Case Law[2022] ZAGPJHC 225South Africa
Abb South Africa (Pty) Ltd and Another v Leago EPC (Pty) Ltd (22278/2019) [2022] ZAGPJHC 225 (13 April 2022)
High Court of South Africa (Gauteng Division, Johannesburg)
13 April 2022
Headnotes
APPLICATION TO DETERMINE WHETHER THE PARTICULARS OF CLAIM IN THE MAIN ACTION INSTITUTED BY PLAINTIFF ARE EXCEPIABLE
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2022
>>
[2022] ZAGPJHC 225
|
Noteup
|
LawCite
sino index
## Abb South Africa (Pty) Ltd and Another v Leago EPC (Pty) Ltd (22278/2019) [2022] ZAGPJHC 225 (13 April 2022)
Abb South Africa (Pty) Ltd and Another v Leago EPC (Pty) Ltd (22278/2019) [2022] ZAGPJHC 225 (13 April 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2022_225.html
sino date 13 April 2022
HIGH COURT OF SOUTH
AFRICA
(GAUTENG DIVISION,
JOHANNESBURG)
Case no: 22278/2019
REPORTABLE: No
OF INTEREST TO OTHER
JUDGES: No
REVISED.
13 April 2022
In the matter between:
ABB
SOUTH AFRICA (PTY)
LTD
First Excipient
ESKOM HOLDINGS SOC
LIMITED
Second Excipient
And
LEAGO EPC (PTY)
LTD
Respondent
Case
Summary
: APPLICATION TO
DETERMINE WHETHER THE PARTICULARS OF CLAIM IN THE MAIN ACTION
INSTITUTED BY PLAINTIFF ARE EXCEPIABLE
JUDGMENT
SENYATSI J
A.
INTRODUCTION
[1]
The first and second excipients are the first and second defendants
in the main action.
They have been sued by the respondent who is the
plaintiff in the main action. For convenience sake the parties will
be referred
to as in the main action. This is an application to
determine whether the particulars of claim in the main action
instituted by
Plaintiff are excepiable.
[2]
Both First and Second Defendants have raised exception to the
particulars of claim.
B.
BACKGROUND
[3]
Plaintiff sued Defendants for declaratory order on the validity of a
written contract
concluded between First and Second Defendant as well
as money judgment against First Defendant.
[4]
In its particulars of claim as against First Defendant, Plaintiff
avers that First
Defendant submitted a bid to Eskom, Second Defendant
and that the bid includes Plaintiff’s contractual involvement.
[5]
Plaintiff alleges that, Second Defendant accepted First Defendant’s
bid and
states that it (Plaintiff) is not in possession of the bid
documents.
[6]
Plaintiff avers that pursuant to submitting the bid, Second and First
Defendants concluded
a written contract during 2015 in Johannesburg
and restates some of the contractual terms. Plaintiff furthermore
avers that it
is the entity referred to between First and Second
Defendants.
[7]
Furthermore, so avers Plaintiff, pursuant the said written contract
between First
and Second Defendants, it concluded a written contract
with First Defendant for the purchase site services.
[8]
First Defendant placed certain orders with Plaintiff in accordance
with the subcontract
concluded between them. It ordered and was
invoiced for services amounting to R8 454 705.70. It was
partly paid R4 028 440
by the First Defendant leaving a
balance of R4 426 259.70 which is what is claimed in the
particulars of claims.
[9]
After First and Second Defendant gave notice to defend the claim they
both gave separately
Notice of Exception.
C.
EXCEPTIONS
First Defendant’s
Exception
First Exception
[10]
(a)
Plaintiff contends
that this court has jurisdiction on the ground that the “
Defendants
principal place of business is situated within the area of
jurisdiction of this Honourable Court” (paragraph 5).
(b)
In
pleading in this manner, so argues First Defendant, Plaintiff appears
to allege that both First and Second Defendants have principal
places
of business within the area of jurisdiction of this Court.
(c)
However the argument from First
Defendant continues, Plaintiff has not pleaded Frist Defendant’s
principal place of business.
(d)
In the light of the aforesaid, the
basis of this Court’s jurisdiction does not appear form the
pleading.
Second Exception
[11]
Plaintiff has not pleaded any basis upon which it is entitled to seek
declaratory relief regarding
a contract to which it is not a party
that is, the contract between First and Second Defendants.
[12]
Plaintiff has furthermore not pleaded any allegations to establish
that;
(a)
there is any dispute between Defendants
regarding the validity of the contract which is said to subsist as
between them or
(b)
the basis on which that dispute is to
be resolved, or
(c)
the grounds on which the court is to exercise its jurisdiction for
purposes of resolving
that dispute or granting the declaratory relief
sought by Plaintiff
.
[13]
Plaintiff, so continues the argument by First Defendant, not having
pleaded a basis for seeking
declaratory relief in respect of the
contract between Defendants, has miss-joined Second Defendant to the
proceedings.
[14]
Plaintiff has not disclosed a valid cause of action for the
declaratory relief sought by it in
first instance.
Third Exception
[15]
Plaintiff has failed to attach the written agreement between
Defendants relief upon in paragraph
10. The attachment of extracts of
the alleged agreement is insufficient:
(a)
First Defendant is unable to ascertain
how the paginated extract which runs from page 1-7 relates to the
pages which occur thereafter;
(b)
The location and status of the extracts within the agreement is not
particularized; and;
(c)
The extracts rely on definitions and cross-references which are not
apparent from
the extracts themselves;
[16]
Plaintiff, so continues the argument from First Defendant, has
accordingly not complied with
the requirements of the Uniform Rules
of court and has not adduced sufficient particularity to enable First
Defendant to understand
the cause of action it is required to meet.
Fourth Exception
[17]
Plaintiff alleges in paragraph 18 that it complied with all its
obligations in terms of the said
contracts with First Defendant “and
the attached documentation.”
[18]
The reference to “attached documentation” is not
understood, the annexes to the particulars
of claim including, as it
does, documents which do not appear to impose obligations on the
Plaintiff.
[19]
First Defendant argues in its fourth exception that Plaintiff does
not identify which of its
obligations it complied with or what
precise obligations it fulfilled which entitle it to payment from
First Defendant.
[20]
Plaintiff furthermore does not plead compliance with the payment
terms set out in paragraph 16.4
of the particulars of claim.
[21]
Plaintiff has not disclosed a valid cause of action for payment of
the amount claimed by it.
Fifth Exception
[22]
First Defendant furthermore submits that Plaintiff alleges in
paragraph 19 that First Defendant
failed and / or refused and / or
neglected to make payment to Plaintiff and in paragraph 20 that First
Defendant made payment to
Plaintiff’s employees for the benefit
of the plaintiff.
[23]
The two allegations set out in para [22] above are mutually
inconsistent and are not understood
and that in any event do not
disclose a cause of action for the relief claimed.
Sixth Exception
[24]
Plaintiff seeks an order declaring that the contract between itself
and First Defendant is valid
and binding.
[25]
Save for disputing First Defendant’s assertion that the
contract is unenforceable, Plaintiff
does not plead any allegation in
support of the declaratory relief it seeks.
[26]
Plaintiff fails to make out a case that the relevant contract is
valid and binding, as contended
for by it.
[27]
First Defendant prays that its exceptions be upheld and that
Plaintiff be afforded fifteen days
from the date of the order within
which to amend its particulars of claim and be struck out in the
event of the Plaintiff failing
to amend the particulars of claim
within the time afforded and costs.
Second Defendant’s
Exceptions
First Exception
[28]
Second Defendant contends that Plaintiff fails to adduce with
sufficient particularity the basis
that Second Defendant is a party
to the proceedings:
(a)
Plaintiff cites Second Defendant as a
party to the proceedings in paragraph 3 of the particulars of claim;
(b)
Plaintiff makes reference to the “Employers Requirements”
in paragraph 4 of
the particulars of claim;
(c)
Plaintiff makes further reference to “Annexure B” which
is “Explanation
of the Contractor’s Local Content and
Related Obligations” in paragraph 7 claiming that it was saved
from Eskom.
[29]
Plaintiff specifically fails to plead the legal and / or contractual
relationship with respect
to Second Defendant, if any. Second
Defendant was not a contracting party to the subcontract.
[30]
Plaintiff further fails to plead that the material facts upon which
it has a right or is party
to “Annexure C” (the contract
between First and Second Defendant). Accordingly, paragraphs 27 and
28 of the Plaintiff’s
particulars of claim remain vague and
embarrassing.
[31]
In paragraph 9 of the particulars of claim the Plaintiff claims that
First Defendant’s
bid which included Plaintiff’s
contractual involvement with First Defendant was accepted by Second
Defendant. Plaintiff does
so without pleading the basis for such
averment.
[32]
Second Defendant contends that Plaintiff has, accordingly, failed to
plead its cause of action
against Second Defendant.
Second Exception
[33]
Second Defendant contends that in paragraph 22 of the particulars of
claim, Plaintiff pleads
that the contract was cancelled by First
Defendant but fails to plead Second Defendant’s involvement in
the termination of
such contract. The contract Annexures “D”
and “E” was entered into between Plaintiff and First
Defendant.
The contract was cancelled by First Defendant and set out
in Annexure “P” to the particulars of claim.
[34]
Consequently, Second Defendant is unable to understand the basis of
Plaintiff’s claim against
it.
Third Exception
[35]
Plaintiff states in paragraph 19 of the particulars of claim that
First Defendant failed to effect
full payment in terms of the
contract but fails to plead the role of second Defendant in the non
–fulfillment of the alleged
payment obligation.
[36]
Plaintiff pleads in paragraph 23 of the particulars of claim that a
request was made to mediate
the dispute between the parties but fails
to plead that Second Defendant was made aware of such request to
mediate and / or Second
Defendant’s attitude and / or
involvement in this regards. Second Defendant contends that pleadings
remain vague and embarrassing.
Fourth Exception
[37]
Plaintiff seeks declaratory relief against Second Defendant together
with First Defendant for:
”
1
An order declaring the contract attached as Annexure “G”
as read with paragraph 4.5 of “8” valid”.
[38]
Second Defendant contends that Plaintiff seeks declaratory relief
without pleading the basis
upon which it is entitled to do so.
[39]
Second Defendant contends that it remains embarrassed as it is unable
to understand the cause
of action it is required to meet.
[40]
Second Defendant prays that its exceptions be upheld with costs.
Plaintiff’s
intentions
[41]
In opposing the exceptions, Plaintiff contends that it has pleaded
sufficient averments to satisfy
the requirements of section 21 of
Superior Courts Act 10 of 2013 (“the Act”) which empowers
a court to give the declaratory
relief sought by the respondent.
[42]
Section 21 of the Act reads as follows:
“
21
Persons over whom and matters in relation to which divisions have
jurisdiction.
(1)
A Division has jurisdiction over all
persons residing or being in, and in relation to all causes arising
and all offences liable
within its area of jurisdiction and all other
matters of which it may according to law take cognizance, and has the
power
(c)
in its discretion, and at the instance of any interested person to
enquire into and determine any existing,
future or contingent right
or obligation, notwithstanding that such person cannot claim any
relief consequential upon the determination.”
[43]
Plaintiff contends that there is nothing vague and embarrassing about
its particulars of claim
as regards the exceptions raised.
[44]
Plaintiff contends that it has an interest in both contracts between
itself and First Defendant
and between Frist Defendant and Second
Defendant. It contends that if there is illegality within contract
between itself and First
Defendant, then that illegality originated
from contract between First and Second Defendant. On that basis, so
contends Plaintiff
it is entitled to seek declaratory order on the
validity of the contact between First and Second Defendants.
[45]
Plaintiff contends that it was entitled to join Second Defendant as
it only seeks the declaratory
order in the validity of the contract
between First and Second Defendant.
Issues for
determination
[46]
The issue for determination is whether the particulars of claim as
amended are excipiable as
being vague and embarrassing and on the
grounds that the particulars fail to disclose a cause of action.
Legal principles
[47]
The principles governing the exceptions to particulars of claim are
regulated at common law as
well in terms of the Uniform Rules of
Court.
[48]
A party is embarrassed if the pleading lacks particularity which is
strictly necessary to enable
a defendant to plead such that the
defendant does not know what case it will have to meet at trial.
[1]
[49]
A pleading is vague if it lacks particularity to the extent that it
is either meaningless or
capable of more than one meaning.
[2]
[50]
The defendant must show that it would be prejudiced if it were
required to plead to the combined
summons in its current form.
[3]
[51]
To succeed in a “no cause of action” exception the
defendant must demonstrate that
on every reasonable interpretation of
the pleading and ensuring all the pleaded allegations to be true, no
cause of action is made
but upon which judgment could be granted.
[4]
[52]
It is also a fundamental principle that when considering whether an
exception should be upheld
the pleadings are considered as a whole
and one does not read paragraphs in isolation.
[5]
[53]
In
Telematrix
(Pty) Ltd t/a Matrix Vehicle Tracking v Advertising Standards
Authority South Africa
[6]
in dealing with the approach where pleadings have been excepted, the
Supreme Court of Appeal held as follows:
“
[3]
Exceptions should be dealt with sensibly. They provide a useful
mechanism to weed out cases
without legal merit. An over- technical
approach destroys their utility. To borrow the imaginary employed by
Miller J, the response
to an exception should be like a sword that
‘cuts through the tissue of which exception is compounded and
exposes its vulnerability.’
[7]
Dealing with an interpretation issue, the added: ‘Nor do I
think that there were notional possibility that evidence of
surrounding
circumstances may influence the issue should necessarily
operate to debar the Court from deciding such issue on exception.
There
must I think, be something more than a notional or remote
possibility.’ Usually that something more can be gathered from
the pleadings and facts alleged or admitted therein. There may be
specific allegations in the pleadings showing the relevance of
extraneous fails, or there may be allegations from which it may be
inferred that further facts affecting interpretation may reasonably
possibly exist. A measure of conjecture is undoubtedly both
permissible and proper, but the shield should not be allowed to
protect
the respondent where it is composed entirely of conjectural
and speculative hypotheses, lacking any real foundation in pleadings
or in the obvious facts.
[8]
[54]
Another important principle on exception that a pleading is vague and
embarrassing may only be
taken when the vagueness and embarrassment
strikes at the root cause of the action.
[9]
[55]
In considering the pleadings as a whole and in context, it then
becomes necessary to determine
if
the
primary / material facts which are necessary for Plaintiff to prove,
have been set out. In so doing, one must be mindful that
it does not
comprise of every piece of evidence which is necessary to prove each
fact.
[10]
[56]
In
McKelvey
v Cowan N.O
.
[11]
the court held as follows:
“
It
is a first principle in dealing with matters of exception that if
evidence can be led which can disclose a cause of action alleged
in
the pleadings, that particular pleadings is not excipiable. A
pleading is only excipiable on the basis that no possible evidence
led on the pleading can disclose a cause of exception.”
[57]
In
National
Director of Public Prosecutions v Phillip and others
[12]
the court held that:
“
Pleadings
must be lucid, logic and intelligible. A litigant must plead his
cause of action or defence that has clarity and the precision
as is
reasonably necessary to alter his opponent to the case he has to
meet.”
[58]
Rule 22(2) of the Uniform Rules of Court stated that:
“
The
Defendant shall in his plea either admit or deny or confess and avoid
all the material facts alleged in the combined summons
or declaration
or state which of the said facts are not admitted and to what extent
and shall clearly and concisely state all material
facts upon which
he relies.”
[59]
Rule 23(1) of the Uniform Rules of Court states that:
“
Where
any pleading is vague and embarrassing… the opposing party
may, within the period allowed for filing any subsequent
pleading,
deliver an exception thereto… Provided that where a party
intends to take an exception that a pleading is vague
and
embarrassing, he shall within the period allowed as aforesaid by
notice afford his opponent an opportunity of remaining the
cause of
complaint within 5 days…”
[60]
It is trite that the purpose of an exception is to dispose of the
case in whole or in part. In
considering an exception, a court
commences from the premise that the allegations contained in the
particulars of claim are correct,
and then considers the pleadings as
a whole. It is required of the Defendant to show that the pleading is
excepiable on every possible
interpretation that can reasonably be
attached to it.
[13]
[61]
In dealing with the principles of exception, Erasmus
[14]
states as follows:
“
(a)
In each case the court is
obliged first of all to consider whether the pleading does lack
particularity to an extent amount to vagueness.
Where a statement is
vague it is either meaningless or capable of more than one meaning.
To put it at its simplest; the reader
must be unable to distill from
the statement a clear single meaning.
(b)
If there is vagueness in this sense the court is then obliged to
undertake a quantitative
analysis of such embarrassment as the
excipient can show is cause to him or her by the vagueness complained
of Exception the validity
of an agreement relied upon or whether a
purported contract may be void for vagueness
.”
[62]
An exception that a pleading is vague and embarrassing, strikes at
the formulation of the cause
of action, and not its legal
validity.
[15]
In dealing with
exceptions that pleadings are vague and embarrassing, courts have
held that such exception can only be taken when
the vagueness and
embarrassment strikes at the cause of the action as pleaded. If the
Defendant cannot show serious prejudice,
then an exception will not
be upheld.
[16]
[63]
An exception that a pleading is vague and embarrassing should not be
directed at a certain paragraph
of the pleading but at the cause of
action as whole, which must be demonstrated to be vague and
embarrassing.
[17]
[64]
It is also a principle of our law that in pleadings, a distinction
must be drawn between the
facta
probantia,
which
are the secondary allegations on which the Plaintiff will rely in
support of his / her primary factual allegations generally
speaking,
the latter are matters for particulars for trial and even then are
limited.
[18]
Reasons for the
judgment
[65]
In the instant case First Defendant excepts to Plaintiff’s
failure to aver the principal
place of business in the initial
particulars of claim. This omission has, however, been cured by the
amended particulars of claim
consequently, the exception on this
point cannot be sustained and must fail.
[66]
With regards to the second exception by First Defendant which is that
the Plaintiff has failed
to plead any basis in the law upon which
Plaintiff is entitled to seek declaratory relief on the contract if
(Plaintiff) is not
a party to which is between First and Second
Defendant, there is merit to this exception.
[67]
I say so because on perusal of the amended particulars of claim and
the annexures attached thereto,
there is no averment that there is a
dispute between First and Second Defendant or the validity of their
contract to which Plaintiff
is not a party to. This is in my
considered view, an omission which opens the particulars of claim to
attack on the ground of being
excepiable. It follows therefore that
no valid cause of action has been established.
[68]
The third exception by First Defendant is that pages 1-7 attached to
the amended particulars
of claim are not ascertainable and do not
make sufficient averment to enable First Defendant to understand the
cause of action.
[69]
Paragraphs 4, 5, 6, 7 and 8 of the amended particulars of claim
states as follows:
“
4.
During or about March 2015 Eskom formulated “Employer’s
Requirements Specific
to the Works” Section 3.4 Scope Kusile
and a Request for proposals under PS (M) 2014 / AB / 02 (‘RFP’).
5.
The above honourable court has jurisdiction to adjudicate this matter
on the
ground that the Defendants principal place of business is
situated within the area of jurisdiction of this Honourable Court.
6.
The first page of the relevant section is attached hereto as “A”
for identification purposes only, as the technical requirements of
Section 3.4 are not relied upon for the plaintiff’s cause
of
action.
7.
At the same time Eskom formulated an “Explanation of
Contractor’s
Local Content and Related Obligations”
document in respect of the Medupi and Kusile power stations, a true
copy which is
attached hereto Annexure “B”.
8.
The relevant express term of Annexure “B” is as follows:
8.1
“
4.5 Evaluation of Industrialization
As set out in
paragraph 2.1 above, Industrialization does not form part of the
evaluation used at tender evaluation stage to measure
a tenderer’s
local content compliance and therefore has no impact on the overall
evaluation scoring and competitive ranking
of tenderers. However,
tenderers who would have an NIPP obligation are obliged to
demonstrate their proposed commitments in respect
of
Industrialization and Eskom reserves the right to negotiate with
tenderers regarding their Industrialization commitments will
serve as
a pre-condition to contract award, which Eskom may waive at its sole
discretion. Once, included as a contractual obligation
industrialization targets will be nominated as stipulated in section
2.2.9 [Contractor’s Local Contend and Related Obligation
Schedule]”
9.
ABB submitted a bid in respect of the RFP, which included Leago’s
proposed
contractual involvement with ABB and which was accepted by
Eskom. These documents are not in Leago’s possession.
10.
Pursuant to submitting the bid, Eskom and ABB both represented by
duly authorized employees,
concluded a written contract during 2015
in Johannesburg, the part relied upon which is attached hereto as
Annexure “C.
11.
The relevant express positions of Annexure “C” are:
11.1
“1.1.10
Industrialization
means the utilization of Eskom suppliers’
procurement spend to faster the establishment of new or the expansion
of existing
manufacturing capacity and capability to create
competitive industries as elaborated on in clause 4 of the
Explanatory of local
Content and related Obligations and which is in
fulfillment of the requirements of the Competitive Supplier
Development Programme
of the Department of Public Works which itself
substitutes for the National Industrial Participation Programme of
the Department
of trade and industry.
11.2
“2.
Contractor’s
Undertaking
2.1
The Contractor’s Legal Content and Related Commitments pursuant
to the Tender are
reflected in Appendices A, B, C, D and E to this
Schedule.
11.3
“9
Mid-term
Review and Final Review
9.1
Local Content Related Obligations Mid-term Review
9.1.1 The Employer
shall conduct a mid-term review of the Contractor’s Local
Content and Related Obligations at the stated
time (and if not stated
then at a time determined by the Engineer to be approximately midway
through the period of execution of
the works).”
11.4.
“9.1.2. The purpose of the Mid- term is to enable the Employer
to review the extent to which the Contractors
has fulfilled the
Contractor’s Local Content and Related Obligations as required
by the time of the Mid – Term Review
as well as whether the
Contractor is making sufficient progress in fulfilling the
Contractor’s Local content and related
obligations by the Local
Content and Related Obligations time for fulfillment.”
11.5
“9.2
Local Content and Related
Obligations Final Review
9.2.1 The
purpose of the Local Content and Related Obligations Final Review is
for the Employer to determine whether
the Contractor has fulfilled
the Contract.”
ABB approached Leago
Engineering to an Industrialization and Enterprise Development
Partner that will be subcontracted in order
to provide certain
services in the Medupi and Kusile C & I Works. The Enterprise
Development Partnership enables both parties
to achieve the
requirements for Industrialization and the Competitive Supplier
Development Programme (CSDP).
ABB will establish a
long term partnership with Leago which will mutual be a benefit and
ensure a value add to both. Building an
industrial capability that
will enhance local supply of C&I skills and experts. The end
result of which, would be that the
identified SMMI will become (sic)
a sustainable supply of C&I service directly to Eskom of core
engineering such as
·
Project management
·
Engineering consulting and
·
Operational capabilities and management.
ABB approached Leago
Engineering to an Industrialization and Enterprise Development
Partner that will be subcontracted in order
to provide certain
services in the Medupi and Kusile C&I Works. The Enterprise
Development Partnership enables both parties
to achieve the
requirements for Industrialization and the competitive Supplier
Development Programme (CSDP).
ABB will establish a
long term partnership with Leago which will mutual be a benefit and
ensure a value add to both parties Building
and industrial capability
that will enhance local supply of C&I skills and expertise. The
end result of which, would be that
the identified SMME will become
(sic) a sustainable supplier of C&I service directly to Eskom and
the South African market.
The Enterprise
Development partnership between ABB and Leago on the C&I project
will provide an integrated solution to Eskom.
ABB will be positioned
to comply and meet same (sic) the essential transformations
requirements. Leago Engineering will benefit
exposure and skill
enhancement in the C&I field.
The strategic
rationale of the Leago proposal and the proposed scope of the service
will yield three benefits:
·
Providing Eskom with integrated
solutions that achieves the objectives for transformation;
·
Building an industrial capability that
will enhance local supply of C&I skills and expertise. The end
result of which would
be that Leago becomes a future sustainable
supplier of C&I services
·
ABB would have achieved the
industrialization action, skills, transfer and enterprise development
objectives.”
13.
The plaintiff is the entity referred to as “Leago Engineering”
in Appendix C.
14.
Pursuant to the conclusion of Annexure “C” between Eskom
and ABB and in compliance
thereof, and on or about 13 May 2015, ABB
and Leago, both represented by authorized employees, concludes a
written “Subcontractor
for purchase of site services”
contract at Johannesburg, a true copy of which is attached hereto
as Annexure “D”, as well as an “ABB General Terms
and Conditions for purchase of site services” contract, a true
copy of which is attached hereto as Annexure “E”
(“the
contract”)
15.
The written contracts “D” and “E” referred to
ABB as “ABB
Contractor” and to Leago as the
“Subcontractor”.
[70]
Plaintiff goes on to relate the relevant terms of Annexure “D”
which I will not repeat
in this judgment. Plaintiff, however fails to
aver what relevance, other that there is a reference to “Leago
Engineering”
in the contract between First and Second
Defendant. It follows that Plaintiff has failed to make an averment
on what factual and
legal basis the contract between it and First
Defendant has anything to do with the agreement between First and
Second Defendant
to sustain the declaratory relief sought.
Consequently, the exception on this ground is upheld.
[71]
With regards to the exceptions raised by Second Defendant as regards
lack of basis for siting
Second Defendant in the dispute between
Plaintiff and First Defendant, Second Defendant contends that no
basis has been averred
by Plaintiff on the role Second Defendant is
alleged to have played in the alleged cancellation of the agreement
between Plaintiff
and First Defendant due to the latter’s
alleged non-performance of the payment obligations.
[72]
Second Defendant states that because Plaintiff failed to allege on
that because Plaintiff failed
to allege on what basis Plaintiff
claims and alleges a relationship with Second Defendant, the
pleadings remain vague and embarrassing
to Second Defendant to
sustain a cause of action against Second Defendant.
[73]
Having considered that pleadings wholly, I am in agreement that both
Defendants remain embarrassed
by the pleadings as they stood. It
follows therefore that the exception should be upheld.
ORDER
[74]
The following order is made:
(a)
First and Second Defendants’ exceptions are upheld.
(b)
Plaintiff is afforded 15 (fifteen) days from the date of this order
within which to amend
its particulars of claim.
(c)
In the event of Plaintiff failing to amend the particulars of claim
within 15 (fifteen)
days as set out in (b) above, the particulars of
claim will be struck out.
(d)
Plaintiff is ordered to pay the costs of the exception.
M.L. SENYATSI
JUDGE OF THE HIGH
COURT
Heard:
7 October 2021
Judgment:
13 April 2022
Counsel for the 1st
Excipient / Defendant: K D
Iles
Attorney for the 1st
Excipient / Defendant: J
Banoobhai
Pinsent Masons
Tel: 010-493-4604
Junaid.banoobhai@pinsentmasons.com
Counsel for the 2nd
excipient / Defendant: H
Kooverjie SC
Tel: 082 496 3105
harshila@clubadvocates.co.za
Attorney for the 2nd
excipient / Defendant: R Motau
Gildenhuys Malatji Attorneys
Tel: 012-428-8600
RMotau@gminc.co.za
Counsel for the
respondent:
H van Eeden SC
Tel: 082 561 0546
vaneeden@law.co.za
Attorney for the
respondent:
M Ntanga Ntanga Nkhulu Inc
Tel: 010-595-1055
mongezi@ntanga.co.za
[1]
See
Jowell
v Bramwell – Jones and others
1998 (1) SA 836
(W) at 902 B-I
[2]
See
Callender
Zasby v Grahamstown Municipality
1981 (2) SA 810
(E) at 812 H
[3]
See
Trope
v South African Reserve Bank and another
1992(3) SA 208 (T) at 210G- 211E.
[4]
See
Lewis
v Oceanate (Pty) Ltd
1992(4)
SA 811 (4) at 817F.
[5]
See
Nel
and others NNO v McArthur
2003(4) SA 142 (T) at 149F.
[6]
2006
(1) SA 461
SCA;
[2006] 1 ALL SA 6
(SCA)
[2005] ZASCA 72
at para 2
[7]
See
Davenport
Corner Tea Room (Pty) Ltd v Joubert
1962 SA 709 (D) 715 H.
[8]
See
Gardner
v Richardt
1974
(3) SA 768
(C) 773 D – E
[9]
See
ABSA
Bank v Boksburg Transitional Local Council
1997
(2) SA 415
(W) at 41 B
[10]
See
McKenzie
v Farmers Co Operative Meat Industries Ltd
1922
AD 16
at 23
[11]
1980
(4) SA 525Z
at 526
[12]
2002
(4) SA 60
(W) at 106 E
[13]
See
Theunissen
en Andere v Transvaalse Lewenhawe Koöp BPK
1988 (2) SA 493
(A) at 500 E – F;
First
National Bank of Southern Africa Limited v Perry N.O and others
2001 (3) SA 960
(SCA) at 965 C – D.
[14]
See
Erasmus Superior Court Practice at B1 154 to B1 154A.
[15]
See
Troped
and Other v South African Reserve Bank
(above) at 269 I – J
[16]
See
Levitan
v Newhaven Holiday Enterprises CC
1991 (2) SA 297
(C) at 298 A-B,
Gallagher
Group Ltd and another v IO Tech Manufacturing (Pty) Ltd and others
2014 (2) SA 157
(GNP) at 166 G – H.
[17]
See
Autopack
Distributors CC v Compendium Insurance Group (Pty) Ltd
(9935/2014) [2015] ZAKZDHC 60 (7 August 2015)
[18]
J
Malan, D van Loggenberg – etal. De Rebus, October 2006, p33
sino noindex
make_database footer start
Similar Cases
South African Municipal Workers Union v Imbeu Development and Project Management (Pty) Ltd and Another (30236/2021) [2022] ZAGPJHC 1021 (21 November 2022)
[2022] ZAGPJHC 1021High Court of South Africa (Gauteng Division, Johannesburg)100% similar
South African National Civil Organisation v Ramosie and Others (7016/2019) [2022] ZAGPJHC 323 (6 May 2022)
[2022] ZAGPJHC 323High Court of South Africa (Gauteng Division, Johannesburg)100% similar
South Africa Enterprise Development (PTY) Ltd v Kerani BTW CC (2021/7285) [2022] ZAGPJHC 371 (1 June 2022)
[2022] ZAGPJHC 371High Court of South Africa (Gauteng Division, Johannesburg)100% similar
South African Municipal Workers Union National Medical Scheme (SAMUMED) v City of Ekurhuleni and Others (5068/2021) [2022] ZAGPJHC 701; [2022] 4 All SA 878 (GJ) (25 August 2022)
[2022] ZAGPJHC 701High Court of South Africa (Gauteng Division, Johannesburg)100% similar
South African Reserve Bank v Chauke (2021/40383) [2022] ZAGPJHC 162 (18 March 2022)
[2022] ZAGPJHC 162High Court of South Africa (Gauteng Division, Johannesburg)100% similar