Case Law[2023] ZAGPJHC 1008South Africa
WBHO-Lubocon JV v Eskom Holdings SOC Limited and Another (005599/2022) [2023] ZAGPJHC 1008 (8 September 2023)
High Court of South Africa (Gauteng Division, Johannesburg)
8 September 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 1008
|
Noteup
|
LawCite
sino index
## WBHO-Lubocon JV v Eskom Holdings SOC Limited and Another (005599/2022) [2023] ZAGPJHC 1008 (8 September 2023)
WBHO-Lubocon JV v Eskom Holdings SOC Limited and Another (005599/2022) [2023] ZAGPJHC 1008 (8 September 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_1008.html
sino date 8 September 2023
FLYNOTES:
ADMINISTRATIVE – Tender –
Disqualification
criteria
–
WBHO
seeking to set aside its disqualification and award to Grinaker –
Eskom avers WBHO had not provided mandatory information
–
Without required information it cannot properly assess a bid –
Bidder had a duty to access document online,
fill and return it –
Tender was not unfair nor was it irrational for Eskom to have
disqualified WBHO for non-compliance
– Application dismissed
–
Promotion of Administrative Justice Act 3 of 2000
.
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
CASE NO:
005599/2022
(1)
REPORTABLE: YES/NO
(2)
OF INTEREST TO OTHER JUDGES: YES/NO
(3)
REVISED: YES/NO
SIGNATURE
DATE
In
the matter between:
WBHO-LUBOCON
JV
Applicant
and
ESKOM
HOLDINGS SOC LIMITED
First Respondent
(REGISTRATION
NUMBER: 2002/015527/30)
GRINAKER
LTA-ENZA CONSTRUCTION
Second Respondent
JONIT
VENTURE
JUDGMENT
Manoim J
[1]
This case concerns whether the court should review and set aside a
tender awarded
by the first respondent Eskom Holdings Soc Ltd
(“Eskom”) because of a disqualification criteria to which
bidders for
the tender were subject. The applicant, a joint
venture known as the WBHO-Lubocon joint venture (“WBHO”),
was
amongst other bidders, disqualified for not meeting this
criteria. The tender was awarded to the only bidder that qualified;
the
second respondent, a joint venture known as Grinaker LTA- Ezra
Construction Joint Venture (“Grinaker”). (Grinaker did
not oppose and filed no papers in these proceedings.)
[2]
WBHO’s case is that there are two independent reasons for
reviewing and setting
aside the award to Grinaker, based on Promotion
of Promotion of Administrative Justice Act 3 of 2000 (“PAJA”).
The
first challenges the legality of its disqualification. Eskom says
it disqualified WBHO because it had not provided mandatory
information.
But says WBHO that obligation was not made clear in the
tender, and it would be unfair for that reason to impose it on
bidders.
Second, WBHO says the scope of the tender was changed after
the award to Grinaker but only the latter was given an opportunity to
re-quote on the revised tender. Rather, says WBHO what should have
happened was that the tender should have been re-opened to all,
including those initially disqualified.
[3]
WBHO has reformulated its relief several times but essentially it
seeks to set aside
its disqualification, and the award to Grinaker.
In consequence of this relief, it further seeks to be awarded the
tender. In the
alternative it seeks to have Grinaker’s, and its
respective tenders re-evaluated, once WBHO is given an opportunity to
submit
the crucial document known as the Appendix to Tender, the
omission of which was the basis for Eskom disqualifying it, and then
for the best scoring tender (as they were on the date of the opening
of the tenders) to be accepted by Eskom.
[4]
Eskom opposes both grounds of review. I will approach the decision by
examining each
ground in turn but first some background is needed.
Background
[5]
On 5 November 2020 Eskom put out a tender to eight construction firms
to bid on a
tender to build a combustion waste terrace at the Kusile
power station in Mpumalanga.
[1]
In layperson’s terms this is a structure to house the ash that
is a byproduct of the coal that is burnt at the power station.
Kusile
already has an existing waste terrace which was built at the power
station by WBHO and is known as Phase 1. However, this
structure will
soon be filled up, so a new structure is required. This is described
in the tender as Phase 2.
[6]
Of the eight firms that were invited to tender for Phase 2 only five
submitted bids,
but for various reasons only that of Grinaker made
its way out of the disqualification stage. None of other firms that
bid has
challenged the award so in this decision I am only concerned
with the challenge brought by WBHO.
[7]
WBHO submitted its bid on 17 February 2021 which was in time for the
deadline. It
claims it heard nothing from Eskom about the outcome of
the tender but then heard rumours that another firm had won.
[2]
Its estimator Joe Carter wrote to Eskom and asked for a debriefing
meeting with them. This is the type of meeting where the employer,
as
the bid offeror is sometimes referred to in the tender literature,
explains to the jilted bidder what its shortcomings were.
Presumably
because if it bids again in the future, it will rectify these.
[8]
On WBHO’s version, the Eskom officials met with its staff who
explained that
WBHO had failed to submit what is referred to as the
“
FIDIC
contract data
”.
This was later confirmed in a letter to WBHOs attorneys where Eskom
wrote that the tenderer had “
been
deemed non-compliant”
with the basic compliance requirements due to the contractors failure
to submit the “
required
FIDIC contract data”.
[3]
More about this term later as the first ground of review turns on its
interpretation. WBHO’s people say they were non-plussed.
They
did not know what this meant and what they should have supplied that
they didn’t. This then led WBHO to decide on litigation.
[9]
On 8 July 2022, WBHO brought Part A of this notice of motion by way
of an urgent application
in which it sought an interim interdict to
restrain the respondents from further implementing the tender pending
the finalisation
of the review. Eskom filed its answer on 14 July
2022. The application was never heard as an urgent matter. That
much is
common cause but not why it was not heard. WBHO claims this
was by agreement as it was not going to be able to file its reply on
time. Eskom claims the withdrawal was unilateral and that the urgency
was self-created and misconceived.
[10]
Whether or not the application justified urgency is not for me to
consider now. What is relevant
from this early exchange of papers is
that for the first time in the answering affidavit, Eskom gave
greater detail for why the
WBHO bid had been disqualified. Eskom
explained that the requirement to provide “FIDIC contract data”
meant filling
in a form called the Appendix to the Tender
(“Appendix”). This document required the bidder to fill
in certain information
in conjunction with the rest of the bid
documents submitted. It is now common cause that WBHO never submitted
the Appendix with
its other bid documents hence this was the basis
for its disqualification.
[11]
Later, when urgency was no longer pressing it, WBHO filed its
replying affidavit. Here the person
responsible for submitting its
tender, its estimator Joe Carter alleged that Eskom only downloaded
the Appendix on 25 January 2021.
Recall, the tender was announced on
5 November 2020. Nevertheless, WBHO submitted its tender only on 17
February 2021. Thus, even
on Carter’s version it would have
been available to it prior to submission. In explanation, WBHO
alleges that Eskom had downloaded
new documents at several times
since the tender was announced and Eskom never alerted WBHO to the
fact that the Appendix had only
been downloaded on 25 January 2021.
But Conradt Meyer, WBHO’s managing director of the relevant
division, and its deponent
to the replying affidavit, states
:
“
If
the applicant knew Eskom added the Appendix to Tender to the tender
documentation it would have been a very simple exercise to
complete
the document and to include it in applicants bid submission.”
[12]
But relying on the version of Carter, WBHO at this stage in its
replying affidavit, confidently
asserted that Carter was correct. He
went as far as to put up screen shots from his computer which he said
shows all the documents
he downloaded from the Eskom tender website
to complete WBHO’s tender. None he said showed the Appendix was
on the website
at the time.
[13]
Since the filing of the replying affidavit, several supplementary
affidavits needed to be exchanged
before the facts on when the
Appendix was downloaded by Eskom to the website became common cause.
Carter, it turns out was wrong.
Although he alleged that the Appendix
to tender had only been downloaded to the website, in his estimate,
on 25 January 2021, the
Appendix had been downloaded to the Eskom
website on 5 November 2020, and thus was available before to WBHO to
access well before
its tender was submitted on 17 February 2021. In
fact, Carter downloaded all his documents the day after, on 6
November, but appears
to have missed the Appendix. Significantly
WBHO’s own IT personnel have now verified that Eskom’s
version on when the
Appendix was downloaded is correct thus
contradicting Carters’ initial assertion.
[14]
Thus, the initial version of WBHO in its founding and replying
affidavits has been proved incorrect
in two respects. First its
allegation that there was no document that existed which corresponded
to the request for FIDIC contract
data; there was, it was the
Appendix. Second, that it had not been downloaded to the website
timeously; it was, on 5 November 2020
along with several other
documents thus was available to WBHO to find on 6
th
November when Carter says he performed the first download.
[15]
During the course of the exchange of papers, WBHO requested and was
provided with, Eskom’s
record of how the tender was decided.
From these papers WBHO has made two further points. First, it emerged
that Grinaker had,
after being appointed as the approved bidder, been
asked to requote for the project based on a new specification for the
lining
of the waste facility. WBHO argues is that this amounted to a
re-designing of the project which meant that Eskom should have
re-tendered
the entire project so that each invited bidder could have
requoted based on the new lower cost design specification for the
lining.
[16]
The failure to re-tender constitutes WBHO second point of review. I
go on to discuss this later.
[17]
The second fact of significance emerging from the record was how
Grinaker had completed the Appendix.
Since the absence of this
document from the WBHO tender submission was Eskom’s
justification for disqualifying it, it is
relevant to whether bidders
were treated equally to see how Grinaker responded. WBHO requested
the document from Eskom. Eskom in
turn asked Grinaker’s
attorney to provide it so that the latter could redact any
confidential information from it. But the
version provided by the
attorney contained several blanks where Grinaker had apparently not
provided the requested information.
If this was the prerequisite for
valid tender, WBHO contended, then Grinaker too should have been
disqualified.
[18]
But here another controversy emerged. When Eskom had this omission
pointed out, it filed another
affidavit, referred to as the
explanatory affidavit. In this affidavit Antonio Mammes, a senior
procurement manager at Eskom, claims
that the version sent that
emanated from Grinaker’s attorney, was not the final version
that Eskom had received with the
tender and considered. He attached
another version of the Appendix from Grinaker which he asserted was
the one Eskom considered.
This one differs from the first one
supplied by Grinaker’s attorney, in that all the questions are
now answered, except in
one respect.
Was
Grinaker’s tender properly completed
[19]
Although this was not advanced as an independent self-standing ground
of review in the papers,
I will deal with it as if it is. Like the
re-tender objection, it is based on the assumption that completion of
the Appendix was
a mandatory returnable and hence must be considered
as a third ground for review – that Eskom has acted
inconsistently in
the application of its own rules.
[20]
The first issue is whether Eskom has provided an authentic version
the Appendix attached to the
Grinaker tender. This version was
supplied by Eskom in the so-called explanatory affidavit, which,
despite its name, was a further
supplementary answering affidavit.
[21]
WBHO whilst not contesting the filing of this affidavit urges me not
to accept this version.
Relying on the well-known
Wightman
decision
counsel for WBHO urged me to reject this version on the basis that
this mere assertion was insufficient.
[4]
It required, he argued, for Mammes to have given more facts; why he
was the person with personal knowledge, where he had extracted
this
version, was it the one supplied at the time and where had it been
retained.
[22]
I do not accept this approach. Mammes has personal knowledge of the
tender and has done all he
needed to do for the purpose of motion
proceedings. He relied on Grinaker’s attorney to supply the
Appendix because he says
she needed to redact confidential
information from it. She had got the wrong document he contends and
now he was providing the
correct version. There was no reason for him
to elaborate on this any further. He is not to quote
Wightman
resting his case on a “…
bare
and ambiguous denial.”
For the purpose of these proceedings, I must apply
Plascon
Evans
and accept Eskom’s version.
[5]
[23]
But WBHO further argues that even if the version now supplied by
Mammes is the correct version
of the Appendix, it is still deficient.
Although Eskom did not require that all the questions in the Appendix
be answered –
only those indicated - one of those it needed to
fill in was the bidder’s bank account details. In answer to
this question
Grinaker had filled in: “
TBA if the tender is
approved
”. Grinaker, WBHO argued, had thus failed to answer
the question. Hence, it was on Eskom’s own version,
non-compliant
and should have been disqualified. But Eskom’s
counsel argued that the question had been answered; the only issue
was whether
the answer should be considered sufficient. I agree with
this, although Eskom has not put up any explanation to justify
sufficiency.
[24]
The question then is what legal conclusion to draw from the allegedly
insufficient answer. Put
differently, is the undertaking to defer
providing the consortium’s banking details, an insufficient
response to the question,
so much so as to justify a conclusion that
Grinaker has submitted a non-responsive Appendix, and hence, not
conformed to a mandatory
requirement to provide the FIDIC contract
data. In my view in the context of this tender one could not conclude
that deferring
the provision of bank account details, was so material
as to render the Appendix submitted non-responsive. The purpose of
the Appendix
as was explained by Eskom, was to enable those tasked
with determining the award to compare information from bidders in a
succinct
format. This was one of the objectives of the Appendix
despite the fact that some of this information had already been
supplied
elsewhere by bidders. But not all the information supplied
serves this comparative objective. It is unlikely that the supply of
banking information would be relevant to the comparison. Thus, the
fact that Grinaker elected to supply this information only later
if
it won the tender would not have been a comparative fact relevant to
the assessments of the bids and hence despite the insufficient
response would not have been a rational basis for disqualifying its
bid.
[25]
I go on now to consider the two other grounds of review. As a point
of departure, the legal standard
for which the lawfulness of a tender
process by a state actor such as Eskom must be judged by is common
cause. Statutory wise,
the governing provisions are section 217(1) of
the Constitution, section 51(1)(a)(iii) of the Public Finance
Management Act (“PFMA”)
and section 2(1)(f) of the
Preferential Procurement Policy Framework Act (“PPPFA”),
among others. The values
the Constitution requires of state
contractors is that their processes are fair, equitable, competitive,
and cost effective.
[6]
[26]
WBHO relies on PAJA and that is central as well to this assessment.
But it has adopted a shotgun
approach to PAJA, contending almost all
of that statute’s review grounds apply, when the case turns on
more narrowly on questions
of fairness, transparency, and equal
treatment, and to the extent that Eskom has given explanations for
its decision making, whether
they are rational.
Mandatory
requirement.
[27]
WBHO commenced this case on the premise that Eskom had made mandatory
a requirement that was
so cryptic and unclear that it was impossible
to comply with. The mandatory requirements were set out in the
document sent out
to the bidders.
[7]
The bid document stipulated that certain requirements had to be
provided with the tender and others could be provided for later.
It
was made clear in the tender document that a bidder would be
disqualified if what were termed as the “
mandatory
returnables”
were not completed. WBHO does not dispute this. What is at issue is
what was meant by one of the returnables which were described
as the
“
completed
FIDIC schedule
and
contract data
”.
(My underlining) The first part of the phrase, the reference to the
“FIDIC completed schedule” was understood
and WBHO
supplied it. Both sides agree on this. Both also understood the
reference to “contract data” to be qualified
by the
adjective “FIDIC” i.e., what was meant was not any
contract data but
FIDIC
contract
data
.
The reference to FIDIC is also clearly understood and is a
well-accepted term used internationally in the building industry
which
references a standard form contract which is then cut and
pasted for specific contracts.
[8]
[28]
WBHO’s complaint is that the term
FIDIC contract data
had
no generally accepted meaning. There was no reference to such a term
in the 1999 FIDIC red book, the bible of the industry,
although it
has come to have a meaning in the latest version of the book, the
second edition of 2017. Nevertheless, WBHO contends,
the bid
documents refer specifically to the first edition, not the second
edition of the red book.
[29]
WBHO raises a series of questions – if Eskom was referring to
the Appendix as the mandatory
returnable document, why did not just
say so in express terms? Why use obtuse language to make a
simple point? Why
did Eskom in its first response not again
make this clear? Why did this explanation only come about in its
answering affidavit?
Why did it, in the answering affidavit, continue
the opaqueness of the term “contract data” by saying it
“included
the Appendix”? This suggests, by the use of the
word “inclusion”, WBHO argues, that the Appendix was a
subset
of the remaining requirement for
contact data
, but if
this was the case, what was the remaining data?
[30]
All these criticisms are valid. Eskom never explains why it
chose to refer to the FIDIC
contract data when it could have more
easily referred to the Appendix if this was the information it was
requesting. The courts
have made clear in a number of cases that it
is a requirement of fairness that tender documents must make bid
requirements clear.
[31]
Thus, in
GVK Siyazama Building Contractors (Pty) Ltd
v
Minister of Public Works & Others
the court held:
“
(…)
,
tender documents which do not provide sufficiently clear information
about bid requirements create confusion and thus fall short
of the
requirements of fairness."
[9]
[32]
In
Babcock Ntuthuko Engineering (Pty) Ltd v Eskom Holdings SOC
Limited and Others
Millar J held
:
“
(…)
,
a tender must be framed in a manner that is not ambiguous and affords
all tenderers an equal opportunity to understand what the
requirements of the tender are and to meet those requirements. It is
inevitable that a poorly drafted and ambiguous … tender,
such
as the one in the present case, would be impeachable”.
[10]
[33]
In
AIIPay
the Constitutional Court put it most succinctly,
explaining that:
“
The
purpose of a tender is not to reward bidders who are clever enough to
decipher unclear directions. It is to elicit the best
solution
through a process that is fair, equitable, transparent,
cost-effective, and competitive.”
[11]
[34]
Eskom does not dispute that these cases set out the law on what is
required of a fair tender
specification. But it argues that reliance
on the linguistic aspect of the case is a red herring. The real issue
is how WBHO approached
the completion of its tender documents and why
it did not follow the instructions it was meant to.
[35]
This place the current case in a different category to those of
GVK
Siyazuma, Allpay
and
Babcock
. Eskom has made two
arguments in relation to the question of sufficient clarity, and I
consider both to be correct.
[36]
First, WBHO knew that the provision of certain information was
compulsory for a bid to qualify.
The bid document states:
“
Mandatory
Tender Returnables
a)
Should the supplier fail to provide any mandatory tender returnables
as clearly specified in the tender enquiry, the tender submission
will be deemed non-responsive;”
[37]
Second, the phrase “
FIDIC contract data”
was
clearly something in addition to the “
FIDIC schedule”
because it was prefaced by the word “
and”
. Once
this additional category of information was required, the bidder
would have been on notice to provide it. If WBHO was still
uncertain
what it was it should have asked. It never did. But because Carter
was unaware that the Appendix had been downloaded,
WBHO is in no
position to argue that it still would not have been aware that this
was the FIDIC contract data. But even if one
speculates that it might
still not have joined the dots, the real question is was there
anything about the Appendix which suggested
it was not a mandatory
returnable?
[38]
There is a footnote on the first page of the Appendix which states
that:
“
Tenderers
are required to insert information, if and as applicable, where items
are referenced [*]"
. The use of the term required is not
ambiguous. It must be completed. If it must be completed it follows
it must be submitted.”
[39]
Then the body of the Appendix document contains three columns. The
first describes the item,
the second references it to a clause number
in the FIDIC Red Book’s particular conditions, whilst the third
indicates the
information required. There can be little doubt that
the reader of the Appendix would have appreciated from reading its
contents
that this was a document that had to be submitted with the
tender, with the referenced items inserted.
[12]
Amongst the items referenced for completion were:
a.
The stipulated profit percentage
b.
The termination profit percentage
c.
The percentage for adjustment of provisional sums.
[40]
Eskom says without this information it is impossible to properly
assess a bid. Carter would have
known this if he had seen the
Appendix. Nor would it require straining the language to conclude
that these three items constitute
data even though the Appendix is
not described as the FIDC contract data. Thus, any reasonable reader
of the Appendix would have
understood that its completion where
indicated and submission, was part of the mandatory tender
requirements even if they did not
appreciate at the time that this
constituted the FIDIC contract data. But Eskom goes further to assert
this should have been appreciated
by those in the industry.
According to Eskom:
“
it
is a common understanding for those working with FIDIC in the
industry that the Appendix to Tender contains the contract data under
the FIDIC suite of contracts.”
[41]
Granted WBHO says the language is used in a later FIDIC Red Book
formulation and not the one
referenced in the tender.
[13]
But the later formulation was in use in the industry at the time WBHO
tendered and should have been familiar to bidders. It is
not a case
of where the FIDIC references were contradictory and WBHO had
mistakenly relied on an earlier version of the same terminology
that
had been given a different meaning. But in any event, as I have
stated, the content of the Appendix was such as to alert the
reader
to its significance and the need for its submission as part of the
bid documents. Indeed, this point was conceded by WBHO
in the
replying affidavit (that was at the time it denied awareness of the
existence of the Appendix having been downloaded at
the relevant
time).
[14]
It stated that it
would have completed and submitted the Appendix if it knew of its
existence then.
[42]
But the existence of this document was not hidden from the bidders.
According to Eskom, and this
is not disputed, the tender
advertisement contained a link. A bidder clicking on the link would
be directed to a page headed “
Drop off summary”
which
listed thirty separate documents that had been downloaded. One of
these documents was headed ‘
Appendix to tender’
.
It is now common cause that the Appendix was on the website on
5 November 2020 and was thus available to WBHO by the 6
th
November 2020, the day Carter says he first downloaded documents from
the Eskom website. His failure to download the Appendix,
it now
accepted, was due to his own error not that of Eskom’s.
[43]
To summarise the position in respect of the first ground of review.
WBHO’s review case
was initially based on two factual
misconceptions. First it alleged that there was no FIDIC contract
data document for bidders
to complete. But Eskom explained in the
answering affidavit that there was such a document – it was the
Appendix. This then
led to the second error. WBHO relying on Carter
contended that even if this was the FIDIC contract data, the Appendix
had never
been on the website prior to WBHO submitting its bid. But
this too proved false – a fact that WBHO now concedes.
[44]
This has limited WBHO’s review case on the first point to a
linguistic one. Had the Appendix
not been available on the website
this may have been an arguable proposition. But its presence on the
website and the requirement
for bidders to read downloaded documents,
coupled with the content of the Appendix which makes its status as a
mandatory returnable
obvious to the reader, removes any ambiguity.
Thus, each bidder had an equal opportunity to access the mandatory
returnable at
the same time and in the words of
Allpay
there
was “
no burden to decipher unclear directions”
imposed on any bidder. The diligent bidder would have accessed the
document form the website as instructed and seen from its contents
that it was something that it was required to complete and return.
[45]
The tender was not unfair nor was it irrational for Eskom to have
acted in the way it did to
disqualify WBHO. Once it had specified
that completion was mandatory it was obliged to disqualify a bidder
which did not submit
the completed Appendix. This review ground
fails.
Second
basis
[46]
The second basis of complaint is about the change in specification.
This was not part of WBHO’s
original cause of action and only
emerged when the record of decision making was produced.
[47]
What emerged from the record in the analysis done by Eskom’s
staff is that they considered
the Grinaker bid was “…
way above the budgeted amount by
[amount was redacted] and
that “…
it should be renegotiated to a market related
price
…”
[48]
Whether there was any connection between this proposal and what
happened next is less clear.
However, what happened is that Eskom
received regulatory approval from the Department of Forestry,
Fisheries and Environment to
change the liner on phase 2 from a Class
A liner to a Class C liner. In less technical terms it meant that
whilst the original
tender required bidders to quote on two layers of
HDP lining (Class A) the new specification required only a single
layer of lining.
[15]
This
would effectively reduce the associated costs since less material
would be required. Eskom got Grinaker, by then the chosen
preferred
bidder, to submit a new quote based on the reduced specification. No
one else was asked to quote. Grinaker’ s bid
which had up until
then been above that of WBHO’s (quoted on Class A linings) was
now below it. WBHO claims that if had been
asked to bid on the new
specification it would still have been lower than that of Grinaker,
and by some margin.
[49]
But what WBHO contends is that this amounted to a ‘major design
change’ and even
worse, amounted to ‘tender manipulation’
designed to bring the Grinaker price down so it was affordable to
Eskom. These
complaints, although not argued in this way, suggests
two criticisms about the design change.
[50]
First that its scope was such that it should have meant that the
whole Phase 2 project should
have been put out for a fresh tender.
This argument depends on the extent of the change or put differently
is an argument about
the consequences of substantiality. The second
suggests bad faith – Eskom was manipulating the costs so as to
bring the favoured
bidder, post award, in line with a market related
price.
[51]
The argument around substantiality required WBHO to establish that
the character of the tender
had changed so materially from what was
originally advertised that fairness required it be put up for a new
bid or that all those
invited should be permitted to re-tender based
on the new specifications. However, it was for WBHO as the applicant
to make out
its case on this aspect both on the facts and on the law.
I was not given any factual basis for doing so. WBHO’s factual
case here amounted to no more than repeating what Eskom stated about
the difference between the two specifications. The fact that
WBHO
could so confidently state what its new bid price would have been had
it been asked to tender on the new specifications, suggests
that they
were not that substantial technically. One layer of the materials to
be used as opposed to two. This does not on the
face of it appear to
be a substantial design change that materially could have affected
the nature of the original bid. It was
not seeking a complete
re-design of the waste facility – only a reduction on the
protective layer, subject to environmental
approval, which it had
got. Moreover, it led to a reduction in expense not an increase.
[52]
Nor has WBHO referred me to any case law as to when a change in
design is so material as to justify
on the grounds of fairness,
transparency, cost effectiveness or equitability, that a new bid is
required. Eskom makes the point
that its tender documents stipulated
that Eskom reserved the right to engage in post tender negotiations
with a preferred bidder.
According to the invitation to tender
document:
“
Please
note: Eskom reserves the right to negotiate with preferred bidders
after a competitive bidding process or price quotations;
should the
tendered prices not be deemed market-related”.
[53]
This is precisely what Eskom did. It concluded the price was not
market related and it negotiated
it to a lower price. Second it makes
the point that the regulatory approval from the Department only came
in October 2021 –
ten months after Grinaker had been awarded
the bid. This negates any suggestion of tender manipulation. Eskom
needed this consent
in order to lower the tender specification
downwards and this was not available to it at the time of the
original bid.
[54]
I find that this second basis for review is also without foundation.
Was
WBHO’s allegation that its bid was superior to Grinaker’s
relevant?
[55]
Much was made by WBHO in its papers about the fact that its bid was
substantially lower than
that of Grinaker’s, before the
specification to Class C was made, and that even thereafter, its bid,
if re-tendered, would
have remained lower.
[16]
It also suggested that as the firm that had undertaken Phase 1 it was
the obvious candidate for Phase 2. Further remarks about
Grinaker’s
financial status were also made arising from concerns that emerged by
Eskom itself in the record. However, this
case does not concern
whether Eskom chose the best candidate. It is about whether WBHO was
incorrectly disqualified from further
consideration. I found that it
was not. Second, whether given the scope change a new tender was
required and I found that it did
not.
Costs
[56]
This case started as an urgent application with Part A being urgent
and Part B, or the present
application, being brought in the ordinary
course. The urgent application was never heard but the pleadings got
as far as the filing
of the founding and answering affidavits. WBHO
never filed its replying affidavit in time for the matter to be heard
on the urgent
roll. There is some dispute about why this happened.
But I see no reason to re-enter this dispute.
[57]
Then it is suggested that punitive costs are appropriate as a measure
of censure of the conduct
of Mr Carter who had initially denied
receiving the Appendix only to have his IT person point out his
error. It was suggested that
he had perjured himself. I am reluctant
to come to that conclusion. Mr Carter may have got it wrong, but I am
unable to come to
the conclusion that he was in bad faith. The tender
comprised voluminous documents and it is entirely reasonable that in
downloading
them all from the website a good faith error could have
occurred. Eskom should not be too quick to come to harsh
conclusions
about WBHO’s sloppiness - it also wasted much time
in this litigation by putting up the wrong version of Grinaker’s
Appendix that required further filings to explain.
[58]
Given the volume of paper that the tender and this litigation
entailed, it is not surprising
that both parties made mistakes.
Carelessness and lack of attention to detail does not, without more,
amount to bad faith.
[59]
The only relevance of delving into this history of the litigation is
whether the costs should
have been based on an attorney-client or
party and party scale. Given that the application is unsuccessful,
and I cannot conclude
that a punitive award is justified, Eskom can
have its costs for both the urgent application (Part A) and this one
(Part B) but
on a party and party scale.
ORDER:
-
[60]
In the result the following order is made:
1.
The application is dismissed.
2.
WBHO is liable for Eskom’s costs for both Part A and Part B of
the application, including the costs of
two counsel, on a party and
party scale.
_____________________________
N.
MANOIM
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION
JOHANNESBURG
Date
of hearing: 11 August 2023
Date
of judgment: 08 September 2023
Appearances:
Counsel
for the Applicants:
Adv C Acker
Adv MO Mudimeli
Instructed
by. Pagel
Schulenburg Inc
Counsel
for First Respondent: Adv
G.I Hulley SC
Adv V.J Heideman
Instructed
by:
Ledwaba Mazwai
[1]
Eskom
Holdings SOC Ltd (hereinafter "Eskom") invites you to
submit a lender for the complete supply 'and setting to
work of the
Combustion Waste Terrace. - Phase 2 ("the Works”) for the
Kusile Power Station at Emalahleni, Mpumalanga
In the Republic of
South Africa ("Kusile Power Station").
Case
Lines page 01-46 a document described as the invitation to tender.
[2]
Eskom
disputes this and says a letter was sent to WBHO informing it of the
outcome. It is not clear why WBHO never received this
or if it did,
why it was not read.
[3]
Letter
dated 30 June 2022, Caselines 01-40.
[4]
Wightman
t/a JW Construction v Headfour (Pty) Ltd and Another
2008 (3) SA 371 (SCA).
[5]
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984] ZASCA 51
;
1984 (3) SA 623
(A) at 634E - 635C.
[6]
Section
217(1) lists these.
[7]
In the document the following is stated under the heading “
TENDER
RETURNABLES, The tenderer must submit the returnables set out
hereunder as part of its lender. Returnables that are mandatory
for
evaluation will result in disqualification if not submitted at
tender closing.”
[8]
FIDIC is the French version of the acronym for the
Federation
Internationale des Ingenieurs-Conseils
.
In English this is translated as the
International
Federation of Consulting Engineers.
The
acronym is defined in the Eskom Procurement and Supply Chain
Management Procedure document.
[9]
2007 JOL 20439 (D).
[10]
(64288/2021) [2022] ZAGPPHC 865 (17 November 2022) paragraph 33.
[11]
AIIPay
Consolidated investments Holdings (Pty) Ltd and others v CEO, SASSA,
and others
2014
(1) SA 604
(CC) paragraph 92.
[12]
Even
the description as an ‘Appendix to the Tender” would
have made its status obvious. Why would one submit a tender
and
leave out an appendix to it?
[13]
WBHO
says that Eskom refers to the first edition of FIDIC in the tender
documents (1999) whilst the reference to the Appendix
is language
used in the second edition (2017).
[14]
“
If
the applicant knew Eskom added the Appendix to Tender to the tender
documentation it would have been a very simple exercise
to complete
the document and to include it in applicants bid submission.”
[15]
In
more technical terms it is described by Eskom in the relevant
document in this way:
“
The
change to a Class C liner resulted in the amount of HDPE liner
material required reducing by approximately 50% and the Liner
Leakage Detection Layer also being removed. The Leakage Detection
Layer consisted of Geocells and River Sand with associated
drainage
piping, the removal of these items also resulted in a significant
cost saving to the project."
[16]
Eskom denies in it papers that WBHO’s was the lowest bid, It
suggests that it was fifth ranked out of the bidders, although
it
does not put up any figures to substantiate this claim whilst WBHO
does.
sino noindex
make_database footer start
Similar Cases
B.W.H v S.A.H (22802/2021) [2023] ZAGPJHC 1348 (21 November 2023)
[2023] ZAGPJHC 1348High Court of South Africa (Gauteng Division, Johannesburg)99% similar
H.W and Another v R.S (18246/2019) [2023] ZAGPJHC 1354 (24 November 2023)
[2023] ZAGPJHC 1354High Court of South Africa (Gauteng Division, Johannesburg)99% similar
H.W. and Another v R.S. (18246/2019) [2025] ZAGPJHC 1125 (10 November 2025)
[2025] ZAGPJHC 1125High Court of South Africa (Gauteng Division, Johannesburg)99% similar
W.L v W.B.L (2022-015956) [2023] ZAGPJHC 1189 (15 September 2023)
[2023] ZAGPJHC 1189High Court of South Africa (Gauteng Division, Johannesburg)99% similar
M.W.W v S (A133/2024) [2025] ZAGPJHC 1082 (30 October 2025)
[2025] ZAGPJHC 1082High Court of South Africa (Gauteng Division, Johannesburg)99% similar