Case Law[2024] ZAGPJHC 13South Africa
SMBT (Proprietary) Limited v Hollard Insurance Company Limited and Others (2022-022086) [2024] ZAGPJHC 13 (12 January 2024)
Headnotes
Summary: Contract – specific contracts – Variable Construction Guarantee and Performance Guarantee – compliance – guarantee in question – consisting, as it did, of an undertaking to make payment of amounts of money in the event of default by the main debtor – autonomous in nature – it must be paid according to its terms – guarantor claiming that guarantee had expired and was therefore no longer valid –
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 13
|
Noteup
|
LawCite
sino index
## SMBT (Proprietary) Limited v Hollard Insurance Company Limited and Others (2022-022086) [2024] ZAGPJHC 13 (12 January 2024)
SMBT (Proprietary) Limited v Hollard Insurance Company Limited and Others (2022-022086) [2024] ZAGPJHC 13 (12 January 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_13.html
sino date 12 January 2024
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT
OF SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
CASE
NO
:
2022-022086
DATE
:
12
th
January 2024
(1)
NOT
REPORTABLE
(2)
NOT
OF INTEREST TO OTHER JUDGES
In
the matter between:
SMBT
(PROPRIETARY)
LIMITED
Applicant
And
HOLLARD
INSURANCE COMPANY LIMITED
First Respondent
CAPE
ISLAND CONSTRUCTION (PTY) LIMITED
Second Respondent
CAPE
ISLAND CONSTRUCTION (PTY) LIMITED
First Third Party
ABLE
,
CAMERON
WARD
Second Third Party
RIMBAULT
,
JOHN
MURRAY
Third Third Party
WIGG
,
CLINTON ST
JOHN
Fourth Third Party
HODGES
,
GREGORY
BRIAN
Fifth Third Party
Neutral Citation
:
SMBT v Hollard Insurance and Others (2022/022086)
[2024]
ZAGPJHC ---
(12 January 2024)
Coram:
Adams J
Heard on
:
02 August 2023
Delivered:
12 January 2024 – This judgment was handed down
electronically by circulation to the parties' representatives by
email, by
being uploaded to
CaseLines
and by release to
SAFLII. The date and time for hand-down is deemed to be 11:00 on 12
January 2024.
Summary:
Contract – specific contracts –
Variable Construction Guarantee and Performance Guarantee –
compliance –
guarantee in question – consisting, as it
did, of an undertaking to make payment of amounts of money in the
event of default
by the main debtor – autonomous in nature –
it must be paid according to its terms – guarantor claiming
that
guarantee had expired and was therefore no longer valid –
Expiration of guarantee –
interpretation of contracts – proper interpretation of the
guarantee must be performed by
applying established principles –
Endumeni Municipality
and
Coral Lagoon
cases –
interpretation to be based on the ‘triad of text, context and
purpose’ – the ‘ordinary’
or ‘literal’
meaning of a contractual provision may be departed from if it would
be clearly contrary to the actual
intention of the parties – or
in order to avoid some absurdity or some repugnance or inconsistency
with the rest of the contract
– interpretation of contract
should not lead to an absurd and an unbusinesslike result –
Expiration defence raised
by respondents rejected as bad in law – judgment granted in
favour of the applicant.
ORDER
(1)
It is declared that
Variable
Construction Guarantee
number
PS GUA 3692312 dated 13 April 2015 issued by the first
respondent in favour of the applicant has not expired.
(2)
Judgment is granted in favour of the
applicant against the first respondent for: -
(a)
Payment to the applicant of the sum of
R855 911.74.
(b)
Payment of interest on the aforesaid sum of
R855 911.74 at the applicable legal interest rate of 7,75% per
annum from 09 June
2022 (being the date of first demand) to date of
final payment.
(3)
The first and the second respondents,
jointly and severally, the one paying the other to be absolved, shall
pay the applicant’s
costs of this opposed application.
(4)
Judgment is granted in favour of the first
respondent against the first to the fifth third parties, jointly and
severally, the one
paying the other to be absolved, for: -
(a)
Payment to the first respondent of the sum
of R855 911.74.
(b)
Payment of interest on the aforesaid sum of
R855 911.74 at the applicable legal interest rate of 7,75% per
annum from 09 June
2022 (being the date of first demand) to date of
final payment.
(c)
Payment of the costs payable by the first
respondent to the applicant as per prayer (3) above.
(d)
Payment of the first respondent’s
costs of the Third Party proceedings.
JUDGMENT
Adams J:
[1].
The applicant
(SMBT) is the registered owner of immovable property in Kloof Road,
Clifton, Cape Town (‘the property’).
On 20 March 2015,
SMBT as ‘Employer’ concluded a written agreement (the
Building Agreement) with the second respondent
(CIC), which is also
the first third party, as ‘Contractor’, pursuant to which
CIC would build a new dwelling on the
property (‘the works’)
for the contract price of R42 795 598. The ‘Principal
Agent’ of SMBT in
terms of the Building Agreement was SBDS
Quantity Surveyors, Western Cape (‘the Principal Agent’).
[2].
As it was
obliged to do in terms of the building contract, CIC on 13 April 2015
caused to be issued by the first respondent (Hollard)
a ‘Variable
Construction Guarantee’ in favour of SMBT (‘the
guarantee’). On 9 June 2022, SMBT demanded
payment of the
amount of R855 911.74 from Hollard under the guarantee. On 14
June 2022, Hollard repudiated SMBT’s demand
on the basis that
the guarantee had expired, which is disputed by SMBT, which contends
that, on a proper interpretation of the
guarantee, the guarantee had
not expired by the time demand was made and Hollard is therefore
obligated to pay the amount demanded.
[3].
In these
proceedings, which came before me on 9 November 2023 as a Special
Motion, SMBT applies for an order declaring that the
guarantee has
not expired and for judgment in its favour against Hollard for
payment of R855 911.74, together with interest
and costs. It is
common cause between the parties that the dispute between SMBT and
Hollard turns solely on the proper interpretation
of the guarantee,
which is a matter for this Court to determine based on the wording
and purpose of the Guarantee, in the light
of the context provided by
the Building Agreement.
[4].
A Third Party
Notice has also been issued by Hollard against CIC (as first third
party) as well as against CIC’s sureties,
being the second to
the fifth third parties (collectively, ‘the third parties’),
in which Hollard seeks to hold the
third parties liable, jointly and
severally, to make payment to it of the full principal amount,
together with interest, in the
event of this Court granting judgment
against it in favour of SMBT. The third parties have adopted
the legal contentions
raised by Hollard in its answering affidavit
against the relief sought by SMBT but have indicated that they will
otherwise abide
the decision of this Court.
[5].
Accordingly,
the only issue which I am required to consider in this matter is
whether, by the time SMBT made demand in terms of
the guarantee, same
had expired. If so, the application falls to be dismissed. This issue
is to be considered in light of the provisions
of the guarantee,
clause 3 of which makes it abundantly clear that it creates neither
an accessory obligation nor a suretyship.
Instead, the
Guarantee imposes a primary obligation on Hollard to pay money, which
is independent of the underlying Building Agreement
[1]
.
The purpose of the guarantee is to protect SMBT in the event of
default by CIC and thus it is to the guarantee that one
should look
to determine the rights and obligations of SMBT and Hollard –
‘the autonomy principle’.
[6].
The
proper interpretation of the guarantee must be performed by applying
the established principles articulated in
Natal
Joint Municipal Pension Fund v Endumeni Municipality
[2]
and
Capitec
Bank Holdings Ltd and Another v Coral Lagoon Investments 194 (Pty)
Ltd
[3]
based on the ‘triad of text, context and purpose’. Thus,
as correctly submitted by Mr Price, Counsel for the applicant,
while
the guarantee establishes a primary obligation on Hollard that is
autonomous from (and thus not accessory to) the distinct
primary
obligations imposed by the Building Agreement on CIC, the Building
Agreement nonetheless remains part of the relevant context
in the
interpretation of the guarantee.
[7].
A convenient
starting point in the interpretative process is the Building
Agreement and its key provisions, which are the following.
[8].
In terms of
clause 26, the Principal Agent shall issue a ‘certificate of
final completion’ once the works have reached
‘final
completion’ as defined, that is when the works are ‘free
of all defects as certified by the principal
agent’ (the final
completion certificate).
[9].
Clause 34, in
relevant part, provides that: (a) The principal agent shall issue the
final account to the contractor within ninety
working days of the
date of practical completion (clause 34.1); and (b) Should the
contractor not object with reasons to the final
account within
forty-five working days of receipt thereof, the principal agent shall
issue the final payment certificate (clause
34.5).
[10].
Importantly,
clause 34.5, with reference to ‘the final payment certificate’,
reads as follows:
‘
The
principal agent shall issue the final payment certificate within
seven calendar days to the contractor. Notwithstanding the
foregoing
such final payment certificate shall not be issued before the issue
of the certificate of final completion other than
where termination
occurs’
[11].
From the
aforegoing, it is clear that the final payment certificate could
never be issued prior to the issue of the final completion
certificate. In terms of clause 34.14, where the final payment
certificate reflects an amount in favour of the employer, the
contractor
shall pay the amount certified within twenty-one calendar
days of the date of issue of the final payment certificate.
[12].
What is
envisaged in the aforegoing provisions in fact occurred in that on
5 May 2022 the Principal Agent issued the final
completion
certificate. The very next day, being 6 May 2022, the Principal
Agent issued the final payment certificate pursuant
to clauses 31.1
and 34, certifying that CIC owed SMBT R2 130 687.49 (the
certified amount). This then means that CIC was obliged,
in terms of
clause 34.13, to pay SMBT the certified amount within twenty-one
calendar days, namely on or before 27 May 2022. CIC
failed to do so.
[13].
On 1 June
2022, SMBT’s attorneys wrote to CIC demanding that it pays SMBT
the certified amount within seven calendar days
of receipt of the
demand, failing which SMBT intended to call upon Hollard, as
guarantor, to make payment in terms of the guarantee
(the contractor
demand). Again, CIC failed to do so.
[14].
That then
brings me to the Guarantee, the key provisions of which are as
follows: The ‘Guaranteed Sum’ was stated to
be a maximum
aggregate amount of R4 279 558.69, and the form of the
Construction Guarantee was to be ‘variable’.
Importantly,
the ‘Guarantee Expiry Date’ is defined as ‘On Issue
of Final Completion Certificate’, which
definition, needless to
say, Hollard places much store on.
[15].
Clause 1 of
the guarantee, which is applicable and relevant
in
casu
,
provides that Hollard’s liability under the Guarantee ‘shall
be limited to the diminishing amounts of the Guaranteed
Sum’ in
four increments, according to a timeline of four distinct periods.
The effect of this provision is that R855 911.74
is provided for
as the guaranteed sum, as being for the period ‘[f]rom and
including the day after the date of the applicable
final completion
certificate and up to and including the date of the final payment
certificate where payment is due to the Contractor,
whereupon this
Construction Guarantee shall expire. Where the final payment
certificate reflects payment due to the Employer, this
Construction
Guarantee shall expire upon payment of the full amount certified.’
(Clause 1.1.4)
[16].
Importantly,
clause 1.2 provides that:
‘
For
avoidance of doubt the Guarantor’s liability limits set out in
[clause] 1.1.1 to 1.1.4 shall apply in respect of any claim
received
by the Guarantor during the period in question’.
[17].
On my reading
of these provisions, this then clearly means that the guarantee was
to expire only upon payment of the full amount
certified. That is so
for the simple reason that the final payment certificate certified
that CIC owed SMBT the certified amount.
It expressly follows that
‘the Construction Guarantee shall expire upon payment of the
full amount certified’. Moreover,
SMBT demanded payment from
Hollard under the Guarantee on or about 9 June 2022. Thus, in
accordance with clause 1.2, SMBT’s
claim was received by
Hollard ‘during the period’ contemplated by clause 1.1.4,
being the period starting on 6 May
2022 (that is ‘the day after
the date of the applicable final completion certificate’) and
ending ‘upon payment
of the full amount certified’ (which
has yet to occur).
[18].
The guarantee
provision of the Variable Construction Guarantee provides that,
subject to the Guarantor’s maximum liability
referred to
supra
,
the Guarantor undertook to pay SMBT the sum certified upon receipt of
the identified documents, which requirement SMBT complied
with in
their demand to Hollard. All of the other conditions were also
complied with by SMBT.
[19].
As already
indicated, despite demand by SMBT to Hollard for payment in terms of
the guarantee, Hollard refused to make such payment
on the basis
that, in its view, the Guarantee had expired on 5 May 2022, being the
date of issue of the final completion certificate.
In that regard,
Hollard relies, almost exclusively on its interpretation of the
definition of ‘Guarantee Expiry Date’
as ‘On Issue
of Final Completion Certificate’ in clause 1 (quoted above), as
well as on clause 11, which provides (in
the relevant part) as
follows:
‘
This
Construction Guarantee … shall expire in terms of either 1.1.4
or 2.1, or payment in full of the Guaranteed Sum or on
the Guarantee
expiry date, whichever is the earlier, where after no claims will be
considered by the Guarantor. …’
[20].
I
do not accept the submissions on behalf of Hollard for the simple
reason that its interpretation of the relevant provisions does
not
accord with the trite principles relating to the interpretation of
written instruments. First, insofar as it may be necessary,
the
‘ordinary’ or ‘literal’ meaning of a
contractual provision may be departed from if it would be clearly
contrary to the actual intention of the parties, or in order to avoid
‘some absurdity or … some repugnance or inconsistency
with the rest of the contract’
[4]
,
or to give a contract a commercially sensible meaning. At the same
time, however, interpretation cannot serve to create a new
contract
for the parties or to insert a term merely out of sympathy for a
contracting party.
[21].
Secondly,
in the exercise of interpreting documents, courts are slow to impute
superfluity to a document and an interpretation which
has this effect
should not be readily accepted. The preferred approach is to give
some effect rather than no effect to the words.
Wallis JA in
Bothma-Batho
Transport (Edms) Bpk v S Bothma & Seun Transport (Edms) Bpk
[5]
pointed out that ‘[a] sensible meaning is to be preferred to
one that leads to insensible and unbusinesslike results or undermines
the apparent purpose of the document’.
[22].
Thirdly,
greater weight ought to be given to special provisions than to
general provisions, it being presumed that the parties cannot
have
intended that a general provision should apply to a case covered by
special words –
generalia
specialibus non derogant
.
[23].
Fourth,
according to the
contra
proferentem
rule, a contract or its terms must, in cases of doubt and ambiguity,
be construed against the party by whom or on behalf of whom
it was
formulated.
[24].
Fifth, it is
well-established that a provision in an insurance agreement which
purports to place a limitation upon a clearly expressed
obligation to
indemnify must be restrictively interpreted.
[25].
Applying these
principles
in
casu
, I
conclude that Hollard’s interpretation of the guarantee is
untenable, as it amounts to narrow literalism and because it
entails
a patent contradiction between the definition of ‘Guarantee
expiry date’ and clause 11, on the one hand, and
clause 1.1.4
quoted
supra
,
on the other hand. As correctly contended by Mr Price, the former
provisions, on Hollard’s literalist interpretation, indicate
that the Guarantee necessarily expired when the final completion
certificate was issued on 5 May 2022. Clause 1.1.4, by contrast,
explicitly confers a guarantee of R855 911.74 in relation to the
period ‘From and including the day after the date of the
applicable final completion certificate…’, namely after
5 May 2022.
[26].
What is more
is that Hollard’s interpretation accordingly has the effect
that clause 1.1.4 is rendered meaningless and of
no practical effect
in circumstances such as the present, namely where the works required
by the Building Agreement have been completed
(and accordingly the
Building Agreement has been performed rather than terminated), the
Principal Agent issues a final payment
certificate at the same time
or after issue of the final completion certificate, as required by
clause 34.5 of the Building Agreement
and the final payment
certificate indicates that the contractor owes an amount to the
employer.
[27].
In these
circumstances, namely ‘Where the final payment certificate
reflects payment due to the Employer’, clause 1.1.4
explicitly
and unambiguously provides that ‘the Construction Guarantee
shall expire upon payment of the full amount certified’.
But
‘payment of the full amount certified’ by Hollard under
the Guarantee could never take place prior to the issue
of the
practical completion certificate. This follows from the various
time-periods and procedures imposed by the Building Agreement
and the
Guarantee (being the obviously relevant context), notably: (a) The
Building Agreement requires the final payment certificate
to be
issued at the same time or after the final completion certificate;
(b) Once the final payment certificate is issued and reflects
an
amount due to the employer, the contractor has twenty-one calendar
days to pay; (c) The Guarantee then provides for an additional
seven
calendar days within which a contractor must not accede to an
employer’s demand for payment, before that employer may
call
upon the guarantor under the Guarantee.
[28].
The point, in
summary, is that Hollard’s literalist interpretation means that
the Guarantee inevitably expired on the day
the final completion
certificate was issued, that is before the twenty-one-day period and
seven-day period could even begin to
run. So Hollard could never be
called upon to pay. Such a consequence is, in my view, in conflict
with the plain wording of clause
1.1.4 of the Guarantee (which
amounts to a ‘special provision’ rather than the ‘general
provision’ that
is contained in the definition of the
‘Guarantee expiry date’). Additionally, it leads to an
absurd and an unbusinesslike
result, which, in any event, defeats the
purpose of the Guarantee, namely to provide protection for SMBT in
the event of CIC’s
default, including ‘after the date of
the applicable final completion certificate…’.
[29].
Moreover,
Hollard’s interpretation is also acontextual: it amounts to an
impermissible ‘narrow peering at words’
that ignores the
relevant context provided by the other provisions of the Guarantee as
well as the Building Agreement. In particular,
in terms of the
Building Agreement, it was not legally possible for CIC to be in
default of its obligation to pay SMBT the certified
amount until
twenty-one calendar days after issue of the final completion
certificate and in terms of the Guarantee, it was not
legally
possible for SMBT to call upon Hollard to pay until a further seven
calendar days after issue of the final completion certificate.
However, on Hollard’s literalist interpretation, the Guarantee
inevitably expired on the day the final completion certificate
was
issued, that being before the twenty-one-day period and the seven-day
period could even begin to run. So Hollard could never
be called upon
to pay.
[30].
These
consequences which would inevitably flow from Hollard’s narrow
literal interpretation of the Guarantee are the very
definition of
absurd and unbusinesslike.
[31].
It is so, as
submitted by Mr Price, that a proper interpretation of the Guarantee
will avoid the absurd, unbusinesslike and acontextual
consequences
embraced by Hollard. The proper interpretation turns on the legal
meaning to be ascribed to clause 11 (quoted
supra
)
which, contemplates three situations (relevant to this dispute) in
which the Guarantee will expire, being: (a) In terms of clause
1.1.4
– ‘Where the final payment certificate reflects payment
due to [SMBT], this Construction Guarantee shall expire
upon payment
of the full amount certified’; (b) On ‘payment in full of
the Guaranteed Sum’; or (c) ‘on
the Guarantee expiry
date’, defined to be ‘on the issue of the final
completion certificate’.
[32].
According to
Hollard’s interpretation, the phrase ‘whichever is the
earlier’ applies to all three situations.
The alternative and,
in my view, the correct interpretation which the words of clause 11
are equally capable of bearing, is that
the phrase ‘whichever
is the earlier’ applies only to the second and the third
situations, namely on payment in full
of the Guaranteed Sum, and –
on issue of the final completion certificate.
[33].
I say that
this is the correct interpretation as it is consistent with the text
of clause 11 and, moreover, is supported by the
presence of a comma
after ‘or 2.1’ which indicates that the qualified
(‘whichever is the earlier’) was
intended to apply only
to the circumstances set out after that comma (‘or payment in
full of the Guaranteed Sum or on the
Guarantee expiry date’),
being the third and fourth situations. Furthermore, as I have found
above, Hollard’s interpretation
would render the cover provided
by clause 1.1.4 to be meaningless and of no practical effect in
circumstances where the works have
been completed and the final
payment certificate (which cannot be issued before the final
completion certificate) reflects payment
due by the contractor to the
employer. By contrast, the alternative interpretation gives meaning
and effect to clause 1.1.4, as
well as the purpose of the Guarantee.
[34].
As alluded to
supra
,
Hollard’s interpretation also amounts to giving a ‘general
provision’ – the general definition of ‘Guarantee
expiry date’ – priority over a ‘special provision’
– the special expiry date set out in clause 1.1.4.
However, our
law adopts the opposite attitude: general words should not derogate
from special words. The alternative interpretation
ensures
this.
[35].
Lastly, as
contended on behalf of SMBT, where, as here, there is a genuine
ambiguity in the meaning of clause 11, the
contra
proferentem
rule should be applied, which militates against Hollard’s
interpretation and in favour of the interpretation contended for
by
SMBT. It is also so that an insurance agreement which purports to
place a limitation upon a clearly expressed obligation to
indemnify
must be restrictively interpreted.
[36].
For all of
these reasons, I am of the view that the applicant should be granted
the relief claimed by it in its notice of motion.
Conclusion
and Costs
[37].
In sum, SMBT
has made out a case for the relief sought by it and judgment should
therefore be granted in its favour against Hollard.
In its third
party proceedings, Hollard claims indemnification against CIC and the
other third parties in the event of judgment
being granted against it
in favour of SMBT. The third parties have indicated that they do not
oppose the third party proceedings
and would abide this court’s
judgment. Judgment in favour of Hollard against the third parties
should therefore follow.
[38].
As
regards costs, the general rule is that the successful party should
be given his costs, and this rule should not be departed
from except
where there are good grounds for doing so, such as misconduct on the
part of the successful party or other exceptional
circumstances. See:
Myers
v Abramson
[6]
.
[39].
I can think of no reason why I
should deviate from this general rule. I therefore intend granting
SMBT its costs of the opposed
application, to be paid by Hollard and
CIC. As regards CIC, it is, as submitted on behalf of SMBT, that it,
in aligning itself
with the Hollard’s case and by adopting the
defences raised by Hollard, has actively opposed the application
despite the
fact that SMBT had indicated in its founding papers that
it would not be seeking any relief against CIC. It would accordingly
be
fair for CIC to be held jointly and severally liable, with
Hollard, for the latter’s costs.
Order
[40].
Accordingly, I make the following
order: -
(1)
It is declared that
Variable
Construction Guarantee
number
PS GUA 3692312 dated 13 April 2015 issued by the first
respondent in favour of the applicant has not expired.
(2)
Judgment is granted in favour of the
applicant against the first respondent for: -
(a)
Payment to the applicant of the sum of
R855 911.74.
(b)
Payment of interest on the aforesaid sum of
R855 911.74 at the applicable legal interest rate of 7,75% per
annum from 09 June
2022 (being the date of first demand) to date of
final payment.
(3)
The first and the second respondents,
jointly and severally, the one paying the other to be absolved, shall
pay the applicant’s
costs of this opposed application.
(4)
Judgment is granted in favour of the first
respondent against the first to the fifth third parties, jointly and
severally, the one
paying the other to be absolved, for: -
(a)
Payment to the first respondent of the sum
of R855 911.74.
(b)
Payment of interest on the aforesaid sum of
R855 911.74 at the applicable legal interest rate of 7,75% per
annum from 09 June
2022 (being the date of first demand) to date of
final payment.
(c)
Payment of the costs payable by the first
respondent to the applicant as per prayer (3) above.
(d)
Payment of the first respondent’s
costs of the Third Party proceedings.
L R ADAMS
Judge of the High
Court
Gauteng Division,
Johannesburg
HEARD ON:
9
th
November 2023
.
JUDGMENT DATE:
12
th
January 2024 – judgment handed down electronically
FOR THE APPLICANT:
Advocate Alistair
Price
INSTRUCTED BY:
Slabbert Venter
Yanoutsos Inc, Wynberg, Cape Town
FOR FIRST RESPONDENT:
Advocate Dwight Snyman
INSTRUCTED BY:
Moll
Quibell and Associates Ferndale, Randburg
FOR SECOND RESPONDENT
AND THE FIRST TO THE FIFTH THIRD PARTIES:
Advocate Gerhard Van
Rhyn
INSTRUCTED BY:
George
Whitehead Incorporated, George
[1]
Lombard
Insurance Co Ltd v Landmark Holdings (Pty) Ltd and Others
2010
(2) SA 86
(SCA) at pg 90E H.
[2]
Natal
Joint Municipal Pension Fund v Endumeni Municipality
2012 (4) SA 593 (SCA).
[3]
Capitec
Bank Holdings Ltd and Another v Coral Lagoon Investments 194 (Pty)
Ltd
2022
(1) SA 100 (SCA).
[4]
Scottish
Union & National Insurance Co Ltd v Native Recruiting Corp Ltd
1934
AD 458
at 465-6 , in which case ‘the Court may modify the
words just so much as to avoid the absurdity or inconsistency but no
more’.
[5]
Bothma-Batho
Transport (Edms) Bpk v S Bothma & Seun Transport (Edms) Bpk
2014 (2) SA 494 (SCA).
[6]
Myers
v Abrahamson
1951(3)
SA 438 (C) at 455
sino noindex
make_database footer start
Similar Cases
S.B.M. v Road Accident Fund (728/19) [2025] ZAGPJHC 548 (4 June 2025)
[2025] ZAGPJHC 548High Court of South Africa (Gauteng Division, Johannesburg)99% similar
B.M.S v J.N.W (2024/110526) [2025] ZAGPJHC 112 (10 February 2025)
[2025] ZAGPJHC 112High Court of South Africa (Gauteng Division, Johannesburg)99% similar
SB Ngento Attorneys and Another v Mbiza obo Mbiza and Others (Leave to Appeal) (082843/2024) [2024] ZAGPJHC 1155 (8 November 2024)
[2024] ZAGPJHC 1155High Court of South Africa (Gauteng Division, Johannesburg)99% similar
B.M.P v T.K.P (A3088/2022) [2025] ZAGPJHC 960 (19 September 2025)
[2025] ZAGPJHC 960High Court of South Africa (Gauteng Division, Johannesburg)99% similar
M.B. v S (A94/2024) [2025] ZAGPJHC 707 (14 July 2025)
[2025] ZAGPJHC 707High Court of South Africa (Gauteng Division, Johannesburg)99% similar