Case Law[2025] ZAGPJHC 717South Africa
Slim B and D Construction (Pty) Ltd v Sinkonde N.O and Another (2025/026408) [2025] ZAGPJHC 717 (8 March 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
8 March 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 717
|
Noteup
|
LawCite
sino index
## Slim B and D Construction (Pty) Ltd v Sinkonde N.O and Another (2025/026408) [2025] ZAGPJHC 717 (8 March 2025)
Slim B and D Construction (Pty) Ltd v Sinkonde N.O and Another (2025/026408) [2025] ZAGPJHC 717 (8 March 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_717.html
sino date 8 March 2025
THE
HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
Case
2025-026408
(1)
REPORTABLE: No
(2)
OF INTEREST TO OTHER JUDGES: No
(3)
REVISED: Yes
8
March 2025
In
the matter between:
SLIM B AND D
CONSTRUCTION (PTY) LTD
Applicant
And
DENNIS
SINKONDE
N.O.
First Respondent
GVK-SIYA
ZAMA BUILDING CONTRACTORS
(GAUTENG)
(PTY) LTD
Second Respondent
JUDGMENT
DU PLESSIS J
# Introduction
Introduction
[1]
The dispute arises from a construction contract between the applicant
(second respondent in the counter application, hereafter
referred to
as "Slim B & D") and the second respondent (applicant
in the counter application, hereafter referred
to as "GVK-Siya
Zama") concerning a project for the construction of a road. A
disagreement emerged over an unresolved
claim, leading to
adjudication proceedings before the first respondent ("the
adjudicator") .
[2]
Initially, the adjudicator confirmed that he is compelled to deliver
his decision on the merits by 12 March 2025. This
prompted Slim B &
D to launch urgent proceedings to interdict the adjudicator from
adjudicating on the merits of the dispute,
pending the finalisation
of arbitration on the issue of jurisdiction.
[3]
In the course of launching its urgent application, Slim B & D
engaged in a series of correspondence that was effectively
aimed at
influencing the adjudicator to revise his position to align with
their own.
[4]
The sequence of events unfolded as follows: On 27 February 2025, Slim
B & D addressed a letter to the adjudicator,
insisting that he
refrain from issuing his decision on the merits while the urgent
court application remained pending. In the same
letter, Slim B &
D warned the adjudicator that an adverse costs order would be sought
against him should he proceed with the
adjudication process "pending
the outcome of the application". This correspondence left little
doubt that, should the
adjudicator continue with his decision, Slim B
& D would initiate legal steps with a cost order implication.
This action would
,thereby, exert considerable pressure on the
adjudicator to suspend the process.
[5]
Despite this pressure, the adjudicator initially responded on 28
February 2025, affirming that the Adjudication Board
Rules governed
his obligations and that he lacked the authority to suspend the
adjudication unless both parties consented unilaterally.
Slim B &
D, however, insisted that he should halt the process.
[6]
Ultimately, on 1 March 2025, following the correspondence, the
adjudicator reversed his initial position and issued a
letter stating
that he would no longer proceed with the adjudication until "the
court's decision" in the urgent application.
He further
indicated that the court proceedings had interrupted the adjudication
process, affecting the timeline for the delivery
of his decision.
Despite his previous statements affirming his obligation to issue a
decision by 12 March 2025, this abrupt change
in stance suggests that
Slim B & D's persistent legal threats and tactics played a role
in his reconsideration. This inference
arises from the correspondence
exchanged, as the adjudicator did not file any papers in the
application, likely out of concern
for an adverse costs order.
[7]
What is evident is that Slim B & D's actions effectively
disrupted the adjudication process, delaying the resolution
of the
dispute and creating legal uncertainty about the enforceability of
the adjudication deadlines. By strategically applying
pressure on the
adjudicator, Slim B & D could stall the adjudication process and
get the adjudicator to make an undertaking
that would not determine
the merits pending "the court's decision" (effectively the
relief sought in the urgent application).
Slim B & D then sought
the removal of their application from the urgent roll, stating that
this undertaking took away the urgency.
[8]
GVK-Siya Zama opposed the withdrawal, submitting that they required
finality in the matter, either in the form of a withdrawal
with costs
or dismissal, as they saythat any other order will leave the first
respondent under the wrong impression that he does
not have to
finalise his decision on the merits by 12 March 2025, because of his
indication that he will wait for the court "to
make a decision".
Removal of the urgent application might not be regarded as a
"decision".
[9]
I required time over lunch to consider the request for removal and
give directions going forward. During that time, GVK-Siya
Zama
launched an urgent counter application, seeking a declarator that the
adjudicator must hand down his decision on 12 March
2025. Again, the
adjudicator did not file papers but sent a letter to state that he
would abide by the court's outcome, but in
light of the fact that he
regarded the launching of the application to suspend his
adjudication, he would need more time to finalise
the adjudication.
[10]
I enrolled the counter application and directed Slim B & D to
file an answering affidavit to the counter application
so that the
issues could be ventilated properly. In the answering affidavit, Slim
B & D then raised the defence of lis pendens.
Slim B & D
stated that they were well within their rights to remove the matter
for lack of urgency and re-enrol it later if
they so wish.
Lis
pendens
[11]
The
doctrine of lis pendens applies when litigation is pending between
the same parties on the same cause of action and seeking
the same
relief. The rationale is to prevent parallel proceedings that may
result in conflicting decisions and unnecessary duplication
of
judicial resources. Lis pendens can also be raised against a
counter-application, but the court has a discretion to allow the
counter-application to proceed if it introduces new or distinct
issues. A court may also refuse to uphold the lis pendens rule
if
doing so would cause an injustice
[1]
or block access to justice.
[2]
[12]
In the present case, the main application has been removed from the
roll but not withdrawn, meaning the substantive dispute
remains
pending before this court. Although framed differently, the counter
application raises, substantially, the same issues
and seeks relief
that overlaps with what will ultimately be determined in the main
application. The applicant wants finality due
to the ambiguously
framed letter from the adjudicator.
[13]
This court will not condone procedural strategies that frustrate
access to justice and obstruct the expeditious resolution
of
disputes, especially in the urgent court. It is particularly
concerning when a party creates procedural hurdles by exerting
pressure on the adjudicator to abide by the court's decision and not
proceed with the adjudication who then writes an ambiguously
worded
letter, only to rely on that same ambiguity as justification for
withdrawing the matter and then refusing that the other
party seeks
clarity. Given the pattern of conduct displayed, it is foreseeable
that, should the adjudicator indicate his intention
to proceed
following the matter's removal (as it is a" decision"),
Slim B & D Construction would seek to re-enrol
the matter on an
urgent basis to prevent him from doing so. Such conduct is
inconsistent with the principles of fairness and procedural
integrity
that underpin the adjudication process.
[14]
The doctrine of lis pendens is important in preventing duplicative
litigation, but it cannot be invoked as a tool to
obstruct access to
relief. The defence must be dismissed when a party raises lis pendens
abusively to prevent another from obtaining
relief. Slim B & D
Construction has merely removed the matter from the roll rather than
withdrawing it only to raise the issue
of lis pendens. This does not
constitute a legitimate basis to invoke lis pendens. Accordingly, the
defence is dismissed.
Urgency
[15]
Slim B & D Construction contends that the counter-application
must stand or fall on its own urgency. It submits that
the matter is
not urgent because GVK-Siya Zama has failed to make out a case for
urgency and that, in any event, GVK-Siya Zama
has adequate
alternative remedies available should the deadline be missed,
including arbitration, further legal proceedings, or
an agreed
extension of time.
[16]
GVK-Siya Zama, on the other hand, submits that the adjudicator must
adhere to the agreed contractual framework and issue
his decision by
12 March 2025. Failure to do so would compromise the adjudication
process, leading to unnecessary delays, increased
costs, and the
frustration of the agreed dispute resolution mechanism. Adjudication
is intended to provide a swift and binding
interim resolution, and
Slim B & D's conduct undermines this fundamental principle by
transforming adjudication into a protracted
and ineffective process.
[17]
The urgency of the counter-application arose, ironically, from the
adjudicator's letter of 1 March 2025, in which he
stated that he
would withhold his decision pending a "decision", creating
uncertainty. Given that adjudication in terms
of the construction
contract is a structured process governed by strict timelines, the
possibility of the adjudicator becoming
functus officio if the
adjudicator does not issue his decision within the prescribed period
creates the urgency.
[18]
However inelegantly this urgency has come about, I am of the view
that the matter is sufficiently urgent to be enrolled.
I will,
therefore, proceed to consider whether the adjudicator was obliged to
deliver his decision on the merits by 12 March 2025.
Ad
merits
[19]
GVK-Siya Zama states that the adjudicator was appointed under the
South African Institution of Civil Engineering (SAICE)
rules and
ruled on 30 January 2025 that the subcontract agreement between the
parties was validly concluded and that the adjudicator
had
jurisdiction to determine the merits. In terms of Rule 6.1 of the
Adjudication Board Rules, the adjudicator must deliver his
decision
within 28 days of the last document being submitted unless the
parties agree upon an extension.
[20]
Since the last submission was made on 12 February 2025, his decision
must be issued by 12 March 2025, failing which he
will become functus
officio. This was also a central issue in the main application, where
Slim B & D submitted that the adjudicator
may not proceed to
determine the merits because they had referred the adjudicator's
jurisdiction to arbitration. They contended
that should his
jurisdictional ruling be overturned in arbitration, his decision on
the merits would be nullified.
[21]
However, the adjudicator's reversal of his position has serious legal
and contractual consequences. The subcontract agreement
and the
Adjudication Board Rules do not provide for the unilateral suspension
of an adjudication decision due to pending court
proceedings. The
adjudicator's authority is derived from the contractual framework
agreed upon by the parties, and his role is
to apply the established
procedural rules, not to introduce new procedural requirements.
Furthermore, the Adjudication Board Rules
allow the parties to agree
on an extension if necessary. The key issue, therefore, is whether
the adjudicator can unilaterally
alter the prescribed timeframes in
the absence of such an agreement.
[22]
In
Group
Five Construction (Pty) Ltd v Transnet SOC Limited,
[3]
Twala J had to determine the implications of an adjudicator who must
decide within a certain time. Referring to the speedy nature
of
adjudication in construction contracts, the court stated
[4]
:
"These clauses do
not state what should happen when a party does not grant the consent
to extend the period. I am of the respectful
view that the intention
of the parties to make the requirement of consent from the parties to
afford the adjudicator more time
is meant to give the parties control
over the process of the adjudication. It is meant to give the parties
some power to deal,
should they find themselves in that situation,
with a recalcitrant adjudicator. The ineluctable conclusion is
therefore that, absent
such consent to the extension of time, the
adjudicator should publish his report on due date failing which his
mandate is terminated.
I am therefore unable to disagree with counsel
for the respondent that, from the plain wording of these clauses, the
adjudicator
is not competent to proceed and act beyond the time
period set by the agreement if he is unable to secure the necessary
consent
from both parties. No other meaning can be ascribed to these
provisions for they are not at all ambiguous."
[23]
A full
bench in this division
in
Proserve Consulting (Pty) Ltd v RMV Engineering Projects (Pty) Ltd
[5]
endorsed this approach, emphasising that time is of the essence in
these types of contracts, stating that
"[…]
international and academic authority […] supports the
conclusion that the court came to. The importance
of speed in these
type of contracts and the importance of keeping to time limits
to achieve that goal, as well as the fact
that the decision is not
permanent and may be challenged on arbitration were pointed out. I
agree with the conclusion by the Court
in Group Five that absent a
consent to an extension, the adjudicator's mandate is terminated."
[24]
I am of the view that there is no basis for treating this case
differently. The referral of the jurisdictional question
to
arbitration did not alter the timeframe for the adjudicator to
deliver his decision on the merits. The parties agreed upon this
during a meeting in October 2024, where it was confirmed that should
the adjudicator find that he has jurisdiction, he would then
determine the merits. At that stage, the only remaining point of
contention was whether the matter would be decided on the papers
or
require an oral hearing.
Remedy
[25]
This brings
me to the remedy GVK-Siya Zama seeks: a declaration confirming that
the adjudicator must issue his decision by 12 March
2025. Such an
order does not compel the adjudicator to act but serves to clarify
his obligations under the agreement, ensuring
certainty in the
adjudication process.
[6]
[26]
In
Rail
Commuters Action Group v Transnet Ltd t/a Metrorail,
[7]
the Constitutional Court emphasised that declaratory orders are
discretionary and flexible. The court stated
[8]
:
"It is quite clear
that before it makes a declaratory order a court must consider all
the relevant circumstances. A declaratory
order is a flexible remedy
which can assist in clarifying legal and constitutional obligations
in a manner which promotes the protection
and enforcement of our
Constitution and its values. Declaratory orders, of course, may be
accompanied by other forms of relief,
such as mandatory or
prohibitory orders, but they may also stand on their own. In
considering whether it is desirable to order
mandatory or prohibitory
relief in addition to the declarator, a court will consider all the
relevant circumstances."
[27]
In
Cordiant
Trading CC v Daimler Chrysler Financial Services (Pty) Ltd
[9]
the
Supreme Court of Appeal confirmed that an application for a
declaratory order follows a two-stage approach. First, the
court must
be satisfied that the applicant has an interest in an existing,
future, or contingent right or obligation. Secondly,
if such an
interest exists, the court must determine whether it is appropriate
to exercise its discretion to grant the declaratory
relief sought.
One of the key considerations in this exercise is whether granting
declaratory relief will settle the question in
dispute between the
parties.
[28]
In my view,this is such a case. GVK-Siya Zama has a clear contractual
right to have the adjudicator issue a decision
within the timeframes
set out in the contract or as agreed between the parties.
Costs
[29]
GVK-Siya Zama seeks a costs order on an attorney-and-client scale
against Slim B & D, contending that its conduct
throughout these
proceedings has been unreasonable, obstructive, and deliberately
aimed at frustrating the adjudication process.
Slim B & D engaged
with the adjudicator in a manner that led to reversing his initial
position, thereby creating unnecessary
legal uncertainty and
compelling GVK-Siya Zama to seek judicial intervention. Furthermore,
Slim B & D's reliance on lis pendens
as a defence appears to be a
tactical manoeuvre to delay and obstruct the adjudication process
rather than a legitimate legal argument.
[30]
I agree with this view insofar as the counter-application is
concerned. Slim B & D's conduct has necessitated this
application, and its procedural tactics have resulted in avoidable
legal costs. As for removing the urgent application, Slim B
& D
is ordered to pay GVK-Siya Zama's wasted costs.
## Order
Order
[31]
The following order is made:
1. The application
is removed from the roll, with Slim B & D Construction (Pty) Ltd
to pay the wasted costs.
2. The counter
application is enrolled and heard on an urgent basis as contemplated
in Rule 6(12) of the Uniform Rules of
Court, and non-compliance with
the prescribed form and time periods, is condoned.
3. It is declared
that the first respondent (the adjudicator) is required to deliver
his adjudication decision on or before
12 March 2025, in terms of
Rule 6.1 of the Adjudication Board Rules, failing which he will
become functus officio.
4. Slim B & D
Construction (Pty) Ltd is to pay the costs of the counter-application
on an attorney-client scale.
WJ
du Plessis
Judge
of the High Court
Gauteng
Division, Johannesburg
Heard
on: 5 & 7 March 2025
Decided
on: 8 March 2025
For
Slim B & D Construction (Pty) Ltd:
Z
Cornelissen instructed by Martini-
Patlansky
Attorneys
For
the respondents
R
Bekker MDA Construction & Technology
attorneys
[1]
Caxton
Ltd and Others v Reeva Forman (Pty) Ltd 1990
(3) SA 547 (A).
[2]
Venmop
275 (Pty) Ltd v Cleverlad Projects (Pty) Ltd
2016
(1) SA 78 (GJ).
[3]
[2019] ZAGPJHC 328 .
[4]
At
para 21.
[5]
[2024] ZAGPPHC 9.
[6]
Naptosa
v Minister of Education, Western Cape
2001 (2) SA 112
(C) at 125. See Erasmus:
Superior
Court Practice
D-229.
[7]
[2004] ZACC 20.
[8]
At
para 107.
[9]
[2005] ZASCA 50.
sino noindex
make_database footer start
Similar Cases
S.L.M. v H.A.C (18281/2021) [2025] ZAGPJHC 687 (19 June 2025)
[2025] ZAGPJHC 687High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Slim B and D Construction (Pty) Ltd v Caterpillar Financial Services (Pty) Ltd (105847/2024) [2025] ZAGPPHC 780 (4 August 2025)
[2025] ZAGPPHC 780High Court of South Africa (Gauteng Division, Pretoria)98% similar
S.B.M. v Road Accident Fund (728/19) [2025] ZAGPJHC 548 (4 June 2025)
[2025] ZAGPJHC 548High Court of South Africa (Gauteng Division, Johannesburg)98% similar
S.L.B v R.L.B (2019/35722) [2025] ZAGPJHC 1229 (26 November 2025)
[2025] ZAGPJHC 1229High Court of South Africa (Gauteng Division, Johannesburg)98% similar
South African Municipal Workers Union v Tirhani Travel and Tours (Pty) Ltd (112/2022) [2025] ZAGPJHC 1217 (21 November 2025)
[2025] ZAGPJHC 1217High Court of South Africa (Gauteng Division, Johannesburg)98% similar