Case Law[2023] ZAGPJHC 105South Africa
VBS Mutual Bank (In Liquidation) v Mafoko and Another (2021/34634) [2023] ZAGPJHC 105 (9 February 2023)
High Court of South Africa (Gauteng Division, Johannesburg)
9 February 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 105
|
Noteup
|
LawCite
sino index
## VBS Mutual Bank (In Liquidation) v Mafoko and Another (2021/34634) [2023] ZAGPJHC 105 (9 February 2023)
VBS Mutual Bank (In Liquidation) v Mafoko and Another (2021/34634) [2023] ZAGPJHC 105 (9 February 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_105.html
sino date 9 February 2023
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
CASE
NO:
2021/34634
Reportable:
No
Of
interest to other Judges: No
Revised:
No
In
the matter between:
VBS
MUTUAL BANK (IN LIQUIDATION)
Applicant
and
ITUMELENG
MAFOKO
First Respondent
MABUYI
ROWENA MEMELA
Second Respondent
J
U D G M E N T
MAIER-FRAWLEY
J:
Introduction
1.
In this application, the applicant, VBS
Mutual Bank (in liquidation), (‘VBS’) seeks to enforce
its rights in terms of
written suretyship agreements respectively
concluded by the respondents, as sureties, in respect of the
indebtedness incurred by
the principal debtor, Leratadima Marketing
Solutions (Pty) Ltd (‘Leratadima’) to VBS, to the extent
provided for in
the respective suretyships.
2.
The first and second respondents, who are
married to one another, were the two shareholders and directors of
Leratadima prior to
its liquidation in December 2018. They each stood
surety for any existing or future indebtedness that was or would be
owed by the
principal debtor to VBS arising from whatsoever cause,
limited to an amount of R100 million, excluding interest.
3.
Consequent upon VBS advancing loan funding
in terms of a revolving credit facility extended to Leratadima during
the period January
2016 to March 2018, which funds Leratadima
(represented by the respondents) received and utilised, but failed,
despite demand,
to repay in full, the applicant instituted motion
proceedings against the sureties in which it claimed:
3.1.
As against the first respondent, payment of
the sum of R100 million, together with interest thereon at 9% per
annum calculated from
date of demand to date of final payment;
3.2.
As against the second respondent, payment
of the sum of R100 million, together with interest thereon at 9% per
annum calculated
from date of demand to date of final payment;
3.3.
As against the respondents, joint and
several payment of the costs of the application on the scale as
between attorney and client.
4.
Counsel acting for VBS informed the court
at the hearing of the matter that VBS was abandoning its claim for
payment (in aggregate
total) of R200 million, seeking only judgment
in the sum of R100 million as against the respondents for joint and
several payment
of the said sum, together with
mora
interest and costs. To this end, a revised draft order was uploaded
to the electronic file to cater for reduced relief. I deal
with this
further below.
5.
The first respondent deposed to the
answering affidavit on his own behalf and on behalf of the second
respondent, who confirmed
the allegations in the answering affidavit
in a confirmatory affidavit attached thereto.
6.
The respondents raised certain technical
procedural points and legal objections in their heads of argument,
essentially premised
on the notion that the applicant failed to make
out a case for the relief sought in its founding affidavit (including
that it had
impermissibly sought to supplement its case in its
replying affidavit) and that the replying affidavit in any event fell
to be
ignored by the court on the basis that the applicant had failed
to make out a case for condonation for the late filing of the
replying
affidavit. It is convenient to deal with the condonation
point before dealing with the merits of the application and all other
defences raised by the respondent.
Preliminary objection
re condonation for late filing of replying affidavit
7.
It is common cause that the applicant filed
its replying affidavit 5 months late. In paragraph 48 of the replying
affidavit, the
applicant sought condonation for the late filing
thereof, submitting that ‘no prejudice will have been caused
thereby’.
8.
The respondent complains that the applicant
tendered no explanation for the delay and submits that ‘the
absence of prejudice
to the respondents does not even arise if no
good cause is shown’. The respondent submits that the replying
affidavit should
therefore be disregarded by the court as
pro
non scripto
.
9.
As fate would have it, the respondents
appear not to have filed their answering affidavit on time, which led
to the matter initially
being enrolled on the unopposed motion court
roll. Eventually the matter was removed from that roll with the court
ordering the
respondents to file their answering affidavit by a
certain date.
10.
A
court has a discretion to consider all circumstances of the case. The
overriding factor is the interests of justice.
[1]
11.
As
pointed out by Wepener J in
Pangbourne:
[2]
“
[16]There
are a large number of matters that come before us in this Division in
which parties, for a variety of reasons, agree to
file affidavits at
times suitable to them.
Each case must
be decided on its own facts and it cannot be said that when
affidavits are filed out of time that is it not, without
more, before
the court
… Affidavits can
validly be before the court pursuant to an agreement between the
parties – see Rule 27(1) which provides
for such an agreement.
It can also be validly before the court
if the interests of justice require it
.”
(emphasis added)
12.
The
learned Judge referred to various authorities in support of the trite
principle that the rules of court exist for the court,
not the court
for the rules.
[3]
In addition,
several authorities were quoted in
Pangbourne
in support of the approach often endorsed by our courts, which is not
to encourage formalism in the application of the rules, as
the rules
are not an end in themselves to be observed for their own sake. They
are, after all, provided to secure the inexpensive
and expeditious
completion of litigation before the Courts.
[4]
Thus, for example, in
Trans-Africa
Insurance Co Ltd v Maluleka
1956 (2) SA 273
at 278F-G Schreiner JA remarked that ‘technical
objections to less than perfect procedural steps should not be
permitted,
in the absence of prejudice, to interfere with the
expeditious and, if possible, inexpensive decision of cases on their
real merits.
’ In
Brenner’s
Service Station and Garage (Pty) Ltd v Milne and Another
1983 (4) SA 233
(W)
at
237E-F
,
Leveson AJ (as he then was) remarked that ‘
I
think it emerges from the passages quoted that, in appropriate cases,
the Court is entitled to refuse to take heed of a technical
irregularity in a procedure which does not cause prejudice to the
opposite party.’
13.
In the present matter, the respondents had
the replying affidavit in their possession for five months, and, as
was the case in
Pangbourne,
they made no attempt to object to the late filing thereof until the
objection was made in argument before me. The respondents did
not
invoke the remedy provided in Rule 30 of the Uniform Rules of Court
to object to the late filing of the replying affidavit.
Moreover, the
respondents have failed to indicate what prejudice, if any, they
suffered as a result of the late filing of the replying
affidavit.
Nor have the respondents made out a case for the striking out of the
replying affidavit.
14.
In
so far as the respondents insinuate in their heads of argument that
they would suffer prejudice if the replying affidavit were
to be
considered (and not struck out) because the replying affidavit
contains new matter
[5]
which
they were not afforded an opportunity to respond to as the applicant
had refused to agree to their proposal that the new
allegations be
addressed by them in a supplementary affidavit, such perceived
prejudice remains unexplained, is unspecified and
is in any event not
related to the late filing of the replying affidavit. The respondents
were, after all, not hamstrung by the
applicant’s alleged
refusal. They could have availed themselves of the right to file a
further affidavit, with leave of court,
a procedure which could have
cured their technical objections but which they failed to pursue. In
this regard, I can do no better
than what Wepener J did in par 18 of
the
Pangbourne
judgment
than to quote the apposite remarks of Brand JA in
Anglo
Operations Ltd v Sandhurst Estates (Pty) Ltd
2007
(2) SA 363
(SCA) at para [32]:
“
I
am not entirely sure what is meant by the description of the
application as ‘totally irregular’. If it is intended
to
convey that the application amounted to a deviation from the Uniform
Rules of Court, the answer is, in my view, that, as is
often been
said, the Rules are there for the Court, and not the Court for the
Rules.
The court a quo obviously
had a discretion to allow the affidavit. In exercising this
discretion, the overriding factor that ought
to have been considered
was the question of prejudice. The perceived prejudice that the
respondent would suffer if the application
were to be upheld, is not
explained. Apart from being deprived of the opportunity to raise
technical objections, I can see no prejudice
that the respondent
would have suffered at all.
At
the time of the substantive application the respondent had already
responded – in its rejoining affidavit – to the
matter
sought to be included in the founding affidavit. The procedure which
the appellant proposed would have cured the technical
defects of
which respondent complained.
The
respondent could not both complain that certain matter was
objectionable and at the same time resist steps to remove the basis
for its complaint.
The
appellant’s only alternative would have been to withdraw its
application, pay the wasted costs and bring it again supplemented
by
the new matter. This would merely result in a pointless waste of time
and costs.
”
(emphasis added)
15.
In
the absence of any demonstrable prejudice to the respondents in the
event the application is to be dealt with and disposed of
on its
merits despite the late filing of the replying affidavit and given
that the replying affidavit sets out relevant facts in
order to
refute salient aspects of the allegations made in the answering
affidavit, it is my view that it is in the interests of
justice that
the replying affidavit be taken into account. I am thus inclined to
exercise my discretion in condoning the late filing
of the replying
affidavit so that the matter can be dealt with on its merits,
‘unfettered by technicalities’.
[6]
Background matrix
16.
The relevant background facts, which are
either common cause, undisputed or unrefuted on the papers, are the
following.
17.
In terms of a Supply and Delivery agreement
(the ‘supply contract’) concluded between the Universal
Service and Access
Agency (‘USAASA’) and Leratadima on 7
November 2015, Leratadima (represented by the first respondent)
agreed to manufacture,
supply and deliver 500 000 digital
terrestrial television set-top boxes (‘STB’s’) and
related equipment
to USAASA for a total consideration of R344 630
000. 00
18.
Pursuant to the conclusion of the supply
contract, Leratadima approached VBS to procure loan funding to enable
it to fulfil its
obligations under the supply contract. In essence,
Leratadima needed finance to fund the manufacture of the STB’s
by its
suppliers.
19.
On
15 January 2016, VBS and Leratadima entered into a written Revolving
Credit Financing Facility Agreement (the ‘facility
agreement’)
in terms whereof VBS agreed to loan the capital amount of R100
million
[7]
to Leratadima in the
form of a revolving credit facility, subject to the terms and
conditions contained in the facility agreement.
The Revolving Credit
Financing Facility account was defined in clause 1.2.9 as the account
held by Leratadima at VBS under account
number 10009820001 (the ‘VBS
Account’).
In
terms of a first written addendum concluded between VBS and
Leratadima on 5 April 2016, the facility amount was later increased
by an additional R150 million to the amount of R250 million.
20.
The facility agreement was to endure for a
period of one year,
commencing on 15
January 2016 and terminating on 14 January 2017. In terms of a second
written addendum concluded between VBS and
Leratadima on 26 January
2017, the duration of the agreement was extended for a further period
of 3 months, thus terminating by
effluxion of time on 25 April 2017.
In terms of the first and second addendums,
inter
alia,
all forms of security provided in
terms of the facility agreement, including suretyships executed by
the respondents would remain
in force until Leratadima discharged its
indebtedness to VBS in full. The first respondent was a signatory to
the facility agreement
and its addenda and both the first and second
addenda were incorporated as part of the facility agreement.
21.
Relevant terms of the facility agreement
included that VBS was entitled to charge an initiation fee of 7% of
the facility amount
(clause 3.2) and to charge interest at a rate of
Prime plus 4% on the facility amount (clause 3.4); All charges
accruing in respect
of the facility account as a result of the
facility agreement were for Leratadima’s account (clause 3.5);
Leratadima agreed to cause all funds
payable to it by USAASA under the supply contract to be paid into the
VBS account and Leratadima
was not entitled, without the written
consent of VBS, to change the VBS account details for as long as any
monies remained outstanding
by Leratadima to VBS under the facility
(clauses 5.6 read with 1.2.9); In terms of clause 6.1, ‘all
payments of proceeds
by USAASA will be made by electronic transfer to
the Revolving Credit Financing Facility’, i.e., into the VBS
account. In
terms of clause 3.3, all payments to be made by VBS in
respect of the facility agreement ‘shall be made as per the
purchase
order received directly from the supplier/s of Leratadima to
the supplier/s bank account as set out in the purchase order; Clause
10 contained a certificate clause in terms of which a certificate of
indebtedness signed by an authorised employee of VBS would
serve as
sufficient proof the amount outstanding; The respondents respectively
would stand surety in their personal capacities
as sureties and
co-principal debtors with Leratadima in respect of Leratadima’s
obligations under the facility agreement
and any losses suffered by
VBS (clauses 4.1.6; 5.7; & 11); The suretyships of the
respondents would remain in force for as
long as Leratadima was
indebted to VBS and the sureties were not entitled to cancel or
withdraw the suretyships until Leratadima’s
indebtedness was
fully discharged (clause 11 & 11.2); the facility agreement would
terminate by effluxion of time on the termination
date (clause 9.1).
22.
In terms of clause 14 of the facility
agreement:
“
14.1
This Agreement constitutes the
whole
agreement
between the Parties, relating to the subject matter hereof
and
no Party shall be bound by any term not recorded herein
.
…
no
extension of time
,
waiver
or relaxation or suspension of any of the provisions or terms of this
Agreement ... shall be binding unless recorded in a
written document
signed by the Parties
....
14.3.
No extension of time or waiver or relaxation of any of the provisions
or terms of this Agreement or any agreement or other
document issued
or executed pursuant to or in terms of this Agreement shall operate
as an estoppel against any Party in respect
of its rights under this
Agreement, nor shall it operate so as to preclude such party
thereafter from exercising its rights strictly
in accordance with
this Agreement.
14.4
No Party shall be bound by any express or implied term,
representation, warranty, promise or the like not recorded herein
.”
(emphasis added)
23.
On 15 January 2016 the respondents each
executed a written suretyship in favour of VBS bank. The respective
suretyships contain
identical terms. Relevant terms included the
following:
23.1.
The respondents respectively individually
bound themselves as sureties and co-principal debtors
in
solidum
with Leratadima for payment of
the amount of R100 million, excluding interest, in respect of any
debt which Leratadima owed, owes
or may in future owe to VBS from
monies lent and advanced (clause 3);
23.2.
No variation of the terms of the suretyship
would be of any force and effect unless reduced to writing and signed
by the surety
and confirmed by VBS in writing (clause 4);
23.3.
The suretyship was to remain in force and
effect for so long as Leratadima was indebted to VBS and the surety
was not entitled to
withdraw from or cancel the suretyship unless or
until all Leratadima’s indebtedness, commitments and
obligations to VBS
had been fully discharged (clause 6);
23.4.
A certificate of indebtedness signed by any
one of VBS’s managers would constitute sufficient proof of the
amount of the surety’s
indebtedness under the suretyship and
shall be a valid liquid document and ‘shall be deemed to
contain sufficient particulars,
inter
alia,
for purposes of pleading, summary
judgment or action instituted by VBS against the sureties’
(clause 7);
23.5.
In terms of clause 11, the surety renounced
every benefit to which he or she was entitled to in law, including
the benefits of excussion,
division, cession of actions, revisions of
accounts, no value received, the force and effect of which the surety
acknowledged he/she
was acquainted with;
23.6.
In terms of clause 17, in respect of any
legal proceedings for the recovery of the amount due to VBS by the
principal debtor, the
surety undertook liability to pay the
creditor’s legal costs on the scale as between attorney and
client.
24.
VBS granted Leratadima access to the
initial facility (R100 million) and later the extended facility
(additional R150 million) and
Leratadima accessed the facility funds
during the period 26 January 2016 until at least November 2017. The
statement of account
pertaining to Leratadima’s credit facility
and attached to the founding affidavit as ‘FA9’ reflects
the draw-
downs made on the VBS account through payment of
Leratadima’s suppliers during the said period, as well as the
payments made
by USAASA into the VBS account from time to time in
respect of goods supplied and delivered under the supply contract.
However,
at a point in time, Leratadima caused USAASA to make
payments under the supply contract into Leratadima’s Absa bank
account
(in aggregate total, the sum of R102 546 219.74 )
as opposed to making such payments into Leratadima’s VBS bank
account, as was incumbent upon it to do under the facility agreement.
25.
VBS fell victim to the perpetration of a
massive fraud during 2017, as was widely publicized in the public
domain.
26.
This
led to VBS being placed under curatorship by the Minister of Finance
in March 2018. On 10 March 2018, a firm of auditors known
as
SNG,
represented by Mr A. Rooplal (Mr Rooplal), the deponent to the
applicant’s affidavits, was appointed as curator.
[8]
According to Mr Rooplal, all credit accounts (including Leratadima’s
facility) at VBS were suspended. At that stage, Leratadima
was still
contractually bound to deliver an outstanding amount of STB’s
to USAASA in terms of the supply contract and needed
additional funds
(to the funds hitherto utilised by it) from VBS with which to do so.
27.
In June 2018, and whilst VBS was under
curatorship, Leratadima (represented by the first respondent)
approached the curator to advance
the amount of R25 million to
Leratadima, which request was declined on the basis that the credit
facility had by then expired and
in any event because the bank did
not have the available funds to advance.
28.
On 23 July 2018, the curator caused VBS’s
attorneys (Werksmans) to despatch a statutory demand to Leratadima in
terms of s
345 of the Companies Act, 1973, in which payment of the
sum of R152 071 422.68 was claimed, together with interest
thereon
as from 24 July 2018, in respect of Leratadima’s then
outstanding indebtedness to VBS in terms of the facility agreement
and extended facility.
29.
Leratadima’s
erstwhile attorneys (Allen & Associates) responded to the
statutory demand in a letter dated 23 July 2018,
in which they
unequivocally conveyed that ‘
our
client
[Leratadima]
does
not dispute its liability to VBS…as discussed and calculated
at the meeting but requests the final financing to comply
with all
its obligations, including payment of your debt …..’
[9]
The
said attorneys
inter
alia
asserted that in terms of the facility agreement, VBS was obliged to
make funding available to Leratadima for completion of the
full
contract with USAASA and not only a portion thereof. It was alleged
that in failing to make further funding available to Leratadima
to
manufacture the outstanding SDT’s, VBS was deliberately
preventing Leratadima from performing its obligations to USAASA
in
breach of its (VBS’s) obligations under the facility agreement.
30.
Werksmans, responded to the aforementioned
letter on 2 August 2018, stating, amongst others, that
“
3.
As at 23 July 2018,
an amount of R152,071,422.68 remained owing by your client under the
Revolving Credit Financing Facility. Despite
clear provisions in the
Revolving Credit Financing Facility Agreement ("the Facility
Agreement") requiring that all proceeds
of the USAASA contract
are to be paid into a specified bank account held by your client at
VBS Mutual Bank ("the Designated
Account"), we understand
that your client has caused USAASA to make payments Into another
account held by your client at another
bank. That is a clear and
material breach of both the terms and spirit of the Facility
Agreement.
5
... the Facilliy Agreement was granted for an initial period 12
(twelve) months and extended in January 2017 for a further period
of
3 (three) months. That extended period has expired, As such, no
further amount may be drawn by your client under the Revolving
Credit
Financing Facility and the full amount owing by your client is due
and payable.
6.
As your client has made no attempt to settle the outstanding balance
of the Facility, we sent them a letter of demand in terms
of section
345 of the Companies Act, 1973 on 24 July 2018. That letter of demand
was sent to the Sheriff for service on your client
at its registered
address prior to our client receiving your letters. A copy is
attached for your attention.
8.
We are pleased to note that your client does not dispute its
liability towards VBS Mutual Bank but our client requires that such
liability is now settled as a matter of priority.”
31.
As a result of Leratadima’s failure
to pay the amount demanded, in October 2018, VBS (in curatorship)
launched an application
for Leratadima to be finally wound-up.
32.
On 6 December 2018, Allen & associates,
acting on the instructions of Leratadima, addressed a letter to
Werksmans informing
VBS that ‘
Leratadima
does not foresee any reasonable possibility to settle the debt under
the revolving credit facility. Our instructions
are therefore not to
oppose the liquidation any further.’
33.
In the meantime, on 13 November, VBS was
placed under final winding-up by order of court at the behest of a
creditor, ‘The
Prudential Authority’. Mr Rooplal was
appointed as the liquidator of VBS by the Master of the High Court.
34.
On 11 December 2018, Leratadima was placed
under final winding-up at the behest of VBS by order of court. VBS
subsequently proved
a claim in the sum of R156 183 602.22
with interest in the insolvent estate of Leratadima. Mr Richard
Pollack was appointed
as one of Leratadima’s joint liquidators.
35.
The
liquidators of Leratadima elected to continue with the supply
contract and procured the manufacture and delivery of all outstanding
STD’s to USAASA under the supply contract, and, notwithstanding
the execution, implementation and finalisation of that agreement,
Leratadima remained hopelessly insolvent and indebted to VBS.
[10]
36.
In his capacity as liquidator, Mr Rooplal
was tasked with the recovery of debts owed to VBS for the benefit of
its creditors. To
this end, he launched the present application
against the respondents on behalf of VBS (in liquidation).
Grounds of opposition
37.
The respondents aver that they should be
released from liability under their surety agreements on account of
VBS’s conduct
in ‘unlawfully and unilaterally’
suspending (and ultimately terminating) the revolving credit
facility, which action
on the part of VBS unlawfully prejudiced the
sureties, warranting their release from the suretyships.
38.
As earlier indicated, certain procedural
and legal objections and additional defences were raised for the
first time in the respondents’
heads of argument. Before
dealing therewith, it is apposite to consider the respondents’
version in the answering affidavit
juxtaposed against the defences
proffered in the heads of argument.
Respondents’
version in the answering affidavit
Tacit extension of
facility agreement during June/July 2016
39.
The
respondents aver that as at March 2018 (being the time when all
credit facility accounts at VBS were suspended pursuant to its
placement under curatorship) the revolving credit facility had not
expired, nor was Leratadima in breach of its obligations under
the
facility agreement. This is because ‘the revolving credit
facilities and the facility agreement was extended’ by
agreement between the parties. Although the respondents failed to
plead whether such agreement was written or oral, who represented
the
parties in its conclusion, where and when precisely it was concluded,
it was averred later in the answering affidavit that
‘
factually,
as at March 2018, there existed (at least) a tacit extension of the
credit facility on the same terms and conditions
as originally
entered into, closely tied to the ultimate successful execution and
finalisation of the USAASA agreement’
.
The respondents state that the tacit extension occurred in the
following circumstances: pursuant to an arbitration award being
granted in June 2017,
[11]
Leratadima and VBS ‘agreed that the revolving credit facilities
of R250 000 000.00… would remain intact’
to
enable Leratadima to supply and deliver a remainder of 324 000
STD’s to USAASA. After June/July 2017, VBS continued
to make
the revolving credit facilities available to Leratadima and funds
from USAASA in respect of proceeds generated from the
supply contract
continued to be paid into the VBS account.
40.
It is noteworthy that this version
presupposes an
extant
facility agreement, the duration of which had been tacitly extended
by the parties after its termination date, which, as per the
second
addendum thereto, was on 25 April 2017.
Provision of credit
facilities under the facility agreement were linked to the successful
execution and finalisation of the supply
contract.
41.
The
respondents aver that the revolving credit facility would not have
existed had it not been for the supply contract. The supply
contract
and its successful execution or completion was, to the knowledge of
VBS, ‘closely tied’ to the credit facility,
which
facility was necessary to enable Leratadima to carry out its
obligations ‘in order to ultimately benefit’ from
the
supply contract. Expressed differently, the contention is that the
availability of funds in the revolving credit facility was
necessary
to enable Leratadima to fulfil its contractual obligations to USAASA
and to secure the balance of payments owing to it
by USAASA, which
proceeds would be utilised for purposes of servicing the facility
agreement (i.e., to enable Leratadima to discharge
its repayment
obligations to VBS under the facility agreement). In their heads, the
respondents emphasise that the express wording
of the facility
agreement ‘make it clear that the proceeds of the supply
contract would be utilised for purposes of servicing
the facility
agreement.’
[12]
42.
The respondents further aver that the
period during which credit facilities would be made available to
Leratadima under the facility
agreement was therefore linked to the
period of manufacturing under the supply contract and its successful
ultimate completion.
Release
from suretyships on account of VBS’s alleged unlawful
suspension/repudiation of the facility agreement
[13]
43.
The respondents aver that they should be
released from their indebtedness arising from their suretyships on
account of VBS’s
alleged repudiation of the terms of an extant
facility agreement (the duration of which was tacitly extended) the
allegation being
that the decision by the curator to suspend the
revolving credit facility, which was an arms- length transaction
between VBS and
Leratadima ‘without proper reason and a
rational decision’ - in circumstances where Leratadima was not
in breach of
its obligations under the facility agreement and which,
by March 2018, had not expired - amounted to a repudiation by VBS of
its
obligation in terms of the facility agreement to make the
revolving credit facilities available to Leratadima until such time
as
the entire USAASA contract was completed. As a result of VBS’s
repudiation of the facility agreement by virtue of its unreasonable
and irrational decision to suspend the credit facility in March 2018
and its concomitant refusal to make further funding available
to
Leratadima, the latter was unable to complete the USAASA contract and
secure the balance of payments owning to it by USAASA.
The suspension
(and ultimate termination) of the credit facility was to the
detriment and prejudice of the sureties, as, so it
was averred, the
obligations of the sureties would never have arisen had the supply
contract with USAASA been completed with the
available revolving
credit facility, which was intact until such time as ‘all
facilities were simply suspended resulting
from fraud not germane to
the principal debtor Leratadima, or the sureties.’ In those
circumstances the sureties contend
that it would be against public
policy and
contra bones mores
to
seek judgment against the sureties and they are accordingly entitled
to be released from their obligations under the suretyships.
I deal
with this defence below.
Defences raised in the
respondents’ heads of argument
Law points
Sureties are liable
only in respect of the capital amount advanced to Leratadima (and not
interest thereon) in terms of suretyships
and the amount of the
sureties’ indebtedness is not determinable from the founding
affidavit
44.
The respondents contend that in terms of
the suretyships, the sureties are liable for monies lent and advanced
to the principal
debtor
excluding
interest. Even if the suretyships are
capable of more than one meaning, the suretyships ought to be
interpreted
contra proferens,
i.e.,
against the author thereof, being the bank/applicant. If so
interpreted, the respondents could only be liable in respect of
the
actual capital lent and advanced by the applicant to the principal
debtor.
45.
The respondents’ further contend that
the applicant has failed to establish the amount of the capital
advanced by VBS to the
principal debtor in its founding affidavit and
the court cannot grant judgment for an undetermined amount of money.
The certificate
of indebtedness of the principal debtor relied upon
in the founding affidavit includes interest that has accrued and has
been capitalised,
which the sureties are not liable for. This, so say
the respondents, is similarly evident from the bank statement annexed
to the
founding papers as annexure ‘FA9’.
46.
The respondents argue that the facility
agreement was concluded on 15 January 2016 in terms of which VBS
agreed to lend and advance
a capital amount of R100 million to the
principal debtor. On the same day, the respondents signed written
suretyships in terms
whereof they acknowledged their liability to the
applicant pertaining to the capital lent and advanced to the
principal debtor
i.e., the loan amount of R100 million, excluding any
interest.
47.
The respondents further argue that on a
proper interpretation of the suretyships, each surety could only be
liable to the applicant
for an amount of R100 million jointly and
severally with the principal debtor and the other surety. The
collective maximum liability
of the sureties would accordingly not
exceed R100 million.
48.
The respondents contend that on the case as
formulated in the founding affidavit, VBS has failed to set out facts
in support of
the capital amount advanced and therefore the quantum
of the sureties’ indebtedness cannot be determined on the
papers and
the application falls to be dismissed on this ground
alone.
Failure to demonstrate
that the suspensive conditions in the facility agreement were
complied with.
49.
The respondents take the point that the
applicant failed to allege or prove in its papers that the conditions
precedent in the facility
agreement were complied with or that they
were waived by the applicant on or before the signature date of the
facility agreement.
50.
The respondents further contend that absent
proof of a valid written credit agreement, there is ‘simply no
underlying
causa.
Absent
a
causa
,
the applicant cannot hold the principal debtor liable nor the…
sureties’. In so far as the applicant could hold the
principal
debtor liable in terms of a possible enrichment claim for ‘certain
capital amounts advanced’, it was contended
that this has
nothing to do with the sureties and is in any event not the case
advanced by the applicant in the application.
New defence on merits
Conclusion of a ‘new
independent credit agreement’ between VBS and Leratadima
51.
The respondents contend that clauses 2.1
and 2.2 of the facility agreement make it clear that the proceeds of
the supply contract
would be utilised for purposes of servicing the
facility agreement. The ability on the part of the principal debtor
to service
its obligations in terms of the USAASA contract is
accordingly related to and dependent on the continued existence of
the facility
agreement. As the anticipated duration of the supply
contract changed (by virtue of USAASA’s unilateral suspension
of the
supply contract in 2016), which culminated in arbitration
proceedings between USAASA and Leratadima and which in turn caused a
significant delay in the finalisation of the supply contract), so too
did the duration of the facility agreement change.
52.
The disputes between Leratadima and USAASA
were partially settled in June 2017. A settlement agreement concluded
pursuant thereto
was made an arbitration award. It terms of the
award, Leratadima resumed the supply of the remaining 324 000
STB’s due
to USAASA under the supply contract.
53.
Absent a waiver/
pactum
de non petendo,
as at June 2017, the
facility agreement (read with the second written addendum thereto),
terminated as a result of the effluxion
of time on 25 April 2017. The
respondents contend that as a result of the termination of the
facility agreement, a
new and
independent credit agreement
was
concluded between VBS and Leratadima in terms of which the credit
facility of R250 million would remain intact and credit would
be
extended to Leratadima to enable the latter to service the supply
contract until the finalisation thereof. The respondents argue
that
the new credit agreement has independent contractual force and does
not purport to amend or vary the facility agreement that
‘lapsed
several months’ earlier. The respondents further contend that
this is what the parties always envisaged and
is the only
interpretation that makes commercial sense. They submit that the
granting of further credit to Leratadima for ‘another
year’
after the facility agreement had lapsed cannot be interpreted to be
an indulgence on any interpretation of the facts.
Discussion
54.
On the affidavits filed, there is no
controversy about the fact that VBS loaned and advanced monies on
credit to the principal debtor,
who utilised same to fund the
manufacture of STB’s in order to supply and deliver same to
USAASA under the supply contract.
USAASA in turn paid for STD’s
supplied and delivered by way of electronic transfer of monies into
the VBS account, at least
until such time as Leratadima (represented
by the respondents) caused USAASA to make payments into Leratadima’s
Absa bank
account. Put differently, i
t
is it is not in dispute on the papers that the
facility
agreement was considered by both applicant and repsondents (including
the principal debtor whom the respondents represented)
to be valid,
binding and enforceable and that it was implemented, in that funds
were advanced to Leratadima, which Leratadima utilised
to fulfil its
obligations to USAASA under the supply contract. Payments by USAASA
were made into the VBS account, at least until
such time as USAASA’s
payments were diverted by Leratadima’s representative/s to
Leratadima’s Absa account.
55.
The respondents acknowledge that monies
loaned and advanced by VBS were required by Leratadima to enable the
latter to fulfil its
obligations under the supply contract with
USAASA. The supply contract was worth approximately R344 million. By
the time the credit
facility was suspended, Leratadima had supplied
and delivered a large quantity of STD’s to USAASA for which it
had been paid.
There is no suggestion by the respondents in their
answering affidavit that Leratadima was not obliged to repay the
monies advanced
to it by VBS, nor is there any dispute that
Leratadima incurred liability for the payment of interest, fees and
charges as provided
in the facility agreement. It is common cause
that the design of the facility agreement was such that Leratadima
would utilise
the payments made by USAASA into the VBS account to
repay the debt arising from the extension of credit by VBS to
Leratadima. That
is why Leratadima agreed, in terms of the facility
agreement, that
all
proceeds from the supply contract were to be deposited into the VBS
account and that Leratadima was not entitled, without the written
consent of VBS, to change the VBS account details for as long as any
monies remained outstanding by Leratadima to VBS. Despite
receiving
and utilising funds that were loaned and advanced by VBS, Leratadima
failed to repay the balance of its outstanding indebtedness
to VBS in
full.
56.
VBS was
entitled
to
prima
facie
prove
the extent of the principal debtor’s liability by means of a
certificate, which it has done. The certificate is in any
event
supported by t
he bank
statement, annexure ‘FA 9’ to the founding affidavit,
which reflects the quantum of the principal debt, as at
1 May 2021,
in the amount of R224 165 264.43. This amount included
accrued interest, as capitalized, and bank fees and
charges debited
against the account. The amount reflected in ‘FA9’ (the
facility account bank statement) is the self-same
amount that was
certified by a manager of VBS as the balance owing by the principal
debtor to VBS. The certificate of balance is
attached as annexure
‘FA14’ to the founding affidavit. Par 2 of the
certificate reads as follows:
“
2.
In my capacity as the Collections Manager of VBS, I do hereby certify
that
VBS (sic) and (sic)
Leratadima Marketing Solutions (Pty) ltd is indebted to VBS in the
amount of R224 165 264.43 (Two hundred and twenty four million,
one
hundred and sixty five thousand, two hundred and sixty fur rand and
forty three cents) as at 1st May 2021 in respect of monies
loaned and
advanced by VBS to
and (sic)
Leratadima Marketing Solutions (Pty) Ltd for the contract Finance
Account.”
57.
Criticisms were levelled by the
respondents’ counsel at the obvious typographical errors
appearing in the above quoted extract
of the certificate, which are
identifiable by reference to the highlighted portions in order to
contend that no reliance can be
placed on the certificate. The
certificate was provided by the applicant to establish the amount of
the principal debtor’s
indebtedness, as supported by the
contents of the facility account in ‘FA9’. There has
never been a contention that
VBS is indebted to itself and it is
common cause that monies were loaned and advanced to Leratadima by
VBS. The obvious typographical
errors appearing in the certificate do
not render it unreliable. Nor does the reference therein to a
‘contract finance account’
detract therefrom. The
addendum (annexure ‘FA8’ to the founding affidavit)
specifically refers to a ‘contract
financing facility’
and such addendum was incorporated by its express terms into the
facility agreement (the contract), whilst
‘FA 9’ is
indisputably the finance account pertaining thereto. Save for
submitting that the certificate cannot be relied
on to establish the
sureties’ indebtedness as it contains accrued interest for
which the sureties are not liable, the respondents
did not challenge
the correctness of the calculations appearing in the certificate in
the answering affidavit. Nor did they put
up evidence to refute the
allegation in the answering affidavit that the amount claimed to be
owing by the principal debtor was
due and payable.
58.
At
the time that VBS claimed repayment of the debt in terms of its
statutory demand, as at 23 July 2018, the principal debtor’s
indebtedness amounted to R152 071 422,68, as evidenced by
the bank statement, annexure ‘FA9’. Liability to
repay
such indebtedness was acknowledged by Leratadima in the letter of 23
July 2018 addressed by its erstwhile attorneys to VBS’s
attorneys. Leratadima admitted its inability to repay its undisputed
indebtedness to VBS in its erstwhile attorney’s letter
of 23
July 2018, which inability to pay the undisputed amount claimed to be
due, owing and payable ultimately culminated in its
final
liquidation. On the unrefuted version of the applicant, the
respondents were the persons who represented Leratadima in all
its
dealings with VBS. As such, they would have had first-hand knowledge
of the incurrence and extent of the indebtedness from
time to time.
There is nothing in the papers to suggest that the respondents,
representing Leratadima, ever queried or disputed
the contents of the
facility account statement, annexure ‘FA9’ to the
founding affidavit (or any other bank statement
pertaining to the
credit facility) prior to the institution of these proceedings. In
the answering affidavit, the respondents baldly
denied the
allegations in par 43 of the founding affidavit
[14]
without putting up any evidence to dispute the accuracy of the
contents of ‘FA9’ and without seriously and unambiguously
addressing the allegations made in the founding affidavit.
[15]
In their heads, the respondents took the point that the sureties are
not liable for interest accrued on the principal debt, pointing
out
that ‘FA9’ contains accrued interest for which the
sureties are not liable.
59.
At the hearing of the matter, the applicant
abandoned any claim against the respondents in respect of accrued
interest on the outstanding
amount owed by the principal debtor. It
thus became unnecessary to determine the respondents’ defence
pertaining to the respondents’
status as capital sureties or to
interpret clause 3 of the suretyships in terms of which interest was
excluded. In doing so, the
applicant significantly decreased its
claim against the sureties from a total combined claim of R200
million to a claim of R100
million, payable by the respondents on a
joint and several basis.
60.
The
respondents took the point in their heads that the capital amount for
which the sureties undertook liability is not determinable
as no
factual evidence of the capital amounts advanced to the principal
debtor were alleged in the founding affidavit. This point
is in my
view contrived. The capital amount advanced in terms of the facility
agreement to Leratadima is easily determinable and
calculable from
the contents of annexure ‘FA9’ to the founding affidavit.
It requires no more than the adding up of
the amounts of the capital
debits (VBS’s advances in respect of payment of Leratadima’s
suppliers together with costs
and charges payable under the facility
agreement) and capital credits (USAASA’s payments) appearing on
‘FA9’
and subtracting the total amount of credits from
the total amount of the debits. The applicant performed such exercise
(i.e., the
adding up of amounts excluding interest pertaining to the
principal debtor’s indebtedness) for purposes of oral argument
tendered at the hearing of the matter,
[16]
which revealed a capital indebtedness sans interest in the amount of
R104 331 386.13. The respondents did not consider
it
necessary to perform such exercise, their counsel merely advocating
during presentation of oral argument that the spreadsheet
provided by
the applicant’s counsel during oral argument would not be
considered and is in any event ‘denied’.
61.
In
the answering affidavit the respondents rely on an extant facility
agreement, which was alleged to have been tacitly extended
on the
same terms and conditions as contained in the original written
agreement and which was in force and implemented until March
2018
when the facility agreement was unilaterally suspended by VBS whilst
under curatorship. Significantly, the respondents did
not plead that
the agreement, as tacitly extended, either excluded the conditions
precedent in clause 5 of the original written
memorial or that such
conditions were unfulfilled. In contradistinction to the pleaded
defence, in their heads, the respondents
contend for the ‘lapse’
by effluxion of time of a binding facility agreement that was extant
until its termination
by effluxion of time in April 2016, followed by
the conclusion thereafter of a new and independent credit agreement
between VBS
and Leratadima. Juxtaposed against or incompatible with
this version, the respondents raise a legal point in their heads,
namely,
that the applicant failed to make out a cause of action in
the founding affidavit in that it failed to allege and prove the
conclusion
of a valid and enforceable revolving credit facility
agreement for want of pleading and providing factual evidence that
the suspensive
conditions contained in clause 5 of the facility
agreement were either fulfilled or timeously waived.
[17]
62.
It bears mention that none of the defences,
which are mutually destructive, were pleaded or raised by the
respondents in the alternative.
63.
Whilst
it is open to a party to raise a legal point
in
limine
that the founding affidavit does not make out a case for the relief
claimed,
[18]
the manner or
circumstances in which it may do so are not unrestricted. As pointed
out by the Supreme Court of Appeal in
Southern
Litigation
[19]
“…
It
is that if a point of law emerges from the undisputed facts before
the court it is undesirable that the case be determined without
considering that point of law. The reason is that it may lead to the
case being decided on the basis of a legal error on the part
of one
of the parties in failing to identify and raise the point at an
appropriate earlier stage.
[20]
But
the court must be satisfied that the point truly emerges on the
papers, that the facts relevant to the legal point have been
fully
canvassed and that no prejudice will be occasioned to the other
parties by permitting the point to be raised and argued.
[21]
”
(emphasis
added) (footnotes included)
64.
In the present case, no facts relevant to
the legal point were canvassed at all in the papers, let alone
fully
canvassed in the papers. The prejudice to the applicant is
self-evident. Had the relevant facts germane to the point been
canvassed
in the papers, the applicant would have had the opportunity
to dispute same and/or to deal therewith by means of putting up
evidence
in rebuttal.
65.
That the facility agreement was binding on
both parties and enforceable, was not challenged in the answering
affidavit. In terms
of the second addendum:
“
2.4
The Customer
[Leratadima]
acknowledges
the repayment arrangement as set out in the Main Agreement shall
continue to be binding on the customer;
2.5 All other terms of
the Main Agreement shall remain binding and enforceable on both
parties.
This
Addendum is attached to and made part of the Main Agreement signed by
and between the Customer and the Bank.”
66.
Moreover,
as earlier mentioned, the respondents relied on an extant facility
agreement in the answering affidavit, with the revolving
credit
facility not having expired as at March 2018 by virtue of an alleged
tacit extension thereof, coupled with VBS’s breach
of the terms
thereof, entitling the sureties to the release from their obligations
under the suretyships.
[22]
The
respondents’ version that the facility agreement was tacitly
extended is premised on the fact that a binding and enforceable
agreement was in place, in other words, that the main agreement had
not come to an end, whether because the suspensive conditions
were
not fulfilled or because of its extension. Significantly, in the
answering affidavit the respondents did not allege that the
suspensive conditions in the tacitly extended facility agreement on
which they relied, were not fulfilled. As pointed out in
Bosch:
[23]
“…
the
effect of non-fulfilment of a suspensive condition is that the
contract comes to an end automatically. That follows necessarily
from
the fact that no action lies to compel the performance of a
suspensive condition. If there is no right to compel performance
there can be no question of a breach warranting a cancellation of the
contract.’ (Footnote omitted.)”
A
fortiori,
there
can be no question of a breach in the form of a repudiation which may
be accepted by the innocent party in order to compel
performance of
an agreement that has not come into existence.
67.
In
Di
Guilio,
[24]
Van
Zyl J conveniently summarised what a claim against a surety entails.
In that case the court accepted, as do I, that the invalidity
of the
main agreement is a special defence that is required to be pleaded,
supported by evidence.
68.
For the reasons given, I conclude that the
respondents were not permitted to raise the invalidity of the
facility agreement in the
manner in which they chose to do so, ie,
belatedly in their heads of argument and as such, their point
pertaining to the invalidity
of the main agreement cannot be upheld.
69.
It might be
useful at this point to have regard to the applicant’s cause of
action in the application, as set out in the founding
affidavit.
70.
The applicant’s case is that the
respondents stood surety for the obligations of Leratadima, a company
that had borrowed considerable
amounts from VBS. Clause 3 reads, in
relevant part, as follows:
“
Hereby
bind myself to the
Creditor as surety for and co-principal debtor in solidum with
Leratadima...on the terms and conditions contained
in this Suretyship
Undertaking for the payment of R100 000 000.00 (One Hundred Million
Rand),excluding interest, which the Principal
Debtor does now or will
at any future time owe to the Creditor from monies loaned and
advanced. Without limiting its meaning, the
word "Debt/s"
wherever it appears on this Suretyship Undertaking includes every
claim, indebtedness, liability, damages
or any other commitment,
direct or indirect of any nature from whatsoever cause without
limitations, Debts not yet due and payable
and unliquidated Debts."
71.
The
conclusion of the written suretyships was not in dispute on the
papers.
The suretyships are valid, extant and form the basis of VBS’s
claim against the sureties.
In terms of clause 3 of the suretyships, the liability of the
sureties was not restricted to the principal debtor’s
indebtedness
arising only from the facility agreement, but included
expansive liability for any indebtedness
of
any nature from whatsoever cause
in
respect of monies loaned and advanced by VBS to the principal debtor.
The only limitation of liability in terms of the suretyships
was in
respect of the amount the sureties undertook to pay, which was
limited to R100 million, excluding interest, as became common
cause
between the parties by the time the matter was argued. The principal
debtor’s liability arose from monies loaned and
advanced to
Leratadima in terms of the facility agreement (including interest,
costs and charges debited to the facility account)
the balance of
which was shown by the applicant to be due, payable and owing but
which was never repaid by the principal debtor
to VBS.
[25]
The
conclusion of the facility agreement and its written addenda,
including the express terms thereof were not disputed in the
answering affidavit. That the balance of monies loaned and advanced
to Leratadima was due and payable but not repaid, was likewise
not
refuted by the respondents in their papers. More significantly,
it
was not in dispute that the
source
of indebtedness (
causa
debiti
)
in terms of the suretyships was one in respect of which the
respondents undertook to be liable consequent upon the principal
debtor’s default of payment of a debt that was due, owing and
payable.
72.
The
respondents rely on a tacit extension of the facility agreement on
the same terms as the original agreement, yet which which
incorporated a new or additional term that obliged VBS to make the
credit facility funds available until the ultimate completion
of the
supply contract (whenever that happened to occur). It is noteworthy
that the version is in conflict with the terms of the
written
facility agreement, which expressly provided for a termination date,
which was extended in writing by no more than three
more months in
terms of the second addendum thereto. Furthermore, the alleged tacit
extension of the facility agreement on terms
not expressly embodied
in the written memorial offends against the ‘whole agreement’
and ‘non-variation’
clauses therein. Any agreement
between the parties and which was not recorded in writing and signed
by or on behalf of the parties
would be unenforceable by virtue of
the non-variation clause in the facility agreement.
[26]
No explanation is given by the respondents as to why, if the period
during which credit facilities would be made available to Leratadima
under the facility agreement was always linked to the period of
manufacturing under the supply contract and its successful ultimate
completion, a termination date had been expressly agreed to in the
agreement read with its addenda. The further difficulty with
the
version is that the importation of a new or additional term regarding
the duration of the facility agreement is in any event
in obvious
contradistinction to the allegation that the extended agreement was
on the same terms and conditions as embodied in
the initial written
memorial, which had expressly provided for an extended termination
date per the second addendum thereto. If
that be so, the facility
could not, as a consequence of the provisions of clause 14, have been
extended in any manner other than
in writing. The respondents’
version in this regard, aside from being inherently implausible, is
simply not legally tenable,
given that it is irreconcilable with the
express terms of the facility agreement, read with the addenda
thereto, and is in any
event in conflict with the version proffered
in the heads concerning the conclusion of a new agreement (as opposed
to the tacit
extension of an existing agreement).
73.
For
these reasons I conclude that the version of a tacit extension of the
facility agreement on the basis that that it would endure
until the
final completion of the supply contract is not tenable
[27]
or sustainable. It follows axiomatically that the alleged repudiation
by VBS of an obligation to provide credit facilities to Leratadima
until such time as all STB’s had been manufactured, supplied
and delivered by Leratadima to USAASA under the supply contract,
cannot be sustained.
74.
The
defence pertaining to the release of the sureties from liability
under the suretyships is premised on the alleged unlawful suspension
of credit facilities after VBS was placed under curatorship, in
alleged breach of its obligation to make the credit facilities
available until the final completion of the supply contract, which
precluded Leratadima from accessing funds with which to manufacture
a
number of outstanding STB’s under the supply contract. As
stated in the founding affidavit, in March 2018 the facility
was
suspended by the appointed curator of VBS under powers conferred on
him by the Minister of Finance, which included the powers
contained
in s 69(1)(c) of the Banks Act, 94 of 1990, as is apparent from the
letter of appointment, annexure ‘FA3’
to the founding
affidavit. The curator’s entitlement to avoid further funds
being lent and advanced to Leratadima by means
of the suspension was
not disputed by the respondents in the answering affidavit. In their
heads, they contend that reference to
s 69(3)(c) was impermissibly
raised in the replying affidavit for the first time. I do not agree.
The evidence tendered in the
replying affidavit did not constitute
impermissible new matter because it was tendered in rebuttal of the
respondents’ allegations
in the answering affidavit that the
curator
unlawfully
refused to advance further funds to Leratadima. The replying
affidavit further sets out facts relating to Leratadima’s
breach
of the terms of the facility agreement by diverting payments
from USAASA to Leratadima’s Absa Bank Account, for purposes of
refuting the allegation in the answering affidavit that Leratadima
was never in breach of the facility agreement. To borrow from
the
words of Leach JA in
Lagoon
Beach:
[28]
“
[T]he
appellant, as respondent
a quo,
did
not seek to avail itself of the opportunity to deal with the
additional matter …set out in reply, and I see no reason
why
these allegations should therefore be ignored.
”
.
75.
The respondents contend in their heads of
argument that reliance by the applicant on s 69(3)(c) of the Banks
Act is misplaced for
the reasons provided in par 7 therein. These
submissions were not pursued at the hearing of the matter and in any
event do not
support the supervening impossibility defence raised by
the respondents to the applicant’s claim. The facts relied on
in
the answering affidavit in support of the respondents’
supervening impossibility defence, which they contend entitles them
to a release from the suretyships (summarised in par 43 above) were
in my view refuted in the replying affidavit, where the applicant
demonstrated that Leratadima’s inability to fulfil its
obligations to USAASA was occasioned by the manner in which
Leratadima
was managed prior to its liquidation, illustrated by its
diversion of payments into its Absa Bank account in breach of its
obligations
to pay all proceeds from USAASA into the VBS account
whilst any existing indebtedness to VBS remained unsettled, including
conduct
relating to the cause of Leratadima’s insolvency. In
any event, Leratadima’s outstanding obligations to USAASA were
indeed fulfilled when Leratadima’s liquidators procured the
manufacture, supply and delivery of all remaining STB’s
to
USAASA and received payment in respect thereof from USAASA,
notwithstanding which Leratadima remained hopelessly insolvent.
76.
In
Davidson,
[29]
the
Supreme Court of Appeal affirmed the legal position that governs the
release of sureties from their obligations under a suretyship
agreement, as follows:
“
As
a general proposition prejudice caused to the surety can only release
the surety (whether totally or partially) if the prejudice
is the
result of a breach of some or other legal duty or obligation. The
prime sources of a creditor’s rights, duties and
obligations
are the principal agreement and the deed of suretyship. If, as is the
case here, the alleged prejudice was caused by
conduct falling within
the terms of the principal agreement or the deed of suretyship, the
prejudice suffered was one which the
surety undertook to suffer.
Counsel who drafted the plea was therefore on the right track when he
sought to base his case upon
prejudice which flowed from the breach
of an obligation, contractual in the present circumstances. In the
event, however, Davidson
failed to prove such a breach.”
77.
In
the present matter, the respondents based their case on the alleged
breach of a contractual obligation by VBS under the alleged
tacitly
extended facility agreement, a version that I have already rejected
as unsound and untenable. In so far as the respondents
averred that
their obligations in terms of the suretyships would never have arisen
had the supply contract with USAASA been completed
with the available
revolving credit facility, no primary facts were disclosed in support
thereof. The insurmountable hurdle, as
regards the proposition, is
that the allegations, being devoid of primary facts, remain
speculative and as such, amount to inadmissible
supposition.
[30]
In any event, the fact of the matter is that the supply contract was
completed, as earlier indicated. Had the respondents (acting
on
behalf of Leratadima) not diverted USAASA’s payments in the
aggregate total amount of R102 546 219.74 to Leratadima’s
Absa bank account, the balance of the principal debtors indebtedness
to VBS would per force have been considerably less. For all
the
reasons given, the release defence must fail.
78.
As regards the defence raised in the
respondents’ heads of argument that a ‘new independent
credit agreement’
was concluded between VBS and Leratadima,
suffice it to say that this was not something that could be raised
for the first time
in the heads of argument. It was incumbent upon
the respondents to plead this defence in the answering affidavit,
supported by
evidence, if they wished to rely on same. The
respondents failed to do so.
79.
It is also immediately apparent that this
version is at variance with respondent’s pleaded case in the
answering affidavit
viz a tacit extension of the facility agreement
on the same terms and conditions as embodied in the written facility
agreement,
which
ex facie
the written memorial did not contain the term relating to the
duration of the facility as contended for in the new credit
agreement.
In their heads, the respondents assert only one term of
the new agreement, namely,
that the
credit facility of R250 million would remain intact
(i.e. credit to that value would be extended to the principal debtor
to enable it to service the supply contract)
until
such time as the supply contract had been ‘finalised’
.
Presumably finalisation entailed the supply and delivery of all
outstanding STB’s under the supply contract by Leratadima
with
payment therefore being effected by USAASA. This begs the question:
which version is correct? The tacit extension alleged
in the
answering affidavit or the new agreement as contended for in the
heads? Assuming, for argument purposes, the correctness
of the
averments made under oath in the answering affidavit (momentarily
leaving aside the validity of a tacit extension of the
facility
agreement) then the tacitly extended facility agreement would have
included its written terms and none other, having regard
to the
provisions of clause 14.1 thereof. But therein lies the difficulty
for the respondents: clause 14.4 precluded any further
extension of
the facility agreement unless an agreement to extend its duration was
recorded in writing, signed by both parties.
As this did not occur,
any tacit extension, which was contractually prohibited unless in
writing, was thus unenforceable.
80.
No
doubt mindful of the legal implications of its pleaded version, the
respondents then asserted for the first time in their heads
of
argument that a new and independent credit agreement had been
concluded between VBS and Leratadima sometime after the lapse
of the
facility agreement by effluxion of time, which new agreement
contained the term contended for, ostensibly to avoid the
consequences of clause 14 of the alleged (tacitly) extended facility
agreement. The first difficulty with the proffered argument
is that
’argument is not evidence and it is not given under oath. It is
merely a persuasive comment made by the parties or
legal
representatives with regard to questions of fact or law. Argument
does not constitute evidence, and cannot replace evidence
.’
[31]
The second difficulty is that it is at variance with the respondents’
pleaded case. The third difficulty is that a party
seeking to rely on
an agreement is required to plead and prove same. Such party is
required in motion proceedings to provide factual
particularity of
whether such agreement was written or oral; who on behalf of the
parties entered into the agreement; the place
where it was concluded,
the date on which it was concluded and all the relevant terms
thereof, to enable the opposing party to
be apprised of the case it
has to meet and if in dispute, to enable such party to refute the
version proffered by the party relying
on the agreement.
[32]
As was affirmed recently in
Strohmenger,
[33]
g
enerally,
a party must plead all facts material to the cause of action (or as
in the present case, the defence sought to be advanced)
against the
opposite party.
[34]
In
Molusi
,
[35]
the Constitutional Court put it thus:
“
It
is trite law that in application proceedings the notice of motion and
affidavits define the issues between the parties and the
affidavits
embody evidence. As correctly stated by the Supreme Court of Appeal
in Sunker: ‘If an issue is not cognisable
or derivable from
these sources, there is little or no scope for reliance on it. It is
a fundamental rule of fair civil proceedings
that parties . . .
should be apprised of the case which they are required to meet; one
of the manifestations of the rule is that
he who [asserts] . . . must
. . . formulate his case sufficiently clearly so as to indicate what
he is relying on.”
81.
The respondents
contend in their heads of argument that VBS and Leratadima agreed
that the credit facility of R250 million would
remain intact to
enable the latter to supply and deliver the remainder of 324000STB’s
to USAASA. Thereafter, VBS continued
to make the credit facility
available to Leratadima and VBS continued to receive funds from
USAASA in respect of proceeds generated
from the USAASA agreement. In
other words, pursuant to the lapse of the facility agreement, the
parties agreed on credit being
given to Leratadima until the
finalisation of the supply contract. The respondents submit that this
‘is what the parties
had always envisaged, and is the only
interpretation that makes commercial sense.’ The respondents
further submit that the
granting of credit to the applicant for
another year after the facility agreement had lapsed ‘cannot be
interpreted to be
an indulgence on any interpretation of the facts. I
disagree for reasons that follow.
82.
Aside from being impermissibly
raised in the heads of argument, the contended for new agreement
lacks particularity in important
respects, such as to where the
agreement was concluded, the date on which it was concluded, whether
it was written or oral, who
on behalf of the parties concluded same
and all relevant express, implied or tacit terms that governed same.
Affidavits in motion
proceedings are a combination of pleadings and evidence and they must
therefore contain the factual averments,
in the form of primary
facts, necessary to support the cause of action or defence sought to
be made out. As this defence was neither
pleaded nor supported by
admissible evidence, it cannot be sustained.
83.
In any event, as is evident from ‘FA9’
to the founding affidavit, after the termination of the agreement in
April 2017,
a total of four further substantial payments were
received from USAASA. The last draw-down on the credit facility
occurred on 3
November 2017, (just over 6 months after the lapse of
the facility agreement) after which date the last two of USAASA’s
payments
were received on 8 December 2017 and 8 January 2018
respectively. The facts bear witness that VBS had accommodated the
appellants,
having had no contractual obligation to do so, likely
because it entertained the hope of securing further payments from
USAASA
in reduction of the huge amount then outstanding to it, which
funds, in accordance with the design of the facility agreement, had
been utilised in reduction of Leratadima’s indebtedness to VBS
and served as a form of security to VBS to obtain repayment
of the
debt. In terms of the provisions of clause 14 of the facility
agreement, the fact that VBS indulged Leratadima by continuing
to
extend credit and receive payment from USAASA, did not and could not
serve as a relinquishment of any of its rights under the
facility
agreement or any waiver thereof or denude its ability to rely on the
terms of the facility agreement.
84.
In my view, the applicant has established
its entitlement to the relief sought which I intend to grant in terms
of counsel’s
revised draft order. The general rule is that
costs follow the result. I see no reason to depart therefrom. The
belated abandonment
of VBS’s claim in relation to the
respondents’ liability for interest was to the advantage of the
respondents and occupied
minimal court time.
85.
Accordingly, the following order is
granted:
ORDER:
1
The first and second respondents are
liable, jointly and severally, to pay the applicant the sum of
R100 000 000.00;
2
The first and second respondents are
liable, jointly and severally, to pay interest on the amount of
R100 000 000.00 at
the prescribed
mora
rate of interest per annum, calculated
from date of demand on 28 November 2019 to final date of final
payment;
3
The respondents are jointly and severally
liable for the costs of this application on the scale as between
attorney and client.
AVRILLE
MAIER-FRAWLEY
JUDGE
OF THE HIGH COURT,
GAUTENG
DIVISION, JOHANNESBURG
Date
of hearing:
1 September 2022
Judgment
delivered
9 February 2023
[1]
See
Van
Wyk v Unitas Hospital (Open Democratic Advice Centre as Amicus
Curiae)
[2007]
ZACC 24
;
2008
(2) SA 472
(CC)
at 477 A-B.;
Minister
of Transport v Road Accident Fund and Others
(1082/2020)
[2022] ZASCA 169
(1 December 2022) at par 34.
[2]
Pangbourne Properties Ltd v Pulse Moving CC and Another
2013 (3) SA
140
(GSJ) at par 16.
[3]
See
Republikeinse
Publikasies (Edms) Bpk v Afrikaanse Pers Publikasies (Edms) Bpk
1972
(1) SA 773
(A) at 783.
The
principle was applied in
s
everal
cases that followed. See the authorities cited in paras 16 and 17 of
Pangbourne
supra.
[4]
See
Federated
Trust Ltd v Botha
1978
(3) SA 645
(A) at at 654C-F.
[5]
The
‘new matter’ involved allegations concerning the
respondents (acting on behalf of Leratadima) diverting payments
which the principal debtor (as creditor) received from USAASA (as
debtor) from being deposited into Leratadima’s bank account
held at VBS - in reduction of its indebtedness to VBS - and causing
same to be deposited into Leratadima’s bank account
held at
ABSA bank, in breach of Leratadima’s payment obligations to
VBS in terms of a written revolving credit facility
agreement
concluded between Leratadima and VBS; and further allegations that
there was an erosion of VBS’s security by
the principal debtor
and its directors.
[6]
(Borrowing
from the words of Wepener J in
Pangbourne.
)
An approach that eschews formalism where the interests of justice so
dictate has been endorsed by the Constitutional Court in
Mukaddam
v Pioneer Foods (Pty) Ltd and Others
2013
(5) SA 89
(CC) at par 39, where the following was said:
“
Flexibility
in applying requirements of procedure is common in our courts. Even
where enacted rules of courts are involved, our
courts reserve for
themselves the power to condone non-compliance if the interests of
justice require them to do so. Rigidity
has no place in the
operation of court procedures. Recently in
PFE
International and Others v Industrial Department Corporation of
South Africa Ltd
,
this Court reaffirmed the principle that rules of procedure must be
applied flexibly. There this Court said:
‘
Since
the rules are made for courts to facilitate the adjudication of
cases, the superior courts enjoy the power to regulate their
processes, taking into account the interests of justice. It is this
power that makes every superior court the master of its own
process.
It enables a superior court to lay down a process to be followed in
particular cases, even if that process deviates
from what its rules
prescribe. Consistent with that power, this Court may in the
interests of justice depart from its own rules.’
”
See
too:
Eke v Parsons
2016
(3) SA 37
(CC) at par 39, where the following was said:
“…
Without
doubt, rules governing the court process cannot be disregarded. They
serve an undeniably important purpose. That, however,
does not mean
that courts should be detained by the rules to a point where they
are hamstrung in the performance of the core
function of dispensing
justice. Put differently, rules should not be observed for their own
sake. Where the interests of justice
so dictate, courts may depart
from a strict observance of the rules. That, even where one of the
litigants is insistent that
there be adherence to the rules. Not
surprisingly, courts have often said “[i]t is trite that the
rules exist for the courts,
and not the courts for the rules”.
(footnotes omitted)
[7]
Defined
in clause 1.2.5, as the ‘facility amount’.
[8]
In
terms of paragraph 4 of the appointment letter, annexure ‘FA3’
to the founding affidavit, Mr Rooplal was afforded
the powers that
arise from section 69(3)(c) of the Banks Act, 94 of 1990, which, in
relevant part, reads as follows:
“
(3)
The Minister may, in the letter of appointment or at any time
subsequent thereto, empower the curator -
(c)
to cancel any agreement between the institution concerned and any
other party to
advance moneys due after the date of his appointment
as curator, or to cancel any agreement to extend any existing
facility,
if, in the opinion of the curator, such advance or any
loan under such facility would not be adequately secured or would
not
be repayable on terms satisfactory to the curator or if the
institution lacks the necessary funds to meet its obligations under
any such agreement or if it would not otherwise be in the interests
of the institution.”
[9]
In
the letter, reference was also made to Leratadima being in breach of
its obligations to USAASA under the supply contract for
failing to
timeously deliver a number of outstanding STD’s to USAASA and
that Leratadima required VBS to make further funding
of R25 million
under the credit facility available to Leratadima to enable it to
fund the performance of its remaining obligations
to USAASA.
[10]
This
was confirmed by Mr Richard Pollack in a confirmatory affidavit. In
his affidavit, Mr Pollack also confirmed having advised
Mr Rooplal
that during an enquiry into the trade affairs of Leratadima, the
respondents conceded that they had traded recklessly,
having used
the assets and income of Leratadima to unlawfully enrich themselves
and further, that they agreed to pay back the
proceeds appropriated
by them but which they have to date failed to do.
[11]
The
award arises from arbitration proceedings involving Leratadima and
USAASA (with the Minister of Communications also being
joined as a
party), which partially became settled in terms of a settlement
agreement concluded between the parties and which
was made an
arbitration award. USAASA had suspended the supply contract in June
2016 before the supply of 500 000 STB’s
was completed,
with the supply and delivery of 324 000 STD’s still remaining
outstanding under the supply contract. Pursuant
to the award, during
June/July 2017, Leratadima continued with the supply and delivery of
the remaining STB’s under the
supply contract, which it says
it did until March 2018 when the credit facility was suspended by
the curator of VBS.
[12]
“
The
facility agreement records the following:
2.1 The
Borrower has entered into a contract with USAASA for the supply and
delivery of Digital Terrestrial Television
Set Boxes and related
accessories under bid number USAASA/DTT/09/2014-15.
2.2 The
Borrower has approached VBS and requested VBS to provide it with the
required loan funding to fulfil the terms
of the contract.”
[13]
Paras
45- 50 of the answering affidavit.
[14]
There
it was averred that the ‘statement of account (‘FA9’)
shows that Leratdima accessed the facility funds
from 25 January
2016 until 8 March 2018. The statement of account in addition
records the running of interest which continued
to accrue on the
outstanding amount owed by Leratadima in terms of the facility.’
[15]
See
in this regard,
Wightman
t/a J W Construction v Headfour (Pty) Ltd and Another
[2008] ZASCA 6
;
2008
(3) SA 371
(SCA) at paras 12- 13.
[16]
The
extrapolation of the capital amounts (less interest) reflected in
annexure ‘FA9” to the founding affidavit - for
which the
respondents assumed liability under the deeds of suretyship - is
contained in a spreadsheet prepared by the applicant’s
counsel
and uploaded at 017-10 to 017-11 of Caselines. The spreadsheet
reflects the capital amounts advanced by the bank to the
principal
debtor, together with costs and charges for which the principal
debtor was liable (and in respect of which the sureties
undertook
liability), less payments received by USAASA in reduction of the
principal debtor’s indebtedness, which amounts
to the sum of
R104 331 386.13
.
[17]
In
Desert
Star Trading
v
No 11 Flamboyant Edleen
(98/10)
[2010]
ZASCA 148
(29
November 2010) at par 11, tThe Supreme Court of Appeal held that:
“
...It
is so that a contract of suretyship is a separate contract from that
of the principal debtor and his or her creditor. It
is however
accessory to that main contract.
Thus
for there to be a valid suretyship there has to be a valid principal
obligation. Put differently, every suretyship is conditional
upon
the existence of a principal obligation. For, as Nienaber JA put it
‘[g]uaranteeing a non-existent debt is as pointless
as
multiplying by nought’. It follows that a surety is not liable
to a person to whom the principal debtor is not liable.It
is well
settled that the general rule is that a surety may avail himself or
herself of any defences that the principal debtor
has save for those
defences that are purely personal to the principal debtor.
”
(footnotes excluded)
The
accessory nature of the contract of suretyship was emphasised by the
Constitutional Court in
Shabangu
v Land and Agricultural Development Bank of South Africa and Others
2020
(1) SA 305
(CC), which held that a suretyship cannot survive where
the underlying obligation is invalid. In that case there was no
dispute
that the principal loan agreement in terms of which the bank
loaned and advanced monies to the principal debtor was invalid as
it
involved the Land Bank exceeding its statutory powers. The principal
debtor entered into an acknowledgement of debt (‘AOD’)
to repay a reduced amount to that which was owing to Land Bank under
the invalid loan agreement. Various parties had stood surety
for the
loans advanced by the bank to the principal debtor The matter turned
on whether the taint of invalidity of the loan agreement
also
stretched to taint the AOD and the liability of the sureties in
respect of the AOD.
The
Constitutional Court however pointed out in par 33 of the judgment
that ‘
What
this judgment does not deal with are compromises by organs of state
where the validity of the agreement remains disputed.’
[18]
See,
for example,
Resisto
Dairy (Pty) Ltd v Auto Protection Insurance Company
1963 (1) SA 632
;
Marais
v Standard Credit Corporation Ltd
2002 (4) SA (A) 892 (W) at 897 A-B.
[19]
Minister
of Justice and Constitutional Development and Others v Southern
African Litigation Centre and Others
2016
(3) SA 317
(SCA) at par 24 (‘Southern Litigation’).
[20]
Van
Rensburg v Van Rensburg & andere
1963
(1) SA 505
(A)
at
510 A-C. The approach has been endorsed by the Constitutional
Court:
CUSA
v Tao Ying Metal Industries & others
(CCT
40/07)
[2008]
ZACC 15
;
2009
(2) SA 204
(CC)
para 68.
[21]
Fischer
& another v Ramahlele
&
others (203/2014)
[2014]
ZASCA 88
;
2014
(4) SA 614
(SCA)
paras 13 and 14.
[22]
See
par 37 of the answering affidavit at 014-12.
[23]
Commissioner,
South African Revenue Service v Bosch and another
[2014]
ZASCA 171
;
2015
(2) SA
174
(SCA)
para 31. See too:
Africast
(Pty) Limited v Pangbourne Properties Limited
(359/2013)
[2014] ZASCA 33
;
[2014] 3 All SA 653
(SCA) (28 March 2014), at paras
37 & 39 where the following was said:
“
[37]
A contract containing a suspensive condition is enforceable
immediately upon its conclusion but some of the obligations are
postponed pending fulfilment of the suspensive condition. If the
condition is fulfilled the contract is deemed to have existed
ex
tunc
.
If
the condition is not fulfilled, then no contract came into
existence
. Once the condition is
fulfilled,‘[t]he contract and the mutual rights of the parties
relate back to, and are deemed to
have been in force from, the date
of the agreement and not from the date of the fulfilment of the
condition, ie
ex tunc
.
[39]...
Upon signature of the agreement an inchoate agreement came into
being, pending the fulfilment of the suspensive condition.
In the
event that the suspensive condition was not fulfilled, neither party
would be bound to the agreement
.” (footnotes excluded)
(emphasis added).
[24]
Di
Guilio v First National Bank Ltd
2002
(6) SA 281
(C) at paras 26-29. There the following was said:
“
[26]
In any claim against a surety the
plaintiff must, at the outset, prove the existence of a valid
contract of suretyship. He must
then prove that the source of
indebtedness (
causa debiti
)
in terms of such agreement is one in respect of which the defendant
undertook to be liable. Finally he must prove that the said
indebtedness is due and payable
.
See the useful discussion of these requirements, with reference to
relevant authorities, in
Amler's
Precedents of Pleadings
(5
th
ed
by LTC Harms, 1998) 381-382.
[27]
If the defendant should place the amount of the claim, relating to
its composition or calculation, in issue, the necessary
evidence to
substantiate such amount must be presented by the plaintiff.
See
Moreriane
v Trans-Oranje Finansierings- en Ontwikkelingskorporasie Bpk
1965
(1) SA 767
(T)
at 769G;
Senekal
v Trust Bank of Africa Ltd
1978
(3) SA 375
(A)
at 383A.
[28]
It is trite that, if the surety should admit liability in terms of
the suretyship agreement, the plaintiff would not be required
to
lead evidence in this regard. If the amount of the claim should
likewise be admitted, no evidence of its composition or calculation
would be required. If the surety should, however, deny liability on
the basis that the principal debt was not due, the principal
would
have to prove that it was. See the
Senekal
case
(par 27 above) at 383A-F. On the other hand,
if the surety
should raise a "special" defence such as illegality,
fraud, lack of contractual capacity or lack of authority,
he would
be required to present evidence in support thereof. This is because
the facts underlying such defence are regarded as
falling beyond the
ambit of the plaintiff's cause of action. See C W H Schmidt and H
Rademeyer
Bewysreg
(4
th
ed
2000) 38-39 and the authorities cited there
.
[29]
Once the party bearing the
onus
of proof has made out a
prima
facie
case, his opponent is burdened with an
onus
of
rebuttal. Should he fail to discharge this
onus
of
rebuttal,
prima
facie
evidence would be regarded as sufficient evidence for purposes of
discharging the main
onus
of proof. See
Senekal
v Trust Bank of Africa Ltd
(par
27 above) 382H-383A; Schmidt and Rademeyer (par 28 above) 65. Even
more so would this be the case if he has personal
knowledge of facts
or information relevant to the discharge of such
onus
,
but fails or refuses to testify. Under such circumstances an adverse
inference may be drawn against him. See
Galante
v Dickinson
1950
(2) SA 460
(A) at 465;
New
Zealand Construction (Pty) Ltd v Carpet Craft
1976
(1) SA 345
(N) at 349G-H;
Hasselbacher
Papier Import and Export (Body Corporate) and Another v MV Stavroula
1987
(1) SA 75
(C) at 79F-80C;
Lazarus
v Gorfinkel
1988
(4) SA 123
(C) at 134B-135C.” (emphasis added)
[25]
Although
the respondents baldly denied in the answering affidavit that
Leratadima failed to repay all the amounts drawn down from
the
facility with interest, as a result of which Leratadima remained
indebted to VBS for the outstanding debt, which was both
due and
payable to it, such a bald denial did not engender a genuine dispute
of fact. The respondents did not deny that Leratadima
received the
loan funding (extended to it on credit by the bank), nor did they
aver or demonstrate in their papers that Leratadima
had repaid all
amounts drawn down from the facility. These were facts that lay
within the knowledge of the respondents in their
capacity as joint
directors of Leratadima, given that they represented Leratadima in
the conclusion of the facility agreement
and addenda thereto.
No
basis was laid in the answering affidavit for disputing the veracity
of the allegations in the founding affidavits in relation
to the
amount of the outstanding indebtedness at varying stages, as
reflected on ‘FA9’.
The
debt became due and payable after the termination of the facility
and at the very least, upon demand. Pursuant to the statutory
demand, Leratadima, admitted its liability in the amount then
claimed. There was no disputation or protestation by the one or
both
respondents, representing Leratadima, of the fact that the debt was
due and payable, as claimed in the statutory demand.
[26]
See
SA
Sentrale Ko-op Graanmaatskappy Bpk v Shifren en Andere
1964
(4) SA 760
(A) (“Shifren’).
Shifren
confirmed the enforceability of non-variation clauses amidst oral
amendment, and was constitutionally approved in
Brisley
v Drotsky
2002
(4) SA 1
(SCA) and
Barkhuizen
v Napier
2007
(5) SA 323 (CC).
[27]
The
respondents’ version proposes that the bank would be obligated
to extend credit to a customer even if it lacked the
necessary
finances resources to do so, as occurred when VBS was placed under
curatorship by the Minister, inter alia, in terms
of s 69(1) of the
Banks Act, and notwithstanding the erosion or inadequacy of the
security afforded to the bank by means of the
payment mechanism
provided for in the facility agreement, whereby USAASA’s
payments would be utilized to discharge Leratadima’s
indebtedness under the loan to VBS, by Leratadima’s diversion
of payments into its Absa bank account. The curator suspended
all
credit facilities at the bank pursuant to his appointment due to the
bank’s financial difficulties as envisaged in
s 69(1)(c) of
the Banks Act. In, par 12 of the replying affidavit, Mr Rooplal
clarified that this was done because VBS did not,
as at June 2018,
have the funds that Leratadima requested be advanced to it and also
because there was no longer any security
to cover the debts that had
already been incurred by Leratadima and inadequate security to cover
the advance of further funds
sought by Leratadima, precisely because
Leratadima had eroded the security previously in place by causing
USAASA’s payments
to be made into its Absa Bank account, in
breach of its obligations under the facility agreement.
[28]
Lagoon
Beach Hotel v Lehane
2016 (3) SA 143
at 152 I.
[29]
A
BSA
Bank v Davidson
2000
(1) SA 1117
(SCA)
para 19.
[30]
As
Lord Wright observed in
Caswell
v Powell Duffryn Associated Collieries Ltd
1939 (3) All ER 722
at 733: ‘
Inference
must be carefully distinguished from conjecture or speculation.
There can be no inference unless there are objective
facts from
which to infer the other facts which it is sought to establish. . .
. But if there are no positive proved facts from
which the inference
can be made, the method of inference fails and what is left is mere
speculation or conjecture.
’
see also:
R
v Blom
1939 AD 188
at 202-203 and
Joel
Melamed & Hurwitz v Cleveland Estates
1984 (3) 155 (A) 164G-165C.
[31]
See
Mhaboho
T and 117 Related Cases v Minister of Home Affairs
,
an unreported decision of Makhafola J in the Limpopo division
,Thohoyandou, delivered on 28/05/2010 under case no’s
833-1128/2007, at par 13.
[32]
It
is trite that t
rial
by ambush is not permissible. See:
Minister
of Land Affairs and agriculture v D&F Wevell Trust
2008
(2) SA 184
(SCA) at 200 E (‘
Wevell
’).
The
principal applies with equal force to motion proceedings.
[33]
Susara
Magrietha Strohmenger v Schalk Willem Victor and Another
(Case
no 1133/20)
[2022]
ZASCA 45
(08
April 2022), paras 9,10.
[34]
It
is trite that in motion proceedings, the affidavits constitute both
pleadings and evidence. See
Radebe
v Eastern Transvaal Development Board
1988
(2) SA 785
(A) at 793 E.
[35]
Molusi
and Others v Voges NO and Others
2016
(3) SA 370
(CC) at paras 27-28
sino noindex
make_database footer start
Similar Cases
VBS Mutual Bank (In Liquidation) v KPMG Incorporated (2021/8826) [2022] ZAGPJHC 567 (18 August 2022)
[2022] ZAGPJHC 567High Court of South Africa (Gauteng Division, Johannesburg)100% similar
VBS Mutual Bank (In Liquidation) v The Universal Service and Access Agency of South Africa (2021/25614) [2022] ZAGPJHC 552 (12 August 2022)
[2022] ZAGPJHC 552High Court of South Africa (Gauteng Division, Johannesburg)100% similar
VBS Mutual Bank (In Liquidation) v Universal Service and Access Agency of South Africa (2021/25614) [2022] ZAGPJHC 1012 (14 December 2022)
[2022] ZAGPJHC 1012High Court of South Africa (Gauteng Division, Johannesburg)99% similar
VBS Financial Services (Pty) Ltd v Madhandzi (36120/21) [2023] ZAGPJHC 1000 (7 September 2023)
[2023] ZAGPJHC 1000High Court of South Africa (Gauteng Division, Johannesburg)99% similar
D.V.M.T v Minister of Police (2021/51114) [2024] ZAGPJHC 921 (30 August 2024)
[2024] ZAGPJHC 921High Court of South Africa (Gauteng Division, Johannesburg)98% similar