Case Law[2025] ZAGPJHC 839South Africa
Group Five Construction (Pty) Ltd v Fikeni and Others (A2024/091672) [2025] ZAGPJHC 839 (22 August 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
22 August 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 839
|
Noteup
|
LawCite
sino index
## Group Five Construction (Pty) Ltd v Fikeni and Others (A2024/091672) [2025] ZAGPJHC 839 (22 August 2025)
Group Five Construction (Pty) Ltd v Fikeni and Others (A2024/091672) [2025] ZAGPJHC 839 (22 August 2025)
Download original files
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_839.html
sino date 22 August 2025
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
Case
Number: A2024-091672
(1)
REPORTABLE: /NO
(2)
OF INTEREST TO OTHER JUDGES: NO
In
the matter between:
GROUP
FIVE CONSTRUCTION (PTY) LTD
Applicant
(BUSINESS
IN RESCUE)
And
DR SOMADODA PATRICK
MAYIBONGWE FIKENI N.O. 1
st
Respondent
DR GCWALISILE CYNHIA
KABANYANE N.O.
2
nd
Respondent
MOROKA
ISAAC BUTCHER MATUTLE N.O.
3
rd
Respondent
ZANDILE
QUEENETTE LAVINIA MDHADHLANA N.O.
4
th
Respondent
MZAMO MICHAEL MLENGANA
N.O.
5
th
Respondent
MATSHIPSANA
MERIAM MOLALA N.O.
6
th
Respondent
TLHOTSE ENOCH
MOTSWALEDI N.O.
7
th
Respondent
NANDISELE FLAVOUR
THOKO MPULWANAN.O.
8
th
Respondent
PHELISA NKOMO
N.O.
9
th
Respondent
RASHID AMOD SADECK
PATEL N.O.
10
th
Respondent
ZAKHELE ALEX TUNNY
ZITHA N.O.
11
th
Respondent
LOMBARD INSURANCE
COMPANY LIMITED
12
th
Respondent
JUDGMENT
MOTHA
J:
Introduction
(1)
On 1 November 2013, Independent Development
Trust (IDT) and
Group Five entered into a
written JBCC building contract agreement for the construction of
Nelspruit High Court, in Mpumalanga.
Following a contractual dispute,
a judgment was handed down in favour of DTI, on 02 February 2024.
(2)
Dissatisfied with the results and having
been refused leave to appeal by the court of the first instance, the
appellant approached
the Supreme Court of Appeal (SCA) and was
granted leave to appeal to this court. Now, serving before this court
of appeal are two
issues, namely: the condonation application for the
appeal that is deemed to have lapsed, pursuant to the appellant’s
failure
to comply with rule 49(6)(a) of the Uniform Rules of court;
and the legal consequences of a final payment certificate in
construction
law.
Condonation
(3)
The first port of call is the question of
condonation. The appellant filed the notice of appeal on 15 August
2024;
ipso facto,
the
sixty-day period, as contemplated in rule 49(6)(a), expired on 10
November 2024. To obtain a trial date, the appellant was required
to
comply with Rules 7(2) and 49(6)(a), which read as follows:
“
7(2)
The registrar shall not
set down any appeal at the instance of an attorney unless such
attorney has filed with the registrar a power
of attorney authorising
him to appeal and such power of attorney shall be filed together with
the application for a date of hearing."
And
“
49(6)(a)
Within sixty days after
delivery of a notice of appeal, an appellant shall make written
application to the registrar of the division
were the appeal is to be
heard for a date for the hearing of such appeal and shall at the same
time furnish him with his full residential
address and the name and
address of every other party to the appeal and if the appellant fails
to do so a respondent may within
ten days after the expiry of the
said period of sixty days, as in the case of the appellant, apply for
the set down of the appeal
or cross-appeal which he may have noted.
If no such application is made by either party the appeal and
cross-appeal shall be deemed
to have lapsed: Provided that the
respondent shall have the right to apply for an order for his wasted
costs."
The failure to file
the Power of Attorney
(4)
On 11 October 2024, the Appellant's
attorneys applied for the allocation of an appeal date to the
registrar. Upon reviewing the
request, the registrar directed an
email to the Appellant, on 8 November 2024, stating the following:
“
Before
a date can be allocated the following have to be uploaded to the
Court Online file:
1- Notice of appeal
2- Power of
attorney
3- Security for
costs
4- Appeal record
5- Heads of
argument (of both sides)
6- Practice notes
(of both sides)
7- Application for
appeal date
8- Proof of service
of the above”
(5)
The appellant lodged the Power of Attorney
with the registrar on 10 February 2025, some three months after the
lapse of the appeal.
Subsequently, the appellant lodged an
application in terms of rule 27(3), which reads:
“
The
court may, on good cause shown, condone any non-compliance with these
rules.”
Good cause
submissions.
The appellant’s
counsel
(6)
Counsel for the appellant submitted that
the delay was caused by the appellant’s attorney who was not
familiar with the Uniform
Rules of Court, since she mainly dealt with
contractual law. In substantiating the reasons for the delay to lodge
the Power of
Attorney timeously and in terms of the rules, the
attorney stated that “after receiving the Registrar's directive
to file
the Power of Attorney on 8 November 2024, a Power of Attorney
was prepared for the Appellant's signature. A Power of Attorney was
prepared on 26 November 2024. An internal draft email attaching the
Power of Attorney was sent to me so that it could be forwarded
to the
Appellant for signature. I was erroneously of the email had been sent
directly to the Appellant, with me in copy. The error
was noted in
January 2025, and Power of Attorney was sent to the Appellant on 20
January 2025…”
(7)
Furthermore, it was stated that the
appellant is currently in Business Rescue. On 4 February 2025, the
Business Rescue Practitioners
of the Appellant called for a
Resolution so that the Power of Attorney could be signed.
The
Resolution and Power of Attorney were signed on 6 February 2025; the
Power of Attorney was filed with the registrar on 10 February
2025.
The respondent
(8)
The respondent submitted that they would be
prejudiced if the appeal was permitted to proceed. He asserted that
by the time the
appellant lodged the Power of Attorney on 10 February
2025, the appeal had, for all intents and purposes, lapsed. Thus, in
the
absence of a proper and timeous application having been made for
a date for the hearing of the appeal, the respondent submitted,
the
appeal was neither correctly set down for hearing by the registrar
nor properly placed on the roll. Accordingly, the appeal
and the
matter should be struck from the roll, he submitted.
Security for Costs
(9)
Security for costs is governed by Rule
49(13)(a) and (b) which provides as follows:
"(a) Unless the
respondent waives his or her right to security or the court in
granting leave to appeal or subsequently on
application to it, has
released the appellant wholly or partially from that obligation, the
appellant shall, before lodging copies
of the record on appeal with
the registrar, enter into good and sufficient security for the
respondent's costs of the appeal.
(b) In the event of
failure by the parties to agree on the amount of security, the
registrar shall fix the amount the appellant
shall enter into
security in the amount so fixed or such percentage thereof as the
court has determined, as the case may be."
(10)
On 28 November 2024, the appellant
dispatched a letter to the respondent, advising them of the directive
received from the Registrar
to lodge Security for Costs. In the
letter, the appellant undertook to lodge security in the sum of R120
000.00. On 3 December
2024, the respondent rejected this amount as
being insufficient as security for costs. On the same day, the
appellant indicated
that in their view the sum was sufficient and
would refer the matter to the registrar for a directive.
(11)
On 12 December 2024, the respondent
recommended that parties moved forward and requested guidance from
the Registrar or Taxing Master
regarding the adequacy of the security
for costs. Unfortunately, this was not done. Six months after the
lapse of the appeal, the
appellant dispatches a letter of security
undertaking dated 13 May 2025.
The law
(12)
It
is trite that condonation will not be had for the mere asking, and a
party that seeks it must give a full explanation for the
reasons for
the delay. In fact, it is an indulgence from the court. In the matter
of
Laerskool
Generaal Hendrik Schoeman v Bastian Financial Services (Pty) Ltd,
[1]
the court held:
“
As
this Court pointed out in Van Wyk v Unitas Hospital, “[a]n
applicant for condonation must give a full explanation for the
delay.
In addition, the explanation must cover the entire period of delay.
And, what is more, the explanation given must
be reasonable.”
As in Van Wyk (though the delay we focus on here is shorter), we
think that the attempt to explain the default
“falls far short
of these requirements.”
[2]
(13)
In In
Grootboom
v National Prosecuting Authority
2014
(2) SA 68
(CC) at paragraph [23] the following is stated:
“
It
is now trite that condonation cannot be had for the mere asking. A
party seeking condonation must make out a case entitling it
to the
court's indulgence. It must show sufficient cause. This requires a
party to give a full explanation for the non-compliance
with the
rules or court's directions. Of great significance, the explanation
must be reasonable enough to excuse the default.”
(14)
Examining
this issue and the role played by lawyers, the court in the matter
MEC
for Health Eastern Cape v A.S obo S.S,
[3]
said:
“
It
is trite that the high court has an inherent right to grant
condonation for a failure to comply with the rules of court where
the
interests of justice demand this. The discretion to do so is
extensive, but it must be exercised judicially. A party seeking
condonation must give a full explanation for the failure to comply
with the rules and this explanation must be reasonable. The
court
must weigh all relevant factors including, depending on the facts of
each case, the degree of non-compliance, the explanation
therefore,
the importance of the case, the avoidance of unnecessary delays in
the administration of justice and the prospects of
success. These
factors are interrelated and must be weighed one against the other.
For example, a slight delay and a good explanation
might compensate
for weak prospects of success. However, in a case of flagrant or
gross non-observance of the rules, a court may
refuse condonation
regardless of the prospects of success.
Where an attorney is to
blame for the non-compliance, a blameless litigant may escape
penalisation, but there is a limit beyond
which she or he may be
indemnified against the attorney’s lack of diligence and
absence of a reasonable explanation. The
negligence of the attorney
is weighed together with the other relevant factors in considering
whether condonation is justified.”
(15)
When
dealing with Rule 7(2), the court in
Aymac
CC v Windgerow
[4]
held:
“
The
application for a date of hearing is that referred to in rule
49(6)(a). The effect of these two rules is that, simultaneously
with
making written application to the registrar for a date for the
hearing of the appeal, the appellant’s attorney (if he
is
represented by one) shall file the power of attorney. Unless the
power of attorney is filed together with the application for
a date
of hearing, the appellant cannot be considered properly to have been
written application in terms of rule 49(6)(a).”
[5]
Analysis
(16)
Indeed, it is correct that the trial date
was obtained irregularly. By any computation, the appeal had lapsed
when the appellant
applied for a trial date in February 2025. The
appellant has not given a full explanation nor accounted for each
period of the
delay. For example, in the email dated 26 November 2024
the following is said: “The Registrar has requested a Power of
Attorney
on behalf of the Group Five Construction. Please see the
attached Special Power of Attorney for your perusal. If you are
happy,
please attend to sign same and send back to us.”
(17)
From the contents of this email, the
appellant seems oblivious to the urgency of the matter. As if that
was not enough, the email
dated 20 January 2025 stated: “Compliments
of the season and wishing you a prosperous new year. In order
to advance
the appeal, it is imperative that we deliver security. We
have not received any meaningful response to our offer from the
Respondents
and cannot afford to delay any longer, as this poses a
risk of our appeal lapsing. Under the circumstances, please proceed
to sign
the attached Special Power of Attorney. Additionally, kindly
ensure that Van Wijk Attorneys sign the guarantee so that we may file
it with the Registrar. Should the Respondents wish to contest the
amount or form of security, they may do so with the Registrar.
However, it is crucial that we provide security as soon as possible.”
(18)
As far back as 8 November 2024, the
registrar advised the appellant that the Power of Attorney was a
prerequisite for the allocation
of a trial date. When having regard
to the emails, the appellant was lackadaisical in handling this
matter. On 20 January 2025,
some two months after the deemed lapse,
the appellant does not display a sense of urgency and states that the
delay poses a risk
of the appeal lapsing, a bizarre statement since
the appeal had already lapsed in 2025.
(19)
Save to state that the attorney does not
practice in litigation and is contrite, and apologises for the
non-compliance with the
rules, the appellant does not offer any
explanation or shed light on the delay to file the Power of Attorney
before the end of
November 2024 nor is there any explanation
proffered about why the registrar’s requests were not adhered
to promptly. This
matter is of importance to both parties. We heard
the submission on the leaking court roofs and cracked walls on one
side, and
on the other, on the importance of the final payment
certificate. Both these issues are of paramount importance,
especially in
construction law. However, it would be a slippery slope
to bend rules for expediency. Without rules, chaos prevails.
(20)
As the matter currently stands, the issue
of security for costs remains unresolved. Counsel for the appellant’s
submission
that the attorney was blindsided by the respondent’s
(IDT’s) failure to reach an agreement on the adequate amount
for
security, and that the respondent must carry some of the blame is
untenable. As far back as December 2024, the respondent invited
the
appellant to approach the registrar for a directive. To date, the
appellant has not done that. To simply belatedly file R120 000.
00, fully aware that the respondent indicated that that amount is
insufficient security and nine (9) days before the hearing, flies
in
the face of rule 49(13)(b). Furthermore, there is absolutely no
explanation proffered about why the R120 000.00 was filed
on 13
May 2025. Whether one views this conduct as a series of
wrongs/mistakes, as submitted by counsel for the appellant, or as
a
fragrant disregard of rules, it is conduct that must neither be
condoned nor countenanced.
(21)
To me, it is baffling why the registrar
allocated the appellant a trial date in conflict with rule 49(6)(a).
As already mentioned
in a
Widgerow’s
case: “In the absence of a proper
making of an application for a date for the hearing of the appeal the
appeal is not properly
set down and should be struck off the role.”
Indeed, there is no appeal serving before this court. In the result,
the matter
stands to be struck off the roll with costs.
MP MOTHA
JUDGE OF THE COURT
GAUTENG LOCAL DIVISION
JOHANNESBURG
WINDELL J
(MAIER-FRAWLEY J CONCURRING):
(22)
The appeal centres on whether a final payment certificate
issued under a JBCC principal building agreement is enforceable
notwithstanding
that defects were identified by the principal agent
at the time of final completion, or whether IDT (the employer) was
entitled
to withhold payment pending rectification of those defects.
(23)
The appellant, Group Five Construction (Pty) Ltd (in business
rescue), seeks an order setting aside the dismissal of its
counter-application
and substituting it with an order directing the
first to eleventh respondents, the IDT, to pay the balance certified
as due in
the final payment certificate issued under the building
contract.
(24)
I have had the benefit of reading the judgment authored by my
colleague, Motha J (‘the first judgment’). The first
judgment
focuses exclusively on the preliminary objections raised by
the respondents and concludes that the appeal has lapsed and must be
struck from the roll. Although I am in agreement with my colleague’s
recitation of the factual background and the legal principles
applicable to condonation, I part ways with him in the result. In my
respectful view, the interests of justice require that condonation
be
granted, and that the merits of the appeal be considered.
(25)
It is common cause that the appellant filed its power of
attorney late, well outside the 60-day period stipulated in Rule
49(6)(a),
and that the finalisation of security for costs was also
delayed. IDT submit that these defects are fatal and the appeal must
be
regarded as having lapsed, and no proper application for set-down
was made.
(26)
The appellant applies for condonation for the non-compliance
with the Uniform Rules of Court and an order for the reinstatement of
the appeal in terms of Rule 49(6)(b). The appellant explains that the
delay arose from its attorney’s inexperience with appeal
procedure and from the internal processes of the business rescue
practitioners, which delayed execution of the necessary resolution
and signature of the power of attorney. Once the omission was
detected, corrective steps were taken and the document lodged. As
regards security, correspondence shows that the appellant offered an
amount, the respondent objected, and the matter could have
been
resolved by referral to the Registrar. The failure to pursue that
process was an error, not an act of bad faith.
(27)
The governing principles are settled: condonation is not had
for the mere asking, but the court must weigh the explanation, the
degree of non-compliance, the absence or presence of prejudice, the
importance of the matter, and the prospects of success (
Melane v
Santam Insurance
1962 (4) SA 531
(A);
Grootboom v National
Prosecuting Authority and Another
2014 (2) SA 68
(CC)).
(28)
I
agree with the first judgment that these are serious non-compliances
and that the appellant’s explanation is not perfect.
It
reflects unfamiliarity with appellate procedure and delays arising
from the internal approval processes of business rescue
practitioners. Nonetheless, the omission was eventually corrected,
and the delay was not wilful. Ignorance, inexperience,
and
naivete on the part of the attorney, explains to some extent the
attorney’s failure to keep to the procedural requirements
and
stipulated time periods contained in the rules regulating the
prosecution of appeals. The attorneys’ conduct should be
viewed
within the bounds of human fallacy. As the constitutional court put
it in
Vodacom
(Pty) Ltd v Makate and Another
[6]
:
‘Justice and, indeed, the court process are not about
perfection’.
(29)
Whilst it is correct that the attorney ought to have properly
acquainted herself in advance with the relevant rules, her bigger
mistake lay in the fact that she failed to appreciate the import of
the rules, more particularly, the consequences attached to the
non-compliance. Thus, even after the appeal had lapsed, she continued
to endeavour to take steps aimed at advancing the appeal
(as opposed
to sitting back and doing nothing and thereby hampering its
progress). Her prior experience lay mainly in conducting
construction
arbitrations, as opposed to litigation in general, including appeals.
(30)
Moreover, the respondents have suffered no tangible prejudice.
The full record is before Court, both parties filed heads of
argument,
and the appeal is ripe for determination.
(31)
On prospects, the appeal enjoys strong merit. The building
contract provides in express terms that “the employer shall pay
to the contractor the amount certified for payment in the final
payment certificate within twenty-one calendar days” of issue
(clause 34.10). It is common cause that payment certificate 72 was
the final payment certificate. The principal agent’s letter
and
the final completion certificate place any outstanding matters within
the latent-defects regime, not as a jurisdictional bar
to payment
under the final payment certificate. In these circumstances, the
interests of justice plainly favour the determination
of the merits.
Condonation for any delay in prosecuting the appeal is therefore
granted.
The
merits
(32)
The IDT appointed Group Five to construct the Mpumalanga High
Court. Lombard Insurance (the twelfth respondent) issued a
construction
guarantee in favour of the IDT for Group Five’s
performance. On 3 June 2021, the duly appointed principal agent
issued final
payment certificate no. 72 in the amount of
R14,498,020.71. This amount became due and payable to Group Five
within 21 days in
terms of clause 34.10 of the building contract.
(33)
On 31 August 2021, the principal agent issued a final
completion certificate, certifying final completion of the works as
at 11
August 2021. The accompanying letter recorded the existence of
latent defects but confirmed that final completion had been reached,
and that rectification of latent defects would occur in the defects
liability period.
(34)
The counter-application in the court a quo sought payment of
the outstanding balance due under the final payment certificate. The
court, however, held that the counter-application was bound to fail
because defects had been identified.
(35)
The
issuing of a final payment certificate is a contractual event with
significant legal consequences. As held in
Ocean
Diners (Pty) Ltd v Golden Hill Construction CC
,
[7]
an architect’s final certificate issued under a standard
building contract is conclusive and binding between the parties—save
for limited exceptions such as fraud—and cannot be cancelled,
withdrawn, or undermined by claims of error, negligence, or
public
policy. The employer is obliged to make payment in accordance with
its terms.
(36)
The IDT, represented by its trustees, argues that the
appellant’s case rests on a misreading of the JBCC contract and
of the
legal effect of the certificates. Their contentions are
threefold. Firstly, the defects liability periods. The contract
distinguishes
between (i) patent construction defects identified
during works completion, (ii) defects identified within the 90-day
defects liability
period, and (iii) latent defects manifesting within
10 years after final completion. It is submitted that the
waterproofing and
structural cracks identified by the principal agent
on 31 August 2021 were not latent defects, but patent defects already
known
before final completion. Group Five was thus obliged to rectify
them before it could demand payment and the court a quo correctly
held that IDT could withhold payment until these defects were
remedied and certified by the principal agent.
(37)
Secondly,
the nature of the liquid documents. The IDT argues that while a
payment certificate may ordinarily be liquid, it may be
subject to
fulfilment of a “simple condition” (
Rich
v Lagerwey;
[8]
Pepler v
Hirschberg
[9]
).
In this case, the principal agent simultaneously certified payment
and required remedial work to be completed. The certificate
was
therefore conditional upon rectification of defects. Until that was
done, Group Five could not demand immediate payment.
(38)
Lastly,
it raises the issue of reciprocity. The principle of reciprocity
applies in contracts of
locatio
conductio operis
.
A contractor cannot claim payment before completing its work (
BK
Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk
[10]
).
It is submitted that IDT’s obligation to pay is reciprocal to
Group Five’s obligation to deliver defect-free works.
Payment
may be withheld under the
exceptio
non adimpleti contractus
until the contractor has complied. It is contended that far from
creating a “stalemate,” the mechanism for resolving
the
issue lies in Group Five remedying the defects and requesting the
principal agent to issue a further certificate.
(39)
The competing contentions present a stark question: whether
clause 34.10 imposes an unconditional obligation on the employer to
pay once a final payment certificate is issued, or whether the
certificate in this case was subject to fulfilment of remedial
obligations
identified contemporaneously with the final completion
certificate.
(40)
The respondents are correct that the JBCC agreement recognises
multiple defects liability regimes. The letter of 31 August 2021
explicitly referred to waterproofing and potential structural cracks
as defects requiring attention. However, the decisive question
is
whether such defects suspended the employer’s obligation to pay
under clause 34.10.
(41)
On a proper reading of the contract, clause 34.10 embodies an
absolute payment obligation: once a final payment certificate is
issued,
the employer must pay within 21 days. Clause 27 separately
provides a remedial mechanism for defects, including patent defects
not rectified by final completion. That mechanism does not override
the clear stipulation of clause 34.10.
(42)
The respondents’ reliance on
Rich v Lagerwey
and
conditional liquidity is misplaced. The certificate issued here was
not expressly conditional: it quantified a fixed amount
due. The
principal agent’s covering letter placed ongoing obligations on
Group Five in relation to defects, but those obligations
were to be
pursued under the defects liability regime, not as a precondition to
payment.
(43)
As for reciprocity, the principle applies only where the
obligations are so closely linked that one is undertaken in exchange
for
the other. In building contracts under the JBCC, the mechanism of
certification was expressly chosen as the trigger for payment,
with
defects addressed through later remedial processes. To import a
reciprocal bar at this stage would be to re-write the contract.
(44)
The practical effect of the respondents’ case is to
allow an employer indefinitely to frustrate a certified payment. This
undermines the commercial function of payment certificates and is
inconsistent with the authorities treating them as liquid and
enforceable instruments.
(45)
The court a quo did not have regard to Clause 34.10 of the
building contract. As alluded to earlier, this clause expressly
provides
that payment certified in the final payment certificate must
be made within 21 days of certification. The employer’s remedy
in respect of latent defects lies in clause 27.1, which allows
enforcement of liability for latent defects within a ten-year period.
The existence of defects does not suspend the employer’s
obligation to pay the certified amount.
(46)
The court a quo regrettably conflated the final payment
certificate with the final completion certificate. They are distinct:
the
former embodies an enforceable monetary obligation, while the
latter is prima facie evidence of the sufficiency of the works. The
obligation to pay under the final payment certificate remains
unaffected by defects to be remedied during the latent defects
period.
(47)
The
effect of the court a quo’s approach is to permit an employer
indefinitely to frustrate payment under a valid certificate,
thereby
undermining both the contract and settled law, including
Joob
Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture
,
[11]
which held that such certificates are the equivalent of cash.
(48)
On a proper interpretation of the contract, IDT was bound to
make payment to Group Five of the amount certified in the final
payment
certificate within 21 days. Any dispute about latent defects
was to be addressed separately under the defects liability provisions
of the contract.
(49)
The court a quo erred in dismissing the counter-application
and in holding that the defects excused non-payment. That finding was
contrary to the contract, contrary to authority, and gave rise to
untenable commercial consequences, both in this case and more
broadly
for the construction industry.
(50)
In the result the following order is made:
1. Condonation is
granted in respect of all preliminary issues.
2. The appeal is
upheld with costs, including the costs of two counsel where so
employed.
3. Paragraph 2 of
the order of the court a quo is set aside and substituted with the
following:
“
2. The Second
Respondent’s (Group Five Construction (Pty) Ltd In business
rescue) counter application is granted with costs.
3. The first to eleventh
respondents in reconvention (IDT) is ordered to make
payment to the applicant,
Group Five Construction (Pty) Ltd In business rescue, in the amount
of R1 728 534.00.
4. Interest thereon
at the rate determined by the Minister of Finance from time to time
in terms of
section 80(1)
of the
Public Finance Management Act, 1999
,
from 24 June 2021 until date of payment in full.”
L WINDELL
JUDGE OF THE HIGH COURT
GAUTENG DIVISION,
JOHANNESBURG
I agree
A. MAIER FRAWLEY
JUDGE OF THE HIGH COURT
GAUTENG DIVISION,
JOHANNESBURG
Delivered: This judgment
was prepared and authored by the Judge whose name
is reflected and is
handed down electronically by circulation to the parties/their
legal representatives by
email and by uploading it to the electronic file of this
matter on Caselines.
The date for hand down is deemed to be 22 August 2025.
APPEARANCES:
Date
of Hearing:
22 May 2025
Date
of Judgment:
22 August 2025
ADV AV VOORMOLEN SC
Instructed by COX YEATS
ATTORNEYS
ADV SJ BEKKER SC
Instructed by SIKUNYANA
INCORPORATED ATTORNEYS
[1]
CCT
22/09)
[2009] ZACC 12
;
2009 (10) BCLR 1040
(CC) ;
2012 (2) SA 637
(CC) (7 May 2009)
[2]
Supra
para 15.
[3]
[2025]
ZASCA 2
(15 January 2025).
[4]
2009
(6) SA 433.
[5]
Supra
para
6.
[6]
[2025]
ZACC 13
para 43.
[7]
[1993] ZASCA 41
;
1993
(3) SA 331
(A).
[8]
1974
(4) SA 748 (A).
[9]
1920
CPD 438.
[10]
1979
(1) SA 391 (A).
[11]
2009
(5) SA 1
(SCA).
sino noindex
make_database footer start
Similar Cases
Group Five Construction Pty Ltd v Fikeni A.O. (43891/2019) [2024] ZAGPJHC 448 (7 May 2024)
[2024] ZAGPJHC 448High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Group Five Construction (Pty) Ltd v Constantia Insurance Company and Others (34068/2019) [2023] ZAGPJHC 233 (15 March 2023)
[2023] ZAGPJHC 233High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Groupair SA (Pty) Ltd v Rexus Trading (Pty) Ltd (015224/2024) [2024] ZAGPJHC 1156 (11 November 2024)
[2024] ZAGPJHC 1156High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Groupline Projects (Pty) Ltd and Another v Aviocean Global (Pty) Ltd and Another (Leave to Appeal ) (24139/2020) [2023] ZAGPJHC 1508 (18 September 2023)
[2023] ZAGPJHC 1508High Court of South Africa (Gauteng Division, Johannesburg)99% similar
PG Group (Pty) Ltd v Amoretti (7151/2021) [2023] ZAGPJHC 6 (9 January 2023)
[2023] ZAGPJHC 6High Court of South Africa (Gauteng Division, Johannesburg)99% similar