Case Law[2023] ZAGPJHC 766South Africa
Karoshoek Solar One (RF) (Pty) Ltd v Dankocom (RF) (Pty) Ltd and Another (2022/13538) [2023] ZAGPJHC 766 (5 July 2023)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 766
|
Noteup
|
LawCite
sino index
## Karoshoek Solar One (RF) (Pty) Ltd v Dankocom (RF) (Pty) Ltd and Another (2022/13538) [2023] ZAGPJHC 766 (5 July 2023)
Karoshoek Solar One (RF) (Pty) Ltd v Dankocom (RF) (Pty) Ltd and Another (2022/13538) [2023] ZAGPJHC 766 (5 July 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_766.html
sino date 5 July 2023
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
Case Number:
2022/13538
NOT REPORTABLE
NOT OF INTEREST TO OTHER
JUDGES
REVISED
05/07/23
In
the matter between:
KAROSHOEK
SOLAR ONE (RF) (PTY) LTD
Applicant
and
DANKOCOM
(RF) (PTY) LTD
First
Respondent
MOHAMMED
ASHRAF EBRAHIM CHOHAN SC
Second
Respondent
JUDGMENT
KEIGHTLEY, J:
Introduction
[1]
The
applicant in this matter, Karoshoek Solar One (RF) (Pty) Ltd applies
to review the award of the second respondent, Mr Chohan,
who was the
arbitrator in arbitration proceedings between the applicant and the
first respondent, Dankocom (RF) (Pty) Ltd.
The application is
brought in terms of section 33(1) of the Arbitration Act
[1]
(the
Act). Mr Chohan abides the decision of the court. To
simplify matters, I refer to Dankocom as “the respondent”
rather than the “first respondent”.
[2]
The dispute that was referred to
arbitration arose out of an Engineering, Procurement and Construction
contract (the contract) concluded
on 12 December 2014 in terms of
which the applicant engaged the respondent to design and build a
solar power plant in the Northern
Cape. During the course of
the project various disputes arose. The parties settled a number of
those disputes in a settlement
agreement dated 12 July 2019.
However, the parties were unable to settle one of the disputes,
consequent upon which that
dispute was referred to arbitration.
[3]
The nature of the dispute is central to the
application for review. As such, it requires particular
analysis. To this
end, the contractual context to the dispute
is important, as is the route followed in the arbitration
.
The contract and the
arbitration
[4]
The parties are agreed that the broad
nature of the dispute involved the interpretation of certain of the
provisions in the contract,
although they differ on the ambit of the
interpretational dispute and on which provisions or schedules to the
contract are relevant
.
[5]
Under the contract the respondent
guaranteed that the solar power plant (the Facility) would achieve a
certain energy capacity,
namely 100 MW net of concentrated solar
power. The contract, and in particular, Schedule 8 thereto,
described the tests to
be performed to determine whether the
guaranteed capacity, the EEOU Performance Guarantee (the guarantee)
had been met. For
purposes of the present dispute, the Long
Term Performance Test (LTPT) is relevant. If the LTPT indicated
that the guarantee
had not been met, the respondent became liable for
performance liquidated damages (PLDs) to the applicant. This
was in terms
of Schedule 9 to the contract
.
[6]
The contract envisages that the outcome of
the LTPT is determined by a computer model, or Facility Power Model
(the FPM) as it is
described in the contract. The contract
states that the FPM is attached asSschedule 30. Much of the
applicant’s
case hinges on Schedule 30 and its relevance, as I
discuss later. For present purposes, it is sufficient to note
that the
FPM is essentially a computer software model that uses input
data, much of which is contained in comma-separated value data
computer
files (.csv files). Using this data, algorithms and so
forth, the FPM models the energy capacity of the Facility. The
success or failure of the Facility to meet the guarantee is based on
the outputs determined through this modelling process
.
[7]
In terms of the settlement agreement, which
ultimately led to the arbitration, paragraph 8.4 recorded that:
“
In regard to the
operating strategy of the Facility and its impact on the EEOU
Performance Guarantee, the Parties acknowledge that
there is a
dispute between the Owner and the Contractor,
which dispute
involves whether the Contractor is entitled to adjust the Facility
Power Model (Schedule 30 to the EPC Contract) when
determining the
amount of the EEQU Performance Guarantee to take into account the
actual operating strategy of the Facility as
opposed to the default
strategy
. The Parties acknowledge and agree that their respective
rights and positions in regard to the interpretation of Schedules 8
and
9 concerning the operational strategy are fully reserved and
agree to discuss the matter further as soon as practicable after the
conclusion of the Agreement, in order to attempt to reach agreement
on the interpretation. If the Parties are unable to resolve
the
dispute concerning the interpretation the Contractor shall be
entitled to refer the dispute to arbitration for determination
under
the dispute resolution clauses in the EPC Contract.” (Emphasis
added)
[8]
One of the categories of reference data
measured for purposes of the LTPT is the operational strategy for the
Facility. The
operational strategy is intended to maximise
revenue for the applicant by ensuring that the thermal storage system
is used to its
full capacity each day so as to facilitate the maximum
sale of energy during peak times. By running the computer model
on
the relevant reference data, the parties can determine whether the
operating strategy is achieving the performance that was guaranteed
by the respondent
.
[9]
As indicated in the underlined portion of
the extract above, the main difference between the parties was
whether the LTPT was to
be conducted based on reference data drawn
from the facility operating strategy actually adopted (post the
Facility coming on line),
or reference data based on the default
operational strategy devised around the time the contract was entered
into, and hence prior
to the Facility coming on line. The default
model (contained in the FPM), which was provided by a separate
service provider, used
reference data based on assumed conditions.
It thus predicted what the performance of the Facility would be in
the future,
based on default, and not actual inputs. The
respondent contended that the contract permitted an adjustment of the
FPM (constituting
the default reference data relevant to the
operational strategy) so as to take into account the actual operating
strategy. The
applicant, on the other hand, took the view that the
default reference data relevant to the operational strategy was what
the parties
had agreed was to be used to the exclusion of actual
reference data inputs that had become available once the Facility
started
operating
.
[10]
The parties were unable to reach agreement
on the disputed issue and the respondent referred the dispute to
arbitration. The
key to the dispute was the interpretation of
the relevant provisions of the contract
.
[11]
Clause 11.6 of Schedule 8 described the
categories of reference data that was to be used for the LTPT as
follows (in relevant part):
“
11.6.1
Annual weather file ….
11.6.2
Restrictions (for example grid and fossil fuel supply restrictions) …
11.6.3
Operation of the Facility
11.6.3.1 Operation of the
Facility according to Operation and Maintenance Manual delivered by
the Contractor;
11.6.3.2 Facility
Operation strategy as defined in the Facility Power Model. This item
specifically refers to the strategy followed
to charge the storage
and maximize production during peak hours.
11.6.3.3. Standard Time
considered as included in the Facility Power Model.
11.6.4 Facility
outage: scheduled outage 12 days.
11.6.5 Solar Field:
11.6.5.1 Solar Field
annual average availability: 99%;
11.6.5.2 total annual
average cleanliness factor: 97%, calculated as the product of mirror
cleanliness factor (98%) and absorber
tube cleanliness factor (99%);
11.6.5.3 annual
percentage of broken/damaged mirrors: 0.25%; and
11.6.5.4 annual
percentage of broken/damaged absorber tubes: 0.5%.
11.6.6
The Post COD Guarantees will be adjusted for degradation … .”
[12]
As is apparent from the above, clause
11.6.3 describes the reference data for the operating strategy as
being that defined in the
FPM. The idea behind the operating
strategy is, as stated, to charge the storage and maximise the
production of electricity
during peak hours
.
[13]
If this was all that Schedule 8 had to say
on the issue, there would have been no dispute between the parties.
However, clause
11.7 of Schedule 8 is critical to the dispute.
It provides for the “Correction of guaranteed values”’
and
states:
“
11.7.1 If there is
any deviation from the reference data referred to in paragraphs
11.5.1
to
11.5.6
(both inclusive) as stated in
paragraph
11.5
, all the results of the Facility Power Model
must be corrected according to the principles described in paragraphs
11.6.3.1
,
11.6.3.2
and
11.6.3.3
.
11.7.2
Paragraphs
11.5.3
,
11.5.4
,
11.5.5
and
11.5.6
apply irrespective of whether the Operator and the
Contractor are Affiliated.
11.7.3 For the avoidance
of doubt, regardless who the Operator is reference data referred to
in paragraphs
11.6.1
and
11.6.2
must in all cases be
corrected for the Long Term Performance Test according to the
following principles:
11.7.3.1 for parameters
differing from the reference data (paragraph
11.5
), the actual
value of the parameters must be measured during the Test period and
used as input data for the Facility Power Model
using the methodology
described in the user manual of the Facility Power Model and in the
rest of the technical documentation.
In case a parameter change
cannot be directly converted into a change of an input of the
Facility Power Model, the Owner, the Contractor,
the Lenders’
Representative and the Operator must agree on the appropriate
correction of the results to be applied;
11.7.3.2; if during the
Long Term Performance Test there is any deviation of an Operating
parameter which is an input of the Facility
Power Model other than
the defined reference data (paragraph
11.5
), the inputs into
the Facility Power Model must be modified by agreement between the
Owner, the Contractor, the Le
nders
’
r
epresentative
and the Operator if a change
in any of these parameters causes a decrease in Energy Output in
respect of which the Contractor is
entitled to relief under the
Contract;
11.7.3.3. the Owner must
provide and facilitate any and all Operating data requested by the
Contractor in order to correct the Post
COD Guarantees as specified
in Schedule 9. This is especially important, but not limited to the
data that may not be extracted
directly from the DCS of the Facility,
such as field cleanliness factor, mirrors and tubes status and
scheduled outages.”
(Emphasis added)
[14]
The paragraphs referenced in bold in the
above extract are relevant to the question of rectification, which is
raised in one of
the applicant’s grounds of review. At
this stage, it should be noted that, save for the reference to
“11.6.1
and 11.6.2” in clause 11.7.3, the parties are
agreed that the cross-referencing is incorrect. Further, that
the references
to 11.5 and its subparagraphs, should be read as a
reference to 11.6 and its subparagraphs. Also, the reference to
11.6 and
its subparagraphs in clause 11.7.1 should be read as a
reference to 11.7 and its subparagraphs. I return to this issue
later,
but it is important to understand that clause 11.7 should be
read accordingly.
[15]
The respondent relied on clause 11.7 to
support its case that a deviation from the default reference data
contained in the FPM was
required. Ultimately, the question was
how these two clauses of Schedule 8 were properly to be interpreted
.
[16]
However, before the arbitrator could
proceed to the main dispute between the parties, he was tasked with
resolving an interlocutory
dispute, which I will refer to as the
disclosure application. The FPM (in Schedule 30) and its
constituent .csv files comprised
confidential information.
Although the applicant had access thereto, without agreement from the
respondent, or without an
award by the arbitrator, it could not
disclose the FPM to its legal representatives and its witnesses.
The applicant wished
to disclose the FPM to its lawyers and its
expert witnesses and when the respondent refused, the applicant
applied to the arbitrator
for an interlocutory award permitting such
disclosure.
[17]
The respondent opposed the disclosure
application, contending that, save for the FPM manual (which was not
confidential information),
the FPM itself and its .csv files,
contained in Schedule 30, were irrelevant to the main dispute between
the parties. The
main dispute was a narrow one, relating simply
to the interpretation of Schedules 8 and 9 of the contract, and not
Schedule 30.
More particularly, contended the respondent, the
dispute was whether the parties had intended that the operation
strategy should
be fixed, with reference to the default operation
strategy, or whether it ought to be variable, with reference to the
input data
drawn from the actual operation strategy. The FPM
model, and its input reference data in the form of the .csv files,
could
not assist in determining this interpretational dispute.
[18]
The applicant maintained that Schedule 30,
comprising the FPM and .csv files, was relevant to the dispute as
pleaded. This
was so on a proper analysis of the respondent’s
statement of claim in the main dispute and, in particular, on certain
declaratory
relief that had been sought.
[19]
During the course of the disclosure
proceedings, the respondent amended its statement of claim so as to
limit its declaratory relief
in prayer 2. It also abandoned an
alternative prayer, prayer 3, which, according to the arbitrator in
his award (the disclosure
award), went beyond the mere interpretation
of the contract. It is not necessary to discuss this
abandonment of prayer 3
any further, save to note that the arbitrator
recognised that had the respondent not abandoned the alternative
relief in prayer
3, it would have necessitated an analysis of the
actual workings of the FPM and the .csv files. According to the
arbitrator:
“The contractor, recognising this difficulty,
consequently abandoned the relief sought in prayer 3”.
[20]
Once the respondent had scaled down the
ambit of its claim for relief, the arbitrator agreed with the
respondent that:
“
In
my view, the now limited prayer 2 must be read in context and against
the articulated dispute pleaded by the contractor in its
statement of
claim. Doing so reveals that it does no more than seek to achieve
a
principled view
on whether or not the operation strategy in the FPM should comprise
the actual operation strategy as it alleges it should, or whether
it
should include the default operation strategy.
It
does not seek to achieve an award on the correctness or otherwise of
the data to be used in the FPM
.”
(emphasis added)
[21]
The arbitrator found that:
“
Having regard to
the pleaded issues, the most important of which I have referred to
above, it is quite clear that
what has been referred to
arbitration is an interpretational dispute
.
Whilst the outcome
of the interpretational dispute of the EPC contract may have
subsequent consequences on other disputes between
the parties,
including whether or not any input data to the FPM was correct or
not, or whether there is any liability for liquidated
damages, those
disputes have not been referred to arbitration. Neither the FPM nor
the .csv data files are relevant to the interpretation
of the EPC
contract and in particular, whether the input data to the FPM ought
to refer to the actual operation strategy or the
default strategy.
”
(emphasis added)
[22]
He also found that:
“…
with the
abandonment of prayer 3, any issues relating to whether or not the
input data was intended to maximise revenue or whether
they were not
intended to conceal operational errors or whether they were in
accordance with international standard practices,
no longer arises
for consideration or determination.
If that is so, an evaluation
or assessment of the FPM and any .csv data files would not only be
unnecessary but would moreover be
irrelevant
.” (emphasis
added)
[23]
The arbitrator dismissed the disclosure
application. The arbitration proceeded without the applicant’s
legal representatives
and its expert witness having access to the FMP
and its .csv files. The information was also not placed before
the arbitrator.
[24]
As we shall see, this state of affairs (the
exclusion of Schedule 30 comprising, the FPM and .csv files, from the
arbitration) constitutes
a key aspect of the applicant’s review
application. It is important to note, however, that the
applicant did not seek
to review the disclosure award, either in its
immediate aftermath, or in its present review application. I
will return to
this observation later in my judgment.
[25]
The arbitration proceeded on the main
disputed issue. In terms of the plea for a declarator, after
the amendment referred
to earlier, this now read:
“
The
input data for the operation strategy in the Facility Power Model
shall comprise of the actual operation strategy followed at
the
Facility on a daily basis.”
The question of whether
in addition the respondent persisted with its plea for the
rectification of clause 11.7 of Schedule 8, as
discussed above, is
contentious and forms the basis for one of the grounds for review.
I deal with this in detail later.
[26]
The parties exchanged witness statements
and led the evidence of their witnesses before the arbitrator.
The applicant led
the evidence of an expert witness, Mr Pine, who, as
I indicated earlier, did not have access to the FPM and .csv files.
Much
is made of this in the applicant’s grounds for review,
which I address later.
[27]
The arbitrator’s award was handed
down on 28 February 2022. It was in the following terms:
“
72.1. paragraph
11.7 of Schedule 8 to the EPC contract is rectified to correct the
cross-references as follows:
‘
11.7.1 lf there is
any deviation from the reference data referred to in paragraphs
11.6.1 to 11.6.6 (both inclusive) as stated in
paragraph 11.6, all
the results of the Facility Power Model must be corrected according
to the principles described in paragraphs
11.7.3.1, 11.7.3.2 and
11.7.3.3;
11.7.2 Paragraphs 11.6.3,
11.6,4, 11.6.5 and 11.6.6 apply irrespective of whether the operator
and the contractor are affiliated;
11.7.3 For the avoidance
of doubt, regardless of who the operator is, reference data referred
to in paragraphs 11.71 and 11.7 2,
must in all cases be corrected for
the long-term performance test according to the following principles:
11.7.3.1 for parameters
differing from the reference data (paragraph 11.6) ...;
11.7.3.2 if during the
long-term performance test there is any deviation of an operating
parameter which has an input of the Facility
Power Model other than
the defined reference data (paragraph 11.6) …’
72.2. the declarator
sought by the claimant in prayer 2 as amended, is dismissed;
72.3. each party is to
pay their own costs of the arbitration.”
[28]
The respondent was the claimant referred to
in paragraph 72 of the award. Its claim for substantive relief
in the form of
the declarator set out earlier was dismissed.
Despite having successfully opposed the respondent’s case for
declaratory
relief, the applicant seeks to review and set aside the
arbitrator’s award, for reasons I discuss shortly. To
understand
the motivation behind the applicant’s review, it is
necessary to examine the body of the award, and the arbitrator’s
reasoning more closely.
[29]
The arbitrator noted that the parties were
agreed that the dispute, “at this stage, is one relating to the
proper interpretation
of the EPC contract.” He set out
the respective views of the parties: the respondent contended that
paragraph 11.7
of Schedule 8 envisaged that the reference data
reflected in paragraph 11.6 ought to be adjusted for actual values,
while the applicant’s
position was that the input data was
fixed and the contract did not permit inputs comprising the actual
operation strategy employed
.
[30]
In paragraph 31 of the award, the
arbitrator reasoned that:
“
Thus
what
paragraph 11.7 contemplates
(certainly in respect of sub
paragraphs 11.6.4 and 11.6.5)
is an adjustment to the parameters
of the reference data when there is a deviation thereof by using the
actual data.
Although the parameters in respect of the reference
data, "operation of the Facility", are not identified,
there is no
reason in principle, why the same approach cannot and
should not be applied when there is a deviation from any of the
parameters
in respect of that reference data.” (Emphasis added)
[31]
However, paragraph 11.7 was “not as
open ended as the contractor (the respondent) may contend”.
The arbitrator
pointed to the second sentence of paragraph 11.7.3.1
and to paragraph 11.7.3.2. Both incorporated qualifications to
the permissibility
of adjustments for the use of actual, as opposed
to default, input data. In the case of the former, if a
parameter change
cannot be directly converted into a change of an
input, then the parties would have to agree on the appropriate
correction of results
to be applied. As to the latter, any
deviation of an input other than that defined in paragraph 11.6, can
only be modified
by agreement, if the change causes a decrease in
energy output. According to the arbitrator, these
qualifications were imposed
to protect the owner/applicant.
This was the more commercially sensible interpretation
.
[32]
It is useful to set out the ‘Final
Analysis’ section of the award in full, as it forms the heart
of much of the applicant’s
review:
“
61. The purpose of
the Model was to enable the contractor in particular to simulate or
project the required capacity that the Facility
would have to meet
for the purposes of the guarantees that the contractor had given to
the owner. In order to do so, the Model
of necessity, had to employ
certain default input data that predicted for example the weather
during a typical meteorological year
as well as the operation
strategy that would be employed by the operator during that period.
62. But the EPC contract
recognised that the data utilised by the Model for the purposes of
these projections or simulations, may
actually be different during
the test period and that consequently, it would be inappropriate to
hold the contractor liable to
certain guarantees based for example on
a weather prediction or forecast that turned out to be inaccurate.
For that reason, paragraph
11 of Schedule 8 contemplated the use of
the actual data insofar as there had been a deviation from the
parameters of the reference
or default data.
63. The owner's witnesses
accepted that the operation strategy that would be employed by the
operator was dependent on the weather.
Once that concession was made
and once the owner acknowledged that the actual weather data is to be
used as an input in the Model,
it would follow that the actual
operating strategy (save for that strategy which was not in
accordance with the agreed upon strategy
and which resulted in an
improper operation or maintenance of the Facility), should be used as
an input data.
64. That is precisely
what sub paragraph 11.7.3.1 contemplates when it refers to the actual
value of the parameters to be measured
during the test period and to
be used as input data for the Model.
65. However neither the
default operation strategy file nor the actual operating strategy
file utilised by the contractor, have
been disclosed by the
contractor.
The owner points out that this impedes the proper
interpretation of the EPC contract and in particular, paragraph 11 of
Schedule
8 thereto. This arises because I had earlier made an award
of the insistence of the contractor, that neither the Model nor the
.csv files were relevant to the proper interpretation of the EPC
contract and consequently need not have been disclosed by the
contractor. In retrospect, it may have been useful if not preferable
to have sight of the .csv files in order to better understand
the
parameters that were used as input data. This does not however make
it impossible to interpret the paragraph, just more difficult.
But
counsel for the owner submitted that because of this difficulty, I
should decline the invitation to make a declaratory order
as prayed
for by the contractor.
66. There is
considerable force in that submission.
67. The award which the
contractor seeks is a declaration that:
"The input data
for the operation strategy in the Facility Power Model shall comprise
of the actual operation strategy followed
at the Facility on a daily
basis."
(my emphasis)
68. But as I have pointed
out above, the actual input data to be used in the Model is subject
to the qualification reflected in
sub paragraph 11.7,3.'I of Schedule
8. In the case of a parameter change which cannot be directly
converted into a change of an
input of the Model, the owner, the
contractor and lender's representatives as well as the operator have
to agree on the appropriate
correction of the results to be applied.
69. I do not know
whether the actual data sought to be used by the contractor can be
directly converted into a change of an input
in the Model. The
declarator sought by the contractor does not take this into account
and is consequently overly broad. It may
include all actual data
irrespective of whether such change may be directly converted as an
input to the Model.
70. Thus, whilst I am
of the view that on a proper interpretation of paragraph 11 of
Schedule 8 to the EPC contract, the parties
intended that the actual
operating data may be used as an input in the Model when determining
the LTPT this is only in circumstances
where there has been a
deviation from the reference data listed in paragraph 11.6(or that
contained in the default .csv files)
and moreover when the parameter
change can be directly converted into a change of an input to the
Model.
71.
In light of the fact that the declarator sought by the contractor
potentially includes those circumstances that may preclude
the
contractor from using the actual operating data as an input into the
Model without obtaining the consent of various other parties
including the owner, it would be inappropriate to grant the
declarator in the form sought by the contractor and I accordingly
exercise my discretion not to grant it.”
(all
emphases added)
[33]
Apart from the issue of whether the
rectification award was properly made, the applicant’s main
cause of complaint is not
the refusal of the declarator sought by the
respondent, but rather what the arbitrator finds in paragraph 70.
The applicant
says that in subsequent communications, the respondent
has asserted that based on this paragraph, the LTPT was in fact
passed in
June 2020. Accordingly, the respondent is claiming a
refund of substantial PLDs that were paid, it says in error.
The
applicant accordingly asserts that paragraph 70 constituted a
finding, which the respondent is treating as if it has operative
effect. It is this finding, which forms the main reason for the
review, although I should make it clear that the applicant
also
challenges the rectification award.
Grounds of review
[34]
It
is trite, although worth repeating in the context of this case, that
the question in a review under s 33(1) of the Act is not
whether the
arbitrator erred in his or her award. As the Supreme Court of
Appeal put it in
Telcordia
:
[2]
“
The fact that the
arbitrator may have either misinterpreted the agreement, failed to
apply South African law correctly, or had regard
to inadmissible
evidence does not mean that he misconceived the nature of the inquiry
or his duties in connection therewith. It
only means that he erred in
the performance of his duties. An arbitrator ‘has the right to
be wrong’ on the merits
of the case… .”
[35]
Section 33(1) provides that:
“
Where-
(a)
any member of an arbitration tribunal has misconducted himself in
relation to his duties as arbitrator or umpire; or
(b)
an arbitration tribunal has committed any gross irregularity in the
conduct of the arbitration proceedings or has exceeded its
powers; or
(c)
an award has been improperly obtained,
the
court may, on the application of any party to the reference after due
notice to the other party or parties, make an order setting
the award
aside.”
[36]
By
agreeing to arbitration the parties limit interference by courts to
the ground of procedural irregularities set out in this section.
They waive their right to any further ground of review, under common
law or otherwise.
[3]
[37]
The applicant relies on both facets of s
33(1) (b) as bases for its review, namely gross irregularity and
excess of power (absence
of jurisdiction). In summary, the
applicant’s grounds of review are the following:
37.1
As to excess of power, the applicant attacks both the rectification
relief granted in paragraph 72.1 of the award, and the
finding in
paragraph 70.
37.2
It contends that in awarding a rectification of paragraph 11.7 of the
contract, the arbitrator exceeded his jurisdiction because:
(1) the
parties had agreed that the respondent would abandon its claim for
rectification; and (2) the rectification granted was
not in line with
the rectification as pleaded in the respondent’s statement of
claim.
37.3
Regarding the finding in paragraph 70, the applicant contends that
this finding was not a prayer that either party claimed.
Nor
was the arbitrator asked to make his own or any alternative
substantive “finding” other than the terms set out
in the
declarator. The applicant asserts that having dismissed the
declarator, the arbitrator had no power to grant any other
declarator
or make any “finding” of any similar force or effect.
In making his finding in paragraph 70, the arbitrator
exceeded his
power.
37.4
On the gross irregularity ground, the applicant again attacks
paragraph 70 of the award on three interrelated bases.
37.5
In the first instance, the applicant contends that the arbitrator
committed a fundamental misdirection and proceeded in a grossly
unfair and irregular manner by making the paragraph 70 finding when
he did not have the whole contract before him. According
to the
applicant, this arose from the arbitrator’s “misdirected”
disclosure ruling to the effect that Schedule
30, comprising the FPM,
with its constituent .csv files, was irrelevant and thus excluded
from the arbitration proceedings.
37.6
The applicant sought also to argue, in its written heads of argument,
that this court should apply the test of gross irregularity
laid down
in the unfair labour context in
Sidumo
.
[4]
The submission in this regard was that in disregarding material facts
and evidence, the arbitrator had reached a decision that
no
reasonable decision-maker could have reached and thus had committed a
gross irregularity, rendering the finding in paragraph
70 reviewable.
37.7
The final contention under the gross irregularity also goes to
paragraph 70. The contention here was that the arbitrator
breached the applicant’s right to a fair trial by, among other
things, ruling that the FPM was excluded from the proceedings.
[38]
I
should point out that the applicant did not press the
Sidumo
point at the hearing, a wise election, given the jurisprudence,
including that of the Constitutional Court, holding that the
Sidumo
principles do not apply to the review of a private arbitration award
under s 33(1) of the Act.
[5]
[39]
In considering the applicant’s case
for review, I start first with the gross irregularity attack against
the finding in paragraph
70 of the award. Thereafter, I deal
with the excess of power ground of review in respect of that
finding. Finally,
I turn to the gross irregularity and excess
of power attacks against the rectification award in paragraph 72.1
.
Gross irregularity:
the finding in paragraph 70
[40]
The
applicant accepts, as it must, that gross irregularity goes to the
arbitrator’s methodology, and not to the merits of
his
decision.
[6]
[41]
It
is the applicant’s case that the origins of the asserted gross
irregularity lie in the arbitrator’s “misdirected”
ruling that the FPM, contained in Schedule 30, was irrelevant to the
issues in dispute. As a consequence of this ruling,
says the
applicant, the arbitrator did not have the whole of the contract
before him. This is because Schedule 30 and the
FPM, were an
integral part of the contract. Accordingly, so the argument
goes, it was grossly unfair and irregular for the
arbitrator to
proceed to interpret the contract and reach the interpretive
conclusion he reached in paragraph 70. The applicant
calls in
aid the frequently cited dictum of Wallis JA in
Endumeni
[7]
that
the interpretation of a document requires: “reading the
particular provision or provisions in the light of the document
as a
whole …”
[8]
.
It relies also on
Capitec
[9]
and
particularly on the underlined sentence below, in which the SCA held
that:
“
[Endumeni]
and its progeny emphasise that the meaning of a contested term of a
contract (or provision in a statute) is properly
understood not
simply by selecting standard definitions of particular words, often
taken from dictionaries, but by understanding
the words and sentences
that comprise the contested term as they fit into the larger
structure of the agreement, its context and
purpose. Meaning is
ultimately the most compelling and coherent account the interpreter
can provide, making use of these sources
of interpretation.
It
is not a partial selection of interpretational materials directed at
a predetermined result
.”
[10]
[42]
The applicant submits that it was a grave
misdirection for the arbitrator to make findings on the meaning of
clause 11.7 without
having before him the entire contract and, in
particular, Schedule 30 and the FPM. According to the
applicant, the FPM was
the focal point of the declarator sought by
the respondent. The arbitrator acted irregularly in making any
finding on the
meaning of the contract in the absence of this
evidence. It was also grossly unfair of the arbitrator to
deprive the applicant’s
lawyers and expert access to the same
parts of the contract to which the respondent had access. For
these reasons, the applicant
contends that the finding in paragraph
70 should be reviewed and set aside.
[43]
In support of its case that the FPM was a
vital component of the contract and the dispute, the applicant
referred to the definition
of the Facility Power Model in the
contract. It is defined as meaning “the Facility power
model attached hereto as
Schedule 30”. It is not disputed
that the .csv files form part of the FPM. The applicant also
pointed out that
the dispute in the settlement agreement was
described as “involving whether the Contractor [respondent] is
entitled to adjust
the Facility Power Model (Schedule 30 to the EPC
Contract) when determining the amount of the EEOU Performance
Guarantee to take
into account the actual operating strategy of the
Facility as opposed to the default strategy.” Further,
that the Notice
of Arbitration described the dispute in similar
terms. These are all indications, according to the applicant,
of the FPM’s
central role in the dispute and support its ground
of review that the .csv files that formed part of the FPM ought not
to have
been excluded
.
[44]
One of the difficulties for the applicant
is that it never sought to review the disclosure award which excluded
the FPM. The
applicant accepts that the review must proceed on
the basis that that award cannot be upset on review at this stage.
This
does not matter, says the applicant, because the irregularity is
to be found not in the exclusion consequent on the disclosure award,
but rather on the effect that the award had on the proceedings in the
main arbitration. The applicant says that having excluded
the
FPM and associated .csv files from the arbitration, the only
appropriate course open to the arbitrator was that he was
fundamentally
precluded from making any findings on the proper
interpretation of the contract. This is what makes his finding
in paragraph
70 reviewable, rather than a non-reviewable error of
law.
[45]
Taking this line of submission further,
counsel for the applicant referred to paragraphs 65 and 66 of the
award, which are set out
in full above. Here, the arbitrator
referred to the disclosure award and how, in retrospect, it may have
been “useful
if not preferable” to have had sight of the
.csv files “in order better to understand the parameters”.
The arbitrator noted that this made it more difficult, albeit not
impossible, to interpret the contract. He referred to the
applicant’s submission that “because of this difficulty,
I should decline the invitation to make a declaratory order
as prayed
by the contractor”, and expressed the view that “[t]here
is considerable force in that submission.”
The arbitrator
then dismissed the respondent’s application for declaratory
relief.
[46]
The applicant submitted in this regard that
it is arguable that the reason for the dismissal of the relief was
because, as counsel
put it, the penny dropped for the arbitrator only
in the main hearing that the absence of the FPM and .csv files
evidence created
an insurmountable obstacle for the declaratory
relief sought by the respondent. It was arguable, contended
counsel for the
applicant, that it was for this reason that the
arbitrator declined to award the declaratory relief sought.
This being so,
the arbitrator took a grossly irregular step by
nonetheless reaching an interpretational finding in paragraph 70.
[47]
I find these submissions fundamentally
problematic. For one thing, once it is accepted, as the
applicant does, that the exclusion
award must stand, the applicant’s
attack on the finding made in paragraph 70 begins to assume very much
the nature of an
appeal, based on an error of law on the part of the
arbitrator by excluding the relevant evidence, rather than a
legitimate gross
irregularity review. The real complaint seems
to be that the arbitrator erred in excluding the evidence in the
disclosure
award, but because that award is unassailable, the
complaint is refashioned as a review. However, even if the
arbitrator
had second thoughts about his disclosure award (and I am
not persuaded that he had any material second thoughts), this can
only
have led to a further error of law on his part in making the
finding that he did in paragraph 70.
[48]
A related problem for the applicant on this
score is that on a proper reading of the award, the dismissal of the
declaratory relief
was not because of any second thoughts on the part
of the arbitrator or because the arbitrator was ultimately persuaded
by the
applicant’s argument. It is patently clear from,
in particular, paragraph 69, immediately preceding the impugned
paragraph
70, and the paragraph following, that the reason the
declaratory relief was refused was because it was “overly
broad”.
The arbitrator could not grant the relief because
he did not know “whether the actual data sought to be used by
the contractor
can be directly converted into a change of input”
and thus, whether the qualification in paragraph 11.7.3.1, discussed
earlier,
applied. It is for this reason that he concluded, in
paragraph 70, that the actual operating data “may” be
used,
this was only in certain circumstances and, in para 71, because
the declarator sought potentially included circumstances where the
rider may apply, it would be inappropriate to grant it.
[49]
Whether the arbitrator was right or wrong
in this interpretation is irrelevant. The point is that the
applicant’s submissions
in this regard do not support a case
for review.
[50]
What is more, there is a fundamental flaw
in the premise on which the gross irregularity ground of review
stands. It proceeds
on the assumption that the FPM and its .csv
files were an integral part of the contract and central to the
interpretational dispute
that was referred to arbitration. It
is for this reason that the applicant contends that a gross
irregularity was committed
by the arbitrator’s failure to
consider the whole contract when he embarked on the interpretive
exercise and made his finding
in paragraph 70. Once again, it
is difficult to understand the complaint as falling properly within
the ambit of a gross
irregularity rather than a non-reviewable error
of law. However, be that as it may, and assuming that it is a
valid review
attack, it is misdirected.
[51]
It is so that the FPM is defined as
Schedule 30 in the contract. It is also so that the FPM is
referred to in the dispute
as formulated. However, this does
not mean that the dispute was about the inner workings of the FPM,
and in particular the
.csv files, algorithms and other formulae of
which it is composed. The respondent’s stance throughout
the arbitration
was that the dispute referred to the arbitrator did
not concern an evaluation of the workings and algorithms of the FPM,
but was
an in-principle dispute concerning the proper interpretation
of Schedules 8 and 9, and not Schedule 30 of the contract. The inner
workings of the FPM were not in dispute. The arbitrator agreed
in his disclosure award. He found:
“
[17]
…In my view, the now limited prayer 2 [the declaratory relief]
must be read in context and against the articulated dispute
pleaded
by the contractor in its statement of claim. Doing so reveals that it
does no more than seek to achieve a principled view
on whether or not
the operation strategy in the FPM should comprise the actual
operation strategy as it alleges it should, or whether
it should
include the default operation strategy.
It
does not seek to achieve an award on the correctness or otherwise of
the data to be used in the FPM
.”
(emphasis added)
And:
“
[27]
Having regard to the pleaded issues, the most important of which I
have referred to above, it is quite clear that what has
been referred
to arbitration is an interpretational dispute.
Whilst
the outcome of the interpretational dispute of the EPC contract may
have subsequent consequences on other disputes between
the parties,
including whether or not any input data to the FPM was correct or
not, or whether there is any liability for liquidated
damages, those
disputes have not been referred to arbitration
.
Neither the FPM nor the .csv data files
are relevant to the interpretation of the EPC contract
and in particular, whether the input data to the FPM ought to refer
to the actual operation strategy or the default strategy.”
(emphasis added)
[52]
Whether or not the arbitrator’s
conclusions were correct is not relevant to this review. The
interpretational dispute was
ruled by the arbitrator to be a narrow
one. The arbitration proceeded on the basis that the dispute was not
about the inner workings
of the FPM, and the FPM and .csv files were
irrelevant to the arbitration. The parties are bound by those
conclusions.
The
dicta
relied on by the applicant in support of its contentions do not
require that irrelevant contractual provisions must be taken into
account. This would be absurd. A decision-maker may err
in her interpretation of a document by not appreciating the
relevance
and significance of certain provisions, but that is a matter for
appeal. In circumstances where, as here, an arbitrator
has made
an unassailable finding on the ambit of the dispute and the
irrelevance of certain evidence, it cannot be said that he
committed
a gross irregularity by interpreting the contract in the absence of
that evidence.
[53]
As to the issues of fairness and the
alleged breach of the applicant’s fair trial rights, these too
must be seen in the context
of the nature and ambit of the dispute.
It is trite that procedural fairness is a contextual measure.
What is unfair
in one context may be fair in another. In this
case, the relevant context is provided by the arbitrator’s
binding ruling
that the dispute was a narrow one, and that the FPM
and .csv files were irrelevant to the dispute. Seen in this
context,
what the applicant contends for is a finding that the
arbitrator acted unfairly in excluding irrelevant evidence.
This simply
cannot be a valid basis for review. The fact that
the applicant’s expert witness bemoaned his inability to view
the
FPM and .csv files, and that the applicant’s counsel
continued to assert his client’s stance on the issue throughout
the arbitration proceedings cannot create a case for unfairness where
no ground exists.
[54]
At the end of the day, the arbitrator ruled
on the irrelevance of the FPM, he approached the dispute as a narrow
one, and in line
with this approach, his interpretation of the
contract was one of principle. He made no finding on the
correctness or not
of the FPM and .csv files. It is not
surprising, then, that he expressed, in paragraph 60 of his award,
that: “[s]ave
for one aspect which I deal with under the final
analysis section of this award, I did not find the evidence of any of
these witnesses
particularly helpful on the interpretation of
paragraph 11 of Schedule 8 to the EPC contract.” The
arbitrator’s
expressed view underscores the point that given
the narrow ambit of the dispute, the exclusion of the FPM and .csv
files from the
arbitration did not give rise to reviewable
unfairness.
[55]
I conclude, for all of these reasons, that
there is no merit in the applicant’s contention that paragraph
70 of the award
should be reviewed and set aside on the grounds of
gross irregularity and unfairness.
Excess of power: the
finding in paragraph 70
[56]
As I noted earlier, and as is clear from my
discussion of the issues thus far, the applicant’s real
complaint is not the dismissal
of the claim for declaratory relief,
but the finding of the arbitrator in paragraph 70. The
applicant does not accept this
finding because it has implications
for the respondent’s liability for PLDs which are adverse to
the applicant’s interests.
If the dispute had been
determined by a court, one would imagine that the applicant would
have appealed this finding. This
avenue not being open to the
applicant in the arbitration context, it has attempted to fit its
complaint into the category of a
review, based on an excess of power
ground.
[57]
Given the obvious difficulty presented by
needing to avoid the complaint being seen as an appeal against the
merits of the finding
in paragraph 70, the case for the applicant is
nuanced. The applicant accepts that the arbitrator had the
power to interpret
paragraph 11 of the contract. However,
according to the applicant, the arbitrator’s power extended
only so far as he
could either grant the declarator in the precise
terms stated by the respondent in its amended statement of claim, or
dismiss it.
What the arbitrator did not have, says the
applicant, was the power to make any other operative award or
conclusive finding on
the meaning of paragraph 11. This is what
the arbitrator did in paragraph 70 and his findings there fell
outside of his jurisdiction.
[58]
In its founding affidavit the applicant
states its case thus:
“
The
Owner [applicant] accepts that the arbitrator was empowered to
consider and interpret the contract. That was indeed his primary
duty, according to the pleaded dispute. But the dispute over the
proper interpretation of the contract that was pleaded and referred
to him for final determination was confined to the Contractor's
[respondent’s] claim for a declarator. The Owner [applicant]
therefore does not question the arbitrator's power to examine and
interpret the contract, provided it was ancillary to and directed
at
determining the central issue on interpretation that was before him,
namely to determine whether or not the declarator sought
accorded
with a proper interpretation of the contract.”
[59]
The applicant goes on to assert that in
paragraph 70 the arbitrator purported to make a definitive finding on
the “proper
interpretation” of the contract although this
was in terms “other than those claimed in the declarator”.
It says that in so doing the arbitrator “most regrettably and
unnecessarily” strayed beyond the narrow issue and beyond
the
power conferred on him.
[60]
I must confess to finding the applicant’s
case peculiar. It accepts that the arbitrator’s primary
duty was to
interpret the contract. It accepts that the
arbitrator had the power to interpret the contract in a manner
“ancillary
to and directed at determining the central issue”
before him. Despite this, it seeks to straight-jacket the
arbitrator’s
interpretive powers to extending no further than a
“yay” or a “nay” to the interpretation
preferred by
the respondent in its declaratory relief.
[61]
How was the arbitrator to reach the point
of a “yay” or a “nay” on that declaratory
relief without reasoning
his way towards that end? How was he
to do so without embarking on a reasoned interpretive exercise and
recording his findings
along that path? How can it possibly be said
that those findings were not ancillary to determining the central
issue before him?
Had paragraph 70 not been there (and indeed
its accompanying paragraphs, particularly 67 to 69 and 71) the
parties would have been
left wondering on what basis the declarator
was dismissed. We know, from my earlier analysis of the award,
that these paragraphs
went to the heart of the dismissal. They
explain that the declarator was dismissed because it was too broad,
and why it was
too broad. It seems to me to be patently clear
that these paragraphs and the findings in them were quintessentially
ancillary
to the arbitrator’s accepted primary power, namely to
interpret the contract and to determine whether, on the basis of that
interpretation, the declarator should be granted or dismissed.
[62]
For these reasons I find that there is no
merit in this ground of review.
The rectification
issue
[63]
The applicant challenges the rectification
awarded in paragraph 72.1 on the ground of excess of power.
There are two legs
to this review ground. In the first
instance, the applicant says that the parties had agreed that the
rectification claimed
by the respondent was to be abandoned. In
the second instance, the applicant says that the rectification in its
terms did
not accord with those of the rectification claimed.
[64]
Regarding the first aspect of this ground
of review, the respondent disputed that the parties had agreed that
it would no longer
seek the rectification it claimed. The
applicant relied on an email it had sent to the arbitrator regarding
the issue of
rectification. Its case is that the email
demonstrates the agreement between the parties that the rectification
would be
abandoned and thus establishes that the arbitrator no longer
had any power to rectify the contract.
[65]
The email reads:
“
Dear
Sir
We
write in connection with the plea for rectification.
As
you will have noted from the Defendant's special plea on
jurisdiction, although the Defendant acknowledges that there is an
error with the cross-referencing, the Defendant does not have the
power to consent to the rectification in terms of the project
documents and furthermore, the Defendant disputed your jurisdiction
to deal with the issue of rectification. We do, however, have
instructions from our client that it is prepared to proceed on the
basis that you may interpret schedule 8 on the basis of the
corrected
cross-referencing indicated in paragraph 18 of the Statement of
Claim.
This
has been communicated to the Claimant and it is agreed that there
will be no order for costs against the owner as a result
of this
approach. The Claimant has indicated that this does not exclude such
costs from an overall costs order that may be issued
by you. The
point is that there will be no special order for costs against the
Defendant based on the fact that the Defendant is
not objecting to
your dealing with the interpretation of schedule 8 on the basis of
the corrected cross-referencing.
Thank
you.
Regards”.
[66]
The defendant referred to in the email is,
of course the applicant. The respondent contends that the email
does no more than
reflect an agreement that there would be no order
for costs against the applicant. It says that there was no
agreement that
the respondent would abandon its plea for
rectification, nor does the letter reflect such agreement.
There is merit in the
respondent’s contention. The first
substantive paragraph in the email records the applicant’s
stance, namely,
that it is prepared to proceed on the basis the basis
of the corrected cross-references contained in the plea for
rectification.
It does not record any agreement that the plea
for rectification would be abandoned. In any event, insofar as
there is any
dispute on this point, the respondent’s version
must prevail.
[67]
There is thus no merit in this aspect of
the review.
[68]
The remaining aspect of this ground of
review is that the rectification awarded in paragraph 72.1 does not
accord with the pleading
for rectification in the statement of
claim. The complaint relates not to the entire paragraph 72.1,
but rather to one portion
of it. More specifically, the
rectification awarded in relation to paragraph 11.7.3. In its
original form, as noted
earlier, this paragraph read (in the
original):
“
For
the avoidance of doubt, regardless of who the operator is, reference
data referred to in paragraphs
11.6.1
and 11.6.2
must in all cases be
corrected for the Long Term Performance Test according to the
following principles … .” (emphasis
added)
[69]
Elsewhere in the original, paragraph 11.7
included cross-references to paragraphs 11.5, and 11.6. The
parties agreed that
these were erroneous and that these references
were to be to read as cross-references to 11.6 and 11.7
respectively. In other
words, it appears that an additional
subparagraph to paragraph 11 was added at some point in the drafting
of the contract, such
that what had originally been 11.5 became
11.6. However, the cross-references clearly were not amended to
follow suit in
paragraph 11.7. Hence the erroneous
cross-references according to the original paragraph numbering.
This is simply
a matter of common-sense if one reads the paragraphs
carefully.
[70]
The applicant’s complaint is that as
regards 11.7.3, in its plea for rectification in the statement of
claim the respondent
had left the reference to 11.
6
.1
and 11.
6
.2
unchanged, but that the arbitrator had nonetheless rectified 11.7.3
such that the references were now to 11.
7
.1
and 11.
7
.2.
This, says the applicant was beyond his power as he was only
empowered to rectify specifically on the terms pleaded by
the
respondent. [underlined for emphasis]
[71]
If one reads paragraph 11.7 in its
entirety, it is patent that the arbitrator’s rectification
accurately reflected what the
parties had intended. Paragraph
11.7.1 (post-rectification) refers to deviations from the reference
data referred to in paragraphs
11.6.1 to 11.6.6. What is more,
it says that the results must be corrected according to the
principles described in paragraphs
11.7.3.1 to 11.7.3.2.
Paragraph 11.7.3 then says (as rectified by the arbitrator) that for
the avoidance of doubt, the reference
data referred to in 11.7.1 and
11.7.2 must be corrected according to the following principles.
[72]
There is a clear link between this
paragraph and paragraph 11.7.1. The only way in which these
paragraphs make any sense is
if the sub-paragraphs are read so that
the “principles” referred to in 11.7.3 apply to all the
reference data identified
in paragraph 11.7.1. To leave 11.7.3
in its original form (as the applicants insist the arbitrator should
have done), would
lead to an irrational result. It would not
lead to the expressed “avoidance of doubt” as to which
reference data
are subject to the 11.7.3 principles. On the
contrary, it would create doubt that could never have been intended
by the parties.
What the parties obviously intended, and what
the arbitrator recognised, was that all the data references were to
be subject to
the principles in paragraph 11.7.3, and not just those
referred to in paragraphs 11.6.1 and 11.6.2, as recorded.
Without
the rectification there would be a clash between paragraph
11.7.1 and 11.7.3. The rectification pleaded simply overlooked
that an additional change had to be made.
[73]
The arbitrator’s rectification was
effected to correct a patent error in the contract. His powers
as arbitrator were
wide enough to do so. Under paragraph
11.2.11 of the applicable arbitration rules, he was afforded the
power to order rectification
of any contract. This is ancillary
to his overall power to exercise the “widest discretion and
powers allowed by law
to ensure the just, expeditious, economical and
final determination of all the disputes raised in the proceedings”.
Rectification was expressly raised as an issue. All that the
arbitrator did was to exercise his overall power to order further
rectification to correct the patent error and to ensure that the
contract accorded with the obvious intention of the parties.
[74]
For these reasons, I find that there is no
merit in this ground of review either.
Conclusion and order
[75]
The applicant has been unsuccessful on all
of the grounds of review advanced. The application must be
dismissed.
[76]
I make the following order:
“
The
application is dismissed with costs, including those of two counsel,
one of whom is senior counsel.”
R M Keightley
JUDGE OF THE HIGH
COURT
JOHANNESBURG
Delivered:
This judgment was prepared and authored by the Judge whose name is
reflected and is handed down electronically
by circulation to the
Parties/their legal representatives by email and by uploading it to
the electronic file of this matter on
Court Online/Case Lines.
The date for hand-down is deemed to be 05 July 2023
.
Date of Hearing:
18 April 2023
Date of Judgment: 05
July 2023
APPEARANCES
For
the Applicant:
Adv.
M Kriegler SC and Adv. M Schafer
Instructed
by:
Norton
Rose Fulbright South Africa
For
the First Respondent:
Adv.
W La Grange SC and Adv. A Russell
Instructed
by:
Pinsent
Masons South Africa
For
the Second Respondent:
Notice
to Abide
Instructed
by:
Dockrat
Attorneys Inc.
[1]
42
of 1965.
[2]
Telcordia
Technologies Inc v Telkom SA Ltd
[2006]
ZASCA 112
;
2007
(3) SA 266
(SCA) at para 85.
[3]
Id
at
para 51.
[4]
Sidumo
& Another v Rustenburg Platinum Mines Ltd and Others
[2007] ZACC 22; [2007] 12 BLLR 1097 (CC); 2008 (2) SA 24 (CC).
[5]
See
Lufuno
Mphaphuli & Associates (Pty) Ltd v Andrews
[2009] ZACC 6
;
2009 (6) BCLR 527
(CC);
2009 (4) SA 529
(CC) par 232
to 234
;
National
Union of Mineworkers obo 35 Employees v Grogan NO & Another
[2010] ZALAC 3
; (2010) 31 ILJ 1618 (LAC) at para 33.
[6]
Ellis v
Morgan; Ellis v Dessai
1909
TS 576
at 581.
[7]
Natal
Joint Municipal Pension Fund v Endumeni Municipality
[2012]
ZASCA 13; 2012 (4) SA 593 (SCA).
[8]
Id
at para 18.
[9]
Capitec
Bank Holdings Ltd and Another v Coral Lagoon Investments 194 (Pty)
Ltd and Others
[2021]
ZASCA 99; 2022 (1) SA 100 (SCA).
[10]
Id
at para 50.
sino noindex
make_database footer start
Similar Cases
Karoshoek Solar One (RF) (Pty) Ltd v Dankocom (RF) (Pty) Ltd and Another (2022/13538) [2023] ZAGPJHC 1284 (3 November 2023)
[2023] ZAGPJHC 1284High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Kariki Pipeline and Water Project (Pty)Ltd v Rand Water Board and Another (2017/0027774) [2022] ZAGPJHC 1005 (9 December 2022)
[2022] ZAGPJHC 1005High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Kariki Pipeline and Water Project (PTY) LTD v Rand Water Board and Another (2017/0027774) [2022] ZAGPJHC 999 (9 December 2022)
[2022] ZAGPJHC 999High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Kariki Pipeline and Water Project (Pty) Ltd v Rand Water Board and Another (2017/0027774) [2022] ZAGPJHC 71 (4 February 2022)
[2022] ZAGPJHC 71High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Moroke v Road Accident Fund (51152/21) [2024] ZAGPJHC 823 (27 August 2024)
[2024] ZAGPJHC 823High Court of South Africa (Gauteng Division, Johannesburg)98% similar