Case Law[2024] ZAGPJHC 643South Africa
LR Management Group (Propriety) Limited v Emfuleni Local Municipality (2023/027863) [2024] ZAGPJHC 643 (4 July 2024)
High Court of South Africa (Gauteng Division, Johannesburg)
4 July 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 643
|
Noteup
|
LawCite
sino index
## LR Management Group (Propriety) Limited v Emfuleni Local Municipality (2023/027863) [2024] ZAGPJHC 643 (4 July 2024)
LR Management Group (Propriety) Limited v Emfuleni Local Municipality (2023/027863) [2024] ZAGPJHC 643 (4 July 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_643.html
sino date 4 July 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
CASE
NO: 2023-027863
1.
REPORTABLE: Yes☐/ No ☒
2.
OF INTEREST TO OTHER JUDGES: Yes☐ / No ☒
3.
REVISED: Yes ☐ / No ☒
4
July 2024
In
the matter between:
THE
LR MANAGEMENT GROUP (PROPRIETY) LIMITED
APPLICANT
and
EMFULENI
LOCAL MUNICIPALITY
RESPONDENT
JUDGMENT
DU
PLESSIS AJ
#
# Background
Background
[1]
This is an application for a money judgment against the Respondent
Municipality for an amount of R1 632 578,48 with
mora
interest
of 7% from 29 December 2020 until payment in full, plus an amount of
R833 045,49 together with
mora
interest of 7% from 17 July
2021 until payment in full.
[2]
The Applicant sent two invoices to the Respondent (on 28 February
2020 and 28 April 2021) in terms of a written Skillsoft
Digital
Learning Renewal Agreement (the SLDR Agreement) concluded between the
parties in April 2019. The invoices were not paid.
Despite various
demands for payment, the demands went unanswered, and the invoices
are still unpaid. No dispute was raised regarding
the indebtedness
before the Respondent’s answering affidavit was delivered.
[3]
On 24 March 2023, the Applicant instituted the application based on
the understanding that the Respondent’s indebtedness
was
undisputed and that there were no foreseeable disputes of fact. The
cause of action is set out as follows: The parties concluded
a
written agreement dated 22 May 2018, in which the Respondent
appointed the Applicant to provide specialised services as set out
in
the agreement. This agreement is a framework for providing services –
the services were to be specified in a project charter.
The Applicant
offered to renew its services in October 2018 by concluding the SLDR
agreement to offer it for another three years.
This offer was
accepted and signed, the terms of which were set out in the SLDR
agreement. In short, the Respondent’s responsibility
is to sign
off on all invoices and deliverables.
[4]
The Applicant states that they fulfilled their obligations under the
agreement. The Respondent performed the first year
by paying the
Applicant. However, for the other two years, the Respondent did not
pay. Despite demands for payment, no responses
were received, no
payment was made, no disputes were lodged, and the contract was not
cancelled.
[5]
However, on 8 May 2023, after the launching of the application, the
Respondent delivered an answering affidavit opposing
the relief
sought. This was the first time the Applicant heard of the
Respondent’s defence, mainly depending on the
exceptio non
adimpleti contractus
. To understand it, some background detail is
necessary.
# The agreement
The agreement
[6]
As stated, the SLDR Agreement emanated from an earlier Master
Agreement dated 22 May 2018 and signed on 10 October 2018.
In terms
of this Master Agreement, the Respondent appointed the applicant as
an independent service provider to provide specialised
services,
including Skillsoft digital learning licences, to assist the
unemployed with computer skills to improve their employment
prospects. The agreement was to endure indefinitely.
[7]
Clause 3.2 of the Master Agreement states that the specifications for
the services shall be stated in the Project Charter.
Cause 15.2
states that all amounts payable to the Applicant shall be set out in
the Project Charter. The “Agreement”
includes the Project
Charter and annexures, underscoring the document's importance. The
Applicant does not rely on this document
for their cause of action.
[8]
In terms of the later SDLR agreement, the software licenses were
renewed for another three years, with the renewal prices
set out on
page 9 of that agreement. It provided that payment is due 30 days
from the invoice payment. The Respondent signed this
SLDR agreement
extending the licenses on the terms set out in that agreement. The
Applicant relies on this document for their cause
of action.
[9]
The Respondent was invoiced in terms of the SDLR agreement, and it
paid for the first year. The non-payment for the other
two years
gives rise to this dispute.
[10]
In terms of clause 10.5 of the Agreement, if the Respondent discovers
a fault or error, the fault or error shall be reported
to the
Applicant before the expiry of the evaluation period, which the
Applicant must correct within the time stipulated in the
project
charter. If the Applicant is not notified of such a fault or query,
the deliverable will be deemed accepted by the client.
[11]
In terms of clause 21, if a party breaches the agreement and fails to
remedy the breach within five days after receipt
of a written notice
from the other party calling upon the defaulting party to remedy the
breach, the aggrieved party may either
claim specific performance or
cancel the agreement. The Respondent did not give the Applicant a
breach notice, did not claim specific
performance and did not cancel
the agreement.
[12]
Clause 15.7 states that the Applicant will invoice the Respondent in
line with the nature of the service provided. An
invoicing schedule
is to be included in the Project Charter. The Respondent must sign
and return to the Applicant an AIC before
receiving the invoice. The
clause states specifically that “[t]he AIC is a document LRMG
(the Applicant) uses to set out
exactly what it intends to invoice
the Client (the Respondent) for”. In case of a dispute, the
Respondent, in terms of clause
15.8, must pay the invoice balance due
and withhold only the disputed amount. The dispute must then be
resolved in terms of clause
26.
[13]
The Respondent avers that the Applicant failed to comply with the
terms of the SDLR Agreement and/or the Proposal and
is, therefore,
not entitled to the payments. This was because:
i. It failed to
ensure that a Project Charter, as per the SDLR Agreement, was signed
between the parties before rendering
any services to the Respondent;
ii. The Respondent
was not informed of the progress of its performance of the services
at all times by preparing for and conducting
review or progress
meetings and periodic reporting to the Respondent;
iii. The Applicant
failed to provide the Respondent with an Authorisation to Invoice
(the “AIC”) to sign before
invoicing the Respondent;
iv. The Applicant
failed to provide a functional portal for 2020 onwards. The portal
provided had constant errors and was
non-functional, as was
communicated to the Applicant’s representative. The Respondent
thus raises the
exceptio non adimpleti contractus
.
[14]
All this constitutes a “dispute” that must, in terms of
clause 26.2 read with clause 15.8 of the SDLR Agreement,
be submitted
to arbitration under the AFSA Rules, which means that this
application must be stayed pending the final determination
of the
dispute by an arbitrator in terms of the SDLR Agreement. The
Respondent is obliged to pay the undisputed amount until the
dispute
is resolved, which it did.
[15]
The Respondent also states that the Applicant failed to plead the
Project Charter and that it has complied with it, which
is a
necessary document before services can be rendered in terms of the
Master Agreement. Given the importance of the document,
the Applicant
had to plead it. Without such a pleading, there is no complete cause
of action, and the claim must fail.
[16]
Likewise, the Applicant failed to produce a signed AIC despite it
being a condition before invoicing in terms of clause
15.7 of the
Master Agreement. The Applicant, therefore, failed to establish a
cause of action. It failed to do so in its founding
affidavit and
cannot make a case or introduce a new matter in reply.
[17]
The Respondent states that a dispute of fact must either be resolved
through the
Plascon-Evans
rule or through the presentation of
oral evidence before an Arbitrator.
[18]
The Applicant disagrees. The Applicant states that this is not a
bona
fide
defence. For one, the Respondent does not disclose his
defence and the material facts upon which it is based with sufficient
particularity
and completeness. In short, there is not enough
information before the court.
[19]
The Applicants also argue that the defence is lacking on the
following grounds:
i. First, the
Respondent did not reply to the two letters of demand and at no time
before the institution of the proceedings
suggested that it had a
defence to the claim. The Respondent also does not explain the
silence.
ii. Secondly, the
Respondents have provided no evidence to support their claim and rely
only on the municipal officials' words.
The nature of the claims is
such that it requires documentary evidence. For instance, it alleges
that the Applicant failed to comply
with its contractual obligations,
but there was no termination of the Agreement on written notice to
the Applicant, there was no
termination or withdrawal from the
Project Charter on written notice to the Applicant, there was not
furnishing the Applicant with
written notice of any problem.
iii. Thirdly, the
replying affidavit shows that their claims are baseless. The
Respondent’s claim that the Project Charter
was signed was
refuted by the Applicant attaching a signed copy; the claim that the
Applicant did not inform the Respondent of
its progress was refuted
by the Applicant giving detailed examples of feedback meetings and
email exchanges; the Respondent’s
claims that it did not sign
an AIC was refuted by the terms of the contract that does not require
an AIC as a condition of payment;
the claim that the portal had
errors and was non-functional cannot stand because only one customer
support query was received,
and was attended to and resolve on the
same day – there were no other complaints lodged.
iv. Fourthly, as
an organ of state, the Respondent is held to a higher standard when
litigating.
v. Fifthly, and
linking with the previous point, an organ of state has unique and
disproportionate power in litigation. It
has access to public funds.
This means that the Respondent’s allegations are informed by an
ulterior purpose – dissuading
the Applicant from recovering its
debt and forcing it into expensive arbitration proceedings. In any
case, in terms of clause 26
of the Master Agreement, a liquidated
claim does not need to go to arbitration.
[20]
The Applicant adds that arbitration proceedings only aim to resolve a
dispute. Without a
bona fide
defence, there is no purpose in
referring the matter to arbitration.
#
# Discussion
Discussion
[21]
What is to
be made of the Respondent’s inaction and silence until the
application was launched?
McWilliams
v First Consolidated Holdings (Pty) Ltd
[1]
stated that although a party not replying to a letter asserting that
there is an obligation owed does not necessarily mean that
they
accept this to be true, in general, based on ordinary commercial
practice and human expectation, a firm repudiation of such
an
assertion would be the norm. In other words, silence or
inaction, unless explained, may be taken as accepting the truth
of
the assertion or at least contribute to an adverse assessment against
such a party as to the probabilities in determining the
dispute.
[22]
The other hurdle that the Respondent must pass, as far as this is
concerned, is clause 10.6 of the Agreement, which states
that if the
Applicant is not notified of a fault or error,
it is deemed to
have been accepted
by the Respondent. This should be read with
the duty to report a fault in clause 10.5. The Respondent did not
provide the court
with any documentary evidence that it informed the
Applicant of such faults or errors. It is thus deemed to have
accepted the Applicant’s
performance.
[23]
The
argument of the Respondent that it stated in the answering affidavit
that the performance is defective and that based on the
Plascon-Evans
rule,
[2]
the court must go with
the version that is also not sustainable. That is only half of the
Plascon-Evans
rule. The rule is qualified in that if, in the court's opinion, there
is no real, genuine or
bona
fide
dispute of fact, or if it is so far-fetched, the court is justified
in rejecting it. This was further explained recently in
Wightman
t/a J W Construction v Headfour (Pty) Ltd.
[3]
The court stated that a true, genuine, and bona fide dispute of fact
can only exist if the court is convinced that the party raising
the
issue honestly and unambiguously addressed the matter in its
affidavit. In its replying affidavit, the Applicant highlights
why
the dispute the Respondent sought to raise is not bona fide, genuine,
or untenable. It does so by attaching a signed version
of the Project
Charter (signed by a representative of the Respondent itself). It
highlights the lack of documentary evidence for
the Respondent’s
claims regarding the defective performance of the Applicant. There is
very little evidence before the court
to back up the ascertain made
in the answering affidavit that the performance was defective, and
there is even less evidence that
these faults and errors were
communicated to the Applicant as per contractual terms.
[24]
As for the AIC, the Respondent contends that the Applicant failed to
provide it with an AIC for the Respondent to sign
before the
Applicant invoiced it. However, in clause 15.7, the obligation rested
on the Respondent to sign and return to the Applicant
an AIC before
receiving the invoice. There is also no indication that the AIC is a
precondition for payment. It also seems that
the purpose of the AIC
is to know what it is invoiced for, but the Respondent already knew
when it signed the SLDR that it was
accepting it.
[25]
The Project Charter was not part of the Applicant’s cause of
action as set out at the beginning of this judgment.
They plead a
master contract, the three-year extension in terms of the SLDR, and
the non-performance of the Respondent in terms
of that agreement. The
Project Charter is not a prerequisite for performance in terms of the
SLDR contract.
[26]
Lastly, to
address the defence of the
exceptio
non adimpleti contractus.
This
defence entitles a party from whom performance is demanded to
withhold such performance until the party who demands it has
rendered
or tendered its performance in full.
[4]
It is a defence against a party demanding performance but who has not
rendered their reciprocal performance precisely or in full.
[27]
Normally,
the
exceptio
is available if the defect in performance is not serious enough to
justify its rejection or the cancellation of the contract by
the
defendant.
[5]
The
exceptio
foresees the upholding of the contract; in other words, the
exceptio
as a defence seeks the enforcement of contractual obligations.
[6]
The burden of proof is on the plaintiff (against whom the
exceptio
is raised) to show that he has performed his part of the contract.
[7]
Having found that the Respondent’s version of defective
performance is untenable on the evidence before me, this defence
is
not available to the Respondent.
[28]
This also
means that there is no dispute to refer to arbitration. In
Parekh
v Shah Jehan Cinemas (Pty) Ltd
[8]
the court stated that arbitration is a method of resolving disputes.
If there is no dispute, arbitration is not needed. Moreover,
there
was no dispute when this application was launched, so it is unclear
why clause 26 would be applicable. Clause 26.6 also provides
for
judgment in relation to a liquidated claim to be adjudicated by a
court, which is what the Applicants did.
[29]
The Applicant is thus entitled to its relief.
# Order
Order
[30]
I, therefore, make the following order:
1. The Respondent
is ordered to make payment to the Applicant of the following sums:
a. R796 533,48 (VAT
inclusive), together with
mora
interest thereon at a rate of
7% from 29 December 2020 until payment in full; and
b. R836 045,49 (VAT
inclusive), together with
mora
interest thereon at a rate of
7,5% from 17 July 2021 until payment in full;
2. The Respondent
is liable for the costs of this application.
WJ
du Plessis
Acting
Judge of the High Court
Delivered:
This judgement is handed down electronically by uploading it to the
electronic file of this matter on CaseLines and sending
it to the
parties/their legal representatives by email.
Counsel
for the applicant:
Ms Z Ngakane
Instructed
by:
Cliffe Dekker Hofmeyr Inc
Counsel
for the respondent:
Mr N Nxumalo
Instructed
by:
Katake Attorneys Inc
Date
of the hearing:
21 May 2024
Date
of judgment:
04 July 2024
[1]
1982
(2) SA 1
(A).
[2]
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984] ZASCA 51
;
1984 (3) SA 623
(A) at 634E-635C.
[3]
[2008]
ZASCA 6
para 13.
[4]
The
case that caused many law students worries,
BK
Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk
1979 1
SA 391
(A)
,
explores this in great detail.
[5]
Thompson
v Scholtz
(167/96) [1998] ZASCA 87.
[6]
Hutchison,
A. "Reciprocity in contract law."
Stellenbosch
Law Review
24.1 (2013)
14.
[7]
Hutchison,
A. "Reciprocity in contract law."
Stellenbosch
Law Review
24.1 (2013)
16.
[8]
1980
(1) SA 301
(D) p 304.
sino noindex
make_database footer start
Similar Cases
Manufacturing, Engineering & Related Services Sector Education & Training Authority v Mhlaba (033076/2022) [2023] ZAGPJHC 1038 (18 September 2023)
[2023] ZAGPJHC 1038High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Manufacturing Engineering & Related Services Sector Education & Training Authority v Social Enterprise Trust (2023-023483) [2024] ZAGPJHC 237; (2024) 45 ILJ 1330 (GJ) (8 March 2024)
[2024] ZAGPJHC 237High Court of South Africa (Gauteng Division, Johannesburg)99% similar
R.L.M.K v M.G.M (20421/2016) [2024] ZAGPJHC 1243 (29 November 2024)
[2024] ZAGPJHC 1243High Court of South Africa (Gauteng Division, Johannesburg)99% similar
L.C.W and Others v Road Accident Fund (2019/15424) [2024] ZAGPJHC 348 (9 April 2024)
[2024] ZAGPJHC 348High Court of South Africa (Gauteng Division, Johannesburg)99% similar
L.R.J and Another v J.B.J (2024/024281) [2025] ZAGPJHC 16 (14 January 2025)
[2025] ZAGPJHC 16High Court of South Africa (Gauteng Division, Johannesburg)99% similar