Case Law[2024] ZAGPJHC 695South Africa
Goldleaf Investments (Pty) Ltd v Orkin (22321/18) [2024] ZAGPJHC 695 (22 July 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 695
|
Noteup
|
LawCite
sino index
## Goldleaf Investments (Pty) Ltd v Orkin (22321/18) [2024] ZAGPJHC 695 (22 July 2024)
Goldleaf Investments (Pty) Ltd v Orkin (22321/18) [2024] ZAGPJHC 695 (22 July 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_695.html
sino date 22 July 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
Case
Number: 22321/18
1.
REPORTABLE:
NO
2.
OF INTEREST TO OTHER JUDGES: NO
3.
REVISED:
NO
In
the matter between:
GOLDLEAF
INVESTMENTS (PTY) LTD
APPLICANT
v.
NADINE
ORKIN
RESPONDENT
In
re:
NADINE
ORKIN
RESPONDENT
And
GOLDLEAF
INVESTMENTS (PTY) LTD
DEFENDANT
JUDGMENT
MIA,
J
:
[1]
The
applicant, the defendant in the trial, appeals the whole of the
judgment handed down on 21 April 2023. The issue for determination
in
the trial was whether or not it was a tacit term of the sale
agreement that the applicant would have had to "
supply
all of the necessary infrastructure so as to provide a fully serviced
site both in respect of municipal and electrical services
alternatively that the defendant would ensure that all of the
necessary infrastructure was in place so as to provide a fully
serviced
site both in respect of municipal and electrical
services
"
[1]
.
If there was such a tacit term, the court was enjoined to determine
whether the applicant had breached such a term and caused
the
respondent to suffer damages. The applicant lodged a counterclaim,
and the court was required to determine whether the respondent
was
liable for the costs of the applicant's counterclaim. The appeal was
opposed.
[2]
The
applicant raised numerous grounds in the application for leave to
appeal, which spanned twenty-nine pages and several grounds.
To
succeed in this application for leave to appeal, in terms of
s17(1)(a)(i)
[2]
of the
Superior
Courts Act 10 of 2013
, the applicant must satisfy the court that the
appeal will have reasonable prospects of success or that there is
some other compelling
reason why the appeal should be heard. The
enquiry does not end there. “
If
the court is unpersuaded of the prospects of success, it must still
inquire whether there is a compelling reason to entertain
the appeal.
This includes an essential question of law or a discreet issue of
public importance that will affect future disputes.
The merits remain
important and are often decisive.
[3]
[3]
I deal with the salient points raised in
the appeal.
[4]
It is appropriate to commence with the
argument on behalf of the applicant that the respondent's case should
fail as she did not
testify. Counsel argued that the respondent had
not met her case as the evidence tendered amounted to hearsay in that
she did not
testify in her matter. It was submitted that Mr Orkin’s
and Mr Parson's evidence constituted hearsay and should not be
accepted.
Regarding the law of evidence, the evidence of Mr Orkin and
Mr Parsons constituted the best evidence. This is so because Mr Orkin
and Mr Parsons had the best knowledge about the aspects they
testified about. Mr Orkin was best qualified to testify where he
assisted his wife each step of the way, completing the agreement and
was best placed to testify about the agreement, the process
and the
payments he made. Mr Orkin was the best witness to explain why they
required a lift to be installed as it met his requirement
due to
frailty.
[5]
Mr Parsons, who engaged with Mr Robinson
directly, was also the best witness to testify regarding his
communication with the contractor.
Counsel’s submission that
the plaintiff was required to testify ignores that the best evidence
is necessary. Mr Orkin’s
evidence about payments made was thus
relevant to prove the amount relating to the loss and damages. It was
also Mr Orkin's evidence
that he and Mrs Orkin would later reconcile
the amounts paid from his account. Thus, he was best placed to
testify regarding how
the parties determined the money would be paid
into his account or how they, as partners, contributed to their joint
living arrangement.
Mr Orkin's evidence indicated as much. The
parties need not be married in community of property to share their
home expenses. On
this ground, I do not see that another court will
come to a different conclusion relating to the best evidence rule.
[6]
A further ground related to the tacit term,
based on paragraph 8 of the judgment which reads:
“
and
the surrounding circumstances as well as the evidence all point to
the developer being responsible for having a fully serviced
site in
place once the construction was completed to enable the plaintiff to
take occupation of the home.”
Counsel
submitted that the agreement presumes that bulk electricity is
supplied to the site. This was erroneous, counsel continued,
as Mr
Orkin indicated that no electricity supplied to the site at the time
the agreement was entered into. The submission is misguided
as a
proper reading of the paragraph indicates that the site was to be
fully serviced upon completion of the construction. As indicated
in
the evidence, this was necessary to test the supply of electricity
and issue the certificates before handing over the occupation
certificate.
[7]
Counsel
argued furthermore that the court found that there was a tacit term
that required the applicant to provide “a fully
serviced site
both in respect of municipal and electrical services alternatively
that the defendant would ensure that all of the
necessary
infrastructure was in place to provide a fully serviced site both in
respect of municipal and electrical services”.
Counsel
submitted that the court erred in this regard at the outset, as this
was an agreement between the applicant and the respondent.
As the
respondent did not testify in the trial, the respondent did not prove
her case. The court referred to the decision of
Alfred
McAlpine & Son (Pty) Ltd v Transvaal Provincial
Administration
[4]
In
the judgment handed down, an unexpressed term or tacit term can be
determined no better than by the officious bystander test.
The test
on this aspect has not changed, and counsel has not persuaded me that
another will find
necessary
for the respondent to lead evidence in person on this aspect or that
the test has changed.
[8]
Counsel further submitted that the court
erred in finding that the applicant failed to ensure that bulk
electricity was supplied
to the site. It was submitted as the court
ignored that bulk electricity was supplied to the site and the
applicant had obtained
a
regulation 38
certificate in terms of the
Town Planning and Township Ordinance which required internal
reticulation. This required cabling to
be laid to particular units.
The last phase was to be completed during construction. The evidence
of the applicant and the contractor
was that the applicant was
responsible for the supply of electricity. This was supported by the
applicant’s evidence that
he sent various communications to
Eskom, approximately fifty-eight.
[9]
Counsel for the applicant referred to these
fifty-eight communications of the applicant which occurred between
March 2017 and March
2018 to ensure the bulk supply to the site. It
is noteworthy that counsel argued that Ms Forstman was not an expert
and her view
is not decisive. That is so as the applicant's evidence
was clear that he engaged with Ms Forstman in respect of many
projects,
and upon his enquiry about Bellisimo, she indicated a
requote was required as the project was “old”. It follows
that
the fifty-eight calls made to Eskom did not relate to the
Bellisimo development alone. The applicant was compelled to act on
the
final stage of the installation on his own evidence when Mr
Robinson approached him and indicated that the respondent would be
requiring occupation of their unit shortly. The applicant’s
response was that he was waiting for Eskom. The applicant’s
plea that there was no obligation to supply electricity, that the
plaintiff frustrated the supply or to blame Eskom are all defences
that fail.
[10]
It
was Mr Robinsons initiative, after Mr Parson’s enquiry about
electricity and the respondent's correspondence demanding
information
and indicating the loss suffered that caused the applicant sign
off and move on the electrical supply. The applicant
approved the
quotation from Consolidated Power Engineering (CPE) to assist in
facilitating the process. The applicant of necessity
and on Mr
Robinson’s advice after Mr Robinson obtained a quotation from
CPE appointed the engineering company to address
the delay after a
substantial delay had already occurred.
[11]
Counsel
for the respondent argued in the present matter there had been an
agreed date for delivery per the sale agreement and building
contract
which were linked, thus the argument made on behalf of the applicant
that the applicant was not placed
in
mora
was
not applicable. It is evident that Mr Parsons enquired in February
2017 alerting the applicant that their programme may not
meet the
agreed occupation date if the electrical installation was not
complete.
[5]
The applicant’s
response at that stage was that occupation was dependant on Eskom
electricity supply. The building contractor
informed the developer
that the final installation electricity supply was urgent. The
applicant was aware in April 2017 that they
would not meet the
installation of installation of electrical supply to the unit by the
agreed date of occupation. The respondent
informed the contractor and
developer in April 2017 that they were not able to take occupation
due to the electrical supply not
being in place and details which
parts of the building works have not been completed. Moreover, the
respondent placed on record
that the delay was costing R 40 000
per month for rental. There is no basis to the argument that the
respondent did not bring
the breach to the attention of the applicant
and the applicant was not required to act on it. The respondent
clearly placed her
position forward in correspondence dated 19 April
2017.
[6]
[12]
The
submission that the respondent agreed to the new occupation date and
thus waived their rights to claim damages ignores the respondent
communication to the applicant and contractor that they incurred
losses as a result of the delay. The sale agreement and builder's
contract were interlinked and set out a reasonably agreed date for
occupation. There was no need to place the applicant
in
mora
.
The respondent informed the applicant per correspondence that she
suffered a loss as a result of the electricity not being installed
and not being able to take occupation per the agreement. The
respondent demanded that the electricity be attended to, indicating
that they, she and Mr Orkin had been prejudiced, as a result of the
electricity issue not being attended to until they demanded
same and
their unit was not habitable without electricity even though they
agreed to a new date of occupation. The respondent pointedly
indicated the loss they incurred as a result of her not being able to
take occupation per the agreed date and having to extend
their rental
amounting to R40 000
[7]
per
month. The applicant’s view when the respondent raised the date
of occupation was that they remain on at their residence.
Their home
had been sold and the respondent incurred costs as a result of the
failure to move into the unit in Bellisimo. The applicant
cannot
waive away the respondent or her claim when the agreement made
provision for occupation within a particular time frame.
I am not
persuaded that another court would find differently on the aspect of
damages.
[13]
It was also submitted that the court erred
in failing to take into consideration the claim by the respondent
against the contractor,
which was alleged to be identical to the
claim against the applicant. The aforementioned claim resulted in a
settlement when the
contractor gave the respondent occupation. The
submission was that the respondent had compromised her claim against
the applicant
when she claimed against the contractor. Whilst the
sale agreement and the building agreement were inextricably linked,
the settlement
agreement between the respondent and the contractor
did not imply a settlement between the respondent and the developer.
The applicant
and contractor had different obligations. The once and
for all rule is applicable between the same parties in the same
litigation.
The applicant did not prove that the respondent claimed
for the same breach against the applicant and the contractor. The
respondent’s
claim is against different defendants for
different breaches in terms of different agreements albeit to obtain
occupation of the
same unit. The settlement agreement between the
contractor and the respondent makes provision for the respondent to
pursue a developer
debt and to pay the contractor and proportionate
amount upon recovered. The respondents claim against the contractor
is not subject
to the once-and for-all rule against the developer.
This is because the once-and-for-all rule is applicable in litigation
between
the same parties.
[14]
Counsel submitted that the court erred in
finding the applicant had no
locus
standi
in respect of the counterclaim.
The reason for finding there was no
locus
standi
is adequately set out in the
judgment. I elaborate no further and am of the view that there is no
possibility a different conclusion
will be reached. The applicant did
not pursue this aspect substantially before me.
[15]
On the issue of costs, counsel submitted
that there was a reasonable possibility that another court would find
that the respondent
failed to make out her case and the claim should
fail with costs. In addition, it was submitted that the counterclaim
should succeed
with costs. The reasons for granting a punitive costs
order are set out in the judgment. I do not intend to elaborate
further on
the reasons.
[16]
Having regard to the standard the applicant
must satisfy to succeed I am not persuaded that there are reasonable
prospects of success
that another court will come to a different
conclusion. There is no other compelling reason why the appeal should
be heard.
[17]
In the result, I grant the following order:
The application for leave
to appeal is dismissed with costs.
SC, MIA
JUDGE OF THE HIGH
COURT
GAUTENG DIVISION,
JOHANNESBURG
APPEARANCES
Counsel
for the Applicant:
Adv. N Stathern
Instructed
by:
Ulrich Roux and Associates
Counsel for the
Respondent: Adv. D Vetten
Instructed
by:
Witz Incorporated Attorneys
Date
of Hearing:
14 June 2024
Date
of Judgment:
22 July 2024
[1]
Record, Caselines (CL) 001-6 - Particulars of claim, para 11,.
## [2]‘Leave
to appeal
[2]
‘Leave
to appeal
## (1)
Leave to appeal may only be given where the judge or judges
concerned are of the opinion that-
(1)
Leave to appeal may only be given where the judge or judges
concerned are of the opinion that-
## (a)
(i) the appeal would have a reasonable prospect of success; or
(a)
(i) the appeal would have a reasonable prospect of success; or
## (ii)
there is some other compelling reason why the appeal should be
heard, including conflicting judgments on the matter under
consideration.
(ii)
there is some other compelling reason why the appeal should be
heard, including conflicting judgments on the matter under
consideration.
[3]
Caratco
(Pty) Ltd v Independent Advisory (Pty) Ltd
(Case
no 982/18)
[2020] ZASCA 17
(25 March 2020)
[4]
Alfred
McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration
1974(3) SA 506 A at 531
[5]
Caselines
004-499 Correspondence to Mr Parsons
[6]
Caselines
004-506 Respondent’s correspondence to developer
[7]
Ibid
004-507 Respondent’s correspondence to developer
sino noindex
make_database footer start
Similar Cases
Gold Leaf Tobacco Corporate (Pty) Ltd v Sasfin Bank Ltd (2022/21063) [2025] ZAGPJHC 32 (24 January 2025)
[2025] ZAGPJHC 32High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Gold Leaf Tobacco Corporation (Pty) Ltd v Sasfin Bank Ltd (2022/21063) [2023] ZAGPJHC 1299 (13 November 2023)
[2023] ZAGPJHC 1299High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Golden Harvest Medical Centre Proprietary Limited v Ntsanu and Others (2024/133489) [2025] ZAGPJHC 528 (27 May 2025)
[2025] ZAGPJHC 528High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Goldman v Thalatse Magistrate for the District of Johannesburg North Held At Randburg and Others (104577/2024) [2025] ZAGPJHC 1221 (24 November 2025)
[2025] ZAGPJHC 1221High Court of South Africa (Gauteng Division, Johannesburg)98% similar
South African Agricultural Machinery Association and Another v Motor Industry Ombudsman of South Africa and Others (20/44414) [2024] ZAGPJHC 824 (30 April 2024)
[2024] ZAGPJHC 824High Court of South Africa (Gauteng Division, Johannesburg)98% similar