Case Law[2025] ZAGPJHC 875South Africa
Peikko South Africa Ltd v JCO Construction (Pty) Ltd (2023/057903) [2025] ZAGPJHC 875 (1 September 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
1 September 2025
Headnotes
Summary
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 875
|
Noteup
|
LawCite
sino index
## Peikko South Africa Ltd v JCO Construction (Pty) Ltd (2023/057903) [2025] ZAGPJHC 875 (1 September 2025)
Peikko South Africa Ltd v JCO Construction (Pty) Ltd (2023/057903) [2025] ZAGPJHC 875 (1 September 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_875.html
sino date 1 September 2025
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
Case
Number: 2023-057903
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
In
the matter between:
PEIKKO
SOUTH AFRICA LTD
Plaintiff
and
JCO
CONSTRUCTION (PTY) LTD
Defendant
JUDGMENT
N S KRÜGER AJ:
Summary
Summary
Judgment-
Rule
32(2)(b)
-
allowance of additional evidence- including documentary
evidence-Tumileng Trading CC v National Security and
Fire
(Pty) Ltd; E&D
Security Systems CC v National Security and Fire (Pty) Ltd
2020-(6) SA 624 (WCC)-
Absa
Bank Limited v Saunderson
2024 (4) SA 582
(NCK)
-
Special
plea for stay of proceedings and referral to arbitration in terms of
arbitration agreement in contract- Bona fide defence
remains to be
established as before with due regard to the effects of the amended
rule.
Introduction and
background
[1]
On or about 7 December 2021, a minor works
agreement framed as a Joint Building Contracts Committee Series 2000
was concluded between
the plaintiff and the defendant (“
the
contract
”). In terms of the
contract, the defendant employed the plaintiff to render construction
services at a specified site in
Randburg. A principal agent was
appointed with full authority to act in terms of the contract. He was
obliged, amongst others,
to administer the contract, monitor the
progress of the works and to render a payment certificate monthly,
certifying the amount
due by the defendant to the plaintiff or
vice
versa
as the case may be
.
The principal agent was also obliged to
issue completion certificates. The defendant was obliged to pay to
the plaintiff the amount
certified by the principal agent within
seven calendar days from the date of issue of the certificate.
[2]
According to the plaintiff a payment
certificate was issued by the principal agent for payment by the
defendant in the amount of
R 1 050 477,88 (“
the
amount
”) in respect of
construction work performed by the plaintiff. The defendant is
alleged to have failed to pay the amount.
The plaintiff issued
summons for payment of the amount together with interest
a
tempore morae
from date of demand, as
well as costs.
[3]
The contract contains an arbitration
agreement. The defendant raised a special plea that the court
proceedings be stayed and the
dispute referred to arbitration. In its
plea over, the defendant denies liability for payment of the amount
claimed. According
to the plea over, the payment certificate attached
to the particulars of claim was wrong and withdrawn by principal
agent on 22
September 2023. An amended payment certificate was issued
in its stead. In terms of the amended payment certificate, the
principal
agent certified the sum of R 879 403,82 to be due by
the plaintiff to the defendant. In a counterclaim, the defendant
claims
payment from the plaintiff in the sum of R879 403,82.
[4]
The plaintiff did not raise an exception to
any of the defendant’s pleadings. On 17 October 2023 the
plaintiff delivered an
application for summary judgment against the
defendant for payment of the amount, together with interest and
costs. Its plea to
the defendant’s counterclaim was delivered
on the same day. The plaintiff denies the principal agent issued an
amended payment
certificate. It further denies that the principal
agent is entitled to amend a payment certificate as the contract does
not empower
him to do so. The plaintiff also avers the amended
payment certificate attached to the defendant’s plea and
counterclaim
does not bear the signature of the principal agent.
[5]
In its affidavit supporting the application
for summary judgment, the plaintiff alleges it was terms of the
contract that the defendant
was supposed to commence with
construction on 7 October 2021, but delayed doing so by four months
in that the bulk earth works
and foundations were defective and
required repair. In addition, it is alleged the defendant did not
timeously arrange concrete
foundations for tower cranes which caused
delays. To substantiate its allegation that construction was supposed
to have begun on
7 October 2021, it relies upon a Nedbank payment
guarantee, a copy of which is annexed to the affidavit. None of these
were alleged
in its particulars of claim, nor in its plea to the
counterclaim (“
the additional
terms
”).
[6]
On 16 April 2025 the defendant filed a
notice of intention to amend its plea and counterclaim. The amended
pages were filed on 16
May 2025. Attached to the amended plea is the
same amended payment certificate attached to its initial pleadings,
now bearing a
signature which purports to be that of the principal
agent. It also contains allegations as to the basis upon which it is
alleged
the certificate relied upon by the plaintiff is wrong. It is
pleaded, amongst others, that the practical completion date of the
construction works to be rendered by the plaintiff was 28 July 2022,
which the plaintiff failed to do. No extension of time was
sought by
the plaintiff. The construction works was only completed on or about
29 November 2022. In the result, according to the
defendant,
practical completion of the construction works was delayed by 124
calendar days. In terms of the contract data to the
contract, it was
agreed that penalties for late completion of the works would be
calculated at R 13 873,35 per calendar day.
In consequence, so
the defendant alleges, penalties due by the plaintiff to the
defendant equals R 1 720 295,83 (“
the
penalties
”) as determined by the
principal agent. The principal agent applied the penalties to the
amount previously certified by him
due to the plaintiff. The amended
payment certificate was issued in terms of which the principal agent
certified R 878 403,82
to be due by the plaintiff to the
defendant.
[7]
The defendant filed its affidavit resisting
summary judgment on 29 May 2025. Therein defendant denies the
allegations made by the
plaintiff in its supporting affidavit are
true and correct. It contends the court should disregard the Nedbank
payment guarantee
annexed to the supporting affidavit as well as the
allegations pertaining to the defendant having delayed commencing
construction
due to the bulk earth works and foundations being
defective and requiring repair. The defendant confirms in detail the
allegations
pleaded in its amended plea and counterclaim pertaining
to the plaintiff’s failure to complete the construction work at
the
agreed time, not having obtained an extension, the project being
delayed by 124 days, contract data to the contract providing for
a
penalty of R 13 873,35 per calendar day and the principal agent
withdrawing his previous certificate and amending it. A
confirmatory
affidavit by the principal agent is annexed to the resisting
affidavit.
The parties’
pertinent arguments and submissions in summary
[8]
Regarding
the issue of arbitration the plaintiff contends there in fact is no
real dispute between the parties which would trigger
the arbitration
agreement. It is argued, with reference to
Parekh
v Shah Jehan Cinemas (Pty) Ltd and Others
[1]
that the object of arbitration is the resolution of disputes. For
arbitration to arise, a dispute must exist. The plaintiff’s
case is that the defendant has not set out any legal basis to impugn
the payment certificate upon which it relies for its claim
in that
the claim is not disputed in the sense there are competing
considerations. If such disputes are found to exist, the matter
would
be subject to arbitration in terms of the arbitration clause.
[9]
On behalf of the plaintiff it was argued
that the contract does not provide for the principal agent to
withdraw his certificate
as relied upon by the plaintiff in its
claim. Nor to amend it or issue a further certificate. In addition,
the delay alleged by
the defendant upon which its defence and the
counterclaim are based by virtue of the resultant penalties, was not
caused by the
plaintiff, but by the defendant. Further it is
contended the resisting affidavit lacks particularity and such facts
as are presented,
do not constitute a defence even if proved at
trial. It was also contended the amount claimed by the defendant in
its counterclaim
is illiquid in that the contract data to the
contract as alleged by the defendant is not before court. It was
submitted that the
defendant failed to explain the “
amended
payment certificate-10 and the annexures thereto.
”
In the result, the defendant’s version is bald, sketchy,
untenable and does not constitute a
bona
fide
defence.
[10]
On behalf of the defendant the argument was
that the plaintiff has not met the peremptory requirements of Rule
32(2)(b) for it to
place further evidence before court. Rule 32 does
not permit further evidence to be produced by way of the supporting
affidavit
or for the cause of action to be amplified. In consequence,
the additional terms alleged by the plaintiff and the Nedbank payment
guarantee should be disregarded.
[11]
The defendant contended the principal agent
was at liberty to issue a further certificate. It was pointed out
that the plaintiff
in its affidavit in support of summary judgment
accepted that the principal agent may issue a further certificate in
having alleged
“
Only the principal
agent was entitled to issue a further payment certificate…
”
[12]
In addition, in terms of the contract the
principal agent is entitled to adjust the net amount certified to
include, amongst others,
amounts due to the defendant or to the
plaintiff. In any event, so it is argued, it is not clear on what
grounds the plaintiff
alleges the principal agent was not entitled to
amend the initial certificate. Even if the principle agent was not so
entitled,
the plea and counterclaim discloses the plaintiff to be
indebted to the defendant in the liquidated amount of R 1 720 295,93
which is indicative of the defendant having a
bona
fide
defence.
Consideration
[13]
Since
the amendment of Rule 32,
[2]
an
affidavit in support of summary judgment is required, amongst others,
to identify any points of law relied upon and to briefly
explain why
the defence pleaded does not raise any issue for trial.
[3]
Plaintiff’s counsel referred the court to
Absa
Bank Limited v Saunderson
2024 (4) SA 582 (NCK)[4]
wherein Olivier AJ held, with particular regard to
Tumileng
,
[5]
that “…
in
view of the fact that more is expected of a Plaintiff in summary
judgment proceedings post-amendment, a more liberal approach
is
necessary in as far as the allowance of additional evidence is
concerned as long as the evidence that is provided by the plaintiff
serves only to support the contentions by the Plaintiff as to why the
defences raised by the Defendant, do not raise issues for
trial and
in the event of this evidence being documentary in nature, same is
attached to the supporting affidavit so that the Defendant
in the
matter is in a position to answer thereto.
”
[14]
In
Tumileng
Binns-Ward
J considered the amended rule 32(2)(b) “…
makes
sense only if the word ‘genuinely’ is read in before the
word ‘raise’ so that the pertinent phrase
reads ‘explain
briefly why the defence as pleaded does not genuinely raise any issue
for trial’
…
The
position would have been made clearer had the words ‘does not
make out a bona fide defence’ been used”
[6]
[15]
I find myself broadly aligned with these
judgments. In my view, the additional allegations and the Nedbank
payment guarantee should
not be disregarded in adjudicating whether
or not a
bona fide
defence
has been made out.
[16]
Much
of previous judgments relating to summary judgment remains
authoritative, but must be read and interpreted with due regard
to
the changes wrought by the amended rule. A court considering summary
judgment is not required to determine the substantive merits
of the
case before it. It should not become involved in determining disputes
of fact on the merits. A court is charged with adjudicating
whether a
defence as pleaded and set out in the affidavit resisting summary
judgment is not a sham, raised for purposes of delay.
[7]
[17]
An
opposing affidavit is required to fully set out the nature and
grounds upon the defence relied upon and the material facts in
support thereof. Such facts and evidence need not be exhaustively
particularised- it would be sufficient if the court is enabled
to
discern the existence of a
bona
fide
defence.
[8]
Having regard to the amended rule 32(2)(b), depending on a
plaintiff’s explanation why the defence does not raise any
issue
for trial, a defendant may be expected to engage with such
averments.
[9]
However, the test
to be applied remains whether or not a defendant has set out facts
that if proved at trial, will constitute a
valid defence against the
claim.
[10]
[18]
The
defendant is obliged only to disclose a genuine defence and not a
‘sham’. In 2023, the Supreme Court of Appeal confirmed
that what the prospects of success might be is irrelevant. Provided
the defence is legally cognisable “…
in
the sense that it amounts to a valid defence if proved at trial, then
an application for summary judgment must fail.
[11]
[19]
In
Liquor
Network Agency
[12]
a full court recently confirmed that in summary judgment proceedings
a defendant is not required to persuade the court of the correctness
of the facts alleged in its defence or, where the alleged facts are
disputed, there exists a preponderance of probabilities favouring
the
defence. Nor does a court need to endeavour weighing or deciding
disputed factual issues on a balance of probabilities. A court
“…
merely
considers whether the facts alleged constitutes a good defence in law
and whether that defence appears to be
bona
fide.”
[13]
[20]
In my view, the additional terms and the
Nedbank payment is not indicative of the absence of a
bona
fide
defence. The plaintiff appears not
to deny the construction works was not completed on the date
specified in the contract, namely
28 July 2022. Nor that no extension
for the date of completion was sought or granted by the principal
agent as provided for in
the contract. Regarding the contract data
which the defendant alleges is part of the contract and which
stipulates the extent of
the daily penalty for late completion, the
plaintiff’s complaint is that it is not on the papers before
me. Its existence
is not denied.
[21]
The crux of the plaintiff’s case is
that the reason for the delay is to be laid at the door of the
defendant. It frames the
additional terms and the Nedbank payment
guarantee as “…
material
express, alternatively tacit, further alternatively implied terms
…”
Considering the manner in which these allegations are set out,
they clearly were not terms of the contract:
a.
“
10.17 The applicant was supposed
to start the construction on the site on 7 October 2021 as per the
Nedbank payment guarantee issued
to the Applicant attached hereto
marked
Annexure “SJ2”
”
The date of the Nedbank
payment guarantee is 24 June 2022, long after the conclusion of the
contract. It follows it was not a term
of the contract.
b.
“
10.18 The Respondent delayed the
Applicant’s start date of construction by four months in that
the bulk earth works and foundations
were defective and required
repair. The Respondent’s concrete foundations had latent defect
s and hat
[sic]
to
be repaired.
”
“
10.19
Additionally, the Respondent did not timeously arrange concrete
foundations for the tower cranes which caused the delays.
”
“
10.20
Despite this, the Applicant duly complied with all of its obligations
in terms of the Agreement.
”
This all allegedly
occurred subsequent to the conclusion of the contract. They are not
terms of contract, but rather allegations
of facts which followed
upon the conclusion of the contract.
[22]
The additional allegations are denied by
the defendant in its affidavit, albeit not directly, but by way of a
general denial- the
defendant denies the allegations contained in the
plaintiff’s supporting affidavit are true and correct.
Nevertheless, the
version put up by the defendant in its plea and
counterclaim as well as its resisting affidavit directly contradicts
the plaintiff’s
version, in particular as regards the cause of
the delay in completing the construction works.
[23]
On
the one hand, a plaintiff’s right to relief ought not to be
frustrated by a defendant’s delaying strategy in contriving
a
defence. On the other hand, a court should be resistant to deprive a
defendant of his right to defend, unless the contrary in
indicated
when applying the tests referred to before. I take to heart the full
court’s view in
Liquor
that
a court must guard against injustice to a defendant who is called
upon without the benefit of further particulars, discovery
or cross
examination to satisfy it of the existence of a
bona
fide
defence.
[14]
[24]
It
is not clear to me upon what basis the plaintiff contends the
principal agent were not at liberty to have done as he did, save
upon
an interpretation of the contract as it stands. In
University
of Johannesburg v Auckland Park Theological Seminary and Another
[15]
the Constitutional Court confirmed that in interpreting a contract,
even in the absence of ambiguity, an expansive approach should
be
taken to the admissibility of evidence pertaining to the context in
which it is used and the purpose of a disputed term, though
extrinsic
evidence is not always permissible in terms of the rule against parol
evidence. The factual matrix of a contract is important
in
interpreting its terms. I do not propose to deal with University of
Johannesburg in any particularity. It is mentioned to illustrate
that
in interpreting a contract context may well need to be considered
upon presentation of extrinsic evidence.
[25]
In
Comwezi
Security Services (Pty) Ltd v Cape Empowerment Trust Limited
it
was held that the conduct of the parties in implementing their
contract may provide evidence as to how reasonable business people
construed a disputed term.
[16]
With
all this in mind, I am loathe venture into interpreting the contract
in the absence of the parties having had the benefit of
a full
ventilation of the context of the contract assisted by discovery,
possible viva voce evidence and the like.
In
any event, at the summary judgment stage, it is not the court’s
function to interpret disputed contractual terms.
[26]
On the papers before me it is apparent the
principal agent, who was appointed with full authority and with the
obligation to act
in terms of the contract, recanted on the
certificate issued by him and relied on by the plaintiff.
Conclusion
[27]
The principal agent’s change of heart
is significant in the context of the applicable requirements and
tests relating to the
consideration of an application for summary
judgment. In terms of the contract, amongst others, the principal
agent was seized
with administering and monitoring the progress of
the works, meeting regularly with the contractor to inspect and
facilitate the
progress of the works, recording all actions taken by
the parties including discussions held, progress of the works,
contract instructions
and decisions regarding delays and payment in
the contract minutes at the periods stated in the contract data. He
was obliged to
issue contract minutes to the parties for action. The
contract minutes were to be tabled for approval at the following
meeting.
To my mind, these are is indicative of the principal agent
having intimate knowledge of the works and its progress, as well as
delays, what caused it and what the parties decided in respect of it.
The issuing of an amended certificate favouring the defendant
lends
weight to the contention that the delays were the result of the
plaintiff’s conduct, rather than the defendant’s.
[28]
For these reasons, I find sufficient
particularity has been provided by the defendant to establish a
bona
fide
defence. I decline to grant
summary judgment. Having regard to all of the above, I grant an order
as set out below.
Order
1.
The application for summary judgment is
dismissed;
2.
The defendant is granted leave to defend;
3.
Costs are costs in the cause.
N. S. KRÜGER
NAME OF JUDGE
ACTING JUDGE OF THE
HIGH COURT
JOHANNESBURG
Electronically
submitted
Delivered:
This judgment was prepared and authored by the Acting Judge whose
name is reflected and is handed down electronically
by circulation to
the parties / their legal representatives by email and by uploading
it to the electronic file of this matter
on CaseLines. The date of
the judgment is deemed to be
1 September
2025
.
For
the plaintiff:
Adv R Pottas instructed by
Cavanagh & Richards Attorneys
For the defendant:
Adv
SN Davis instructed by Casper le Roux Incorporated
Date
of hearing:
12
June 2025
Date
of judgment:
1
September 2025
[1]
1980 (1) SA 302
(D&CLD) at 304E-G, per Didcott J
[2]
The amendments to rule 32 has been in effect since 1 July 2019
[3]
Rule 32(2)(b): “
The
plaintiff shall, in the affidavit…, verify the cause of
action and the amount, if any, claimed, and identify any point
of
law relied upon and the facts upon which the plaintiff’s claim
is based, and explain briefly why the defence as pleaded
does not
raise any issue for trial.
”
[4]
At
[37]. An application for leave to appeal was dismissed.
[5]
Tumileng
Trading CC v National Security and Fire
(Pty) Ltd; E&D
Security Systems CC v National Security and Fire (Pty) Ltd
2020
(6) SA 624
(WCC)
[6]
Tumileng
at
[21]
[7]
Tumileng
at
[23]
[8]
Maharaj
v Barclays National Bank Ltd
1976
(1) SA 418
(A) at 426A-E:
“
Where
the defence is based upon facts, in the sense that material facts
alleged by the plaintiff in his summons, or combined summons,
are
disputed or new facts are alleged constituting a defence, the Court
does not attempt to decide these issues or to determine
whether or
not there is a balance of probabilities in favour of the one party
or the other. All that the Court enquires into
is: (a) whether the
defendant has 'fully' disclosed the nature and ground of his defence
and the material facts upon which it
is founded, and (b) whether on
the facts so disclosed the defendant appears to have, as to either
the whole or part of the claim,
a defence which is both bona
fide and good in law. If satisfied on these matters the Court
must refuse summary judgment,
either wholly or in part, as the case
may be. The word 'fully', as used in the context of the Rule (and
its predecessors), has
been the cause of some Judicial controversy
in the past. It connotes, in my view, that, while the defendant need
not deal exhaustively
with the facts and the evidence relied upon to
substantiate them, he must at least disclose his defence and the
material facts
upon which it is based with sufficient particularity
and completeness to enable the Court to decide whether the affidavit
discloses
a bona fide defence . . .
"
[9]
Tumileng
[24]
[10]
Visser
and Another v Kotze
[2013]
JOL 29985
(SCA)
at [11]: “
As
already indicated, one of the ways in which a defendant can avoid
summary judgment, is to satisfy the Court by affidavit that
he or
she has a bona fide defence to the claim on which summary
judgment is being applied for. The word "satisfy"
does not
mean "prove". What the rule requires is that the defendant
must set out in his or her affidavit facts which,
if proved at the
trial, will constitute an answer to the plaintiff's claim.
”
[11]
Cohen
N.O and Others v Dean
[2023]
JOL 58657
(SCA) at [29]. The plaintiff in the supporting affidavit
had dealt with the defences raised in the plea, as required by the
amended
rule 32(2).
[12]
Liquor
Network Agency CC and Another v Skylim Beverages CC
2025 (2) SA 507 (GJ)
[13]
Liquor
at
[29]
[14]
Liquor
at [26]
[15]
See
also
Capitec
Bank Holdings Ltd and Another v Coral Lagoon Inv all actions taken
by theestments 194 (Pty) Ltd and Others
[2021]
3 All SA 647
(SCA)
[16]
[2012]
ZASCA para 15
sino noindex
make_database footer start
Similar Cases
N.P.K. v K.A.K (2020/15202; 2024/023432) [2025] ZAGPJHC 669 (11 July 2025)
[2025] ZAGPJHC 669High Court of South Africa (Gauteng Division, Johannesburg)98% similar
P.G.M. obo M.M. v Road Accident Fund (22670/2018) [2025] ZAGPJHC 469 (8 May 2025)
[2025] ZAGPJHC 469High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Paizes Attorneys Incorporated v Gorven (2023/058836) [2025] ZAGPJHC 868 (29 August 2025)
[2025] ZAGPJHC 868High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Poole N.O and Another v Stanger N.O (2024/064772) [2025] ZAGPJHC 898 (5 September 2025)
[2025] ZAGPJHC 898High Court of South Africa (Gauteng Division, Johannesburg)98% similar
P. v Housing Development Agency (21/50612) [2024] ZAGPJHC 234 (4 March 2024)
[2024] ZAGPJHC 234High Court of South Africa (Gauteng Division, Johannesburg)98% similar