Case Law[2023] ZAGPJHC 1103South Africa
Wanga Engineering And Construction Services CC v Malange (16427/22) [2023] ZAGPJHC 1103 (5 July 2023)
High Court of South Africa (Gauteng Division, Johannesburg)
5 July 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 1103
|
Noteup
|
LawCite
sino index
## Wanga Engineering And Construction Services CC v Malange (16427/22) [2023] ZAGPJHC 1103 (5 July 2023)
Wanga Engineering And Construction Services CC v Malange (16427/22) [2023] ZAGPJHC 1103 (5 July 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_1103.html
sino date 5 July 2023
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG LOCAL
DIVISION, JOHANNESBURG
Case No: 16427/22
NOT REPORTABLE
NOT OF INTEREST TO OTHER
JUDGES
REVISED
In
the matter between:
WANGA
ENGINEERING AND CONSTRUCTION SERVICES CC
Applicant
And
AZWINDINI
ZELDA MALANGE
Respondent
JUDGMENT
FRIEDMAN AJ:
1 In this application,
the applicant seeks payment of R307 044.50, interest, and costs
in terms of an agreement which it concluded
with the respondent on 1
May 2020. I shall describe this agreement as “the building
contract” below. The applicant
also seeks a punitive costs
order, which I discuss more fully below.
2 The building contract
contains various terms, many of which are not relevant to the issues
arising in this application, aimed
at facilitating the construction
by the applicant of a house for the respondent. The total contract
price was R1 050 000.00.
In essence, the building contract
imposed obligations on the respondent to purchase the land on which
the house was to be built
and to procure a mortgage to fund the
construction of the house. The building contract required the
respondent to pay a deposit
of R600 000.00 within 14 days of
acquisition by her of the bank loan. The remaining component of the
contract price would
be funded by the mortgage. As is common in
agreements of this nature, the contract price was to be paid in
progress payments, with
the balance to be paid on completion.
3 Despite the
requirements of the building contract, the respondent did not pay the
R600 000.00 deposit. Rather, between the
period 1 June 2021 and
26 October 2021, she made four payments to the applicant. The
respondent first paid an initial deposit of
R50 000.00. Three
progress payments were then made of R215 707.21, R177 248.25
and R300 000.00 on 8 July 2021,
27 August 2021, and 26 October
2021 respectively.
4 The applicant says that
the construction of the house was completed on 6 December 2021. It
says that the respondent took occupation
on the same day. Two clauses
of the building contract became relevant at that stage:
4.1 Clause 2.1.6 provides
that:
“
Upon completion of
the construction of the House, the Purchaser specifically undertakes
to attend the final inspection of the house
and signing of the Happy
Letter and the final building progress payment forms to authorize the
bank or other financial institutions
to pay the full proceeds of the
mortgage loan and/or guarantee to the Developer”.
4.2 Clause 2.1.7 provides
that:
“
It is a specific
term of this Agreement that the Purchaser shall not after having
signed the Happy Letter and/or having taken occupation
of the
property, instruct the bank to hold back and not pay the Developer
any outstanding amounts, and any attempt to do so, shall
immediately
entitle the Developer to claim the full outstanding amount directly
from the Purchaser”.
5 It presumably goes
without saying that the “Developer” is defined in the
agreement (in clause 1.4) as the applicant
and the “Purchaser”
is defined (in clause 1.3 read with page 1 of the agreement) as the
respondent. The term “Happy
Letter” is defined as “[t]he
Purchaser signing and accepting the House and confirming that the
House has been completed
in accordance with this Building Contract”.
That is a verbatim quote from the building contract.
6 The applicant says
that, after the respondent took possession of the house, she did not
authorise the payment by the bank of the
final instalment to the
applicant. Instead, she withdrew the funds from the bank and refused
to pay the balance then owing, of
R307 044.50, to the applicant.
Based on the allegations described above, and in reliance on clause
2.1.7 (to which I return
below), the applicant seeks payment of this
sum in these proceedings.
# THE RESPONDENT’S
DEFENCE
THE RESPONDENT’S
DEFENCE
7 Before addressing the
merits in her answering affidavit, the respondent took the point that
the deponent to the founding affidavit,
Ms Rapalalane, did not
establish her authority to represent the applicant in the founding
papers. Reference was made to a rule
7 notice sent by email by the
respondent’s attorney to the applicant’s attorney in
which the authority of Ms Rapalalane
and Dube Lesley Attorneys, the
applicant’s attorneys of record, is disputed. To its replying
affidavit, the applicant attached
a resolution dated 7 June 2022
which authorised Ms Rapalalane to “sign all documents, depose
to all affidavits and do all
things necessary on behalf of the
Company in pursuance of the aforesaid application” and
confirming that “Dube Lesley
Attorneys are the appointed Legal
Representatives in the matter”. The email attaching the rule
7(1) notice was sent by the
respondent’s attorney to the
applicant on 31 May 2022 and the resolution is dated 7 June 2022. The
answering affidavit was
filed on 20 June 2022, which is after the
resolution was apparently taken by the applicant. The applicant says
in its replying
affidavit that the resolution was sent to the
respondent’s attorneys, but does not say when this happened –
in particular,
whether it was sent before or after the filing of the
answering affidavit. In the answering affidavit, the respondent says
that
the rule 7(1) notice “remains unanswered by the
Applicant”, which suggests that at that stage the applicant’s
attorney had not yet sent the resolution to the respondent. In any
event, the response of the applicant to the rule 7(1) notice
adequately addresses the issue of authority and the point was not
pressed on behalf of the respondent in argument. It is not necessary
for me to address that issue further.
8 As to the merits, the
respondent in her answering affidavit did not deny that she had
failed to pay the outstanding sum of R307 044.50.
Rather, she
said the following:
8.1 First, she denied
having been presented with, or having signed, a Happy Letter.
8.2 Secondly, she
referred to various respects in which she said that the applicant had
breached the building contract. These allegations
of breach relate to
issues which I would broadly describe as “workmanship
complaints”. The respondent put up evidence,
in the form of an
extract from a WhatsApp chat, to show that she had raised her
dissatisfaction with the applicant’s work
with the applicant;
although the precise nature of the dissatisfaction is difficult to
discern from the extract from the WhatsApp
text annexed to the
answering affidavit.
8.3 Thirdly, she denied
having taken occupation on 6 December 2021. She said that she only
took occupation in February 2022 and
that, at the time she took
occupation, “the cupboards, electrical work, bathroom tiles and
accessories fittings [sic] as
well as the double garage door were not
even done and I had to spend R141 000.00 to install them”.
8.4 Lastly, the
respondent took the position that there were irresolvable disputes of
fact on the papers which precluded the applicant
from obtaining the
relief sought in motion court. I do not discuss the details of this
stance here and prefer to deal with that
argument separately below.
9
Mr Zwane
, an
attorney with right of appearance, filed heads of argument on behalf
of the respondent. In them, he repeated the points summarised
above
(except, as already noted, the authority point). He framed the
dispute-of-fact point as a “preliminary objection”.
# THE MERITS
THE MERITS
10 In my view the merits
of this matter are straightforward. The applicant is entitled, for
the reasons given below, to the relief
which it seeks. I proceed to
explain why, and then conclude by addressing two matters: the
supposed disputes of fact and –
something which I have not
mentioned above – the fact that the building contract has an
arbitration clause.
# The contractual cause
of action
The contractual cause
of action
11 The applicant admitted
in its replying affidavit that no Happy Letter was signed by the
respondent, blaming this on its allegation
that communication with
the respondent had become difficult by that stage. (I pause to note
that the replying affidavit appears
to have been filed four days
late. Condonation for its late filing is sought in the body of the
affidavit, but no formal condonation
application was brought. The
respondent has not sought to take issue with the late filing of the
replying affidavit, and it is
my view that it would be in the
interests of justice for me to have regard to it. Since no formal
condonation application was brought,
I do not see the need to make a
formal order to this effect.)
12 So, it is common cause
that no Happy Letter was signed by the respondent. In this regard,
the text of clause 2.1.7 of the agreement
is important. I have
reproduced it in paragraph 4.2 above, but repeat it for convenience
here. It provides that:
“
It is a specific
term of this Agreement that the Purchaser shall not after having
signed the Happy Letter and/or having taken occupation
of the
property, instruct the bank to hold back and not pay the Developer
any outstanding amounts, and any attempt to do so, shall
immediately
entitle the Developer to claim the full outstanding amount directly
from the Purchaser”.
13 The building contract
provides, in clause 2.1.4, that progress payments will be made from
time to time and that the “full
amount including the
‘initiation fees’ will be paid upon completion of the
house”. The plain text of clause 2.1.7
suggests that if one of
two events takes place the Purchaser (ie the respondent) becomes
precluded from instructing the bank to
withhold the final payment;
which carries the corollary that the final payment must be made at
that point. One of these events
is the signing of the Happy Letter
and the second of these events is the taking of occupation of the
property by the Purchaser.
So, in other words, this clause seems to
be clear that, if the Purchaser takes occupation of the property, she
cannot interfere
with the requirement that the bank makes the final
payment; and, if she does, the Developer (ie, the applicant) may
claim the final
payment directly from her.
14 The applicant says
that the respondent took occupation of the property on 6 December
2021. The respondent denies this and says
that she only took
occupation in February 2022. In its replying affidavit, the applicant
says that the respondent is misleading
the court when she says she
only moved into the house in February 2022. To support this
contention, a WhatsApp exchange from 20
November 2021 in which the
respondent appears to say that she would “start moving
tomorrow” and an electrical compliance
certificate, which is
dated 4 November 2021, are provided.
15 I cannot say, on the
evidence before me, precisely when the respondent took occupation. I
say this, in particular, while keeping
an eye on the test applicable
to disputes of fact in motion court, a topic to which I return below.
Yes, on the one hand, the WhatsApp
exchange does suggest that, in
November 2021, the respondent was about to move in (the electrical
certificate is entirely inconclusive
on the issue of occupation). But
anything could have happened between the time when the respondent
sent that text and when she
ultimately moved in. I simply do not have
sufficient evidence on this issue to make a definitive finding.
16 But nothing turns on
that for present purposes. This is because, as shown above, it is
common cause that in February 2022, before
this application was
launched, the respondent took occupation. So, for my purposes, I must
proceed on the basis that two key facts
are common cause:
16.1 First, that, as of
February 2022, the respondent was in occupation of the property.
16.2 Secondly, despite
taking occupation, the respondent did not pay the final payment of
R307 044.50, reflecting the sum needed
to discharge the total
contract price by that time.
17 On the plain text of
clause 2.1.7 of the building contract, this would seem to suggest
that the respondent has no defence to
this application. Having taken
occupation, she was obliged to facilitate payment of the final
instalment of the contract price
to the applicant. And, having failed
to do so, the applicant became entitled to claim that sum.
18 The respondent’s
defence to this application – leaving aside the claim that
disputes of fact prevent the applicant
from obtaining the relief
which it seeks – is that there were defects in the applicant’s
performance. As framed in
the answering affidavit, the respondent
takes the view that the applicant’s breach of the building
contract means that the
respondent is not obliged to pay the balance
of the contract price. In fairness to the respondent, and reading her
papers generously,
her stance seems to be slightly more nuanced than
that. She appears to contend (although the point was not framed in
this way)
that she is entitled to some sort of set-off arising from
the poor workmanship, and that the quantum of the applicant’s
claim
cannot be determined in motion proceedings.
19
Having
regard to the fact that courts are now enjoined to interpret
agreements in a unitary exercise in which language, context
and
purpose assume equal importance,
[1]
the question is whether the agreement can be interpreted to support
the respondent’s defence. Put differently, does the building
contract, properly interpreted, permit the respondent to withhold the
final payment on the basis that the applicant allegedly breached
the
agreement by not providing the quality of workmanship required by the
contract?
20 I have already
intimated that the plain text of clause 2.1.7 does not support the
respondent’s defence. But clause 2.1.7
must also be read in the
context of the agreement as a whole. In my view, the building
contract, read as a whole, does not envisage
a defence along the
lines of the defence which the respondent wishes to raise. In
particular, the building contract envisages specific
remedies for the
respondent in circumstances where she was not satisfied with the
applicant’s workmanship.
20.1 Clause 5 of the
building contract is headed “Warranties and Defects Liability”.
Clause 5.1 provides that, on completion
of the house, the Purchaser
“shall take possession of, and inspect, the house” and
provide the applicant with a “final
written list within 14 days
of any work still to be completed and/or defects to be remedied”.
It then provides that the “defects
liability period shall
commence from the date of completion”.
20.2 Clause 5.2 provides
that as soon as any remedial work identified on the list has been
completed and accepted by the Purchaser,
the house will be deemed to
be complete.
20.3 Clause 5.3 then
provides that:
“
Any payment
defects, shrinkage or other faults which may appear within 3 months
after completion of the house due to material or
workmanship not in
accordance with this Agreement, or faults occurring before completion
of the house, shall within a reasonable
time after receipt of the
Purchaser’s written instructions be made good by the Developer
at his own cost”.
20.4 Clause 5.5 is
also relevant to the interpretive exercise. It provides that:
“
Any repair of a
leakage in the roof or any damage to the house caused thereby,
arising from the faulty materials or workmanship,
occurring within a
period of 12 months after completion of the house shall be undertaken
within 30 days after receipt of the Purchaser’s
written
notification of such leakage and/or damage”.
20.5 Clause 5.9 then
provides that:
“
The Developer
shall be relieved of the above undertakings if the Purchaser fails to
give the Developer written notice on/before
the expiry of the said
period, to the effect that the Developer is required to fulfil the
relevant undertakings. A certificate
by the appointed inspector
stating that any defect for which the Developer is liable, and which
is rectified, shall be final and
shall relieve the Developer from any
further obligations”.
20.6 In addition to these
provisions of clause 5, the clause dealing with breach has relevance
to the interpretive exercise. It
envisages the resolution of disputes
by arbitration, a topic to which I return below. But it also contains
the following relevant
clauses:
20.6.1 First,
clause 8.1 provides:
“
Should a party to
this agreement fail timeously or fully to perform any obligation
resting upon it in terms of this agreement or
arising out of the
agreement (“the defaulting party”) then the other party
having the right to have the obligation
in question performed (the
“aggrieved party”) shall call upon the defaulting party
to remedy the failure within 14
(fourteen) days after the date on
which the defaulting party has been called upon to remedy such
failure”.
20.6.2 Secondly,
clause 8.2 provides:
“
Should the
defaulting party fail to remedy its failure within the period
stipulated in the notice, the aggrieved party shall be
entitled to
terminate this agreement forthwith by notice in writing, and without
prejudice to any rights which it may have in law,
to take action
against the defaulting party for damages it may have suffered as a
result. Alternatively, the aggrieved party may,
should it so wish,
proceed against the defaulting party for specific performance in
terms of this agreement.”
21 It seems to me that,
in the light of these clauses of the building contract (including, of
course, clauses 2.1.6 and 2.1.7),
the position under the agreement is
the following:
21.1 The agreement
envisages that, on completion of the construction of the house, there
will be a final inspection which will enable
the purchaser to
identity any problems. If no problems are identified, then the
purchaser will sign the Happy Letter with the consequences
which flow
from that.
21.2 If the purchaser is
dissatisfied with the workmanship in any respect, her first and
primary remedy is not to take occupation
and not to sign the Happy
Letter. But, of course, defects in workmanship might appear after a
purchaser takes occupation and a
purchaser cannot be expected to
notice, and highlight, every defect before taking occupation. This is
why the agreement also gives
the purchaser the right to identify
defects in workmanship which might come to her attention within the
first three months after
the completion of the house. This right is
to be exercised by giving the developer written instructions to
remedy the defect; and,
on receiving such instructions, the developer
is obliged to remedy the defect at its own cost.
21.3 There is also the
self-standing right, not confined to a particular time limit, on
either party effectively to place the other
party in breach of an
obligation in the building contract by giving the other party 14 days
to remedy the breach. This carries
the concomitant right of the
innocent party, if the breach is not cured within the period
stipulated in the notice, either to cancel
the agreement and claim
damages or claim specific performance.
21.4 Therefore, if the
respondent was aggrieved by the standard of workmanship even before
taking occupation, she could have elected
not to take occupation and
then place the applicant on terms to remedy the defects in terms of
the provisions discussed above.
Or, if the respondent became aware of
problems after moving in, she could have used her rights in the
agreement to oblige the applicant
to address the problems –
including on pain of cancellation, if necessary. But what the
respondent could not do is take occupation
of the premises, fail to
avail herself of any of the rights described above, and simply refuse
to pay the balance of the contract
price. The provisions discussed
above demonstrate that this conduct is categorically precluded.
22 There is an indication
in the papers that, in fact, the respondent
did
avail herself
of some of the rights mentioned above. As I noted above when
explaining the respondent’s stance in the answering
affidavit
(see paragraph 8.3 above), the respondent explains that, when she
took occupation, she had to spend R141 000.00
taking care of
aspects of the building work which were not done. The applicant
accepts that this is the case, and says (with a
proof of payment
attached in support) that it reimbursed the respondent for this
payment which was “inclusive of all complaints
that were raised
by the Respondent”.
23 Both parties filed
relatively terse affidavits and many of the factual allegations made
by both sides raise more questions than
answers. This applies to the
dispute about the R141 000.00, amongst others. It is not
necessary for me to become engaged with
those factual disputes,
including the one about the R141 000.00. I mention it to
illustrate a fundamental point about the
clear intention of the
parties as reflected in the proper interpretation of the agreement.
The building contract envisages a series
of mechanisms which assist
the purchaser to compel the developer to ensure that proper
workmanship was provided in all cases. The
idea clearly being to
preserve the agreement and ensure that it was properly fulfilled by
both sides, rather than to make it easy
for either party to walk
away. While providing the purchaser with various protections, it also
protects the developer by preventing
the purchaser from doing
precisely what the respondent has attempted to do in this case.
24 It follows that, on a
proper interpretation of the building contract, the respondent’s
answering affidavit discloses no
defence. On the key common cause
fact – that the respondent took occupation of the property –
nothing alleged by the
respondent in her answering affidavit
exonerated her from the obligation to ensure payment of the final
instalment of the purchase
price.
# Disputes of fact?
Disputes of fact?
25 Rule 6(5)(g) provides
that, “where an application cannot properly be decided on
affidavit the court may dismiss the application
or make such order as
it deems fit with a view to ensuring a just and expeditious
decision.” The respondent has not relied
on rule 6(5)(g)
expressly in her answering affidavit or heads of argument but has
used its terminology to explain why she says
that the application
should be dismissed.
26
In
Lombaard
,
[2]
an application was brought in the High Court by Mr Lombaard to
transfer certain immovable property to him. His application failed
and he appealed to the Supreme Court of Appeal. There was no
application in the High Court for the matter to be referred for the
hearing of oral evidence or to trial. The High Court simply
determined the matter on the papers. But, in the SCA, a debate arose
as to whether the matter ought to have been, and therefore should now
be, referred to oral evidence. The majority of the SCA held
that a
proper factual basis for a defence had been set out in the answering
affidavit and had not been addressed by the applicant
(now appellant)
in his replying affidavit. In holding that it would not be
appropriate to refer the matter to oral evidence –
and that,
instead, it was appropriate for the SCA to confirm that the
application was rightly dismissed by the High Court –
the SCA
said the following:
“
An
order to refer a matter to oral evidence presupposes a genuine
dispute of fact (
Room
Hire Co (Pty) Ltd v Jeppe Street Mansions (Pty)
Ltd
1949 (3) SA 1155
(T)
at 1163;
Ripoll-Dausa
v Middleton NO and others
2005 (3) SA 141
(C)
at 151F ff [also reported at
[2005]
2 All SA 83
(C)
– Ed]). The appellant chose not to respond to the factual
allegations concerning rectification. He did so at his
peril . .
.”
[3]
27
There are
several ways in which the
Lombaard
matter
is distinguishable from the present case. But, I have referred to
Lombaard
because it is helpful in the following respect: when there are
genuine disputes of fact, the court will normally dismiss an
application
in circumstances where the applicant ought reasonably to
have anticipated them.
[4]
However, before a court even enters into an enquiry as to whether the
applicant ought to have anticipated that there would be genuine
disputes of fact on the papers, it has to be convinced that there are
genuine disputes of fact on the papers in the first place.
If there
are not, no purpose would be served in referring the matter for the
hearing of oral evidence or trial under rule 6(5)(g).
Rather, the
result of the application will be determined largely by the question
of which party has failed to raise a genuine dispute
of fact: if it
is the respondent, then the application would normally be granted on
the basis of the principles expressed in
Plascon-Evans
.
[5]
If it is the applicant – which would arise in circumstances
such as in
Lombaard
when the applicant fails to, or cannot, address a genuine factual
defence put up in the answering affidavit – then the
application
would simply be dismissed.
28 To determine that
there is a genuine dispute of facts, it is necessary to consider the
allegations in the affidavits of each
side and ask: if the
allegations made in the papers of each side turn out, with the
leading of oral evidence, to be true, would
they disclose a cause of
action or defence? To give an easy example (and let us leave aside
that an applicant would be most unlikely
to bring a claim of this
nature on application): a particular applicant sues a respondent for
R500 000 in delict for intentional
damage to property. In her
founding affidavit, she gives a detailed narrative of how the
respondent caused extensive damage to
the applicant’s car. In
the respondent’s answering affidavit, he gives a detailed
narrative of how he had nothing to
do with the damage and was out of
the country at the time. If the applicant’s version is true,
she must win. If the respondent’s
version is true, he must win.
This is a genuine dispute of fact.
29 On the other hand, a
genuine dispute of fact will not even be triggered if the respondent
puts up a version saying something
along the lines of: the applicant
is wrong when she says that I destroyed her car with a hammer, I
actually did it with explosives.
Yes, the parties may have different
factual versions as to what actually happened. But, on either of
their versions, the applicant
must win.
30 Therefore, it seems to
me that a court faced with a decision of how to apply the provisions
of rule 6(5)(g) should ask the following
questions:
30.1 Is there a
genuine
dispute of facts on the papers?
30.2 If there is, then
the next question is: ought the applicant to have anticipated these
disputes of fact when launching the application?
If the answer to
that is yes, then ordinarily the court would dismiss the application.
30.3 If the applicant
cannot have anticipated that disputes of fact would arise, or there
is some other compelling consideration,
the court would then ask
whether it is in the interests of justice for the matter to be
referred to trial or for a referral to
oral evidence in respect of a
discrete topic to be made. This will depend on the facts of each
case.
31 In her answering
affidavit, the respondent in essence flagged the following factual
disputes:
31.1 Whether the
applicant completed the building and construction in compliance with
the building contract.
31.2 Whether there were
structural defects that ought to have been remedied by the applicant,
and which it failed to remedy despite
them being brought to its
attention.
31.3 The quantum of what
the respondent owes the applicant, if anything. The respondent says
that the quantum is not readily ascertainable
from the papers.
32 In her heads of
argument, the respondent says that it is clear from the papers that
there is a material dispute about whether
the applicant completed the
building and construction in compliance with the building contract.
33 In should by now be
apparent that none of these supposed disputes of fact can assist the
respondent in resisting the applicant’s
claim. On the proper
approach to disputes of fact, which I have set out above, one has to
place each party’s version side
by side (assuming, for the sake
of conducting this exercise, that the respondent’s factual
version triggers a genuine dispute
as to what the true facts are) and
ask: does the respondent’s version of the facts constitute a
defence to the applicant’s
case? For all of the reasons given
above, even if the respondent is correct that the applicant did not
comply with its obligations
under the agreement, and even if the
respondent is correct that there were structural defects, these facts
do not disclose a defence
to the applicant’s claim for payment.
34 Once one accepts that
the existence of defects in the workmanship of the applicant does not
constitute a valid defence to the
claim as framed by the applicant,
it also becomes apparent that there is no dispute of fact on the
question of the respondent’s
indebtedness. The only way for
there to be such a dispute, on the facts as alleged by the
respondent, would be if the respondent
were entitled to withhold
payment of some or all of the outstanding amount as a result of the
allegedly shoddy workmanship. Once
one finds, as I must, that the
respondent does not have this entitlement, the quantification of the
amount that she owes become
a straightforward exercise. It is common
cause that the contract price was R1 050 000.00. It is also
common cause that
the respondent paid R742 955.46, which is the
sum of the payments made as itemised in paragraph 3 above. The
applicant is
clearly entitled to the balance, which is R307 044.54.
(The astute reader will notice that this sum differs, in the amount
of 4c, from the sum claimed in the notice of motion. I address that
below.)
# The arbitration clause
The arbitration clause
35 The last issue which I
must address is the fact that the agreement contains an arbitration
clause. Neither party referred to
this issue at all and I raised it
with them during the hearing. The applicant acknowledged that there
was such a clause, but pointed
out that the respondent did not object
to the jurisdiction of this Court by relying on it in her answering
affidavit (or, indeed,
in argument). The applicant submitted that, in
the absence of an objection by the respondent, that was the end of
the matter and
this Court has jurisdiction to grant the relief
sought.
36
The
applicant is clearly correct. In the answering affidavit, the
respondent did not take the point that her right to have the dispute
arbitrated precluded the applicant from obtaining the relief which it
seeks from this Court. It appears now to be settled that,
even where
an agreement has an arbitration clause, an applicant or plaintiff is
entitled to proceed via litigation in court. If
the
respondent/defendant wishes to assert its right to arbitrate, it must
do so – in other words, it must elect whether to
challenge the
step taken by the applicant/plaintiff to proceed via litigation or to
submit to it. If it fails to assert that right
by objecting to the
jurisdiction of the court, and instead submits to the jurisdiction of
the court, it must be taken to have waived
its right to arbitrate.
[6]
37 It follows that the
applicant was entitled to take its chances by bringing court
proceedings. The failure of the respondent to
object means that this
Court has jurisdiction to grant the relief sought.
# THE NATURE OF THE COSTS
ORDER
THE NATURE OF THE COSTS
ORDER
38 The building contract
does not deal with the issue of costs. I mention this because both
parties asked, in the event of success,
for a costs order on the
attorney-client scale. Neither party substantiated this request in
the heads of argument which were filed.
It was clarified in argument
that both parties sought a punitive costs order, in the event of
success, on the basis of their view
that the other party had
litigated unreasonably.
39
As Todd AJ
recently put it in
Beer
,
[7]
relying on the decision of the SCA in
Claase
[8]
and quoting from the decision of the Constitutional Court in
Swartbooi
:
[9]
“
Our courts will
grant costs on a punitive scale where a party has been put to
unnecessary expense in consequence of conduct by a
litigant that can
reasonably be characterized as unreasonable or obdurate. An
award of this kind requires ‘
special considerations arising
either from the circumstances which gave rise to the action or from
the conduct of the losing party
’.” (Emphasis in the
original.)
40 I have explained above
that the applicant’s claim in this Court must succeed and that
the respondent’s defences to
the application have no merit.
However, I can find no basis to conclude that the respondent’s
conduct – either through
the conduct in the litigation or from
the circumstances leading to the present dispute – rises to the
level of being characterised
as unreasonable. She clearly felt
aggrieved by the workmanship of the applicant. Whether her grievances
were objectively justified
is unclear to me; and, as demonstrated
above, this issue is irrelevant to the decision which I must make on
the merits. What does
seem clear is that her response to this
application was not so palpably indefensible as to rise to the level
of being unreasonable
– at least in the sense understood by our
courts in the context of punitive costs orders.
41 If follows that the
applicant has not made out a case for a punitive costs order.
# CONCLUSION AND ORDER
CONCLUSION AND ORDER
42 As appears from
everything which I have said above, the applicant’s claim must
succeed.
43 I have explained above
(see paragraph 34) that the outstanding balance of the contract price
is R307 044.54. In the notice
of motion, the applicant claims
R307 044.50. Either the applicant voluntarily and deliberately
abandoned 4c of its claim (perhaps
in a rounding-down exercise
similar to that conducted by some of our major retailers at points of
sale), or the sum claimed in
the papers was derived as a result of an
oversight. While I doubt that either of the parties would grumble
over 4c, I intend to
stick with what is claimed in the notice of
motion because I did not have the opportunity to ask the parties
about this.
44 In the notice of
motion, the applicants simply seeks “interest at the prescribed
rate”. Interestingly, clause 2.1.8
of the building contract
provides that interest “is payable on all amounts which is
[sic] due and payable by the Purchaser
under this Agreement and which
remains [sic] unpaid for a period of 7 days from date of receipt of
demand, at the prime interest
rate plus 3% as charged by ABSA from
time to time and shall be calculated and compounded monthly in
arrears.” It is unclear
to me why the applicant did not seek to
rely on this clause in these proceedings. But, since it did not do
so, I say nothing more
about this provision of the building contract.
45
The reason
why I raise the issue of interest is that there could be a reasonable
debate about whether the building contract fixes
a date for
performance by the respondent of its obligation to pay the final
instalment of the contract price.
[10]
For instance, had it been common cause that the respondent signed a
Happy Letter on a particular date, or if it had been common
cause
that the respondent took occupation on a particular date, then it
might have been possible to identify a term of the agreement,
properly interpreted, which fixed the date of performance. However,
not only is there insufficient evidence before me as to when
precisely the respondent was in breach, the applicant has not
attempted to argue that the building contract envisaged a specific
date for performance of the obligation on which it sues, which was
earlier than when it demanded payment.
46
The
applicant’s claim clearly constituted a claim for a liquidated
amount. As a consequence, the default position is that
interest began
to run when the respondent received the applicant’s letter of
demand.
[11]
On the evidence
before me, this was no later than 22 February 2022 – this is
the date on which the respondent said that she
received the letter of
demand, in an email which she sent on 1 March 2022. To avoid any lack
of clarity on this issue, I intend
to spell this out in my order.
47 I accordingly make the
following order:
1. The respondent is
ordered to pay to the applicant the sum of R307 044.50.
2. The respondent is
ordered to pay interest on the sum described in paragraph 1 above at
the prescribed rate, calculated from 22
February 2022 to date of
payment.
3. The respondent is
ordered to pay the costs of this application.
ADRIAN FRIEDMAN
ACTING JUDGE OF THE
HIGH COURT
GAUTENG LOCAL
DIVISION, JOHANNESBURG
Delivered: This judgment
was prepared and authored by the Judge whose name is reflected above
and is handed down electronically
by circulation to the parties/their
legal representatives by email and by uploading it to the electronic
file of this matter on
CaseLines. The date for hand down is deemed to
be 5 July 2023.
APPEARANCES:
Attorney
for the applicant:
Dube
Lesley Attorneys
Counsel
for the applicant:
L
Dube (Attorney with right of appearance)
Attorney
for respondent:
Peter
Zwane Attorneys
Counsel
for the respondent:
P
Zwane (Attorney with right of appearance)
Date
of hearing: 15 March 2023
Date
of judgment: 5 July 2023
[1]
University
of Johannesburg v Auckland Park Theological Seminary
2021 (6) SA 1
(CC) at para 65
[2]
Lombaard v Droprop CC [2010] 4 All 229 (SCA)
[3]
Lombaard (supra) at para 26
[4]
See Economic Freedom Fights v Manual
2021 (3) SA 425
(SCA) at para
114
[5]
Plascon Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984] ZASCA 51
;
1984 (3)
SA 623
(A) at 634-5
[6]
See
BDE Construction v Basfour 3581 (Pty) Ltd
2013 (5) SA 160
(KZP) at
paras 9-10
[7]
Beer
v South African Institute of Chartered Accountants 2022 JDR 3058
(GJ) at para 45
[8]
Claase
v Information Officer, South African Airways (Pty) Ltd
2007 (5) SA
469
(SCA) at para 11
[9]
Swartbooi
v Brink
2006 (1) SA 203
(CC) at para 27
[10]
See
Scoin Trading (Pty) Ltd v Bernstein NO
2011 (2) SA 118
(SCA) at para
13; Dunn v Road Accident Fund
2019 (1) SA 237
(KZD) at para 19
[11]
See
Da Cruz v Bernado
2022 (2) SA 185
(GJ) at para 45; Thoroughbred
Breeders’ Association v Price Waterhouse
2001 (4) SA 551
(SCA)
at para 86
sino noindex
make_database footer start
Similar Cases
Ngwenya v Allied Builders Home Centre (Pty) Ltd (2022/18959) [2023] ZAGPJHC 1330 (17 November 2023)
[2023] ZAGPJHC 1330High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Ngwenya v Ngwenya NO and Others (16549/2021) [2023] ZAGPJHC 1002 (6 September 2023)
[2023] ZAGPJHC 1002High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Magwabeni v Magwabeni and Others (29566/19) [2023] ZAGPJHC 80 (2 February 2023)
[2023] ZAGPJHC 80High Court of South Africa (Gauteng Division, Johannesburg)99% similar
N.W.M v N.Q.M and Another (2018/39527) [2023] ZAGPJHC 956 (16 August 2023)
[2023] ZAGPJHC 956High Court of South Africa (Gauteng Division, Johannesburg)99% similar
W.L v W.B.L (2022-015956) [2023] ZAGPJHC 1189 (15 September 2023)
[2023] ZAGPJHC 1189High Court of South Africa (Gauteng Division, Johannesburg)99% similar