Case Law[2025] ZAGPJHC 74South Africa
Tibco Software South Africa (Pty) Ltd v Techsoft International (Pty) Ltd and Another (2023/011485) [2025] ZAGPJHC 74 (3 February 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
3 February 2025
Headnotes
in the well-known Sun Packaging decision where a contract is susceptible to several meanings the courts are reluctant to make this determination at exception stage.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 74
|
Noteup
|
LawCite
sino index
## Tibco Software South Africa (Pty) Ltd v Techsoft International (Pty) Ltd and Another (2023/011485) [2025] ZAGPJHC 74 (3 February 2025)
Tibco Software South Africa (Pty) Ltd v Techsoft International (Pty) Ltd and Another (2023/011485) [2025] ZAGPJHC 74 (3 February 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_74.html
sino date 3 February 2025
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
CASE
NO:
2023-011485
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
3
February 2025
In
the matter between:
TIBCO
SOFTWARE (SOUTH AFRICA (PTY) LTD
PLAINTIFF
and
TECHSOFT
INTERNATIONAL (PTY) LTD
FIRST DEFENDANT
TS
INNOVATIONS (Pty) Ltd t/a Tibo Solutions
SECOND DEFENDANT
JUDGMENT-
Exception application
Manoim J
INTRODUCTION
[1]
This case concerns an exception application that the two
defendants have brought in relation to the plaintiff’s
particulars
of claim.
[2]
The defendants are both subsidiaries of a large US based software
company known as Tibco Incorporated. Because the US
company, although
not a defendant in the matter, plays a role in the events, I will
refer to it as the Tibco Parent.
[3]
The Tibco Parent licences its affiliates worldwide, which in turn
sublicence its software rights to local intermediary
companies. This
is where the defendants fit in. They are affiliates of the Tibco
Parent, based in South Africa, and in turn selected
the plaintiff,
Techsoft, as a sub-licensee of its products. Plaintiff then licenced
Tibco products to its customers who were end
users. Thus, the
plaintiff is an intermediary. It licences users for which it earns
revenue and it in turn pays royalties to the
defendants. The
relationship soured. The details are not of concern at this stage.
Suffice to say that the plaintiff alleges that
the defendants were in
breach of the licensing agreement and in 2023 it elected to accept
the repudiation and cancel.
[5]
It then brought a claim for damages both in contract and
in delict. The plaintiff has made out four separate claims
for
damages. In a related application the defendants have brought an
application for the winding up of the plaintiff which has
not yet
been heard. This judgment only concerns exceptions raised in the
damages claim.
BACKGROUND
[6]
Over the course of the life of the damages claim the
defendants have raised various exceptions. On two occasions
the
plaintiff has amended its particulars of claim in response these
exceptions. However, this has not satisfied the defendants.
In the
latest round of exceptions, the defendants raise five grounds of
exception to three of the four claims brought by the plaintiff.
Since
the plaintiff does not consider these exceptions have any merit this
dispute has to be decided by me.
[7]
In the damages action the plaintiff makes out four
claims.
[8]
In the first claim it seeks a refund of a balance paid. No exception
is raised in this connection, so it need not be considered
further.
[9]
In the second claim it seeks damages for breach of contract. The
claim arises out of an agreement that plaintiff entered
into with the
first defendant in November 2020. It was known as the Strategic
Partnership Agreement (SPA) and according to Techsoft,
subject to
various conditions being fulfilled, was set to continue until 2033.
[10]
Pursuant to this agreement the plaintiff entered into various
agreements with end user customers. These are known as
End User
Licence Agreements or EULAS. The plaintiff entered into 106 such
agreements. They are classified differently but that
distinction is
not material for present purposes.
[11]
The parties fell out with one another. In September 2022, the
defendant served a notice of breach on the plaintiff and
required it
to rectify its breach within 30 days. The plaintiff has challenged
the validity of this notice but in any event in
February 2023
announced that it had accepted the defendant’s repudiation.
[12]
Hence from this alleged unlawful breach and lawful
repudiation, the plaintiff’s claim for damages arises.
[13]
What the plaintiff alleges is, that but for the breach, its EULAS
would have continued for the entire duration of the
SPA until 2033,
provided that it continued to perform in terms of the EULA
agreements. Put differently, as the intermediary, the
plaintiff would
have continued to earn revenue from its customers, the end users, as
long as it, as the supplier, and the defendants,
adhered to the SPA.
Once the defendants had breached the SPA, the Plaintiff alleges it
suffered damages in respect of the loss
of just over R 350 million.
[14]
The third and fourth claims relate to damages owing to the alleged
unlawful termination of contracts that the plaintiff
had with
specific clients. The third claim relates to a contract with Telkom
and the fourth relates to a contract with Nedbank.
Both are similar
in that the plaintiff alleges that these contracts, originally with
the Tibo Parent, were assigned to it with
the consent of the two
respective customers but then terminated due to the alleged breach
which plaintiff alleges amounted to a
repudiation of the respective
agreements that it had accepted. Each of these claims has attracted
two objections, one relates to
whether the contracts were lawfully
assigned to the plaintiff and if they were, the basis for alleging
that they would have endured
until 2033, which is the same duration
period as for the EULAS.
First
objection: EULAS
[15]
The plaintiff has only attached one of the EULA agreements. It pleads
that it is unable to attach the remaining 105,
as these were all on a
server controlled by the defendants to which it (the plaintiff) no
longer has access. Put simply it says
it has been blocked. However,
it has attached one EULA, with Mediclinic, as the end customer. It
says the standard terms of this
EULA are the standard terms of all
the others.
[16]
However, and this is where the first objection comes from the
defendants. They allege that the particulars read with
the agreements
attached, do not sustain the allegation that the EULAS would have
persisted until 2033. The defendants point out
that the EULA’s
comprise a standard form agreement ( called the Master terms) and a
separate document containing terms called
an Order form. The
Order form, forms part of the contract and contains in its preamble
that if there is any conflict between its
terms and that of the
Master agreement, the terms of the Order form prevail. On the
Mediclinic order form there is a table which,
inter alia, provides
for the start date and the term end date. According to this Order,
the Mediclinic contract starts on 7 November
2019 and ends on 6
November 2022.
[17]
Given the limited duration of the contract on this Order form the
defendants allege that no basis is set out in the contract
for the
allegation that the EULAS (i.e. all 106 of them) would have continued
until 2033. Thus, the conclusion is that the order
form, which forms
part of the contract, and supersedes the terms of the Master
agreement, conflicts with the particulars of claim
in respect of
duration and render it expiable.
[18]
But the plaintiff argues that this is a misreading of the
contracts. The order form it argues simply provides for that
is
termed an ‘initial period’ notwithstanding the words
“Term end date” found on the Mediclinic order form.
[19]
Instead, the plaintiff argues one must read the terms of the Master
agreement which are complementary to and not contradictory
with the
duration terms on the Order form. In Annexure A of the Master
agreement Clause 12.1 says the agreement commences on the
effective
date reflected in the “initial order” form and shall
remain in effect for a period of one year. Granted thus
far this is
making the excipients’ point. But in the next sentence it
states that: “
Subject to … the parties may agree to
renew the agreement for additional one year periods subject to
payment by the partner
of the applicable annual fees.”
[20]
Then in Annexure B two provisions deal with continuity. The
first is section 12(a) which provides that the agreement
remains in
effect until terminated. But the more meaningful section is 12(c)
which says:
“
Following the
end of the initial term for … the Term will automatically
renew continuously for the same length as the Initial
term unless
either party gives written notice of at least 60 days prior to the
end of the initial or any renewal term of its intention
to
terminate.”
[21]
The plaintiff argues that this provides that the contract
between the parties is one that continually rolls over despite
the
fact that it has an initial period and is composed of several renewal
period. On this interpretation of the Agreement there
is a reasonable
interpretation that the contract remains in place subject of course
to contingencies for an indefinite period.
Given that the plaintiff’s
rights existed until 2033 in terms of the SPA, that would, on this
interpretation, be a plausible
end period.
[22]
In this respect the exception fails. The provisions on the
Order and the Master agreement can be read to complement
one another
and not to contradict the allegations made out in the Particulars of
claim. As was held in the well-known
Sun
Packaging
decision where a contract is susceptible to several meanings the
courts are reluctant to make this determination at exception stage.
[1]
[23]
More problematic is how the plaintiff reaches the quantum of damages
for this claim. Here the assumption made by the
defendants was that
the amount was realised using the Mediclinic fees as a proxy for all
the others. This was a reasonable assumption.
However, during the
hearing counsel for the plaintiff advised that this was not the case,
and each contract was different in this
respect. If that is the
situation then it is necessary for the plaintiff to specifically
plead how these figures are arrived at.
Granted a spreadsheet is
provided of the total figures for each year until 2033, but there is
no breakdown for each respective
contract if these figures are
different. These figures should be provided. The plaintiff’s
response is that this was not
an issue specific to the exception and
should not ordered. That may be so, but it is implicit in the
exception taken based as it
was on a reasonable misunderstanding of
the pleading. Given that the plaintiff is going to have to go back to
the drawing board
in respect of some of the exceptions which I will
uphold, it would be convenient to order this now to avoid a further
series of
exceptions from the defendants – precisely what the
plaintiff has complained about.
Second
Objection: The Telkom claim
[24]
In its third claim the plaintiff claims damages from the
defendants for repudiating a contract between itself and Telkom
which
it alleged would have persisted until 2033. This repudiation took
place in October 2022 when the second defendant withheld
access to
certain rights and services to the plaintiff and approached Telkom
directly to provide the services. The plaintiff accepted
the
repudiation in February 2023 and now sues for damages for loss of
profit.
[25]
The claim is based on a tripartite contract entered into
between the second defendant, Telkom, and the plaintiff in
March
2020. The contract is annexed to the particulars of claim.
[26]
To found its claim under this head of damages the plaintiff
relies on the following clauses in the tripartite contract.
[27]
A clause that records that the parent company had a contract
with Telkom in terms of a Master agreement dated September
2007.
[28]
Then a clause in which the second defendant assigns its rights
and obligations arising from the Master agreement to
the plaintiff.
There are then clauses in which the plaintiff accepts the assignment
and to which Telkom gives its consent. Thus,
the claim is based on
the terms of this assigned agreement.
[29]
But the exception is that there is a gap here. The Master
agreement was with the parent. This is evident from clause
2.4. But
2.4 is phrased in this way under a section headed recordal:
“
Addenda 14 and
15 are governed by the terms of the Agreement No 091C/06 for the
provision of Licensed Software Maintenance, Support
and Services
entered into on 29 September 2006 with contract number SLSA4 877
between Telkom SOC Limited and TIBCO Software inc.
("Master
Agreement") as assigned from TIBCO Software Inc
[Tibco
parent]
to TS Innovations (Pty) Limited
[the second defendant]
on 28 September 2007
.”
[30]
Addenda 14 and 15 comprise the agreement allegedly then
assigned on to the plaintiff. But says the second defendant,
there is
no allegation that these rights were assigned by the parent company
to the second defendant. The most that can be said
is an allegation
by way of a recordal that they had been assigned to the second
defendant.
[31]
But this does not mean that the plaintiff has not made out a
cause of action. It relies on the tripartite agreement,
and it
alleges that the second defendant had been assigned these rights by
its parent in September 2007. Granted it does not attach
the
agreement of assignment, but it alleges it had taken place. If there
was no such assignment and the second defendant could
not lawfully
pass on these rights the plaintiff, then the defendants can plead
that. The plaintiff’s cause of action here
is made out clearly.
[32]
I find that there is no basis to this objection, and it is
dismissed.
Third
Objection: Duration of the Telkom claim
[33]
Recall that the claim is for the duration of the contract
which the plaintiff alleges would have persisted until 2033.
In this
objection the defendants allege there is no basis to contend that the
contract would have endured for this period.
[34]
The pleaded case is that the agreement was in force for one
year from the effective date. However, in the miscellany
of contracts
that govern the Telkom agreement is one referred to as 091C/06. That
contains in paragraph E a clause that states:
“
Term
and Termination. This initial term for the provision of Maintenance
shall be from the Effective Dale of this Agreement and
thereafter may
be renewed annually upon payment of the applicable Maintenance Fee.
Maintenance Services may be terminated: (a)
by either upon a default
of the other, such default remaining uncured for fifteen days from
written notice from the non-defaulting
party; (b) upon the filing for
bankruptcy or insolvency of the other party, (c) by either party upon
prior written notice at least
sixty days prior to the end of any
annual Maintenance period.”
[35]
The plaintiff’s argument here is the same as that
with the EULAS; whilst there is mention of an initial period, the
contract
contemplates an annual renewal provided the conditions are
met. Thus, the renewed annual provision subject to the fulfilment of
the conditions can be interpreted to provide a roll over provided the
plaintiff retains its rights from the second defendant. This
it is
alleged is retained until 2033. Again, I find that a cause of action
is disclosed here for the period alleged. This exception
must be
dismissed.
Fourth
Objection: the Nedbank contract: assignment
[36]
Here the plaintiff alleges an assignment of a contract again
of a key customer, Nedbank. The plaintiff alleges that
in October
2020 it entered into a three way assignment agreement with a
representative of the second defendant, as well as Nedbank.
This
agreement is said to be verbal by which I understand this to mean an
oral agreement between the three parties. As a matter
of law although
unusual, an assignment of an agreement does not require the formality
of being reduced to writing. But unlike with
the Telkom contract
there is no agreement annexed.
[37]
Instead, what is attached is a consent from Nedbank dated 15
September 2020. The document records that Nedbank had had
a Master
service agreement with the Tibco Parent company since 2006. Thus far
this is on all fours with the Telkom situation. However
here Nedbank
in the consent states the following:
“
Nedbank
acknowledges that TIBCO intends to assign Agreements to TechSoft
International (Proprietary) Limited, Registration Number
2016/365152/07 (eTechSoft").”
[38]
From this letter which is all that has been provided by the
plaintiff there is an allegation that the Tibco Parent company
( that
is the Tibco contemplated in the letter) will assign the agreements
directly to the plaintiff. Here there is no intermediate
role for the
second defendant, unlike there was with Telkom. Yet in the
particulars of claim the allegation is that it is the second
defendant which makes the assignment to the plaintiff. Thus, there is
confusion and the exception that there has been no assignment
alleged
is well taken. The plaintiff needs to clarify this issue. Did the
representative of the second defendant who according
to the
particulars of claim agreed to the assignment, represent the parent
as well, or had the parent already assigned the agreement
to the
second defendant and the Nedbank letter is mistaken on this point.
The exception here is upheld and the plaintiff must clarify
its case
on this point. The defendant is entitled to know which entity is
alleged to have assigned these rights to the plaintiff.
Fifth
Objection: the Nedbank contract: duration
[39]
The same allegation is made by the plaintiff that the Nedbank
agreement would have endured to 2033 but for the unlawful
repudiation
by the second defendant. But given that I have upheld the exception
in respect of the underlying agreement it is premature
to decide this
point. In anticipation of future challenges, this challenge will be
determined by the existence of same roll over
provisions as in the
Telkom agreement. If that is on the same terms, then a roll over
would have been sufficiently pleaded. But
if not, the outcome will
depend on the particularity that will be furnished.
Conclusion
[40]
I have dismissed three exceptions, upheld one, partially
upheld another (the Eula quantification aspect) and have
not
been able to determine the one which is contingent on the outcome of
further pleading in respect of the objection I upheld
(the Nedbank
duration). As no party has been completely successful each should pay
its own costs.
[41]
Both parties agreed that if an exception was upheld the
plaintiff was entitled to be given an opportunity to amend its
pleadings. I have done so.
ORDER: -
[42] In the result
the following order is made:
1.
Objection on is partially dismissed, but partially upheld. It is
partially upheld in respect the plaintiff failing to plead
in
what respect each respective claim for damages for the Eulas is made
up. The plaintiff is given 20 days to amend its particulars
of claim
in this respect.
2.
Objections two and three are dismissed.
3.
Objection four is upheld. The plaintiff is given 20 days to amend its
particulars of claim in this respect.
4.
Objection five is postponed, pending the outcome of the amendment of
the particulars in respect of objection four.
5.
Each party is liable for its own costs.
N. MANOIM
JUDGE OF THE HIGH
COURT
GAUTENG DIVISION
JOHNANNESBURG
Date of hearing: 04
December 2024
Date of Reasons: 3
February 2025
Appearances:
Counsel for the First and
second defendant
(Excipient):
N J Graves SC
A
Vorster
Instructed
by:
White and Case Inc.
Counsel
for the Plaintiff
(respondent in
exception): A R Bhana SC
R R.
Kirsten
Instructed
by:
Pather & Pather Attorneys Inc
[1]
Sun
Packaging Ltd v Vreulink
[1996] ZASCA 73
;
1996 (4) SA 176
(A) at 186J
sino noindex
make_database footer start
Similar Cases
Technologies Acceptances Receivables (Pty) Limited and Others v Selebogo Incorporated and Another (2022/001657) [2025] ZAGPJHC 491 (21 May 2025)
[2025] ZAGPJHC 491High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Technologies Acceptances Receivables (Pty) Ltd and Another v Thavalerie Travel CC and Another (2022/11927) [2025] ZAGPJHC 573 (10 June 2025)
[2025] ZAGPJHC 573High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Tabletpot Admin (Pty) Ltd v Jolliet and Another (2025/061274) [2025] ZAGPJHC 605 (17 June 2025)
[2025] ZAGPJHC 605High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Catalina Invstments (Pty) Ltd v Government Pension Administration Agency (A2024/084497) [2025] ZAGPJHC 565 (11 June 2025)
[2025] ZAGPJHC 565High Court of South Africa (Gauteng Division, Johannesburg)98% similar
T.R.S.T v U.A.R and Others (019086/2023) [2025] ZAGPJHC 399 (14 April 2025)
[2025] ZAGPJHC 399High Court of South Africa (Gauteng Division, Johannesburg)98% similar