Case Law[2023] ZAGPJHC 1476South Africa
Gauteng Enterprise Propeller v Amahlo Consulting Services CC (22/13270) [2023] ZAGPJHC 1476 (28 December 2023)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 1476
|
Noteup
|
LawCite
sino index
## Gauteng Enterprise Propeller v Amahlo Consulting Services CC (22/13270) [2023] ZAGPJHC 1476 (28 December 2023)
Gauteng Enterprise Propeller v Amahlo Consulting Services CC (22/13270) [2023] ZAGPJHC 1476 (28 December 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_1476.html
sino date 28 December 2023
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG LOCAL
DIVISION, JOHANNESBURG
CASE
NO: 22/13270
In the matter between:
GAUTENG
ENTERPRISE PROPELLER
Applicant
and
AMAHLO
CONSULTING SERVICES
CC
Respondent
JUDGMENT
YACOOB
J
:
INTRODUCTION
1.
The applicant, Gauteng Enterprise Propeller
(“GEP”) is a provincial public entity. It provides
financial support
and development services to small, micro and medium
businesses and co-operatives, hence “propelling”
enterprise in
the province.
2.
GEP seeks the review and setting aside of
three of its own decisions, all of which it contends were made
unlawfully, and all of
which deal with the appointment of the
respondent, Amahlo Consulting Services CC (Amahlo), as project
co-ordinator in a job-creation
project to have lasted three years.
GEP also seeks an order that Amahlo pay back an amount of R59 762
578.46.
3.
The first decision is the decision to
appoint Amahlo, the second is the conclusion of a Memorandum of
Understanding (“MOU”)
and the third is the conclusion of
an addendum to the MOU. I detail the particulars of these decisions
later.
4.
Amahlo opposes the review and setting aside
of the decisions on the basis that GEP has delayed unreasonably in
bringing the application,
that GEP should not benefit from its own
delay and that Amahlo should be allowed to proceed and perform (and
benefit) from the
decisions. Amahlo’s only factual submission
relevant to lawfulness is that it was not involved in the decision
making. It
sets out circumstances which it contends support a
conclusion that GEP’s delay was unreasonable and therefore that
the decisions
should not be reviewed. It also sets out reasons why it
contends that the review of the decisions would not be just and
equitable.
These are also related to delay and alleged performance.
5.
The
review is premised on the principles of legality, in accordance with
the dictum of the Constitutional Court in
State
Information Technology Agency v Gijima Holdings
.
[1]
FACTUAL
BACKGROUND
6.
The facts giving rise to this application
are, in the main, common cause.
7.
GEP initiated a job creation project called
Project Vuthela in 2016. The purpose of the project was to create
about 75 000 job opportunities
in Gauteng, thereby reducing youth
unemployment. The value of the project was approximately R65
million.
8.
GEP
being listed in Schedule 3C of the Public Finance Management Act
(“the PFMA”),
[2]
it
had to follow prescribed procurement procedures when appointing
service providers. Amahlo’s sole member, Mr Tshauambea,
who is
the deponent to its answering affidavit, alleges that he was not
aware of this. He also alleges that he has provided services
for a
number of other government entities, so this allegation must be taken
with a pinch of salt.
9.
In March 2016, a resolution by GEP’s
Business Development Committee (“BDC”) appointed Amahlo
project coordinator
of the pilot project, and approved an initial
grant of R2 400 000. No tender process was followed. This is the
first decision that
is sought to be reviewed.
10.
On 30 March 2016 a memorandum of agreement
(“MOA”) was signed by Ms Leah Manenzhe, the then acting
Chief Executive Officer
of GEP, and Mr Tshauambea. Ms Manenze signed
the agreement without obtaining board approval, even though GEP’s
delegation
of authority document required board approval for
agreements worth R2 500 000 or more. This is the second impugned
decision.
11.
In terms of the MOA, Amahlo would create 75
000 job opportunities for which it would be paid R65 million. In
2016, Ms Manenzhe and
Mr Tshauambea signed an addendum to the MOA,
reducing the number of job opportunities to be created to only 5 000,
but keeping
the “financial implications” at R65 million.
The date on the header of the addendum is 05 December 2016, but the
date
handwritten at Ms Manenzhe’s signature is 26 May 2016.
There is no date at Mr Tshauambea’s signature, although he
alleges
that the date on which he signed was 26 May 2016. GEP alleges
that the addendum without board approval was unauthorized and that
reducing the number of jobs to be created so drastically while
retaining the amount “implicated” is irrational. This
is
the third impugned decision.
12.
On 28 March 2019, two days before the MOA
was due to expire, a memorandum was prepared requesting board
approval for a three month
extension of the MOA, on the basis that
tender processes had to be followed to appoint a new service
provider. The memorandum included
the information that about R60
million had been spent already on the project, and that the extension
would cost around R3.725 million.
The extension did not happen.
13.
In October 2019 GEP received a complaint
that some 366 students who claimed to be part of Project Vuthela, who
were being trained
at Ekurhuleni East College and who were entitled
to be paid stipends, were not being paid those stipends. The
complaint was first
directed to the Public Protector. Amahlo was
responsible for the payment of monthly stipends.
14.
The students were requesting that GEP pay
them directly because they were not being paid by Amahlo. This led to
a forensic investigation.
15.
The investigation revealed various
anomalies and irregularity, including payments being made without
compliance checks being made,
and occasional double invoices and
payments in a month. Amahlo also paid out far less to each student
than it apparently retained.
Amahlo did not cooperate with the
investigation.
16.
The forensic report was commissioned in
2020. Apparently there were some delays in getting the required
information because of the
interruption caused by the Covid-19 health
emergency. The report was received in January 2022. The application
was launched on
4 April 2022.
17.
Amahlo denies that the student who made the
complaint was part of Project Vuthela. However, it has not provided
lists of students
and what they have been paid. It does allege that
all funds received from GEP were used for the intended purpose,
although the
amounts it discloses do not come close to what it
received from GEP.
18.
Amahlo chooses not to provide a response to
the details of the forensic report, which sets out the basis on which
the amount now
claimed back by GEP, on the basis that it was
hearsay. Mr Tshauambea claims that he had not had an
opportunity to respond
to the report, although he does not deny the
allegation that he declined to co-operate with the investigation. He
annexes financial
statements to the answering affidavit, although not
for all the years it was appointed to the project. No invoices from
alleged
service providers are annexed, nor any details of how the
project was run and money spent. No list of students is attached.
19.
Mr Tshauambea alleges that Amahlo was
unable to perform in terms of the MOA and that is why the addendum is
signed. There is no
explanation of why, being unable to perform
already, two months into the contract period, Amahlo should have been
given such an
advantageous amendment to the terms, particularly that
the amount being paid by should remain the same.
20.
Mr Tshauambea alleges that “some”
students were enrolled for a 3 month cycle, being paid a R1 500 per
month stipend,
an undisclosed amount for transport and food, and
training fees of R4 500 per month. He does not disclose the invoices
for these
payments, particularly the training fees. An examination of
the financial statement for the year ending February 2018 shows that
on the income statement, income from “sales” for 2018 is
listed as almost R25 million, while “cost of sales”
is
over R5 million. Gross profit is listed as over R19 million. For the
year ending February 2017, listed on the income statement
as a
comparator, “sales” is over R48 million, while “cost
of sales” is just over R23 million. Gross profit
is listed as
over R25 million. The biggest expenditure in each of those years is
“salaries and wages”. However the
names of employees and
what they were paid is not disclosed.
21.
The financial statements for 2018 and 2019
show similar patterns.
Prima facie
Amahlo has retained far more than it
has expended, even taking into account that it may have received
money from more sources than
GEP. It certainly does not show that it
has expended the amounts it ought to have done in pursuance of
Project Vuthela, had it
properly carried it out.
22.
The only “evidence” of students
who were trained is contained in two verification reports from GEP
confirming that in
April and June 2018 142 students had signed
attendance registers.
23.
Amahlo was also not able to produce a
number of documents requested by GEP in a Rule 35(12) notice. These
include GEP’s advertisement
of Project Vuthela, which Amahlo
alleges it responded to after finding it on GEP’s website and
which GEP denies having published
on its website; contracts with one
of the two service providers to whom large amounts were allegedly
paid, A and D Catering, and
proof of payment of those amounts;
contracts entered with any learning institutions attended by
participants, and lists of students,
courses and institutions which
were part of the Project.
24.
Amahlo has disclosed that it invoiced and
was paid for duplicate amounts within a month, which is consistent
with the findings of
the report. Dates of invoicing and payment also
show that verification procedures were usually not carried out before
Amahlo was
paid.
THE ISSUES
25.
Amahlo does not contest the unlawfulness of
the decisions, nor does it contest the factual basis on which the
unlawfulness is premised.
It is clear on the papers that the
decisions were unlawful. Amahlo contends that the decisions should
not be reviewed and set aside
because GEP delayed unreasonably in
bringing the review application.
26.
Amahlo’s main contention is that
because GEP allowed Amahlo to perform in terms of the agreement, GEP
should not “benefit”
by setting aside the agreement.
Amahlo wishes to have its rights preserved and contends that an order
that it pay back any money
would be unfair. The argument appears to
be that because the application was only brought after performance
had taken place, it
was unreasonably delayed and should be dismissed.
27.
I must therefore decide, firstly, whether
the delay was unreasonable, and secondly, if I do declare the
decisions unlawful, what
relief would be just and equitable. In
considering relief, I must also consider whether GEP has established
its entitlement to
the repayment of the amount it claims.
DELAY
28.
GEP requested the forensic report in August
2020. It was unable to institute proceedings against Amahlo until the
report was complete.
That would have been premature.
29.
It appears that there was some delay
between the receipt of the complaints in October 2019 and the request
for the investigation,
which was ten months later. GEP does not
explain why it waited so long, and in fact denies that the delay was
undue. It was submitted
by counsel that part of the problem was the
confusion caused by the State of Emergency declared in March 2020 in
response to the
Covid-19 pandemic, which caused inconvenience and a
need to find new ways to work.
30.
The forensic report appears to have taken
some 16 months to produce. There is no detailed explanation of
why it took that
length of time.
31.
Amahlo claims in its response to GEP’s
rule 35(12) notice that it is unable to produce supporting documents
because of effluxion
of time. Of course this claim cannot apply to
the period when the forensic report was being produced. It is also
doubtful at the
time when the answering affidavit was being produced.
Documents dating back to 2016 ought to have been available, as the
Income
Tax Act 58 of 1962 requires such documents to be retained for
five years after a return is submitted.
32.
Amahlo contends that the effective date
from which to evaluate whether there was an unreasonable delay is the
date on which the
decisions are taken. It therefore contends that the
application is six years too late and therefore that the delay is
unreasonable.
33.
This is clearly not the case. The effective
date is the date on which GEP became aware that the decision may be
problematic. This
is at the earliest October 2019.
34.
GEP contended that the effective date is
the date on which the report was produced. My view is that it must
have been earlier, at
some point between the receipt of the complaint
and the decision to commission the report. For purposes of this
judgment it is
not necessary to decide the exact date.
35.
Both
parties rely on the decision of the Constitutional Court in
Buffalo
City Metropolitan Municipality v ASLA Construction (Pty) Limited
[3]
(“
Buffalo
City
”)
in support of their argument regarding delay.
36.
The
test set out in
Buffalo
City
is a two-stage enquiry, in which a court first determines whether the
delay was undue and secondly whether the court should nevertheless
entertain the application.
[4]
37.
An
applicant must provide an explanation for the whole of the delay.
[5]
A court may exercise its discretion to overlook even an unreasonable
delay, and in doing this must consider factors including prejudice
to
the parties, the consequences of setting the decision aside, the
merits of the challenge and the extent of the alleged illegality.
The
approach is flexible and requires an evaluation of all relevant
factors.
[6]
38.
The
Constitutional Court in
Buffalo
City
also
intimates that clear unlawfulness of the decision may well be an
overriding factor.
[7]
The
objectives of the delay rule are to be balanced with the purpose of
declaring unlawful conduct unlawful.
[8]
39.
The purpose of the delay rule is to provide
certainty. It also includes an element of fairness to those affected
by the impugned
decision. The purpose of declaring unlawful conduct
unlawful is to uphold the rule of law and ensure that public power is
exercised
lawfully. Procedural defects should not, without more,
permit unlawful conduct by public decision makers remain intact.
40.
As
Skweyiya J stated in
Khumalo
and Another v MEC for Education, KwaZulu-Natal
,
[9]
In the previous section
it was explained that the rule of law is a founding value of the
Constitution, and that the state functionaries
are enjoined to uphold
and protect it, inter alia, by seeking the redress of their
departments’ unlawful decisions. Because
of these fundamental
commitments, a court should be slow to allow procedural obstacles to
prevent it from looking into a challenge
to the lawfulness of an
exercise of public power.
41.
In addition, functionaries who act
unlawfully, and service providers who benefit from unlawful actions,
should not be rewarded with
impunity simply by the fact that the
unlawfulness has not been detected for a period of time.
42.
In this case, GEP has not provided a full
explanation of the entire period between receiving a complaint in
October 2019 and instituting
proceedings in April 2022.
However, although GEP did not act as if the issue was urgent, it is
clear that it did not sit
on its hands and do nothing. I am
satisfied that the delay was not unreasonable.
43.
Even if I had found that the delay was
unreasonable, I consider that the patent unlawfulness of the
decisions requires me to condone
the delay and to deal with the
merits of the review.
JUST AND EQUITABLE
RELIEF
44.
I
have already found that GEP has demonstrated that the decisions are
unlawful and therefore unconstitutional. In terms of section
172(1)(a) of the Constitution
[10]
I must therefore declare them invalid. The question then is what
consequential relief is just and equitable.
45.
GEP contends that it is just and equitable
to order the repayment of R59 762 578.46, which is the amount,
according to the forensic
report, that Amahlo was paid.
Alternatively, it submits that the surplus paid to Amahlo on its
calculations based on Amahlo paying
142 students per month a stipend
of R1 500 per month, is R52 343 964, which should be recovered.
46.
Amahlo
simply contends that there is no surplus and that it has performed,
without being able to substantiate these allegations.
If Amahlo is an
innocent party, it still may not benefit from the unlawful
contract.
[11]
The default
position on a finding that a decision is invalid is that the
consequences must be corrected.
[12]
47.
In this case the correction of the
consequences of the invalid contract would require that GEP would be
refunded the money it has
unlawfully paid in terms of the contract.
Amahlo has not shown any reason why that relief should not be
granted. It has not taken
the court into its confidence at all about
what its profits from the project were, what it actually expended and
to whom. It simply
submits that ordering repayment would not be just
and equitable. Without any factual support for that submission, I am
unable to
agree.
48.
I see no reason then to make any order
other than that Amahlo must repay the money it received, less the
stipends paid. The calculation
in Amahlo’s favour is that this
was paid every month to 142 students, and that is the basis on which
the amount to be repaid
will be determined.
CONCLUSION
49.
There was no submission that any unusual
costs order is called for. I therefore find that costs must follow
the results.
50.
I make the following order:
1.
The following decisions are declared
unlawful and invalid, and are set aside:
1.1.
GEP’s decision to appoint Amahlo as
co-ordinator of Project Vuthela and approve an initial grant of
R2,400,000;
1.2.
the conclusion of the Memorandum of
Agreement, and the resultant appointment of Amahlo as the
co-ordinator of Project Vuthela, and
1.3.
the decision to change Amahlo’s scope
of obligations through the conclusion of an addendum to the
Memorandum of Agreement
by reducing the number of job opportunities
that Amahlo had to deliver.
2.
Amahlo is ordered to pay back to GEP the
amount of
R52 343 964.
3.
Amahlo shall pay the costs of this
application, including two counsel where so employed.
____________________________
S. YACOOB
JUDGE OF THE HIGH
COURT
GAUTENG LOCAL
DIVISION, JOHANNESBURG
Appearances
Counsel for the
appellant:
L Haskins
Instructed by:
Edward Nathan Sonnenbergs
For the
respondent:
J W Kloek
Instructed
by:
Scalco Attorneys Incorporated
Date of
hearing:
02 October 2023
Date
of judgment:
28 December 2023
[1]
2018
(2) SA 23 (CC)
[2]
Act
1 of 1999
[3]
2019
(4) SA 331 (CC)
[4]
At
[48]
[5]
At
[52]
[6]
At
[54]
[7]
At
[66]
[8]
At
[68]
[9]
2014
(5) SA 579
(CC) at [45]
[10]
Constitution
of the Republic of South Africa, 1996
[11]
Central
Energy Fund SOC Ltd and Another v Venus Rays
Trade
(Pty) Ltd and Others
2022 (5) SA 56
(SCA) at [42]
[12]
Allpay
Consolidated Investment Holdings (Pty) Ltd and Others v Chief
Executive Officer of the South African Social Security Agency
and
Others
2014
(4) SA 179
at [30]
sino noindex
make_database footer start
Similar Cases
Gauteng Provincial Government : Department of Human Settlements and Others v Busha and Others (9074/2020) [2024] ZAGPJHC 138 (19 February 2024)
[2024] ZAGPJHC 138High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Gauteng Refinery (PTY) Ltd v Eloff (A3005/2021) [2022] ZAGPJHC 739; 2023 (2) SA 223 (GJ) (2 September 2022)
[2022] ZAGPJHC 739High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Gauteng Provincial Government: Department of Human Settlements and Another v Motasi and Others (2021/42636) [2022] ZAGPJHC 663 (8 September 2022)
[2022] ZAGPJHC 663High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Gauteng Housing Secondary Co Operative Ltd v Eastsleigh Court Housing Co Operative and Others (2021/22783) [2022] ZAGPJHC 318 (3 May 2022)
[2022] ZAGPJHC 318High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Gauteng Provincial Government: Department of Human Settlements and Others v Pogatsi and Others (2020/19559) [2022] ZAGPJHC 762 (7 October 2022)
[2022] ZAGPJHC 762High Court of South Africa (Gauteng Division, Johannesburg)100% similar