Case Law[2023] ZAGPJHC 135South Africa
Mthethwa v Passenger Rail Agency of South Africa (PRASA) (2020/33363) [2023] ZAGPJHC 135 (14 February 2023)
High Court of South Africa (Gauteng Division, Johannesburg)
14 February 2023
Headnotes
Summary
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 135
|
Noteup
|
LawCite
sino index
## Mthethwa v Passenger Rail Agency of South Africa (PRASA) (2020/33363) [2023] ZAGPJHC 135 (14 February 2023)
Mthethwa v Passenger Rail Agency of South Africa (PRASA) (2020/33363) [2023] ZAGPJHC 135 (14 February 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_135.html
sino date 14 February 2023
IN
THE HIGH COURT OF SOUTH AFRICA,
GAUTENG
DIVISION, JOHANNESBURG
CASE
NO: 2020/33363
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: YES
DATE:
14 February 2023
In
the matter between:
MTHETHWA,
SPHAMANDLA
LYMON
Plaintiff
and
PASSENGER
RAIL AGENCY OF SOUTH AFRICA (PRASA)
Defendant
JUDGMENT
MOORCROFT
AJ:
Summary
Negligence
– defendant permitted train to travel with open doors of both
sides and to keep the doors open on both sides when
the train was
stationary – plaintiff pushed out of door on the far side of
platform – Permitting a train to operate
with open doors prima
facie negligent - defendant bore onus of rebuttal but chose not to
lead evidence – Defendant liable
in delict for plaintiff’s
damages arising from his injuries
Order
[1]
In this matter I make the following order:
1.
The defendant is liable for 100% of the agreed or proven
damages suffered by the plaintiff as a result of having fallen from a
train
at Lindela Station on 12 September 2019;
2.
The defendant is ordered to pay the plaintiff’s agreed
or taxed costs to date;
3.
The trial on quantum is postponed sine die.
[2]
The reasons for the order follow below.
Introduction
[3]
The plaintiff claims delictual damages from the defendant arising out
of an
incident at Lindela Station on 12 September 2019 when he fell
out of a stationary passenger train operated by the defendant.
[4]
It was ordered at a case management meeting that the issues of merits
and
quantum
be separated in terms of Rule 33(4) and the matter
proceeded before me on merits only.
[5]
The
plaintiff was the only witness who testified to the events
surrounding the incident. The plaintiff’s brother and the
defendant’s supervisor, both of whom arrived on the scene some
time after the incident, also testified; as did the plaintiff’s
attorney on the contents of a letter
[1]
dated 9 July 2020 where she had written that the incident occurred
when the plaintiff was ‘boarding’ the train. She
testified that this was an error caused by the questionable practice
of ‘cutting and pasting’ when the letter was written.
The
amendment
[6]
The
plaintiff’s case as pleaded was that he was ‘pushed or
dislodged’ when there was a fire in the back of the
carriage.
He lost his balance and fell out of the open door of the carriage
onto a cement platform.
[2]
He
also alleged in the particulars of claim that he was ‘boarding’
the train.
[3]
[7]
The
amendment
[4]
involved the
substitution of ‘the railway tracks’ for the reference to
‘a cement platform.’ The defendant
objected to the
amendment on the basis that the reference to ‘a cement
platform’ meant that it was the plaintiff’s
case that he
fell from the train onto the station platform, but this was of course
not the only interpretation of the phrase ‘a
cement platform’
as it could also mean a cement platform of any description near the
railway tracks, other than the station
platform.
[8]
It was not all clear from the particulars of claim whether the
plaintiff fell
onto the station platform, or onto some or other
cement platform on the other side of the train.
[9]
The application to amend was of course late and Mr Kromhout explained
that the
discrepancy between the evidence and the facts only came to
light during consultations a few days before trial. The application
was served on Sunday, the 6
th
of February 2023 and the
defendant was jusfified in opposing it.
[10]
After hearing argument I granted the amendment and ordered the
plaintiff to pay the costs of the amendment.
I concluded that the
question of negligence was not impacted by whether the plaintiff fell
on a cement platform (which may or may
not on the pleadings be the
station platform) or on a railway track.
The
plaintiff’s evidence
[5]
[11]
It was common cause that there are two railway lines at Lindela
station, the one for the train coming
from Germiston station towards
Pilot station and the other for the train going in the opposite
direction, from Pilot to Germiston.
There are two platforms serving
the two railway lines, situated on the outside of the lines.
[12]
It
was also common cause that the plaintiff was the holder of a valid
train ticket.
[6]
[13]
On the day of the incident the plaintiff (coming from his place of
employment at the end of a working
day in Boksburg and via the train
station at Angelo) changed trains at Germiston and boarded the train
to Pilot, his destination.
He was in the second carriage behind the
locomotive. The train was crowded and many passengers were
standing.
[14]
The doors on both sides of the carriage were open and there were
passengers standing in the doorways,
preventing the doors from
closing when the train departed Germiston. The plaintiff was standing
between two opposing doors and
approximately on the centre line.
[15]
The train stopped at Lindela station, which is not far from Pilot
station. The platform was on the
left side of the train, the
‘near-side’ or ‘platform side’ and the second
railway line was on the right
side, the ‘far-side’‘
of the train. The plaintiff was still standing between two doors and
at the centre of the
carriage.
[16]
The train jerked, forwards and backwards twice but did not depart.
Then there was some kind of explosion,
a ‘loud bang’ at
the back of the carriage. Passengers panicked and jostled, and in the
melee the plaintiff was pushed
out of the carriage on the far side.
He fell onto the rails and was injured. There was no train on the
tracks for the train bound
for Germiston when he fell.
[17]
The train bound for Pilot that the plaintiff should have been on
departed without him. Some time later
he was moved by bystanders to
the platform on the other side, the side where trains bound for
Germiston would stop. This is where
his brother and the supervisor of
the defendant who attended at the incident, encountered him later. An
ambulance fetched him and
took him the hospital in Vosloorust.
[18]
I do not find it necessary to deal at length with the evidence of the
plaintiff’s brother and
the defendant’s supervisor who
arrived on the scene a considerable time after the incident took
place. The supervisor conceded
that during his time working on the
railway stations he dealt with a great many incidents and accidents,
and his memory as to what
exactly was said and by whom, might not be
accurate four years later under circumstances where he had no reason
to remember this
specific incident in any detail.
[19]
What is common cause is that the defendant’s supervisor was
shown a copy of the plaintiff’s
ticket and wrote down his
personal particulars.
Wrongfulness
[20]
The
railway system is a primary mode of transport for many, and users are
entitled to a railway system that is safe, well-managed
and efficient
within the constraints imposed by economic realities. The breach of
public law obligations are wrongful for purposes
of public law
remedies and for the purposes of determining delictual liability.
[7]
[21]
Operating
a train under conditions where the doors remain open even though the
train is travelling at speed and when there is no
platform onto which
to step out is per se dangerous and wrongful.
[8]
The
question of negligence
[22]
The
test for negligence has often been stated and was formulated as
follows in
Kruger
v Coetzee
:
[9]
For
the purposes of liability culpa
[10]
arises
if –
(a)
a
diligens paterfamilias
[11]
in the position of the defendant –
(i)
would foresee the reasonable possibility of his conduct
injuring another in his person or property and causing him
patrimonial loss;
and
(ii)
would take reasonable steps to guard against such occurrence;
and
(b)
the defendant failed to take such steps
[23]
The plaintiff’s case for the negligence of the defendant and
its employees and agents was based
solely on the fact that the doors
were kept open on both sides of the carriage from Germiston station
and then at Lindela station.
While the train was stationary one would
expect the doors to be open at the platform side, but there no was no
explanation for
the open doors on the far side. It was common cause
that on the platform side, the floor of the carriage was at the
approximate
height of the platform whereas on the far side, there was
an appreciable drop from the floor of the carriage to ground level.
Passengers
are not expected to embark or disembark on the far side.
[24]
Neither the plaintiff nor the defendant dealt with the number of
guards and conductors (if any) on
the train or with the policies, the
procedures and practices of the defendant in operating an urban
passenger rail network, the
measure of control that the personnel had
over the doors, the extent to which personnel could interfere when
passengers impermissibly
kept the doors open, and the mechanical or
electronic systems used to manipulate the doors.
[25]
When
reading the case law I must be careful to differentiate between
statements of law and the analysis of factual evidence in those
cases. I am bound by precedent but may not have regard to factual
evidence
[12]
and findings of
fact in other cases.
[26]
The undisputed evidence in this matter is that the doors were open on
both sides of the carriage when
the train travelled between Germiston
and Lindela, and when it was stationary at Lindela. A crowded railway
carriage travelling
at normal speeds pose an obvious danger to
passengers and injury or death is foreseeable in the event of a
passenger falling out
or being pushed out. The reasonable man (and
the reasonable operator of a rail service) will foresee the
possibility of harm under
these circumstances.
[27]
The
Constitutional Court declared in 2004 that Transnet Ltd (first
respondent) and the present defendant (second respondent) “
have
an obligation to ensure that reasonable measures are taken to provide
for the security of rail commuters whilst they are making
use of
rail transport services provided and ensured by,
respectively, the first and second respondents.
”
[13]
[28]
When the train is stationary at a designated stop next to a station
platform one would expect the near
side doors to be open at some
stage so that passengers may embark and disembark. The reason for the
existence of a railway platform
is for the platform to be flush with
the doors and floor of the railway carriage so passengers can step
from one to the other in
safety. On the far side there is a
considerable drop between the floor of the carriage and ground level.
There is no reason for
the doors on the far side to be open at any
time whether the train is stationary or in motion.
[29]
The reasonable man will foresee the possibility of injury or death if
a person fell out or were pushed
out the door on the far side
and fell onto the ground, and this would be the case irrespective of
whether the train was in
motion or not. The undisputed evidence was
that the adjacent railway lines were about two meters apart; a
carriage is wider than
the tracks and two trains passing would be in
close proximity. The danger of failing onto, or under the wheels of
another train
is therefore real, and utterly foreseeable. The
reasonable man would guard against it.
[30]
There
is considerable authority to the effect that a railway operator has a
duty to see to it that the doors of a train are closed
at relevant
times.
[14]
A failure to comply
with the duty can be interpreted as an
omissio
(the failure to see to it that the doors are properly closed) or a
commissio
(permitting
the train to depart a station and to travel with doors open).
[31]
The
onus
[15]
to prove
[16]
his case remains throughout on the plaintiff. The defendant’s
liability is not absolute-
[17]
the liability of a railway operator is not strict liability, and a
prima
facie
case presented by the plaintiff can be rebutted.
[32]
The defendant’s duties must be exercised in a reasonable
manner. Absolute perfection in a perfect
World is not required.
[33]
The
undisputed evidence in this matter casts an onus of rebuttal
[18]
or evidentiary burden onto the defendant. The
prima
facie
case made out by the plaintiff can conceivably be rebutted by the
defendant by leading evidence to show that it took all reasonable
steps to ensure that the doors were closed before the train departed
a station and that the doors on the far side were always closed.
[19]
The defendant however elected to lead no evidence.
Causation
[34]
Had
the far side door been closed the plaintiff would not have fallen out
of the train. The open door (left open wrongfully and
negligently)
was a
conditio
sine qua
non for the fall and the injuries suffered by the plaintiff.
[20]
Contributory
negligence
[35]
There is no evidence of contributory negligence. It was suggested in
cross examination that the plaintiff
had jumped from the train, but
the defendant’s witness who gave evidence to the effect that he
had been told this by the
plaintiff had to concede that his memory
may be faulty.
[36]
The plaintiff’s undisputed evidence was that he was on his way
home and intended to disembark
at Pilot station. There would be no
reason for him to disembark at the Lindela station. There was also no
evidence that his behaviour
differed from that of the other
passengers when the explosion occurred in the back of the carriage
and that he jumped out because
of fear or that he over-reacted.
Conclusion
[37]
The plaintiff made out a
prima facie
case and the defendant
failed to lead evidence to discharge the evidentiary burden. The
defendant is liable for the damages suffered
by the plaintiff.
[38]
I therefore make the order as set out above.
J
MOORCROFT
ACTING
JUDGE OF THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION
JOHANNESBURG
Electronically
submitted
Delivered:
This judgement was prepared and authored by the Acting Judge whose
name is reflected and is handed down electronically
by circulation to
the Parties / their legal representatives by email and by uploading
it to the electronic file of this matter
on CaseLines. The date of
the judgment is deemed to be
14 FEBRUARY 2023
.
COUNSEL
FOR THE PLAINTIFF: E KROMHOUT
INSTRUCTED
BY: MNGUNI
ATTORNEYS INC
COUNSEL
FOR DEFENDANT: L
MATSIELA
INSTRUCTED
BY: PADI
INC
DATE
OF THE TRIAL: 7
& 8 FEBRUARY 2023
DATE
OF ORDER: 14
FEBRUARY 2023
DATE
OF JUDGMENT: 14
FEBRUARY 2023
[1]
CaseLines 027-37.
[2]
Particulars of claim, paras 6, 8.12, 8.13, and 8.15.
[3]
Particulars of claim, par. 8.12.
[4]
CaseLines 032-1.
[5]
The plaintiff testified through a Zulu/English
interpreter, Mr. Mthombeni.
[6]
CaseLines 027-4.
[7]
See
Rail
Commuters Action Group and Others v Transnet Ltd t/a Metrorail and
Others
2005 (2) SA 359 (CC) par. 79
et
seq,
and
Mashongwa
v Passenger Rail Agency of South Africa
2016 (3) SA 528 (CC) paras 16 to 21.
[8]
See
Mashongwa
v Passenger Rail Agency of South Africa
par. 23. Mogoeng CJ said: “
An
omission will be regarded as wrongful when it ‘evokes moral
indignation and the legal convictions of the community require
that
the omission be regarded as wrongful.’”
[9]
Kruger
v Coetzee
1966 (2) SA 428
(A) 430E-F.
[10]
I.e., negligence.
[11]
The reasonable man, travelling on the proverbial bus to Putney.
[12]
For
instance, in
Transnet
Ltd t/a Metrorail and Another v Witter
2008 (6) SA 549 (SCA) 555 the Supreme Court of
Appeal evaluated the written operating instructions of the
appellant
and heard evidence by experts. Such a document and such evidence
could very well be very relevant to the present matter
but neither
the plaintiff nor the defendant elected to present such evidence. In
Mazibuko
v Passenger Rail Agency of South Africa
,
2011/40493, South Gauteng High Court, 7 December 2012, reference was
made to the Metrorail General Operating Instructions.
[13]
Rail
Commuters Action Group and Others v Transnet Ltd t/a Metrorail and
Others
2005 (2) SA 359 (CC).
[14]
Shabalala
v Metrorail
2008 (3) SA 142 (SCA) par. 8,
Transnet
Ltd t/a Metrorail and Another v Witter
[2008] ZASCA 95
;
2008 (6) SA 549
(SCA)
Mashongwa
v Passenger Rail Agency of South Africa
2016 (3) SA 528 (CC) paras 9, 18, 44 to 62,
Motloung v
Passenger Rail Agency of South Africa (PRASA)
2022 JDR 0398,
[2022] ZAGPJHC 50 paras 11 to 15,
Mmatli
v SA Rail Commuter Corporation
,
2009/51438, South Gauteng High Court, 30 January 2012,
Mazibuko
v Passenger Rail Agency of South Africa
,
2011/40493, South Gauteng High Court, 7 December 2012, paras 31 to
36. In the latter case negligence stemmed from the General
Operating
Instructions (not relevant from the present) or from the failure of
the rail operator to give proper instructions and
imposing
obligations on staff. Weiner J said in par. 33 that “
no
train should be in motion unless all the doors are properly closed”
and
in par. 34
that
to “avoid liability, the defendant would have to take such
reasonable steps necessary under the circumstances to prevent
people
in the position of the plaintiff from being harmed whilst travelling
on a moving train.”
[15]
‘
Bewyslas’
or ‘burden of proof.’
[16]
Pillay
v Krishna
1946 AD 946
at 952.
[17]
See
Shabalala
v Metrorail
2008 (3) SA 142 (SCA) paras 11 and 12.
[18]
‘
Weerleggingslas
.’
See
South
Cape Corporation (Pty) Ltd v Engineering Management Services (Pty)
Ltd
1977 (3) SA 534
(A) 548, Hoffmann & Zeffertt
The
South African Law of Evidence
4
th
ed. 1988 p 496, and
Schwikkard
& Others
Principles
of Evidence
4
th
ed. 2014 par. 31.2.
[19]
In the words of Weiner J (as she then was) in
Mazibuko
v Passenger Rail Agency of South Africa
,
2011/40493, South Gauteng High Court, 7 December 2012, the defendant
“
failed
to provide any evidence of measures adopted to protect the plaintiff
in such a situation.”
[20]
See the distinction between factual causation and legal
causation in
Mashongwa
v Passenger Rail Agency of South Africa
2016 (3) SA 528 (CC) paras 63 to 69.
sino noindex
make_database footer start
Similar Cases
Mthetwa v S (A20/2022) [2022] ZAGPJHC 330 (11 May 2022)
[2022] ZAGPJHC 330High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Mthembu v Mlamba and Others (17373/2019) [2025] ZAGPJHC 269 (7 March 2025)
[2025] ZAGPJHC 269High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Mthembu v Minister of Police (2018/14036) [2024] ZAGPJHC 813 (22 August 2024)
[2024] ZAGPJHC 813High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Mthimunye and Others v Mthimunye and Another (037606/2022) [2023] ZAGPJHC 1405 (4 December 2023)
[2023] ZAGPJHC 1405High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Mthembu v Woolworths (Pty) Limited and Another (44235/2019) [2024] ZAGPJHC 914 (29 July 2024)
[2024] ZAGPJHC 914High Court of South Africa (Gauteng Division, Johannesburg)99% similar