begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 914
|
Noteup
|
LawCite
sino index
## Seletje Construction and Management CC v City of Ekurhuleni Metropolitan Municipality (2020/44579)
[2025] ZAGPJHC 914 (17 September 2025)
Seletje Construction and Management CC v City of Ekurhuleni Metropolitan Municipality (2020/44579)
[2025] ZAGPJHC 914 (17 September 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_914.html
sino date 17 September 2025
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
CASE
NO
:
2020-44579
DATE
:
17
September
2025
(1)
NOT
REPORTABLE
(2)
NOT
OF
INTREST TO OTHER JUDGES
In the matter between:
SELETJE
CONSTRUCTION & MANAGEMENT CC
Applicant
and
CITY
OF EKURHULENI METROPOLITAN MUNICIPALITY
Respondent
Neutral
Citation
:
Seletje Construction &
Management v City of Ekurhuleni Metropolitan Municipality
(2020-44579)
[2025] ZAGPJHC ---
(17 September 2025)
Coram:
Adams J
Heard
:
20 May 2025
Delivered:
17 September 2025 – This judgment was handed down
electronically by circulation to the parties' representatives by
email,
by being uploaded to
CaseLines
and by release to
SAFLII. The date and time for hand-down is deemed to be 11:30 on
17 September 2025.
Summary:
Arbitration –
Arbitration Act 42 of 1965
– arbitral award declaring cancellation of building contract
invalid and unlawful – cancellation set aside and specific
performance of contract by respondent directed by the Arbitrator –
application to have arbitral award made an order of court
in terms of
s 31(1)
of the
Arbitration Act – respondent
opposing
application on the basis that the contract terminated by the
effluxion of time – further grounds of opposition raised
in the
form of a counter-application, such as the fact that the respondent
was entitled to cancel the contract due to breach of
contract by the
applicant – further, respondent persisted with the defences
raised during the arbitration – claims
that the specific
performance orders of the Arbitrator should be varied or set aside in
terms of
s 31(2)
and
s 33
of the
Arbitration Act on
the basis that
the respondent breached the agreement – respondent contends
that the specific performance order is against
public policy –
Held
that arbitral awards are binding on parties and should be set aside
by a court only on very limited grounds – an arbitral
award
should, on application by any of the parties to the arbitration
proceedings, be made an Order of Court, unless valid grounds
exist on
which such an award falls to be set aside as provided for in
s 33
of
the
Arbitration Act –
by
agreeing to
arbitration, the parties had limited the grounds of interference in
their contract by the courts to the procedural
irregularities set out
in
s 33(1)
of the Act – they had waived the right to rely on
any further grounds of review, whether at common law or otherwise -
the
Act did not allow for review on the ground of material error of
law and that the general principle was that an irregularity related
to the conduct of the proceedings rather than to the merits –
Application granted and
counterapplication dismissed.
ORDER
(1)
The Arbitration Award dated 3 July 2021 by
the Arbitrator, Mr P F Rossouw SC, and handed down / published by him
on 1 September
2021, be and is hereby made an Order of this Court.
(2)
The respondent shall pay the applicant’s
costs of this opposed application, including the costs of Counsel on
scale ‘C’
of the applicable tariff provided for in the
Uniform Rules of Court.
(3)
The respondent’s application for
condonation be and is hereby dismissed with costs.
(4)
The respondent’s counter-application
be and is hereby dismissed with costs.
(5)
The respondent shall pay the applicant’s
costs of the opposed condonation application and the oppose
counter-application,
such costs to include the costs consequent upon
the utilisation of Counsel on scale ‘C’ of the applicable
tariff provided
for in the Uniform Rules of Court.
JUDGMENT
Adams J:
[1].
Some six years ago on 4 April 2019, the applicant (‘Seletje
Construction’) and the respondent (‘City
of Ekurhuleni’
or simply ‘the City’) concluded a written agreement for
the construction of the new Elandsfontein
/ Isando Fire Station in
Klopperpark, Germiston. The agreement was constituted by the JBCC
Principal Building Agreement, Edition
6.2 (‘the JBCC
Agreement’), the Contract Data and the ‘General
Preliminaries’, and was concluded pursuant
to and following a
duly compliant public procurement process. ‘JBCC’ is an
acronym for ‘Joint Building Contracts
Committee’ and the
Principal Building Agreement is a standard agreement published by the
said Committee in the interest of
‘… good practice, with
an equitable distribution of contractual risks’. The contract
price agreed upon was the
total sum of R40 585 831.64 and
the date for practical completion of the contract provided for was 17
January 2021.
[2].
Seletje Construction was given possession of the site on 19 March
2019, whereafter the works commenced. However, between
April 2019 and
March 2020 numerous disputes arose between the parties, culminating
in a purported cancelation by the City of Ekurhuleni
on 16 March
2020 of the agreement on the basis of alleged malperformance and
breach of contract by Seletje Construction. From
their side, Seletje
Construction complained of non-payment by the City of amounts due to
them as interim progress payments –
duly certified as due and
payable in terms of the contract. During March 2020, the works came
to a standstill.
[3].
During January 2021, in terms of the alternative dispute resolution
provisions of the agreement and an Order of this
Court (per Yacoob
J), the dispute between the parties were referred to arbitration.
Advocate P F Rossouw SC, Senior Council at
the Johannesburg Bar, was
duly appointed as arbitrator, by agreement between the parties, to
arbitrate the dispute.
[4].
On 1 September 2021, Advocate Rossouw, after the arbitration
proceedings had proceeded before him, published his award
dated 3
July 2021 (‘the arbitral award’) and directed as follows:
-
‘
(a) The City
of Ekurhuleni must make payment to [Seletje Construction] of the
following amounts:
(i) R467 877.01
(excluding VAT) in respect of payment certificate number 11;
(ii) R9 535.27 as
interest on the late payment of payment certificate number 1;
(iii) R32 637.19 as
interest on the late payment of payment certificate number 2;
(iv) R90 587.25 as
interest on the late payment of payment certificate number 10;
(v) R101 699.74
as interest on the outstanding payment of payment certificate number
11;
(b) It is declared
that [the City of Ekurhuleni] had no contractual basis or entitlement
to terminate the agreement concluded
between the parties on 4 April
2019 and the notice of termination dated 20 March 2020 is set aside;
(c) It is declared
that [Seletje Construction] may remain in possession of the
construction site of the new Klopperpark Fire
Station at 67 Welkom
Street, Klopperpark, Germiston, and that it may proceed with the
execution of the Works in terms of the agreement
concluded between
the parties on 4 April 2019;
(d) It is declared
that [Seletje Construction] is entitled to be compensated for work
done during February 2020 (and not covered
by payment certificate
number 11) and March 2020;
(e) The [City of
Ekurhuleni] must pay the costs of the arbitral proceedings,
including:
(i) the
arbitrator's fees;
(ii) the costs of
the venue of the hearing;
(iii) the costs of
recording the proceedings and the transcription;
(iv) [Seletje
Construction's] costs of reference, on the party and party High Court
scale, including the costs of Senior Council.’
[5].
The City of Ekurhuleni has complied with the payment requirements of
paragraphs (a) and (d) of the award and it has also
made payment of
the costs awarded against it in favour of Seletje Construction in
terms of paragraph (e) of the award. That means
that those portions
of the award by the Arbitrator have, for all intents and purposes,
been rendered moot, and I need not concern
myself any further with
those paragraphs of the award.
[6]. In this
opposed application, Seletje Construction applies
to
have the award of the Arbitrator made an order of this court
in
accordance with the provisions of
s 31(1)
of the
Arbitration Act 42
of 1965
.
In essence, what
Seletje Construction prays for is an order that they be permitted to
continue with the contract, which expired
during 2021, through no
fault on their part.
[7].
The City of Ekurhuleni
opposes the application and has somewhat belatedly instituted a
counter-application – supported by
a combined affidavit in
answer to Seletje’s application and the founding affidavit in
support of the counter-application
– for an order declaring
the
agreement entered into between the parties on 4 April 2019 to have
terminated through effluxion of time. In the alternative,
the City
applies for an order correcting – in terms of
s 31(2)
of the
Arbitration Act – paragraphs
60(b) and 60(c) of the arbitral
award. In effect what the City prays for in the alternative is an
order limiting paragraphs (b)
and (c) of the award to provide
specifically that the review and the setting aside of the
cancellation of the contract was based
solely on the basis of its
non-payment of amounts due in terms of the contract during March
2020. There are prayers for further
alternative relief by the City,
which I will deal with later in this judgment insofar as that may be
necessary. Suffice to state
at this stage that the City applies for
an order declaring that paragraph 60(c) of the Award cannot be
enforced ‘…
as, given the particular circumstances of
the matter and the constitutional and statutory obligations of [the
City of Ekurhuleni],
enforcement thereof is against public policy’.
[8].
Seletje Construction’s main application to have the arbitral
award made an Order of Court was delivered on or about
14 April 2022,
and the City of Ekurhuleni delivered notice of its intention to
oppose on or about 11 May 2022. The respondent’s
answering
affidavit was therefore required to be delivered in terms of the
Uniform Rules of Court within fifteen days from that
date, therefore
on or before 1 June 2022. The combined answering / founding affidavit
was delivered on or about 29 August 2022
– therefore, out of
time by some three months. Some of the relief sought by the City in
its counter-application, as will
become apparent later, was also
required to be brought within limited periods of time, which was not
complied with by the City
in its counter-application. All the same,
the City, as it was obliged to do, applies for condonation for the
late filing of its
application and for the late filing of its
answering affidavit. I deal with the application for condonation as
part of my decision
on the merits of the application and the
counter-application.
[9].
Therefore, the issue in this
application is simply whether, all things considered, Seletje
Construction is entitled to an order
for specific performance of the
agreement, notwithstanding the fact that, on first principles, the
agreement expired during January
or June 2021. This issue is to be
considered by me having regard to the trite principles relating to
arbitral awards in general
and those relating to the making of such
awards orders of court. Those principles are set out briefly in the
paragraphs which follow.
[10].
Section 28
of the
Arbitration Act provides
as follows: -
’
28
Award to be binding
Unless
the arbitration agreement provides otherwise, an award shall, subject
to the provisions of this Act, be final and not subject
to appeal and
each party to the reference shall abide by and comply with the award
in accordance with its terms.’
[11].
Section 31
provides thus: -
’
31
Award
may be made an order of court
(1) An award may,
on the application to a court of competent jurisdiction by any party
to the reference after due notice to
the other party or parties, be
made an order of court.
(2) The court to
which application is so made, may, before making the award an order
of court, correct in the award any clerical
mistake or any patent
error arising from any accidental slip or omission.
(3) An award which
has been made an order of court may be enforced in the same manner as
any judgment or order to the same
effect.’
[12].
As was held
by the Supreme Court of Appeal in
Telcordia
Technologies Inc v Telkom SA
Limited
[1]
,
arbitral awards are binding on parties and should be set aside by a
court only on very limited grounds. This implies, in my view,
that an
arbitral award should, on application by any of the parties to the
arbitration proceedings, be made an Order of Court,
unless valid
grounds exist on which such an award falls to be set aside as
provided for in
s 33
of the
Arbitration Act, which
reads as follows:
-
’
33
Setting
aside of award
(1) Where –
(a) any member of
an arbitration tribunal has misconducted himself in relation to his
duties as arbitrator or umpire; or
(b) an arbitration
tribunal has committed any gross irregularity in the conduct of the
arbitration proceedings or has exceeded
its powers; or
(c) an award has
been improperly obtained,
the court may, on the
application of any party to the reference after due notice to the
other party or parties, make an order setting
the award aside.
(2) An application
pursuant to this section shall be made within six weeks after the
publication of the award to the parties:
Provided that when the
setting aside of the award is requested on the grounds of the
commission of an offence referred to in
Part 1
to
4
, or
section 17
,
20
or
21
(in so far as it relates to the aforementioned offences) of
Chapter 2 of the
Prevention and Combating of Corrupt Activities Act,
2004
, such application shall be made within six weeks after the
discovery of that offence and in any case not later than three years
after the date on which the award was so published.
(3) The court may,
if it considers that the circumstances so require, stay enforcement
of the award pending its decision.
(4) If the award is
set aside the dispute shall, at the request of either party, be
submitted to a new arbitration tribunal
constituted in the manner
directed by the court.’
[13]. In
Telcordia
Technologies
the SCA explained the rationale behind the foregoing
principle as follows. By agreeing to arbitration, the parties had
limited
the grounds of interference in their contract by the courts
to the procedural irregularities set out in
s 33(1)
of the Act. By
necessary implication, they had waived the right to rely on any
further grounds of review, whether at common law
or otherwise. The
Court also held that the Act did not allow for review on the ground
of material error of law and that the general
principle was that an
irregularity related to the conduct of the proceedings rather than to
the merits. A qualification to
that general principle is that a
'gross irregularity' was committed where the decision-maker
misconceived the whole nature of the
enquiry, namely he misconceived
his mandate or his duties in connection therewith.
[14].
Importantly, it was held by the SCA that a wrong interpretation of an
agreement, for example, also did not entail the
arbitrator's
exceeding his powers. The power given to him was to, rightly or
wrongly, interpret the agreement; determine the applicable
law; and
determine what evidence was admissible. Errors of this kind had
nothing to do with his exceeding his powers but were errors
committed
by him within the scope of his mandate.
[15].
The question
in casu
is therefore whether the City of
Ekurhuleni is entitled to object to the arbitral award being made an
Order of Court on the basis
of the defences raised by it. Put another
way, do these grounds of opposition warrant a deviation from the
above general principle?
[16].
All of the foregoing issues in this matter are to be decided against
the factual backdrop. I deal with the facts in
paragraphs which
follow as and when I deal with a discussion and an analysis of the
matter.
[17].
As already indicated, the agreement was concluded between the parties
on 4 April 2019, Seletje Construction, as the
contractor, having been
given possession of the construction site before that on 19 March
2019. Between April 2019 and February
2020 numerous site meetings
were held at which the City and/or its agents complained consistently
as regards
inter alia
the slow progress made with the
contract, poor performance and workmanship on the part of Seletje
Construction and their failure
to rectify defects. This ultimately
resulted in a notice of termination of the agreement on 20 March 2020
from the City to Seletje,
which cancellation was subsequently
reviewed and set aside on 7 April 2020 by this Court, which also
directed that the disputes
between the parties be referred to
arbitration.
[18].
The arbitration proceedings commenced on 24 May 2021, were concluded
on 2 June 2021 and the arbitral award dated 3 July
2021, as detailed
supra
, was published on 1 September 2021.
[19].
Through its counter-application, the City of Ekurhuleni resists the
application by Seletje on the basis of the grounds
set out above. I
now proceed to deal in turn with those grounds of opposition.
[20].
Primarily, the City contends that the arbitral award should be set
aside because the agreement between the parties has
terminated
through the effluxion of time. As already indicated, the agreement
expressly made provision for the 17
th
of January 2021 as
‘the date for practical completion’. On 20 January 2020,
the contract term was extended by the City
to 30 June 2021 and the
agreement, so the City contends, thus terminated through effluxion of
time on 30 June 2021.
[21].
In terms of clause 23 of the agreement, Seletje is, however,
‘entitled to a revision of the date for practical
completion’
with an adjustment of the contract price in a number of
circumstances. One such circumstance provided for in
clause 23.2.13
is ‘Suspension of the works’. Importantly, clause 23.3
provides as follows:
‘
Further
circumstances for which [Seletje Construction] may be entitled to a
revision of the date for practical completion and an
adjustment of
the contract value are
delays to practical completion due to any
other cause beyond [Seletje’s] reasonable control that could
not have reasonably
been anticipated and provided for. The principal
agent shall adjust the contract value where such delay is due to [the
City of
Ekurhuleni] and/or its agents
’. (Emphasis
added).
[22].
In the alternative, the City applies for a declaratory order to the
effect that the contract has previously been validly
terminated,
alternatively had been terminated upon the launching of its
counter-application, consequent upon the anticipatory breach
(repudiation) of the contract by Seletje.
[23].
The first difficulty with this ground of opposition is the fact that
clause 23 of the agreement, referenced above, is
a complete reply to
the case by the City in that regard. The simple point is that, having
regard to the circumstances in the matter,
notably the protracted
disputes and litigation between the parties, Seletje is fully
entitled to apply for a revision of the date
for practical
completion. If nothing else, Seletje has the right to insist on a
revision of the practical completion date on the
basis that, at the
instance of the City, the Works were suspended during March 2020 –
approximately one year after the commencement
of the contract and
about one year before the date of practical completion.
[24].
Moreover, the case on behalf of Seletje – which is not
seriously disputed on behalf of the City – is that,
following
publication of the award, it attempted to resume performance in line
with prayer (c) of the Award, including a formal
request dated 10
November 2021. The City however failed to cooperate and filed a
notice to oppose enforcement, which amounts, in
my view, to an
unequivocal refusal to comply with the award. For this reason too,
the defence should fail. The City cannot benefit
from the very delay
it caused. It obstructed dispute resolution, unlawfully removed the
contractor from site, and refused to implement
the award. It cannot
now rely on the passage of time – which it engineered –
as a ground to argue that the contract
expired.
[25].
What is more is that this issue is an issue which would have been
before the Arbitrator when he adjudicated the dispute
relating to the
cancellation of the contract by the City. If it was not before him
explicitly, it certainly was before him by implication
in that by the
time the arbitration proceedings were concluded and the Arbitrator
scripted the Award in close proximity to the
date for practical
completion. He nevertheless directed specific performance of the
contract by the City of Ekurhuleni. Howsoever
one views this matter,
it has to be accepted that this issue raised on behalf of the City is
an issue which was before the Arbitrator
and was decided against the
City, who now desires to have that issue decided afresh as an appeal
under the guise of an order setting
aside the Arbitrator’s
Award.
[26].
There is
accordingly no merit in this ground of opposition. As was held by the
SCA in
Telcordia
Technologies
[2]
,
the parties had limited the grounds of interference in their contract
by the courts to the procedural irregularities set out in
s 33(1)
of
the Act. By necessary implication, they had waived the right to rely
on any further grounds of review, whether at common law
or otherwise.
In any event, if the City believes this issue to be a dispute between
them at this stage, then they are required,
in accordance with
Telcordia
Technologies
,
to refer this matter back to arbitration.
[27].
The City also contends that, even if this Court is of the view that
the agreement did not terminate on 30 June 2021
through effluxion of
time, its counter-application with its combined affidavit at the very
least served as reasonable notice to
Seletje of the termination of
the agreement for the reasons mentioned in the said affidavit. In
that regard, the City places reliance
on an expert report dated 22
July 2022, that is after the date on which the Arbitrator’s
award was published. This report
regurgitates the grievances
complained of by the City in its notice of termination of the
contract and which complaints were all
raised by them in the
arbitration. The Arbitrator rejected this defence and held that the
City was not justified in cancelling
the agreement.
[28].
The case on behalf of the City is that the agreement terminated
through the effluxion of time. Additionally, so the
contention
continues, the arbitrator erred by holding that ‘... [the City
of Ekurhuleni] relied on the wrong grounds for
the purported
termination of the agreement .... the Agreement was not validly
terminated. [The City] remains obliged to give [Seletje]
possession
of the site and the contractor may proceed with the works to bring it
to practical completion and eventually to final
completion’.
This, so the contention is concluded, also constitutes a patent error
by the arbitrator as provided for under
Section 31(2)
of the
Arbitration Act.
[29].
I do not accept this contention and I do so for the reasons already
alluded to above. In particular, the City is bound
by the findings of
the Arbitrator and it cannot apply for a review of the Award on the
basis that the Arbitrator made an error
of fact or law. The point,
which bears emphasis, is that even if the arbitrator had erred in
assuming the contract remained extant,
which in effect would amount
to an error of law or interpretation, it is not a gross irregularity
reviewable under
section 33(1)
of the
Arbitration Act. As
was held in
Telcordia Technologies
at para 86:
‘
[86] Likewise, it
is a fallacy to label a wrong interpretation of a contract, a wrong
perception or application of South African
law, or an incorrect
reliance on inadmissible evidence by the arbitrator as a
transgression of the limits of his power. The power
given to the
arbitrator was to interpret the agreement, rightly or wrongly; to
determine the applicable law, rightly or wrongly;
and to determine
what evidence was admissible, rightly or wrongly. Errors of the kind
mentioned have nothing to do with him exceeding
his powers; they are
errors committed within the scope of his mandate. To illustrate, an
arbitrator in a “normal” local
arbitration has to apply
South African law but if he errs in his understanding or application
of local law the parties have to
live with it. If such an error
amounted to a transgression of his powers it would mean that all
errors of law are reviewable, which
is absurd.’
[30].
This principle, in my view, finds application
in casu
.
[31].
Moreover, the reliance by the City of Ekurhuleni on the provisions of
s 31(2)
of the
Arbitration Act is
misplaced. By no stretch can
it be said with any conviction that the arbitral award contained a
‘clerical mistake or any
patent error arising from any
accidental slip or omission’, which require correction by this
Court. There most certainly
is no evidence before me in support of a
finding to that effect.
[32].
The aforegoing also apply to the other grounds of opposition raised
by the City, in particular its claim that the arbitral
Award should
be set aside on the basis that making the Award an Order of Court
would be significantly prejudicial and contrary
to public policy. The
City alleges that Seletje Construction has not only neglected to
comply with its obligations under the agreement
but is also clearly
incapable of complying with those obligations. Therefore, so the
contention goes, it would therefore be against
public policy to
compel the City to comply with its obligations in terms of the
agreement. The aforegoing is illustrated, so the
City contends,
through the expert evidence alluded to
supra
, which proves
that Seletje is incapable of performing its obligations in terms of
the agreement to render a fire station compliant
with the standards
and code of practice as referred to by the expert, Mr van Straten.
[33].
I reiterate that this defence has no merit. It is also an issue which
should be arbitrated as prescribed by the agreement,
as is the ground
of opposition raised by the City as an application for the purported
correction of prayers (b) and (c) of the
arbitral award in terms of
s
31(2)
of the
Arbitration Act, alternatively
that these prayers (b)
and (c) of the award be reviewed and set aside in accordance with the
provisions of
s 33(1)(b)
and (2) of the
Arbitration Act, with
the
period of six weeks to be extended in accordance with the provisions
of
s 38
of the
Arbitration Act to
date of service and filing of the
City’s counter-application.
[34].
I therefore conclude that the arbitration award issued on 1 September
2021 remains valid, final and binding. Seletje
Construction has
satisfied all the requirements of
section 31(1)
of the
Arbitration
Act for
enforcement. There is no merit in any of the grounds of
opposition raised by the City, whose opposition is, as submitted by
Seletje
Construction, nothing more than an appeal against the
findings of the Arbitrator disguised as a review. It fails to meet
the stringent
threshold for relief under
s 33(1)
, and its
application is both procedurally defective and substantively
unmeritorious.
[35].
Whilst it is so that there may have been compliance with certain
parts of the Award, such as the orders relating to
payment of
monetary sums, it is so, as contended on behalf of Seletje
Construction, that this does not prevent the Award from being
made an
Order of Court in terms of
s 31(1).
Compliance with one part of an
award does not extinguish the award itself. The
Arbitration Act does
not envisage a ‘partial enforcement’ process. The
Applicant is entitled to rely on the award as a whole and is not
required to isolate portions that may have been informally or
inadequately addressed.
[36].
Accordingly, Seletje
Construction’s application to have the Arbitrator’s award
made an Order of Court should be granted
and the counter-application
of the City of Ekurhuleni falls to be dismissed with costs. In view
of my findings relating to the
merits of the counter-application,
which imply that the counter-application had no reasonable prospects
of success, the City’s
condonation application should also be
dismissed.
Costs
[37].
The
general rule in matters of costs is that the successful party should
be given his costs, and this rule should not be departed
from except
where there are good grounds for doing so, such as misconduct on the
part of the successful party or other exceptional
circumstances. See:
Myers
v Abramson
[3]
.
[38].
I can think of no reason why I should deviate from
this general rule. The applicant should therefore be granted its
costs of its
main application, as well as the costs relating to the
respondent’s counter-application.
Order
[39].
In the result, I make the following order:
(1)
The Arbitration Award dated 3 July 2021 by
the Arbitrator, Mr P F Rossouw SC, and handed down / published by him
on 1 September
2021, be and is hereby made an Order of this Court.
(2)
The respondent shall pay the applicant’s
costs of this opposed application, including the costs of Counsel on
scale ‘C’
of the applicable tariff provided for in the
Uniform Rules of Court.
(3)
The respondent’s application for
condonation be and is hereby dismissed with costs.
(4)
The respondent’s counter-application
be and is hereby dismissed with costs.
(5)
The respondent shall pay the applicant’s
costs of the opposed condonation application and the oppose
counter-application,
such costs to include the costs consequent upon
the utilisation of Counsel on scale ‘C’ of the applicable
tariff provided
for in the Uniform Rules of Court.
L R ADAMS
Judge of the High
Court
Gauteng Division,
Johannesburg
HEARD ON:
20 May 2025
JUDGMENT DATE:
17
September 2025 –Judgment handed down electronically
FOR THE
APPLICANT:
D Thumbati
INSTRUCTED BY:
Ledwaba Zwai Attorney,
Pretoria
FOR
THE
RESPONDENT:
J
C Uys SC
INSTRUCTED
BY:
Klopper
Jonker Incorporated, New Redruth, Alberton
[1]
Telcordia
Technologies Inc v Telkom SA
Limited
2007 (3) SA 266 (SCA).
[2]
FN 1 supra.
[3]
Myers
v Abrahamson
1951(3)
SA 438 (C) at 455
sino noindex
make_database footer start