capable company under the same
umbrella group of companies. In this situation, the second company
had been deliberately rejected in the award of the contract. The
Alcon managers and directors knew this fact which is why they
[■i
I
I
I
34
i
i
The Arbitration Act allows for 30 days in which to appeal an arbitral
award. However it should be noted that in law, fraud or fraudulent
The respondent rightly mentions that Under S.12 of the Arbitration
Act, an arbitral award can only be set aside where the award is
improperly procured or the arbitrator has misconducted himself and
by extension whether there is an error of law, on the face of the
record. However, it is also a well settled principle of law, that if a
transaction has been originally founded on fraud, the original vice will
continue to taint it, however long the negotiation may continue, or to
whatever ramifications it may extend. Not only is the person who has
committed the fraud precluded from deriving any benefit under it, but
an innocent person is so affected, unless there has been some
consideration moving from himself. Therefore, although the issue is
raised in relation to the arbitral award, it actually applies to the whole
which contract is tainted having been based on fraudulent
misrepresentation.
concealed it. This therefore cannot be anything other than a
deliberate concealment of pertinent information. Counsel for the
respondent rightly refers to Stephen Lubega vs Barclays Bank
(supra) where the court stated the 'fraud must not only be pleaded, it
must be particularized.' The appellant has made reference to the
various incidences that prove that these actions by Alcon of
substituting one company with another were a planned operation.
They also proved this allegation with reference to admissions by the
directors of Alcon for example over the assignment that was made
after a discussion within the family members only.
I ; ’
I
I
I
I
35
Mr. Lule for the 1 st Appellant submitted that the learned trial Judge
erred in sending the matter to arbitration as this reference was made
without jurisdiction and therefore anything out of it is a nullity.
Arguments of Parties:
The appellants contend that the learned Justices of Appeal erred in
law in holding that the learned Judge did not err in law in staying the
suit and referring the matter to Arbitration.
breach of contract postpones the period of the commencement of the
period of limitation.
GROUNDS:
ARBITRATION
On what amounts to public policy, the Kenyan case of Christ for All
Nations vs Apollo Insurance Co. Ltd (2002) 2 EA 366 indicated
that public policy would cover anything that was either inconsistent
with the Constitution or the Laws of Kenya whether written or
unwritten that was against the national interest of Kenya was contrary
to justice and morality. In this case, it is not enough to simply show
that a party was misled. Court must be satisfied that some form of
reprehensible or unconscionable conduct has contributed
substantially to the award being obtained. As has been proved,
Alcon deliberately misled NSSF by substituting one company with
another. The arbitral award was then given on the basis of fraudulent
information which might not have otherwise happened. The award
was obtained contrary to public policy. Accordingly, I would allow this
ground of appeal.
ERROR IN REFERRING THE MATTER TO
I
I
I
I
I
I
36
Dr. Byamugisha also argued that the arbitration could not even be
ordered by the court under Order 47 Rule 1 of the Civil Procedure
Rules. He stated that the learned Judge ought to have complied with
j
u
Counsel pointed out that when the matter came up for trial, the trial
Judge considered the plaint and the defences and having regard to a
provision in defence that the suit was premature on the ground that it
should have been referred to arbitration, the trial Judge then said that
is where it should go. He contended that the .trial Judge did not take
into account the provisions of law which give her the jurisdiction. The
Judge made the orders that temporary injunction should not be
issued against the respondents but that the main suit be stayed and
the matter referred to arbitration.
Learned counsel pointed out that the appellants then filed the appeal
in the Court of Appeal where Dr. Byamugisha who was counsel for
the appellants submitted that Section 17 of the Arbitration Act (Cap
55) (Laws of Uganda 1964 revision) provides for an order of stay of
the suit by the Court and reference of the matter to arbitration.
However, this order can only be made any time after appearance but
before filing a written statement of defence or taking any other Jn the
proceedings. He argued that in this case it was too late for the Judge
to refer to arbitration, after all the two defences had already been
filed, the application to amend the plaint had been made, heard and
the reply thereto had been filed. The court was therefore at the stage
of disposing of the application for a temporary injunction.
Furthermore, the parties had not yet been given the opportunity of
making any submissions on the reference to arbitration.
I
I
1
I
I
37
Counsel pointed out the learned Judge in her judgment stated that
the application is partially allowed and the Order sought under the
prayer, namely, any other or further orders that the court may deem
fit, is granted and it is further ordered that in the interest of-justice,
and for the speedy disposal of this matter, the main suit be stayed
and the matter be referred to arbitration Dr. Byamugisha submitted
that these therefore are the grounds given by the Judge as to why
she made that ruling and not under other any provision of the law.
He also referred to Order 43 Rule 1(1) of the Civil Procedure Rules
(old) now (0 47 R 1 (1) where it is provided,
"(1) Where in any suit all parties interested who are
not under disability agree that any matter in
difference between them in any such suit shall be
referred to arbitration, they may, at any time before
judgment is pronounced, apply to court for an order
of reference."
express provisions of order 47 instead of invoking the inherent
powers of the court which was erroneous. He added that the inherent
powers cannot be invoked where there is an express provision of the
law. He cited Article 126 of the Constitution to the effect that courts
must first and foremost apply the law even under the unlimited
jurisdiction of the High Court as provided for in Article 1 39(,1 ) ;of the
Constitution and Section 14(2) of the Judicature Act. Counsel
contended that the jurisdiction was ousted by an express provision of
the law and therefore the staying of the suit and the ordering of
arbitration were without jurisdiction.
38
■
It was counsel ’ s submission that the import of this rule is that the
court can only refer a matter to arbitration upon written application by
one of the parties and the court then has power to make an order of
reference after the consent of all parties.
Dr. Byamugisha for the 2 nd Appellant submitted that the trial Judge
erred in law in staying the suit and referring the matter to arbitration in
respect of the 2 nd Appellant who was not a party to the arbitration
clause and this was not justified either under the Arbitration Act or
Order 43.
On whether the High Court has the inherent power to stay a suit and
refer it for arbitration, counsel for the respondent contended that in
Yuqasta Construction vs Coffee Marketing Board , Arbitration
Cause No 1/94 it was noted that under the Constitution of Uganda
Mr. Tumusiime, learned counsel for the respondent, submitted that
the contract that parties entered, into was an East African Institute of
Architects Model which had an arbitration clause. When the parties
started having disputes, the 1 st appellant gave to the respondent a
notice to terminate the contract. The respondent responded by
requesting the 1 st appellant to submit to arbitration in accordance with
clause 36. The 1 st appellant refused this and a week later terminated
the contract. Following that, the respondent filed High Court Civil suit
No. 1255 of 1998 and under that suit filed Application No 542 of 1999
to get a temporary injunction principally to stop NSSF from giving the
contract to another party until the parties have gone to arbitration or
have gone to court under Rule 55 and resolved their disputes.
I
I
11
[
r
39
I
I
and the Judicature Act, the High Court has unlimited original
jurisdiction over all matters criminal and civil subject to written law.
He contended that in that case they were trying to challenge the
appointment of an arbitrator by the High Court. It is a cardinal
principle of arbitration law and practice, counsel submitted, that
where there is an arbitration clause, courts will always refer the
dispute to arbitration. He relied on various cases including Wellsford
vs Watson Homes and Overseas Insurance (1870) 3 CH 257and
the Tanzanian Court of Appeal decision of Construction Engineers
and Builders vs Sugar Development Corporation. (1985) LRC
(Comm) 596 In the Tanzanian Case, the Court of Appeal stated:
“ I venture in things that not enough attention has
been directed to the true nature and functions of an
arbitration clause in a contract. It is guite distinct
from the other clause, the other clause set out the
obligations which the parties undertake towards each
other but the arbitration clause does not impose on
one of the party ’ s an obligation in favour of the other.
It embodies the agreement of both parties that if any
dispute arises with regard to the obligations which
the one party has undertaken to the others such
dispute shall be settled by a tribunal of their own
constitution. And there is this very material
difference that whereas in an ordinary contract the
obligations of the parties which other cannot in
general be specifically enforced and breach of them
results only in damages the arbitration clause can be
specifically enforced by the machinery of the
Arbitration Acts. The appropriate remedy for breach
of the agreement to arbitrate is not damages but
enforcement. Moreover, there is the further
significant difference that the courts of England had
discretion power of dispensation as regards
arbitration clauses which they do not possess as
regards the other clauses of the contract. ”
I
u
I
40
r
i
h
He pointed out that in this case the Court was looking at exactly
Clause 36 of the East African Institute of Architects Building Model
type of contract. Counsel maintained that the two parties therefore
had to submit to arbitration. Section 17 of old Arbitration Act, Cap 55
which the appellant referred to refers to instances where one of the
parties goes to court and applies for stay and does not cover
instances where the High Court invokes its own jurisdiction to stay
the proceedings and refer them to arbitration. .
Counsel for the respondent further argued that this ground of
jurisdiction should not even be entertained at all by this Court for two
reasons. On the record of appeal there is Miso: Application No.417 of
2001 which was filed together with Arbitration Cause No 04 of 2001
which her Lordship consolidated. In Misc. Application No.417, the
appellants applied to remove the arbitrator after the arbitrator had
filed the award. Her Lordship found that this application had been
overtaken by events. The application was premised on the same
grounds like the ones we have here that the court made a mistake to
stay the proceedings and refer the matter to arbitration and for that
reasons they wanted the arbitrator removed. Since that application
failed and was abandoned, it cannot be raised here as this is not an
appeal against Misc. App. 417/2001. Secondly, following trial Judges
ruling, counsel for the appellant filed a Notice of Appeal against the
ruling on 14 th October 1999. On 1 st October 2003, he got a record of
proceedings from the court but up to today, that Notice of Appeal has
been lying in the court and nothing has been done. It is 13 years
later and this issue cannot now arise. It belongs to that appeal and it
is in that appeal that this ground should have been addressed.
J ■
i
I
L
41
Consideration of the Submissions and the Law:
In Misc. Application No 0542 of 1999, the respondent applied for a
temporary injunction to stop the new contractor Roko Construction
Company from executing the contract until the suit the respondent
had filed is determined.
Mr. Tumusiime then submitted that the issue of waiver and
acquiescence was discussed in a decision of the Supreme Court of
India in Prasun Roy vs Karcata Metropolitan Development
Authority (1988) LRC (Comm) 596. In that case, the arbitrator was
appointed by a court that had no jurisdiction to appoint an arbitrator
and the parties went to arbitration and after 74 hearings, but before
the award was made, one of the parties sought to challenge or to
impeach the proceedings on the basis that the court which had
appointed the arbitrator did not have jurisdiction. The court held that
in participating in the proceedings they waived their rights and could
not challenge the proceedings. In that case the award had not even
been made.
Counsel referred to the case of Suleiman Vaco vs Lakhani and
Co.(1957) EA 49 Counsel also referred to S.4 of the Arbitration and
Conciliation Act that states that “ where a party to arbitration
proceedings knows of any part of the act that is not being
followed and continues to participate in these proceedings
instead of going to court to apply for relief that party should not
be heard to complain or should not raise that issue after that. ”
r.- '
i
42
The learned trial Judge refused to grant the application for temporary
injunction and instead ordered the suit to be stayed and the matter to
be referred to arbitration. The learned Judge stated:
I
II
“ if this injunction is granted it will interfere with the
contract of Roko Construction, 3 rd party and the 1 st
Respondent will face another suit by Roko
Construction. On the other hand if the injunction is
not granted, the applicant will suffer some
inconvenience, which in my view can be taken care of
under Clause 25 of the Contra ct signed between the
two parties which provide for the rights of the
contractor in case of termination by the employer.
Most importantly, the parties have a right to
arbitration in case of any dispute or difference
between the parties during the progress of the works.
Clause 36 of the contract provides, that such
disputes or difference shall be referred to an
arbitrator to be agreed on by parties within 14 days of
notice, failing which an arbitrator shall be appointed
by the Chairman or Vice Chairman of the East African
Institute of Architects, who may delegate such
appointment to be made by the chairman or vive
chairman of the local (national) society of Architects
- in this case the Uganda Institute of Architects.
Finally according to Kakooza ’ s affidavit, the status
quo has changed and there is therefore no status quo
to be maintained by any injunction order. In the
circumstances and for the reasons stated herein
above, the orders sought in 1, 2, 3 and 5 are not
granted. Instead the application is partially allowed
and the order sought under 4, namely any or further
orders that the court may deem fit is granted and it is
further ordered that in the interest of justice, and for
the speedy disposal of this matter:- (i) The main suit
be referred to arbitration (2) The parties agree on an
independent arbitrator within 14 days from the date
thereof (3) Failure of which the applicants shall refer
the matter to the Chairman of the East African
I
I
43
The learned Justice of Appeal observed, quite correctly in my view,
that the import of this rule is that the Court can only refer a matter to
arbitration upon written application by one of the parties and the
Court has power to make an order of reference after the consent of
all the parties to the case before it. The learned Justice of Appeal
then went on to say,
In the Court of Appeal, Mpagi Bahigeine JA (as she then was) who
wrote the lead judgment referred to the above conclusion of the trial
judge and then cited the provisions of old order 43 rule 1 (I) of the
Civil Procedure Rules which is now O 47 R 1 (i) which states:
“ Where in any suit all the parties interested who are
not under disability agree that any matter in
difference between them in such a suit shall be
referred to arbitration, they may, at any time before
judgment is pronounced apply to court for order of
reference. ”
Institute of Architects to appoint an arbitrator in
accordance with Clause 36 of the contract."
"In the instant case, none of the parties applied for
the matter to be referred to arbitration as per order 43
R 1(1) of the old Civil Procedure Rules. The Judge
relied on the prayer any other or further orders that
the court may deem fit, to stay the main suit and
referred the matter to arbitration. She made an order
of reference at the time of hearing an application for
an order of interlocutory injunction, when the main
suit was set for hearing but before judgment. I do
consider that the time was opportune for the court to
make such order.
-
I
j
44
However, the learned Justice of Appeal found a justification for
reference to arbitration in Clause 36(i) of the contract which provided,
In the first place there had been no such application for reference to
arbitration, nor had the parties agreed to the reference.
I
“ Provided always that in case a dispute or difference
shall arise between the Employer or Architect on his
behalf and the Contractor or either during the
progress or after the completion or abandonment of
works, as to the construction of this contract or as to
any matter or thing left by this contract to the
discretion of the Architect or the withholding by the
architect of any certificate to which the contractor
may claim to be entitled to or the measurement and
valuation mentioned in Clause 30 (5) (a) of these
conditions or the rights and liabilities of the parties
under clauses 23, 25, 32, 33, 34 of these conditions,
then such a dispute or reference shall be and is
hereby referred to the arbitration and the final
decision of the person to be agreed between the
parties or failing agreement within 14 days after either
party had given to the other a written request to
concur in the appointment of an arbitrator a person to
be appointed on a request of either party by the
Chairman or Vice Chairman for the time being of the
East African Institute of Architects who will, then
appropriate, delegate such appointment to be made
by the Chairman or Chairman of the Local (National)
Society of Architects (4) The award of such arbitrator
shall be final and binding on the parties."
Clearly the learned Justice of Appeal considered that the trial judge
was justified in making the order referring the matter for arbitration
under the Rules cited. I think the learned Justice of Appeal was
wrong in so holding.
45
The learned Justice of Appeal then observed that in fact the arbitrator
had stated in his decision that he did not receive any objection by any
The learned Justice of Appeal went on to observe that by
incorporating the above clause in their contract both the appellants
and the respondent, for all intents and purposes recognized
arbitration as an effective and efficient means of resolving all the
disputes arising out of the building contract. She also recognized that
the clause was binding on the parties to the contract. She noted that
an arbitral award has an enduring and special effect, that is even if
the parties decide to adopt a different dispute resolution mechanism
for a particular dispute that arises under a contract, the arbitration
continues in force and is not thereby totally repudiated unless there is
a solid reason for doing so. She concluded, that courts will always
refer a dispute to arbitration where there is an arbitration clause in a
contract. In this connection she relied on Russel on Arbitration 22 nd
Ed, page 80, paragraph 2-119 where the authors state,
"A party may abandon its right to arbitration, for
example by the delay or inaction, or by
commencing court proceedings in breach of an
arbitration agreement. However the Courts are
slow to find such repudiation or abandonment
without very clear evidence of an intention to
abandon the right to arbitrate together with
reliance by the other party to its detriment.
Even if the right to arbitrate a particular dispute
has been abandoned that does not necessarily
mean that the arbitration mean that the
arbitration agreement itself had been
abandoned. ”
(a)
(b)
Section 5 of the Arbitration and Conciliation Ar: 'Cap 4,) provides for
stay of proceedings where the Court refers the matter to arbitration.
It provides as follows;
The question is whether the learned Justice of Appeal with whom the
other Justices of Appeal agreed was correct in holding that since the
contract contained an arbitration clause the trial judge was justified in
referring the matter to arbitration without the application of any of the
parties to the contract, and when one of the parties had filed a suit
despite the existence of arbitration clause in the contract.
party to arbitration. She entertained no doubt that the learned judge
did not err in law in staying the suit and referring the matter to
arbitration.
that the arbitration agreement is null and void,
inoperative incapable of being performed, or
that there is not in fact any ..ispute between the
parties with regard to the matters agreed to be
referred to arbitration. "
In the present case there is no doubt that no pnrty to the arbitration
agreement applied to the court to refer the n alter to arbitration. It
was argued that the court invoked its inherent h : isdiction to refer the
matter to arbitration. However inherent jurisdiction cannot be invoked
46
“ (1) A judge or magistrate befor: whom proceedings
are being brought in a matter which is the subject of
an arbitration agreement shall, if a party so applies
after the filing of a statement cf defence and both
parties having been a hearing refer the matter back to
the arbitration unless he or she finds -
I
I
47
I
wc
. In my view the learned trial judge prematurely referred the matter to
arbitration thereby depriving the court of the opportunity to determine
whether the reference to arbitration compiled with the provisions of
section 5 of the Arbitration Act.
As a consequence of the orders of the trial judge the party which had
signed the arbitration agreement and which was entitled to file the
suit and benefit from the arbitral award was not the beneficiary of the
arbitral award and was ordered by the Court of Appeal to be struck off
' from all proceedings pertaining to this case.
: -Secondly both parties were not given a hearing regarding the
propriety of referring the matter to arbitration.* There must have been
good reasons why the respondent filed a suit instead of referring the
matter to arbitration. Thirdly the appellant objected to the reference
of the matter to arbitration and participated in the arbitration
■ proceedings under protest. Fourthly it is doubtful whether the 2 nd
• appellant was a proper party to arbitration having not been a party to
. the arbitration agreement.
■ The respondent who was declared the right party to the proceedings
was not a party to the proceedings and had no valid assignment as
there was no evidence presented. The 1 st appellant had not
consented in writing to the assignment as required by the building
contract.
where there is an express statutory provision dealing with the matter
. like in. this matter where Section 5 is clear and unambiguous.
GROUND 5(a) ALLEGED MISCONDUCT BY THE ARBITRATOR
!?■
7
I
Accordingly, it is my view that the Court of Appeal, having discovered
. . fraudulent conduct against the respondent, it erred in upholding the
decision of the trial judge to stay proceedings and refer the matter to
arbitration. Ground 3 should therefore succeed.
In this ground of appeal, the appellants complain that the learned
•_ ■' Justices of appeal erred in law in holding that the arbitrator did not
•• misconduct himself. Dr Byamugisha 2 nd for appellant submitted that
counsel for the respondent did not contradict him when he stated that
the gift of $5000 received by the 2 nd Appellant was for his daughter ’ s
wedding. He urged court to hold that the arbitrator wa's wrong in
■ holding that the gift was a bribe.
In reply Mr. Tumusiime for the respondent submitted that it is true the
arbitrator held that the 2 nd appellant should not have been made a
party to the proceedings Section 27 of the Civil Procedure Act gives
discretion to the arbitrator to deny a party costs for good reasons. He
argued that the arbitrator gave sound reasons which included the 2 nd
48
.. With regard to the denial of costs to the 2 nd appellant counsel
.. contended that there is no law prohibiting parties from filing a joint
• defence. The issue was framed whether the 2 nd appellant was a
proper party to the suit and it was for the court to decide. Costs could
not be denied for adjournments which were properly granted.
Counsel submitted that the failure to award costs were errors in law.
He prayed that the award be set aside in respect of the 2 nd appellant.
49
appellants ’ voluntary submission to the proceedings, filing a joint
defence with the 1s appellant on issues in the contract of which he
was not a party and failure to challenge his rejoinder in the arbitration.
Counsel relied on the case of Sheikh Jama vs Dubat Farah (1959)
EA 789 where it was held that “ costs of and incidental to all suits
are in the discretion of the Court but where the court decides
that any costs shall not follow the event the court must set out
the reasons in writing. ”
'. With regard to the complaint by learned counsel for the 2 nd appellant
_■ that the two appellants were wrongly lumped together in the appeal,
Mr. Tumusiime acknowledged that this was an error of fact by the
•' court which was not brought to its attention. He prayed that this
ground of appeal be dismissed.
Finally learned counsel for the respondent prayed that the appeal be
dismissed with costs and since the case has been going on since
1999 and a lot of research has been going on in the appeal, the court
grants a certificate for three counsel.
It was not contested that it was wrong to proceed against the 2 nd
■ appellant when he was a party to the contract or the arbitration
agreement. The reasons the arbitrator gave were insufficient to deny
costs to the 2 nd appellant. Accordingly, I would allow this ground of
. appeal.
DECISION AND ORDERS
I would remit the case back to the High Court for expeditious trial.
2013
50
■ As the other members of the Court also agree this appeal is allowed
with the orders I have proposed.
For the foregoing reasons I would allow this appeal, set aside the
judgment and orders of the Court of Appeal, and orders of the Courts
. below including the arbitral award.
E^JjCtdoki
CHIEF JUSTICE
Dated this
/ /
I would order that the costs of this appeal and of Courts below
between the 1 st appellant and respondent abide the outcome of the
trial. I would award the 2 nd appellant costs in this Court and Courts
below.
day of .
5
[Coram: Odoki, CJ., Tsekooko, Katureebe, Kitumba & Kisaakye, JJSC.]
Civil Appeal No. 15 of. 2009
10
15
& PARTNERS
And
AU3ON INTERNATIONAL LTD. RESPONDENTS
20
25
30
Delivered at Kampala this ......2013.
< -
The costs of the appeal in respect of the 1 st appellant should abide the trial
However, in the circumstances of this case, the respondent should meet
the costs of the 2 nd appellant in this Court and in the two Court below
because I do not find any rational basis why he was made a party to the
case.
THE REPUBLIC CF UGANDA
IN THE SUPREME COURT (F UGANDA
AT KAMPALA
JUDGMENT OF J.W.N. TSEKOOKO, JSC.
I have had the benefit of reading in advance and in daft the judgment
prepared by his lordship the learned Chief Justice and I agree with him
that this appeal ought to succeed and that the orders of the two courts
below should be set aside. I also agree that the case should be returned to
the High Court for trial.
..S?.-.... day of
■WjN< Tsekooko
Justice of the Supreme Court
Between
APPELLANTS
1. NATIONAL SOCIAL SECURITY FUND '
2. W.H. SSENTOOGO
T/A SSENT
{Appeal from the decision of the Court of Appeal at Kampala (Mpagi-Bahigeine, Twinomujuni
&Kavuma, JJA ) dated 28* August, 2009 in Civil Appeal No. 02 of 2004}
«=1
\ 5
THE REPUBLIC OF UGANDA
r < -> .i
10
CORAM:
CIVIL APPEAL NO.15 OF 2009
15
BETWEEN
1. NATIONAL SOCIAL SECURITY FUND
APPELLANTS
20
VERSUS
ALCON INTERNATIONAL LTD RESPONDENT
25
IUDGMENT OF KITUMBA |SC
30
35
1
I would like, to say something about Miscellaneous Application No. 50 of
2007 which was filed by the respondent before the commencement of Civil
Appeal No. 2 of 2004, with specific reference to the issue of assignment of a
contract and the award that was obtained illegally and contrary to public
policy.
I have had the benefit of reading in draft, the judgment of My Lord Odoki, C.J
and I agree with him that this appeal ought to succeed.
[Appeal from the decision of the Court of Appeal of Uganda (Mpagi-Bahigeine,
Twinomujuni, Kavuma JJA) dated 25 th August 2009 in Civil Appeal No 02 of 2008)]
IN THE SUPREME COURT OF UGANDA
AT KAMPALA
ODOKI, C.J, TSEKOOKO, KATUREEBE, KITUMBA, AND
KISAAKYE, JJ.S.C.)
2. W.H. SSENTOOGO T/A SSENTOOGO AND PARTNERS^
i
10
15
20
25
30
After the arbitration award had been given, the appellants filed Arbitration
Cause No 4 of 2004 seeking to set aside the arbitral award on the grounds that
the arbitrator had misconducted himself and by reason of the same the
arbitration had been improperly procured. The learned trial judge considered
both applications and dismissed.
r?'
The appellants appealed against the decision of the trial judge to the Court of
Appeal in Civil Appeal No 2 of 2004. During the protracted trial in the High
Court and before the arbitrator, the respondents were represented by M/S
Tumusiime Kabega and Co. Advocates with instructions from Alcon
International Ltd (Uganda) by Mr Kultar Hanspal, the Managing Director and
Mr. Rajesh Kent and Mrs. Manjit Kent. The same firm of lawyers handled
numerous other cases on behalf of Alcon International Ltd (Uganda). Before the
actual commencement of the hearing of Civil Appeal No. 2 of 2004, learned
Counsel Peter Kabatsi of Kampala Associated Advocates appeared before court
to represent the respondent in that appeal. He stated that he had instructions
from Mr Davinder Hanspal of Alcon International Ltd (Kenya) to which M/S
Tumusiime Kabega and Co. Advocates and their clients resisted stating that
they were the only law firm with instructions from the respondent.
Consequently, Miscellaneous Application No. 50 of 2007 was filed in court.
The issue for determination in that application was who should represent the
respondent in Civil Appeal No. 2 of 2004. A number of affidavits were sworn
in support of and in opposition to the application. The Court of Appeal ruled
that Alcon International Limited (Kenya) had no locus standi in Civil Appeal No
2 of 2004. The Court of Appeal held further that M/S Tumusiime Kabega & Co.
Advocates were the right advocates to represent Alcon International Ltd
(Uganda) in the appeal. Alcon International Ltd (Kenya) was accordingly struck
off the record in Civil Appeal No. 2 of 2004.
2
st
10
15
20
25
30
3
C'
<
5*
. Assignment was ground 1; Mr. Tumusingize argued ground one for the 1
Appellant. The complaint on that ground was that the Justices of Appeal erred
when they upheld the arbitral award whereas the respondents did not have a
cause of action against the appellants. It was counsel's strong argument that the
appellants made the building contract agreement with Alcon International Ltd
Company incorporated in Kenya. Its address was Enterprise Road Industrial
Area. P. O. Box 47160 Nairobi.
Counsel contended that Alcon International Ltd (Kenya) is the company that
executed the building contract between itself and the 1 st appellant and went to
arbitration. Appellant's counsel argued that in spite of the ruling in
Miscellaneous Application No 50 of 2007 by the Court of Appeal that held
Alcon International Ltd (Kenya) had no locus standi in Civil Appeal No. 2 of
2004 that was pending in court had no capacity to instruct advocates and was
struck off the record in the pending suit, that did give rise to a cause of action
to the Alcon International Ltd (Uganda) to sue on a contract that was not
executed between it and the first respondent. He argued further that there was
a co-financing agreement between the 1 st respondent and Alcon International
Ltd (Kenya). Counsel's argument was that the company that was sued in the
High Court and during arbitration was Alcon International Ltd (Kenya). He
contended that Alcon International Ltd (Uganda) could only sue on the said
contract if it had been assigned to it. Unfortunately the respondent did not
plead assignment anywhere in their pleadings. Besides, according to clause 17
of the contract, the contract could not be assigned without the consent of the
employer. In support of his submission, counsel relied on Lindens Garden
Trust Vs Lenesta Sludge Disposals Ltd and Others (1993) House of Lords,
10
15
20
25
I
30
It may be true that the respondent Alcon International Ltd (Uganda) erected the
building in issue but that was done without the consent of the 1 5 ‘ appellant as is
stipulated in clause 1 7 of the contract. The respondent did not produce any
written evidence of that assignment. The respondent was not a party to the
contract.
A company is a legal entity and is different from its managing director. The fact
that Kultar Hanspal signed all the contracts between the first appellant and the
respondent and came to Uganda to execute and to build Workers House is no
4
The submissions by counsel for the appellant are that there was no assignment
of contract by Alcon International Ltd (Kenya) to Alcon International Ltd
(Uganda). That being the case, the respondent cannot sue on the contract to
which it is not a party either in court or during arbitration and derive any
benefit.
Counsel for the respondent has heavily relied on the fact of construction of the
building and the decision of the Court of Appeal in Miscellaneous Application
No 50 of 2007.
In reply, Mr Tumusiime, for the responded, contended that Alcon International
Ltd (Kenya) assigned the contract in issue to Alcon International Ltd (Uganda)
and the 1 st appellant was aware of that. He asserted that the assignment was
done on the first day the first brick was laid. Counsel contended that the issue
of assignment is answered by who built Workers' House. Besides, the first
appellant all the time communicated to Alcon International Ltd at their
Kampala office and not Nairobi. The first appellant sent the notice of
termination of the contract to that office.
which held that assignment is a point of law and where assignment is done
where there is such prohibition such assignment is not effective assignment.
10
15
20
25
30
2013 Dated at Kampala this day of
5
assignment of the contract from the Kenyan Company to the Ugandan
Company. With due respect to the Justices of the Court of Appeal, their order
of striking off the record Alcon International Ltd (Kenya) from Civil Appeal No.
2 of 2004 was made without close scrutiny of the pleadings in HCCS No 1255
of 1998 and the claim in arbitration proceedings where the contract between
Alcon International Ltd (Kenya) and the first respondent was annexed. It is trite
that courts do not write contracts for parties. It is rather unfortunate that in spite
of the finding of the Court of Appeal that the members of Hanspal family told
"truth sometimes by accident" the same court went on to believe them on the
issue of assignment.
I would set aside the Judgment of the Court of Appeal, the arbitral award and
the orders of the High Court. I would order that the HCCS No. 1255 of 1998
should be returned to the High Court for trial. In respect of the first appellant,
the costs of this appeal and of the courts below abide by the results of the trial.
However, the respondent should pay the costs of the second appellant in this
court and in the courts below.
However, the proceedings in this case were tainted with fraud and illegalities
and can not, therefore, stand.
It is obvious that the 2 nd appellant should have never been sued together with
NSSF on a contract he was not party to.
C.N.B. KITUMBA
JUSTICE OF THE SUPREME COURT
I
I
'i s
Similar Cases
Kampala District Land Board and Another v Babweyaka and 3 Others (Civil Appeal No. 2 of 2007) [2007] UGSC 36 (11 February 2007)
[2007] UGSC 36Supreme Court of Uganda85% similar
Nuru Kaaya v Crescent Transportation Ltd (Civil Appeal No. 6 of 2002) [2003] UGSC 65 (12 March 2003)
[2003] UGSC 65Supreme Court of Uganda83% similar
Omunyoko Akol Johnson v Attorney General (Civil Appeal No 06 of 2012) [2015] UGSC 129 (8 April 2015)
[2015] UGSC 129Supreme Court of Uganda83% similar
Hwan Sung Industries Ltd v Tajdin and others (Civil Appeal 8 of 2008) [2009] UGSC 39 (6 October 2009)
[2009] UGSC 39Supreme Court of Uganda82% similar
Dr. Maj. Rtd Anthony Jallon Okullo v Attorney General (Civil Appeal No. 3 of 2020) [2025] UGSC 32 (11 September 2025)
[2025] UGSC 32Supreme Court of Uganda82% similar