Case Law[2024] ZAGPJHC 990South Africa
Eskom Holdings Soc LTD v Babcock Ntuthuko Engineering (Pty) Ltd (A2023/099598) [2024] ZAGPJHC 990 (3 October 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 990
|
Noteup
|
LawCite
sino index
## Eskom Holdings Soc LTD v Babcock Ntuthuko Engineering (Pty) Ltd (A2023/099598) [2024] ZAGPJHC 990 (3 October 2024)
Eskom Holdings Soc LTD v Babcock Ntuthuko Engineering (Pty) Ltd (A2023/099598) [2024] ZAGPJHC 990 (3 October 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_990.html
sino date 3 October 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
Appeal
Court Case No: A2023-099598
Court
a quo Case No: 21/32783
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: YES
DATE:
03/09/2024
SIGNATURE
In
the matter between:
ESKOM HOLDINGS SOC
LTD
APPLICANT
And
BABCOCK
NTUTHUKO ENGINEERING (PTY) LTD
t/a
BABCOCK NTUTHUKO POWERLINES
RESPONDENT
This judgment was handed
down electronically by circulation to the parties’
representatives by email and released to SAFLII.
The date for
hand down is deemed to be 10h00 on 3 October 2024.
Key words: Appeal-
Enforceability of Adjudicator’s Award-
until revised, is enforceable as a matter
of contractual obligation.
JUDGMENT
THE COURT:
Introduction
[1]
This is an appeal against the judgment of Makume J (“the
court
a quo
”) brought with leave of the Supreme Court of
Appeal granted on 4 September 2023. The appeal relates to the
enforcement of
an adjudicator’s decision communicated to the
parties on 16 November 2020 (‘the Decision’).
Condonation
[2]
The appellant, Eskom, has delivered, rather belatedly, a
reinstatement and condonation application on 3 July 2024, no doubt as
a
response to the respondent’s, Babcock’s, heads of
argument delivered on 30 May 2024, regarding the lapse of this
appeal.
In addition, Babcock notified Eskom of the lapsing of the
appeal earlier than the delivery of Babcock's heads, in two letters
dated
2 May and 8 May 2024 respectively. Eskom seeks (conditional)
condonation for the late filing of the record as well as the delivery
of security for costs, which is opposed.
[3]
Eskom's version in this reinstatement application is that it
could not apply for a hearing date without delivering the record, and
that it could not deliver the record without entering into security
for costs. Eskom's initial tender of R 50,000 as security for
Babcock's appeal costs, was unsurprisingly rejected by Babcock. Eskom
in turn, rejected Babcock's proposal of R 250 000. Subsequently,
on 8 February 2024, after hearing both parties pursuant to rule
49(13)(b) of the Uniform Rules of Court, the Registrar fixed R
350
000 as the amount for security, to be provided by way of bank
guarantee or as agreed otherwise between the parties. However,
there
was no such agreement
.
[4]
Eskom sought to review the Registrar's decision, which it
never pursued. It is common cause that, Eskom's attorneys filed a
written
notice that it holds R 350,000 as security. However, it
does not secure Babcock to the same extent and falls short of the
Registrar's ruling that security in favour of Babcock be provided by
bank guarantee. At the appeal hearing, Eskom tendered to correct
the
position by providing the requisite bank guarantee the very next day
.
[5]
It
is trite that in all cases of time limitation, whether statutory or
in terms of the Rules of Court, this Court has inherent powers
to
condone the non-compliance with time limits where the principles of
justice and fair play demand it and where the reasons for
non-compliance with the time limits have been explained
satisfactorily.
[1]
[6]
Relevant
considerations may include not only the explanation therefor, but
also include the degree of non-compliance with the rules,
the
prospects of success on appeal, the importance of the case, the
respondent’s interest in the finality of his or her judgment,
the convenience of the court, and the avoidance of unnecessary delay
in the administration of justice. There is no exhaustive list.
[2]
[7]
Rule 49(2) of the Uniform Rules requires delivery of a notice
of appeal within 20 court days of the granting of leave to appeal.
Eskom's notice of appeal was promptly delivered on 28 September 2023
as required by the rule. Rule 49(6)(a) prescribes that an
appellant
shall make written application to the Registrar for a date for the
hearing of the appeal, within 60 court days after
delivery of the
notice of appeal, in this instance by 21 December 2023, failing which
the appeal would be deemed to have lapsed
10 court days later. It is
not in dispute that the appeal record in this matter was available to
Eskom on 23 November 2023. The
respondent correctly pointed out that
Eskom could and should have delivered the appeal record together with
an application for
a hearing date on 21 December 2023.
[8]
On Eskom's version, it belatedly sought to apply for a date by 17
January
2024, but only delivered the record on 9 April 2024. Whilst
Babcock is correct in pointing out that Eskom failed to make timeous
written application to the Registrar for a hearing date, the vexed
issue of payment of security has been laid to rest. As pointed
out
above, there is the overriding interest for both parties in bringing
finality to this matter, and to avoid needless delay in
the
administration of justice and the disbursement of public funds
regarding this matter. For reasons that will become apparent
regarding the merits of the appeal, condonation and reinstatement of
the appeal is granted
.
The Merits of the
Appeal
[9]
Eskom and Babcock concluded a contract in terms of which Eskom
retained
Babcock to construct 400kV transmission lines
.
[10]
The
contract, was in broad terms, governed by the NEC3 Core Clauses:
Engineering and Construction Contract April 2013 edition. Dispute
resolution was governed by the W Clauses
[3]
which in turn provided for a dispute resolution process which
contemplated the referral of disputes between the parties first to
adjudication and thereafter to arbitration.
[11]
Babcock contended that it had claims under the contract. It referred
a dispute to adjudication.
Eskom responded to the claim. The
adjudicator considered the referral made by Babcock as well as
Eskom’s response and delivered
the Decision. Given its
relevance to our judgment, it is necessary to say something about the
Babcock referral and the Eskom
response.
The
referral and response
[12]
Seven disputes were referred by Babcock. In relation to the disputes
referred, Babcock
devoted a considerable portion of the referral
dealing with why it contended that its referral to the adjudicator
was timeous.
[13]
In its response, Eskom dealt comprehensively with the topic of
whether there had been timeous
referral of the disputes. The broad
thrust of Eskom’s defence was that the disputes were time
barred in the sense that there
had not been timeous referral of the
disputes by Babcock to adjudication.
[14]
In its response, Eskom
verbatim
“[a]dmits that the
Adjudicator has jurisdiction to hear these claims and submit [sic]
that the issue is not about jurisdiction
but about whether in terms
of the contract the claims were notified, the disputes notified or
the disputes referred, in time.”
Eskom explained this by
asserting that it is its “….
submission that the
Contractor (Babcock) is time barred from referring the dispute to the
Adjudicator since it did not notify and
neither referred the dispute
in time and lost its rights to claim any relief in respect thereof
.”
(the Time Bar question”). The Time Bar question was what the
adjudicator had to answer.
[15]
The adjudicator considered Babcock’s referral and Eskom’s
response, including
the Time Bar question. Ultimately, the
adjudicator answered the Time Bar question against Eskom. All of this
was, rightly, conceded
by counsel for Eskom.
[16]
The Decision determined certain monies were to be paid by Eskom.
Eskom, as it was entitled
to do, noted a dissatisfaction with the
Decision. This meant that the matter would proceed to arbitration.
Eskom in relation to
the arbitration has indicated that it would be
agreeable to an expedited arbitration.
[17]
In the
meantime, Babcock brought an application to enforce the Decision. It
said as much in its notice of motion. As to enforcement
of an
adjudicator’s Decision, pending the arbitration, this Court
(per Wepener J) in
Stefanutti
Stocks (Pty) Ltd v S8 Property (Pty) Ltd
[4]
made the position plain. The Court explained the position as follows:
“
[5] Adjudication
was first introduced in the United Kingdom through the Housing Grants
Construction and Regeneration Act 1996 (‘the
Housing Act’).
The Housing Act provides for an accelerated process for deciding
disputes. It provides in particular that
an adjudicator’s
decision may be rejected by either party and submitted to arbitration
but it is provisionally binding on
the parties unless and until
overturned in the subsequent arbitration. The enforcement of an
adjudicator’s decision and the
referral of the dispute to
arbitration is dealt with in England and Wales by a scheme
promulgated as regulation 1998 which is quoted
in the judgment of the
Queen’s Bench Division in
Carillion Construction Ltd v
Devonport Royal Dock Yard
[2005] EWHC 778
(TCC) at para 6. The
relevant regulation provides that:
‘
The
decision of the adjudicator shall be binding on the parties and they
shall comply with it until the dispute is finally determined
by legal
proceedings, by arbitration…or by agreement between the
parties’.
[6] At para 59 of
Carillion
, and discussing the law, the court explained the
purpose of adjudication as follows:
‘
It was to
introduce a speedy mechanism for settling disputes in construction
contracts on a provisional interim basis and requiring
the decisions
of adjudicators to be enforced pending final determination of
disputes by arbitration, litigation or agreement.’
In
Carillion
at
para 80 the court found that even errors of procedure, fact or law by
the adjudicator did not constitute defences to the enforcement
of the
adjudicator’s decision.
[7] In South Africa
adjudication has found its way into major construction agreements,
such as the JBCC agreement, and is regulated
contractually. The
purpose, however, of the two procedures and the enforcement of the
adjudicator’s decision are, in my view,
similar.
[8] Eyvind Finsen
The
Building Contract - A commentary on the JBCC Agreements
, 2 ed p
229 explains the enforcement of the adjudicator’s decision as
follows:
‘
The
purpose of adjudication being the quick, if possible temporary,
resolution of a dispute and the granting of interim relief to
the
successful party, the whole purpose of adjudication would be
frustrated if the successful party was unable to enforce the
determination against the other party’.”
[18]
The court
a quo
granted the application for enforcement of the
Decision. Eskom says the application was incorrectly granted. There
were three main
arguments made by Eskom in the appeal in support of
why the court
a quo
’s decision was wrong.
[19]
The first
is that the Decision was not enforceable because it was made in
circumstances where the adjudicator did not have jurisdiction
and in
consequence was unenforceable (“the Jurisdictional Complaint”).
The argument was premised upon Eskom’s
reading of the decision
in
Framatome
v Eskom Holdings SOC Ltd
[5]
in which the court stated that “
[i]t
is trite that, if upon an application for enforcement of an
adjudication decision, it is found that the adjudicator did not
have
the requisite jurisdiction, his decision will not be binding or
enforceable
”.
[6]
The reason that the adjudicator did not have jurisdiction, according
to Eskom, was because the referral by Babcock was time barred,
in
other words, the Time Bar question. Eskom’s complaint was that
the Time Bar question was wrongly decided by the adjudicator.
Of
course, what this also means is that Eskom contended that the court
a
quo
should have considered the Time Bar question and should have decided
it in its favour.
[20]
The second is that the court
a quo
decided the matter on a
basis other than the pleaded case. In this regard the contention was
that the court
a quo
found that there had been an agreed
extension of the time periods for a referral of the dispute. This of
course traces back to
the Time Bar question. It is not an issue,
given our findings later in this judgment, that is of relevance. This
is so because
the adjudicator decided the Time Bar question, albeit
not in the way that Eskom wanted him to. We shall explain the import
of this
when we deal with the Jurisdictional Complaint.
[21]
The third was that the relief that was sought by Babcock did not
“
constitute an enforcement of the Decision and it was not
authorised by the contract
”. In this regard Eskom’s
argument is two pronged. It says: (1) Babcock calculated its own
amounts as opposed to using
the amounts decided by the adjudicator;
and (2) Babcock’s entitlement to payment only arises from
payments certified by the
Project Manager in terms of the contract
(the Payment Complaint). Tied to this Eskom criticises the court
a
quo
for making credibility findings in relation to the Project
Manager and his impartiality.
The
Jurisdictional Complaint
[22]
Eskom has misconceived the statement made in
Framatome.
[23]
A useful
starting point are the English cases on the topic.
The
first decision is
C&B
Scene Concept Design Ltd v Isobars Ltd
[7]
where it was held that that the enforcement of an adjudicator’s
decision cannot be prevented whether it was caused by errors
of
procedure, fact, or law, unless the adjudicator has purported to
decide matters which were not referred to him.
The second is the decision in
Bouygues
UK Ltd v Dahl-Jensen UK Ltd
.
[8]
Albeit that
Bouygues
dealt with adjudication in the statutory context, the principle in
the case is, in our view, of application.
[24]
The court
in
Bouygues
held the following in relation to an argument that the adjudicator’s
decision was not binding:
[9]
“
27.
The first question raised by this appeal is whether the adjudicator's
determination in the present case is
binding on the parties - subject
always to the limitation contained in section 108(3) and in
paragraphs 4 and 31 of the Model Adjudication
Procedure to which I
have referred. The answer to that question turns on whether the
adjudicator confined himself to a determination
of the issues that
were put before him by the parties. If he did so, then the parties
are bound by his determination, notwithstanding
that he may have
fallen into error. As Knox J put it in Nikko Hotels (UK) Ltd v MEPC
PLC
[1991] 2 EGLR 103
at page 108, letter B, in the passage cited by
Buxton LJ, if the adjudicator has answered the right question in the
wrong way,
his decision will be binding. If he has answered the wrong
question, his decision will be a nullity.”
[25]
This theme
was re-affirmed in the third decision, the matter of
Prater
Ltd v John Sisk & Son (Holdings) Ltd
.
[10]
In
Prater
[11]
,
a decision cited by Eskom in support of its argument, the court dealt
with a jurisdictional complaint which in turn was raised
as an
impediment to enforcement. The court said the following:
“
15.
I take as my starting point the fundamental principle set out at
paragraph 7.37 of Coulson On Construction
Adjudication (4th
Ed.):
‘
The
fundamental principle that governs all enquiries into the
adjudicator’s jurisdiction can be simply stated. If a dispute
has arisen between two parties to a construction contract and the
adjudicator is validly appointed to decide that dispute, then,
provided his decision attempts to answer that dispute, his decision
will be binding in accordance with the 1996 Act, regardless
of errors
of fact or law or procedure. If, on the other hand, he was not
validly appointed, or he decided something other than
the dispute
that was referred to him, his decision will be unenforceable because
it would have been made without jurisdiction.
Thus it follows that it
is not enough for the defendant to show an error on the part of the
adjudicator. What matters, in the words
of Sir Murray Stuart-Smith in
C&B Scene, is whether the error on the part of the adjudicator
went to his jurisdiction, or was
merely an erroneous decision of law
(or fact) on a matter within his jurisdiction. If it was the former,
the decision would be
unenforceable; if it was the latter, the
decision would be enforceable by way of summary judgment’.”
[26]
This theme is also present in
Framatome
where the court was
careful to point out the following:
“
[29]
In the final analysis, the question to be asked is whether the
adjudicator's determination is binding on the parties.
The
answer to that question turns on whether the adjudicator confined
himself to a determination of the issues that were put before
him by
the parties. If he did so, then the parties are bound by his
determination, notwithstanding that he may have fallen into
an
error
.” Our underlining.
[27]
Eskom thus misunderstands the
dicta
in
Framatome
. It is
in keeping with a long line of established cases which we have
referred to. It says no more than this: If the adjudicator
confined
himself to the question put before him, whether he answers it
wrongly, the parties are still bound.
[28]
That he may wrongly answer a deeply contested issue about whether a
time bar is of application
does not, in our view, mean that he has
acted in excess of his jurisdiction. He is simply answering that
which has been asked of
him by the parties. A permissible attack on
jurisdiction (and in consequence enforceability of the Decision)
because a party is
aggrieved with the outcome of a question put to
the adjudicator is not what
Framatome
says at all.
[29]
To summarise, the Time Bar question was put before the adjudicator
and the adjudicator
considered it and decided it. When dealing with
the Time Bar question, it is stated in the Decision that: “
[t]he
Adjudicator has taken into account the arguments put forward by the
Parties
”. He may be wrong in his answer, he may also
be right. But that is not for this Court to consider. Eskom has its
remedy
in the arbitration, which it is pursuing.
[30]
Further, it is also not for this Court to pre-empt what is to be
determined by the arbitrator
in due course. If this Court, as Eskom
invites it to do, deals with the Time Bar question and rules in
Eskom’s favour, it
will be doing precisely that. What then,
rhetorically speaking, is the use of the arbitration?
[31]
For the reasons canvassed, we do not consider there to be any merit
in the Jurisdictional
Complaint raised by Eskom.
The
Payment Complaint
[32]
Firstly, Eskom argues that Babcock claims for sums which are not in
accordance with the
Decision. It is necessary to pay closer attention
to the Decision in order to deal with this issue. We deal with the
Decision on
each dispute, which we quote
verbatim
below.
[33]
Dispute 1:
“
63.
The Adjudicator rules that the quotation is accepted; the 24 day
extension to be applied to the Completion
Date for the whole of the
works; the change in Prices is R620 916.49 (excl VAT); the change in
Prices is to be adjusted for inflation
in terms of the Contract;
interest is payable on the amount of the change in Prices plus
adjustment for inflation, In terms of
the Contract; any delay damages
applied erroneously because of the invalid Key Date and Sectional
Completion Date penalties, prior
to the Completion Date for the whole
of the works are to be returned and interest applied in terms of the
Contract.”
[34]
Dispute 2:
“
68.
Because of the non-validity of the Key Date,
Sectional completion and delay damages associated therewith,
as
discussed above. The Adjudicator rules any delay damages applied
erroneously because of the Invalid Key Date and Sectional Completion
Date penalties, prior to the Completion Date for the whole of the
works are to be returned and interest applied in terms of the
Contract.
I am informed by the Claimants
submission that the sum is R12 935 656.50 (excl. VAT), In
addition interest in terms of
the Contract is payable to the
Contractor for the amounts wrongly deducted
.”
[underlined for emphasis]
[35]
Dispute 3:
“
90.
The Adjudicator assessment is to proportion the 9 working day
quotation of R 4,767,017.24 (excl VAT)
to 6 days which equates
to R3,178,013.08 (excl VAT).
91.
The change to the Prices above is subject to price adjustment due to
Inflation in terms of X1 using
Indices at the adjusted Completion
Date. Interest is payable on the amount of the change In Prices plus
adjustment for Inflation.
In terms of the Contract.”
[36]
Dispute 4:
“
106.
The Adjudicator decides the Completion Date for the whole of
the works be extended by 11 days.
107. Any
deduction of penalties prior to the Completion Date for the whole of
the works, for
missing invalid key dates and
invalid sectional completion dates are to be returned together with
interest payable to the Contractor.
108. Both
quotations are accepted with changes to the Prices being
R1, 191,286.29 (excl VAT) and R2,955,723.35 (excl
VAT)
respectively.
109. The
changes to the Prices are both to be adjusted for inflation in terms
of X1.
110.
Interest in terms of the conditions of contract is payable.”
[37]
Dispute 5:
“
114. The
Adjudicator decides that the estimated extension of the Completion
Date to April 2018 should be re-assessed and
finalised in terms of
the extensions to the Completion Date as decided by the Adjudicator
above.
115. The
Adjudicator decides that the Parties meet in attempt to reach
agreement on CPA relating to payment certificates
number 29 & 30.
This should be re-assessed in light of the Adjudicator's decisions
concerning the adjusted Completion Date
as well as compensation
events being valued at current rates or not.
116. The
Defendant shall pay Interest on the late payments in terms of the
Contract.”
[38]
Dispute 6:
“
132. The
Adjudicator decides the Defendant must pay the Claimant the
settlement amount offered by the Claimant. i.e.
………
.
R 696 792.15 (excl. VAT).
………
.
R 666 250.25 (excl. VAT).
133. The
Adjudicator decides the Defendant must pay the Claimant on the sum
above, the calculated amount in terms of
X1 Price Adjustment for
inflation.
134. The
Adjudicator decides the Defendant must pay the Claimant Interest in
terms of the Contract.”
[39]
Dispute 7:
“
147. The
Adjudicator decides the compensation event arising from carrying out
the verbal Instruction is valid and the Adjudicator
assesses the
change in the Prices to be the amount as quoted by the Contractor
being R288,392.96 (excl Vat)
148. The
Adjudicator decides interest is payable on this amount in terms of
the Contract.”
[40]
Apart from this the Decision specified that Babcock would send Eskom
an invoice and Eskom
would pay within the time stipulated in the
Contract. Moreover, the parties were required to meet within a week
to resolve the
issue of interest to be levied on the late payments
identified in the Decision. It is clear that the Decision required an
arithmetical
update. This is precisely what Babcock did. That it did
this in accordance with the Decision, does not mean that it is not
enforcing
the Decision in its terms.
[41]
First,
Babcock states that the capital amounts invoiced and claimed in
enforcement proceedings are the exact amounts stated in the
Decision.
Eskom disagrees in its answering affidavit but does not explain why.
This does not give rise to a genuine dispute.
[12]
[42]
Second, Babcock states that inflationary adjustments were made in
accordance with the contract,
more particularly Option X1. This
Option sets out an objective mechanism to calculate inflation. Eskom
does not dispute the mechanism,
nor does it seriously dispute
Babcock’s calculation.
[43]
Third, Babcock explains that in relation to interest, it utilised the
contractual mechanism
to calculate this. Indeed, Babcock annexed a
schedule to its papers setting out the relevant rate per month.
Again, Eskom does
not seriously dispute this.
[44]
In our view the amounts claimed are in line with the Decision and as
we have said, are
merely the arithmetical updates contemplated by the
Decision.
[45]
The second contention by Eskom is that Babcock was only entitled to
be paid upon certification
by the Project Manager. But that is not
what the Decision says. The Decision requires of Eskom to pay on
receipt of Babcock’s
tax invoice within the contractually
agreed time period. It makes no mention of further certification. We
point out that Eskom’s
stance is that there can be further
certification and if Babcock is unhappy with the certification, it
must then initiate a further
dispute about the certification. This is
the antithesis of a speedy resolve of a dispute. What it does is
perpetuate it. The Decision
does not interpose a requirement of
certification. It expressly provides for payment within a specified
time.
[46]
We are of the view that there is no merit in the Payment Complaint.
[47]
In our view this disposes of the main arguments and grounds persisted
with by Eskom.
[48]
We point out that this Decision was made in December 2020. It is now
almost four years
later. There has been no arbitration on the issue
in the meantime. There has been no payment by Eskom. The rationale of
adjudication
has been subverted.
[49]
For the reasons expressed herein, the appeal has no merit.
[50]
In the result, we make the following order:
a.
The appeal is dismissed.
b.
The appellant is to pay the costs of the appeal including the
costs
of the application for condonation, with such costs to include the
costs of two Counsel on Scale C.
TP MUDAU
JUDGE OF THE HIGH
COURT
JOHANNESBURG
A
MAIER-FRAWLEY
JUDGE OF THE HIGH
COURT
JOHANNESBURG
A
GOVENDER
ACTING JUDGE OF THE
HIGH COURT
JOHANNESBURG
APPEARANCES
:
For
the Appellant:
Adv S Tshikila assisted by Adv T Mpulo-Merafe
Instructed
by:
Dlamini Attorneys
For the
Respondent:
A Kemack SC assisted by M Nieuwoudt
Instructed
by:
Hattingh Massey Bennett Inc Attorneys
Date
of Hearing:
13 August 2024.
Date of Judgment:
3 October 2024
[1]
See
SWA
Munisipale Personeel Vereniging v Minister of Labour
1978
(1) SA 1027
(SWA) at 1038B; see also
Yunnan
Engineering CC v Chater
and
Others
2006
(5) SA 571
(T) at para 22; and
Aymac
CC v Widgerow
2009
(6) SA 433
(W) at para 7.
[2]
See
in this regard
United
Plant Hire (Pty) Ltd v Hills
1976 (1) SA 717
(A) at 720E–G
;
and
PAF v
SCF
[2022]
ZASCA 101
;
2022 (6) SA 162
(SCA) at para 15
.
[3]
In
this contract the W1 option was chosen.
[4]
2013 JDR 2441 (GSJ) at paragraph 5
[5]
[2021]
ZASCA 132
;
2022 (2) SA 395
(SCA) (“
Framatome
”).
[6]
Id
at para 25.
An
endorsement of the position is in
Carillon
Construction v Devonport Royal Dockyard Ltd
[220] EWCA Civ 1358 which held “where an adjudicator has acted
in excess of his jurisdiction or in serious breach of the
rules of
natural justice, the court will not enforce his decision”.
Carillon
was quoted with approval in Supreme Court of Appeal judgment of
Sasol
Africa (Pty) Ltd v Murray and Roberts Ltd
[2021] ZASCA 94.
[7]
[2002]
EWCA Civ 46
;
[2002] BLR 93
(TCC) at paragraph 30
[8]
[2000] EWCA Civ 507
(“
Bouygues
”).
[9]
See
Boygues
at paragraph 27
[10]
[2021] EWHC 1113
(TCC) (“
Prater
”).
[11]
See
paragraph 15 of
Prater
[12]
Wightman
t/a JW Construction v Headfour (Pty) Ltd and Another
[2008]
ZASCA 6
;
2008 (3) SA 371
(SCA), at par 13.
sino noindex
make_database footer start
Similar Cases
Eskom Holding SOC Limited Ltd v Sokweba and Others (101726/2024) [2024] ZAGPJHC 935 (18 September 2024)
[2024] ZAGPJHC 935High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holdings SOC LTD v City of Johannesburg Metropolitan Municipality and Others (2024/048808) [2024] ZAGPJHC 794 (12 August 2024)
[2024] ZAGPJHC 794High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holdings SOC Ltd v City of Johannesburg Metropolitan Municipality and Others (2024/048808) [2024] ZAGPJHC 579 (20 June 2024)
[2024] ZAGPJHC 579High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holdings SOC Ltd v City of Johannesburg Metropolitan Municipality and Others (2024/075944) [2024] ZAGPJHC 882 (6 September 2024)
[2024] ZAGPJHC 882High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holding SOC Limited v Santam Limited and Another (2021/51709; 2023/104516) [2025] ZAGPJHC 725 (21 June 2025)
[2025] ZAGPJHC 725High Court of South Africa (Gauteng Division, Johannesburg)100% similar