Case Law[2022] TZCA 402Tanzania
Sinyonya Company Limited vs Bulyanhulu Gold Mined Limited (Civil Appeal 172 of 2017) [2022] TZCA 402 (29 June 2022)
Court of Appeal of Tanzania
Judgment
IN THE COURT OF APPEAL OF TANZANIA
AT PAR ES SALAAM
(CORAM: MWARIJA, J.A.. KEREFU. J.A. And KENTE, J.A.^
CIVIL APPEAL NO. 172 OF 2017
SINYOMA COMPANY LIM ITED........................................................APPELLANT
VERSUS
BULYANHULU GOLD MINE LIM ITED .......................................... RESPONDENT
(Appeal from the judgment of the High Court of Tanzania
(Commercial Division) at Dar es Salaam)
(Sonqoro, J.)
dated 24th day of February, 2016
in
Commercial Case No. 102 of 2014
JUDGMENT OF THE COURT
18th February & 29th June, 2022
MWARIJA. 3.A.:
This appeal arises from the decision of the High Court of Tanzania
(Commercial Division) sitting at Dar es Salaam in Commercial Case No.
102 of 2014 (the suit). The appellant, Sinyoma Company Limited
instituted the suit against the respondent, Bulyanhulu Gold Mine Limited
following a dispute between it and the appellant over a contract termed
as "Purchase and Transport of Scrap Materials Sales Agreement" executed
by them on 8/5/2021 (hereinafter "the contract").
i
According to the contract, the appellant, who was described as "the
buyer" was to buy, collect, transport and dispose scrap materials from the
respondent's gold mine after fulfilling the conditions stipulated in the
contract. The conditions include those which are contained in clauses 24
and 25 of the contract. Under the former clause, the appellant was
required to obtain insurance premiums for inter alia, workers
compensation, employers liability, public liability as well as motor vehicles
and equipment insurance premiums. The insurance covers were to be
paid in USD currency. As for the latter clause, the appellant was to take
out and provide for inspection, when demanded, all the insurance covers
which ought to be in place prior to performance of the contract.
Having satisfied itself that it had complied with the terms and
conditions of the contract, the appellant commenced the business and on
6/12/2012, it purchased from the respondent, 28,000 kgs of scrap
materials worth TZS 7,150,000.00 (VAT inclusive). That was through
invoice No. Buly Des. 6/2012. The invoice was admitted in evidence as
exhibit P19. The receipt evidencing payment was also admitted in
evidence as exhibit P8.
A day later, on 7/12/2012 however, the appellant was notified by
the respondent through a letter, that it had terminated the contract.
According to the letter which was admitted in evidence as exhibit P13, the
appellant had failed to comply with the conditions set out in clauses 24
and 25 of the contract pointed out above.
The appellant was dissatisfied with the reasons for termination of
the contract. It thus instituted the suit in the trial court. In the plaint,
the appellant contended that it complied with requisite conditions
stipulated under the contract including those contained in clauses 24 and
25 and therefore, the termination thereof by the respondent was
wrongful. It claimed that the respondent committed a breach and thus
claimed for the following reliefs:
"(a) Payment o f special damages amounting to TZS
2,512,902,000/= and United State Dollars 552, 400.00.
(b) Payment o f deposit balance amounting to Tshs 57,124,000/=.
(c) Interest on (a) and (b) above a t the rate o f 20% for Tanzania
Shillings and 12% for United State Dollars from the date o f
term ination o f the agreem ent... to the date o fjudgm ent
(d) General damages for beach o f contract as the court may
assess.
(e) Interest on the decretal amount a t the rate o f 7% from the
date o fjudgm ent to the date o f fin al satisfaction o f the decree.
(f) Cost and any other reliefs that the honourable court may dream
fit to grant . "
In its written statement of defence, the respondent denied all the
claims raised by the appellant and urged the trial court to dismiss the suit
3
with costs. It maintained, among other things, that the appellant had
failed to comply with the conditions stated under clauses 24 and 25 of the
contract.
During the hearing of the case, whereas the appellant relied on the
evidence of three witnesses, Timoth Daniel Kilumile (PW1), Colodios Shoo
(PW2) and Peter Shiganga Kusamba (PW3), the respondent called one
witness, David Nzaligo (DW1).
The evidence adduced by the appellant's witnesses was to the effect
that the conditions alleged to have been breached by the appellant were,
to the contrary complied with. PW1 who was until the material time, the
Director of the appellant company testified that the conditions precedent
were complied with by the appellant, including the requirements
stipulated in clauses 24 and 25 of the contract. He contended that the
appellant hired four trucks, yards at Nyakato and Usagara areas, complied
with environmental and safety regulations as stipulated in the contract
and obtained a permit (exhibit P9) from the NEMC authorizing the
appellant to carry out the business of collecting and disposing metal
scraps.
The witness contended also that the appellant purchased insurance
covers as specified in the contract. He tendered the receipts in respect of
insurance premiums which were admitted in evidence as exhibit P4 and
also the receipts for payment of rental charges for Usagara yard which
were admitted in evidence as exhibit P7.
The other two witnesses (PW2 and PW3) supported PWl's
testimony. PW2 who was at the material time the appellant's
Environmental Manager, testified that, by virtue of his position, he
supervised collection and transportation of scrap materials from the
mine's compound. He said also that he ensured that the contract was
executed in accordance with the terms and conditions stipulated therein.
According to him, the appellant obtained among other things, a permit
from the NEMC and medical certificates for its employees who were
involved in the scrap materials collection activity. He tendered the
relevant certificates and the same were admitted in evidence as exhibits
P22 collectively.
On his part, PW3 was employed by the appellant in the capacity of
a Manager, added that in effect, performance of the contract was delayed,
the reason being that the appellant was ensuring that the terms and
conditions, including those contained in clauses 24 and 25 were complied
with. He went on to state that, before the termination of the contract,
the appellant had commenced its execution by transporting sixteen trips
of scrap materials per month.
In its defence, the respondent denied the appellant's allegation that
the contract was wrongly terminated. In his evidence, DW1 who was
formerly the employee of the appellant but testified for the respondent,
its subsequent employer stated that, by virtue of his position with the
respondent company, he had the duty of making a follow-up on the
execution of the contract. In the course of doing so, he said, he found
first, that the validity of the permit shown to have been issued to the
appellant by the NEMC was doubtful because the same was issued on the
same date on which it was applied for and secondly, that the appellant
did not furnish the respondent with the requisite insurance covers from
reputable companies. According to the witness, the submitted insurance
covers were in the names of two individuals instead of being in the name
of the appellant. Thirdly, DW1 went on to state that, the appellant did
not have its own yard for storage of scrap materials, instead, it depended
on the yards leased from other persons. He concluded his evidence by
contending that, it was because of such non-compliances that the
respondent terminated the contract.
Having considered the tendered evidence, the trial court found that
the respondent had properly exercised its right under the contract to
terminate it. The learned trial Judge believed the respondent's evidence
that the appellant had failed to comply with clauses 24 and 25 of the
6
contract in that; although it had submitted insurance premiums, the same
were not in USD currency but in Tanzanian shillings. He was therefore,
of the view that the notice of termination served on the appellant by the
respondent brought the contract to an end.
Notwithstanding the finding that the respondent had rightly
terminated the contract, the trial court found that the appellant was
entitled to compensation by way of general and special damages. It held
that the appellant was entitled to special damages of a total of TZS
87,866,000.00 and USD 400 as compensation for the expenses it incurred
in procuring the requisite facilities stipulated in the contract with a view
to implement the contract. The expenses in question were in respect of
the money spent in hiring and maintaining the trucks, payment for the
NEMC permit, rentals for the yards, insurance covers and the money used
to purchase scraps materials from the respondent. It also awarded the
appellant general damages of TZS 150,000,000.00. The appellant was
furthermore, awarded interest on the decretal sum and costs of the suit.
The appellant was aggrieved by the finding of the High Court that
the respondent was justified first, to terminate the contract and
secondly, the finding that some of the claims were not proved. It raised
a total of twelve grounds of appeal. In his written submission filed in
support of the appeal however, the counsel for the appellant abandoned
the 9th ground. The remaining eleven grounds may in effect, be
consolidated into four grounds as follows:
1. That the learned tria l Judge erred in law and fact in holding that the
appellant had breached the term s o f the contract particularly
clauses 24 and 25 thereof thus entitleling the respondent to
term inate it
2. That the learned tria l Judge erred in law and fact by failing to award
special damages and anticipated damages pleaded by the appellant\
while the adduced evidence proved to the required standard that
the same were suffered.
3. That the learned tria l Judge erred in law and fact by deciding the
issue relating to the lease by the appellant, o f ex- Kauma yard while
the same did not feature in the case.
4. That the learned tria l Judge erred in law and fact in failing to
determ ine the issue relating to the costs incurred by the appellant
in leasing Usagara yard fo r storage purpose.
On its part, the respondent filed a cross appeal consisting of 4
grounds that:
"1. The Court erred in fact and in law to award
damages to the appellant under s. 37 (1) o f
the law o f contract having found that there
was no breach o f Contract by the
respondent.
2. Having found that the appellant failed to
prove his claim o f damages against the
8
respondent the court erred in law and fact
by proceeding to award exorhabitant sum o f
general damages to the appellant.
3. The court erred in law in awarding interest
a t 12 % without an agreem ent to that effect
as required by law, and
4. having found that the appellant did not
com ply with conditions precedent stipulated
in the agreement, the court erred in law by
concluding that there was valid contract
executed between the parties."
At the hearing of the appeal, the appellant was represented by Mr.
Mpaya Kamara, learned advocate while the respondent had the services
of Mr. Faustin Malongo assisted by Ms. Caroline Kivuyo, learned
advocates. As required under Rule 106 (1) and (7) of the Tanzania Court
of Appeal Rules, 2009 as amended, the learned counsel for the appellant
and the respondent duly filed their respective written submissions for and
against the appeal.
Submitting in support of the first ground of appeal as paraphrased
above, the counsel for the appellant argued that the trial court erred in
holding that the contract was wrongly terminated because the appellant
had failed to comply with clauses 24 and 25 of the contract. According to
9
the learned counsel, the appellant complied with the conditions stipulated
under the stated clauses. He went on to submit that, even if there would
have been a breach, before it could terminate the contract, the
respondent was required to give the appellant 14 days' notice so that it
would remedy the breach. His argument was based on clause 19 (c) of
the contract. It was Mr. Kamara's further submission that, the letter
(exhibit P13) in which the respondent notified the appellant that the
contract had been terminated, did not in terms of clause 19 (c) of the
contract, amount to a valid letter of termination of contract. He stressed
that, under the contract, the appellant had the right of being given a
notice of 14 days within which it would remedy the breach, if any, before
the respondent could exercise its right of terminating it.
With regard to the contention that the Usagara yard was not
approved for storage of scrap materials, the learned counsel submitted
that the respondent had denied that allegation both in PW l's statement
and in the written statement of defence. He added that, whereas the
appellant adduced evidence through PW1 proving that the yard was
inspected and approved by the respondent's officials, the respondent did
neither tender evidence to the contrary nor was PW1 cross-examined on
that fact. The effect of the respondent's failure to cross-examine PW1
10
rendered his evidence trustworthy as the same remained unchallenged,
argued Mr. Kamara. He cited the Court's decisions in the cases of Anna
Moises Chisano v. Republic, Criminal Appeal No. 273 of 2019 and
Hatari Masharubu @ Babu Ayubu v. Republic, Criminal Appeal No.
590 of 2017 (both unreported) to bolster his argument.
The appellant's counsel submitted also that although in exhibit P13,
reference was made to clauses 15 of the contract which entitled the
respondent to suspend the whole or any part of the contract for such
period as it may deem fit, the letter had the effect of terminating, not
suspending the contract.
In reply to the submission made in support of the first ground of
appeal, Mr. Malongo opposed Mr. Kamara's argument that by virtue of the
provisions of clause 19 of the contract, termination of the contract was
supposed to be preceded by 14 days' notice within which the appellant
would remedy the breaches, if any. According to Mr. Malongo, the
requirement applied only to the conditions stated under paragraph (c) of
that clause of the contract, not breaches involving theft, corruption and
either illegal activity. He said further that, the respondent was entitled to
terminate the contract without 14 days' notice in the case of breach of
li
the company's environmental policy, NEMC requirements or good
environmental practices.
In this case, Mr. Malongo went on to argue, it was the use of
Usagara yard, which was not approved by the respondent that constituted
one of the reasons for termination of the contract. According to him, the
respondent found that the use of the yard contravened the company's
policy and NEMC requirement. He argued also that the appellant's failure
to comply with the requirement of furnishing the insurance premiums
entitled the respondent to instant termination of contract.
From the submissions of the learned counsel for the parties on the
first ground of appeal, the issue which arises for our determination is
whether or not by terminating the contract, the respondent properly
exercised its right under the contract. The respondent's right to terminate
the contract for breach of the terms and conditions thereof is provided by
clause 19 of the contract under the heading Termination for breach.
It states that:
"If at any time Buyer:
(a) Commits an act o f gross negligence, w iifui misconduct, fraud, or
dishonesty in respect o f any m atter undertaken or required to be
undertaken under this agreement;
12
(b) Acts In a m anner which Company considers to be substantially
prejudicial or harm ful to company;
(c) Commits a breach o f any other provision o f this agreem ent and
fa ils to rem edy the breach a t its own expenses and to the
reasonable satisfaction o f the company within 14 days o f a notice
by company specifying the nature o f the breach, or, if the breach
is not capable o f remedy, fails to offer adequate compensation
to company for the loss and damage suffered as a result o f the
breach.
(d) Breaches any o f the company's site, Health and Safety,
Environm ental or community relations policies Company may
forthw ith im m ediately term inate this Agreem ent by notice In
w riting to buyer."
In its letter (exhibit P13), the respondent informed the appellant about
termination of the contract. The relevant part of that letter reads as
follows:
"Under clause 15, the Company is entitled to suspend the
whole or any part o f the scrap m etals rem oval for such tim e as
the Company sees fit, and the buyer is not to be entitled to any
costs due to suspension by the Company.
Follow ing separate review follow ing o f the contract, a number
o f serious breaches o f term s and conditions o f the contract have
been identified. A number o f these are se t out below in the
attached annexure. In the view o f the Company, any and each
o f these breaches is sufficient m aterial to give rise to a right o f
term ination under clause 19 o f the contract.
13
Accordingly, in lig h t o f the nature o f these breaches, the
Company hereby gives notice o f term ination o f the contract
effective im m ediately."
From the wording of clause 15 of the contract, we agree with Mr.
Kamara that the letter exhibit P13 written to the appellant was not a notice
stipulated under that clause of the contract. As clearly stated in the letter,
the respondent terminated the contract with immediate effect. In doing
so, it acted pre-maturely because it was required to issue to the appellant
14 days' notice with a view to allowing it to remedy the breaches, if any.
The argument by Mr. Malongo that the requirement of issuing 14
days' notice was not applicable is not, in our view, tenable. Exhibit P 13,
the letter through which the respondent informed the appellant about the
former's decision to terminate the contract specifies the breaches which
the latter had allegedly committed. It is shown that the appellant had
failed to satisfy the respondent on compliance of the conditions stipulated
under clauses 24 and 25; that it failed to show that it had obtained the
workers' compensation and employment liability insurance, motor vehicles
insurance and equipment insurance.
Another reason was the use by the appellant, of an alternative
storage; Usagara yard instead of Nyakato yard which was shown in the
tender document. The respondent contended that the alternative yard
14
was found to be unsuitable because the appellant did not obtain a permit
from NEMC for use of that facility as a scrap metal yard.
We do not, with respect, agree with the respondent's counsel that
the nature of non-compliance said to have been done by the appellant
entitled the respondent to immediate termination of the contract. This is
because the alleged breaches do not fall under paragraphs (a) (b) and (d)
of clause 19 of the contract. They fall under other provisions of the
contract and are thus covered by paragraph (c) of clause 19 which, in
case of their non-compliance, termination of contract must be preceded
by 14 days' notice within which the appellant remedy the breach or offer
adequate compensation to save the contract from being terminated.
Mr. Malongo has argued that the use by the appellant, of Usagara
yard was in effect a breach of the respondent's environmental policy thus
entitling it to immediate termination of the contract under clause 19 (d)
of the contract. With respect, that is not correct because, even if it would
have been established that the Nyakato yard was unsuitable for scrap
metal storage, the site did not belong to the respondent. We do not
therefore find merit in that argument.
On the basis of the above stated reasons, it is our considered view
that the respondent was duty bound to comply with clause 19 (c) of the
15
contract by issuing to the appellant, 14 days' notice before terminating
the contract. Failure to do so entails that the contract had not been
terminated. Since the finding on the first ground of appeal suffices to
dispose of the appeal, we find no need to canvass the other grounds.
In the event, we reverse the finding of the trial court that the
respondent had rightfully terminated the contract. In that respect, we
quash that decision and the subsequent orders arising therefrom. The
appeal is consequently allowed to the extent that the contract subsists.
The appellant shall have its costs.
DATED at DAR ES SALAAM this 27th day of June, 2022.
A. G. MWARIJA
JUSTICE OF APPEAL
R. J. KEREFU
JUSTICE OF APPEAL
P. M. KENTE
JUSTICE OF APPEAL
The judgment delivered this 29th day of June, 2022 in the presence of Ms.
Caroline Kivuyo, learned counsel for the Respondent and also holding brief
of Mr. Mpaya Kamara, learned counsel for the Appellant, is hereby
certified as a true copy of the original.
16