Case Law[2025] ZASCA 87South Africa
Maano Water (Pty) Ltd v Eskom Holdings SOC Limited (383/24) [2025] ZASCA 87 (12 June 2025)
Supreme Court of Appeal of South Africa
12 December 2022
Headnotes
Summary: Reviewability of tender cancellation – State owned enterprises – executive action distinguished from administrative action – rationality as ground for review – absence of authority as ground for review - pactum de contrahendo – averred ‘right to negotiate to deadlock’.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Supreme Court of Appeal
South Africa: Supreme Court of Appeal
You are here:
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
2025
>>
[2025] ZASCA 87
|
Noteup
|
LawCite
sino index
## Maano Water (Pty) Ltd v Eskom Holdings SOC Limited (383/24) [2025] ZASCA 87 (12 June 2025)
Maano Water (Pty) Ltd v Eskom Holdings SOC Limited (383/24) [2025] ZASCA 87 (12 June 2025)
Download original files
PDF format
RTF format
Links to summary
PDF format
RTF format
make_database: source=/home/saflii//raw/ZASCA/Data/2025_87.html
sino date 12 June 2025
THE
SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT
Not Reportable
Case no: 383/24
In the matter between:
MAANO WATER (PTY)
LTD
APPELLANT
and
ESKOM
HOLDINGS SOC LIMITED
RESPONDENT
Neutral
citation:
Maano
Water (Pty) Ltd v Eskom Holdings SOC Limited
(383/24)
[2025] ZASCA 87
(12 June 2025)
Coram:
MATOJANE
and KEIGHTLEY JJA, and PHATSHOANE AJA
Heard:
20
May 2025
Delivered:
This judgment was handed down
electronically by circulation to the parties’ representatives
by email, published on the Supreme
Court of Appeal website, released
to SAFLII. The date and time for hand-down is deemed to be 11h00 on
12 June 2025.
Summary:
Reviewability of tender cancellation –
State owned enterprises – executive action distinguished from
administrative
action – rationality as ground for review –
absence of authority as ground for review -
pactum
de contrahendo
– averred ‘right
to negotiate to deadlock’.
ORDER
On appeal from: Gauteng
Division of the High Court, Johannesburg (Malindi J, sitting as a
court of first instance):
1
The appeal is dismissed.
2
The appellant
is ordered to pay the costs of the appeal.
JUDGMENT
Matojane JA (Keightley
JA and Phatsoane AJA concurring):
Introduction
[1]
This appeal lies against the judgment of the Gauteng Division of the
High Court, Johannesburg
(high court) delivered on 12 December 2022,
which dismissed an urgent application of the appellant (Maano). In
that application
Maano sought a mandamus to compel the respondent
(Eskom) to resume contract-price-adjustment (CPA) negotiations or, in
the alternative,
to review and set aside Eskom’s decision,
communicated to Maano in a letter dated 4 August 2022 and published
on the National
Treasury E-portal and Eskom tender bulletin
platforms, to cancel Tender CORP 5542. Leave to appeal was granted by
the high court
on 27 March 2024.
[2]
The factual matrix is largely common cause. In August 2021 Eskom
issued Tender CORP 5542 to procure
a five-year contract to supply
sulphuric acid to its power stations. Eskom entered into negotiations
with the highest ranked bidder
(Afro-Zonke) for the conclusion of a
contract. A key component of the contract was an agreed model for
calculating the CPA. When
Eskom commenced negotiations with
Afro-Zonke, the global price of sulphur had risen by approximately
250%. The primary cause was
the conflict in Ukraine, which commenced
in early 2022. The spike in the cost of crude sulphur and shipping
had not been foreseen
when the tender was issued.
[3]
Negotiations between Eskom and Afro-Zonke failed because Afro-Zonke
tried to pass its increased
costs, arising from the global spike, on
to Eskom. Subsequently, Eskom began talks with Maano, the second
preferred bidder. On
21 April 2022, Maano proposed a hybrid model for
calculating the CPA that was entirely dollar-based. However, on
4 May 2022,
Eskom rejected this, stating that a dollar-based model
was unacceptable. Its further reasoning was that it created
unmanageable
exposure due to exchange rate fluctuations and
changes in the dollar price of crude sulphur, which they could
not
hedge against. A meeting held between Maano and Eskom on 10 May
2022, concluded with both parties maintaining these stances.
Subsequently,
Eskom decided to cancel the entire tender process.
Maano now seeks to challenge this cancellation and compel a return to
the negotiating
table.
[4]
A factual dispute exists centred on the meeting between the parties
of 10 May 2022. Maano contends
that Eskom undertook to consider the
hybrid model and either accept it or make a counter-proposal. Eskom
disputes this, asserting
that it had consistently communicated its
rejection of dollar-based CPA models due to the unacceptable transfer
of exchange rate
and commodity price risk to Eskom.. Eskom contends
that negotiations had reached an impasse by 10 May 2022.
[5]
After 10 May 2022, Eskom did not revert to Maano. Following some
prodding from Maano, Eskom published
a notice in August 2022,
cancelling the entire tender process. Eskom's stated reasons appear
in the
Procurement Tender Committee (PTC) extract
of minutes of
10 June 2022. The PTC received a report (the
feedback report) from the mandated team negotiating with Maano. The
feedback report
included a request for approval from the PTC to
‘terminate the negotiations held with Maano Water (Pty) Ltd,
cancel the tender
and re-issue the tender’. The report stated
that the initial mandate for the negotiation was based on a value of
about R289
million for the 2023 to 2027 financial years.
However, the price based on Maano’s CPA model would be
significantly higher,
at about R529 million. This was substantially
above Eskom's desired ‘aspiration base’ of about R246
million.
[6]
Ultimately, the report detailed the failure of
negotiations with Maano and cited reasons for the request to
approve the
cancellation of the tender altogether. Significantly, the
PTC accepted the negotiating team’s explanation that if they
were
to commence negotiations with the third-ranked bidder, the
probability was high that the same challenges would be experienced as
with Maano, in that the third-ranked bidder would also pass on their
increase to Eskom. As a result, the PTC approved both
recommendations,
namely to terminate the negotiations with Maano, and
to cancel the current tender and issue a new one.
[7]
Maano relies on it having a right, under the terms of the tender
documents, to hold Eskom to negotiate
until deadlock. Maano asserts
further that the sole reason for the cancellation of the tender was
the alleged failure of its negotiations
with Eskom. It disputes that
deadlock had been reached as, it says, had Eskom engaged further,
Maano would likely have reverted
to its original rand-based CPA
model.
[8]
Maano launched its urgent application on 25 August 2022, pursuing its
primary remedy of a mandamus,
in final form, to force Eskom back to
the negotiating table. It based its assertion of a clear right
on the argument
that Eskom was legally obliged, and hence Manno
had a corresponding right, to continue negotiations as no deadlock
had been reached.
Consequently, Eskom had breached Maano’s
right by unilaterally terminating the tender process after
negotiations had commenced,
and while the tender validity period –
being until 28 September 2022 - had not yet expired.
The
core issue: reviewability of the tender cancellation
[9]
The high court proceedings focused entirely on the mandamus relief
sought by Maano. It dismissed
the application on the basis that Maano
had failed to establish a clear right to hold Eskom to continue
negotiations. The high
court found that Eskom was entitled, under
clause 1.6.1 of the tender contract, to terminate negotiations where,
after good faith
engagement, a deadlock was reached. The high court
did not address Maano’s alternative relief, namely the review
and setting
aside of the tender. However, when the appeal was argued
before this Court, it became clear that, contrary to the approach
adopted
in the high court, the fundamental issue was that of review.
In other words, the antecedent question for Maano to succeed in
getting
Eskom back to the negotiating table, was whether it could
establish that the decision to cancel the tender was unlawful and
reviewable.
This is because, without a successful challenge to this
cancellation, any relief seeking to compel further negotiations would
be
moot for the simple reason that the tender would no longer exist.
Put differently, unless set aside, the cancellation of the tender
effectively terminated any claim by Maano to a right to continue to
negotiate.
[10]
Unfortunately, Maano’s focus on interdictory relief, in the
form of a mandamus, as its primary form
of relief had the effect that
its case for a review of the tender cancellation was not fully
ventilated in its founding papers.
A related complicating factor is
that Maano eschewed any reliance on rule 53 of the Uniform Rules of
Court. Consequently, neither
the high court nor this Court had access
to the record of the decision to cancel the tender process.
[11]
Insofar as the grounds of review were addressed in the founding
affidavit, Maano contended, first,
that the tender cancellation was
not an independent administrative act because it was ‘designed
as a reason for not continuing
with the negotiations’. In the
alternative, and if the cancellation was considered to be an
independent administrative act,
Maano argued that it was subject to
review and setting aside under ‘virtually all of the provisions
of s 6(2)’ of the
Promotion of Administrative Justice Act 2 of
2000 (PAJA). It cited, among other grounds, that Eskom had no power
to cancel a procurement
process where a tender has been awarded and
the details of the contract are being negotiated. It also identified,
as additional
grounds, bias, procedural unfairness, and
irrationality.
[12]
A preliminary question is whether the decision to cancel the tender
constitutes administrative action, subject
to review under PAJA, or
an executive action, reviewable under the principle of legality. As I
have indicated, Maano’s stance
was that it was the former.
[13]
This Court has consistently held that decisions by organs of state
and state owned enterprises not to procure
goods or services,
particularly prior to the formation of a binding contract, typically
fall within the realm of executive
action. This Court in
Tshwane
City and Others v Nambiti Technologies (Pty) Ltd (Nambiti)
[1]
stated that such decisions do not directly affect rights and are
therefore not administrative action. This Court explained that
when a
tender is cancelled, no one loses any rights, as no contract has been
formed.
[2]
Tenderers only have
expectations, not rights, at that stage. A decision not to procure
services by tender does not have a direct,
external legal effect on
the tenderers' rights.
[3]
[14]
Maano sought to distinguish this case from
Nambiti
on the
basis that it had been awarded the tender and that, pursuant to that
award, the parties were at, what Maano asserted to
be, an advanced
stage of negotiations. However, Maano’s underlying assumption
is incorrect. It had not been awarded the tender:
after negotiations
with the preferred bidder, Afro-Zonke failed, Maano became no more
than the first reserve bidder. Had the tender
not been cancelled, the
failure of negotiations with Maano would have resulted in the third
bidder taking Maano’s place as
the second reserve. The material
overlap between this case and
Nambiti
is that in neither case
had a contract been concluded before the tender was cancelled. Maano
is thus in the substantially same
position as the reviewing party in
Nambiti
: the cancellation of the tender may have affected its
expectations, but not any rights.
[15]
The wording of the tender document in the present case, which
explicitly grants Eskom the right to ‘
cancel
the tender process at any time prior to the formation of a
contract,’
[4]
reinforces this position. Even in the absence of such explicit
wording, the fundamental reasons animating public procurement –
being essentially an executive function – would likely lead to
the same conclusion. It follows that the review falls outside
of the
ambit of PAJA. Is it nonetheless possible to discern from Maano’s
application a valid basis for review under the broader
principle of
legality?
[16]
As indicated earlier, Maano’s case for review was not fully
developed in its founding affidavit. A
generous reading of the
grounds of review identified by Maano presents limited possibilities:
absence of authority, and irrationality,
with bias or mala fides
as sub-categories of the latter.
[17]
As to rationality, the question is whether the respondent's decision
to cancel the tender was rationally
connected to the purpose for
which it was taken. Maano contended that the sole reason for the
cancellation of the tender was to
provide Eskom with a reason to
avoid continuing negotiations. According to Maano, Eskom gave no
indication that Maano had not complied
with any tender requirements:
it simply aborted the tender process without explanation,
demonstrating bias or mala fides on Eskom’s
part.
[18]
There are obvious difficulties with Maano’s submissions in this
regard. Most fundamentally, its averment
as to the sole reason for
the cancellation is patently wrong. Eskom provided clear and
consistent reasons for this, as articulated
in its answering
affidavit and corroborated by contemporaneous documents, including
the feedback report and the Procurement Tender
Committee resolutions.
These reasons fundamentally stem from changed global
circumstances pertaining to sulphuric acid prices.
The respondent
explained that the proposed CPA model, particularly Maano’s
shift to a dollar-based index, exposed Eskom to
an unlimited and
unsustainable financial risk. This was not only a sticking point in
the negotiations with Maano but, as recorded
in the feedback report,
and accepted by the PTC, would be equally problematic in negotiations
with the second reserve bidder. The
core problem was that the tender
had been overtaken by broader global events, giving rise to broader
policy and economic issues
for Eskom, which rendered the original
tender no longer fit for purpose.
[19]
The evidence demonstrates that Eskom engaged in six meetings with
Maano, consistently articulating its position
regarding the
unacceptability of the proposed pricing model. The decision to cancel
was not a capricious one but a considered response
to external market
volatility and the need to protect public funds. It would, in fact,
have been irrational for a public body,
entrusted with finite
resources, to proceed with a contract that exposed it to such
significant and unmanageable financial risk.
Realistically, these
external factors meant that none of the tenders received were
acceptable. This was the reason cited by Eskom
in its letter advising
Maano of the cancellation. It was a permissible reason for tender
cancellations under regulation 13(1)(
c
)
of the 2017 Regulations promulgated under the
Preferential
Procurement Policy Framework Act 5 of 2000
.
[5]
Any suggestion of irrationality, bias or mala fides on the part of
Eskom in these circumstances is without any foundation.
[20]
The remaining question is whether there is any merit in Maano’s
argument that Eskom had lacked authority
to cancel the tender. The
fulcrum around which the argument turns is Maano’s assertion
that it had a ‘right to negotiate
to deadlock’, which it
contends Eskom breached. From a review perspective, the gist of
Maano’s case is that Eskom had
no authority to cancel the
tender before deadlock was reached in its negotiations with Maano.
This alleged right, and hence correlative
obligation on Eskom, is
purportedly sourced from clause 1.1 in Eskom’s Standard
Conditions of Tender (the SCTs).
[21]
Maano made no reference to the SCTs in its founding papers. They
were, in fact, attached to Eskom’s
answering affidavit, and
Maano’s reliance on clause 1.1 was only articulated in its
submissions to this Court. The clause
simply reads that ‘[t]he
Employer [Eskom], the Eskom Representative and each eligible tenderer
submitting a tender shall
act timeously, ethically and in a manner
which is fair, equitable, transparent, competitive and cost
effective.’ From this
provision, Maano sought to infer a
restriction on Eskom’s power to cancel the tender until a
deadlock in negotiations was
reached.
[22]
The argument has two components: legal and factual. The legal
component raises the question of whether Eskom’s
undertaking in
the SCTs to act in a manner which is ‘fair, equitable [and]
transparent’ requires it to remain at the
negotiating table,
and bars it from exercising its power to cancel the tender, until
deadlock. If so, the factual component of
the argument is triggered,
with the question being whether there was a deadlock in negotiations
with Maano.
[23]
As to the legal component, what Maano effectively argues is that
clause 1.1 of the SCTs constitutes a
pactum
de contrahendo
,
or an ‘agreement to agree’. The general principle, as
established in cases like
Premier,
Free State and others v Firechem Free State (Pty) Ltd
[6]
and
Southernport
Developments (Pty) Ltd v Transnet Ltd
,
[7]
is that an agreement to agree is generally too vague to be enforced
unless the parties have agreed on the essential terms of the
contemplated contract, and there is an objective mechanism or
external yardstick by which any outstanding terms can be determined.
Letaba
Sawmills
(Edms)
Bpk v Majovi (Edms) Bpk (Letaba Sawmills
)
[8]
concerned a lease agreement where the rental amount was to be agreed
upon by the parties but, if they failed to agree, the amount
would be
determined by an arbitrator. The term was held not to be vague and
was enforceable because the arbitration clause provided
a clear
deadlock-breaking mechanism.
[24]
The judgment in
Makate
v
Vodacom (Pty) Ltd
,
[9]
while not directly addressing ‘negotiate to deadlock’
clauses, underscored the role of good faith in
contracts.
It highlighted that less formal agreements can be legally binding if
both parties clearly intended to be bound and
if there is a
way to determine crucial, undefined terms – like ‘reasonable
remuneration’ in that specific instance.
The Constitutional
Court, in line with the
Letaba
Sawmills
principle, reaffirmed that for an ‘agreement to agree’ to
be enforceable, there must be a deadlock-breaking mechanism in
place. The court held:
‘
Agreements
to negotiate in good faith are taken as a species of the
pacta
de contrahendo
(agreements to agree). Generally they are regarded as a category of
contracts whose purpose is to create other contracts in future.
But
sometimes contracting parties, as was the position here, may be
confronted by a situation where they are not able to agree
on some of
the terms of the contract. To resolve the problem, they may arrange
to negotiate and agree on the outstanding terms
on a future date. The
arrangement may form part of the concluded agreement. A dispute may
arise, if one of the contracting parties,
as was the case here,
refuses to negotiate the outstanding term so that the parties’
agreement may be executed. When this
occurs, the question that arises
sharply is whether the term to negotiate is enforceable at the
instance of the innocent party.’
[10]
[25]
The contractual clause relied upon by Maano is too vague to give rise
to an enforceable right to negotiate
to deadlock, and hence a
limitation on Eskom’s power to cancel the tender. At best, it
records an undertaking by both parties
as to how they will be guided
in their conduct. It is not directed specifically at contract
negotiations. Even if it could be interpreted
more favourably for
Maano, clause 1.1 provides no mechanism for resolving an impasse,
which is a crucial element for such an agreement
to be enforceable.
Finally on this score, Maano’s preferred interpretation is
untenable given the express power provided
to Eskom in clause 1.6.1
of the SCTs to ‘cancel the tender process at any time prior to
the formation of a contract.’
[26]
Although it is not strictly necessary to do so, for completeness’s
sake, it is worth recording that
Maano’s argument fails also at
the factual level. It claims that on 10 May Eskom committed to review
its hybrid model and
respond with either an acceptance or a
counter-offer. Eskom, however, refutes this, stating it
consistently rejected the dollar-based
hybrid CPA model due to the
inherent financial risks, specifically exposure to rand-dollar
exchange rate fluctuations and
volatile global sulphur prices. Eskom
maintains that by 10 May 2022, a clear deadlock had been
reached. This was because Maano
continued to push for the
dollar-based model despite Eskom's persistent objections. Eskom
further argues that its delay in informing
Maano of the cancellation
until 4 August 2022, was not in bad faith, as it intended to
provide reasons if Maano requested
them.
[27]
Applying the
Plascon-Evans
rule
for factual disputes in motion proceedings, where final relief is
sought, the Court must accept the facts averred by
Eskom that are not
denied by Maano, and Maano’s facts admitted by Eskom, unless
Eskom’s version is so far-fetched
or clearly untenable that the
Court is justified in rejecting it merely on the papers.
[11]
[28]
Eskom's consistent position throughout the negotiations, articulated
in meetings and correspondence, was
that dollar-based CPA models were
unacceptable due to the transfer of risk against which it could not
hedge. Maano's repeated insistence
on dollar-based models, even after
Eskom articulated its objections, lends credence to Eskom's assertion
that negotiations had
reached a dead end on this specific point.
While Maano's replying affidavit belatedly suggested it ‘would
probably have reverted’
to its original rand-based model, this
was not conveyed to Eskom during the negotiations, nor does it
override Eskom's consistent
rejection of the proposed dollar-based
models. Furthermore, Maano's prior statements indicating the
unsustainability of its original
rand-based model under changed
market conditions (due to a 250% increase in raw material costs)
weaken the credibility of its late
assertion that it would have
reverted.
[29]
Therefore, on the facts, Eskom’s version prevails. By 10 May
2022, Eskom had genuinely concluded that
further negotiation on
Maano's proposed CPA models would be fruitless due to Maano's
persistence in a model Eskom found unacceptable
and unmanageable. The
notion that Eskom made an abrupt about-turn and undertook to consider
the hybrid model again, or to make
an entirely new counter-proposal,
is not supported by the consistent narrative of the negotiations.
Conclusion
and order
[30]
Maano has not made out a case for the review and setting aside
of the cancellation of the tender. The
decision to cancel was an
executive action, rationally taken in response to significant and
unavoidable changes in market conditions.
In addition, there is no
merit in Maano’s contention that Eskom lacked authority to
cancel the tender. Clause 1.1 of
the SCTs did not limit the
express power of Eskom to cancel the tender process. The high court
was correct to dismiss Maano’s
application.
Order
[31]
In the premises, the following order is made:
1.
The appeal is dismissed.
2.
The appellant is ordered to pay the costs of the appeal.
K
E MATOJANE
JUDGE
OF APPEAL
Appearances
For
the appellant:
P F
Louw SC and J W Steyn
Instructed
by:
Van
Der Vyver Inc, Midrand
EG
Cooper Majiedt Inc, Bloemfontein.
For
the respondent:
A
Stein SC and M Augustine
Instructed
by:
Cheadle
Thompson & Haysom Inc, Johannesburg
McIntyre
Van Der Post Inc, Bloemfontein.
[1]
Tshwane
City and Others v Nambiti Technologies (Pty) Ltd
[2015]
ZASCA
167;
2016
(2) SA 494 (SCA); [2016] 1 All SA 332 (SCA).
[2]
Nambiti
para
24
states the general principle as follows: ‘Whether the
cancellation of a tender before adjudication is administrative
action in terms of these requirements depends on whether it involves
a decision of an administrative nature and whether it has
direct,
external legal effect.’ See also
Grey's
Marine Hout Bay (Pty) Ltd and Others v Minister of Public Works and
Others
[2005] ZASCA 43
;
2005 (6) SA 313
(SCA) para 21.
[3]
Nambiti
para
32.
[4]
Clause
1.6.1 of Eskom’s Standard conditions of Tender reads: ‘Eskom
may accept or reject any variation, deviation
or alternative tender
and reserves the right to accept the whole or any part of the
tender. Eskom may cancel the tender process
at any time prior to the
formation of a contract and will give written reasons for the
cancellation upon written request to do
so… .’
[5]
Preferential Procurement Regulations, 2017 published under GN R32 in
GG 40553 of 20 January 2017, repealed by GN 2721 in GG 47452
of 4
November 2022.
[6]
Free
State & others v Firechem
Free
State
(
Pty
)
Ltd
2000 (4) SA 413 (SCA)
at 431G–J Schultz JA explained that ‘[a]n agreement that
the parties will
negotiate to conclude another agreement is not
enforceable, because of the absolute discretion vested in the
parties to agree
or disagree:
Scheepers
v Vermeulen
1948 (4) SA 884 (O)
at 892,
Putco
Ltd v TV & Radio Guarantee Co
(
Pty
)
Ltd
and other Related Cases
1985 (4) SA 809 (A)
at 828I. Such a discretion was vested in the parties as they were to
sign 'a contract'
the precise terms of which were not fixed in the
letter of acceptance, which, unlike the action committee's
recommendation, did
not refer to annexure B. As the Tender Board
neither awarded a contract for the whole of the Free State nor
exactly followed
that committee's recommendations as to demarcation,
the elusive annexure B, whatever it did contain, could not have
served as
the contract to be signed. There was, accordingly, room
for a breakdown in negotiations before a contract was concluded.’
[7]
Southernport
Developments (Pty) Ltd v Transnet Ltd
2005 (2) SA 202 (SCA).
[8]
Letaba
Sawmills
(Edms)
Bpk v Majovi (Edms) Bpk
1993 (1) SA 768 (A).
[9]
Makate
v Vodacom (Pty) Ltd
[2016] ZACC 13; 2016 (4) SA 121 (CC).
[10]
Ibid
para 95.
[11]
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984] ZASCA 51
;
1984 (3) SA 623
(A).
sino noindex
make_database footer start
Similar Cases
Eskom Holdings Soc Ltd v Lekwa Ratepayers Association and Others; Eskom Holdings Soc Ltd v Vaal River Development Association (Pty) Ltd and Others (870/2020) [2022] ZASCA 10; [2022] 1 All SA 642 (SCA); 2022 (4) SA 78 (SCA) (21 January 2022)
[2022] ZASCA 10Supreme Court of Appeal of South Africa98% similar
Eskom Holdings SOC Limited v Letsemeng Local Municipality and Others (990/2020) [2022] ZASCA 26; [2022] 2 All SA 347 (SCA) (9 March 2022)
[2022] ZASCA 26Supreme Court of Appeal of South Africa98% similar
Waterberg Boulevard (Pty) Ltd v Smulhoekie Tuisnywerheid (Pty) Ltd and Another (283/2024) [2025] ZASCA 167 (4 November 2025)
[2025] ZASCA 167Supreme Court of Appeal of South Africa98% similar
Eskom Holdings SOC Limited v Babcock Ntuthuko Engineering (137/2023, 156/2023 and 148/2023) [2024] ZASCA 63 (29 April 2024)
[2024] ZASCA 63Supreme Court of Appeal of South Africa98% similar
Eskom Holdings Soc Ltd and Another v Sonae Arauco (Pty) Ltd (1018/2023) [2024] ZASCA 177; 2025 (3) SA 78 (SCA) (18 December 2024)
[2024] ZASCA 177Supreme Court of Appeal of South Africa98% similar