Case Law[2022] ZAGPJHC 441South Africa
ARK Construction (PTY) Ltd v Veatel (PTY) Ltd (10869/2020) [2022] ZAGPJHC 441 (3 May 2022)
High Court of South Africa (Gauteng Division, Johannesburg)
3 May 2022
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2022
>>
[2022] ZAGPJHC 441
|
Noteup
|
LawCite
sino index
## ARK Construction (PTY) Ltd v Veatel (PTY) Ltd (10869/2020) [2022] ZAGPJHC 441 (3 May 2022)
ARK Construction (PTY) Ltd v Veatel (PTY) Ltd (10869/2020) [2022] ZAGPJHC 441 (3 May 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2022_441.html
sino date 3 May 2022
IN
THE HIGH COURT OF SOUTH AFRICA,
GAUTENG
LOCAL DIVISION, JOHANNESBURG
CASE
NO: 10869/2020
REPORTABLE:
NO
OF
INTEREST TO OTHER JUDGES: NO
REVISED.
3
May 2022
In
the matter between:
ARK
CONSTRUCTION (PTY) LTD
(Registration
No: 2016/347605/07
Applicant
and
VEATEL
(PTY) LTD
(Registration
No: 2017/271009/07)
Respondent
## JUDGMENT
JUDGMENT
CRUTCHFIELD
J:
[1]
The applicant, Ark Construction (Pty) Ltd, sought an
order of
provisional winding-up, alternatively final winding-up placing the
respondent, Veatel (Pty) Ltd, in the hands of the Master
of the High
Court.
[2]
The applicant alleged that the respondent owed it an
amount of
R4 425 529.50 for construction services rendered at the
respondent’s instance and which amount remained
due and payable
to the applicant.
[3]
On 4 December 2020, the applicant made demand upon
the
respondent in terms of s 345(1)(a) and (c) of the Companies Act 61 of
1973 (as amended) (‘the Act’). The demand
was served by
the sheriff on 4 December 2020. The respondent failed to pay,
secure or compound the indebtedness within the
21-day period in terms
of s 345(1) of the Act or at all.
[4]
The respondent’s attorney remitted correspondence
alleging a
‘
bona fide
dispute’. Notwithstanding, the
applicant proceeded with this application for the respondent’s
winding-up. The respondent
opposed the application.
[5]
At the hearing of the application on Monday, 25 April
2022, the
respondent tendered payment of an amount of R1 457 539.69
in respect of which it admitted its indebtedness
to the applicant.
The admission arose pursuant to an assessment of the work completed
by the applicant, conducted by a chartered
accountant, one P J
Carstens.
[6]
The application stood down until Thursday, 28 April
2022, for
the respondent to pay the tendered amount of R1 457 539.69
(‘the tendered amount’) to the applicant’s
attorney’s trust account, which duly transpired.
[7]
At the hearing on 28 April 2022, the applicant’s
counsel
persisted with the application on the basis that the respondent’s
alleged dispute of fact in respect of the balance
of the respondent’s
indebtedness to the applicant was devoid of merit. Furthermore, that
the applicant had a statutory right
to the winding-up of the
respondent in terms of s 345 of the Act given that an amount of
approximately R3 million remained
due and payable to the
applicant.
[8]
The applicant referred in particular to the report of
P J
Carstens (‘the Carstens report’), which reflected that
Carstens had not considered all of the applicant’s
invoices for
work performed by the applicant, and that the respondent had not
placed the invoices of third party contractors, allegedly
utilised to
complete the work that the applicant did not attended to adequately,
(being invoices that the respondent must have
had in its possession
when it deposed to its answering affidavit), before the Court.
[9]
The respondent’s answer was that it was not obliged
to place
the entirety of its evidence before this Court.
[10]
The applicant is obliged to show that the respondent is indebted in
an amount
of more than R100.00, which amount is due and payable and
that the respondent is unable to pay its debts.
[11]
The respondent sought to differentiate between an inability and an
unwillingness
to pay its debts, contending that the latter applied in
this instance pursuant to the dispute of fact that militated against
a
court ordering its winding-up.
[12]
The test to be applied in respect of a provisional winding-up based
on s 344
of the Act is whether the requirements are met on a
prima
facie
basis by the applicant, regard being had to whether the
balance of probabilities on all of the affidavits favour the
applicant’s
case.
[13]
The respondent raised various grounds, allegedly reasonable and
bona
fide
, on which it disputed its liability and indebtedness to the
applicant. These were:
13.1
In terms of
the partly oral partly written agreement entered into
between the parties;
13.2
The extent
of the services rendered by the applicant, specifically in
relation to the CAC invoices and the actual meters claimed to have
been
completed by the applicant;
13.3
The existence
of an ostensible oral agreement in relation to the
respondent’s purported liability for interest on the factoring
agreement
of Enable; and
13.4
The indebtedness
by the respondent to the applicant.
[14]
It is well
to remember that the respondent has to show only that its
indebtedness is disputed on
bona
fide
and
reasonable grounds.
[1]
The
respondent does not have to demonstrate that it is not indebted at
all to the applicant.
[2]
[15]
The respondent contended that the terms of the partly written partly
oral agreements
concluded by the parties were disputed and that the
applicant failed to set out the written portions of the agreement
concluded
between the parties.
[16]
The respondent alleged that the terms of the agreement that were
disputed were
that the applicant, on the respondent’s version,
was entitled to 75% of R140 per meter of the work performed, after
completion
of the CWC certificates, after which the outstanding 25%
of R140 per meter of work performed would fall due and payable after
completion
of the CAC certificates, which the respondent alleged the
applicant did not complete. In addition, the respondent contended
that
the applicant did not complete the CAC works.
[17]
In the light of the
Kalil v Decotex
and
Badenhorst
authorities referred to above, my task is to determine only whether
the disputes of fact raised by the respondent are
bona fide
disputed on reasonable grounds.
[18]
As to the reasonable grounds of the disputed terms of the agreement,
the respondent
pointed to the fact that the invoices issued by the
applicant and on which it relied, correlated with the terms of the
agreement
relied on by the respondent. The respondent referred in
this regard to annexure FA5 to the applicant’s founding
affidavit,
calculated and based on 75% of R140 per metre of completed
work or R105 per metre, being the terms alleged by the respondent in
respect of the CWC works.
[19]
In addition, the respondent referred to annexure FA19 to the
applicant’s
founding affidavit, allegedly calculated at the
rate of 25% of R140 per metre of completed work or R35 per metre,
being the terms
agreed upon in respect of the CAC works as alleged by
the respondent.
[20]
Given the
above-mentioned, the dispute raised by the respondent in respect of
the terms of the agreement on which the parties contracted,
is raised
on grounds that are reasonable and that if proven at the trial would
constitute a defence to the applicant’s claim.
[3]
[21]
Similarly, the respondent disputes the extent of the services
rendered by the
applicant and in respect of which it contends an
entitlement to payment. The respondent contends that the applicant
only performed
in respect of the CWC works, which the applicant
allegedly did partially, until termination of the agreement.
[22]
The respondent allegedly had to employ third party contractors to
complete
the CWC works and also the CAC works. The respondent
contended that the applicant did not perform any of the CAC work.
[23]
The alleged cost to the respondent of completing the CWC work, being
an amount
of R77 883.81, was not supported by an invoice or
invoices attached to the respondent’s answering affidavit and
nor
were details of the computation of the amount furnished by the
respondent, thus casting doubt on the reasonable basis of the
respondent’s
alleged counterclaim.
[24]
However,
the respondent does not have to prove its defence or adduce the
evidence upon which it will rely at the trial in these
proceedings.
All that the respondent has to do at this stage is set out grounds
that are not unreasonable and on which the respondent
disputes the
applicant’s claim.
[4]
[25]
In my view the respondent has set out sufficient facts, even taking
account
of the issues raised by the applicant, such as to meet the
onus resting on the respondent to show that it disputes the
applicant’s
claim on grounds that are both
bona fide
and
reasonable.
[26]
In addition, however, the respondent contended that to wind up the
respondent,
even provisionally, at the instance of the applicant
after the applicant received payment of an amount exceeding
R1 400 000.00,
would be to favour one creditor above the
balance of the respondent’s creditors. I am in agreement with
that contention.
[27]
In the circumstances and by reason of the aforementioned, it is not
in the
interests of justice for the respondent to be provisionally
wound up and an order in these terms will follow hereunder.
[28]
In respect of the costs of the application, the respondent’s
tender of
payment was made on the morning on which the matter was
called.
[29]
In the circumstances, given the lateness of the tender on the part of
the respondent,
it is appropriate that the respondent be ordered to
pay the costs of the application.
[30]
Accordingly, I grant the following order:
1.
The application is dismissed.
2.
The respondent is ordered to pay the costs of the application.
I
hand down the judgment.
CRUTCHFIELD
J
JUDGE
OF THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION
JOHANNESBURG
Electronically
submitted therefore unsigned
Delivered:
This judgment was prepared and authored by the Judge whose name is
reflected and is handed down electronically by circulation
to the
Parties / their legal representatives by email and by uploading it to
the electronic file of this matter on CaseLines. The
date of the
judgment is deemed to be
3 May 2022
.
COUNSEL
FOR THE APPLICANT: Ms N
Lombard.
INSTRUCTED
BY:
Van Zyl Johnson Attorneys.
COUNSEL
FOR THE RESPONDENT: Mr FW Botes SC
and Mr C van Gass.
INSTRUCTED
BY:
Steenkamp Van Niekerk Inc Attorneys.
DATE
OF THE HEARING:
25 and 28 April 2022.
DATE
OF JUDGMENT:
3 May 2022.
[1]
Kalil
v Decotex (Pty) Ltd & Another
1988 (1) SA 943 (AD).
[2]
The ‘
Badenhorst
Rule;’
Badenhorst
v Northern Construction Enterprises (Pty) Ltd
1956
(2) SA 346
(T) at 347H – 348B.
[3]
GAP
Merchant Recycling CC v Goal Reach Trading 55 CC
2016 (1) SA 261
(WCC).
[4]
Hulse-Reutter
& Another v HEG Consulting Enterprises (Pty) Ltd (Lane v Fey NNO
intervening)
1998
(2) SA 208
(C) at 219F – 220 C.
sino noindex
make_database footer start
Similar Cases
ARB Electrical Wholesalers (Pty) Ltd v De Jager Electrical Maintenance CC and Another (2022/20849) [2023] ZAGPJHC 701 (14 June 2023)
[2023] ZAGPJHC 701High Court of South Africa (Gauteng Division, Johannesburg)99% similar
A.R.C v A.M.M (076276/2024) [2025] ZAGPJHC 348 (3 April 2025)
[2025] ZAGPJHC 348High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African Transport and Allied Workers Union v South African Securitisation Programme (RF) Ltd and Others (2020/ A5066) [2022] ZAGPJHC 66 (7 February 2022)
[2022] ZAGPJHC 66High Court of South Africa (Gauteng Division, Johannesburg)98% similar
South African Reserve Bank v Chauke (2021/40383) [2022] ZAGPJHC 162 (18 March 2022)
[2022] ZAGPJHC 162High Court of South Africa (Gauteng Division, Johannesburg)98% similar
South Africa Enterprise Development (PTY) Ltd v Kerani BTW CC (2021/7285) [2022] ZAGPJHC 371 (1 June 2022)
[2022] ZAGPJHC 371High Court of South Africa (Gauteng Division, Johannesburg)98% similar