Case Law[2025] ZAGPJHC 1156South Africa
Royal Haskoningdhv (Pty) Ltd v Airports Company South Africa Soc Ltd and Another (2023/029979) [2025] ZAGPJHC 1156 (17 November 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
17 November 2025
Headnotes
the onus was on RHDHV, as the party invoking clause 3.9, to prove that it had submitted its claim within the six-week window. He found that RHDHV had failed to discharge this onus because Ms. Nabagala’s evidence did not provide a clear answer as to when RHDHV first became aware of the need for the claim.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 1156
|
Noteup
|
LawCite
sino index
## Royal Haskoningdhv (Pty) Ltd v Airports Company South Africa Soc Ltd and Another (2023/029979) [2025] ZAGPJHC 1156 (17 November 2025)
Royal Haskoningdhv (Pty) Ltd v Airports Company South Africa Soc Ltd and Another (2023/029979) [2025] ZAGPJHC 1156 (17 November 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_1156.html
sino date 17 November 2025
REPUBLIC OF SOUTH
AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA,
GAUTENG DIVISION,
JOHANNESBURG
CASE
NO: 2023-029979
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
17
November 2025
In
the matter between
ROYAL
HASKONINGDHV (PTY) LTD0
Applicant
And
AIRPORTS
COMPANY SOUTH AFRICA SOC LTD
First Respondent
BERNARD
MAKGABO NGOEPE (J) N.O
Second Respondent
JUDGMENT
Mdalana-Mayisela
J
Introduction
[1]
Before this court is an application to review and
set aside an arbitration award dated 2 March 2023 (“award”),
rendered
by the second respondent, retired Honorable Mr. Justice
Ngoepe (“the arbitrator”). The application is brought
under
section 33(1) of the Arbitration Act 42 of 1965 (“the
Arbitration Act&rdquo
;). The applicant, Royal HaskoningDHV (Pty) Ltd
(hereinafter referred to as “RHDHV”), was the claimant in
the arbitration,
and the first respondent, Airports Company South
Africa SOC Ltd (hereinafter referred to as “ACSA”), was
the defendant.
[2] The core of the
dispute in the arbitration was whether RHDHV was entitled to an
extension of time and an additional payment
of R2,165,019.84 for
professional services rendered in a construction project at OR Tambo
International Airport. The arbitrator
dismissed RHDHV’s claim.
Aggrieved by the arbitrator's award, RHDHV has approached this court
for an order reviewing and
setting aside the award on the ground of
gross irregularity. The arbitrator has filed a notice to abide by the
decision of this
court. The application is opposed by ACSA, which
filed an answering affidavit accompanied by a condonation application
for the
late filing thereof.
Background
[3] RHDHV concluded a
written contract with ACSA on or about 26 February 2016 for the
provision of certain specified services by
RHDHV to ACSA.
Essentially, RHDHV was appointed as a multi-disciplinary consulting
engineer to ACSA in respect of a project known
as “Additional
Baggage carousel in Terminal A, Arrivals project at OR Tambo
International Airport.
[4] The parties were
bound by a professional services contract based on the CIDB standard
form. A critical provision was clause
3.9, which entitled RHDHV to
apply for a change in the contract price or period of performance
upon the occurrence of certain events,
such as delays caused by ACSA
or others (clause 3.9.1). Crucially, clause 3.9.2 stipulated that any
such proposal had to be submitted
to ACSA within six weeks of
becoming aware of an event described in clause 3.9.1 occurring;
failing this, the right would be forfeited.
[5] On 28 November 2019,
RHDHV submitted its claim. ACSA rejected it. The contract provided
for the resolution of disputes arising
from the contract or its
interpretation through private arbitration, with the parties to agree
upon an arbitrator. In the event
of disagreement, the dispute would
be referred to an arbitrator appointed by the chairperson of the
Johannesburg Society of Advocates
(“Johannesburg Bar Council”).
The dispute between RHDHV and ACSA proceeded to arbitration. Retired
Justice Ngoepe
was appointed as arbitrator by agreement between the
parties.
The arbitral
proceedings and the award
[6] At the arbitration,
the parties exchanged pleadings in the form of a statement of claim
and a statement of defence. RHDHV's
statement of claim relied on
clause 3.9 but did not expressly plead the date on which it became
aware of the events triggering
its claim. ACSA’s statement of
defence included a special plea, pleading that the claim was
time-barred under clause 3. 9.2.
In paragraph 3.11 of its plea, ACSA
contended that even on the claimant's own version the expiry date was
31 December 2019 and
the claim of 28 November 2019 fell outside the
six-weeks period from that date, a contention that, on its face,
misapprehends the
clause, which runs from awareness of an event, not
from an expiry date.
[7] During the
arbitration, the evidence of RHDHV’s witness, Ms. Nabagala, was
that she became aware of the need for the claim
in November 2019,
upon receiving an email on 22 November, and submitted the claim on 28
November. Under cross-examination, she
was questioned about when she
became aware, but was not challenged on the basis that her awareness
may have arisen as early as
May 2019.
[8] ACSA’s witness,
Ms. Sisilana, testified that a key contractor had been appointed in
May 2019, from which she inferred
that RHDHV should have been aware
of delays at that time. This May 2019 date had not been mentioned in
the ACSA’s pleadings
or witnesses' statements. It was first
elicited by RHDHV's counsel during the cross-examination of Ms.
Sisilana.
[9] In paragraph 17 of
his award, the arbitrator made two crucial findings:
[9.1] The primary finding
(onus): he held that the onus was on RHDHV, as the party invoking
clause 3.9, to prove that it had submitted
its claim within the
six-week window. He found that RHDHV had failed to discharge this
onus because Ms. Nabagala’s evidence
did not provide a clear
answer as to when RHDHV first became aware of the need for the claim.
[9.2] The alternative
finding (
obiter dictum
): the arbitrator added, “
in
any case, even if the onus were on the defendant to show claimant’s
non-compliance with the demands of the clause, the
defendant
would have discharged it
.” He based this alternative
finding on the evidence of Ms. Sisilana regarding the May 2019 date,
which he found was based
on undisputed milestones.
[10] The parties did not
agree on an appeal prior to the commencement of the arbitration. The
effect of this was that the arbitrator's
award was final and binding
and could, in accordance with the provisions of the
Arbitration Act,
be
made an order of the court, unless reviewed and set aside in
accordance with
section 33
of the
Arbitration Act.
>
The parties’
contentions in the review
[11] RHDHV's case is that
the arbitrator committed a gross irregularity. It argues that the
arbitrator decided the case on a basis,
the May 2019 date, that was
not pleaded by ACSA, and upon which RHDHV's witness was never
cross-examined. This, it contends, constituted
a failure to afford it
a fair hearing and amounted to the arbitrator straying beyond the
issues defined by the pleadings, thus
exceeding his powers.
[12] ACSA’s defence
is twofold. First, it contends that the review is a disguised appeal.
It asserts that the award stands
on the unchallenged, primary finding
that RHDHV failed to discharge its onus. The comments regarding May
2019 were merely obiter
and irrelevant to the outcome. Second, ACSA
contends that even if the court finds for RHDHV on the time-bar
point, the arbitrator
made an independent finding that the RHDHV’s
claim letter did not comply with the substantive requirements of
clause 3.9.1,
which provides a separate and valid basis for the
award.
The legal framework
[13]
The test for review under
section 33(1)
of the
Arbitration Act is
narrow. As stated in
Telcordia
Technologies Inc v Telecom SA Ltd
[1]
,
a court does not sit as a Court of Appeal. An arbitrator has the
right to be wrong on the merits. The inquiry is into the conduct
of
the proceedings, not the result.
[14] A gross irregularity
occurs when an arbitrator fails to apply his mind to the issues,
conducts the proceedings in a manner
that is fundamentally unfair, or
exceeds his powers. A fundamental principle reiterated in
Hos+Med
Medical Aid Scheme v Thebe ya Pelo Healthcare and Others
is that
an arbitrator’s jurisdiction is determined by the parties’
pleadings. While evidence may supplement a pleaded
case, an
arbitrator cannot make an award on an issue not contemplated by the
pleadings, as this denies a party a fair opportunity
to address that
issue.
[15]
Furthermore, the right to a fair hearing includes the right to have a
version contradicting one's own put to one's witnesses,
as
encapsulated in the rule in
Browne
v Dunn.
[2]
Evaluation
[16] The central question
is whether the arbitrator's primary finding on the onus is sufficient
to sustain the award, insulating
it from review, regardless of any
irregularity in the alternative finding.
[17] I agree with ACSA
that the arbitrator was correct in his primary finding on the onus.
The legal principle is clear; a party
seeking to rely on a
contractual right must prove the fulfillment of any conditions
precedent to that right. Clause 3.9.2, with
its strict time bar, is
such a condition. RHDHV, as the claimant, bore the onus to allege and
prove that it submitted its claim
within six weeks of becoming aware
of a triggering event. Its failure to plead this date with
specificity and the perceived vagueness
in Ms. Nabagala’s
testimony provided a sustainable, rational basis for the arbitrator
to find that this onus was not discharged.
[18] This finding would
indeed be unassailable on review. An error in this finding would be
an error of law or fact, not a gross
irregularity.
[19] The primary finding
on who bore the onus has not been challenged. In fact, RHDHV accepted
its legal duty of discharging the
onus of proof on the disputed
issue. It only sought to challenge the alternative finding that
followed in paragraph 17 of the award
after the main finding had been
made. The alternative finding based on the May 2019 date was an
obiter dictum
. It was not an integral part of his
justification for rejecting the claim. The obiter dictum was of
no legal consequence
to the award and did not alter the outcome.
[20] The primary finding
by the arbitrator remains intact even in the absence of the obiter.
The obiter’s presence is superfluous
to the issue already
determined by the arbitrator. There is no gross irregularity
committed by the arbitrator, and the application
should fail on this
basis.
[21] The same applies to
the allegation that the arbitrator has curtailed the
cross-examination of ACSA’s witness by counsel
for RHDHV on the
evidence of Ms Sisilana about the May 2019 date. The record does not
establish such curtailment. However, this
was a non-issue because it
did not find expression in the primary finding, which is not the
subject of a challenge in this court.
It becomes unnecessary to deal
with ACSA’s alternative defence on the status of the letter of
28 November 2019.
Condonation
[22] ACSA sought
condonation for the late filing of its answering affidavit. I am
satisfied that ACSA has made out a proper case
for the court to
condone the late filing of the answering affidavit. Among the factors
I considered was the importance of the matter
to the parties and
finality in litigation, so that certainty is achieved by both
parties. I also considered that RHDHV was not
substantially
prejudiced by the delay. Also, the application for condonation was
not vigorously opposed on substantive grounds.
Accordingly,
condonation is granted with no order as to costs.
Costs
[23] Regarding the main
application, I see no reason why costs should not follow the event.
ACSA has shown substantial success in
opposing the review
application, and it should thus be entitled to the costs of the
application.
ORDER
[24] In the premises, the
following order is made:
1. The first respondent's
application for condonation for the late filing of its answering
affidavit is granted.
2. The application to
review and set aside the arbitration award is dismissed with costs
inclusive of counsel’s costs on scale
C.
MMP
Mdalana-Mayisela
Judge
of the High Court
Gauteng
Division
Digitally
delivered by uploading to Caselines and emailing to the parties.
Date
of hearing:
31 July 2025
Date
of delivery:
17 November 2025
Appearances:
For
the applicant:
Adv A Govender SC
Instructed
by:
Mortimer Govender Attorneys
For
the first respondent:
Adv L Sisilana
Instructed
by:
Mncedisi Ndlovu & Sedumedi Attorneys
[1]
[2006] ZASCA 112
;
2007
(3) SA 266
SCA.
[2]
(1893)
6 R. 67 (H.L).
sino noindex
make_database footer start
Similar Cases
Royal Trading Enterprise (Pty) Ltd and Others v Phezulu Ilanga Vending (Pty) Ltd and Others (2025/183282) [2025] ZAGPJHC 1024 (13 October 2025)
[2025] ZAGPJHC 1024High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Kingdom of Lesotho v Frazer Solar GMBH and Others (2020/33700) [2023] ZAGPJHC 1486 (31 August 2023)
[2023] ZAGPJHC 1486High Court of South Africa (Gauteng Division, Johannesburg)99% similar
King Civil Contractors (PTY) Ltd v Enviroserv Waste Management (PTY) Ltd (45747/2021) [2022] ZAGPJHC 467 (13 July 2022)
[2022] ZAGPJHC 467High Court of South Africa (Gauteng Division, Johannesburg)99% similar
King of the Road Transport and Others v Minister of Police and Others (22254/2022) [2022] ZAGPJHC 996 (7 December 2022)
[2022] ZAGPJHC 996High Court of South Africa (Gauteng Division, Johannesburg)99% similar
King Prince Insurance Company Limited v Matuba Transport and Logistics CC (A050244/2023) [2025] ZAGPJHC 866 (31 July 2025)
[2025] ZAGPJHC 866High Court of South Africa (Gauteng Division, Johannesburg)99% similar