Case Law[2025] ZAGPJHC 420South Africa
Ram Transport South Africa (Pty) Ltd ta Ram Hand to Hand Couriers v DHL Supply Chain South Africa (Pty) Ltd (A2024/054003) [2025] ZAGPJHC 420 (29 April 2025)
Headnotes
discussions to ascertain DHL’s requirements. The companies conducted reciprocal site visits to inspect each other’s
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 420
|
Noteup
|
LawCite
sino index
## Ram Transport South Africa (Pty) Ltd ta Ram Hand to Hand Couriers v DHL Supply Chain South Africa (Pty) Ltd (A2024/054003) [2025] ZAGPJHC 420 (29 April 2025)
Ram Transport South Africa (Pty) Ltd ta Ram Hand to Hand Couriers v DHL Supply Chain South Africa (Pty) Ltd (A2024/054003) [2025] ZAGPJHC 420 (29 April 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_420.html
sino date 29 April 2025
FLYNOTES:
CONTRACT – Interpretation –
Conduct
of parties
–
Existence
of binding contract – Letter of intent and request for
quotation contemplated further negotiations –
No binding
contract was formed until final terms were agreed –
Protracted negotiations and unresolved disputes over
key terms –
Demonstrated an absence of a meeting of minds – Lack of
evidence for misrepresentation – Conduct
of parties
indicated that no valid agreement existed – No misdirection
– Appeal dismissed.
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, JOHANNESBURG)
Case
No: A2024-054003
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
29.04.2025
IN
THE MATTER BETWEEN:
RAM
TRANSPORT
APPELLANT
SOUTH
AFRICA (PTY) LTD
t/a
RAM HAND TO HAND COURIERS
AND
DHL
SUPPLY CHAIN
RESPONDENT
SOUTH
AFRICA (PTY) LTD
JUDGMENT
Siwendu
J (Maier- Frawley J and Flatela J concurring):
Introduction
[1]
The is appeal involves a contractual dispute between the appellant,
RAM Transport (South Africa) Pty Ltd t/a RAM Hand-to-Hand
Couriers,
(RAM) and the respondent, DHL Supply Chain (South Africa) (Pty) Ltd
(DHL).
[2]
RAM and DHL are well known logistics and supply chain companies. DHL
provides wholesale distribution services. DHL conducts
the wholesale
distribution of pharmaceutical products, which feature in this
appeal, through its Life Sciences and Healthcare Distribution
Supply
Chain division (LSH). LSH’s clients, referred to as “the
principals,” include companies like Bard Medical,
BMX,
Octopharma, Smith and Nephew, Mlungisi Healthcare and Omni. LSH
wholesale distribution service has two components, a multiuser
facility and one dedicated to Netcare (also referred to as Omni).
[3]
RAM provides bulk collection and delivery services, warehousing
management services, courier services and other logistics
services.
It has an established footprint and operates forty two hubs
throughout the Southern African region. It also provides
shipments
and courier services containing medical and pharmaceutical products
to its own clients like United Pharmaceutical Distributors,
Dischem,
Dischem Oncology, Transpharm, Equipharm.
[4]
The wholesale distribution of pharmaceutical products is regulated by
the Medicine Control Council (MCC). Other applicable
regulatory
standards include the Good Wholesaling Practice, Pharmaceutical
Inspection Convention, Pharmaceutical Inspection Co-operation
Scheme
and South African National Accreditation System. Quality assurance
and Health and Safety, and Standard Operating Procedure
are a
critical to the provision of the wholesale distribution service. DHL
is licensed to conduct its wholesale distribution business
in respect
of pharmaceutical products in terms of these regulations. When it
subcontracts its deliveries services to third parties,
such as RAM,
it cascades the regulatory compliance to its subcontractors.
[5]
The trial evidence showed that it requires infrastructure comprising
warehousing (hubs and depots), temperature controlled
vehicles.
Coordination between the wholesaler, the distribution service
provider and the end customer, through efficient IT systems,
is an
integral component of the distribution service. The maintenance of a
cold supply chain at varying levels to safeguard integrity
and
quality of the pharmaceutical products is a critical requirement. The
rates for transportation of the pharmaceutical products
are linked to
whether they are transported by road and or air freight and depend on
customer delivery requirements. This has an
implication on rates
charged and the profit margin to be realised between the wholesaler
and the distributor. These considerations
featured prominently during
the trial and subsequent disputes between the parties.
[6]
The disagreement on appeal is about whether, when DHL nominated RAM
in terms of a Letter of Intent (LOI) to distribute
pharmaceutical
products on its behalf, the parties concluded a binding unconditional
contract. It is common cause that from 26
March 2018 to July 2018,
RAM distributed pharmaceutical products on DHL’s behalf.
Whether by permitting RAM to provide the
distribution services, DHL
suspended or waived the need to conclude a contract is in issue. The
terms upon which RAM provided the
distribution services during that
period are in dispute.
Background
[7]
In August 2017, Mr Craven (Craven), DHL’s Sourcing and
Procurement Manager sent a Request for Quotation (RFQ) to
RAM’s
Senior Sales Executive, Mr Walker (Walker), in what RAM alleged was a
closed bid, requesting RAM to populate a Case
Study and provide DHL
with rates for distributing pharmaceutical products. Craven and
Walker, both members of the respective parties’
sales teams,
played a prominent role during the RFQ process. At the time, DHL had
subcontracted the delivery services to Seabourne
Couriers (Seabourne)
[8]
RAM submitted its last proposal on 11 September 2017, after Craven
consulted with Mr Graeme Lazarus (Lazarus), RAM's Managing
Director,
following a request by Craven for RAM to adjust its initial rates.
The last proposal comprised of: (a) the
populated case study, (b) the rate cards recording pricing and
(c) the Statement of services.
[9]
It is common cause that before the nomination, between 12 September
2017 and 30 November 2017, RAM and DHL representatives
held
discussions to ascertain DHL’s requirements. The companies
conducted reciprocal site visits to inspect each other’s
infrastructure. Separate meetings were held between Ms Gail Mkele
(Mkele) and Cindy Hayward (Hayward), RAM and DHL’s responsible
pharmacists, to understand the nature of RAM's service offering and
what would be required to deliver the services stipulated by
the RFQ.
[10]
On 30 November Craven advised Walker that RAM’s proposal was
successful, and congratulated RAM on the “successful
nomination”, stating that “we wish to initiate the
implementation planning going forward.” A letter dated 27
November 2017 signed by Graven and Ms Margareutte van der Merwe (Van
der Merwe), the designated General Manager LS & H (DSC),
was
attached to Craven’s email. Craven reported to Van der Merwe. I
return to the contents of the letter, which must be read
with the RFQ
in due course.
[11]
On 30 November 2017, DHL terminated the distribution service contract
with Seabourne with effect from 31 January 2018.
In addition, Ms
Lindie Smith (Smith), the Key Accounts manager for Netcare, advised
Ms Anthea Richie, that RAM would be taking
over the distribution
services from Seabourne. Netcare is one of DHL’s significant
customers, constituting 60% of the pharmaceutical
products business.
Walker testified that from December 2017 he and Craven worked on
“implementation plans.”
[12]
During December 2017, Mr Derrick Bode (Bode), entered the discussions
as the newly appointed operations manager and became
a key role
player. His role was to ensure that RAM and DHL would be
operationally ready to render the services from the “go
live
date” on 1 February 2018. Craven and Walker scheduled a site
visit with Bode and others on 14
th
December 2017.
[13]
A separate meeting between the principal pharmacists Hayward and
Mkele took place in tandem, to exchange information
on the
pharmaceutical related parts of the service, in particular, the pre
supplier Audit processes, Quality Management System,
Health and
Safety Policy audit. After this meeting, Mkele forwarded RAM’s
Standard Operating Procedures (SOP) and existing
Quality Assurance
documents to Hayward.
[14]
On 18 December 2017, Walker circulated the first project “medical
implementation tracker report” to Bode,
Padayachee, Craven (the
DHL team) reflecting items discussed and milestones to be achieved on
different components of the logistics
and distribution chain. Bode’s
evidence was that Change Management control from one service provider
to another was an important
component of the project plan and
integral to the readiness to “go -live.” The induction or
training of personnel,
ensuring regulatory compliance and
understanding of reciprocal infrastructure and systems of both RAM
and DHL and the needs of
the principal customers was integral to
readiness before the “go-live” date. Bode was concerned
that the Netcare business
be retained. He testified on a need to
“...have a project person on RAM’s side working hand in
hand with DHL on the
project (and not the sales guy as he will say
yes to everything without thinking it through).”
[15]
Bode assembled a project plan and motivated for the appointment of a
project manager to oversee the milestones and implementation
of the
project. DHL appointed Daniel du Plessis (du Plessis) as the DHL
Project Manager to manage the transition process. Bode
was concerned
about the readiness to “go live” on 1 February 2018. As
result, DHL took a decision to postpone the “go-live”
date following internal discussions. The consequence was that the
termination of Seabournes’ contract had to be extended
for a
period while DHL and RAM worked on completing the milestones for the
implementation of the project. The transition date was
moved to 1
April 2018.
[16]
On the 20th of December 2017, Van der Merwe wrote to several role
players in DHL including Bode, Smith and Craven about
the decision to
“change vendors.” The email included Ravil Raman (Raman),
Kevin Makkie (Makkie) whose role in the project
was at that stage was
not yet clear, and stated:
“
Dear Business
partner
DHL Supply Chain has
taken the decision to move from its current 3rd party vendor to RAM.
This change will be effective in Q2 2018.
This change was not taken
lightly and is as result of a rigorous RFQ process.
RAM has placed a very
compelling service offering on the table and DHL is looking forward
to working with them in the future.
There will be a dedicated
project team compromising all the DHL stakeholders in place as of
January 2018 and the timelines will
be made available to all as soon
as the project kicks off in January 2018.
DHL Regulatory has
already been in contact with your responsible Pharmacists to align on
the technical agreements and to obtain
sign-off.
From a business
perspective please advise by return email that you are comfortable
with the move so I can note on our side.
Rest assured that all the
regulatory and operational checks and balances will be in place and
signed off with a SLA in place before
go live…..”
[17]
Although Netcare, as the principal was informed of the nomination of
RAM by Smith on 30 November 2017, the change in
vendor received the
attention of Ms Anita Hamilton (Hamilton), who wrote to Van der Merwe
as follows:
“
Dear Margareutte
One of the challenges we
have experienced with Seabourne was their cold chain management —
despite the SLA in place. I trust
that RAM offers an accredited and
approved cold chain management well reviewed for competence. Your 3rd
Party provider to outlying
areas has often been responsible for KPI's
not reached and therefore your SLA should be watertight with
measurement tools and recourse
for failure.
Please
confirm same, and please share that with ourselves.”
[18]
DHL together with representatives from RAM went on a roadshow
to Cape Town where they met with Netcare’s key representatives.
Bode conceded that, in a presentation to Netcare, he had referred to
several reasons why DHL chose RAM. DHL’s principals
had to
approve of any change in service provider. Such approval was not yet
in place on 30 November 2017.
[19]
Mkele’s evidence confirmed the need to customize RAM and DHL
Standard Operating Procedures (SOP), and to reach
agreement and
document these procedures. On the other hand, Hayward’s
evidence emphasised the integrity of the storage, handling
and
conveyance of the pharmaceutical product prior to utilization of a
supplier, which was subject to an audit review. Part of
this included
the winter and summer Qualification of RAM’s vehicles. Although
RAM was nominated and several meetings held
between the parties, a
Pre- Approval Supplier Audit Review Report was outstanding. Hayward
was responsible for completing the Audit
Review. She emailed the
“Pre-Approval Supplier Audit Report Version 2”, dated 5
March 2018, to Mkele on 6 March 2018.
It conveyed “two critical
findings” requiring attention. Although RAM distributed
pharmaceutical products, DHL’s
principals (in particular
Netcare) appeared to have had additional requirements which differed
from RAM’s service offering.
[20]
For example, Mkele agreed with the finding that the line haul was not
temperature monitored and had not been mapped.
A solution was
required before products at ambient temperatures were to be
transported by line haul. It was not disputed that not
all of RAM’s
vehicles were temperature controlled to ensure the integrity of the
product, but there was disagreement on whether
this was a critical
finding. Its common cause that RAM later purchased a fleet of 52
vehicles for approximately R18m.
[21]
Mkele and Hayward agreed that a Technical or Quality agreement was
necessary and had to be signed off by the responsible
pharmacist
prior to “go live” date. Mkele’s evidence was that
since there was no such agreement, same had to
be constructed, and
the parties had been working through the technical and quality
requirements from January 2018.
[22]
Between January and March 2018, the parties monitored the completion
of the project milestones using an “implementation
tracker
report” which was updated by different work streams as the
project developed. The conclusion of a Master Logistics
Agreement
(MLA) and Service Level Agreement (SLA)
with
Draft agreements targeted for completion early February 2018
was amongst the outstanding items. As of 1 March 2018, the SLA and
related agreement agreements had not been finalised.
[23]
On 6 March 2018, RAM’s Group General Counsel, Mr Alan Da Costa
(Da Costa) entered the project implementation discussions.
He
circulated the draft Interpretation Schedule Master Logistics
Agreement (MLA), the Service Level Agreement (SLA) on 8 March
2018 to
DHL’s legal counsel, Ms Lisa Cronwright (Cronwright) and copied
Hayward, Van Der Merwe, Lazarus, Kassim, and Mkele
amongst others.
[24]
On 13 March 2018, Da Costa raised several points of contention under
various heads of discussion, about (a) Ti
ming and Rollout, (b)
Rates, (c) Technical, (d) Full Liability / Insurance, (e) integration
and IT, (f) Linehaul, (g) Local Fleet
and (h), Pallets.
[25]
Despite the above outstanding issues, the “go-live”
scheduled for 1 April 2018 was brought forward because
Seabourne
refused further extensions and gave a notice terminating its services
with DHL earlier than expected. Svoboda testified
that DHL called on
RAM to commence the services from 26
th
March 2018, earlier
than the scheduled “go-live” date. Svoboda testified that
DHL had anticipated that the necessary
agreements would be reached
before “go- live” date.
[26]
On 13 March 2018, simultaneously with draft agreements sent to DHL,
Da Costa advised DHL that:
“
Should the
agreements not be signed before start date, the fall back would be
that we would carry the goods on our standard terms
and conditions
which are available on our website.”
[27]
On 16 March 2018, he wrote to DHL stating:
“
We understand that
you may have to bring us on board sooner rather than later as we are
advised that you service provider is already
moving out.
We understand the
materiality of the Contract with a number of large principals and in
order to ensure that we do not drop the ball,
we urgently need to
conclude all the legal and other documentation and SOP's and are
working closely with your team to ensure timeous
rollout.”
[28]
He reaffirmed earlier emails that should RAM commence work before the
signing of the MSA and the SLA, then “all
shipments will be
collected and delivered in accordance with RAM's standard terms and
conditions, a copy of which is available
on RAM's website.” Da
Costa was aware that the “test/overlap week” would need
to be accelerated to the week
of 19 March 2018. I understand this
allows for a period of a hand over from Seabourne to RAM. On 20 March
2018, Da Costa informed
DHL that RAM would not commence with the
distribution services until “the legals are sorted.” He
repeated this stance
on 22 March 2018.
[29]
Svoboda’s evidence was that DHL reluctantly signed RAM’s
credit application with the standard terms and conditions,
even
though the nature of the service was not a standard courier service,
until the proper contract was agreed. The rates for the
service were
not the standard RAM rates that would be available in the market.
They were the rates as per what was tendered in
October [sic]
September 2017. He had assumed that the rates tendered for would be
applied. Walker had testified that the rates
were not discussed again
after the last proposal. It was a compromise, as RAM would not be
taking any liability under those terms.
[30]
According to Hayward DHL had no contractual basis to compel RAM to
comply with the quality and the material regulatory
requirements of
DHL's clients. When questioned about allowing RAM to commence
distributing the products under those circumstances,
Hayward
testified that:
“
We had SOB,
standard operating procedures in place. There was excessive training.
We did a change control which is a GWP document
on our side at DHL to
ensure that we look at all the different aspects and do a risk
assessment and address the risks, but always
understanding and even
on that change control document, that a quality agreement needed to
be agreed upon between the two entities.
What we were doing, we were
operating on risk and we were mitigating it.”
[31]
After RAM commenced the services, several iterations of the draft
MLA, an SLA, an Interpretation Schedule, and a Quality
Agreement were
exchanged between March 2018 to July 2018. It is common cause that as
late as June 2018, several contentious issues
which had arisen had
not been resolved. It is not necessary to chronicle all of them.
Indicative areas will suffice. One related
to the liability insurance
for Goods in Transit (GIT) reflected in the statement as part of the
tender. However, this issue was
resolved in an interim arrangement
during contract negotiations.
[32]
Svoboda’s evidence was that after an analysis, DHL found there
was a “mismatch between how the service types
were being
applied by RAM versus what they tendered,” prompting
discussions which were escalated to Lazarus. RAM could not
effect
Next Business Day Deliveries (NBD) to distant centres by road but
could only do so by air. RAM had tendered to deliver by
road. This
affected pricing.
RAM indicated that it
would not assume liability or warrant that RAM would comply with
DHL’s MMC obligations, which
remained a point of some
contention between the parties.
[33]
Da Costa revised the initial period of the draft Service Level
Agreement to be for 30 months as opposed to 3 years. However,
he
stated to DHL that RAM could not agree to termination on a month's
notice by a party without cause. This also featured in the
revised
draft Master Logistics Agreement, where Da Costa also appeared to
delete DHL’s comment in respect of the termination
clause.
[34]
Zanoodene Kassim (Kassim) who was employed as Legal Counsel for Sub-
Saharan Africa DHL Supply Chain (South Africa) (Pty)
reported to
Cronwright and was involved in what she referred to as protracted
negotiations of the contract. There were at least
seven iterations of
draft agreements circulated between the parties between March 2018 to
July 2018, all of which were not brought
to finality.
[35]
DHL sought to bring an end to the negotiations with RAM and to stop
using RAM for the rendering of the services. On 29
August 2018, DHL
sent a letter of a "Notice of Termination of Services" to
RAM. Da Costa’s stance in reply to the
notice of termination
was that, since the receipt of the LOI, RAM and DHL had agreed all
material terms of the contract and had
concluded a partly written,
and partly oral agreement. RAM would therefore not accept the
Termination Notice.
Before
the Trial Court
[36]
The action came before Manoim J, sitting as the Commercial Court
(trial court) who determined the dispute concerning
the existence of
the contract on the terms alleged separately from quantum.
[37]
RAM alleged that it had:
i.an exclusive contract
to render the distribution services for the duration of 24 months,
which contract could only be terminated
for material breach (for
cause), which contract came into force on 30 November 2017,
commencing on 1 February 2016 which date was
subsequently amended to
26 March 2018.
ii.The express, or
implied or tacit terms of the contract were embodied in the (a)
Statement, (b) Case Study and (c) Rates Card
submitted as its last
offer to DHL in response to the RFQ and subsequent conduct of the
parties evidenced that there was a binding
enforceable contract.
iii.From 26 March 2018
RAM rendered the distribution services for the pharmaceutical
products until DHL gave it a notice of an intention
to terminate the
distribution service on 31 August 2018 with effect from 30 September
2018.
iv.DHL repudiated the
contract and as a result, RAM suffered a loss of profit in the sum of
R36 003 703.00.
v.It also pleaded in the
alternative that the reference to the “initial period of 24
months”, “final award”
and the conclusion of a
contract in the letter of nomination did not constitute a suspensive
condition and if the court found it
was, then the parties tacitly
alternatively, by their conduct amended the condition by deleting the
suspensive condition, alternatively
waived it, alternatively waived
its fulfilment.
vi.As a further
alternative, it alleged a representation by the defendants’
representatives who led RAM it to believe DHL
believed the terms of
the agreement and this bound the defendants through the doctrine of
quasi- mutual assent.
[38]
After a trial of long duration in which thirteen witnesses were
called, the trial court dismissed RAM’s action
with costs. It
considered the RFQ, RAM’s last offer, the LOI and the language
employed in the documents. It found that textually,
the LOI expressed
itself in aspirational terms rather than those consonant with a
binding contract. The Statement forming part
of RAM’s last
offer was not drafted in imperative contractual terms but comprised
criteria for the qualification of RAM as
tenderer. Nevertheless, it
concluded that the LOI was “sufficiently ambiguous for the
context to tilt interpretation.”
[39]
The trial court found that the evidence of the context, the
subsequent events and the conduct of the parties for the
earlier
period (in this I read conduct leading to the nomination), the
rendering of the distribution services from 26 March 2018
and the
failure by DHL to call key witnesses suggested the context supported
RAM’s interpretation, noting that:
“
RAM, as I noted at
the outset, needed to get around the 'final sentence problem'. It
relied on the context to do so. On 30 November
2017 that contextual
history must be construed in its favour-that RAM had been appointed
on two-year contract and whatever final
contract was concluded was a
matter of finer detail.”
[40]
However the latter period, (in this I read to mean conduct post the
nomination and after March), the conduct and context
was “messy”
and not “static.” It tilted the scales against RAM’s
interpretation because RAM’s
conduct suggested that the parties
had decided their future relationship depended on a final agreement.
Mr da Costa’s conduct
and evidence appears central to this
finding.
[41]
It dismissed the alternative claims based on quasi mutual assent and
or waiver, because “the factual matrix for
their support was
based on the same principal argument on which RAM relied. First,
there is no direct evidence of this apparent
mutual decision. Second,
the notion of a suggestion cannot be elevated to one of probability.
The fact that RAM initiated the process
of the final contract is
irrelevant.” Having dismissed that argument, RAM’s
alternative claims followed a similar fate.
Aggrieved by the
dismissal, RAM appealed to this Court and the appeal is with the
leave of the trial court.
On
Appeal
[42]
RAM’s case is premised on the trial court’s failure to
apply the principles
CGEE
Alsthom
Equipments
et Enterprise Electriques, South African Division v GKN Sankey (Pty)
Ltd
[1]
(
Alsthom)
in
evaluating the facts and the conduct of the parties. In
Alsthom
the
court held that:
“
Whether in a
particular case the initial agreement acquires contractual force or
not, depends upon the intention of the parties,
which is to be
gathered from their conduct, the terms of the agreement and the
surrounding circumstances."
[43]
It contends, based on
Alsthom,
that the determinative events
were those leading up to the 30 November 2017, being the date when
the LOI was issued and a binding
contract concluded with DHL. The
covering email to the Statement, the Statement, the Populated Case
Study read together with the
LOI constitute a binding contract. The
essence of this submission is that as of 30 November 2017, the
essentialia of the contract
were agreed. The services to be rendered,
the rates, the initial period and the commencement date were known.
The fact that there
were outstanding issues to be resolved was
immaterial and not determinative of whether an unconditional contract
came into force.
Witnesses who had knowledge of the facts leading up
to the issuance of the LOI were Van de Merwe and, later Smith. An
adverse inference
should have been drawn for DHL’s failure to
call them.
[44]
RAM also relies on events after the LOI and contends that from
December 2017, steps were taken to implement the contract,
and this
included the termination of the services of the existing distributor,
Seabourne. It claims that such termination was designed
to coincide
with the “go-live” date of 1 February 2018, as
contemplated in the LOI. It further contends that from 26
March 2018,
RAM rendered services for the distribution of pharmaceutical products
on behalf of DHL, which is consistent with an
unconditional agreement
having come into force. The parties’ mutual conduct pointed to
unambiguous steps taken to implement
the contract.
[45]
Part of the complaint is that the trial court over emphasized, in its
the interpretative exercise, the wording in the
RFQ and the LOI and
placed insufficient weight on steps taken to implement the contract
when determining the intention of the parties.
[46]
RAM argued that, if the court finds that its nomination was
conditional upon the conclusion of a contract, DHL had waived
the
condition, alternatively, that the parties proceeded by quasi- mutual
consent. Although that view was dismissed by the trial
court, it
remained alive for determination on appeal.
Discussion
[47]
As the court in
Command
Protection Services (Gauteng) t/a Maxi Security v SA Post Office
Ltd
[2]
(Command Protection
Services)
observed,
“disputes of this nature are not novel in complex transactions
where parties reach agreement by tender (offer) and
acceptance while
there are clearly some outstanding issues that require further
negotiation and agreement.” The court points
to two
possibilities, one being that the acceptance of the offer does not
create an
animus
contrahendi
if
it is conditional on further negotiations of outstanding issues. The
other possibility is the principle in
Alsthom,
that parties intended the
offer and acceptance to give rise to a binding contract and for the
outstanding issues to be left for
later negotiation. RAM’s case
is based on the latter proposition in
Alsthom.
[48]
Although the word “nominates” is capable of a variety of
meanings depending upon the context in which it
is used,
[3]
both parties accepted that “nominate” meant “appoint.”
DHL’s case in opposition is that RAM’s
nomination
as a preferred service provider was no more than an agreement or
an
invitation to negotiate
a
contract.
[49]
RAM submits that the court must determine whether there was
animus
contrahendi.
If
the principle in
Alsthom
is
applied in conjunction with the approach by the Constitutional Court
in Univ
ersity
of Johannesburg v Auckland Park Theological Seminary and Another
(Auckland Park)
[4]
,
the only relevant considerations are those leading up to the LOI,
hence the complaint about the failure to call Van der Merwe
and
Smith. In its heads of argument it contends that “the most
satisfactory analysis in disputed cases of this nature is
to isolate
the offer and ascertain whether the evidence shows that the offeree
knew, or ought to have known, that it was intended
to be accepted on
a provisional basis only, and that the conclusion of a binding
contract was to be dependent on agreement on further
points.”
[5]
It found support in the decision in
Pitout
v North Cape Livestock Co-op Ltd
[6]
( Pitout)-
also referred to in
Alsthom
Equipments.
In
Pitout
the court held:
“
The question which
arises, accordingly, is whether the undertaking, given as it was
during the course of uncompleted negotiations,
had, or has been shown
to have had, contractual force. Was the undertaking an offer
made,
animo
contrahendi
,
which upon acceptance would give rise to an enforceable contract, or
was it merely a proposal made by the appellant while the
parties were
in the process of negotiating and were feeling their way towards a
more precise and comprehensive agreement? This
is essentially a
question to be decided upon the facts of the particular case”
[50]
Although the trial court found that DHL expressed its
acceptance of RAM’s last proposal in aspirational terms
using
phrases like it “
intends
to partner”, it “would like to contract,” however
,
what distinguishes an offer to contract from any other proposal or
statement is the express, or tacit intention to be legally
bound by
the offeree's acceptance.
[7]
As
DHL contends,
t
he
LOI appointing RAM as a preferred supplier was “conditional”
upon the conclusion of the RFQ contract, evident from
its terms. The
conclusion of a final binding contract was not a suspensive condition
susceptible to waiver. There was thus no binding
agreement with RAM
on the terms alleged.
[51]
The RFQ states in relevant part that:
“
This RFQ does not
commit DP DHL GROUP or any official of it to any specific course of
action. The issuance of this RFQ does not
bind DP DHL GROUP or any
official of it to accept any proposal, in whole or in part, whether
it includes the lowest bid, nor does
it bind any official of DP DHL
GROUP to provide any explanation or reason for its decision to accept
or reject any proposal. Moreover,
while it is the intention of DP DHL
GROUP to enter contract negotiations with the selected Supplier, the
fact that DP DHL GROUP
has given acceptance to a Supplier does not
bind it or any official of it to purchase any product or service from
such a Supplier.”
[52]
The letter of intent states:
LETTER
OF INTENT FOR PROVISIONING OF LIFE SCIENCES AND HEALTHCARE PRODUCT
DISTRIBUTION SERVICES TO DHL SUPPLY CHAIN S.A
.
Dear
Graeme
It
is our pleasure to inform you that DHL Supply Chain S.A. has
nominated RAM Hand To Hand Couriers to be its preferred service
provider and with whom DHL Supply Chain S.A. intends to partner with
for the provisioning of their required Life Science and Healthcare
Product Distribution Services.
This
nomination is based on the requirements as stipulated in the RFQ and
as per RAM's last proposal.
It
is to this end that DHL Supply Chain S.A. would like to contract with
RAM Hand To Hand Couriers for an initial period of 24 months
effective 012 (sic) February 2018.
DHL
Supply Chain S.A. would like this letter of intent to serve as a
means to an end for the preparations necessary for the implementation
of these services with the targeted effective date being no later
than 26 January 2018.
The
final award shall be subject to the successful conclusion of the
contract accordingly.”
[53]
Lazarus who confirmed the acceptance of the award the same day,
wrote:
“
Hi John
Many thanks for the award
and please be rest assured that we ensure our partnership and
execution of this contract makes DHL stronger
within the healthcare
field.
We need to urgently
please sure that we have the correct working teams to execute this
integration to ensure we are ready to start
date.”
[54]
RAM’s construction of DHL’s LOI is that of a “firm
offer” to RAM. It says the enforceable unconditional
contract
came about, upon Lazarus’s email, accepting the ‘award.’
The first difficulty is that this construction
subverts the RFQ
process followed, conflates the issues and is applied in a manner
that is inconsistent with the common cause facts,
the evidence and
the pleadings.
[55]
The correct position is that the RFQ, issued by DHL was an invitation
to RAM to make “a proposal” for the
distribution
services. In procurement parlance, DHL invited RAM to tender (make an
offer) for the distribution services. RAM accepted
at the trial that
it made a “final bid” by submitting its “Last
Proposal” on 11 September 2017 in response
to the RFQ, an
invitation to make an offer for the services. RAM’s last
proposal was the “firm offer” to DHL
open to rejection or
acceptance according to the RFQ terms and conditions. RAM was the
“offeror” and DHL “offeree”
and not the other
way round.
[56]
The second difficulty is that RAM seeks to overcome what was referred
to by the trial court as “the last sentence
problem” in
the LOI. It asks of the Court to isolate the offer and to instead
look to events leading to its nomination as
a preferred supplier on
the strength of the Constitutional Court’s decision in
Auckland
Park,
[8]
[57]
If adopted, RAM’s approach would avoid the debate about two
important rules; namely (a) the parole evidence rule,
and (b) the
express language of the RFQ and the LOI stipulating the terms on
which RAM participated and accepted the nomination
by DHL. In the
face of the express language of the RFQ and the LOI, evidence of
events leading to the LOI would be inadmissible
evidence and would be
hit by the parole evidence rule. It would avoid the evidence from
RAM’s witness, Walker,
who testified that he understood
that the covering email to the Statement, the Statement, the last
proposal, the LOI and the “acceptance”
of the nomination
on which RAM relies did not give rise to an agreement as contended
for. Walker was best placed to give the evidence
as he was directly
involved in the process with Craven.
[58]
Considering the express language of the RFQ and the LOI, the LOI is
explicit and clear that: “The
final
award shall be subject to the successful conclusion of the contract
accordingly.”
RAM’s
acceptance o
f
the terms of the RFQ, its
firm
offer in its last proposal, read with th
e
LOI
does
not admit any doubt that
,
a final award would come into effect on conclusion of a contract. In
these circumstances,
Pitout
and
Auckland
Park
do
not aid RAM’s case. As the court in
Capitec
Bank Holdings Ltd and Another v Coral Lagoon Investments 194(Pty) Ltd
and Others
[9]
clarified,
Auckland
Park
did
not jettison the need to have regard to the express language used by
the parties above context. The facts in
Pitout
are distinguishable from
the current facts because there, the court was seized with an
undertaking that was not memorialised in
writing.
[59]
The language employed in the RFQ inviting RAM to quote on the
distribution services, and the language employed in the
LOI,
accepting the proposal to render the distribution services, remain
the point of departure that the court must consider to
discern the
intention of the parties. T
he LOI served to
elect RAM as a party with whom DHL wished to negotiate and conclude a
binding service contract. Viewed in this
light, the pre-nomination
meetings and site visit held from 12 September and 30 November
2017
were no more than part of an initial
investigation to determine whether RAM was suitable for appointment
and as a party with whom
to negotiate a future contract. As th
e
trial evidence shows, the intention to conclude the contract
(referred to in the LOI), formed part of the project milestones,
monitored through the project implementation trackers circulated in
December, January and February and March.
[60]
Dealing with a tender, the Court in
Premier
of the Free State Provincial Government and others v Firechem Free
State (Pty) Ltd
[10]
citing
Christie
[11]
held that:
“
An
agreement that the parties will negotiate to conclude another
agreement is not enforceable, because of the absolute discretion
vested in the parties to agree or disagree”
The finding that there
was no enforceable agreement should be dispositive of RAM’s
case, but for the contention that the conclusion
of a contract was a
suspensive condition which DHL waived. The averment about the
existence of a condition presupposes that upon
DHL’s acceptance
of RAM’s last proposal (the true offer), a binding contract
operational
ab initio
came into effect. As I have already
found, the LOI merely appointed RAM as a party with whom it sought to
negotiate a contract.
[61]
Similarly, t
he
argument that the Court should import an implied or tacit terms on
the strength of the decision in
Desai
v Greyridge Investments (Pty) Ltd (Desai
[12]
)
is
equally misplaced. An existence of a contract is a prerequisite for
determining whether there is room to import an implied or
tacit
term.
[13]
[62]
If anything, the trial evidence concerning
disputes about (a) the applicable rates (b) the routes and mode of
delivery (c) the duration,
(d) termination and (e) the exclusivity
serves to confirm that the documents on which RAM relies did not
constitute a binding and
enforceable contract and lacked the material
terms which e
nabled the parties to know their rights or
performance obligations.
[63]
To the extent that there were other agreements which had not been
concluded, the decision by the court in
Kenilworth
Palace Investments (Pty) Ltd v Ingala
[14]
(Kenilworth)
has
some relevance and supports the conclusion that documents relied on
by RAM could not have acquired contractual force. T
he
evidence demonstrates
that the conclusion of the Technical or Quality Agreements
incorporating compliance requirements and Key Performance
Indicators
(KPI’s) which would apply to multiple principals, were central
to the Master Logistics Agreement (the MLA) and
a Service Level
Agreement (SLA) and the nature of the services required. DHL and RAM
spent several months negotiating the terms,
resulting in at least six
iterations of the MLA and SLA agreements and failed to agree or
display common intention about the terms.
[15]
[64]
RAM’s reliance on the doctrine of
quasi-mutual
assent was correctly
dismissed by the trial court. RAM would have been required to show
that there was a misrepresentation, identify
the person who made it,
in addition to showing that it was reasonably misled and that a
reasonable person who have been so misled.
[16]
The reliance on
quasi
mutual
assent
disregards the evidence of Walker (the sale executive) and Da Costa
(the General Legal Counsel). The inescapable evidence
is that RAM was
aware that the documents relied on lacked contractual force and when
it
commenced
the distribution services on 26 March 2018, Da Costa made it clear
that it would do so under RAM’s standard terms
until a binding
contract is concluded.
Conclusion
[65]
For the reasons stated above, RAM’s claim must fail, and the
appeal dismissed.
[66]
What remains is the question of costs. On 11 February 2025, I
directed the parties to prepare a Core Bundle to assist
the Appeal
Court, given the voluminous trial record running to forty two
volumes. The Appeal record was already uploaded and available
on Case
Lines. Instead, the full record was delivered despite the limited
request. At the hearing the parties were requested to
make written
submissions on who should bear the costs of the unnecessary
additional record. I have considered and accepted the
representations
by RAM’s attorneys.
[67]
The costs of the appeal which include the costs of the preparation of
the record must follow the result.
Accordingly,
I make the following order:
a. The appeal is
dismissed with costs.
b. The costs shall
include those consequent upon the employment of two counsel.
'
NTY
SIWENDU J
I
agree
A
MAIER-FRAWLEY J pp
I
agr
ee
L FLATELA J pp
This
Judgment is handed down electronically by circulation to the
Appellant’s Legal Representatives and the Respondent by
email,
publication on Case Lines. The date for the handing down is deemed 29
April 2025
Date
of appearance: 12 March 2025
Date
Judgment delivered: 29 April 2025
Appearances:
For
the Appellant: Advocate M Antoni SC
With
his Junior: Advocate A Berkowitz
Instructed
by: Werksmans Incorporated
For
the Respondent: Advocate JPP McNally SC
With
his Junior: Advocate J Heher
Instructed
by: Eversheds Sutherland Incorporated
[1]
1987(1)
SA 81 at 92 A-E
[2]
2013(2)
SA 133 SCA at para 12
[3]
Michael
v Caroline's Frozen Yoghurt Parlour (Pty) Ltd
1999
(1) SA 624
(W) at 634J to 635B
[4]
2021 (6) SA 1 (CC)
[5]
Although
not cited, in RAM’s heads, the approach is to be found in
Christie
Law
of Contract
4
th
Edition
page 39.
[6]
1977 (4) SA 842 (A)
[7]
R H
Christie, Law of Contract 4
th
Ed
,
page 33
[8]
2021 (6) 1 (CC) para 66
[9]
2022 (1) SA 100
(SCA), at para [51] states that: “Most
contracts, and particularly commercial contracts, are constructed
with a design
in mind, and their architects choose words and
concepts to give effect to that design. For this reason,
interpretation begins
with the text and its structure. They have a
gravitational pull that is important. The proposition that context
is everything
is not a licence to contend for meanings unmoored in
the text and its structure. Rather, context and purpose may be used
to elucidate
the text.”
[10]
[2000]
JOL 6603
(A) para 35
[11]
“
The
Law of Contract in SA
3ed
152 states that it is somewhat of a solecism to describe as a
conditional contract one in which the condition is purely
potestative (the
si
volam
of
Roman law), as such a provision is destructive of any enforceable
agreement. Nor does it matter if the provision is cast as
a term:
Christie (op cit) 109. The result is the same. Accordingly, if the
provision is potestative it does not matter for present
purposes
whether it is classified as a condition or a term. In either case
enforcement is dependent upon the will of both parties,
in this case
particularly the will of the province.”
[12]
Desai v
Greyridge Investments (Pty) Ltd
1974
(1) SA 509
(A) at 522-3; See
Consol
Ltd v Twee Jonge Gezellen (Ply) Ltd
2005
(6) SA 1
[13]
Alfred
McAlpine & Son (Pty) Lid v Transvaal Provincial Administration
1974 (3) SA 506 (A)
[14]
1984(2)
SA (C) 1, at para H page 12
[15]
Alfred
McAlpine
& Son (Pty) Ltd v Transvaal Provincial Administration
1974
(3) SA 506 (A)
[16]
Sonap
Petroleum (SA) (Pty) Ltd (formerly known as Sonarep (SA) (Pty) Ltd)
v Pappadogianis
1992 (3) SA 234 (A)
at 239J–240A.
sino noindex
make_database footer start
Similar Cases
Ram Transport (South Africa) Proprietary Limited t/a Ram Hand-to-Hand Couriers v DHL Supply Chain (South Africa) Proprietary Limited (20232/2020) [2024] ZAGPJHC 381 (17 April 2024)
[2024] ZAGPJHC 381High Court of South Africa (Gauteng Division, Johannesburg)100% similar
RAM Transport (South Africa) Proprietary Limited t/a RAM Hand -To-Hand Couriers v DHL Supply Chain (South Africa) Proprietary Limited (20232/2020) [2022] ZAGPJHC 802 (18 October 2022)
[2022] ZAGPJHC 802High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Ramaphakela v Municipal Employees Pension Fund and Another (40359/2016) [2024] ZAGPJHC 634 (14 June 2024)
[2024] ZAGPJHC 634High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Ramontja v Legal Aid South Africa (2021/44369) [2024] ZAGPJHC 1222 (26 November 2024)
[2024] ZAGPJHC 1222High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Ramotsoele and Others v Ramotsoele and Others (30681/2017) [2023] ZAGPJHC 1172 (17 October 2023)
[2023] ZAGPJHC 1172High Court of South Africa (Gauteng Division, Johannesburg)98% similar