Case Law[2023] ZAGPJHC 941South Africa
Transnet SOC Ltd v Totalenergies Marketing South Africa (Pty) Ltd and Others (2022/007321) [2023] ZAGPJHC 941 (23 August 2023)
High Court of South Africa (Gauteng Division, Johannesburg)
23 August 2023
Headnotes
Summary: Application to compel – Targeted discovery ito Rule 26 of the Commercial Court Rules – Relevance under Commercial Court Rules considered
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 941
|
Noteup
|
LawCite
sino index
## Transnet SOC Ltd v Totalenergies Marketing South Africa (Pty) Ltd and Others (2022/007321) [2023] ZAGPJHC 941 (23 August 2023)
Transnet SOC Ltd v Totalenergies Marketing South Africa (Pty) Ltd and Others (2022/007321) [2023] ZAGPJHC 941 (23 August 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_941.html
sino date 23 August 2023
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
Case No: 2022/007321
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED.
SIGNATURE
DATE: 23/08/2023
In
the matter between:
TRANSNET
SOC LTD
Plaintiff/Respondent
and
TOTALENERGIES
MARKETING SOUTH AFRICA (PTY) LTD
First Defendant
SASOL
OIL (PTY) LTD
Second
Defendant/Applicant
NATIONAL
PETROLEUM REFINERS
OF
SOUTH AFRICA (PTY) LTD
Third
Defendant
NATIONAL
ENERGY REGULATOR OF SOUTH AFRICA
Fourth Defendant
Coram
:
Ingrid Opperman J
Heard
:
16 August 2023
Delivered
:
This
judgment was handed down electronically by circulation to the
parties’ legal representatives by email. The date and time
for
hand-down is deemed to be 14h00 on 23 August 2023
Summary
:
Application to compel – Targeted discovery ito Rule 26 of the
Commercial Court Rules – Relevance under Commercial
Court Rules
considered
ORDER
The application for
targeted document disclosure dated 24 July 2023 is dismissed with
costs, such costs to include the costs of
two counsel where so
employed.
JUDGMENT
INGRID
OPPERMAN J
Introduction
[1]
This is an application, brought by Sasol
against Transnet, to compel the production of documents under Rule 26
of the Commercial
Court Rules.
[2]
The background to the main action is,
briefly, that Transnet charges Total and Sasol amounts for use of its
Crude Oil Pipeline (
COP
).
Transnet concluded an agreement during December 1991 which stipulated
a formula for increases in the crude oil tariff (
the
variation agreement
). On 21 June 2022,
the Constitutional Court found that the variation agreement was
validly terminated with effect from September
2020. There is at
present no contractual arrangement between the parties.
[3]
Transnet claims amounts from Sasol and
Total for invoices issued for services rendered for the period after
the termination of the
variation agreement and relies on tariffs set
by the National Energy Regulator of South Africa (
NERSA
).
The services relate to the use of Transnet’s COP for the
conveyance of crude oil from Durban to the NATREF refinery
in
Sasolburg. Total and Sasol have not paid what they were charged by
Transnet. Instead, they have paid less than what was claimed
by
Transnet, contending that Transnet is under a legal obligation to
discount the tariff charged to Total and Sasol. Transnet has
instituted this action for the difference between what was charged
and what Sasol and Total have paid (
the
short payment
).
[4]
The essence of the dispute before this
Court in the main action is whether Transnet is under a legal
obligation to discount the
tariff charged to Total and Sasol.
[5]
Transnet holds a licence to operate a
petroleum pipeline system (
the
Licence
). In terms of clause 16.1
of the Licence, Transnet is required to charge users of COP tariffs
that are consistent with
sections 28(2)(a)
to (d) of the
Petroleum
Pipelines Act 60 of 2003
, as amended (
PPA
).
In terms of clause 16.2 of the Licence, Transnet must comply with
section 28(6)
of the PPA.
Section 28(6)
provides that: “
A
licensee [Transnet] may not charge a tariff for the licensed activity
in question other than that set or approved by the Authority
[NERSA]”
[6]
NERSA’s decision-making process is
governed by statute. Neither Total nor Sasol have challenged NERSA’s
decision-making
process in the main action. Accordingly, the way in
which NERSA went about making its decision is irrelevant to these
proceedings.
Sasol’s
position
[7]
Sasol contends that the tariff set by NERSA
is a maximum tariff and that Transnet (not NERSA) is obliged to
charge tariffs that
are consistent with
section 28(2)(a)
to (d) of
the PPA. In breach of its legal obligations, Transnet charged a
tariff by merely applying the ‘maximum’ tariff
without
taking a decision, as it was required to do, to charge a discounted
rate. In the alternative, Sasol contends that if Transnet
did make a
decision, such decision was invalid on certain review grounds set out
in Promotion of Administrative Justice Act 3 of
2000 (
PAJA
).
Sasol also pleads that the tariff was not fair and was discriminatory
and that Transnet was exercising coercive power over Sasol
when it
applied the tariff.
[8]
Sasol does not seek, in this action, any
relief under PAJA or the principle of legality to review and set
aside the tariff.
Instead, it contends that Transnet is not
entitled to charge, and Sasol is not obliged to pay, the allegedly
invalid tariff, also
referred to as the impugned tariff.
The request
[9]
On 24 July 2023, Sasol filed a six page
request for documents which forms the basis of this application to
compel. The request,
brought under Rule 26 of the Commercial
Court Rules, seeks two broad streams of information.
[10]
The first relates to a category of
documents which focuses on whether Transnet
ever made a
decision in respect of the tariff to be charged to Sasol. A review of
these documents, so it is contended, will
permit the Court (and
Sasol) to see if Transnet properly applied its mind to whether to
discount the tariff charged for the
conveyance of
crude in the COP. It includes documents ‘
demonstrating
steps taken by Transnet when deciding to charge the impugned
tariff’
.
[11]
The second category, outlined in paragraph
2 of the request, encompasses a demand by Sasol that Transnet
‘
produce documents reflecting
information
’ on about 50
wide-ranging topics about the commercial value, operating costs,
efficiency, and productivity of Transnet’s
pipeline system.
Sasol indicates that it wants this information in order to enable it
to file an expert report.
The First Category
[12]
It is clear, from Transnet’s
replication to Sasol’s plea, that Transnet pleads that it did
not take a decision to charge
Sasol a discounted rate. Although the
reason for doing so is irrelevant for purposes of deciding whether
targeted disclosure of
the documents sought are to be allowed, the
reason advanced is that it can only do so if NERSA approves a
discount for which none
was applied. Thus, should this Court find
that there was a legal obligation on Transnet to consider a
discounted tariff, it failed
to do so and that’s the end of
that. Transnet considered itself bound to apply the NERSA approved
tariff, and that is what
it did. A choice of whether to charge a
discounted tariff or not to charge a discounted tariff was not, as
Transnet pleads it,
open to Transnet. It simply charged the NERSA
approved tariff. Transnet pleads that it did not have to apply its
mind regarding
a lower tariff and no decision had to be made or was
made regarding a lower tariff. A such none of the documents in this
category
have to be provided.
The Second Category
[13]
Mr
Turner SC, representing Sasol, argued that relevance is determined
with reference to the issues crystalised in the pleadings.
This of
course, as a general proposition and within the Uniform Rules of
Court, is correct.
[1]
But
Ms Pillay SC, acting for Transnet, correctly emphasized the fact
that, this matter being one in the Commercial Court, one should
look
not only to the Uniform Rules of Court but also to the Commercial
Court Rules. She argued that the concept of relevance has
been
somewhat widened if regard is had to Rule 26 of the Commercial Court
Rules which provides:
‘
[T]he
Judge may allow for the
targeted disclosure
of documents.
If permitted, a request for disclosure must be made concerning
specific documents or classes of documents that
are relevant to the
dispute
as defined in the statement of case or responsive
statement of the case.
’ (emphasis added)
[14]
The ‘statement of case’, in
this case, includes Transnet’s amended particulars of claim,
its amended replication,
the summary of the claim contained in the
statement of case, the essential documents listed therein as well as
the summary of the
evidence. Similarly, the ‘responsive
statement’ includes Sasol’s amended plea, the essential
documents listed
therein and the summary of the evidence.
[15]
In my view, the enquiry into relevance in
this case should be commenced with an enquiry into what relief the
parties are seeking:
Transnet seeks:
‘
(a)
An order declaring that the plaintiff [Transnet] is obliged to
charge, and the first and second defendants [Total and Sasol]
are
obliged to pay, the tariff set by NERSA for the conveyance of crude
oil from Durban to NATREF.
(b) The first defendant
[Total] is ordered to pay ZAR461,946,277.55 to the plaintiff
(c) The second defendant
[Sasol] is ordered to pay ZAR815,590,950.53 to the plaintiff’.
[16]
Both Sasol and Total seek the dismissal of
Transnet’s claim. Both Sasol and Total have referred to PAJA in
their respective
pleas but have sought no review relief against
Transnet; they have not pleaded nor claimed what a tariff, compliant
with their
legal arguments, would have been. The tariff as charged is
impugned. What tariff should have been charged is not stated.
[17]
As mentioned previously, the essence of the
dispute before this Court is whether Transnet is under a legal
obligation to discount
the tariff charged to Total and Sasol.
Transnet does not dispute that it is
entitled
to discount the tariff charged if NERSA approves such discounted
tariff but disputes that it is
obliged
to discount the tariff where NERSA has not approved a discounted
tariff.
[18]
The difficulty with Sasol’s case, as
currently framed, is what this Court is to do if, at the end of the
day, it should make
a finding in Sasol’s favour that Transnet
was
obliged in law
to discount the tariff. Neither Transnet nor Sasol have pleaded nor
claimed that payment should be made of a lesser sum based on
such a
finding. Thus, a legal finding in Sasol’s favour, on the
existing relief claimed, would be one in which Transnet’s
claim
is dismissed. There is no relief sought based on Sasol’s legal
construction other than the dismissal of Transnet’s
claim. If
an entire trial were to be run on, not only what facts should have
been considered by Transnet but which facts were considered,
one
knows that one will probably arrive at a lesser tariff because one
knows, from what Sasol has pleaded, that Transnet charged
the
‘maximum’ tariff (on Transnet’s version, the only
tariff it was authorised by NERSA to charge). But it matters
not at
which tariff one arrives, because if the law is against Transnet,
Transnet’s claim for payment at the NERSA approved
tariff would
be dismissed and Sasol would win. Sasol has not asked for a
declarator that what it paid is legally compliant with
the notional
lesser tariff that Transnet should allegedly have charged. All this
Court knows is that Sasol unilaterally paid a
lesser amount. The
Court does not have the benefit of knowing how that lesser amount was
arrived at. The question which falls for
determination is why this
Court is to direct discovery to be made of documents which will
explore what the lesser tariff should
have been when Transnet’s
case does not depend on it nor does Sasol’s case depend on a
finding as to what the lesser
‘correct’ tariff should
have been. All that matters is whether the tariff charged was legally
the correct one to charge
or not. To explore the foundations for a
lesser tariff is to invite a descent into an irrelevant factual
morass
in this
action.
[19]
Transnet’s replication alleges
NERSA’s
tariff
is compliant with the PPA. It is not
Transnet’s
tariff. Transnet’s stance is that
they were applying the tariff considered by NERSA. If that tariff
i.e., NERSA’s, is
not legally compliant, Transnet contends that
that fight is one to be had between NERSA and Sasol, and is not to be
traversed in
this action.
[20]
Transnet
further submitted in the heads of argument filed, that even if it
were to be found that it made a decision, Sasol’s
application
is fundamentally flawed because it overlooked the first principle of
Oudekraal,
[2]
which
holds that an administrative action, once taken, exists in fact and
has legal consequences that cannot simply be overlooked
but must be
treated as fact until set aside by a Court .
Transnet
contended that the effect of this
principle
is that, even if Transnet’s tariff were unfair or
discriminatory, Sasol “
is
compelled
to
pay that tariff until and unless it has been set aside on review
”.
Sasol
on the other hand contended that Transnet failed to appreciate the
distinction that the cases have drawn between ‘classical’
collateral challenges on the one hand and ‘reactive’
challenges by organs of state on the other. Both Transnet and
Sasol
cautioned that I should not rule on this feature as Total’s
rights, (and Total is not party to the current application),
will be
affected by such a ruling.
[21]
Mr Turner SC, representing Sasol, argued
that Transnet raised what is essentially a legal objection to Sasol’s
plea and that
if Sasol’s defence were indeed objectionable on
this basis, then Transnet ought to have raised its objection by way
of an
exception. It has not done so, so the argument continues, and
it cannot now raise such an objection
in
order to deny Sasol the documents it requires to establish its
defence. Indeed, in raising
this
objection at this stage, the criticism continues, Transnet conflates
the merits of Sasol’s defence, with Sasol’s
entitlement
to obtain disclosure of documents required to establish its defence.
I was urged to conclude that the trial
Court
will, in due course, determine whether Sasol’s defence is
sustainable in law but that that was not the question for
present
purposes.
[22]
I disagree that Transnet is asking this
Court at this stage to determine the validity of Sasol’s
defence. In my view, the
position at present can be summarised as
follows: Transnet has pleaded that it charged the tariff set by
NERSA. It has pleaded
that it is obliged to do so. It has also
pleaded that it is entitled to charge Sasol a discounted rate
provided NERSA approves
such discounted rate which did not occur. It
took no decisions in relation to Sasol which involved the exercise of
discretions
or the weighing up of interests. It pleaded essentially
that it applied the NERSA set tariff in a robotic or mechanistic
manner
as it submits it was obliged to do, to charge the tariff set
by the body which sets tariffs. Thus: if the Court finds that a)
Transnet
was obliged in law to charge NERSA’s
set
tariff; b) Transnet was entitled in law to charge a discounted NERSA
tariff provided the discount was approved by NERSA (which
would then
amount to the set tariff contemplated in a)); and c) that NERSA in
fact had not approved a discounted rate (i.e. it
had not set the
discounted tariff), it would follow, that Transnet would be entitled
to its declaratory relief. On this scenario,
the PAJA challenges all
come into play in Sasol’s relationship with NERSA (not
Transnet) and are irrelevant to the issues
which fall for
determination by this Court on the current pleadings.
[23]
Sasol placed much reliance on paragraph 5
of Transnet’s replication: Transnet “
pleads
specifically that it
appropriately applied the extant
tariff set by NERSA, which tariff is: 5.1 lawful
under section 28(1) of the Act; 5.2
warranted under section 28(2) of the Act; and
5. .
3
properly to be applied under section
28(3) of the Act.”
These
allegations so the argument goes, show
that Transnet does not accept that its
application of the tariff was flawed and that it intends to rely on
attributes of the tariff.
This in turn shows that the information
informing the make-up of the tariff, to justify charging the tariff,
is relevant as it
will be relied upon. The replication thus requires
factual allegations on whether the tariff set was based on the
factors set out
in section 28 of the PPA and evidence on Transnet’s
evaluation of the NERSA tariff from which it satisfied itself that
the
NERSA tariff took into account the factors set out in section
28(2)(a) of the PPA.
[24]
Transnet is not contending that it did have
regard to such factual allegations. If it is found that it ought to
have considered
any such factual allegations, it should fail in its
claim.
[25]
Sasol also pins its argument on the
following paragraph in Transnet’s amended replication to
Sasol’s plea:
‘
11.2
In the event that it be concluded (contrary to Transnet's stance)
that a discretionary power existed to impose a tariff other
than the
one imposed by NERSA, and that Transnet's conduct is irregular in any
material respect, then Transnet pleads that the
tariffs imposed by
NERSA constitute an appropriate
quantum
meruit
to which it is entitled as just
and equitable relief, whether under section 172 of the
Constitution, section 8 of PAJA or
otherwise.
[26]
It is this
quantum
meruit
position (the reasonable value
of services) which Sasol contends throws open the net for Sasol to
explore the reasonableness of
the tariff. The documents sought are,
under these circumstances, self-evidently relevant as all that ought
to have been considered
should then be unpacked.
[27]
Transnet’s pleaded position though is
that it took no decision in relation to the tariff charged. It’s
pleaded position
is that it slavishly applied a tariff dictated to it
by NERSA which tariff is informed by the PPA and other applicable
legislation
including the PFMA. It followed NERSA which applied a
methodology which was decided upon after input from all stakeholders
and
this approach, it contends is appropriate and reasonable and
constitutes an appropriate quantum meruit. Transnet’s position
as I understand it is that the actual considerations in respect of
NERSA’s methodology, are not relevant to the tariff Transnet
charged as it was NERSA who set the tariff, not Transnet. The
considerations in setting such a tariff pertain to factors considered
by NERSA, not Transnet. The only “factor” Transnet would
have considered is whether or not to apply the NERSA tariff.
The
documents requested pertain to factors informing the setting of the
tariff (which lies with NERSA) and not factors informing
Transnet’s
“decision” to impose NERSA’s tariffs. Essentially,
the documents requested would not inform
the basis for the set tariff
– NERSA is the entity that would be in possession of the
documents underlying the setting of
the tariff.
[28]
If I am wrong on my construction of the
documents which informs relevance in these proceedings, I would
nonetheless find that all
the PAJA considerations can be raised in
principle, but it is unnecessary to give factual content thereto
because Sasol is not
seeking any tariff-compliant relief. I
thus do not agree with Sasol’s contentions that evidence will
need to be led
to show what facts ought to have been considered by
Transnet when setting the tariff. Transnet has pleaded clearly: it
took no
decision.
[29]
The Commercial Court rules make no
provision for the taking of an exception to a pleading, for a request
for further particulars
or for general discovery. Paragraph 1 of
Chapter 1 of the Commercial Court Rules provides that the ‘
Commercial
Court aims to promote efficient conduct of litigation in the High
Court and resolve disputes quickly, cheaply, fairly
and with legal
acuity.’
Aligned with that are
the provisions of paragraph 18 which reads: ‘
Matters
heard in the Commercial Court will be dealt with in line with the
broad principles of fairness, efficiency and cost-effectiveness’
.
[30]
As highlighted earlier, Rule 26 of the
Commercial Court Rules casts the net for relevance somewhat wider. I
conclude that at this
stage of the proceedings, the documents sought
are not relevant. This is an interlocutory ruling and as matters
unfold and pleadings
are amended, this might change, and this ruling
can be revisited.
[31]
I
was specifically asked not to rule on Transnet’s assertion that
Sasol’s application is fundamentally flawed because
it has
overlooked the first principle of
Oudekraal
[3]
,
which
holds that an administrative action, once taken, exists in fact and
has legal consequences that cannot simply be overlooked
but must be
treated as fact until set aside by a Court .
[32]
I want to make it plain that my ruling in
respect of relevance has assumed that Sasol’s challenge is one
falling within the
‘classical’ collateral challenge
category and that Sasol is not required to institute review
proceedings and Sasol
is entitled to challenge the validity of the
‘administrative act’ (if it is found to be one) as of
right. These
are all assumptions made in Sasol’s favour
but nonetheless do not disturb my finding on relevance.
[33]
I thus rule that it may well constitute a
legal defence but there are no facts which need to be explored and
which require the production
of documents by Transnet.
Confidentiality and
extent of the request
[34]
In my view, the concern can be dealt with
by imposing confidentiality restrictions on disclosure and Ms Pillay
suggested as much
during argument. This is not the real issue at
present though.
[35]
A further criticism raised was that the
Rule 26 request is overly broad, vague and lacks particularity. In my
view, if the documents
are relevant, it is perfectly permissible to
describe them in categories as Sasol did. It is difficult to ask for
that which one
doesn’t have and to describe where to find that
which one does not even know whether it exists. In my view, however,
this
application stands or falls on relevance, and I need not concern
myself with the nature of the request and accordingly decline to
do
so.
Costs
[36]
No reason has been advanced as to why the
costs should not follow the result. Even though I have ruled that a
request of this nature
could conceivably be entertained again, this
application is self-contained, and the costs should be dealt with
herein.
Order
[37]
I accordingly make the following order:
The application for
targeted document disclosure dated 24 July 2023 is dismissed with
costs, such costs to include the costs of
two counsel where so
employed.
I
OPPERMAN
Judge of the High Court
Gauteng Local Division,
Johannesburg
Counsel
for the applicant (Sasol):
Adv D
Turner SC, Adv M Mbikiwa and Adv A Ngidi
Instructed
by:
Mchunu
Attorneys
Counsel
for the Respondent (Transnet):
Adv K
Pillay SC, Adv R Tulk, Adv YS Ntloko, Adv N Nyembe and Adv M Dafel
Instructed
by:
Webber
Wentzel
Date
of hearing:
17
August 2023
Date
of Judgment:
23
August 2023
[1]
Indeed,
a Court’s jurisdiction is determined with reference to the
pleadings see
Gcaba
v Minister of Safety and Security and Others
2010
(1) SA 238
(CC) at paras [74] to [75]
[2]
Oudekraal
Estates (Pty) Ltd v City of Cape Town and Others
,
2004 (6) SA 222 (SCA)
[3]
Oudekraal
Estates (Pty) Ltd v City of Cape Town and Others
,
2004 (6) SA 222
(SCA)
sino noindex
make_database footer start
Similar Cases
Transnet SOC Ltd v Santam Ltd (30445/2014) [2023] ZAGPJHC 879 (7 August 2023)
[2023] ZAGPJHC 879High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Transnet Soc Limited T/A Transnet Freigth Rail v Tanker Services Fuel And Gas (Pty) Ltd (33982/2019) [2023] ZAGPJHC 199 (6 March 2023)
[2023] ZAGPJHC 199High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Transnet Second Defined Benefit Fund v Wood (21875/21) [2022] ZAGPJHC 906 (10 November 2022)
[2022] ZAGPJHC 906High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Transnet SOC Limited v Santam Limited (30445/2014) [2022] ZAGPJHC 918 (9 November 2022)
[2022] ZAGPJHC 918High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Transnet Limited v ERF 152927 Cape Town (PTY) Ltd : In re: ERF 152927 Cape Town (PTY) Ltd v Transnet Limited (35967/2010) [2022] ZAGPJHC 542 (29 July 2022)
[2022] ZAGPJHC 542High Court of South Africa (Gauteng Division, Johannesburg)100% similar