Case Law[2026] TZHC 2623Tanzania
Alexander Rutakinikwa John vs Dodoma City Council and Another (Civil Case No. 21012 of 2024) [2026] TZHC 2623 (25 May 2026)
High Court of Tanzania
Judgment
1 | P a g e
IN THE HIGH COURT OF TANZANIA
DODOMA SUB REGISTRY
AT DODOMA
CIVIL CASE NO. 21012 OF 2024
BETWEEN
ALEXANDER RUTAKINIKWA JOHN …………………………..PLAINTIFF
VERSUS
DODOMA CITY COUNCIL ………..………………………1
ST
DEFENDANT
THE ATTORNEY GENERAL ………………………………2
ND
DEFENDANT
JUDGMENT
Date of last order: 22/04/ 2026
Date of Judgment: 25/05/ 2026
LONGOPA, J.:
On 14 August 2024, the Plaintiff instituted this civil suit against the
Defendants for declaration that the 1st Defendant has disrupted the
Plaintiff’s project of extracting fill materials (kifusi) from the Plaintiff’s
2 | P a g e
property by unilaterally and unjustifiably canceling his licence, a declaration
that the 1st Defendant has disrupted the Plaintiff’s investment plan over his
property, a claim for loss of business, loss of investment and general
damages.
According to the Plaint, the Plaintiff is a lawful owner of land
measuring 44,740 square metres located at Msangalale Mashariki, Dodoma
Makulu Ward, Dodoma City Council whereby the Plaintiff decided to
develop by levelling the land surface by extracting fill materials / rubble
(kifusi) for construction activities and to achieve that, he approached all
relevant authorities to obtain permits as demonstrated including a Broker’s
Licence No. BL/027/DOM/2023/2024 issued by Mining Commission, permit
to extract rubble vide a letter Ref. No. HJD/M.30/1/60 dated 23rd
November 2023 and obtained recommendations from the Ward
Development Committee (WDC) of Dodoma Makulu Ward through an Extra
Ordinary Meeting held on 8th November, 2023. A copy Minutes of the WDC
in a meeting held of 8th November 2023 as well as having engaged
prepared an Environmental Protection Plan for the Proposed Site Leveling
3 | P a g e
Project at Msangalale Mashariki ‘Mtaa’, Dodoma Makulu Ward, Dodoma
City Council in Dodoma Region which formed basis for issuance of a
permit.
According to the Plaint, the Plaintiff started executing the Project but
to his surprise, three days after commencement of operations, on 8th
December, 2023, vide the 1
st
Defendant’s letter Ref. No. HJD/F.30/4/50,
the 1st Defendant, without consultation and further without any justifiable
cause unilaterally ordered the project to stop. According to the Plaintiff the
1
st
Defendant’s act was activated by malice and sole intention of disrupting
his business. Plaintiff added that reason stated by the 1
st
Defendant’s order
was environment degradation was unjustified because the Plaintiff was
adhering to the Environmental Protection Plan prepared for the Project and
there were ongoing extraction of rubble (kifusi) in the close neighborhood
without the intervention of the 1
st
Defendant and that Plaintiff was not
consulted or heard before the 1
st
Defendant cancelled his permit.
4 | P a g e
It was further averment of the Plaintiff that Plaintiff’s project
disrupted by the 1
st
Defendant’s acts has a value in excess of Tanzania
Shillings One Billion (TZS 1,000,000,000/=). As a result, the Plaintiff prayed
for Judgment and Decree against the Defendants on the following orders:
(a) A declaration that the 1
st
Defendant has unlawfully
disrupted the Plaintiff’s project of extracting fill
materials (kifusi) from his property located at
Msangalale Mashariki, Dodoma Makulu Ward,
Dodoma City Council by unilaterally canceling his
licence without any just cause.
(b) A declaration that the 1
st
Defendant has disrupted
the Plaintiff’s investment plan of developing his land
located at Msangalale Mashariki, Dodoma Makulu
Ward, Dodoma City Council.
(c) An order that Defendants pay to the Plaintiff an
amount of not less than Tanzania Shillings One
Million per day from 8th December, 2023 until the
date of Judgment being loss of business income from
sale of fill material (kifusi) extracted from the
Plaintiff’s property.
(d) An order for payment of general damages for all
inconveniences caused to the Plaintiff for loss of
5 | P a g e
business and disruption of investment plan as may
be assessed by the Court.
(e) A permanent injunction restraining the 1st
Defendant, his agents, employees, assigns or
successor in title from interfering with the Plaintiff in
the carrying out his project save for material
deviation from the Environmental Protection Plan for
the Proposed Site Leveling of the Plaintiff’s property.
(f) That the Defendant pay interests on the amount
awarded in (c) and (d) above at Court rate from the
date of the date of Judgment until the sum is paid in
full.
(g) Costs of this suit be borne by the Defendants
(h) That the Court be pleased to grant and other
relief(s) it may deem fit and just to grant
The Defendants refuted any wrong doing and reiterated that the
stoppage of the activities in the land in question was violation of the
permit’s conditions
There were three issues that were drafted for determination of the
suit before this Court. These framed issues are that:
6 | P a g e
1. Whether the 1
st
Defendant disrupted the Plaintiff’s
business of extracting fill matters (kifusi) and levelling his
land;
2. Whether the 1
st
Defendant had justifiable reasons to
cancel the permit to extract fill matters(kifusi) issued to the
Plaintiff?; and
3. What are the reliefs are the parties entitled thereto?
In course of hearing of the suit, the Plaintiff enjoyed the legal
services of Mr. Respicious Didace, learned advocate and Omary Ngatanda,
learned State Attorney for the Defendants. The parties called a total of five
witnesses and the Defendants called a single witness. The summary of
evidence is as follows:
PW 1 was one Eladi Focus Tarimo stated that he an environmental
expert who was engaged by Mr. Alexander Rutakinikwa John since 2023 to
prepare Environmental Protection Plan (EPP) for residential area where
levelling of the plot was to be conduct while ensuring environmental
protection is maintained. PW 1 stated to have prepared the EPP Report in
7 | P a g e
collaboration with Salvatory John as an Environmental expert and Glory
Charles who was Environmental Scientist and Health and Safety Expert.
According to PW 1, the EPP was prepared and submitted to Dodoma
City Council for permit and the Mining Commission for the Licence to
extract the rubble (fill/ kifusi). The Environmental Protection Plan for the
Proposed Site Levelling Project at Msangalale Mashariki “Mtaa” Dodoma
Makulu Ward in Dodoma City Council in Dodoma Region 17
th
November
2023 was admitted as Exhibit PE. 1.
It was PE 1’s testimony that preparation of EPP Report involved site
visit involving the Environmental Experts from Dodoma City Council,
holding of the Meetings with Mtaa residents, leaders of the local
government at Mtaa level and Ward Level at Dodoma Makulu Ward and the
name of the Mtaa is Msangalale Mashariki. DW 1 further noted that
minutes of those meetings were recorded forming part of the Report that
was submitted to Dodoma City Council and the Mining Commission to
8 | P a g e
validate participation of leadership and residents of the area where EPP
applies as seen on page 34 of the Report.
PW 1 averred that preparation of Exhibit PE 1 was aimed to facilitate
the levelling the site prior to construction of the residential buildings as the
area required the EPP due to nature of the area. The levelling involves
removing or extracting heavy materials that would be shifted to another
area. The fill/ rubble (kifusi) was to be extracted as Plaintiff obtained the
broker mining licence from the Mining Commission as found on page 42 of
the Report. Upon submission of the Report, the 1
st
Defendant issued a
permit to allow levelling to be done.
It was PW 1’s evidence that levelling commenced but Dodoma City
Council had stopped the activities after three days of operation. The
reasons were stated to be the environmental degradation/ pollution that
was being caused by the activities in question. It was PW 1 ’s evidence that
on arrival at the site he did not find any environmental degradation as the
9 | P a g e
Plaintiff did not extract more than five meters deep as permitted by
authorities.
PW 1 stated that at the site there were no activities of drilling that
were being conducted at the site other than normal levelling as the EPP
Report had only allowed levelling and the stoppage has made the site
remain unleveled.
In cross-examination, PW 1 admitted to have not tendered any
certificate from the Occupational Safety and Health Authority (OSHA) nor
any evidence that he once performed EPP or related assignments. Also, PW
1 noted that in the EPP Report there was no certificate with his name as
the person who did conduct EPP.
PW 1 added that the EPP was for levelling of the site, the Mining
Licence is silent on depth of the levelling but the permit from Dodoma City
Council is one stating about the depth. PW 1 added that he saw the permit
from Dodoma City Council but nothing indicates about the depth of the
levelling of the site. PW 1 had not stated the measurement tools/ facilities
10 | P a g e
he used to measure that levelling had not exceeded five meters but it was
estimated. PW 1 admitted to have not tendered any evidence whatsoever
to prove that degradation/pollution did not happen.
Moreover, PW 1 reiterated that he was not registered EIA Expert and
that though he was there when operations to level commenced yet he
could not recall the date when the levelling of the site commenced. PW 1
added that he saw a letter stopping levelling due to environmental
degradation/ pollution from Dodoma City Council. PW 1 noted that EPP
Report was for protection of environmental to water sources, degradation
or pollution to residents and not affect the passage as there is a road. PW
1 admitted that monitoring and audit of EPP was a function of the Dodoma
City Council.
It was PW 1’s evidence that he was engaged by the Plaintiff
separately as a consultant to ensure implementation and that there was no
drilling in that plot of the land. PW 1 admitted that the permit required the
Plaintiff to ensure environmental management through restoration by
11 | P a g e
planting the trees. The permit was for extraction of the fill matter/ rubble
and then restore the area by planting trees only. At this juncture, PW 1
noted that the permit was issued on 23/11/ 2023 while operation
commenced on 27/11/ 2023 but the stoppage of activities letter was issued
on 03/ 12/ 2023.
In re-examination, PW 1 noted that object of EPP Report to ensure
there is environmental protection and safety of the community sorrounding
the area where the project was to be implemented. PW 1 refuted on
existence of drilling as no holes were created and that EPP Report involved
all stakeholders including the Environmental Experts from Dodoma City
Council. PW 1 added that the consultant is the one who puts the
certificate. The registered expert was one Salvatory John. The result of
the work the experts were doing resulted into the preparation of the EPP
Report.
PW 2 was Gerald Juma Chalo stated that he was a ten-cell leader at
the area where the land is situated in Njedengwa East as the Plaintiff
12 | P a g e
resides there. PW 2 stated to had introduced the Plaintiff to Mtaa/ Street
Leadership in 2017 when the Plaintiff informed about owning that land.
PW 2 stated that he saw some tractors/ machineries that were
levelling the land but after three days he was informed about the stop
order to level the land in question from Dodoma City Council. PW 2 noted
to have seen the environmental degradation though he was not expert to
ascertain that aspect. He added that the experts are the one to explicitly
say on existence or otherwise of the pollution/degradation.
In cross examination, PW 2 stated that as a ten-cell leader at
Njedengwa East, saw the Plaintiff extracting the fill as the land was being
levelled which involved digging the fill.
Another Plaintiff ‘s witness was Daudi Chawala Chakulanga who
testified as PW 3. PW 3 stated that he knows Alexander Rutakinikwa John
who was a resident in Msangalale East since 2019 and that in 2023 the
Plaintiff submitted documents from the Mining Commission and Dodoma
13 | P a g e
City Council allowing levelling of the land for construction/ erecting
buildings at that area. The documents were permit and licences.
It was PW 3’s testimony that a s a Chairman of the Mtaa/ Street,
there was conducted Mtaa Council meeting to approve the project of
levelling whereas the Plaintiff promised to construct an office for Mtaa,
rehabilitate the road for the Msangalale East Street/ Mtaa as part of Social
Responsibility to residents as he was conducting a project. PW 3 noted
that upon several days of implementing the project, the Plaintiff received a
letter from Dodoma City Council estopping the Plaintiff from continuing
with the project to level the land. On lamentation by Mr. Alexander
Rutakinikwa, the Mtaa leadership informed the Plaintiff to visit Dodoma City
Council for resolution of the matter.
PW 3 noted that he saw permit and licence to operate the project but
PW 1 explicitly noted that he was not aware of manner and process of
obtaining the documents. It was PW 3 testimony that at the site there
were excavators that was taking the fill/ kifusi and the personnel from
14 | P a g e
Dodoma City Council were there with Point on Sale (POS) devices to collect
levies.
According to PW 3, the activities operated for about three days
before stoppage on grounds of environmental pollution/ degradation
though personally PW 3 did not environmental degradation nor heard any
complaint except dust from the road that affected the houses along the
road. PW 3 reiterated that having noted dusts affecting houses from the
lorries ferrying the fill, the Plaintiff was informed, brought water boozer to
prevent dusts which calmed the situation.
According to PW 3, the stop order of the project affected the
residents as there was stoppage of the construction of the Mtaa Office and
rehabilitation of roads along that street thus residents were not very much
pleased as those projects could not take off despite the same being
announced at Mtaa General Assembly.
In cross-examination, PW 3 reiterated that he brought no evidence to
identify him as Mtaa Chairman from 2019 to 2024. PW 3 noted that he
15 | P a g e
never brought the permits and licences that Plaintiff to Mtaa office nor
records of the Minutes and other meetings regarding the implementation of
the project and the corporate social responsibility of the investor. PW 3
admitted that he was not aware of the person who signed the stoppage
letter and did not bring it to court.
In respect of the levelling, PW 3 stated that there was levelling and
drilling but he was not an expert to confirm whether it was levelling or
drilling. He added that was Dodoma City Council who issued the permit,
inspected/ audited the implementation but he cannot ascertain that they
found him violated the permitted actions. PW 3 added that Mtaa
Government has not stopped any person who is implementing a project
correctly and that generally the Government cannot stop a person who
operates activities in accordance with the law and procedure who was not
in violation of the law. PW3 noted that he was not an environmental
expert. In re-examination, PW 3 stated that he was not an expert in
environmental management but he did not see environmental degradation.
16 | P a g e
PW 4 was Amosi Sanda stated to have known the Plaintiff since 2022
as he sold the Plaintiff a piece of land in that area and that Plaintiff bought
other neighbouring lands neighbouring the plot he sold to the Plaintiff. PW
4 noted that he saw the levelling land but after few days there was
stoppage of the same. According to PW 4, there was no degradation of
environment at that area as the it is a hill-land that should be levelled to
remove gorge/canyon so that one could proceed with the construction in
that site.
In re-examination, PW 4 admitted to have never tendered any
documentations on description of land in terms of size, neighborhoods or
purchase price. The evidence of PW 4 added that Plaintiff commenced
levelling after he purchased land but PW 4 was not sure if there were any
permits from the government except seeing the levelling that land. PW 2
admitted that he was not environment expert and he knows nothing about
environmental degradation.
The last witness for Plaintiff was PW 5 was Alexander Rutakinikwa
John who testified that dispute arose out of stoppage by the Dodoma City
17 | P a g e
Council on the levelling of land belonging to him located at Msangalale
Mashariki in Makulu Ward in Dodoma thus prevented his investment.
PW 5 stated that he owns land having purchased it from neighbours
for developing by constructing the buildings but required levelling as it is a
hilly land. PW 5 added to have obtained broker mining licence from
Resident Mines Office for Dodoma to request for extracting the fill
materials. At this juncture, a Broker Licence No BL/027/DOM/2023/2024
dated 30
th
October 2023 was admitted as Exhibit PE 2.
PW 5 stated to have applied for the permit from the Dodoma City
Council whereby Dodoma City Council granted the permit as land in
question was hilly thus levelling was allowed while considering
environmental protection. PW 5 reiterated to engaged Salvatory Tarimo as
an Environmental Expert prepare Environmental Protection Plan (EPP)
whereby stakeholders’ meetings were conducted at Mtaa level Residents
and Ward Officials for Makulu Ward. The EPP Report which is Exhibit PE 1
was submitted to Dodoma City Council who upon being satisfied permitted
18 | P a g e
the extraction of the gravel/ fill. It was PW 5 ’s testimony that contains
aspects of environmental protection during the investment/ extractions. It
included presence of broker’s licence, the records of meetings of the Mtaa
residents, meetings’ records from the Ward Officials, ownership of the land
documents, the correspondences between the Mining Commission and the
Dodoma City Council and documents relating to qualification and practice
by the consultant.
Exhibit PE 1 was submitted to Dodoma City Council and the Regional
Office of the Mining Commission. It was the satisfaction by Dodoma City
Council that permitted the activities to be carried on.
PW 5 stated that extraction of fill commenced on November 2023 but
within five days of operation, Dodoma City Council stopped the extraction
of the fill vide a letter on account of environmental destruction/ pollution.
A letter dated 8
th
December 2023 from Dodoma City Council to Alexander
Ruttakinikwa John entitled: Kusitisha Kibali cha Kuchimba Kifusi cha tarehe
23/11/ 2023 kwenye eneo lenye leseni Na. BL/ 027/DOM iliyopo Kata ya
19 | P a g e
Dodoma Makulu Mtaa wa Msangalale Mashariki was admitted as Exhibit
PE 3 .
It was PW 5 evidence that upon receipt of the letter, Plaintiff waited
for Dodoma City Council to call him for discussion but nothing came up. It
was PW 5 that he thus consulted the learned advocate thus a Ninety days’
notice was prepared and served to the Defendants.
It was further evidence of PW 5 that the letter stopping the activities
at the site was communicated to various persons including the Regional
Mining officer, District Commissioner, Police Station and the Ward Office.
PW 5 noted that he got a letter from the Resident Mines Office for Dodoma
lamenting on non-involvement in stoppage of the activities. At this
juncture, a letter dated 20
th
December 2023 from Mining Commission to
Dodoma City Council was tendered and admitted as Exhibit PE 4 .
PW 5 added that the consultant for EPP visited Mtaa residents and
Ward Officials on the comments regarding the project and the meetings
records indicate that aspect thus tendered a Letter and Minutes of the
20 | P a g e
Meeting before the Ward Executive Officer date 9
th
November 2023 which
were Exhibit PE 5 collectively.
It was testified by PW 5 that the reason stated in the letter stopping
the extraction of the fill materials was not satisfactory at all as none of the
persons involved in operation of the project from Mining Commission and
Dodoma City Council stated anything on environment being polluted or
destroyed.
PW 5 stated that stoppage of activities has caused the Plaintiff a lot
of inconveniences as he had secured investment capital from the bank, he
had agreements with the persons who were constructing roads which were
terminated and the Plaintiff had to compensate them. It was PW 5 that
stoppage of extracting the fill materials shuttered all his dreams to have
income and profits that could be realised. PW 5 added that had
arrangement with Mining Commission to collect the payments on the fill
materials he was extracting. In fact, PW 5 reiterated to that he had to pay
21 | P a g e
the loans using other means while no production at the site where he
intended to realise profit.
It was added by PW 5 that the nature of project required called
engagement of persons who are dealing with fill. The contractors were
engaged and brought machinery which are costly for each day that the
machineries are there. PW 5 reiterated to have entered into agreement
with Mtaa wa Msangalale Mashariki residents to build office of the Mtaa
and employed the residents of that area to have livelihoods. PW 5
concluded that stoppage affected him for continuing with the project to
construct/ built houses there for leasing as planned came to halt.
PW 5 prayed that this court be willing to declare that stoppage of the
project by Dodoma City Council was not proper and impaired Plaintiff’s
investment as it was wrongly stopped thus this Court should order that
project must proceed to operate. The licence and permits should be re-
issued and prayed that he be compensated for the amounts of costs he
had incurred throughout this process.
22 | P a g e
In cross examination, PW 5 stated to have not tendered any report
from the Mining Commission to validate that plot of land to have been
suitable for extraction of fill materials. PW 5 admitted that though
Paragraph 4 of the Plaint indicates that Dodoma City Council unjustifiably
cancelled the Licence, he stated that he never got any letter from the
Mining Commission cancelling the broker ’s licence.
PW 5 reiterated that he was levelling the plot only not mining
whereby he had mining operation extracting the fill materials/ rubble from
that area. The permit was for levelling not mining operation. PW 5 noted
that had engaged in several agreements but nothing of such agreements
was tendered. PW 5 further noted that he never mentioned any amount
that was incurred nor amount of profit that he would have generated from
the project. PW 5 added that he never tendered any agreements on loan
amounts he had taken to facilitate project operation.
PW 5 reiterated that though he intended to construct housing for
leasing but no architectural drawings were tendered before this Court. The
23 | P a g e
permit was levelling the area and extract the fill materials, but refuted to
have mined.
In re-examination, PW 5 stated that Exhibit PE 4 which was a Mining
Commission ’s letter categorically indicated that the decision by Dodoma
City Council was not proper and requested the project to proceed. PW 5
added that levelling involved the excavators taking the soil after cutting
that soil first in order get the level that is required. Accordingly, PW 5
stated that he had not violated the permit from Dodoma City Council as he
was levelling the area as permitted.
Conversely, the defence had two witnesses. DW 1 one Neema
Gaudence Komba, an Environmental Officer in Dodoma City Council
testified that she was aware of the dispute before the court that Plaintiff
was granted a permit to level the land at Msangalale Mashariki where he
had a plot of land which needed levelling to allow development in the plot.
However, on the third day of operation of the levelling at the site as per
the permit, the Head/director of the Capital Development and the Head of
24 | P a g e
Environmental Division visited the site for inspection and audit where they
found the site was being drilled in contravention of the permit. It wa stated
that upon perusal of the records, it was revealed that Plaintiff had done an
Environmental Protection Plan (EPP) instead of the Environmental Impact
Assessment (EIA) to allow drilling activities. The permit was only for
extraction of fill/rubble by levelling without drilling of the land in question.
It was DW 1 testimony that EPP is only done is gorges and canyons
where sand is collected without drilling of the land but in the disputed site
there was drilling contrary to terms of the permit. The Head of the Capital
Development Division on behalf of Dodoma City Council Director decided
that the Plaintiff should be stopped from execution of the project.
According to DW 1, Exhibit PE 1 was the EPP relating to place where
fill materials/rubble is collected without drilling. The levelling is only be
taken have happened especially when the same does not involve the
drilling at all. DW 1’s testimony reiterated that a ny drilling of the land
would require Environmental Impact Assessment to be done before the
25 | P a g e
project commences. The document in form of a letter attached on
introduction of the Plaintiff required the EIA to be conducted not EPP.
The findings by 1
st
Defendant who visited the site found that drilling
was taking place instead of levelling as allowed in the permit for the
Plaintiff. Thus, the Plaintiff had violated the terms of the permit by drilling
instead of just levelling of the plot of land.
Also, admitted that Exhibit PE 3 was a letter which was authored to
stop the excavation or drilling in the site dated 23 November 2023. The
reasons for the stoppage of the permit was the environmental degradation
as the activities would have required the EIA to be conducted.
In Exhibit PE 1 there is a letter from Dodoma City Council to Resident
Mines Office Dodoma Regional relating to the inspection of the site and in
Paragraph 4 was categorically clear that development shall be levelling
alone not drilling at all and inspection would be done regularly. On
paragraph 6, the developer was required to conduct the Environmental
Impact Assessment (EIA), seek and obtained EIA Certificate from the
26 | P a g e
Minister for Environment. Further, there was a requirement that the
developer should visit Dodoma City Council for all the procedural
requirements to be complied having obtained the Certificate of EIA.
There was no EIA Certificate but the Plaintiff was drilling the land not
levelling of the land contrary to the permit. The Plaintiff never complied to
the requirements as there were excavators drilling the land on the site
which contravened the permit.
In totality, there was environmental degradation and pollution on the
site by the Plaintiff. It was a prayer of DW 1 that this court be pleased to
dismiss the case for want of merits as there is nothing tangible on claims of
the Plaintiff.
In the cross examination reiterated to hold a Bachelor Degree in
Urban Development and Environmental Management from Institute of
Rural Development in 2015 and employed since 2017 as the Environmental
Officer at Dodoma City Council.
27 | P a g e
In relationship to extraction of rubble/fill materials (kifusi), DW 1
stated her responsibilities are to ensure that there is Licence from the
Mining Commission and the City Council writes/issues a letter of
introduction with the conditions attached thereto including the need for
EIA. It is the Dodoma City Council that supervises the environmental
protection against pollution and ensure protection of the rights of the
Corporate Social Responsibility, to ensure that the vehicles collecting the
rubble/fill materials are not causing pollution and supervise collection of
government dues etc.
It was further evidence of DW 1 that the fill materials are extracted
in hilly areas where there is ample soil and that the Plaintiff’s land w as
allowed to extract the fill materials as per permit. The City Council also
issues a permit to extract rubble/fill material. Conditions are that officers
must visit the site to take coordinates to know land use to determine if the
land use allows extraction of fill and in case land is not permissible to
extract the fill materials then permit cannot be issued. It is the EIA that
allows the activities to progress as it guides the project implementations
28 | P a g e
and consider the vicinity with the residents and existence of roads to avoid
conflicts. All these are pre-conditions to the project implementation.
It was DW 1 testimony that the permit is issued by City Director and
that such permit is only issued where the preconditions are met. There was
permit to extract the fill materials in the disputed land. DW 1 stated that
she did not participate in the issuance of the permit and that she does not
recall the date of the issuance of permit. DW 1 noted to have not tendered
the permit attached to the WSD and reiterated her willingness to tender
the same. At that juncture, a document entitled: Yah: Kibali cha Kuchimba
Kifusi kwa ajili ya kusawazisha Eneo lenye Leseni Namba BL/027/DOM
iliyopo Kata ya Dodoma Makulu Mtaa wa Msangalale Mashariki” dated
23/11/2023 was admitted and marked as Exhibit DE 1 .
It was added that the pre-conditions were to be complied with prior
to issuance of the permit. DW 1 stated that the Plaintiff did not comply
with the terms and conditions of the permit but EIA requirement in respect
of the project in disputed land was not part of the WSD.
29 | P a g e
Further, DW 1 noted that Exhibit PE 3 was the letter that stopped the
operation at the site and reasons for the stoppage was absence of the EIA
which was not stated in Exhibit PE 3. It was added by DW 1 that stoppage
was done as a result of existence of environmental degradation/ pollution.
DW 1 noted that parties did not meet to resolve the matter.
According to DW 1, there was a process of consultations before the
permit was issued and that environmental degradation resulted from
drilling using excavators not levelling. It was true that there were fees
collected from that area by the Dodoma City Council and reiterated that
rubble extraction is only done after the EIA has been done. DW 3 stated
that existence of excavators in the land where rubbles/fill extractions was
being done meant that it was not levelling but drilling. DW 1 admitted that
she had nothing of documentary nature to show that there was
environmental degradation in documentary evidence nature.
It was reiterated that Exhibit PE 3 which was stoppage letter stated
that cause of cancellation/stoppage was environmental degradation and
30 | P a g e
that there was drilling of the land in question and not levelling. Levelling is
only extraction of the upper part of the soil but drilling involved excavating
the holes downwards to certain depth. According to DW 1, what the
Plaintiff was doing was not levelling but excavating deeply in the land.
DW 1 stated that she was not aware that cancellation of the permit
had impact to the Plaintiff, noted the lamentation in Exhibit PE 4 from the
Mining Commission to Dodoma City Council on failure to consult the Mining
Commission. DW 1 stated that it was correct that Dodoma City Council has
no claims against the Plaintiff in this case, and that a letter dated
03/11/2023 with conditions in Exhibit PE 1 was issued before the permit.
The permit was issued on 23/11/ 2023. The issuance of permit would allow
activities planned to take place.
In re-examination, DW 1 reiterated that WSD at paragraph 2 reveals
that EIA was there though words used are not explicit and that conditions
in the Exhibit PE 3 are reflecting the need for EIA. DW 1 added that she
was aware that Plaintiff was found drilling and not levelling the land as per
31 | P a g e
permit. As per DW 1, conditions are prerequisite for permit to be issued
and in case after the permit is granted, it is discovered that the conditions
were not met then permit is stopped or suspended/cancelled immediately.
That was totality of the evidence on record.
Also, it is on record that the learned counsel for the Plaintiff complied
with the court order to file final written submission, if any, by the parties as
per the order dated 22 April 2026.
Having heard the parties, this court is duty bound to determine the
validity of the claim or otherwise. In attempt to address the matter, a
serious perusal of the pleadings, evidence on record, final written
submissions and applicable legal principles both statutory and case laws
were consulted and reviewed to address the issues of this case. However,
by virtue of the principle that pleadings and written submissions are not
evidence as encompassed in Ibrahim Abdallah vs Selemani Hamisi
(Civil Appeal 314 of 2020) [2022] TZCA 43 (21 February 2022) (TANZLII),
32 | P a g e
at page 11, this court shall not reproduce the written submissions in this
judgment.
At the outset, it is of paramountcy to state the general position with
regard to proof of civil cases. Both the statutory law, namely sections 3(2)
(b), 117 and 118 of the Evidence Act, Cap 6 R.E. 2023, and case law
provide to the effect that proof in civil cases is on balance on probabilities
and the burden lies on the party who claims to establish the existence of
facts so alleged.
For instance, in the case of Sure Freight Tanzania Ltd vs XCMG
Tanzania Ltd (Civil Appeal No.101 of 2020) [2023] TZCA 17286 (31 May
2023) (TANZLII), at pages 13-15, the Court reiterated at lengthy that:
The third cherished principle of law is that, generally, in
civil proceedings, the burden of proof lies on the party who
alleges anything in his favour. We are fortified in this view
by the provisions of sections 110 and 111 of the Tanzania
Evidence Act, [Cap 6 R.E. 2002] (the Evidence Act). It is
also common knowledge that in civil proceedings, the
party with legal burden also bears the evidential burden
33 | P a g e
and the standard in each case is on the balance of
probabilities. See, for example Godfrey Sayi v. Anna
Siame as Legal Personal Representative of the late
Marry Mndolwa , Civil Appeal No. 114 of 2012
(unreported). This is also provided for under section 3 (2)
(b) of the Evidence Act. It means that, the court will
sustain such evidence which is more credible than
the other on a particular fact to be proved. There is a
litany of authorities in this aspect and one case which
stands out and which this Court has always sought
inspiration is the statement by Lord Denning in Miller v.
Minister of Pensions [1937] 2 All. ER 372 in which he
states that: "If at the end of the case the evidence turns
the scale definitely one way or the other, the tribunal must
decide accordingly but if the evidence is so evenly
balanced that the tribunal is unable to come to a
determinate conclusion one way or the other, then the
man must be given the benefit of the doubt This means
that the case must be decided in favour of the man unless
the evidence against him reaches the same degree of
cogency as is required to discharge a burden in civil case.
That degree is well settled. It must carry a reasonable
degree of probability, but not so high as required in
criminal case. If the evidence is such that the tribunal can
34 | P a g e
say- We think it is more probable than not, the burden is
discharged, but, if the probabilities are equal, it is not..."
It is again elementary law that the burden of proof
never shifts to the adverse party until the party on
whom onus lies discharges his burden and that the
burden of proof is not diluted on account of the
weakness of the opposite party's case. We seek
inspiration from the extract in Sarkar's Laws of
Evidence, 18th Edition M.C. Sarkar, S.C. Sarkar and
P.C. Sarkar , published by Lexis Nexis and our previous
decision in Paulina Samson Ndawavya v. Theresia
Thomasi Madaha , Civil Appeal No. 45 of 2017
(unreported): "...the burden of proving a fact rest on the
party who substantially asserts the affirmative of the issue
and not upon the party who denies it; for negative is
usually incapable of proof. It is ancient rule founded on
consideration of good sense and should not be departed
from without strong reason... Until such burden is
discharged the other party is not required to be
called upon to prove his case. The Court has to
examine as to whether the person upon whom the
burden lies has been able to discharge his burden.
Until he arrives at such a conclusion, he cannot
35 | P a g e
proceed on the basis of weakness of the other
party... "[Emphasis added].
Simply summed up the legal position reveals that: One, the burden of
proof lies on the party who institutes a case in a court of law. Two, the
standard of proof is on balance of probabilities whereby the court shall
uphold evidence that is more credible than the other. Three, the
weaknesses of the opposite party do not form basis of proof of the
claimant’s case. In other words, failure of the defendant/respondent to
defend its case cannot be the basis of the court entering judgment in
favour of the Plaintiff/applicant unless the latter had managed to
sufficiently prove the case to the required standard.
The first issue is whether the re was interference with the Plaintiff’s
business of extracting fill matters (kifusi) and levelling his land. This aspect
is not hard to determine. The evidence of the Plaintiff and Defendant
reveal that: One, the Plaintiff was granted permission to extract the fill
materials (rubble) at Dodoma Makulu Ward. This was supported by
Exhibit DE 1 which was the permit titled: Yah: Kibali cha Kuchimba Kifusi
36 | P a g e
kwa ajili ya kusawazisha Eneo lenye Leseni Namba BL/027/DOM iliyopo
Kata ya Dodoma Makulu Mtaa wa Msangalale Mashariki ” dated 23/11/20 23.
Two, the Plaintiff commenced operating the activities on the suit land.
Among other conditions, the permit allowed the Plaintiff to collect sand for
period of three months subject to renewal upon compliance with terms and
conditions contained therein Three, after sometimes (some days of
operations), the activities were stopped by the 1
st
Defendant. Exhibit PE 3
which was a letter dated 8th December 2023 from Dodoma City Council to
Alexander Ruttakinikwa John entitled: Kusitisha Kibali cha Kuchimba Kifusi
cha tarehe 23/11/ 2023 kwenye eneo lenye leseni Na. BL/ 027/DOM iliyopo
Kata ya Dodoma Makulu Mtaa wa Msangalale Mashariki was illustrative of
the stoppage of activities on the Plaintiff’s site.
Totality of the Plaintiff’s evidence is revealing that the activities of the
Plaintiff to extract fill materials was in operation for few days of
commencement but later on stopped. Similarly, testimony of Defendant ’ s
witness is not disputing the fact that there was stoppage of activities in the
Plaintiff’s land, it is lucid that such stoppage by the 1
st
Defendant interfered
37 | P a g e
with the Plaintiff’s business of extraction of fill materials (rubble). Thus, the
first issue is answered in the affirmative.
With regard to the second issue, namely whether the 1
st
Defendant
had justifiable reasons to cancel the permit to extract fill matters(kifusi)
issued to the Plaintiff, the parties are at cross-roads. Each party shares a
different view altogether on this aspect.
The basis of the Plaintiff’s assertion that there were no justifiable
reasons are premised on three aspects: one, that Plaintiff had done
Environmental Protection Plan (EPP) prior to issuance of the permit to
extract fill materials. Two, the Plaintiff obtained the permit from the 1
st
Defendant. Three, the cancellation was done without involving the Mining
Commission. Four, there was no environmental degradation or pollution on
the site. That was totality of the evidence of the Plaintiff on record in
particular from PW 1 and PW 5.
Conversely, DW 1 reiterated that there was found environmental
degradation/ pollution on the Plaintiff’s site. One, the Plaintiff had violated
38 | P a g e
the terms and conditions of the permit by drilling the land instead of
levelling. Two, there was no EIA in place to allow the drilling as such
activity would require to conduct EIA study prior to the issuance of the
permit. That was essentially the totality of DW 1 testimony.
To underscore if there were justifiable reasons for the stoppage of
the extraction of the fill materials, it is pertinent to revisit the evidence on
record both oral and documentary in particular the documentary evidence.
Exhibit PE 3 and Exhibit DE 1.
Exhibit DE 1 had the following conditions related to the
environmental issues among other conditions, in Clause 3 of the Permit
namely:
(iii) Halmshauri italazimika kufanya ukaguzi wa
kimazingira mara kwa mara katika eneo la mradi
wako.
(vi) Shughuli za uvunaji zifanyike kwa kuzingatia mpango
wa ulinzi wa Mazingira uliopo katika Taarifa yako ya
Tathmini ya Athari kwa Mazingira (EIA)
39 | P a g e
(ix) Utalazimika kutunza na kuhifadhi eneo unalovuna
kifusi, Aidha hakikisha malori ya kusomba kifusi hayaharibu
Mashamba ya Wakulima ili kuepusha migogoro inayoweza
kujitokeza.
(xi) Utalazimika kuandaa taarifa ya utekelezaji wa
mpango uliopo katika Tathmini ya Athari kwa
Mazingira unaonyesha namna ya kudhibiti Uharibifu
wa Mazingira unaotokana na mradi wako.
Iwapo itabainika kukiuka masharti haya /kuchukua
madini eneo jingine lolote nje ya leseni yako, Kibali hiki
kitafutwa mara moja na kupigwa faini isiyopungua Tsh
300,000/= papo hapo.
Generally, conditions reveal that: One , the 1
st
Defendant was obliged
to visit site, inspect and audit the activities undertaken by the Plaintiff.
Two , the Plaintiff was obliged to strictly adhere to Environmental
Protection Plan (EPP) as per Environmental Impact Assessment (EIA)
Report. Three , the Plaintiff was duty bound to ensure protection and
conservation of the land where the fill materials were extracted including
ensuring degradation was not happening. Four, the Plaintiff was required
mandatorily to prepare the implementation report of the EPP indicating
40 | P a g e
methods of controlling the degradation or pollution in the project area.
Five, failure to comply (no compliance) to the terms and conditions stated
attracted immediate cancelation of the permit in question.
Essentially, determination on stoppage of the activities in the
Plaintiff’s project site was justifiable or otherwise depends on the
compliance to the conditions stated out in Permit forming Exhibit DE 1 .
Critical perusal of the evidence on record reveals that there is no serious
evidence on record indicating that the Plaintiff complied with these
conditions of the permit to warrant conclusion that the stoppage of the
activities by 1
st
Defendant in the Plaintiff’s project was unjustifia bly. It is
this court’s settled view that stoppage was justified and reasons were
categorically enumerated in the letter that communicated the
cancellation/revocation of the permit. This court is not oblivious of
testimony of PW 1 whose evidence might have bearing to the aspects in
question. This court shall revert to this evidence later.
In respect of Exhibit PE 3 dated 08/12/2023, partly reads as follows:
41 | P a g e
YAH; KUSITISHA KIBALI CHA KUCHIMBA KIFUSI
CHA TAREHE 23/11/2023 KWENYE ENEO LA
LESENI NAMBA BL/027/DOM ILIYOPO KATA YA
DODOMA MAKULU MTAA WA MSANGALALE
MASHARIKI
Tafadhali rejea kichwa cha habari tajwa hapo juu.
Ofisi ya Mkurugenzi wa Jiji ilipokea barua yako ya tarehe
24/10/2023 isiyo na kumbukumbu yenye kichwa cha
habari tajwa hapo juu.
Mkurugenzi wa Jiji anasitisha Kibali cha kuvuna
kifusi baada ya ukaguzi uliofanywa na Mkuu wa
Idara ya Uendelezaji Makao Makuu na kubaini
u haribifu wa Mazingira katika eneo hilo.
Mara upatapo barua hii unatakiwa kusitisha shughuli ya
uvunaji wa kifusi katika eneo hilo, endapo ukiendelea na
shughuli za uvunaji wa kifusi hatua kali za kisheria
zitachukuliwa dhidi yako.
42 | P a g e
It is lucid that reason for the stoppage/cancellation of the permit
was stated categorically in the letter dated 8 December 2023. Such reason
was existence of environmental degradation/ pollution at the project site
following site visit, inspection and audit by the Dodoma City Council
officers.
In fact, this evidence is in consonance with the oral testimony of DW
1 that there was a visit to the site by relevant officers from the 1
st
Defendant who found that there was environmental degradation/pollution
caused by activities undertaken by the Plaintiff. Similarly, PW 3 stated
among others, that there were dusts arising from the Plaintiff’s site
activities that was later on addressed by bring water boozer to minimize
impacts of the dusts to the residents.
It is certain that contents of Exhibit PE 3 reveal that 1
st
Defendant
acted well within the boundaries of the law in accordance with conditions
set out in the permit, Exhibit DE 1. Indeed, Exhibit DE 1 had two aspects
related to the 1
st
Defendant namely duty to visit site, inspect and audit on
compliance to conditions of the permit and take actions including
43 | P a g e
cancellation or suspension where there is non-compliance to the conditions
of the permit. As per evidence on record, the 1
st
Defendant acted within
the parameters set out in the permit thus was justified to act in the
manner demonstrated in Exhibit PE 3 as stoppage/cancellation arose out of
site visit and inspection at the site.
It is on record that Plaintiff’s counsel basis in support of the Plaintiff’s
entitlement to the judgment and decree of the court is based on
misconceptions. The learned counsel’s emphasis on the Plaintiff possession
of lawful approvals from both the Mining Commission and Dodoma City
Council, the permit being issued only after fulfilment of mandatory
preconditions, inspections and consultations; Dodoma City Council itself
participated in and approved the process prior to commencement of the
project, the allegations of non-compliance were not pleaded in the Written
Statement of Defence; and absence of technical or scientific evidence
supporting the allegations of environmental degradation do not in any
manner support the Plaintiff’s case.
44 | P a g e
The only tangible proof of the Plaintiff’s case would depend on
project post commencement date not pre-commencement. The permit had
conditions which needed to be complied with. That was the basis of the
stoppage of the activities/ cancellation of the permit.
Unfortunately, there is no evidence from the Plaintiff to rebut the 1
st
Defendant’s evidence on this aspect that there was environmental
degradation . There was no rebuttal from any of the Plaintiff’s witness that
no visit and inspection was done at the Plaintiff’s site prior to cancellation
of the permit/ stoppage of the activities in the project site. Also, there is no
evidence that Plaintiff complied to the terms set out in the permit. Plaintiff
ought to have produced a report from environmental expert post
commencement of the activities on the site revealing actions taken to
ensure environmental protection and conservation was done in light of the
contents of EPP, Exhibit PE 1 . The permit , Exhibit DE 1 was issued after
the EPP was submitted to the 1
st
Defendant, Dodoma City Council. EPP
which was Exhibit PE 1 is not the envisaged report stated in Exhibit DE
1 as the Plaintiff ought to have prepared a report evidencing that in
45 | P a g e
undertaking the extraction of fill materials no environmental pollution or
degradation occurred at all. That would have assisted this court to
ascertain that contents of Exhibit PE 3 were incorrect or otherwise. At
this juncture, it is with clear and informed view, this court finds that the 1
st
Defendant was justified with valid reasons to cancel/stop the undertaking
of the activities to extract fill materials at Plaintiff’s site as there was
environmental pollution/degradation on that site arising out of such
activities. The second issue is answered in the affirmative in favour of the
Defendants.
The third issue is what reliefs are parties entitled to, which essentially
entails two main aspects: proof of the case to the required standard of
balance of probabilities and remedies available to parties thereto.
On burden and standard of proof in civil cases, it is established law
that the burden lies on the person who alleges and standard is on balance
of probabilities as per the provisions of Section 3(2)(b), 117 and 118 of the
Evidence Act, Cap 6 R.E. 2023.
46 | P a g e
In Anitha Muhidini Mboya vs Joseph Nemes Makoi & Others
(Civil Appeal No. 117 of 2021) [2026] TZCA 392 (10 April 2026) (TANZLII),
at pages 17-18, the Court reiterated that:
The burden to prove forgery could not be shifted to the
2nd respondent by the appellant. Since the allegation of
forgery was raised/pleaded by the appellant, it was
incumbent, in terms of section 110(1) and (2) of the
Evidence Act, upon her to prove so evidentially. On the
subject, we recall, for the benefit of the parties, that in the
case of Paulina samson Ndawavya vs Theresia
Thomas Madaha, Civil Appeal No. 45 of 2017
(unreported), the Court reproduced the passage from
Sarkar’s Laws of Evidence, 18th Edition M.C. Sarkar,
S.C. Sarkar and P. C. Sarkar, published by Lexis
Nexis as below: - “...the burden of proving a fact rests on
the party who substantially asserts the affirmative of the
issue and not upon the party who denies it; for negative is
usually incapable of proof. It is ancient rule founded on
consideration of good sense and should not be departed
from without strong reason...Until such burden is
discharged the other party is not required to be called
upon to prove his case. The Court has to examine as to
whether the person upon whom the burden lies has been
47 | P a g e
able to discharge his burden. Until he arrives at such a
conclusion he cannot proceed on the basis of weakness of
the other party... "(At page 1896).
It is unfortunate, the record bears out, that the appellant
did not discharge her legal duty to prove her assertion of
forgery. Instead, she appears to even blame the trial court
for not taking the initiative to engage handwriting experts.
This view is definitely misplaced as the court, being a
fountain of justice, cannot step into the shoes of either
party in the case and assist it avail the court with material
evidence either proving or disproving any allegation of
fact.
Having perused the evidence on record thoroughly, this court is
inclined to find out that the Plaintiff failed to discharge the solemn duty to
prove the case to the required standard. This is addressed on five main
components: failure to take bonafide steps, the status of the EPP in respect
of the matter in question, effect of the letter from Mining Commission,
variance between pleadings and evidence on days of operation of the
project and failure to establish damages.
48 | P a g e
In respect of failure to take any bona fide steps, it is humble and
considered opinion of this court that defendant did not take any tangible
steps to attempt to address the matter in a bona fide manner. The
importance of section 13 of the Civil Procedure Code, Cap 33 R.E. 2023 is
illustrative on the matter. It caters for the bona fide steps by the parties in
resolution of the dispute. The provision states explicitly that:
13 (1) For purposes of this Act, a person shall be deemed
to have taken bona fide steps to resolve a dispute if the
steps taken by the person in relation to the dispute
constitute a sincere and genuine attempt to resolve the
dispute out of court, having regard to the person’s
circumstances and the nature and circumstances of the
dispute.
(2) For purposes of this Act, the following steps may be
taken by a person as part of bona fide steps to resolve a
dispute with another person:
(a) notifying the other person of the issues that are, or
may be, in dispute, and offering to discuss them with a
view to resolving the dispute;
(b) responding appropriately to any notification referred to
under paragraph (a);
49 | P a g e
(c) providing relevant information and documents to the
other person to enable the other person to understand the
issues involved and how the dispute may be resolved;
(d) considering whether the dispute could be resolved by a
process other than a court action, including reconciliation,
negotiation, mediation, arbitration, warning, diversion, as
applicable;
(e) if a process referred under paragraph (d) is agreed to
(i) agreeing on a particular person to facilitate the process,
where feasible; and (ii) attending the process;
(f) if a process agreed under paragraph(e) is conducted
but does not result in resolution of the dispute, considering
a different process; or
(g) attempting to reconcile or negotiate with the other
person or otherwise engage in independent evaluation,
with a view to resolving some or all the issues in dispute,
or authorising a representative to do so, before escalating
the matter to mediation or arbitration.
(3) For avoidance of doubt, the provisions of subsection
(1) shall not limit the steps that may constitute taking
bona fide steps to resolve a dispute.
(4) The provisions of this section shall apply to all
proceedings intended to be initiated in court.
50 | P a g e
In the case of Beka Trading Company Limited and Another vs
Tanzania Electrical Mechanical and Electronics Service Agency and
Another (Civil Case No. 10631 of 2025) [2025] TZHC 7247 (26 November
2025) (TANZLII), this Court (Hon Mwakapeje, J.), at pages observed that:
I am obligated at the outset to state that Section 13 of the
Civil Procedure Code, Cap. 33 R.E. 2023 is the statutory
gateway for pre-action conduct intended to encourage
resolution of disputes outside court and to regulate which
matters are fit for immediate litigation. In Frode
Farestveit vs Mrisho Kinega Mrisho (supra) , this
Court in interpreting the said section, observed that:
“Section 13 thus operates as the procedural vehicle for
realising that constitutional obligation by placing an initial
duty on litigants to attempt settlement before invoking
judicial intervention. Subsection (1) of section 13
establishes the standard of "bona fide steps," requiring
that any pre-litigation engagement be sincere, substantive,
and meaningfully directed at resolving the dispute.
Subsection (2) provides a non-exhaustive continuum of
actions that may constitute compliance, including giving
notice of potential issues, inviting dialogue, exchanging
information and documents, considering ADR options,
51 | P a g e
participating in agreed dispute-resolution processes, and
exploring alternative mechanisms if initial attempts fail.
Subsection (3) reinforces the obligation's flexible yet
compulsory nature by clarifying that the listed steps are
not exhaustive. The mandatory character of the provision
culminates in subsection (4), which unequivocally states
that the section applies to all proceedings intended to be
initiated in court. The statutory language leaves no room
for discretion. Section 13, therefore, serves as a
jurisdictional gateway, not merely a procedural ideal."
Therefore, by its terms and when read together, section 13
establishes both a substantive objective (a bona fide
attempt) and procedural obligations (disclosure/pleading of
the steps taken) which are applied to all intended
proceedings to be filed in court. The statutory text thus
combines a mandatory thrust, that proceedings must be
informed by bona fide pre-action conduct, with a measure
of flexibility as to the forms that conduct may take. The
Civil Procedure Code, as enacted, confirms section 13's
place within the procedural code governing competence
and the conduct of civil litigation.
52 | P a g e
The Plaintiff’s evidence provides to the effect that upon receipt of
letter forming Exhibit PE 3 which estopped the Plaintiff from the activities
as a result of environmental degradation/pollution, Plaintiff never visited
the 1
st
Defendant’s office nor consulted the 1
st
Defendant for clarifications
or the modality of addressing the anomalies identified for continuance of
the levelling activities. According to PW 5, he waited for the 1
st
Defendant
to initiate the meetings. In addition, the communication by 1
st
Defendant to
various institutions relating to the suspension/cancellation of the permit
resulted into issuance of the letter of complaint by the Mining Commission
forming Exhibit PE 5 . It is not Plaintiff who complained to the Mining
Commission about the suspension rather a communication by the 1
st
Defendant.
Given the Plaintiff’s inaction in relationship to taking initiatives to
understand the magnitude of the anomalies that led to stoppage of the
activities in his project and modalities of ameliorating them by visiting,
discussing and coming to terms with 1
st
Defendant, he rushed to court for
litigation. This was a prematurely preferred litigation on account that if the
53 | P a g e
Plaintiff would have taken bonafide steps to resolve the matter with 1
st
Defendant by addressing all the environment degradation/pollution
anomalies nothing would have prevented furtherance of his land levelling
activities.
Second limb is on the status of the EPP Report which formed Exhibit
PE 1. It was evidence on record particularly PW 1 and PW 5 that Plaintiff
engaged one Eladi Focus Tarimo to conduct the Environmental Protection
Plan. The evidence of PW 1 is expert evidence.
The role of expert evidence is persuasive and advisory in nature. In
Anitha Muhidin Mboya (Supra), at pages 11-12, the Court held that:
Apart from some of them being of a persuasive nature,
others, read closely, are advisory by nature to the trial
Judges. In neither of them, the Court explicitly stated that
in the absence of an expert opinion, the findings made by
a trial judge after invoking the provisions of section 75(1)
of the Evidence would be ineffective.
Instead, the expert opinions were taken to be of assistance
to the trial Judge. A clear example is that in the case of S
54 | P a g e
vs Palirama (supra) where the court treated it as the
"prudent course to obtain the handwriting expert opinion
and assistance of an expert" In Khalife Mohamed vs
Aziz Khalife and Another (supra) , the Court was just
considering the credibility of an expert (CW1) who had
testified, hence whether or not to call an expert was not
an issue before it. While we acknowledge the caution to
the courts in the case of Abinger Ltd vs Aston (supra ),
that decision has only a persuasive affect in our jurisdiction
as the law on expert opinion is well settled that courts are
not bound by expert opinions, but where there is one, a
departure from it require reasons be stated (see a
persuasive decision in Saidi Mwamwindi vs R [1972]
HCD n. 212 cited by the Court with approval in the
unreported case of Marwa Chacha Gekondo vs The
Republic, Criminal Appeal No. 463 of 2020).
There are four quick observations on evidence of the so-called
environmental expert. First , PW 1 is not registered Environmental Experts
as per the requirements of the Environment Management Act, Cap 191
R.E.2023 and its regulations. This was oral evidence of PW 1 himself. Also,
Exhibit PE 1 reveals that Salvatory John was the registered Environmental
55 | P a g e
Expert who prepared the EPP Report. Second , the registered
environmental expert never appeared before the court to testify on
contents of Exhibit PE 1. Third, there was nothing on record in terms of
documentary evidence to establish that PW 1 had special knowledge,
expertise, experience or training to conduct EPP which are prerequisite
requirements for expert opinions. Fourth , there is nothing on record to
show that actually either of the two Salvatory John or Eladi Focus Tarimo
was engaged to conduct the study leading to EPP report. Neither
engagement letter nor contract was tendered before this court to vindicate
that actually PW 1 or the alleged registered Environmental Expert (EIA
Expert) was engaged to prepare the EPP and supervise implementation of
alleged project. None exists on record.
On account of these weaknesses, this court finds that evidence of PW
1 including Exhibit PE 1 lacks credibility to be relied upon by this court to
validate existence of compliance with environmental related aspects by the
said project.
56 | P a g e
Further, this Court is mindful of the provision of section 108 of the
Evidence Act, Cap 6 R.E. 2023 prevents oral evidence to contradict, vary,
substitute or add terms contained in written evidence. The Contents of
Exhibit PE 1 , is explicitly that the study on environmental issues at the
project site leading EPP Report, Exhibit PE 1 was prepared by Salvatory S.
John, Reg. No NEMC/EIA.0498. Also, the Environmental Experts’
Certificates issued on 20 May 2016 and 19 May 2017 are in the name of
Salvatory S. John. Further, Practising Certificate dated 28 February 2022
with Reference No. NEMC/PC/EIA/2021/0076 as well as that of 2021 are
both in the name of Salvatory Silvest John, and the Taxpayer Identification
Number (TIN) from Tanzania Revenue Authority (TRA) dated 16 October
2018 is in the name of Salvatory John Tarimo.
Simply, totality of Exhibit PE 1 has nothing to do with PW 1 who is
alleged to have conducted the environmental study and prepared the EPP
Report. As such both oral evidence of PW 1 and PW 5 as that there was
compliance to environmental issues on the project site ought to be
discarded. This was a legal position in the case of Nuru Finance &
57 | P a g e
Business Services Co. Ltd vs Benjamin Adamson Masuba (Civil
Appeal No. 284 of 2020) [2024] TZCA 169 (8 March 2024) (TANZLII), at
page 15, the Court of Appeal of Tanzania guided that:
Once it is shown as in this case that the contract was
reduced into writing, then in terms of S. 101 of the
Evidence Act, a party to such contract is not permitted to
adduce oral evidence for the purpose of contradicting,
varying, adding or subtracting from its terms … In view of
the foregoing, the respondent is barred from
adducing oral evidence for the purpose of varying
the written contract. The respondent tendered
exhibit P1 and it is binding upon him and the
appellant. We find no false representation which
prejudiced the respondent.
As both PW 1 and PW 5 stated that it was one Eladi Focus Tarimo
(PW1) who was engaged, conducted the environmental study on the
project and prepared the EPP Report which is Exhibit PE 1 , while the
contents of Exhibit PE 1 reveal otherwise, the whole oral evidence of those
two witnesses relating to the matter in question is of no evidential value.
This is attributed also to the fact that no evidence as to terms of
58 | P a g e
agreement for undertaking such activities was tendered or stated before
the court.
The remaining evidence on record from PW 2, PW 3 and PW 4 on
question of environmental compliance miserably fails to establish such
compliance to sustainable environmental management as none of them
claimed any expertise in such field.
Third limb is on the effect of the letter from Mining Commission. It is
on evidence that PW 5 that his claim is supported by a letter from the
Mining Commission that non-consultation by Dodoma City Council prior to
suspension of the permit was improper and might have impaired the right
of the Plaintiff.
Having perused contents of Exhibit PE 4 , this court notes that
following matters, namely: One, the letter arose out of communication that
1
st
Defendant copied to the Mining Commission among other institution on
the reasons for cancellation/suspension of the permit to extract fill
materials by the Plaintiff. Two, the Plaintiff never complained to the Mining
59 | P a g e
Commission on suspension/cancellation of permit, Exhibit PE 3 . Three,
contents of Exhibit PE 4 represent Mining Commission’s personal opinion
on the suspension/cancellation without any tangible basis in terms of how
it arrived at that conclusion. As result, Exhibit PE 4 cannot in any legal
sense be a basis of the Plaintiff’s claim. It does not state what loss, if any,
has the Plaintiff suffered as a result of the suspension/cancellation of the
permit.
The fourth limb, is on variance between pleadings and evidence. It is
settled that evidence tendered in court should be in consonance with
pleadings such evidence intended to support. In case there are variance,
then such evidence should be disregarded and the pleadings considered to
have not been proved.
In the instant suit, there are two pertinent issues pleaded but the
evidence on record is contrary to pleadings. One, the Plaintiff in Clause 4
stated that 1
st
Defendant did a cancellation of the licence in relation to the
project in question. In evidence, both oral and documentary testimonies
60 | P a g e
revealed that what was suspended/ cancelled was not a licence but a
permit. This is as per Exhibit PE 3 which states categorically that Dodoma
City Council suspended/cancelled the permit to extract fill materials. The
Plaintiff Licence issued by the Mining Commission was never touched.
Two, there is significant variance on days of operation at the project
site. The Plaint in Clause 7 states that within three days of operation at the
project site the 1
st
Defendant stopped the activities. The oral testimonies of
PW 1, PW 2 and PW 3 supports three days’ version. PW 5, the owner of
the alleged project states the same to be within five days of operation.
Exhibit PE 3 and Exhibit DE 1 reveal more days than three or five days. As
the permit was issued on 23/11/2023 and the suspension/cancellation was
done on 08/12/2026, the number of days of operation of the same exceeds
three days pleaded in the Plaint. The fact that the Plaintiff, who is the
owner of the project, testified that it was five days of operation in the
project site when the activities were stopped, then such material evidence
is in variance with pleadings.
61 | P a g e
The principle on parties being bound by pleadings and treatment of
variance between pleadings and evidence to lead to failure to prove the
case was reiterated in the case of John Bunini vs Charles M. Mbusiro
(Civil Appeal No. 576 of 2022) [2025] TZCA 350 (11 April 2025) (TANZLII),
at page
With regard to the variance between the appellant's
pleading and the evidence led in support of his claim, there
is a myriad of case law and it is indeed very elementary to
observe that, in any legal proceedings, parties are
generally bound by the facts and claims they present in
their pleadings. This means that, in the absence of
amendments, parties to a civil suit cannot present a case
that contradicts or goes beyond what, they have stated in
their pleadings. The rationale behind this principle is not
far-tetched. It is to ensure and maintain a fair and orderly
trial process by preventing the parties from changing their
case in the course of trial and ensuring that the court
focuses on the issues arising from the pleadings … With due
respect to the appellant, this was an unauthorised
departure from the facts which he had pleaded. It must be
very elementary to say that, if a party attempts to present
a case that departs significantly from their pleadings
62 | P a g e
without seeking amendment as it happened in this case,
the court may refuse to consider the new evidence or
arguments and that is what the learned High Court Judge
did.
The fifth and last limb is on failure to establish damages by the
Plaintiff has seriously impaired the Plaintiff’s case. Among others, the
Plaintiff sought this court to grant orders on specific damages and general
damages. Those damages ought to have been proved by evidence.
In respect of the specific damages, the Plaint in Paragraph 4 and in
the Orders sought reveals that Plaintiff claims for loss of business and loss
of investment to the tune of not less than Tanzania Shillings One Million
per day from 8th December, 2023 until the date of Judgment being loss of
business income from sale of fill material (kifusi) extracted from the
Plaintiff’s property.
That forms partially one side of the coin that specific damages should
be specifically pleaded. However, it fell short of the legal requirements on
two main aspects. Apart from prayers, there is nowhere such amount of
63 | P a g e
TZS 1,000,000/= was pleaded categorically on how the same was arrived
at. Second, no evidence at all was tendered to support the claim.
The guidance on specific damages was reiterated in the case of
Reliance Insurance Co. T. Ltd & Others vs Festo Mgomapayo (Civil
Appeal No. 23 of 2019) [2019] TZCA 323 (2 October 2019) (TANZLII), at
page 19, where the Court held that:
The law in specific damages is settled, the said
damages must be specifically pleaded and strictly
proved , but this is not the case in the current appeal.
Much as we appreciate that, the respondent's vehicle was
damaged during the said accident as expounded above,
the evidence on record falls short of materials to form the
basis of awarding specific damages.
The evidence on record from all witnesses have not mentioned any
single cent to have spent or incurred as loss of business or investment.
Neither of the Plaintiff’s witnesses stated any amount be incurred as loss. It
was expected that Plaintiff would rally evidence on the costs of conducting
EIA/ EPP Study, costs of holding alleged meetings at the Ward and Mtaa
64 | P a g e
level, costs of allegedly hire excavators, agreements of sale of fill materials
that Plaintiff allegedly entered into, or income that was being generated in
a day during the days of operation of the alleged business/investment.
None of those aspects was either orally stated or proved by
documentary evidence. Thus, the question of specific damages was strictly
speaking never proved by an iota of evidence on record.
The meaning and scope of specific damages were analysed in the
case of SANLAM General Insurance Tanzania Ltd vs Dennis Charles
& Another (Civil Appeal No. 51 of 2021) [2024] TZCA 105 (23 February
2024) (TANZLII) at pages 22-24, where the Court of Appeal stated that:
So far as special damages are concerned, the
jurisprudence instructs that such compensation must
specifically pleaded and strictly proven, In Stanbic Bank
Tanzania Limited (supra) , the Court, reproduced with
approval, the following definition of special damages by
Lord McNaughten in Stroms Bruks Aktie Bolag &
Others v. J & P Hutchison [1950] AC 515 at 525:
“Special damages ... are such as the law will not infer from
the nature of the act. They do not follow in the ordinary
65 | P a g e
course. They are exceptional in their character, and
therefore, they must be claimed specially and proved
strictly.” If such a claim is sufficiently particularised or
detailed in the plaint , it must then be proved strictly
especially by presenting documentary proof, such
as receipts of payments made to substantiate loss
or economic injury sustained . To compare the
incidents of special damages and general damages, we
wish to extract, with approval, a passage from the Kenyan
decision in Joseph Kipkorir Rono v. Kenya Breweries
Limited & Another Kericho HCCA No. 45 of 2003, in
which Kimaru, J. aptly held that: " In current usage,
special damage or special damages relate to part
pecuniary loss calculable at the date of the trial ,
whilst general damages relate to all other items of damage
whether pecuniary or non-pecuniary. If damages are
special damages they must be specifically pleaded and
proved as required by law. For a loss to be calculable at
the date of trial it must be a sum that has actually been
spent or loss that has already been incurred...Special
damages and general damages are used in corresponding
senses. Thus, in personal injury claims, 'special damages'
refers to past expenses and lost earnings, whilst ‘general
damages’ will include anticipated loss as well as damages
66 | P a g e
for pain and suffering and loss of amenities.... Special
damage is in the nature of past pecuniary losses or
expenses while general damage is futuristic pecuniary loss
or expenses. "
As the evidence on record is completely silent on existence of any
costs incurred or income realised by the Plaintiff prior to the date of
cancellation or suspension of the activities at the site, there was no proof
of specific damages at all in the circumstances of the case.
On general damages, this court is confined to find out that the same
was not established owing to the fact that suspension/cancellation was
rightly done for valid reasons and in accordance with terms and conditions
of the permit that allowed the Plaintiff to undertake activities in the site in
question.
In the case of Reliance Insurance Co. T. Ltd (Supra) , at page
20, the Court of Appeal stated that:
67 | P a g e
The position of the law in regard to an award of general
damages is settled. There is a number of authorities
stating that general damages are normally awarded at the
courts discretion and need not to be specifically proved.
Also, this court in the case of Lello Laurent Sawe vs National
Microfinance Bank PLC and Reliance Insurance Company
(Tanzania) Limited, at pages 57-58, held that:
Exercising the discretion of the court in granting general
damages should be done judiciously. It was expected that
the Plaintiff would demonstrated kind of suffering that
resulted from the destruction of the goods part of the
business. Without indicating in evidence any possibilities of
suffering whether mental, psychological or physical made
the exercise of the discretion of the court on general
damages unfounded.
There is no tangible evidence on record to vindicate that Plaintiff in
this suit suffered any loss at all. There in neither evidence of any costs
being incurred nor mental or any other suffering being suffered by the
Plaint. Given the 1
st
Defendant’s actions were well justifiable in compliance
68 | P a g e
to terms and condition of the permit issued to the Plaintiff, the Plaintiff
cannot be heard claiming to have suffered any loss in circumstances as it is
demonstrated that no evidence on loss at all exist on record. The question
of failure to prove damages is settled at this juncture.
Having considered all those five limbs, it is lucid that the evidence of
the Plaintiff fell short of the required burden and standard of proof in civil
cases. Weighed on scale, the evidence of the Defendant is more credible
that the cancellation/stoppage of permit in the Plaintiff’s project site was
justified on account of environmental degradation/pollution. Thus, the
claim against the Defendants was not proved thus frivolously preferred by
the Plaintiff.
The last aspect is on costs of the case should not detain this court. It
is the law that ordinarily costs follow the events. In this suit, it has been
demonstrated that Plaintiff failed to take bonafide steps to address the
matter before the institution of the case in this court. Also, the evidence on
69 | P a g e
record did establish the claim. This case is one of those circumstances that
this court is enjoined to consider the question of costs.
The guidance on award of costs can be found on the case of DB
Shapriya & Co. Ltd vs Regional Manager, TANROADS Lindi (Civil
Reference No 1 of 2018) [2018] TZCA 256 (25 September 2018)
(TANZLII), at pages 7-8, the Court stated that:
For a start, it is common cause that costs of, and incidental
to, all civil actions are awarded in the discretion of the
Court: see, for instance, the decision of the Court in
Tanzania Fish Processors Ltd (supra). In exercise of
its discretion to award costs, the Court is generally
enjoined to award costs to the successful party on the
basis of the principle that "costs follow the event."
Nonetheless, it is also trite that the Court may withhold
costs to a successful party on any justifiable ground , which
may include that party's misconduct . In this regard, I fully
subscribe to the stance taken by the High Court in Nkaile
Tozo (supra), in particular, that the awarding of costs,
being a discretionary process, is not automatic and that
costs are not awarded to the successful party as a matter
of course. I find Nkaile Tozo (supra) quite relevant even
70 | P a g e
though it concerned the construction of section 30 of the
CPC, which is, admittedly, not applicable to the procedure
before this Court. In my view, the same principles for
awarding costs apply in both the High Court and this Court
even though their respective sources may be different. I
would also add that since the discretion in awarding or
denying a party his costs must be exercised judicially and
not by caprice, the Court is enjoined to state explicitly and
specifically which party is to meet the costs of the action of
the other party to the action. That is so especially on the
reason that an award of costs to one party against the
other grants a benefit to the former and imposes a liability
on the latter. Such an award, therefore, cannot be merely
implicit.
That being the guidance, the Defendants are entitled to costs of the
case to ameliorate the costs incurred as a result of the Plaintiff’s action to
institute a case without tangible merits in it.
It is settled view of this court that the Plaintiff did not discharge his
duty to prove the suit to the required standard of balance of probabilities
to be entitled to the judgment of the court. In the circumstances, the claim
71 | P a g e
against the Defendants remain unproved as there was no tangible and
cogent evidence to that effect.
Conclusively, the Plaintiff’s suit deserve s to be dismissed for lack of
merits. The suit in Land Case No 122 of 2025 is hereby dismissed for want
of merits. The Defendants are entitled to costs of the case.
It is so ordered.
DATED and DELIVERED at Dodoma this 25
th
day of May 2026.
E.E. LONGOPA
JUDGE
25/05/2026.